Pmp3
1. the process framework
Exam Questions
1. You’re a project manager working on a software engineering project. The programmers have
started building the software, and the testers have started to create the test environment. Which
process group includes these activities?
A.
B.
C.
D.
Initiating
Planning
Executing
Closing
2. Which of the following is not a stakeholder?
A.
B.
C.
D.
The project manager who is responsible for building the project
A project team member who will work on the project
A customer who will use the final product
A competitor whose company will lose business because of the product
3. A project manager runs into a problem with her project’s contractors, and she isn’t sure
if they’re abiding by the terms of the contract. Which knowledge area is the BEST source of
processes to help her deal with this problem?
A.
B.
C.
D.
Cost Management
Risk Management
Procurement Management
Communications Management
4. You’re a project manager for a construction project. You’ve just finished creating a list of all of
the people who will be directly affected by the project. What process group are you in?
A.
B.
C.
D.
Initiating
Planning
Executing
Monitoring & Controlling
5. Which process group contains the Develop Project Charter process and the Identify
Stakeholders process?
A.
B.
C.
D.
Initiating
Executing
Monitoring and Controlling
Closing
you are here 4 81
Download at Boykma.Com
2. exam questions
Exam Questions
6. Which of the following is NOT a project?
A.
B.
C.
D.
Repairing a car
Building a highway overpass
Running an IT support department
Filming a motion picture
7. A project manager is running a software project that is supposed to be delivered in phases. She was
planning on dividing the resources into two separate teams to do the work for two phases at the same time,
but one of her senior developers suggested that she use an Agile methodology instead, and she agrees. Which
of the following BEST describes the relationship between her project’s phases?
A.
B.
C.
D.
Sequential relationship
Iterative relationship
Constrained relationship
Overlapping relationship
8. Which of the following is NOT true about overlapping phases?
A.
B.
C.
D.
Each phase is typically done by a separate team
There’s an increased risk of delays when a later phase can’t start until an earlier one ends
There’s an increased risk to the project due to potential for rework
Every phase must go through all five process groups
9. You’re the project manager for an industrial design project. Your team members report to you, and you’re
responsible for creating the budget, building the schedule, and assigning the tasks. When the project is
complete, you release the team so they can work on other projects for the company. What kind of organization
do you work in?
A.
B.
C.
D.
Functional
Weak matrix
Strong matrix
Projectized
10. You’re a project manager working in a weak matrix organization. Which of the following is NOT true?
A.
B.
C.
D.
Your team members report to functional managers
You are not in directly charge of resources
Functional managers make decisions that can affect your projects
You have sole responsibility for the success or failure of the project
82 Chapter 3
Download at Boykma.Com
3. Answers
the process framework
Exam Questions
1. Answer: C
The Executing process group is the one where the team does all the work. You’ll get a good feel for the
process groups pretty quickly!
2. Answer: D
One of the hardest things that a project manager has to do on a project is figure out who all the
stakeholders are. The project manager, the team, the sponsor (or client), the customers and people who
will use the software, the senior managers at the company—they’re all stakeholders. Competitors aren’t
stakeholders, because even though they’re affected by the project, they don’t actually have any direct
influence over it.
3. Answer: C
The Procurement Management knowledge area deals with contracts, contractors, buyers and sellers. If
you’ve got a question about a type of contract or how to deal with contract problems, you’re being asked
about a Procurement Management process.
4. Answer: A
People who will be directly affected by the project are stakeholders, and when you’re creating a list of
them you’re performing the Identify Stakeholders process. That’s one of the two processes in the Initiating
process group.
5. Answer: A
The first things that are created on a project are the charter (which you create in the Develop Project
Charter process) and the Stakeholder Register (which you create in the Identify Stakeholders process).
You do those things when you’re initiating the project.
you are here 4 83
Download at Boykma.Com
4. exam answers
Answers
Exam Questions
6. Answer: C
The work of an IT support department doesn’t have an end date—it’s not temporary. That’s why it’s
not a project. Now, if that support team had to work over the weekend to move the data center to a
new location, then that would be a project!
I see—so even when
something is a process and
not a project, there could
be projects related to it.
7. Answer: B
Agile development is a really good example of an iterative approach to project phases. In an Agile
project, the team will typically break down the project into phases, where they work on the current
phase while planning out the next one.
84 Chapter 3
Download at Boykma.Com
5. Answers
the process framework
Exam Questions
8. Answer: B
If there’s an increased risk of a project because one phase can’t start until another one ends, that means your project
phases aren’t overlapping. When you’ve got overlapping phases, that means that you typically have multiple teams
that start their phases independently of each other.
Also, take another look at answer C, because it’s an important point about overlapping phases. When your
phases have an overlapping relationship, there’s an increased risk of rework. This typically happens when one
team delivers the results of their project, but made assumptions about what another team is doing as part of their
phase. When that other team delivers their work, it turns out that the results that both teams produced aren’t quite
compatible with each other, and now both teams have to go back and rework their designs. This happens a lot
when your phases overlap, which is why overlapping phases have an increased risk of rework.
9. Answer: D
In a projectized organization, the project manager has the power to assign tasks, manage the budget, and release the
team.
10. Answer: D
In a weak matrix, project managers have very limited authority. They have to share a lot of responsibility with
functional managers, and those functional managers have a lot of leeway to make decisions about how the team
members are managed. In an organization like that, the project manager isn’t given a lot of responsibility.
likely to
That’s why you’re pediter
find a project ex
in a weak matrix.