SlideShare une entreprise Scribd logo
1  sur  41
ROUGH-CUT
CAPACITY PLANNING
Capacity
Planning (RCCP)
 Type of capacity planning using some
load profiles (sometimes called
“representative routings) defined for
the product families, focused on key
or critical work centers, lines,
departments, cells, suppliers, and
support areas (engineering,
distribution, shipping).
Importance of RCCP
MRP system assumes that needed capacity always
is available.

RCCP helps to identify the key resources and to
test the feasibility of the supply plan, production
plan and master schedule before doing any
detailed capacity/material planning.

 It also helps to initiate action for making mid- to
long-term capacity adjustments.
What is RCCP and
    how does it work?
 Rough Cut Capacity Planning (RCCP) is a rough check
to evaluate all the key resources, to test the validity of
MPS, to determine the feasibility of fulfilling the
approved Production Plan that was developed in the
Sales & Operations Planning process.

  Once the master scheduler determines that a realistic
  plan exists, the production plan is then load into MRP to
  drive the allocation for all the lower-level materials. The
  production plan now translates into discrete part
  numbers, quantities and due dates.
Overstated MPS
It is a problem commonly
encountered in operating MRP
systems .
An overstated master production
schedule is one that orders more
production to be released than
production can complete.
Causes of Overstated MPS
It causes raw materials and WIP
inventories to increase.
It also causes a build-up of job queues
on the shop floor.
 Since jobs have to wait to be processed,
actual lead time increase.
As lead times increase, forecast
accuracy over the lead-time diminishes.
Few reasons of why RCCP
techniques are not used in
some companies are:
  Data requirements are quite high - firm
 demand, forecasts, past data, lead times,
 utilization, products and process
 knowledge.
 They don't have a stable MPS.
 They don't have the right skill, it is very
 time-consuming, or they are doing it the
 wrong ways.
Standard Time
   It refers to Setup time and Run
  time (processing time) which
  impact the workload on a
  resource because it actually tie
  up that resource.
Lead-Time Offset
   It is the time between the need
  for the resource and the date that
  the product has been promised.
  Lead-Time Offset is necessary if a
  product has longer lead times.
When using process routings sheet and
   BOM to create the Resource Profile, it is
   better to use this formula


Required Resource Time = (Run Time x BOM qty)
                       + (Setup Time x number
                       of Setups required)
                       + margin % of total
                       non- standard times
Several types of capacities
being used:
 Demonstrated Capacity
     - This is the proven or historical capacity
 of a key resource or work center.
 Demonstrated capacity could potentially
 change if resources are added or if operations
 are altered. In such case, adjustments to
 planned capacity must be considered before
 making evaluation of the production plan.
Planned Capacity
    - This is demonstrated capacity plus or minus
anticipated changes or adjustments to the
product-flow process.

Maximum Capacity
    - This is the maximum load a resource can
handle under any reasonable set of
circumstances. This can be achieved through
several means: use of available overtime, adding
shifts, staff additions, offload volume to outside
vendors, pay extra for supply priorities, paying
premium freights to expedite materials delivery,
etc).
Determining Capacity
Available or Planned
      Capacity
Adjustment Factors:
Utilization. Utilization is a number between 0
and 1 which is equal to 1 minus the proportion of
time typically lost due to machine breakdown,
labor shortage, parts failure, or material
unavailability.
Efficiency. Efficiency is defined as the average of
standard hours of actual production (after minus
the unavoidable lost time - setup time, change
shift, rest time).
If a time standard is exactly right,
efficiency is 1.
 If the time actually required to
perform the work is less than the
standard, efficiency is more than 1.
 If the time actually required to
perform the work is more than the
standard time, efficiency is less
than 1.
Capacity available is determined
by multiplying time available x
utilization x efficiency

  Capacity Available = Time Available
                      x Utilization
                      x Efficiency
The Resource Profile
Technique
 This technique is designed to convert the master
 production schedule from units of end items to
 be produced into the amount of time required on
 the key resources.
 Resource Profile approach considers lead-time
 offsets.
 Resource Profile technique is the most detailed
 rough-cut approach, but is not as detailed as
 Capacity Requirements Planning.
 Resource Profile technique uses detailed data on
 the time standards for each product at the key
 resources.
Time Standard
  It is the time it should take an
  average worker working at a normal
  pace to produce one unit of an item.
  The time standard for any part has
  built into it an allowance for rest to
  overcome fatigue or unavoidable
  delays, etc.
It would seems logical to accept that if
the required capacity is :

 No more than 10% greater than the
planned capacity, the master schedule is
considered realistic.
More than 20% greater than the planned
capacity, the master schedule is considered
unrealistic.
Between 10% and 20% greater than the
planned capacity, the master schedule is
questionable.
In many of today's ERP systems, there is
also a "What-If" scenarios analysis
capability being built into the capacity
planning module, that makes it possible
for the scheduler to juggle the numbers -
shifting workers, reschedule in and -out,
alternate routings, splitting lots, add
equipments, off-loading to vendors,
overtime, hiring temporary workers and
so on.
3 Approaches to Rough-
 Cut Capacity Planning
 Capacity planning using Overall factors
(CPOF) Approach – the least detailed
approach which is quickly computed but is
insensitive to shifts in product mix.
 Bill of Labor – a second approach which
involves multiplying two matrices, the bill of
labor and the master production schedule..
 Resource Profile – approach which takes
lead-time offsets into account.
Drum-buffer Rope
  It is an emerging procedure that
 eliminates the need for iteration
 found in all RCCP approaches.
  It is presently used by a small but
 growing number of corporations.
Material Requirements
   Planning (MRP)
  It uses Master Production Schedule
 (MPS) of end items to determine the
 quantity and timing of component part
 production.
  It is capacity insensitive; it implicitly
 assumes that sufficient capacity is
 available to produce components at the
 time they’re needed.
APICS Monograph
    (Berry, Voliman, and Whybark
   1979) presents case histories of
   several companies, including
   details on the capacity
   planning process.
Production Planning &
      Control
 Capacity management techniques usually
are separated into four categories that
represent the four time horizons :
 Manufacturing Resource Planning (MRP
II)
 Aggregate Production Planning
 Rough Cut Capacity Planning (RCCP)
 Capacity Requirements Planning (CRP).
In any MRP system, the same
sequence is to create a master
schedule, use Rough Cut Capacity
Planning to verify that the MPS is
feasible, perform the MRP
explosion, and send the Planned
Order Release data to Capacity
Requirements Planning
Role of RCCP in the overall PPC system:
 To develop an achievable Master Production Schedule.
 To plan and control priorities and capacities.
 Priority Planning is the process of specifying batch
 quantities and their start and finish dates for all Supply
 Orders where procurement and manufacturing are involved.
 Priority Control is making the right things at the right time.
 It is completely dependent on maintaining a balance
 between MPS requirements and factory Output rates, in
 which suppliers delivery performance is vital.
 Capacity planning is the task of determining how much
 output is needed from factory and from suppliers.
 Capacity control is the comparison between planned levels
 and actual outputs achieved, and the identification of
 significant variances above or below plan. Corrective action
 must be done quickly (adjust capacity or changing the
 master schedule).
Typical resources that might be planned as
pat of rough-cut capacity planning:
Overall plant capacity
Labor hours in total or for people with unique skills
Assembly hours in a specific cell or bottleneck
process.
Testing cell capacity
Engineering hours needed to configure the final
product to the customer’s specification.
Space required in a warehouse or storage area
Waste or effluent release, etc.
Shipping labor
Design time or credit release time
Inspection or QC time
Supplier Capacity
Rough-Cut Capacity
Planning Functions
Shows consumption of critical resources.
Enables master schedulers to:
   Test end-item production plans
   Calculate capacity to meet the master schedule
   Compare and modify required and planned
   capacity
   Analyze load on key resources by time period
   Isolate and resolve potential problems.
Rough-cut Capacity
Planning V.S. Capacity
      Planning
 CRP uses time-phased material plan
information, while RCCP uses aggregate data.
 MRP takes into account capacity stored as
inventory.
 Shop floor systems take into account W.I.P. –
only consider what's needed to complete the
requirement.
 CRP considers service and spare parts
requirements also.
EXAMPLE problem:
Let's assume a lamps manufacturer I call
it Johor's Lamps. Johor's Lamps runs 3
shifts, 120 hours per week from Monday
to Friday; Planned Production Lost Time
per shift (change shift & rest time) is 35
minutes, and company allows a
maximum overtime of 10% of per shift
either during weekdays or through Sat.
& Sunday.


Contenu connexe

Tendances

What is master production schedule
What is master production scheduleWhat is master production schedule
What is master production scheduleMRPeasy
 
Material Requirement Planning (MRP)
Material Requirement Planning (MRP)Material Requirement Planning (MRP)
Material Requirement Planning (MRP) Konok Mondal
 
Scheduling
SchedulingScheduling
Schedulingjaya_22
 
Materials requirement planning
Materials requirement planningMaterials requirement planning
Materials requirement planningAnila Vanguri
 
Material and capacity requirements planning (mrp and crp) part 2
Material and capacity requirements planning (mrp and crp) part  2Material and capacity requirements planning (mrp and crp) part  2
Material and capacity requirements planning (mrp and crp) part 2Dr. Mahmoud Al-Naimi
 
Master Production Scheduling (MPS)
Master Production Scheduling (MPS) Master Production Scheduling (MPS)
Master Production Scheduling (MPS) Pankil Shah
 
Capacity Requirement Planning, Rough Cut Capacity Planning
Capacity Requirement Planning, Rough Cut Capacity PlanningCapacity Requirement Planning, Rough Cut Capacity Planning
Capacity Requirement Planning, Rough Cut Capacity PlanningRaju Pegada
 
Material requirement planning - Production and Operation Management
Material requirement planning - Production and Operation ManagementMaterial requirement planning - Production and Operation Management
Material requirement planning - Production and Operation ManagementSuryakumar Thangarasu
 
Material requirements planning & erp ppt @ bec doms
Material requirements planning & erp  ppt @ bec domsMaterial requirements planning & erp  ppt @ bec doms
Material requirements planning & erp ppt @ bec domsBabasab Patil
 
Capacity planning ppt
Capacity planning pptCapacity planning ppt
Capacity planning pptGagan bhati
 
Material requirement planning presentation
Material requirement planning presentationMaterial requirement planning presentation
Material requirement planning presentationjhanakshah
 
Presentation aggregate planning
Presentation aggregate planningPresentation aggregate planning
Presentation aggregate planningLauraRLR
 
Manufacturing Resource Planning | Management
Manufacturing Resource Planning | ManagementManufacturing Resource Planning | Management
Manufacturing Resource Planning | ManagementTransweb Global Inc
 
Material and capacity requirements planning (mrp and crp) part 1
Material and capacity requirements planning (mrp and crp) part  1Material and capacity requirements planning (mrp and crp) part  1
Material and capacity requirements planning (mrp and crp) part 1Dr. Mahmoud Al-Naimi
 
Types of loading, production & operations management
Types of loading, production & operations managementTypes of loading, production & operations management
Types of loading, production & operations managementMahima Mutnuru
 
Material Resource Planning
Material Resource PlanningMaterial Resource Planning
Material Resource PlanningBiswajit Ghosh
 

Tendances (20)

What is master production schedule
What is master production scheduleWhat is master production schedule
What is master production schedule
 
Material Requirement Planning (MRP)
Material Requirement Planning (MRP)Material Requirement Planning (MRP)
Material Requirement Planning (MRP)
 
Scheduling
SchedulingScheduling
Scheduling
 
Materials requirement planning
Materials requirement planningMaterials requirement planning
Materials requirement planning
 
Planned order release
Planned order releasePlanned order release
Planned order release
 
Material and capacity requirements planning (mrp and crp) part 2
Material and capacity requirements planning (mrp and crp) part  2Material and capacity requirements planning (mrp and crp) part  2
Material and capacity requirements planning (mrp and crp) part 2
 
Master Production Scheduling (MPS)
Master Production Scheduling (MPS) Master Production Scheduling (MPS)
Master Production Scheduling (MPS)
 
Capacity Requirement Planning, Rough Cut Capacity Planning
Capacity Requirement Planning, Rough Cut Capacity PlanningCapacity Requirement Planning, Rough Cut Capacity Planning
Capacity Requirement Planning, Rough Cut Capacity Planning
 
Material requirement planning - Production and Operation Management
Material requirement planning - Production and Operation ManagementMaterial requirement planning - Production and Operation Management
Material requirement planning - Production and Operation Management
 
Material requirements planning & erp ppt @ bec doms
Material requirements planning & erp  ppt @ bec domsMaterial requirements planning & erp  ppt @ bec doms
Material requirements planning & erp ppt @ bec doms
 
Capacity planning ppt
Capacity planning pptCapacity planning ppt
Capacity planning ppt
 
Input to MRP
Input to MRPInput to MRP
Input to MRP
 
Material requirement planning presentation
Material requirement planning presentationMaterial requirement planning presentation
Material requirement planning presentation
 
Mrp ii
Mrp iiMrp ii
Mrp ii
 
Presentation aggregate planning
Presentation aggregate planningPresentation aggregate planning
Presentation aggregate planning
 
Manufacturing Resource Planning | Management
Manufacturing Resource Planning | ManagementManufacturing Resource Planning | Management
Manufacturing Resource Planning | Management
 
Aggregate planning
Aggregate planningAggregate planning
Aggregate planning
 
Material and capacity requirements planning (mrp and crp) part 1
Material and capacity requirements planning (mrp and crp) part  1Material and capacity requirements planning (mrp and crp) part  1
Material and capacity requirements planning (mrp and crp) part 1
 
Types of loading, production & operations management
Types of loading, production & operations managementTypes of loading, production & operations management
Types of loading, production & operations management
 
Material Resource Planning
Material Resource PlanningMaterial Resource Planning
Material Resource Planning
 

Similaire à Rccp report

Capacity-Planning-Report - Measurement of Capacity
Capacity-Planning-Report - Measurement of CapacityCapacity-Planning-Report - Measurement of Capacity
Capacity-Planning-Report - Measurement of CapacityJoanRachelCalansingi
 
Reading 03 rough cut capa ci-ty planning_supplement for mps_2011
Reading 03 rough cut capa ci-ty planning_supplement for mps_2011Reading 03 rough cut capa ci-ty planning_supplement for mps_2011
Reading 03 rough cut capa ci-ty planning_supplement for mps_2011naveenupmanyu01
 
Reading 03 rough cut capa ci-ty planning_supplement for mps_2011
Reading 03 rough cut capa ci-ty planning_supplement for mps_2011Reading 03 rough cut capa ci-ty planning_supplement for mps_2011
Reading 03 rough cut capa ci-ty planning_supplement for mps_2011naveenupmanyu01
 
Productionplanning aggregate capacity
Productionplanning aggregate capacityProductionplanning aggregate capacity
Productionplanning aggregate capacityzmagtoto
 
prakash agrawal crp presentation
prakash agrawal   crp presentationprakash agrawal   crp presentation
prakash agrawal crp presentationAkash Maurya
 
Operations ppt
Operations pptOperations ppt
Operations pptPritam RW
 
Aggregate planning
Aggregate planningAggregate planning
Aggregate planningPritam RW
 
Operations ppt
Operations pptOperations ppt
Operations pptPritam RW
 
Mrp systems & scheduling
Mrp systems & schedulingMrp systems & scheduling
Mrp systems & schedulingvarun0610
 
Manish 13 mrp2
Manish 13 mrp2Manish 13 mrp2
Manish 13 mrp2samjune
 
Operation engine ii session iv operations scheduling
Operation engine  ii session iv  operations schedulingOperation engine  ii session iv  operations scheduling
Operation engine ii session iv operations schedulingFatima Aliza
 
Ch13 - Aggregate Planning
Ch13 - Aggregate PlanningCh13 - Aggregate Planning
Ch13 - Aggregate PlanningPelly Sianova
 
Capacity Planning
Capacity PlanningCapacity Planning
Capacity PlanningMOHD ARISH
 
Planning the AMPPLE Way
Planning the AMPPLE WayPlanning the AMPPLE Way
Planning the AMPPLE Wayatif.hussain
 
Capacity Planning.ppt
Capacity Planning.pptCapacity Planning.ppt
Capacity Planning.pptCamranKhan2
 

Similaire à Rccp report (20)

Capacity-Planning-Report - Measurement of Capacity
Capacity-Planning-Report - Measurement of CapacityCapacity-Planning-Report - Measurement of Capacity
Capacity-Planning-Report - Measurement of Capacity
 
Capacity planning
Capacity planningCapacity planning
Capacity planning
 
Reading 03 rough cut capa ci-ty planning_supplement for mps_2011
Reading 03 rough cut capa ci-ty planning_supplement for mps_2011Reading 03 rough cut capa ci-ty planning_supplement for mps_2011
Reading 03 rough cut capa ci-ty planning_supplement for mps_2011
 
Reading 03 rough cut capa ci-ty planning_supplement for mps_2011
Reading 03 rough cut capa ci-ty planning_supplement for mps_2011Reading 03 rough cut capa ci-ty planning_supplement for mps_2011
Reading 03 rough cut capa ci-ty planning_supplement for mps_2011
 
Manish 13 mrp2
Manish 13 mrp2Manish 13 mrp2
Manish 13 mrp2
 
Close Loop MRP
Close Loop MRPClose Loop MRP
Close Loop MRP
 
Close Loop Mrp
Close Loop MrpClose Loop Mrp
Close Loop Mrp
 
Productionplanning aggregate capacity
Productionplanning aggregate capacityProductionplanning aggregate capacity
Productionplanning aggregate capacity
 
prakash agrawal crp presentation
prakash agrawal   crp presentationprakash agrawal   crp presentation
prakash agrawal crp presentation
 
Operations ppt
Operations pptOperations ppt
Operations ppt
 
Aggregate planning
Aggregate planningAggregate planning
Aggregate planning
 
Operations ppt
Operations pptOperations ppt
Operations ppt
 
Mrp systems & scheduling
Mrp systems & schedulingMrp systems & scheduling
Mrp systems & scheduling
 
Manish 13 mrp2
Manish 13 mrp2Manish 13 mrp2
Manish 13 mrp2
 
Operation engine ii session iv operations scheduling
Operation engine  ii session iv  operations schedulingOperation engine  ii session iv  operations scheduling
Operation engine ii session iv operations scheduling
 
Ch13 - Aggregate Planning
Ch13 - Aggregate PlanningCh13 - Aggregate Planning
Ch13 - Aggregate Planning
 
Capacity Planning
Capacity PlanningCapacity Planning
Capacity Planning
 
Pom unit 3
Pom unit 3Pom unit 3
Pom unit 3
 
Planning the AMPPLE Way
Planning the AMPPLE WayPlanning the AMPPLE Way
Planning the AMPPLE Way
 
Capacity Planning.ppt
Capacity Planning.pptCapacity Planning.ppt
Capacity Planning.ppt
 

Plus de jetromarquez

Inventory management-1224844053656038-9
Inventory management-1224844053656038-9Inventory management-1224844053656038-9
Inventory management-1224844053656038-9jetromarquez
 
Cdocumentsandsettingscromamydocumentssemivpminventorycontrol 100213073759-php...
Cdocumentsandsettingscromamydocumentssemivpminventorycontrol 100213073759-php...Cdocumentsandsettingscromamydocumentssemivpminventorycontrol 100213073759-php...
Cdocumentsandsettingscromamydocumentssemivpminventorycontrol 100213073759-php...jetromarquez
 
Inventory 1213683812410770-9
Inventory 1213683812410770-9Inventory 1213683812410770-9
Inventory 1213683812410770-9jetromarquez
 
C9inventorymanagement 111031134635-phpapp01
C9inventorymanagement 111031134635-phpapp01C9inventorymanagement 111031134635-phpapp01
C9inventorymanagement 111031134635-phpapp01jetromarquez
 
Materials requirements planning
Materials requirements planningMaterials requirements planning
Materials requirements planningjetromarquez
 
Relationships in supply systems 2
Relationships in supply systems 2Relationships in supply systems 2
Relationships in supply systems 2jetromarquez
 

Plus de jetromarquez (11)

Inventory management-1224844053656038-9
Inventory management-1224844053656038-9Inventory management-1224844053656038-9
Inventory management-1224844053656038-9
 
Cdocumentsandsettingscromamydocumentssemivpminventorycontrol 100213073759-php...
Cdocumentsandsettingscromamydocumentssemivpminventorycontrol 100213073759-php...Cdocumentsandsettingscromamydocumentssemivpminventorycontrol 100213073759-php...
Cdocumentsandsettingscromamydocumentssemivpminventorycontrol 100213073759-php...
 
Inventory 1213683812410770-9
Inventory 1213683812410770-9Inventory 1213683812410770-9
Inventory 1213683812410770-9
 
C9inventorymanagement 111031134635-phpapp01
C9inventorymanagement 111031134635-phpapp01C9inventorymanagement 111031134635-phpapp01
C9inventorymanagement 111031134635-phpapp01
 
Logistics
LogisticsLogistics
Logistics
 
3 in-1 scissors
3 in-1 scissors3 in-1 scissors
3 in-1 scissors
 
Penlight
PenlightPenlight
Penlight
 
Ppt in ppc(s&op)
Ppt in ppc(s&op)Ppt in ppc(s&op)
Ppt in ppc(s&op)
 
Materials requirements planning
Materials requirements planningMaterials requirements planning
Materials requirements planning
 
Logistics
LogisticsLogistics
Logistics
 
Relationships in supply systems 2
Relationships in supply systems 2Relationships in supply systems 2
Relationships in supply systems 2
 

Dernier

2024 April Patch Tuesday
2024 April Patch Tuesday2024 April Patch Tuesday
2024 April Patch TuesdayIvanti
 
Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...
Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...
Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...Alkin Tezuysal
 
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptx
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptxPasskey Providers and Enabling Portability: FIDO Paris Seminar.pptx
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptxLoriGlavin3
 
A Journey Into the Emotions of Software Developers
A Journey Into the Emotions of Software DevelopersA Journey Into the Emotions of Software Developers
A Journey Into the Emotions of Software DevelopersNicole Novielli
 
Take control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test SuiteTake control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test SuiteDianaGray10
 
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024BookNet Canada
 
Genislab builds better products and faster go-to-market with Lean project man...
Genislab builds better products and faster go-to-market with Lean project man...Genislab builds better products and faster go-to-market with Lean project man...
Genislab builds better products and faster go-to-market with Lean project man...Farhan Tariq
 
How to write a Business Continuity Plan
How to write a Business Continuity PlanHow to write a Business Continuity Plan
How to write a Business Continuity PlanDatabarracks
 
Generative AI for Technical Writer or Information Developers
Generative AI for Technical Writer or Information DevelopersGenerative AI for Technical Writer or Information Developers
Generative AI for Technical Writer or Information DevelopersRaghuram Pandurangan
 
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...Wes McKinney
 
How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.Curtis Poe
 
How to Effectively Monitor SD-WAN and SASE Environments with ThousandEyes
How to Effectively Monitor SD-WAN and SASE Environments with ThousandEyesHow to Effectively Monitor SD-WAN and SASE Environments with ThousandEyes
How to Effectively Monitor SD-WAN and SASE Environments with ThousandEyesThousandEyes
 
Why device, WIFI, and ISP insights are crucial to supporting remote Microsoft...
Why device, WIFI, and ISP insights are crucial to supporting remote Microsoft...Why device, WIFI, and ISP insights are crucial to supporting remote Microsoft...
Why device, WIFI, and ISP insights are crucial to supporting remote Microsoft...panagenda
 
DevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsDevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsSergiu Bodiu
 
Generative Artificial Intelligence: How generative AI works.pdf
Generative Artificial Intelligence: How generative AI works.pdfGenerative Artificial Intelligence: How generative AI works.pdf
Generative Artificial Intelligence: How generative AI works.pdfIngrid Airi González
 
A Framework for Development in the AI Age
A Framework for Development in the AI AgeA Framework for Development in the AI Age
A Framework for Development in the AI AgeCprime
 
The Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsThe Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsPixlogix Infotech
 
Data governance with Unity Catalog Presentation
Data governance with Unity Catalog PresentationData governance with Unity Catalog Presentation
Data governance with Unity Catalog PresentationKnoldus Inc.
 
Rise of the Machines: Known As Drones...
Rise of the Machines: Known As Drones...Rise of the Machines: Known As Drones...
Rise of the Machines: Known As Drones...Rick Flair
 
TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024Lonnie McRorey
 

Dernier (20)

2024 April Patch Tuesday
2024 April Patch Tuesday2024 April Patch Tuesday
2024 April Patch Tuesday
 
Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...
Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...
Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...
 
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptx
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptxPasskey Providers and Enabling Portability: FIDO Paris Seminar.pptx
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptx
 
A Journey Into the Emotions of Software Developers
A Journey Into the Emotions of Software DevelopersA Journey Into the Emotions of Software Developers
A Journey Into the Emotions of Software Developers
 
Take control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test SuiteTake control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test Suite
 
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
 
Genislab builds better products and faster go-to-market with Lean project man...
Genislab builds better products and faster go-to-market with Lean project man...Genislab builds better products and faster go-to-market with Lean project man...
Genislab builds better products and faster go-to-market with Lean project man...
 
How to write a Business Continuity Plan
How to write a Business Continuity PlanHow to write a Business Continuity Plan
How to write a Business Continuity Plan
 
Generative AI for Technical Writer or Information Developers
Generative AI for Technical Writer or Information DevelopersGenerative AI for Technical Writer or Information Developers
Generative AI for Technical Writer or Information Developers
 
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...
 
How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.
 
How to Effectively Monitor SD-WAN and SASE Environments with ThousandEyes
How to Effectively Monitor SD-WAN and SASE Environments with ThousandEyesHow to Effectively Monitor SD-WAN and SASE Environments with ThousandEyes
How to Effectively Monitor SD-WAN and SASE Environments with ThousandEyes
 
Why device, WIFI, and ISP insights are crucial to supporting remote Microsoft...
Why device, WIFI, and ISP insights are crucial to supporting remote Microsoft...Why device, WIFI, and ISP insights are crucial to supporting remote Microsoft...
Why device, WIFI, and ISP insights are crucial to supporting remote Microsoft...
 
DevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsDevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platforms
 
Generative Artificial Intelligence: How generative AI works.pdf
Generative Artificial Intelligence: How generative AI works.pdfGenerative Artificial Intelligence: How generative AI works.pdf
Generative Artificial Intelligence: How generative AI works.pdf
 
A Framework for Development in the AI Age
A Framework for Development in the AI AgeA Framework for Development in the AI Age
A Framework for Development in the AI Age
 
The Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsThe Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and Cons
 
Data governance with Unity Catalog Presentation
Data governance with Unity Catalog PresentationData governance with Unity Catalog Presentation
Data governance with Unity Catalog Presentation
 
Rise of the Machines: Known As Drones...
Rise of the Machines: Known As Drones...Rise of the Machines: Known As Drones...
Rise of the Machines: Known As Drones...
 
TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024
 

Rccp report

  • 2. Capacity Planning (RCCP) Type of capacity planning using some load profiles (sometimes called “representative routings) defined for the product families, focused on key or critical work centers, lines, departments, cells, suppliers, and support areas (engineering, distribution, shipping).
  • 3. Importance of RCCP MRP system assumes that needed capacity always is available. RCCP helps to identify the key resources and to test the feasibility of the supply plan, production plan and master schedule before doing any detailed capacity/material planning. It also helps to initiate action for making mid- to long-term capacity adjustments.
  • 4. What is RCCP and how does it work? Rough Cut Capacity Planning (RCCP) is a rough check to evaluate all the key resources, to test the validity of MPS, to determine the feasibility of fulfilling the approved Production Plan that was developed in the Sales & Operations Planning process. Once the master scheduler determines that a realistic plan exists, the production plan is then load into MRP to drive the allocation for all the lower-level materials. The production plan now translates into discrete part numbers, quantities and due dates.
  • 5. Overstated MPS It is a problem commonly encountered in operating MRP systems . An overstated master production schedule is one that orders more production to be released than production can complete.
  • 6. Causes of Overstated MPS It causes raw materials and WIP inventories to increase. It also causes a build-up of job queues on the shop floor. Since jobs have to wait to be processed, actual lead time increase. As lead times increase, forecast accuracy over the lead-time diminishes.
  • 7. Few reasons of why RCCP techniques are not used in some companies are: Data requirements are quite high - firm demand, forecasts, past data, lead times, utilization, products and process knowledge. They don't have a stable MPS. They don't have the right skill, it is very time-consuming, or they are doing it the wrong ways.
  • 8. Standard Time It refers to Setup time and Run time (processing time) which impact the workload on a resource because it actually tie up that resource.
  • 9. Lead-Time Offset It is the time between the need for the resource and the date that the product has been promised. Lead-Time Offset is necessary if a product has longer lead times.
  • 10. When using process routings sheet and BOM to create the Resource Profile, it is better to use this formula Required Resource Time = (Run Time x BOM qty) + (Setup Time x number of Setups required) + margin % of total non- standard times
  • 11. Several types of capacities being used: Demonstrated Capacity - This is the proven or historical capacity of a key resource or work center. Demonstrated capacity could potentially change if resources are added or if operations are altered. In such case, adjustments to planned capacity must be considered before making evaluation of the production plan.
  • 12. Planned Capacity - This is demonstrated capacity plus or minus anticipated changes or adjustments to the product-flow process. Maximum Capacity - This is the maximum load a resource can handle under any reasonable set of circumstances. This can be achieved through several means: use of available overtime, adding shifts, staff additions, offload volume to outside vendors, pay extra for supply priorities, paying premium freights to expedite materials delivery, etc).
  • 13. Determining Capacity Available or Planned Capacity Adjustment Factors: Utilization. Utilization is a number between 0 and 1 which is equal to 1 minus the proportion of time typically lost due to machine breakdown, labor shortage, parts failure, or material unavailability. Efficiency. Efficiency is defined as the average of standard hours of actual production (after minus the unavoidable lost time - setup time, change shift, rest time).
  • 14. If a time standard is exactly right, efficiency is 1. If the time actually required to perform the work is less than the standard, efficiency is more than 1. If the time actually required to perform the work is more than the standard time, efficiency is less than 1.
  • 15. Capacity available is determined by multiplying time available x utilization x efficiency Capacity Available = Time Available x Utilization x Efficiency
  • 16. The Resource Profile Technique This technique is designed to convert the master production schedule from units of end items to be produced into the amount of time required on the key resources. Resource Profile approach considers lead-time offsets. Resource Profile technique is the most detailed rough-cut approach, but is not as detailed as Capacity Requirements Planning. Resource Profile technique uses detailed data on the time standards for each product at the key resources.
  • 17. Time Standard It is the time it should take an average worker working at a normal pace to produce one unit of an item. The time standard for any part has built into it an allowance for rest to overcome fatigue or unavoidable delays, etc.
  • 18. It would seems logical to accept that if the required capacity is : No more than 10% greater than the planned capacity, the master schedule is considered realistic. More than 20% greater than the planned capacity, the master schedule is considered unrealistic. Between 10% and 20% greater than the planned capacity, the master schedule is questionable.
  • 19. In many of today's ERP systems, there is also a "What-If" scenarios analysis capability being built into the capacity planning module, that makes it possible for the scheduler to juggle the numbers - shifting workers, reschedule in and -out, alternate routings, splitting lots, add equipments, off-loading to vendors, overtime, hiring temporary workers and so on.
  • 20. 3 Approaches to Rough- Cut Capacity Planning Capacity planning using Overall factors (CPOF) Approach – the least detailed approach which is quickly computed but is insensitive to shifts in product mix. Bill of Labor – a second approach which involves multiplying two matrices, the bill of labor and the master production schedule.. Resource Profile – approach which takes lead-time offsets into account.
  • 21. Drum-buffer Rope It is an emerging procedure that eliminates the need for iteration found in all RCCP approaches. It is presently used by a small but growing number of corporations.
  • 22. Material Requirements Planning (MRP) It uses Master Production Schedule (MPS) of end items to determine the quantity and timing of component part production. It is capacity insensitive; it implicitly assumes that sufficient capacity is available to produce components at the time they’re needed.
  • 23. APICS Monograph (Berry, Voliman, and Whybark 1979) presents case histories of several companies, including details on the capacity planning process.
  • 24. Production Planning & Control Capacity management techniques usually are separated into four categories that represent the four time horizons : Manufacturing Resource Planning (MRP II) Aggregate Production Planning Rough Cut Capacity Planning (RCCP) Capacity Requirements Planning (CRP).
  • 25. In any MRP system, the same sequence is to create a master schedule, use Rough Cut Capacity Planning to verify that the MPS is feasible, perform the MRP explosion, and send the Planned Order Release data to Capacity Requirements Planning
  • 26. Role of RCCP in the overall PPC system: To develop an achievable Master Production Schedule. To plan and control priorities and capacities. Priority Planning is the process of specifying batch quantities and their start and finish dates for all Supply Orders where procurement and manufacturing are involved. Priority Control is making the right things at the right time. It is completely dependent on maintaining a balance between MPS requirements and factory Output rates, in which suppliers delivery performance is vital. Capacity planning is the task of determining how much output is needed from factory and from suppliers. Capacity control is the comparison between planned levels and actual outputs achieved, and the identification of significant variances above or below plan. Corrective action must be done quickly (adjust capacity or changing the master schedule).
  • 27. Typical resources that might be planned as pat of rough-cut capacity planning: Overall plant capacity Labor hours in total or for people with unique skills Assembly hours in a specific cell or bottleneck process. Testing cell capacity Engineering hours needed to configure the final product to the customer’s specification. Space required in a warehouse or storage area Waste or effluent release, etc. Shipping labor Design time or credit release time Inspection or QC time Supplier Capacity
  • 28. Rough-Cut Capacity Planning Functions Shows consumption of critical resources. Enables master schedulers to: Test end-item production plans Calculate capacity to meet the master schedule Compare and modify required and planned capacity Analyze load on key resources by time period Isolate and resolve potential problems.
  • 29.
  • 30. Rough-cut Capacity Planning V.S. Capacity Planning CRP uses time-phased material plan information, while RCCP uses aggregate data. MRP takes into account capacity stored as inventory. Shop floor systems take into account W.I.P. – only consider what's needed to complete the requirement. CRP considers service and spare parts requirements also.
  • 31. EXAMPLE problem: Let's assume a lamps manufacturer I call it Johor's Lamps. Johor's Lamps runs 3 shifts, 120 hours per week from Monday to Friday; Planned Production Lost Time per shift (change shift & rest time) is 35 minutes, and company allows a maximum overtime of 10% of per shift either during weekdays or through Sat. & Sunday.
  • 32.
  • 33.
  • 34.
  • 35.
  • 36.
  • 37.
  • 38.
  • 39.
  • 40.
  • 41.