SlideShare une entreprise Scribd logo
1  sur  11
Télécharger pour lire hors ligne
A case study into the effects of wind
loading on pushing and pulling manual
handling operations
James McCann
2015
A study into the use and operations of manually operated gates from a shop floor perspective
.
Introduction .
A Manager when asked, whatthe safe wind speed would be for safe operations of manually operated gates, did
not know! Nor did the manager know how much force was required to put the gate into motion even without the
effects of wind. As it would only require the wind to exert a force greater than that needed to set the gate in
motion and if uncontrolled to accelerate possibly to a dangerous extent, this should be or ought to be regarded as
a significant finding in a risk assessment. The Risk Assessments that were carried out indeed mention 'windy
conditions' however failed to further amplify what was meant by windy conditions, In any manual handling
operation it is the responsibility of those carrying out the work to carry out a Risk Assessment prior to
commencement of the work. This begs the question as to how the operators can carry out a dynammic risk
assessment prior to the operating of a manually operated gate, in windy conditions, that is 'adequate and
sufficient' if they do not have the information or tools needed to make the assessment? Or indeed what the safe
parameters are after the assessment. One suggestion that was made, was for theoperators to 'test' whether or not
they can operate the gate safely! This would be akin to testing whether a gun was loaded by pulling the trigger.
Operators have complained of aches and pains after prolonged use, there have also been a number of accidents
and near miss reports involving 'windy conditions' as being a contributory factor that have not been taken into
consideration
The HSE guidance regarding Risk Factors to be considered TILE;- TASK, INDIVIDUAL, LOAD &
ENVIRONMENT appears to underplay the influence of wind as a significant hazard to manual handling
operations seemingly sending the wrong measage regarding communication of risk. Manual handling injuries
reportedly contribute to one third of all 3 day absence, one wonders to what extent wind played as a factor in
these manual handling injuries?
A further suggestion that if in doubt, another person will be asked to help. None of the gates examined in this
study were found to be suited for 'team' operating and it is doubtful that the HSE guidanceof "2/3 the combined
capacity" would be appropriate for any gate operations as the positioning of adequate handles would
undoubtedly make coordination difficult and increase therisk of serious injury. None of the gates looked at have
extra handles for 'team operation' and in some cases are not been fitted with any handles!
It has been observed that gates are frequently used as convenient places to place site information notices, this
practice increases the effect of wind loading on the gate by increasing the effective surface area exposed to the
wind.
Accidents; In simple terms, when the wind acts on a gate, the gateacts like a sail. The magnitude of the wind
pressure will be at its greatestwhen acting perpendicularly to the gateand willdecrease proportionally as the
gate opens or closes, to use a sailing analogy 'luffing' or depowering of a sail. If the initial impetus from the sum
of the wind and human force is greater than the force required to keep thegate in motion then thegate will
accelerate and require an equal and opposite force to stop the momentum. If this force is greater than can be
controlled by the operator they willeither be dragged or willlet go and the gatewill swing out of control until it
reaches a solid object that will absorb or disperse the kinetic energy . The greater themass of the gate the
greater the kinetic energy and thegreater thecrash. When the wind strength is gusting and the area of the gate is
large enough then the force exerted by the wind maybesudden and overwhelming for the operator, in tests a
2000 kg gate reqired an impetus of 9kgf and a continuous force of 5kgf to maintain a walking pace of 3mph
however a gust of wind recorded an increase to 21.5kgf requiring theoperator to exert an equal and opposite
force (pulling) to bring thegate safely to a halt, simmilarly when closing the gate the operator experienced an
increase in effort to the same magnitude increasing to 21.5kgf (pushing) over a distance of 7m in this case the
greatest magnitude was at the end of the travel distance and theoperator now had to change sidesand hold the
gate with one hand inorder to secure the retaining bolt. This operation being repeated several times in a one hour
period.. Other environmental conditions included: heavy rain, cold, poor ,lighting and night shift, dressed in full
ppe of high visability jacket and over trousers on top of a uniform.
In one reportable (over 3 days) accident which involved opening and closing a 1500kg gate 4 x 4m in a full
force eight gale to allow upto 12 pedestrians access between 0700 and 0800 unaware that the securing hook had
not engaged properly the guard moved towards a pedestrian to check their id passes and was hit from behind
and catapulted into the opposite gate leaf and trapped by the closing leaf, he sustained damage to three vertebrae
and a chipped thigh bone. The cause of this accident was investigated from an office and declared as an operator
error, on inspection of the risk assessment there was no mention of wind, although mentioned in the assessment,
the reason a pedestrian gate or automation were not put in place (although the electrical controls were fitted),
was that it was not cost effective? how this computation was made is unclear. Not cost effective is simply
another way of saying 'notreasonably practicable' The test here would be 'Edwards v. The National Coal Board'
and in Coltness Iron Co v Sharp. Lord Atkin said: "The time of non-protection is so short, and
the time, trouble and expense of any other form of protection is so disproportionate that I
think the defence is proved." This shows that in every case it is the risk that has to be weighed
against the measures necessary to eliminate the risk. The greater the risk, no doubt, the less
will be the weight to be given to the factor of cost.
There would appear to be a number of conflicting 'risk perceptions' at work here or perhaps one of the many
myths surrunding risk , Sven Ove Hanssson Philosophy Unit RIT Stockholm et al . The risk to the individual
and the risk to security. Empirical v. Intelegence
There appears to be little or no empirical data available for manual handling of large single or double leafed
gates and the effects that wind loading has on them, this is probably as a result of increased automation
C RR 248/1999. AK Weyman & CJ Kelly In their Repor t highlight the many Risk Per ception & R isk
C ommunication Theor ies. One particular comentary stood out "However, the degree of consensu s
r egarding the precise nature of the influence of organisational role on per ception of r isk appear s to be
limited Lee et al (1993) for example, pr ovide findings which indicate that managers and supervisor s tend
to be mor e cautious in their appr oaches to r isk than workmen. By contrast other stu dies have shown that
supervisor s ar e poor sour ces of risk information and have a tendency to und erestimate r isk, r eportedly
they ar e 'too far r emoved from operations to make meaningful assessments, R osner & Markowitz (1995)
or mor e exposed to pr oduction pr essur es than other staff, Ostber g (1980) .
There are of course many other reasons and theories suggesting reasons for poor risk communication, perhaps
the expression ' aquila non capit muscas' may have some resonance whereby opening of gates is generally a
security function carried out by low skilled staff and health and safety is percieved to be a low priority over
security and perhaps it is only for those in the lowest levels of organisations that the cost of automation "is not
cost effective". This came into sharpe focus recently, The BBC Reported that a security officer in India was
murdered by being run over, for, "not opening a security gate fast enough" Other communication failures have
come to light whereby security officers failed to express their reasoning for having a security gate open " the
gate was too heavy" theresponse " no heavier than yesterday, now get it closed" the difference between the days
in question was that the previous day there was no wind on the next a gale force 8 was blowing!. From first
hand experience the higher the security risk the less health safety or welfare are considered! The less authority
within an organisation the less likely to challenge poor decission making by those with authority, this manifests
it's self in statements ' just get on with it' and ' you will have to put in a business plan' before changes can be
made. This becomes more evident when on closer inspection many of the gates were found to be below
industry standards to the point of being extremely dangerous. Fig 3, 1, 2, 3 5, 6, 7 & 8
It is regognised that gates come in different sizes, mass and drag coefficient making it difficult to give a more
accurate estimate compared with other push/ pulling manual handling operations, however it is believed that
sufficient data can be obtained that will allow guidance to be given as to the effects of wind loading to enable a
risk assessment to be made that is adequate and sufficient to reduce the risks to ALARP or indeed to justify
automation. Many of the gates looked at were installed prior to much of the regulations now inforce and only
recently brought into operation or back into operational use after many years of restricted use.. The imperative
to bring back these gates would appear to override safety issues or that the risks to security justifies the means,
this attidudinal disconect from policy which "inextricably linked H&S to security" manifest it's self in
comments by managers and supervisors to "just get on with it" neither empirical or epidemiological evidence
being considered, risk assessments apparently downplaying risk or ignoring wind as a significanthazard
Manual handling of loads, pushing and pulling, this type of operation is discused in HSE RR526 Fig 1 giving
data on frequency of pushing and pulling loads, giving guidance estimates of safe loads over distance and time/
frequency of pushing and pulling activities and is a usefulstart point.
The data collected and reproduced in RR526 was however obtained under laboratory conditions and were not
influenced by other contributory environmental factors or conditions such as wind loading. Although air
movement is mentioned as a contributory factor, contextually, 'draughts' only refer to an indoor environmental
condition and would not have sufficient energy to be regarded as significant to the load being pushed or pulled
but may have an effect on the operator I.e. Comfort.
There is also the problem of how to work out the math involved e.g. angular momentum/ torque the sum of the
forces, with or against the wind force, both positive or negative and measuring angles / vectors e.t.c. This is
complicated enough but becomes almost imposible where the wind force is unpradictable and variable, to
complicate matters the designs or where construction materials and dimentions differ make it unrealistic that
'generic' Risk Assessments would be sufficient Fig2 demonstrates the generic type risk/hazard identification
associated with gates.
There are two elements of risk associated with wind loading, first, the increase/decrease in load force for the
operator and second, the uncontrolled acceleration caused by wind loading. Unlike other manual handling
operations, pushing and pulling of gates or loads are often subject to sudden increase and or decrease of load
from the effects of wind . The analogy here would be pushing and pulling a load using a trolly, where, sudden
and unpredictable varying degrees of slopes appeared out of nowhere. Opening a gate or moving a load maybe
easier with the wind however converslely closing or changing direction would be subject to an increase in effort
from the effect of the wind acting against the gate or load. Gusting winds are more difficult to contend with, the
increased pressure may be sudden and overwhelming or again conversely a sudden drop in wind pressure may
be difficult to compensate for and control resulting in an increase likelyhood of serious injury.. These problems
are exacerbated by the lack of suitable handles often only one being fitted on one side of a gate or the only
handle thatis available is fitted on a slide bolt, often only a short metal bar.
The HSE, through examination of reported accidents, have determined that 11% musculoskeletal injuries
resulting from manual handling operations are associated with pushing or pulling loads, however it is unclear
whether any of the reported incidents included wind loading as a contributory factor.
Wind loading is recognised in many other areas of Health and Safety I.e crane operations and also plays a major
role in structural engineering
There is little to no wind loading information available in Gate Manufacturers Data sheets e.g. Pitts Security
Gates, Barriers, Blockers and Bollards PAS 68 Range, et al. British Standards BS EN 13241-2003, BS EN
12635-2002 BS EN 12605, BS EN 13849 - 2008 Although some of these Standards reference automated gates,
many of these gates can be disconected from their power source and can be operated manually when necessary.
Swing type security barriers found in e.g. Carparks, were the subjectof a HSE warning alert after a number of
accidents being reported (HSE Advice on horizontal swing carpark barriers) A number of simmilarities are
apparent, human intervention, locking mechenisms, the effects of wind and poor lighting and safety marking.
It is doubtful that mechanical dampening devices would be beneficial as they would only control sudden
changes in force however thepush pullforces would remain.or indeed be increased.
OBJECTIVES The purpose of this study is to examinethe effects of wind loading on manually operated gates.
Recognising that the operators would not have access to measuring devices inorder to carryout adequate or
sufficient risk assessments prior to operating the gates. To give managers and operators guidance on the safe
perameters for manually operating gates thatare simple and easy to understand
Examine if wind loading increases the load above the accepted limits 20kgf for men 15 kgf for women, 10 kgf
and 7 kgf respectively for keeping the load in motion. The HSE advise " that even for a minority of fit well
trained individuals under faverable conditions, may if the operation guideline limits are exceeded by a factor of
2 or more may be at risk of serious injury"
Determine the operationalloads in stillair
Determine wind speeds above which wind loading would increase the likelyhood of serious injury
Devise a graphicmanual handling toolthat willgive clearly understood inform
Determining risk factors for inclusion in the graphicmanual handling tool
l Provide estimates of impact(kinetic energy) forces from the gates whilst in motion
l We will be looking at the effects of wind loading on gates as they affect the manual operation and not the
structural integrity or design of the gates themselves but concentrating on the generality of the effects that
wind loading may have and to prepare guidance on contributory risk
l For ease of calculation a number of assumptions are being made, area of the gates in question will be
regarded as solid flat surfaces this will give an absolute maximum for wind pressure acting on the gate.
Angular movement/acceleration will be regarded as non vector or torque for simplicity of calculation as
wind direction is complex and variable therefor willbe calculated as perpendicular to thegate, again giving
a maximum for wind loading. It will be assumed that the greatest area of danger for the operator is at the
furthest from the hinge and refered to as the impact zone (IZ) . For the purpose of these calculations it is
not necessary for a higher degree of accuracy however if a higher degree of accuracy is required this may
be achieved by using the data and appropriate non linear formulas. The angle of wind direction relative to
thegate willbe recorded for those that wish to make more accurate assessments.
l As the most important factor will be that of wind pressure acting on the gates and not the capabilities of
the opperators, it is intended to make direct measurements under a range of wind conditions and compare
them to those taken under still air conditions this will give a direct comparison of increased loading on
gates of different dimensions and construction under different environmentalconditions
l Wind speed = m/s
l Acceleration =m/s^2
l Mass = kg
l Wind pressure = kg/m^2 = N/m^2
l Force, pushing or pulling required to control the gatein motion = kgf
Fig 1
Fig 1 It would be tempting for managers not to consider wind as a significant hazard. For managers,
RR526 Although "other environmentalfactors" have to be considered it is believed thatthisreport missed the
significance of the effects of wind on high risk push pull operations being carried out
Figure 2
Fig 2 . For the average person, carrying out the mathmatics prior to a manual handling
operation (push pull) would be wholly unreasonable and like an Inspector "who do not
typically pocess objective force measuring equipement " RR562 Executive
Recommendations, et al, would be unrealistic
Figure 3 Typical layout for identifying risk areas on gates
Note that the forces required to operate the gate or frequency of use (push pull manual
handling) handles and fittings are absent nor is wind identified as a significant factor. The
'weight' of the gate is supported by the hinges and load bearing style however the mass of the
gate is independent of how the weight is supported.
Fig 4a Guidance to the increase in force required to control the loading
Figure 4a A suggested diagram of the extra force needed to carryout push pull opperations.
where wind is a significant factor. For simplicity and ease of use this diagram uses the same
'traffic signal' format and should be used in conjunction with the load diagram Fig 1. The
combination of wind pressure in N/m^2 and the bodily force in kgf to control the gate whilst
in motion
Fig 4b
Fig 4b Wind force conversion
Figure 5. Suggested data for inclusion
Figure 5 Data collection
Data collection
Details of the gates, construction, dimensions and approximate mass..
Number of hinges and fittings
Orientation I.e 270°-90° = East / West. 0° - 180° = North / South
Wind speed and direction (from perpendicular to the gate) 0° = perpendicular .
Defects
Environmental conditions, day, night, rain, lighting etc.

Contenu connexe

Tendances

office final ppt [7760835] final update
office final ppt [7760835] final updateoffice final ppt [7760835] final update
office final ppt [7760835] final updateAashish Soin
 
Pets inc-04 procedimiento de transporte de materiales, acarreo y descarga con...
Pets inc-04 procedimiento de transporte de materiales, acarreo y descarga con...Pets inc-04 procedimiento de transporte de materiales, acarreo y descarga con...
Pets inc-04 procedimiento de transporte de materiales, acarreo y descarga con...MAVILA ELIZABETH ROJAS SILVA
 
PETAR de Trabajos en Altura MyS (versión 2).docx
PETAR de Trabajos en Altura MyS (versión 2).docxPETAR de Trabajos en Altura MyS (versión 2).docx
PETAR de Trabajos en Altura MyS (versión 2).docxabel foraquita choque
 
Operador martillo demoledor
Operador martillo demoledorOperador martillo demoledor
Operador martillo demoledorRose Tapia
 
14-Hazardous Area Classification.ppt
14-Hazardous Area Classification.ppt14-Hazardous Area Classification.ppt
14-Hazardous Area Classification.pptAsadPatel11
 
NFPA 780 detailed Risk assessment
NFPA 780 detailed Risk assessmentNFPA 780 detailed Risk assessment
NFPA 780 detailed Risk assessmentJose Dariel Arcila
 
Presentacion izamiento-de-cargas
Presentacion izamiento-de-cargasPresentacion izamiento-de-cargas
Presentacion izamiento-de-cargasOswaldo Velasquez
 
hot works for construction of temporary facilities
hot works for construction of temporary facilitieshot works for construction of temporary facilities
hot works for construction of temporary facilitiesFãrük Ñäzmî
 
Storage Tank Fire And Solution I Gaurav Singh Rajput
Storage Tank Fire And Solution I Gaurav Singh RajputStorage Tank Fire And Solution I Gaurav Singh Rajput
Storage Tank Fire And Solution I Gaurav Singh RajputGaurav Singh Rajput
 
41914644 storage-tank-design-calculations-seismic-design-overturning-moment-b...
41914644 storage-tank-design-calculations-seismic-design-overturning-moment-b...41914644 storage-tank-design-calculations-seismic-design-overturning-moment-b...
41914644 storage-tank-design-calculations-seismic-design-overturning-moment-b...141jdf
 
Excavaciones manual-de-zanjas
Excavaciones manual-de-zanjasExcavaciones manual-de-zanjas
Excavaciones manual-de-zanjasMauricio Castro
 
Pets fls-mol22 fabricaciones diversas en taller de soldadura
Pets fls-mol22 fabricaciones diversas en taller de soldaduraPets fls-mol22 fabricaciones diversas en taller de soldadura
Pets fls-mol22 fabricaciones diversas en taller de soldaduraJose Carlos Durand Medrano
 
Trunnion calculation sheet
Trunnion calculation sheetTrunnion calculation sheet
Trunnion calculation sheetFreeusersabi
 
MAC-BV-ITC-003 Desmontaje de Estructuras y Coberturas Sector IV..pdf
MAC-BV-ITC-003 Desmontaje de Estructuras y Coberturas Sector IV..pdfMAC-BV-ITC-003 Desmontaje de Estructuras y Coberturas Sector IV..pdf
MAC-BV-ITC-003 Desmontaje de Estructuras y Coberturas Sector IV..pdfAnthonyLopezCuper
 
SG-SSMA-IPERC Excavacion y Movimiento de Tierras.pdf
SG-SSMA-IPERC Excavacion y Movimiento de Tierras.pdfSG-SSMA-IPERC Excavacion y Movimiento de Tierras.pdf
SG-SSMA-IPERC Excavacion y Movimiento de Tierras.pdfYoiceDamarisCardenas
 
Ehst 18 trabajos de alto riesgo
Ehst 18 trabajos de alto riesgoEhst 18 trabajos de alto riesgo
Ehst 18 trabajos de alto riesgoAlberto Galván
 

Tendances (20)

office final ppt [7760835] final update
office final ppt [7760835] final updateoffice final ppt [7760835] final update
office final ppt [7760835] final update
 
Pets inc-04 procedimiento de transporte de materiales, acarreo y descarga con...
Pets inc-04 procedimiento de transporte de materiales, acarreo y descarga con...Pets inc-04 procedimiento de transporte de materiales, acarreo y descarga con...
Pets inc-04 procedimiento de transporte de materiales, acarreo y descarga con...
 
PETAR de Trabajos en Altura MyS (versión 2).docx
PETAR de Trabajos en Altura MyS (versión 2).docxPETAR de Trabajos en Altura MyS (versión 2).docx
PETAR de Trabajos en Altura MyS (versión 2).docx
 
Operador martillo demoledor
Operador martillo demoledorOperador martillo demoledor
Operador martillo demoledor
 
14-Hazardous Area Classification.ppt
14-Hazardous Area Classification.ppt14-Hazardous Area Classification.ppt
14-Hazardous Area Classification.ppt
 
Storage Tank.pdf
Storage Tank.pdfStorage Tank.pdf
Storage Tank.pdf
 
NFPA 780 detailed Risk assessment
NFPA 780 detailed Risk assessmentNFPA 780 detailed Risk assessment
NFPA 780 detailed Risk assessment
 
Presentacion izamiento-de-cargas
Presentacion izamiento-de-cargasPresentacion izamiento-de-cargas
Presentacion izamiento-de-cargas
 
hot works for construction of temporary facilities
hot works for construction of temporary facilitieshot works for construction of temporary facilities
hot works for construction of temporary facilities
 
Storage Tank Fire And Solution I Gaurav Singh Rajput
Storage Tank Fire And Solution I Gaurav Singh RajputStorage Tank Fire And Solution I Gaurav Singh Rajput
Storage Tank Fire And Solution I Gaurav Singh Rajput
 
floating tank design
floating tank designfloating tank design
floating tank design
 
41914644 storage-tank-design-calculations-seismic-design-overturning-moment-b...
41914644 storage-tank-design-calculations-seismic-design-overturning-moment-b...41914644 storage-tank-design-calculations-seismic-design-overturning-moment-b...
41914644 storage-tank-design-calculations-seismic-design-overturning-moment-b...
 
Excavaciones manual-de-zanjas
Excavaciones manual-de-zanjasExcavaciones manual-de-zanjas
Excavaciones manual-de-zanjas
 
Tutorial #4 - SACS Basic
Tutorial #4 - SACS BasicTutorial #4 - SACS Basic
Tutorial #4 - SACS Basic
 
Hazloc overview
Hazloc overviewHazloc overview
Hazloc overview
 
Pets fls-mol22 fabricaciones diversas en taller de soldadura
Pets fls-mol22 fabricaciones diversas en taller de soldaduraPets fls-mol22 fabricaciones diversas en taller de soldadura
Pets fls-mol22 fabricaciones diversas en taller de soldadura
 
Trunnion calculation sheet
Trunnion calculation sheetTrunnion calculation sheet
Trunnion calculation sheet
 
MAC-BV-ITC-003 Desmontaje de Estructuras y Coberturas Sector IV..pdf
MAC-BV-ITC-003 Desmontaje de Estructuras y Coberturas Sector IV..pdfMAC-BV-ITC-003 Desmontaje de Estructuras y Coberturas Sector IV..pdf
MAC-BV-ITC-003 Desmontaje de Estructuras y Coberturas Sector IV..pdf
 
SG-SSMA-IPERC Excavacion y Movimiento de Tierras.pdf
SG-SSMA-IPERC Excavacion y Movimiento de Tierras.pdfSG-SSMA-IPERC Excavacion y Movimiento de Tierras.pdf
SG-SSMA-IPERC Excavacion y Movimiento de Tierras.pdf
 
Ehst 18 trabajos de alto riesgo
Ehst 18 trabajos de alto riesgoEhst 18 trabajos de alto riesgo
Ehst 18 trabajos de alto riesgo
 

Similaire à Wind loading on gates

Enclosed Space Operations - Do We Understand the risks
Enclosed Space Operations - Do We Understand the risksEnclosed Space Operations - Do We Understand the risks
Enclosed Space Operations - Do We Understand the risksNippin Anand
 
Caught in Numbers, Lost in Focus: What it Means to Manage Safety in Global Sh...
Caught in Numbers, Lost in Focus: What it Means to Manage Safety in Global Sh...Caught in Numbers, Lost in Focus: What it Means to Manage Safety in Global Sh...
Caught in Numbers, Lost in Focus: What it Means to Manage Safety in Global Sh...Nippin Anand
 
Accident investigations at Sea: Learning from Failure or Failure to Learn?
Accident investigations at Sea: Learning from Failure or Failure to Learn?Accident investigations at Sea: Learning from Failure or Failure to Learn?
Accident investigations at Sea: Learning from Failure or Failure to Learn?Nippin Anand
 
assignment 2
assignment 2assignment 2
assignment 2Kai Guan
 
Technology Encourages Employees To Promote Facility Safety
Technology Encourages Employees To Promote Facility SafetyTechnology Encourages Employees To Promote Facility Safety
Technology Encourages Employees To Promote Facility SafetyGarrett Foley
 
Running Head SAFETY IN AVIATION .docx
Running Head SAFETY IN AVIATION                                  .docxRunning Head SAFETY IN AVIATION                                  .docx
Running Head SAFETY IN AVIATION .docxcharisellington63520
 
Running Head SAFETY IN AVIATION .docx
Running Head SAFETY IN AVIATION                                  .docxRunning Head SAFETY IN AVIATION                                  .docx
Running Head SAFETY IN AVIATION .docxtodd521
 
JUST CULTURE IN AVIATION SAFETY MANAGEMENT (ASM)
JUST CULTURE IN AVIATION SAFETY MANAGEMENT (ASM)JUST CULTURE IN AVIATION SAFETY MANAGEMENT (ASM)
JUST CULTURE IN AVIATION SAFETY MANAGEMENT (ASM)DigitalPower
 
Expensive ergonomics
Expensive ergonomicsExpensive ergonomics
Expensive ergonomicsMert Daggecen
 
7 STEPS TO LEADERSHIP EXCELLENCE IN WORK SAFETY & HEALTH.
7 STEPS TO LEADERSHIP EXCELLENCE IN WORK SAFETY & HEALTH. 7 STEPS TO LEADERSHIP EXCELLENCE IN WORK SAFETY & HEALTH.
7 STEPS TO LEADERSHIP EXCELLENCE IN WORK SAFETY & HEALTH. Abdul Shukor
 
'Risk Culture' - The missing link in Safety Culture?
'Risk Culture' - The missing link in Safety Culture?'Risk Culture' - The missing link in Safety Culture?
'Risk Culture' - The missing link in Safety Culture?Cranfield University
 
Analyzing The Near Miss: Are companies overlooking crucial data?
Analyzing The Near Miss: Are companies overlooking crucial data?Analyzing The Near Miss: Are companies overlooking crucial data?
Analyzing The Near Miss: Are companies overlooking crucial data?Garrett Foley
 
arriers thatd due to lackm factorsthese causalent ca.docx
arriers thatd due to lackm factorsthese causalent ca.docxarriers thatd due to lackm factorsthese causalent ca.docx
arriers thatd due to lackm factorsthese causalent ca.docxdavezstarr61655
 
Running head ACCIDENT INVESTIGATION1ACCIDENT INVESTIGATION5.docx
Running head ACCIDENT INVESTIGATION1ACCIDENT INVESTIGATION5.docxRunning head ACCIDENT INVESTIGATION1ACCIDENT INVESTIGATION5.docx
Running head ACCIDENT INVESTIGATION1ACCIDENT INVESTIGATION5.docxSUBHI7
 
Angharad Boyson dissertation
Angharad Boyson dissertationAngharad Boyson dissertation
Angharad Boyson dissertationAngharad Boyson
 

Similaire à Wind loading on gates (20)

Risk Assessment
Risk AssessmentRisk Assessment
Risk Assessment
 
Enclosed Space Operations - Do We Understand the risks
Enclosed Space Operations - Do We Understand the risksEnclosed Space Operations - Do We Understand the risks
Enclosed Space Operations - Do We Understand the risks
 
Caught in Numbers, Lost in Focus: What it Means to Manage Safety in Global Sh...
Caught in Numbers, Lost in Focus: What it Means to Manage Safety in Global Sh...Caught in Numbers, Lost in Focus: What it Means to Manage Safety in Global Sh...
Caught in Numbers, Lost in Focus: What it Means to Manage Safety in Global Sh...
 
Accident investigations at Sea: Learning from Failure or Failure to Learn?
Accident investigations at Sea: Learning from Failure or Failure to Learn?Accident investigations at Sea: Learning from Failure or Failure to Learn?
Accident investigations at Sea: Learning from Failure or Failure to Learn?
 
assignment 2
assignment 2assignment 2
assignment 2
 
Technology Encourages Employees To Promote Facility Safety
Technology Encourages Employees To Promote Facility SafetyTechnology Encourages Employees To Promote Facility Safety
Technology Encourages Employees To Promote Facility Safety
 
Running Head SAFETY IN AVIATION .docx
Running Head SAFETY IN AVIATION                                  .docxRunning Head SAFETY IN AVIATION                                  .docx
Running Head SAFETY IN AVIATION .docx
 
Running Head SAFETY IN AVIATION .docx
Running Head SAFETY IN AVIATION                                  .docxRunning Head SAFETY IN AVIATION                                  .docx
Running Head SAFETY IN AVIATION .docx
 
JUST CULTURE IN AVIATION SAFETY MANAGEMENT (ASM)
JUST CULTURE IN AVIATION SAFETY MANAGEMENT (ASM)JUST CULTURE IN AVIATION SAFETY MANAGEMENT (ASM)
JUST CULTURE IN AVIATION SAFETY MANAGEMENT (ASM)
 
Near miss mgt. in chemical process
Near miss mgt. in chemical processNear miss mgt. in chemical process
Near miss mgt. in chemical process
 
Expensive ergonomics
Expensive ergonomicsExpensive ergonomics
Expensive ergonomics
 
7 STEPS TO LEADERSHIP EXCELLENCE IN WORK SAFETY & HEALTH.
7 STEPS TO LEADERSHIP EXCELLENCE IN WORK SAFETY & HEALTH. 7 STEPS TO LEADERSHIP EXCELLENCE IN WORK SAFETY & HEALTH.
7 STEPS TO LEADERSHIP EXCELLENCE IN WORK SAFETY & HEALTH.
 
'Risk Culture' - The missing link in Safety Culture?
'Risk Culture' - The missing link in Safety Culture?'Risk Culture' - The missing link in Safety Culture?
'Risk Culture' - The missing link in Safety Culture?
 
Analyzing The Near Miss: Are companies overlooking crucial data?
Analyzing The Near Miss: Are companies overlooking crucial data?Analyzing The Near Miss: Are companies overlooking crucial data?
Analyzing The Near Miss: Are companies overlooking crucial data?
 
arriers thatd due to lackm factorsthese causalent ca.docx
arriers thatd due to lackm factorsthese causalent ca.docxarriers thatd due to lackm factorsthese causalent ca.docx
arriers thatd due to lackm factorsthese causalent ca.docx
 
Safety Matters Fall 2015
Safety Matters Fall 2015Safety Matters Fall 2015
Safety Matters Fall 2015
 
Running head ACCIDENT INVESTIGATION1ACCIDENT INVESTIGATION5.docx
Running head ACCIDENT INVESTIGATION1ACCIDENT INVESTIGATION5.docxRunning head ACCIDENT INVESTIGATION1ACCIDENT INVESTIGATION5.docx
Running head ACCIDENT INVESTIGATION1ACCIDENT INVESTIGATION5.docx
 
5 steps prior erecting a scaffold
5 steps prior erecting a scaffold5 steps prior erecting a scaffold
5 steps prior erecting a scaffold
 
Angharad Boyson dissertation
Angharad Boyson dissertationAngharad Boyson dissertation
Angharad Boyson dissertation
 
Pace IT - Introduction to Safety Procedures
Pace IT - Introduction to Safety ProceduresPace IT - Introduction to Safety Procedures
Pace IT - Introduction to Safety Procedures
 

Plus de James McCann

For decades the question of how good and evil originate and manifest in us wa...
For decades the question of how good and evil originate and manifest in us wa...For decades the question of how good and evil originate and manifest in us wa...
For decades the question of how good and evil originate and manifest in us wa...James McCann
 
Accident investigation full version
Accident investigation full versionAccident investigation full version
Accident investigation full versionJames McCann
 
Promoting a positive health and safety culture
Promoting a positive health and safety culturePromoting a positive health and safety culture
Promoting a positive health and safety cultureJames McCann
 
Full moon fallacy.pptx2
Full moon fallacy.pptx2Full moon fallacy.pptx2
Full moon fallacy.pptx2James McCann
 
Managing disability 5
Managing disability 5Managing disability 5
Managing disability 5James McCann
 
Health safety and disability
Health safety and disabilityHealth safety and disability
Health safety and disabilityJames McCann
 
Floodprobe factsheet-casestudy-gloucester
Floodprobe factsheet-casestudy-gloucesterFloodprobe factsheet-casestudy-gloucester
Floodprobe factsheet-casestudy-gloucesterJames McCann
 
Presentation globalisation & Health and Safety
Presentation globalisation & Health and SafetyPresentation globalisation & Health and Safety
Presentation globalisation & Health and SafetyJames McCann
 
Health and safety_is_just_common_sense...
Health and safety_is_just_common_sense...Health and safety_is_just_common_sense...
Health and safety_is_just_common_sense...James McCann
 
D Part 2 H & S Regulations
D  Part 2 H & S RegulationsD  Part 2 H & S Regulations
D Part 2 H & S RegulationsJames McCann
 
D Part 3 Health Safety Revision By J Mc Cann
D  Part 3 Health Safety Revision By J Mc CannD  Part 3 Health Safety Revision By J Mc Cann
D Part 3 Health Safety Revision By J Mc CannJames McCann
 
D Part 4 Hswa Revision Law
D  Part 4 Hswa  Revision LawD  Part 4 Hswa  Revision Law
D Part 4 Hswa Revision LawJames McCann
 
D Part 7 Section 2 Hswa Revision
D  Part 7 Section 2 Hswa RevisionD  Part 7 Section 2 Hswa Revision
D Part 7 Section 2 Hswa RevisionJames McCann
 
D Part 8 Hseoh Conference 2005
D  Part 8 Hseoh Conference 2005D  Part 8 Hseoh Conference 2005
D Part 8 Hseoh Conference 2005James McCann
 
D Part 9 H & S Regs Revision By J Mc Cann
D  Part 9 H & S Regs Revision By J Mc CannD  Part 9 H & S Regs Revision By J Mc Cann
D Part 9 H & S Regs Revision By J Mc CannJames McCann
 
D Part 5 Revision 6 Pack
D  Part 5 Revision 6 PackD  Part 5 Revision 6 Pack
D Part 5 Revision 6 PackJames McCann
 

Plus de James McCann (20)

For decades the question of how good and evil originate and manifest in us wa...
For decades the question of how good and evil originate and manifest in us wa...For decades the question of how good and evil originate and manifest in us wa...
For decades the question of how good and evil originate and manifest in us wa...
 
Accident investigation full version
Accident investigation full versionAccident investigation full version
Accident investigation full version
 
Promoting a positive health and safety culture
Promoting a positive health and safety culturePromoting a positive health and safety culture
Promoting a positive health and safety culture
 
Full moon fallacy.pptx2
Full moon fallacy.pptx2Full moon fallacy.pptx2
Full moon fallacy.pptx2
 
Managing disability 5
Managing disability 5Managing disability 5
Managing disability 5
 
Health safety and disability
Health safety and disabilityHealth safety and disability
Health safety and disability
 
BACK TO THE FLOOR
BACK TO THE FLOORBACK TO THE FLOOR
BACK TO THE FLOOR
 
Floodprobe factsheet-casestudy-gloucester
Floodprobe factsheet-casestudy-gloucesterFloodprobe factsheet-casestudy-gloucester
Floodprobe factsheet-casestudy-gloucester
 
Presentation globalisation & Health and Safety
Presentation globalisation & Health and SafetyPresentation globalisation & Health and Safety
Presentation globalisation & Health and Safety
 
Shift work
Shift workShift work
Shift work
 
Health and safety_is_just_common_sense...
Health and safety_is_just_common_sense...Health and safety_is_just_common_sense...
Health and safety_is_just_common_sense...
 
Work At Height
Work At HeightWork At Height
Work At Height
 
First Aid Slides
First Aid SlidesFirst Aid Slides
First Aid Slides
 
D Part 2 H & S Regulations
D  Part 2 H & S RegulationsD  Part 2 H & S Regulations
D Part 2 H & S Regulations
 
D Part 3 Health Safety Revision By J Mc Cann
D  Part 3 Health Safety Revision By J Mc CannD  Part 3 Health Safety Revision By J Mc Cann
D Part 3 Health Safety Revision By J Mc Cann
 
D Part 4 Hswa Revision Law
D  Part 4 Hswa  Revision LawD  Part 4 Hswa  Revision Law
D Part 4 Hswa Revision Law
 
D Part 7 Section 2 Hswa Revision
D  Part 7 Section 2 Hswa RevisionD  Part 7 Section 2 Hswa Revision
D Part 7 Section 2 Hswa Revision
 
D Part 8 Hseoh Conference 2005
D  Part 8 Hseoh Conference 2005D  Part 8 Hseoh Conference 2005
D Part 8 Hseoh Conference 2005
 
D Part 9 H & S Regs Revision By J Mc Cann
D  Part 9 H & S Regs Revision By J Mc CannD  Part 9 H & S Regs Revision By J Mc Cann
D Part 9 H & S Regs Revision By J Mc Cann
 
D Part 5 Revision 6 Pack
D  Part 5 Revision 6 PackD  Part 5 Revision 6 Pack
D Part 5 Revision 6 Pack
 

Dernier

THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONjhunlian
 
Mine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxMine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxRomil Mishra
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - GuideGOPINATHS437943
 
National Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdfNational Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdfRajuKanojiya4
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substationstephanwindworld
 
Class 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm SystemClass 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm Systemirfanmechengr
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)Dr SOUNDIRARAJ N
 
home automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasadhome automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasadaditya806802
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Industrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.pptIndustrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.pptNarmatha D
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Energy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxEnergy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxsiddharthjain2303
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleAlluxio, Inc.
 
Internet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptxInternet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptxVelmuruganTECE
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 
Virtual memory management in Operating System
Virtual memory management in Operating SystemVirtual memory management in Operating System
Virtual memory management in Operating SystemRashmi Bhat
 

Dernier (20)

THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
 
Mine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxMine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptx
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - Guide
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
National Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdfNational Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdf
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substation
 
Class 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm SystemClass 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm System
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
 
home automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasadhome automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasad
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Industrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.pptIndustrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.ppt
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Energy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxEnergy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptx
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at Scale
 
Internet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptxInternet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptx
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 
Virtual memory management in Operating System
Virtual memory management in Operating SystemVirtual memory management in Operating System
Virtual memory management in Operating System
 

Wind loading on gates

  • 1. A case study into the effects of wind loading on pushing and pulling manual handling operations James McCann 2015
  • 2. A study into the use and operations of manually operated gates from a shop floor perspective . Introduction . A Manager when asked, whatthe safe wind speed would be for safe operations of manually operated gates, did not know! Nor did the manager know how much force was required to put the gate into motion even without the effects of wind. As it would only require the wind to exert a force greater than that needed to set the gate in motion and if uncontrolled to accelerate possibly to a dangerous extent, this should be or ought to be regarded as a significant finding in a risk assessment. The Risk Assessments that were carried out indeed mention 'windy conditions' however failed to further amplify what was meant by windy conditions, In any manual handling operation it is the responsibility of those carrying out the work to carry out a Risk Assessment prior to commencement of the work. This begs the question as to how the operators can carry out a dynammic risk assessment prior to the operating of a manually operated gate, in windy conditions, that is 'adequate and sufficient' if they do not have the information or tools needed to make the assessment? Or indeed what the safe parameters are after the assessment. One suggestion that was made, was for theoperators to 'test' whether or not they can operate the gate safely! This would be akin to testing whether a gun was loaded by pulling the trigger. Operators have complained of aches and pains after prolonged use, there have also been a number of accidents and near miss reports involving 'windy conditions' as being a contributory factor that have not been taken into consideration The HSE guidance regarding Risk Factors to be considered TILE;- TASK, INDIVIDUAL, LOAD & ENVIRONMENT appears to underplay the influence of wind as a significant hazard to manual handling operations seemingly sending the wrong measage regarding communication of risk. Manual handling injuries reportedly contribute to one third of all 3 day absence, one wonders to what extent wind played as a factor in these manual handling injuries? A further suggestion that if in doubt, another person will be asked to help. None of the gates examined in this study were found to be suited for 'team' operating and it is doubtful that the HSE guidanceof "2/3 the combined capacity" would be appropriate for any gate operations as the positioning of adequate handles would undoubtedly make coordination difficult and increase therisk of serious injury. None of the gates looked at have extra handles for 'team operation' and in some cases are not been fitted with any handles! It has been observed that gates are frequently used as convenient places to place site information notices, this practice increases the effect of wind loading on the gate by increasing the effective surface area exposed to the wind. Accidents; In simple terms, when the wind acts on a gate, the gateacts like a sail. The magnitude of the wind pressure will be at its greatestwhen acting perpendicularly to the gateand willdecrease proportionally as the gate opens or closes, to use a sailing analogy 'luffing' or depowering of a sail. If the initial impetus from the sum of the wind and human force is greater than the force required to keep thegate in motion then thegate will accelerate and require an equal and opposite force to stop the momentum. If this force is greater than can be controlled by the operator they willeither be dragged or willlet go and the gatewill swing out of control until it reaches a solid object that will absorb or disperse the kinetic energy . The greater themass of the gate the greater the kinetic energy and thegreater thecrash. When the wind strength is gusting and the area of the gate is large enough then the force exerted by the wind maybesudden and overwhelming for the operator, in tests a 2000 kg gate reqired an impetus of 9kgf and a continuous force of 5kgf to maintain a walking pace of 3mph however a gust of wind recorded an increase to 21.5kgf requiring theoperator to exert an equal and opposite force (pulling) to bring thegate safely to a halt, simmilarly when closing the gate the operator experienced an increase in effort to the same magnitude increasing to 21.5kgf (pushing) over a distance of 7m in this case the
  • 3. greatest magnitude was at the end of the travel distance and theoperator now had to change sidesand hold the gate with one hand inorder to secure the retaining bolt. This operation being repeated several times in a one hour period.. Other environmental conditions included: heavy rain, cold, poor ,lighting and night shift, dressed in full ppe of high visability jacket and over trousers on top of a uniform. In one reportable (over 3 days) accident which involved opening and closing a 1500kg gate 4 x 4m in a full force eight gale to allow upto 12 pedestrians access between 0700 and 0800 unaware that the securing hook had not engaged properly the guard moved towards a pedestrian to check their id passes and was hit from behind and catapulted into the opposite gate leaf and trapped by the closing leaf, he sustained damage to three vertebrae and a chipped thigh bone. The cause of this accident was investigated from an office and declared as an operator error, on inspection of the risk assessment there was no mention of wind, although mentioned in the assessment, the reason a pedestrian gate or automation were not put in place (although the electrical controls were fitted), was that it was not cost effective? how this computation was made is unclear. Not cost effective is simply another way of saying 'notreasonably practicable' The test here would be 'Edwards v. The National Coal Board' and in Coltness Iron Co v Sharp. Lord Atkin said: "The time of non-protection is so short, and the time, trouble and expense of any other form of protection is so disproportionate that I think the defence is proved." This shows that in every case it is the risk that has to be weighed against the measures necessary to eliminate the risk. The greater the risk, no doubt, the less will be the weight to be given to the factor of cost. There would appear to be a number of conflicting 'risk perceptions' at work here or perhaps one of the many myths surrunding risk , Sven Ove Hanssson Philosophy Unit RIT Stockholm et al . The risk to the individual and the risk to security. Empirical v. Intelegence There appears to be little or no empirical data available for manual handling of large single or double leafed gates and the effects that wind loading has on them, this is probably as a result of increased automation C RR 248/1999. AK Weyman & CJ Kelly In their Repor t highlight the many Risk Per ception & R isk C ommunication Theor ies. One particular comentary stood out "However, the degree of consensu s r egarding the precise nature of the influence of organisational role on per ception of r isk appear s to be limited Lee et al (1993) for example, pr ovide findings which indicate that managers and supervisor s tend to be mor e cautious in their appr oaches to r isk than workmen. By contrast other stu dies have shown that supervisor s ar e poor sour ces of risk information and have a tendency to und erestimate r isk, r eportedly they ar e 'too far r emoved from operations to make meaningful assessments, R osner & Markowitz (1995) or mor e exposed to pr oduction pr essur es than other staff, Ostber g (1980) . There are of course many other reasons and theories suggesting reasons for poor risk communication, perhaps the expression ' aquila non capit muscas' may have some resonance whereby opening of gates is generally a security function carried out by low skilled staff and health and safety is percieved to be a low priority over security and perhaps it is only for those in the lowest levels of organisations that the cost of automation "is not cost effective". This came into sharpe focus recently, The BBC Reported that a security officer in India was murdered by being run over, for, "not opening a security gate fast enough" Other communication failures have come to light whereby security officers failed to express their reasoning for having a security gate open " the gate was too heavy" theresponse " no heavier than yesterday, now get it closed" the difference between the days in question was that the previous day there was no wind on the next a gale force 8 was blowing!. From first hand experience the higher the security risk the less health safety or welfare are considered! The less authority
  • 4. within an organisation the less likely to challenge poor decission making by those with authority, this manifests it's self in statements ' just get on with it' and ' you will have to put in a business plan' before changes can be made. This becomes more evident when on closer inspection many of the gates were found to be below industry standards to the point of being extremely dangerous. Fig 3, 1, 2, 3 5, 6, 7 & 8 It is regognised that gates come in different sizes, mass and drag coefficient making it difficult to give a more accurate estimate compared with other push/ pulling manual handling operations, however it is believed that sufficient data can be obtained that will allow guidance to be given as to the effects of wind loading to enable a risk assessment to be made that is adequate and sufficient to reduce the risks to ALARP or indeed to justify automation. Many of the gates looked at were installed prior to much of the regulations now inforce and only recently brought into operation or back into operational use after many years of restricted use.. The imperative to bring back these gates would appear to override safety issues or that the risks to security justifies the means, this attidudinal disconect from policy which "inextricably linked H&S to security" manifest it's self in comments by managers and supervisors to "just get on with it" neither empirical or epidemiological evidence being considered, risk assessments apparently downplaying risk or ignoring wind as a significanthazard Manual handling of loads, pushing and pulling, this type of operation is discused in HSE RR526 Fig 1 giving data on frequency of pushing and pulling loads, giving guidance estimates of safe loads over distance and time/ frequency of pushing and pulling activities and is a usefulstart point. The data collected and reproduced in RR526 was however obtained under laboratory conditions and were not influenced by other contributory environmental factors or conditions such as wind loading. Although air movement is mentioned as a contributory factor, contextually, 'draughts' only refer to an indoor environmental condition and would not have sufficient energy to be regarded as significant to the load being pushed or pulled but may have an effect on the operator I.e. Comfort. There is also the problem of how to work out the math involved e.g. angular momentum/ torque the sum of the forces, with or against the wind force, both positive or negative and measuring angles / vectors e.t.c. This is complicated enough but becomes almost imposible where the wind force is unpradictable and variable, to complicate matters the designs or where construction materials and dimentions differ make it unrealistic that 'generic' Risk Assessments would be sufficient Fig2 demonstrates the generic type risk/hazard identification associated with gates. There are two elements of risk associated with wind loading, first, the increase/decrease in load force for the operator and second, the uncontrolled acceleration caused by wind loading. Unlike other manual handling operations, pushing and pulling of gates or loads are often subject to sudden increase and or decrease of load from the effects of wind . The analogy here would be pushing and pulling a load using a trolly, where, sudden and unpredictable varying degrees of slopes appeared out of nowhere. Opening a gate or moving a load maybe easier with the wind however converslely closing or changing direction would be subject to an increase in effort from the effect of the wind acting against the gate or load. Gusting winds are more difficult to contend with, the increased pressure may be sudden and overwhelming or again conversely a sudden drop in wind pressure may be difficult to compensate for and control resulting in an increase likelyhood of serious injury.. These problems are exacerbated by the lack of suitable handles often only one being fitted on one side of a gate or the only handle thatis available is fitted on a slide bolt, often only a short metal bar. The HSE, through examination of reported accidents, have determined that 11% musculoskeletal injuries resulting from manual handling operations are associated with pushing or pulling loads, however it is unclear whether any of the reported incidents included wind loading as a contributory factor.
  • 5. Wind loading is recognised in many other areas of Health and Safety I.e crane operations and also plays a major role in structural engineering There is little to no wind loading information available in Gate Manufacturers Data sheets e.g. Pitts Security Gates, Barriers, Blockers and Bollards PAS 68 Range, et al. British Standards BS EN 13241-2003, BS EN 12635-2002 BS EN 12605, BS EN 13849 - 2008 Although some of these Standards reference automated gates, many of these gates can be disconected from their power source and can be operated manually when necessary. Swing type security barriers found in e.g. Carparks, were the subjectof a HSE warning alert after a number of accidents being reported (HSE Advice on horizontal swing carpark barriers) A number of simmilarities are apparent, human intervention, locking mechenisms, the effects of wind and poor lighting and safety marking. It is doubtful that mechanical dampening devices would be beneficial as they would only control sudden changes in force however thepush pullforces would remain.or indeed be increased. OBJECTIVES The purpose of this study is to examinethe effects of wind loading on manually operated gates. Recognising that the operators would not have access to measuring devices inorder to carryout adequate or sufficient risk assessments prior to operating the gates. To give managers and operators guidance on the safe perameters for manually operating gates thatare simple and easy to understand Examine if wind loading increases the load above the accepted limits 20kgf for men 15 kgf for women, 10 kgf and 7 kgf respectively for keeping the load in motion. The HSE advise " that even for a minority of fit well trained individuals under faverable conditions, may if the operation guideline limits are exceeded by a factor of 2 or more may be at risk of serious injury" Determine the operationalloads in stillair Determine wind speeds above which wind loading would increase the likelyhood of serious injury Devise a graphicmanual handling toolthat willgive clearly understood inform Determining risk factors for inclusion in the graphicmanual handling tool l Provide estimates of impact(kinetic energy) forces from the gates whilst in motion l We will be looking at the effects of wind loading on gates as they affect the manual operation and not the structural integrity or design of the gates themselves but concentrating on the generality of the effects that wind loading may have and to prepare guidance on contributory risk l For ease of calculation a number of assumptions are being made, area of the gates in question will be regarded as solid flat surfaces this will give an absolute maximum for wind pressure acting on the gate. Angular movement/acceleration will be regarded as non vector or torque for simplicity of calculation as wind direction is complex and variable therefor willbe calculated as perpendicular to thegate, again giving a maximum for wind loading. It will be assumed that the greatest area of danger for the operator is at the furthest from the hinge and refered to as the impact zone (IZ) . For the purpose of these calculations it is not necessary for a higher degree of accuracy however if a higher degree of accuracy is required this may be achieved by using the data and appropriate non linear formulas. The angle of wind direction relative to thegate willbe recorded for those that wish to make more accurate assessments. l As the most important factor will be that of wind pressure acting on the gates and not the capabilities of the opperators, it is intended to make direct measurements under a range of wind conditions and compare them to those taken under still air conditions this will give a direct comparison of increased loading on gates of different dimensions and construction under different environmentalconditions l Wind speed = m/s
  • 6. l Acceleration =m/s^2 l Mass = kg l Wind pressure = kg/m^2 = N/m^2 l Force, pushing or pulling required to control the gatein motion = kgf Fig 1 Fig 1 It would be tempting for managers not to consider wind as a significant hazard. For managers, RR526 Although "other environmentalfactors" have to be considered it is believed thatthisreport missed the significance of the effects of wind on high risk push pull operations being carried out
  • 7. Figure 2 Fig 2 . For the average person, carrying out the mathmatics prior to a manual handling operation (push pull) would be wholly unreasonable and like an Inspector "who do not typically pocess objective force measuring equipement " RR562 Executive Recommendations, et al, would be unrealistic
  • 8. Figure 3 Typical layout for identifying risk areas on gates Note that the forces required to operate the gate or frequency of use (push pull manual handling) handles and fittings are absent nor is wind identified as a significant factor. The 'weight' of the gate is supported by the hinges and load bearing style however the mass of the gate is independent of how the weight is supported.
  • 9. Fig 4a Guidance to the increase in force required to control the loading Figure 4a A suggested diagram of the extra force needed to carryout push pull opperations. where wind is a significant factor. For simplicity and ease of use this diagram uses the same 'traffic signal' format and should be used in conjunction with the load diagram Fig 1. The combination of wind pressure in N/m^2 and the bodily force in kgf to control the gate whilst in motion
  • 10. Fig 4b Fig 4b Wind force conversion Figure 5. Suggested data for inclusion
  • 11. Figure 5 Data collection Data collection Details of the gates, construction, dimensions and approximate mass.. Number of hinges and fittings Orientation I.e 270°-90° = East / West. 0° - 180° = North / South Wind speed and direction (from perpendicular to the gate) 0° = perpendicular . Defects Environmental conditions, day, night, rain, lighting etc.