Scheduling Performance Index
(SPI)
SPI =
EV
PV
Scheduling Performance Index
(SPI)
TABLE 13.3
Interpretation of SPI
0 0.5 1 1.5 2 2.5
SPI
CPI
Ahead of ScheduleBehind Schedule
On Schedule
Scheduling Performance Index
(CPI)
Activity A: Total PV = $24,000
SPI
Today
Activity A: PV BY TODAY= $16,000
Scheduling Performance Index
(CPI)
Activity A: Total PV = $24,000
SPI
Activity A: PV BY TODAY= $16,000
Today
Scheduling Performance Index
(CPI)
50%
Activity A: Total PV = $24,000
(CPI)SPI
Activity A: PV BY TODAY= $16,000
Today
Scheduling Performance Index
(CPI)
Activity A: Total PV = $24,000
50%
EV= $24,000* 50% = $12,000
SPI
EV $12,000
Activity A...
Scheduling Performance Index
SPI
$12,000
= = .75
0.75
$16,000
0 0.5 1 1.5 2 2.5
TABLE 13.3
Interpretation of SPI
0 0.5 1 1.5 2 2.5
SPI
CPI
Ahead of ScheduleBehind Schedule
On Schedule
0.75
TABLE 13.3
Interpretation of SPI
0 0.5 1 1.5 2 2.5
SPI
CPI
Project
0.75
Scheduling Performance Index
(CPI)
Activity A: Total PV = $24,000
SPI
Today
Activity A: PV BY TODAY= $16,000
Scheduling Performance Index
(CPI)
Activity A: Total PV = $24,000
SPI
Activity A: PV BY TODAY= $16,000
Today
Scheduling Performance Index
(CPI)
83.33%
Activity A: Total PV = $24,000
(CPI)SPI
Activity A: PV BY TODAY= $16,000
Today
Scheduling Performance Index
(CPI)
Activity A: Total PV = $24,000
EV= $24,000* 83.33% = ~$20,000
SPI
EV $20,000
Activity A...
0 0.5 1 1.5 2 2.5
1.25
Scheduling Performance Index
SPI= = 1.25
$16,000
$20,000
TABLE 13.3
Interpretation of SPI
0 0.5 1 1.5 2 2.5
SPI
CPI
Ahead of ScheduleBehind Schedule
On Schedule
1.25
TABLE 13.3
Interpretation of SPI
0 0.5 1 1.5 2 2.5
SPI
CPI
1.25
Project
TABLE 13.3
Interpretation of SPI
0 0.5 1 1.5 2 2.5
SPI
CPI
Ahead of ScheduleBehind Schedule
On Schedule
Be Careful When
Using Money to
Measure Time
Be Careful When
Using Money to
Measure Time
Activity A: Total PV = $24,000
EV= $24,000* 75.00% = ~$18,000EV $18,000
Activi...
TABLE 13.3
Interpretation of SPI
0 0.5 1 1.5 2 2.5
SPI
CPI
Ahead of ScheduleBehind Schedule
On Schedule
0.75
Be Careful When
Using Money to
Measure Time
Activity A: Total PV = $24,000
EV= $24,000* 100.00% = ~$24,000EV $24,000
Activ...
TABLE 13.3
Interpretation of SPI
0 0.5 1 1.5 2 2.5
SPI
CPI
Ahead of ScheduleBehind Schedule
On Schedule
1.00
Indexes to Monitor Progress
Prochain SlideShare
Chargement dans…5
×

Schedule Performance Index (SPI) in Project Management

824 vues

Publié le

How to calculate and interpret SPI as it is used in earned value analysis in project management. From Project Management Fundamentals, a new type of textbook designed to be: granular, easy to use with a "flipped" classroom approach, and designed for electronic distribution on iPads, kindle readers, and PCs/Mac. Find out more at http://pmf.education/

Publié dans : Ingénierie
  • Soyez le premier à commenter

  • Soyez le premier à aimer ceci

Schedule Performance Index (SPI) in Project Management

  1. 1. Scheduling Performance Index (SPI)
  2. 2. SPI = EV PV Scheduling Performance Index (SPI)
  3. 3. TABLE 13.3 Interpretation of SPI 0 0.5 1 1.5 2 2.5 SPI CPI Ahead of ScheduleBehind Schedule On Schedule
  4. 4. Scheduling Performance Index (CPI) Activity A: Total PV = $24,000 SPI Today Activity A: PV BY TODAY= $16,000
  5. 5. Scheduling Performance Index (CPI) Activity A: Total PV = $24,000 SPI Activity A: PV BY TODAY= $16,000 Today
  6. 6. Scheduling Performance Index (CPI) 50% Activity A: Total PV = $24,000 (CPI)SPI Activity A: PV BY TODAY= $16,000 Today
  7. 7. Scheduling Performance Index (CPI) Activity A: Total PV = $24,000 50% EV= $24,000* 50% = $12,000 SPI EV $12,000 Activity A: PV BY TODAY= $16,000 Today $16,000
  8. 8. Scheduling Performance Index SPI $12,000 = = .75 0.75 $16,000 0 0.5 1 1.5 2 2.5
  9. 9. TABLE 13.3 Interpretation of SPI 0 0.5 1 1.5 2 2.5 SPI CPI Ahead of ScheduleBehind Schedule On Schedule 0.75
  10. 10. TABLE 13.3 Interpretation of SPI 0 0.5 1 1.5 2 2.5 SPI CPI Project 0.75
  11. 11. Scheduling Performance Index (CPI) Activity A: Total PV = $24,000 SPI Today Activity A: PV BY TODAY= $16,000
  12. 12. Scheduling Performance Index (CPI) Activity A: Total PV = $24,000 SPI Activity A: PV BY TODAY= $16,000 Today
  13. 13. Scheduling Performance Index (CPI) 83.33% Activity A: Total PV = $24,000 (CPI)SPI Activity A: PV BY TODAY= $16,000 Today
  14. 14. Scheduling Performance Index (CPI) Activity A: Total PV = $24,000 EV= $24,000* 83.33% = ~$20,000 SPI EV $20,000 Activity A: PV BY TODAY= $16,000 Today $16,000 83.33%
  15. 15. 0 0.5 1 1.5 2 2.5 1.25 Scheduling Performance Index SPI= = 1.25 $16,000 $20,000
  16. 16. TABLE 13.3 Interpretation of SPI 0 0.5 1 1.5 2 2.5 SPI CPI Ahead of ScheduleBehind Schedule On Schedule 1.25
  17. 17. TABLE 13.3 Interpretation of SPI 0 0.5 1 1.5 2 2.5 SPI CPI 1.25 Project
  18. 18. TABLE 13.3 Interpretation of SPI 0 0.5 1 1.5 2 2.5 SPI CPI Ahead of ScheduleBehind Schedule On Schedule
  19. 19. Be Careful When Using Money to Measure Time
  20. 20. Be Careful When Using Money to Measure Time Activity A: Total PV = $24,000 EV= $24,000* 75.00% = ~$18,000EV $18,000 Activity A: PV BY TODAY= $24,000 LF= Jan 4, 2020 Interpretation of SPI Today June 5, 2021 EV 75.00% SPI = $24,000 $18,000 = 0.75 <-18 Months Late->
  21. 21. TABLE 13.3 Interpretation of SPI 0 0.5 1 1.5 2 2.5 SPI CPI Ahead of ScheduleBehind Schedule On Schedule 0.75
  22. 22. Be Careful When Using Money to Measure Time Activity A: Total PV = $24,000 EV= $24,000* 100.00% = ~$24,000EV $24,000 Activity A: PV BY TODAY= $24,000 LF= Jan 4, 2020 Interpretation of SPI Today June 5, 2021 EV 100.00% SPI = $24,000 $24,000 = 1.0 <-18 Months Late->
  23. 23. TABLE 13.3 Interpretation of SPI 0 0.5 1 1.5 2 2.5 SPI CPI Ahead of ScheduleBehind Schedule On Schedule 1.00
  24. 24. Indexes to Monitor Progress

×