Brief
• A lot of talk recently occurred about value engineering, its applications, and the success of
the global and local levels that applied in.
• Value engineering is not specialized engineered - as is the case in science Computer
Engineering or Electrical Engineering or Civil, but is a method and a structured
methodology to solve problems, whether administrative or engineering, or
manufacturing.
• The approach value engineering of the most
important and most programs that have been
implemented.
• Now in much of the country technologically
advanced method has value engineering is a
scientific method thoughtful became with
effectively by a lot of companies and institutions
global engineering and local communities.
Fundamentals of Value Engineering By Eng Karim Ragab
Brief
• And their success is due to it easier for product decision-making and help them to get the
greatest return material at the same time achieving the goals and tasks required, taking
into account access to jobs desired by the product, such as Beauty and the environment,
safety and flexibility and other important factors that meet or exceed the expectations of
the product and the customer.
• Where this method in the development of performance and productivity on the idea of
combining to achieve targeted production, whether through the construction of projects
or the provision of goods and services, and achieve cost savings without compromising
quality and basic functionality expected by customers and producers.
Fundamentals of Value Engineering By Eng Karim Ragab
Contents
• Introduction
• What is Value Engineering?
• Why & When to Apply Value Engineering ?
• Six Steps VE Plan
• Case Study : Using Concrete Bored Piles instead of Middle Barrettes in
Construction of General cargo Berth Project at Port.
• References.
Fundamentals of Value Engineering By Eng Karim Ragab
Value Engineering
Introduction
Introduction
• Value Management concentrates on the actual needs of the user to focus its resources. It
is different to cost-cutting exercises, which achieve economies by using less or cheaper
materials.
• The Value Management approach
involves the use of creative
techniques, combined with the
latest technical information on
materials and construction
methods.
Fundamentals of Value Engineering By Eng Karim Ragab
Introduction
• Value, in its broadest sense, is the benefit to the client offered by a project. Value means
ensuring that the right choices are made about obtaining maximum benefit for the client
within time, cost and quality constraints.
• Value Management is a process that gives all stakeholders in a proposed development the
opportunity to be involved in the decision-making process. It constitutes an examination of
all relevant options for the design and construction of the project, leading to a refinement of
the design brief and identification of any budget constraints.
• Value Management is a structured, systematic and analytical methodology that seeks to
achieve the essential functions of a project at the lowest total cost, consistent with required
levels of performance and quality.
• The underlying assumption to Value Management is that there are always many ways to
achieve any function, and that an examination of alternatives may produce a better-value
solution.
Fundamentals of Value Engineering By Eng Karim Ragab
Value Engineering
What is
Value Engineering?
What is Value Engineering?
• Value Management originated in the United States emerging resulted from components and
materials shortage in the manufacturing sector during World War Two. Mr. Lawrence Miles
(The Founder of Value Management, then known as Value Analysis) of The General Electric
Company was greatly responsible for the establishment of the technique in 1942 and since
then the technique is very much accepted in various industries.
• Presently United States Government and many other nations such as United Kingdom,
Japan, Korea, Australia, Saudi Arabia amongst others adopt Value Management technique to
be applied for their Capital work projects.
• If, for example, the buyer wants to get more item value, he/she needs to either increase the
item's functionality at the same time he/she is containing cost; or he/she needs to reduce
cost while holding or improving its functionality. Either way, the result is more value for the
customer .
Fundamentals of Value Engineering By Eng Karim Ragab
What is Value Engineering?
• Value Engineering (VE)
Is an intensive, interdisciplinary problem solving activity that focuses on improving the value of
the functions that are required to accomplish the goal, or objective of any product, process,
service, or organization.
• VALUE METHODOLOGY
“The systematic application of recognized techniques which identify the functions of the
product or service, establish the worth of those functions, and provide the necessary functions
to meet the required performance at the lowest overall cost.”
FUNCTION + Quality
VALUE = ‫ـــــــــــــــــــ‬
Cost
Fundamentals of Value Engineering By Eng Karim Ragab
What is Value Engineering?
Bone and Law (2000) identified ten mandatory characteristics of Value Management
practice:
1. It is visibly supported by senior management.
2. It generates a clear program of work.
3. It involves structured team-based workshops.
4. It employs a range of analytical tools.
5. It involves creative brainstorming.
6. It is led by a qualified value practitioner.
7. It follows a structured ‘Job Plan’.
8. It involves customers.
9. It involves suppliers.
10. It causes study terms to achieve sustained improvements.
Fundamentals of Value Engineering By Eng Karim Ragab
What is Value Engineering?
According to Dell I’sola, the relationship between Value, Function (Worth), Quality and
Cost can be symbolized as follows:-
FUNCTION + Quality
VALUE = ‫ـــــــــــــــــــ‬
Cost
Where:
• Function = The specific worth that a design/item must perform
• Quality = The owner’s or user’s needs, desires, and expectations
• Cost = The life cycle cost of the product/project.
• Value = The most cost effective way to reliably accomplish a function that will meet the
user needs, desires and expectations.
Fundamentals of Value Engineering By Eng Karim Ragab
What is Value Engineering?
Fundamentals of Value Engineering By Eng Karim Ragab
Value Engineering
Why & When to
Apply Value Engineering ?
Why & When to Apply Value Engineering ?
o Value Engineering is used to determine the best design alternatives for Projects.
o Value Engineering is used to reduce cost on existing Projects.
o Value Engineering is used to improve quality, increase reliability and availability, and
customer satisfaction.
o Value Engineering is also used to improve organizational performance.
o Value Engineering is used to improve schedule
o Value Engineering is used to reduce risk
o Value Engineering is a powerful tool used to identify problems and develop recommended
solutions.
Fundamentals of Value Engineering By Eng Karim Ragab
• Value Management studies can take place at any stage in the development of a project.
However it is acknowledged that there is the potential for greater return on investment if it
is used at the very clear stages illustrated in figure 3 and 4 below.
• As such Value Management should be performed as early as possible even before the
commitment of funds, approval of systems or design as to maximize results.
Why & When to Apply Value Engineering ?
Fundamentals of Value Engineering By Eng Karim Ragab
When to Apply Value Engineering ?
o The cost of making changes and remedial works will be greatly increased later in the
development stage.
Fundamentals of Value Engineering By Eng Karim Ragab
Value Engineering
Six Steps VE Plan
Six Steps VE Plan
• Clearly identify the problem(s) to be solved,
and gather information on the background,
functions and requirements of the project.
1- Information
Phase
• What must the project do?
• What are the functions ?
• and how are they related?
2- Functional
Analysis
• Brainstorm ideas on how to improve the
high cost, broken, or inadequately
performed key functions.
3- Creativity
Phase
Fundamentals of Value Engineering By Eng Karim Ragab
Six Steps VE Plan
• Screen ideas for acceptance, score
remaining ideas on a scale and group ideas
into categories. Develop design scenarios,
and selection criteria. Rate and rank ideas.
4-Evaluation
Phase
• Plan how to sell ideas to management,
identify key recommendations, plan
management presentation.
5-Development
Phase
• Give oral presentation to management, or
develop written report.
6-Reporting
Phase
Fundamentals of Value Engineering By Eng Karim Ragab
Six Steps VE Plan
1. Information Phase
 What do you need to know about the problem that you don’t know now?
o What facts are known?
o What are the requirements of the system?
o Are these facts, opinions, assumptions, or
prejudices?
 Where or how can information be obtained?
Fundamentals of Value Engineering By Eng Karim Ragab
Six Steps VE Plan
2. Functional Phase
 Functions -Describe what something does.
 Functions -Use active verb and measurable noun.
 FAST (Function Analysis System Technique) -A logic diagram to describe how a system
works.
o Examples:
Verb Noun
1) Plan Finishing Material
2) Magnify Living Room Area
3) Reduce Wall Thickness
4) Design Exposure
5) Minimize Defect
6) Design Finishing
Key Function :
Satisfy Tenant
SecondaryFunctions
Fundamentals of Value Engineering By Eng Karim Ragab
1) Design Unit Plan
2) Put Cavity Wall
3) Control Temperature
4) Minimize Exterior Surface
5) Execute Natural Ventilation
6) Maintain Cleanliness
7) Supply Air Conditioner
8) Keep View
9) Install Insulation
10) Control Humidity
Six Steps VE Plan
2. Functional Phase
Key Function :
Maintain Facility
SecondaryFunctions
Fundamentals of Value Engineering By Eng Karim Ragab
Six Steps VE Plan
2. Functional Phase
Verb Noun
1) Supply Pipeline Space
2) Design Ventilation Space
3) Provide Elec. Pipe Space
4) Add Sewage Space
Key Function :
Install equipment
SecondaryFunctions
Verb Noun
1) Arrange Wall
2) Collect Opinion
3) Install Art
Key Function :
Design Interior
SecondaryFunctions
Fundamentals of Value Engineering By Eng Karim Ragab
Six Steps VE Plan
3. Creativity Phase
 Creativity is the art of bringing something new into existence.
 It has the art of making, inventing, or producing something new and different.
“ You must blast before you can create. Blow apart the misconceptions, skeptics, and
naysayers. Blow-up the preconceived ideas and common theories of how things
should be done. Rather, focus on possibilities.”
J. R. Wixson -2004
“ Imagination is more important than knowledge, for
knowledge is limited, while imagination embraces the
entire world.”
Albert Einstein
Fundamentals of Value Engineering By Eng Karim Ragab
Six Steps VE Plan
3. Creativity Phase
“ When you always do what you have always done -you always get what you have
always gotten.”
Socrates
Fundamentals of Value Engineering By Eng Karim Ragab
Six Steps VE Plan
3. Creativity Phase
 IDEAS Vs. Solutions
o A solution requires justification & validation, and idea needs no justification.
o A solution is an end point, an idea is just the beginning.
o A solution is solid and self supporting, an idea is tender and must be built upon.
DON’T KILL IDEAS WITH ROADBLOCKS !!
Fundamentals of Value Engineering By Eng Karim Ragab
Six Steps VE Plan
3. Creativity Phase
 Information for Skeptics
"... after a few more flashes in the pan, we shall hear very little more of Edison or his
electric lamp. Every claim he makes has been tested and proved impracticable.“
[New York Times, January 16, 1880]
"Heavier-than-air flying machines are impossible.“
[Lord Kelvin, president, Royal Society, 1895]
"Airplanes are interesting toys but of no military value.“
[Marechal Ferdinand Foch, Professor of Strategy, Ecole Superieure de Guerre]
Fundamentals of Value Engineering By Eng Karim Ragab
Six Steps VE Plan
3. Creativity Phase
 Information for Skeptics
"I think there is a world market for maybe five computers.“
[Thomas Watson, chairman IBM, 1943]
"There is no reason anyone would want a computer in their home."
[Ken Olson, Chairman and founder Digital Equipment Corp., 1977]
"640K ought to be enough for anybody."
[Bill Gates, 1981]
Fundamentals of Value Engineering By Eng Karim Ragab
Six Steps VE Plan
3. Creativity Phase
 Counter Skepticism for Skeptics
“ Tilt-up Construction is an
innovative construction method
that will replace traditional
construction of low and mid rise
buildings in the Middle East
within few years.”
Fadi Elayache 2010
Fundamentals of Value Engineering By Eng Karim Ragab
Six Steps VE Plan
3. Creativity Phase
 Rules of Brainstorming
 Generate a large number of ideas -quantity, not quality.
 Free-wheeling is encouraged -Listen and improve on the ideas of others.
 Don’t criticize -No evaluation of ideas.
 Encourage everyone to participate.
 Record all ideas presented.
 Time to let ideas “incubate” should be allowed.
 Select an appropriate meeting place.
Fundamentals of Value Engineering By Eng Karim Ragab
Six Steps VE Plan
4. Evaluating Ideas
 GO -NO GO
 Scratch ideas that hold no interest.
 CHAMPION
 Who will speak for the ideas and support them?
 GFI (Gut Feel Index)
 Discuss pro/con and vote. GFI is team average.
 Combine ideas; add new ideas.
 Record all assumptions
Fundamentals of Value Engineering By Eng Karim Ragab
Six Steps VE Plan
4. Evaluating Ideas
1 = Acceptable
2 = Good
3 = Excellent
A- Performance Comparison
Fundamentals of Value Engineering By Eng Karim Ragab
Six Steps VE Plan
4. Evaluating Ideas
B- Cost Comparison Cost Saving of 4 million AED
Fundamentals of Value Engineering By Eng Karim Ragab
Six Steps VE Plan
5. Development Phase
o What is recommended?
o Who has to approve it?
o What is the implementation plan?
o Are mockups or prototypes required to verify final decisions?
o What are the cost, schedule, and deliverables?
o What needs to be done?
o Who should be assigned the action?
o Assign a team member.
o Assign a completion date for the action.
o When should the task be completed ?
o Plan regular team status meetings.
Fundamentals of Value Engineering By Eng Karim Ragab
Six Steps VE Plan
6. Reporting Phase
 Give oral presentation.
 Support it with written executive brief.
 Be clear, concise, and positive.
 Anticipate roadblocks
 Use good human relations.
Follow –up Activity
 Recognize the participants.
 Publicize the results.
 Audit the performance of the implemented actions.
 Close out the project.
Fundamentals of Value Engineering By Eng Karim Ragab
Value Engineering
Case Study
Using Concrete Bored Piles instead of Middle Barrettes
in Construction of General cargo Berth Project at Port.
Six Steps VE Plan
1. Information Phase
Project Overview
o Construction of General Cargo Berth (Quay Wall Construction), at Damietta Port .The
Main elements are:
o Construction of the main quay wall (diaphragm wall panels and Middle Barrette).
o Construction of the connection between main new quay wall and existing quays.
o Dredging in front of the quay wall, the dredging to be carried out in accordance with
profiles, levels slopes, tolerances shown in the drawings and specifications.
o Apron pavements.
o Supply and construction of the electrical room.
o Electrical Works: M Cables and Feeders, Distribution Boards, Lighting circuits outlets,
Lighting fixtures, Earthing System ...etc.
o Fire Fighting Works: Construct and supply valves box overall dimensions 800 x 2400mm
and accessories.
Fundamentals of Value Engineering By Eng Karim Ragab
Six Steps VE Plan
2. Functional Phase
Functions of the required structural element are to:
o be formed to depths of 30 m approx., through virtually different soil types and
through rock, and with great control over geometry and continuity.
o facilitate excavations below groundwater while eliminating dewatering.
o provide structural stiffness which reduces ground movements and adjacent
settlements during excavation.
o be load bearing transferring loads to the underlying layer be reinforced to allow
o incorporation of many structural configurations, accommodate connections to
structures.
o be easily adapted to both anchors and internal structural bracing systems.
Bear (Verb) Loads (Noun)
Fundamentals of Value Engineering By Eng Karim Ragab
Six Steps VE Plan
3. Creativity Phase
 Use Middle Barrette. or
 Use Concrete Bored Piles.
Fundamentals of Value Engineering By Eng Karim Ragab
Six Steps VE Plan
4. Evaluating Ideas
Criteria Barrette Piles
Formation through virtually different soil
types with control over geometry and
continuity.
3 3
Structural stiffness. 3 3
Load bearing : transferring loads to the
underlying layer
3 3
Incorporation of many structural
configurations, accommodate connections to
structures.
3 3
Adapted to anchors. 3 3
Total 15 15
1 = Acceptable
2 = Good
3 = Excellent
A- Performance Comparison
Fundamentals of Value Engineering By Eng Karim Ragab
Six Steps VE Plan
4. Evaluating Ideas
Differences between Barrette & Piles in this project
 Barrette needed for this Project 88 VS 131 Piles.
 Machine used for Barrette construction is Cutter PC 40
 Machine used for Piles construction is Drilling rig BG 30
 Barrette construction production rate is 1.5 Panel / Day (24 hr.)
 Piles construction production rate is 6 Pile / Day (24 hr.)
 Total working days needed for Barrette = 88 / 1.5 = 59 day
 Total working days needed for Piles = 131 / 6 = 22 day
Fundamentals of Value Engineering By Eng Karim Ragab
Six Steps VE Plan
4. Evaluating Ideas
Differences between Barrette & Piles in this project
 Barrette dimensions 1 x 1.5 x 30.40 m
 Piles dimensions 1 x 34.5 m
 Bentonite slurry used in both Barrette & Piles.
 RFT rebar & concrete used in construction of both Barrette & Piles.
 Guide walls are needed in construction Barrette only.
 The construction Company (In this project) need a subcontractor for construction
of the Barrette but could construct the Piles by itself.
Fundamentals of Value Engineering By Eng Karim Ragab
Six Steps VE Plan
4. Evaluating Ideas
Criteria Barrette Piles
Bentonite slurry 3,617,280 550,000
RFT rebar 2,298,450 3,317,280
Concrete (QB=3830.75 m3 , QP= 3705.98 m3) 1,500,000 2,223,588
Guide walls 1,180,000 0
Manpower rates (DB=59 Day, DP= 22 Day) 1,180,225 440,000
Subcontractors 0 0
Pile Dynamic Load Test 343,377 97,000
X-logging Test 334 Ea. 3,617,280 0
Total 10,684,332 6,627,868
B- Cost Comparison
Cost Saving of 4 million EGP
Fundamentals of Value Engineering By Eng Karim Ragab
Six Steps VE Plan
5. Development Phase
o It is recommended to replace the middle Barrette with concrete bored piles.
o Project, Technical, Financial ,project control managers need to approve this
alternative and submit the proposal to the owner and his consultant get their
approval .
o The schedule will reduce from 10,684,332 EGP to 6,627,868 EGP with reduction value
4,056,464 EGP with reduction percent 38 %
o The schedule will reduce from 59 day to 22 day with reduction percent 62.7 %
o Will need redesign of the Barrette to convert it to piles.
o Redesign phase should finish within 3 months.
Fundamentals of Value Engineering By Eng Karim Ragab
Six Steps VE Plan
6. Reporting Phase
 A meeting will hold after Redesign phase finish and its agenda will include :
1) Oral presentation.
2) Written executive brief.
Follow –up Activity
 Recognize the participants.
 Publicize the results.
 Audit the performance of the implemented actions.
 Close out the project.
Fundamentals of Value Engineering By Eng Karim Ragab
Value Engineering
References
References
• VALUE MANAGEMENT GUIDELINES, August 2005 (Department of Housing and Works
-Government of Western Australia)
• VALUE MANAGEMENT – THE WAY FORWARD Sr. Dr. Mohd Mazlan Che Mat, Institute
of Value Management Malaysia (IVMM)
• VALUE ANALYSIS, VALUE ENGINEERING, by Nick Rich, BSc MBA Matthias Holweg,
Dipl.- Wirtschaftsing.(FH) MSc Lean Enterprise Research Centre
Cardi f , U n i ted Kingdom
• Value Base Planning Using Value Engineering / Value Analysis / Value Management
By: Fred McAuley, Jr.
• VALUE ENGINEERING by Roger Knowles And Nigel Barr
Fundamentals of Value Engineering By Eng Karim Ragab
References
http://www.value-engineering.com/consulting.htm
http://www.wordiq.com/definition/Value_engineering
http://en.wikipedia.org/wiki/Value_engineering
http://www.nab.usace.army.mil/whatwedo/ValueEngineering.htm
http://www.lza.com/lza/vs/value_engineering1.html
http://www.vetoday.com/value-engineering.php
http://www.vecp.com/
http://www.whitehouse.gov/omb/circulars/a131/a131.html
Fundamentals of Value Engineering By Eng Karim Ragab
1 sur 49

Recommandé

Value engineering seminar presentation par
Value engineering seminar presentationValue engineering seminar presentation
Value engineering seminar presentationamrutrajbk
4.2K vues19 diapositives
Vave nttf- tech talk par
Vave nttf- tech talk Vave nttf- tech talk
Vave nttf- tech talk Nettur Technical Training Foundation
656 vues13 diapositives
What is VAVE par
What is VAVE What is VAVE
What is VAVE Reff Ren
280.6K vues38 diapositives
Value engineering par
Value engineeringValue engineering
Value engineeringArushi Chadha
4.4K vues20 diapositives
Value engineering Short Over view ppt par
Value engineering Short Over view pptValue engineering Short Over view ppt
Value engineering Short Over view pptMashfiq Albartross
10.7K vues28 diapositives
Value engineering and Analysis par
Value engineering and AnalysisValue engineering and Analysis
Value engineering and AnalysisChaitanya Chenna
3.4K vues22 diapositives

Contenu connexe

Tendances

Value analysis and Value Engineering par
Value analysis and Value EngineeringValue analysis and Value Engineering
Value analysis and Value EngineeringTushar Lohani
1.2K vues11 diapositives
Value Engineering And Value Analysis par
Value Engineering And Value AnalysisValue Engineering And Value Analysis
Value Engineering And Value Analysisthombremahesh
130.8K vues63 diapositives
A Study Report on Value Analysis and Value Engineering (VAVE) par
A Study Report on Value Analysis and Value Engineering (VAVE)A Study Report on Value Analysis and Value Engineering (VAVE)
A Study Report on Value Analysis and Value Engineering (VAVE)Avijeet Suryavanshi
2.7K vues80 diapositives
Value engineering pom par
Value engineering pomValue engineering pom
Value engineering pomVishal Naik
676 vues12 diapositives
VALUE ENGINEERING CONCEPT-A BRIEF IN CONSTRUCTION INDUSTRY par
VALUE ENGINEERING CONCEPT-A BRIEF IN CONSTRUCTION INDUSTRYVALUE ENGINEERING CONCEPT-A BRIEF IN CONSTRUCTION INDUSTRY
VALUE ENGINEERING CONCEPT-A BRIEF IN CONSTRUCTION INDUSTRYSJMIT,now NMAMIT NITTE
4.6K vues15 diapositives
Business Success Through VA/VE par
Business Success Through VA/VEBusiness Success Through VA/VE
Business Success Through VA/VEgojo67
1.9K vues15 diapositives

Tendances(20)

Value analysis and Value Engineering par Tushar Lohani
Value analysis and Value EngineeringValue analysis and Value Engineering
Value analysis and Value Engineering
Tushar Lohani1.2K vues
Value Engineering And Value Analysis par thombremahesh
Value Engineering And Value AnalysisValue Engineering And Value Analysis
Value Engineering And Value Analysis
thombremahesh130.8K vues
A Study Report on Value Analysis and Value Engineering (VAVE) par Avijeet Suryavanshi
A Study Report on Value Analysis and Value Engineering (VAVE)A Study Report on Value Analysis and Value Engineering (VAVE)
A Study Report on Value Analysis and Value Engineering (VAVE)
Value engineering pom par Vishal Naik
Value engineering pomValue engineering pom
Value engineering pom
Vishal Naik676 vues
Business Success Through VA/VE par gojo67
Business Success Through VA/VEBusiness Success Through VA/VE
Business Success Through VA/VE
gojo671.9K vues
Value Engineering and Value Analysis.pptx par virshit
Value Engineering and Value Analysis.pptxValue Engineering and Value Analysis.pptx
Value Engineering and Value Analysis.pptx
virshit404 vues
VALUE ANALYSIS,VALUE ENGINEERING, BUSINESS PROCESS REENGINEERING par T HARI KUMAR
VALUE ANALYSIS,VALUE ENGINEERING, BUSINESS PROCESS REENGINEERINGVALUE ANALYSIS,VALUE ENGINEERING, BUSINESS PROCESS REENGINEERING
VALUE ANALYSIS,VALUE ENGINEERING, BUSINESS PROCESS REENGINEERING
T HARI KUMAR5.1K vues
Value Analysis Value Engineering & Business Process Reengineering par T HARI KUMAR
Value Analysis Value Engineering  &  Business Process ReengineeringValue Analysis Value Engineering  &  Business Process Reengineering
Value Analysis Value Engineering & Business Process Reengineering
T HARI KUMAR6.3K vues
Value_Analysis_and_Value_Engineering, A_seminar_by_Mohan_Kumar_G par Mohan Kumar G
Value_Analysis_and_Value_Engineering, A_seminar_by_Mohan_Kumar_GValue_Analysis_and_Value_Engineering, A_seminar_by_Mohan_Kumar_G
Value_Analysis_and_Value_Engineering, A_seminar_by_Mohan_Kumar_G
Mohan Kumar G4.2K vues
Value engineering case study ppt par AnuragTewari2
Value engineering case study pptValue engineering case study ppt
Value engineering case study ppt
AnuragTewari215.2K vues
Value Engineering for Roads & Highways Project par ajmal4
Value Engineering for Roads & Highways ProjectValue Engineering for Roads & Highways Project
Value Engineering for Roads & Highways Project
ajmal412.7K vues
Value Analysis & Value Engineering par Himangi Thattey
Value Analysis & Value EngineeringValue Analysis & Value Engineering
Value Analysis & Value Engineering
Himangi Thattey8.7K vues
Concept of Value Engineering with Case Study par Aditya Deshpande
Concept of Value Engineering with Case StudyConcept of Value Engineering with Case Study
Concept of Value Engineering with Case Study
Aditya Deshpande783 vues

Similaire à Fundamentals of value engineering

Value engineering in residential house construction par
Value engineering in residential house constructionValue engineering in residential house construction
Value engineering in residential house constructionIAEME Publication
798 vues7 diapositives
VALUE ENGINEERING IN RESIDENTIAL HOUSE CONSTRUCTION par
VALUE ENGINEERING IN RESIDENTIAL HOUSE CONSTRUCTIONVALUE ENGINEERING IN RESIDENTIAL HOUSE CONSTRUCTION
VALUE ENGINEERING IN RESIDENTIAL HOUSE CONSTRUCTIONIAEME Publication
284 vues7 diapositives
Value engineering _2_ par
Value engineering _2_Value engineering _2_
Value engineering _2_Swetlina .
3.8K vues16 diapositives
4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt par
4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt4. PAE AcFn621Ch-4a Project Alaysis and Selection.ppt
4. PAE AcFn621Ch-4a Project Alaysis and Selection.pptProfDrAnbalaganChinn
6 vues42 diapositives
Introduction à l'agilité - Martin Goyette par
Introduction à l'agilité - Martin GoyetteIntroduction à l'agilité - Martin Goyette
Introduction à l'agilité - Martin GoyetteAgile Montréal
780 vues54 diapositives
VA-VE Presentation.pptx par
VA-VE Presentation.pptxVA-VE Presentation.pptx
VA-VE Presentation.pptxDevenJally1
127 vues84 diapositives

Similaire à Fundamentals of value engineering (20)

Value engineering in residential house construction par IAEME Publication
Value engineering in residential house constructionValue engineering in residential house construction
Value engineering in residential house construction
VALUE ENGINEERING IN RESIDENTIAL HOUSE CONSTRUCTION par IAEME Publication
VALUE ENGINEERING IN RESIDENTIAL HOUSE CONSTRUCTIONVALUE ENGINEERING IN RESIDENTIAL HOUSE CONSTRUCTION
VALUE ENGINEERING IN RESIDENTIAL HOUSE CONSTRUCTION
Value engineering _2_ par Swetlina .
Value engineering _2_Value engineering _2_
Value engineering _2_
Swetlina .3.8K vues
Introduction à l'agilité - Martin Goyette par Agile Montréal
Introduction à l'agilité - Martin GoyetteIntroduction à l'agilité - Martin Goyette
Introduction à l'agilité - Martin Goyette
Agile Montréal780 vues
VA-VE Presentation.pptx par DevenJally1
VA-VE Presentation.pptxVA-VE Presentation.pptx
VA-VE Presentation.pptx
DevenJally1127 vues
IRJET- Value Engineering-An Approach to Enhance Real Estate Industry par IRJET Journal
IRJET- Value Engineering-An Approach to Enhance Real Estate IndustryIRJET- Value Engineering-An Approach to Enhance Real Estate Industry
IRJET- Value Engineering-An Approach to Enhance Real Estate Industry
IRJET Journal33 vues
Application of-value-engineering-in-residential-building-ijertv9 is050725 par Minn Lwin
Application of-value-engineering-in-residential-building-ijertv9 is050725Application of-value-engineering-in-residential-building-ijertv9 is050725
Application of-value-engineering-in-residential-building-ijertv9 is050725
Minn Lwin14 vues
Application of Value Engineering in Construction Projects par nitinrane33
Application of Value Engineering in Construction ProjectsApplication of Value Engineering in Construction Projects
Application of Value Engineering in Construction Projects
nitinrane3349 vues
VM: CONCEPTS, TERMS, RISKS 7 COSTS par Hui May Lee
VM: CONCEPTS, TERMS, RISKS 7 COSTSVM: CONCEPTS, TERMS, RISKS 7 COSTS
VM: CONCEPTS, TERMS, RISKS 7 COSTS
Hui May Lee79 vues
Unit iii-Architecture in the lifecycle par Dhivyaa C.R
Unit iii-Architecture in the lifecycleUnit iii-Architecture in the lifecycle
Unit iii-Architecture in the lifecycle
Dhivyaa C.R232 vues
Value engineering significance par Yash Patel
Value engineering significanceValue engineering significance
Value engineering significance
Yash Patel109 vues
Enterprise Architecture & Project Portfolio Management 1/2 par Jean Gehring
Enterprise Architecture & Project Portfolio Management 1/2Enterprise Architecture & Project Portfolio Management 1/2
Enterprise Architecture & Project Portfolio Management 1/2
Jean Gehring6.2K vues
Project Management Essentials par QBI Institute
Project Management EssentialsProject Management Essentials
Project Management Essentials
QBI Institute648 vues
Application of Value Engineering in Commercial Building Projects par nitinrane33
Application of Value Engineering in  Commercial Building ProjectsApplication of Value Engineering in  Commercial Building Projects
Application of Value Engineering in Commercial Building Projects
nitinrane3316 vues
Introduction to value engineering and value analysis par Prathamesh Kadam
Introduction to value engineering and value analysisIntroduction to value engineering and value analysis
Introduction to value engineering and value analysis
Prathamesh Kadam5.2K vues

Plus de Karim Ragab

DCMA 14 Point Assessment by Karim Ragab.pdf par
DCMA 14 Point Assessment by Karim Ragab.pdfDCMA 14 Point Assessment by Karim Ragab.pdf
DCMA 14 Point Assessment by Karim Ragab.pdfKarim Ragab
121 vues30 diapositives
Project management using Primavera 6.x by Karim Ragab par
Project management using Primavera 6.x by Karim RagabProject management using Primavera 6.x by Karim Ragab
Project management using Primavera 6.x by Karim RagabKarim Ragab
355 vues242 diapositives
Microsoft project 2010 by Karim Ragab par
Microsoft project 2010 by Karim RagabMicrosoft project 2010 by Karim Ragab
Microsoft project 2010 by Karim RagabKarim Ragab
742 vues102 diapositives
Employee turnover and maximizing staff retention par
Employee turnover and maximizing staff retentionEmployee turnover and maximizing staff retention
Employee turnover and maximizing staff retentionKarim Ragab
3.2K vues30 diapositives
Workplace safety infection control par
Workplace safety   infection controlWorkplace safety   infection control
Workplace safety infection controlKarim Ragab
2.6K vues16 diapositives
Appreciation Letter for Total Plant shutdown March 2014 par
Appreciation Letter for Total Plant shutdown March 2014Appreciation Letter for Total Plant shutdown March 2014
Appreciation Letter for Total Plant shutdown March 2014Karim Ragab
1.9K vues1 diapositive

Plus de Karim Ragab(9)

DCMA 14 Point Assessment by Karim Ragab.pdf par Karim Ragab
DCMA 14 Point Assessment by Karim Ragab.pdfDCMA 14 Point Assessment by Karim Ragab.pdf
DCMA 14 Point Assessment by Karim Ragab.pdf
Karim Ragab121 vues
Project management using Primavera 6.x by Karim Ragab par Karim Ragab
Project management using Primavera 6.x by Karim RagabProject management using Primavera 6.x by Karim Ragab
Project management using Primavera 6.x by Karim Ragab
Karim Ragab355 vues
Microsoft project 2010 by Karim Ragab par Karim Ragab
Microsoft project 2010 by Karim RagabMicrosoft project 2010 by Karim Ragab
Microsoft project 2010 by Karim Ragab
Karim Ragab742 vues
Employee turnover and maximizing staff retention par Karim Ragab
Employee turnover and maximizing staff retentionEmployee turnover and maximizing staff retention
Employee turnover and maximizing staff retention
Karim Ragab3.2K vues
Workplace safety infection control par Karim Ragab
Workplace safety   infection controlWorkplace safety   infection control
Workplace safety infection control
Karim Ragab2.6K vues
Appreciation Letter for Total Plant shutdown March 2014 par Karim Ragab
Appreciation Letter for Total Plant shutdown March 2014Appreciation Letter for Total Plant shutdown March 2014
Appreciation Letter for Total Plant shutdown March 2014
Karim Ragab1.9K vues
عادات الأكل الصحية في رمضان par Karim Ragab
عادات الأكل الصحية في رمضانعادات الأكل الصحية في رمضان
عادات الأكل الصحية في رمضان
Karim Ragab1.2K vues

Dernier

Trust Metric-Based Anomaly Detection via Deep Deterministic Policy Gradient R... par
Trust Metric-Based Anomaly Detection via Deep Deterministic Policy Gradient R...Trust Metric-Based Anomaly Detection via Deep Deterministic Policy Gradient R...
Trust Metric-Based Anomaly Detection via Deep Deterministic Policy Gradient R...IJCNCJournal
5 vues25 diapositives
AWS Certified Solutions Architect Associate Exam Guide_published .pdf par
AWS Certified Solutions Architect Associate Exam Guide_published .pdfAWS Certified Solutions Architect Associate Exam Guide_published .pdf
AWS Certified Solutions Architect Associate Exam Guide_published .pdfKiran Kumar Malik
6 vues121 diapositives
MongoDB.pdf par
MongoDB.pdfMongoDB.pdf
MongoDB.pdfArthyR3
53 vues6 diapositives
MODULE-1 CHAPTER 3- Operators - Object Oriented Programming with JAVA par
MODULE-1 CHAPTER 3- Operators - Object Oriented Programming with JAVAMODULE-1 CHAPTER 3- Operators - Object Oriented Programming with JAVA
MODULE-1 CHAPTER 3- Operators - Object Oriented Programming with JAVADemian Antony D'Mello
8 vues14 diapositives
Global airborne satcom market report par
Global airborne satcom market reportGlobal airborne satcom market report
Global airborne satcom market reportdefencereport78
8 vues13 diapositives
CPM Schedule Float.pptx par
CPM Schedule Float.pptxCPM Schedule Float.pptx
CPM Schedule Float.pptxMathew Joseph
9 vues5 diapositives

Dernier(20)

Trust Metric-Based Anomaly Detection via Deep Deterministic Policy Gradient R... par IJCNCJournal
Trust Metric-Based Anomaly Detection via Deep Deterministic Policy Gradient R...Trust Metric-Based Anomaly Detection via Deep Deterministic Policy Gradient R...
Trust Metric-Based Anomaly Detection via Deep Deterministic Policy Gradient R...
IJCNCJournal5 vues
AWS Certified Solutions Architect Associate Exam Guide_published .pdf par Kiran Kumar Malik
AWS Certified Solutions Architect Associate Exam Guide_published .pdfAWS Certified Solutions Architect Associate Exam Guide_published .pdf
AWS Certified Solutions Architect Associate Exam Guide_published .pdf
MongoDB.pdf par ArthyR3
MongoDB.pdfMongoDB.pdf
MongoDB.pdf
ArthyR353 vues
MODULE-1 CHAPTER 3- Operators - Object Oriented Programming with JAVA par Demian Antony D'Mello
MODULE-1 CHAPTER 3- Operators - Object Oriented Programming with JAVAMODULE-1 CHAPTER 3- Operators - Object Oriented Programming with JAVA
MODULE-1 CHAPTER 3- Operators - Object Oriented Programming with JAVA
2023-12 Emarei MRI Tool Set E2I0501ST (TQ).pdf par Philipp Daum
2023-12 Emarei MRI Tool Set E2I0501ST (TQ).pdf2023-12 Emarei MRI Tool Set E2I0501ST (TQ).pdf
2023-12 Emarei MRI Tool Set E2I0501ST (TQ).pdf
Philipp Daum6 vues
Basic Design Flow for Field Programmable Gate Arrays par Usha Mehta
Basic Design Flow for Field Programmable Gate ArraysBasic Design Flow for Field Programmable Gate Arrays
Basic Design Flow for Field Programmable Gate Arrays
Usha Mehta24 vues
GDSC Mikroskil Members Onboarding 2023.pdf par gdscmikroskil
GDSC Mikroskil Members Onboarding 2023.pdfGDSC Mikroskil Members Onboarding 2023.pdf
GDSC Mikroskil Members Onboarding 2023.pdf
gdscmikroskil75 vues
Different type of computer networks .pptx par nazmul1514788
Different  type of computer networks .pptxDifferent  type of computer networks .pptx
Different type of computer networks .pptx
nazmul151478820 vues
REACTJS.pdf par ArthyR3
REACTJS.pdfREACTJS.pdf
REACTJS.pdf
ArthyR339 vues
Programmable Logic Devices : SPLD and CPLD par Usha Mehta
Programmable Logic Devices : SPLD and CPLDProgrammable Logic Devices : SPLD and CPLD
Programmable Logic Devices : SPLD and CPLD
Usha Mehta44 vues
Programmable Switches for Programmable Logic Devices par Usha Mehta
Programmable Switches for Programmable Logic DevicesProgrammable Switches for Programmable Logic Devices
Programmable Switches for Programmable Logic Devices
Usha Mehta37 vues
Ansari: Practical experiences with an LLM-based Islamic Assistant par M Waleed Kadous
Ansari: Practical experiences with an LLM-based Islamic AssistantAnsari: Practical experiences with an LLM-based Islamic Assistant
Ansari: Practical experiences with an LLM-based Islamic Assistant
M Waleed Kadous13 vues

Fundamentals of value engineering

  • 1. Fundamentals of Value Engineering By Eng Karim Ragab Planning and Project Controls Engineer E-mail: Karimrgb@hotmail.com Mob.:0100 83 83 103
  • 2. Brief • A lot of talk recently occurred about value engineering, its applications, and the success of the global and local levels that applied in. • Value engineering is not specialized engineered - as is the case in science Computer Engineering or Electrical Engineering or Civil, but is a method and a structured methodology to solve problems, whether administrative or engineering, or manufacturing. • The approach value engineering of the most important and most programs that have been implemented. • Now in much of the country technologically advanced method has value engineering is a scientific method thoughtful became with effectively by a lot of companies and institutions global engineering and local communities. Fundamentals of Value Engineering By Eng Karim Ragab
  • 3. Brief • And their success is due to it easier for product decision-making and help them to get the greatest return material at the same time achieving the goals and tasks required, taking into account access to jobs desired by the product, such as Beauty and the environment, safety and flexibility and other important factors that meet or exceed the expectations of the product and the customer. • Where this method in the development of performance and productivity on the idea of combining to achieve targeted production, whether through the construction of projects or the provision of goods and services, and achieve cost savings without compromising quality and basic functionality expected by customers and producers. Fundamentals of Value Engineering By Eng Karim Ragab
  • 4. Contents • Introduction • What is Value Engineering? • Why & When to Apply Value Engineering ? • Six Steps VE Plan • Case Study : Using Concrete Bored Piles instead of Middle Barrettes in Construction of General cargo Berth Project at Port. • References. Fundamentals of Value Engineering By Eng Karim Ragab
  • 6. Introduction • Value Management concentrates on the actual needs of the user to focus its resources. It is different to cost-cutting exercises, which achieve economies by using less or cheaper materials. • The Value Management approach involves the use of creative techniques, combined with the latest technical information on materials and construction methods. Fundamentals of Value Engineering By Eng Karim Ragab
  • 7. Introduction • Value, in its broadest sense, is the benefit to the client offered by a project. Value means ensuring that the right choices are made about obtaining maximum benefit for the client within time, cost and quality constraints. • Value Management is a process that gives all stakeholders in a proposed development the opportunity to be involved in the decision-making process. It constitutes an examination of all relevant options for the design and construction of the project, leading to a refinement of the design brief and identification of any budget constraints. • Value Management is a structured, systematic and analytical methodology that seeks to achieve the essential functions of a project at the lowest total cost, consistent with required levels of performance and quality. • The underlying assumption to Value Management is that there are always many ways to achieve any function, and that an examination of alternatives may produce a better-value solution. Fundamentals of Value Engineering By Eng Karim Ragab
  • 9. What is Value Engineering? • Value Management originated in the United States emerging resulted from components and materials shortage in the manufacturing sector during World War Two. Mr. Lawrence Miles (The Founder of Value Management, then known as Value Analysis) of The General Electric Company was greatly responsible for the establishment of the technique in 1942 and since then the technique is very much accepted in various industries. • Presently United States Government and many other nations such as United Kingdom, Japan, Korea, Australia, Saudi Arabia amongst others adopt Value Management technique to be applied for their Capital work projects. • If, for example, the buyer wants to get more item value, he/she needs to either increase the item's functionality at the same time he/she is containing cost; or he/she needs to reduce cost while holding or improving its functionality. Either way, the result is more value for the customer . Fundamentals of Value Engineering By Eng Karim Ragab
  • 10. What is Value Engineering? • Value Engineering (VE) Is an intensive, interdisciplinary problem solving activity that focuses on improving the value of the functions that are required to accomplish the goal, or objective of any product, process, service, or organization. • VALUE METHODOLOGY “The systematic application of recognized techniques which identify the functions of the product or service, establish the worth of those functions, and provide the necessary functions to meet the required performance at the lowest overall cost.” FUNCTION + Quality VALUE = ‫ـــــــــــــــــــ‬ Cost Fundamentals of Value Engineering By Eng Karim Ragab
  • 11. What is Value Engineering? Bone and Law (2000) identified ten mandatory characteristics of Value Management practice: 1. It is visibly supported by senior management. 2. It generates a clear program of work. 3. It involves structured team-based workshops. 4. It employs a range of analytical tools. 5. It involves creative brainstorming. 6. It is led by a qualified value practitioner. 7. It follows a structured ‘Job Plan’. 8. It involves customers. 9. It involves suppliers. 10. It causes study terms to achieve sustained improvements. Fundamentals of Value Engineering By Eng Karim Ragab
  • 12. What is Value Engineering? According to Dell I’sola, the relationship between Value, Function (Worth), Quality and Cost can be symbolized as follows:- FUNCTION + Quality VALUE = ‫ـــــــــــــــــــ‬ Cost Where: • Function = The specific worth that a design/item must perform • Quality = The owner’s or user’s needs, desires, and expectations • Cost = The life cycle cost of the product/project. • Value = The most cost effective way to reliably accomplish a function that will meet the user needs, desires and expectations. Fundamentals of Value Engineering By Eng Karim Ragab
  • 13. What is Value Engineering? Fundamentals of Value Engineering By Eng Karim Ragab
  • 14. Value Engineering Why & When to Apply Value Engineering ?
  • 15. Why & When to Apply Value Engineering ? o Value Engineering is used to determine the best design alternatives for Projects. o Value Engineering is used to reduce cost on existing Projects. o Value Engineering is used to improve quality, increase reliability and availability, and customer satisfaction. o Value Engineering is also used to improve organizational performance. o Value Engineering is used to improve schedule o Value Engineering is used to reduce risk o Value Engineering is a powerful tool used to identify problems and develop recommended solutions. Fundamentals of Value Engineering By Eng Karim Ragab
  • 16. • Value Management studies can take place at any stage in the development of a project. However it is acknowledged that there is the potential for greater return on investment if it is used at the very clear stages illustrated in figure 3 and 4 below. • As such Value Management should be performed as early as possible even before the commitment of funds, approval of systems or design as to maximize results. Why & When to Apply Value Engineering ? Fundamentals of Value Engineering By Eng Karim Ragab
  • 17. When to Apply Value Engineering ? o The cost of making changes and remedial works will be greatly increased later in the development stage. Fundamentals of Value Engineering By Eng Karim Ragab
  • 19. Six Steps VE Plan • Clearly identify the problem(s) to be solved, and gather information on the background, functions and requirements of the project. 1- Information Phase • What must the project do? • What are the functions ? • and how are they related? 2- Functional Analysis • Brainstorm ideas on how to improve the high cost, broken, or inadequately performed key functions. 3- Creativity Phase Fundamentals of Value Engineering By Eng Karim Ragab
  • 20. Six Steps VE Plan • Screen ideas for acceptance, score remaining ideas on a scale and group ideas into categories. Develop design scenarios, and selection criteria. Rate and rank ideas. 4-Evaluation Phase • Plan how to sell ideas to management, identify key recommendations, plan management presentation. 5-Development Phase • Give oral presentation to management, or develop written report. 6-Reporting Phase Fundamentals of Value Engineering By Eng Karim Ragab
  • 21. Six Steps VE Plan 1. Information Phase  What do you need to know about the problem that you don’t know now? o What facts are known? o What are the requirements of the system? o Are these facts, opinions, assumptions, or prejudices?  Where or how can information be obtained? Fundamentals of Value Engineering By Eng Karim Ragab
  • 22. Six Steps VE Plan 2. Functional Phase  Functions -Describe what something does.  Functions -Use active verb and measurable noun.  FAST (Function Analysis System Technique) -A logic diagram to describe how a system works. o Examples: Verb Noun 1) Plan Finishing Material 2) Magnify Living Room Area 3) Reduce Wall Thickness 4) Design Exposure 5) Minimize Defect 6) Design Finishing Key Function : Satisfy Tenant SecondaryFunctions Fundamentals of Value Engineering By Eng Karim Ragab
  • 23. 1) Design Unit Plan 2) Put Cavity Wall 3) Control Temperature 4) Minimize Exterior Surface 5) Execute Natural Ventilation 6) Maintain Cleanliness 7) Supply Air Conditioner 8) Keep View 9) Install Insulation 10) Control Humidity Six Steps VE Plan 2. Functional Phase Key Function : Maintain Facility SecondaryFunctions Fundamentals of Value Engineering By Eng Karim Ragab
  • 24. Six Steps VE Plan 2. Functional Phase Verb Noun 1) Supply Pipeline Space 2) Design Ventilation Space 3) Provide Elec. Pipe Space 4) Add Sewage Space Key Function : Install equipment SecondaryFunctions Verb Noun 1) Arrange Wall 2) Collect Opinion 3) Install Art Key Function : Design Interior SecondaryFunctions Fundamentals of Value Engineering By Eng Karim Ragab
  • 25. Six Steps VE Plan 3. Creativity Phase  Creativity is the art of bringing something new into existence.  It has the art of making, inventing, or producing something new and different. “ You must blast before you can create. Blow apart the misconceptions, skeptics, and naysayers. Blow-up the preconceived ideas and common theories of how things should be done. Rather, focus on possibilities.” J. R. Wixson -2004 “ Imagination is more important than knowledge, for knowledge is limited, while imagination embraces the entire world.” Albert Einstein Fundamentals of Value Engineering By Eng Karim Ragab
  • 26. Six Steps VE Plan 3. Creativity Phase “ When you always do what you have always done -you always get what you have always gotten.” Socrates Fundamentals of Value Engineering By Eng Karim Ragab
  • 27. Six Steps VE Plan 3. Creativity Phase  IDEAS Vs. Solutions o A solution requires justification & validation, and idea needs no justification. o A solution is an end point, an idea is just the beginning. o A solution is solid and self supporting, an idea is tender and must be built upon. DON’T KILL IDEAS WITH ROADBLOCKS !! Fundamentals of Value Engineering By Eng Karim Ragab
  • 28. Six Steps VE Plan 3. Creativity Phase  Information for Skeptics "... after a few more flashes in the pan, we shall hear very little more of Edison or his electric lamp. Every claim he makes has been tested and proved impracticable.“ [New York Times, January 16, 1880] "Heavier-than-air flying machines are impossible.“ [Lord Kelvin, president, Royal Society, 1895] "Airplanes are interesting toys but of no military value.“ [Marechal Ferdinand Foch, Professor of Strategy, Ecole Superieure de Guerre] Fundamentals of Value Engineering By Eng Karim Ragab
  • 29. Six Steps VE Plan 3. Creativity Phase  Information for Skeptics "I think there is a world market for maybe five computers.“ [Thomas Watson, chairman IBM, 1943] "There is no reason anyone would want a computer in their home." [Ken Olson, Chairman and founder Digital Equipment Corp., 1977] "640K ought to be enough for anybody." [Bill Gates, 1981] Fundamentals of Value Engineering By Eng Karim Ragab
  • 30. Six Steps VE Plan 3. Creativity Phase  Counter Skepticism for Skeptics “ Tilt-up Construction is an innovative construction method that will replace traditional construction of low and mid rise buildings in the Middle East within few years.” Fadi Elayache 2010 Fundamentals of Value Engineering By Eng Karim Ragab
  • 31. Six Steps VE Plan 3. Creativity Phase  Rules of Brainstorming  Generate a large number of ideas -quantity, not quality.  Free-wheeling is encouraged -Listen and improve on the ideas of others.  Don’t criticize -No evaluation of ideas.  Encourage everyone to participate.  Record all ideas presented.  Time to let ideas “incubate” should be allowed.  Select an appropriate meeting place. Fundamentals of Value Engineering By Eng Karim Ragab
  • 32. Six Steps VE Plan 4. Evaluating Ideas  GO -NO GO  Scratch ideas that hold no interest.  CHAMPION  Who will speak for the ideas and support them?  GFI (Gut Feel Index)  Discuss pro/con and vote. GFI is team average.  Combine ideas; add new ideas.  Record all assumptions Fundamentals of Value Engineering By Eng Karim Ragab
  • 33. Six Steps VE Plan 4. Evaluating Ideas 1 = Acceptable 2 = Good 3 = Excellent A- Performance Comparison Fundamentals of Value Engineering By Eng Karim Ragab
  • 34. Six Steps VE Plan 4. Evaluating Ideas B- Cost Comparison Cost Saving of 4 million AED Fundamentals of Value Engineering By Eng Karim Ragab
  • 35. Six Steps VE Plan 5. Development Phase o What is recommended? o Who has to approve it? o What is the implementation plan? o Are mockups or prototypes required to verify final decisions? o What are the cost, schedule, and deliverables? o What needs to be done? o Who should be assigned the action? o Assign a team member. o Assign a completion date for the action. o When should the task be completed ? o Plan regular team status meetings. Fundamentals of Value Engineering By Eng Karim Ragab
  • 36. Six Steps VE Plan 6. Reporting Phase  Give oral presentation.  Support it with written executive brief.  Be clear, concise, and positive.  Anticipate roadblocks  Use good human relations. Follow –up Activity  Recognize the participants.  Publicize the results.  Audit the performance of the implemented actions.  Close out the project. Fundamentals of Value Engineering By Eng Karim Ragab
  • 37. Value Engineering Case Study Using Concrete Bored Piles instead of Middle Barrettes in Construction of General cargo Berth Project at Port.
  • 38. Six Steps VE Plan 1. Information Phase Project Overview o Construction of General Cargo Berth (Quay Wall Construction), at Damietta Port .The Main elements are: o Construction of the main quay wall (diaphragm wall panels and Middle Barrette). o Construction of the connection between main new quay wall and existing quays. o Dredging in front of the quay wall, the dredging to be carried out in accordance with profiles, levels slopes, tolerances shown in the drawings and specifications. o Apron pavements. o Supply and construction of the electrical room. o Electrical Works: M Cables and Feeders, Distribution Boards, Lighting circuits outlets, Lighting fixtures, Earthing System ...etc. o Fire Fighting Works: Construct and supply valves box overall dimensions 800 x 2400mm and accessories. Fundamentals of Value Engineering By Eng Karim Ragab
  • 39. Six Steps VE Plan 2. Functional Phase Functions of the required structural element are to: o be formed to depths of 30 m approx., through virtually different soil types and through rock, and with great control over geometry and continuity. o facilitate excavations below groundwater while eliminating dewatering. o provide structural stiffness which reduces ground movements and adjacent settlements during excavation. o be load bearing transferring loads to the underlying layer be reinforced to allow o incorporation of many structural configurations, accommodate connections to structures. o be easily adapted to both anchors and internal structural bracing systems. Bear (Verb) Loads (Noun) Fundamentals of Value Engineering By Eng Karim Ragab
  • 40. Six Steps VE Plan 3. Creativity Phase  Use Middle Barrette. or  Use Concrete Bored Piles. Fundamentals of Value Engineering By Eng Karim Ragab
  • 41. Six Steps VE Plan 4. Evaluating Ideas Criteria Barrette Piles Formation through virtually different soil types with control over geometry and continuity. 3 3 Structural stiffness. 3 3 Load bearing : transferring loads to the underlying layer 3 3 Incorporation of many structural configurations, accommodate connections to structures. 3 3 Adapted to anchors. 3 3 Total 15 15 1 = Acceptable 2 = Good 3 = Excellent A- Performance Comparison Fundamentals of Value Engineering By Eng Karim Ragab
  • 42. Six Steps VE Plan 4. Evaluating Ideas Differences between Barrette & Piles in this project  Barrette needed for this Project 88 VS 131 Piles.  Machine used for Barrette construction is Cutter PC 40  Machine used for Piles construction is Drilling rig BG 30  Barrette construction production rate is 1.5 Panel / Day (24 hr.)  Piles construction production rate is 6 Pile / Day (24 hr.)  Total working days needed for Barrette = 88 / 1.5 = 59 day  Total working days needed for Piles = 131 / 6 = 22 day Fundamentals of Value Engineering By Eng Karim Ragab
  • 43. Six Steps VE Plan 4. Evaluating Ideas Differences between Barrette & Piles in this project  Barrette dimensions 1 x 1.5 x 30.40 m  Piles dimensions 1 x 34.5 m  Bentonite slurry used in both Barrette & Piles.  RFT rebar & concrete used in construction of both Barrette & Piles.  Guide walls are needed in construction Barrette only.  The construction Company (In this project) need a subcontractor for construction of the Barrette but could construct the Piles by itself. Fundamentals of Value Engineering By Eng Karim Ragab
  • 44. Six Steps VE Plan 4. Evaluating Ideas Criteria Barrette Piles Bentonite slurry 3,617,280 550,000 RFT rebar 2,298,450 3,317,280 Concrete (QB=3830.75 m3 , QP= 3705.98 m3) 1,500,000 2,223,588 Guide walls 1,180,000 0 Manpower rates (DB=59 Day, DP= 22 Day) 1,180,225 440,000 Subcontractors 0 0 Pile Dynamic Load Test 343,377 97,000 X-logging Test 334 Ea. 3,617,280 0 Total 10,684,332 6,627,868 B- Cost Comparison Cost Saving of 4 million EGP Fundamentals of Value Engineering By Eng Karim Ragab
  • 45. Six Steps VE Plan 5. Development Phase o It is recommended to replace the middle Barrette with concrete bored piles. o Project, Technical, Financial ,project control managers need to approve this alternative and submit the proposal to the owner and his consultant get their approval . o The schedule will reduce from 10,684,332 EGP to 6,627,868 EGP with reduction value 4,056,464 EGP with reduction percent 38 % o The schedule will reduce from 59 day to 22 day with reduction percent 62.7 % o Will need redesign of the Barrette to convert it to piles. o Redesign phase should finish within 3 months. Fundamentals of Value Engineering By Eng Karim Ragab
  • 46. Six Steps VE Plan 6. Reporting Phase  A meeting will hold after Redesign phase finish and its agenda will include : 1) Oral presentation. 2) Written executive brief. Follow –up Activity  Recognize the participants.  Publicize the results.  Audit the performance of the implemented actions.  Close out the project. Fundamentals of Value Engineering By Eng Karim Ragab
  • 48. References • VALUE MANAGEMENT GUIDELINES, August 2005 (Department of Housing and Works -Government of Western Australia) • VALUE MANAGEMENT – THE WAY FORWARD Sr. Dr. Mohd Mazlan Che Mat, Institute of Value Management Malaysia (IVMM) • VALUE ANALYSIS, VALUE ENGINEERING, by Nick Rich, BSc MBA Matthias Holweg, Dipl.- Wirtschaftsing.(FH) MSc Lean Enterprise Research Centre Cardi f , U n i ted Kingdom • Value Base Planning Using Value Engineering / Value Analysis / Value Management By: Fred McAuley, Jr. • VALUE ENGINEERING by Roger Knowles And Nigel Barr Fundamentals of Value Engineering By Eng Karim Ragab