1- Half way through the executing processes of your
project, a team member alerts you to a potential cost
overrun for a specific deliverable. What do you do first?
A ) Determine the projected actual cost.
B ) Implement a change control process to track the
change
C ) Inform the customer.
D ) Determine the cause of the overage
2- Which of the following represents the value of
work we have actually completed?
A ) Earned value
B ) Planned value
C ) Actual cost
D ) Estimate to complete
3- While completing your project, you realized that you
need to decrease the project costs. After researching
your options, you came up with the following choices.
Which choice would DECREASE project costs?
A ) Change to component A from component B. component A
costs more to purchase, but has a lower life cycle cost than B.
B ) Change activity A to be completed by resource B instead of
resource c. resource B is more experienced worker.
C ) Move activities B and H to occur concurrently, and accept a
30 percent increase in the risk that five more resources will be
needed later.
D ) Remove a test from the project management plan.
4- If earned value (EV) is U.S.$300000, actual
cost (AC) is U.S.$350000, and planned value (PV)
is U.S. $375000, what does the schedule
performance index (SPI) indicate?
A ) You are progressing at 86% of the rate originally
planned.
B ) You are progressing at 125% of the rate originally
planned.
C ) You are progressing at 116% of the rate originally
planned.
D ) You are progressing at 80% of the rate originally
planned.
5- The formula, EAC = BAC/CPI, assumes that:
A ) All subsequent work will be completed at the planned
expenditures.
B ) All subsequent work will be completed at the planned
expenditures, excluding the work packages currently
under way
C ) All subsequent work will be completed based upon the
cost performance to-date
D ) The cost performance cannot change during the project
6- What tool must project managers rely upon
to accurately identify the costs associated with
the project?
A ) A bill of materials
B ) A Gantt chart
C ) A precedence diagram network
D ) A work breakdown structure
7- If the Earned Value is equal to Actual Cost, it
means:
A-Project is on budget and on schedule
B-Schedule Variance Index is 1
C-There is no schedule variance
D-There is no cost variance
8-Suppose you have a budgeted cost of a project at
$900,000. The project is to be completed in 9 months.
After a month, you have completed 10% of the project
at a total expense of $100,000. The planned
completion should have been 15%. At the current
progress rate, how much more money is required to
complete the project?
A) $ 800,000
B) $ 900,000
C) $ 1,000,000
D) $ 1,100,000

More Related Content

What's hot

Calculating ETC In 4 Different Scenarios
Calculating ETC In 4 Different ScenariosCalculating ETC In 4 Different Scenarios
Calculating ETC In 4 Different ScenariosPraveen Malik, PMP
 
Calculating Estimate At Completion (EAC) Using 5 Different Formulas
Calculating Estimate At Completion (EAC) Using 5 Different FormulasCalculating Estimate At Completion (EAC) Using 5 Different Formulas
Calculating Estimate At Completion (EAC) Using 5 Different FormulasPraveen Malik, PMP
 
Learn The Right Way To Apply TCPI Formulas In Project Management
Learn The Right Way To Apply TCPI Formulas In Project ManagementLearn The Right Way To Apply TCPI Formulas In Project Management
Learn The Right Way To Apply TCPI Formulas In Project ManagementPraveen Malik, PMP
 
Earned value management
Earned value managementEarned value management
Earned value managementwhizkris
 
Earned value analysis
Earned value analysisEarned value analysis
Earned value analysisNikhil Raj
 
101 - A Beginner's Guide To Earned Value Management
101 - A Beginner's Guide To Earned Value Management 101 - A Beginner's Guide To Earned Value Management
101 - A Beginner's Guide To Earned Value Management Praveen Malik, PMP
 
Long Range Mine Planning Using Mathematical Programming
Long Range Mine Planning Using Mathematical ProgrammingLong Range Mine Planning Using Mathematical Programming
Long Range Mine Planning Using Mathematical ProgrammingTerry Jackson
 
E2E - ERP integrated planning for Pay costs
E2E - ERP integrated planning for Pay costsE2E - ERP integrated planning for Pay costs
E2E - ERP integrated planning for Pay costsAnatoly Ryabukha
 
PPP05 - Creating Preventive Maintenance Schedules (MCU)
PPP05 - Creating Preventive Maintenance Schedules (MCU)PPP05 - Creating Preventive Maintenance Schedules (MCU)
PPP05 - Creating Preventive Maintenance Schedules (MCU)Maintenance Connection
 
10 20150105 South-Sudan TopSheet for CON Calculation plus Contingencies Tende...
10 20150105 South-Sudan TopSheet for CON Calculation plus Contingencies Tende...10 20150105 South-Sudan TopSheet for CON Calculation plus Contingencies Tende...
10 20150105 South-Sudan TopSheet for CON Calculation plus Contingencies Tende...Helmut F Giesa HFG2404@gmail.com
 
SSRS BI Project
SSRS BI ProjectSSRS BI Project
SSRS BI Projectpencarver
 
AOTB Accounting for Agile
AOTB Accounting for AgileAOTB Accounting for Agile
AOTB Accounting for AgileBrett Ansley
 
Wind energy Project Strategy revised
Wind energy Project Strategy revisedWind energy Project Strategy revised
Wind energy Project Strategy revisedleif2016
 
Lecture 06 project_cost_management
Lecture 06 project_cost_managementLecture 06 project_cost_management
Lecture 06 project_cost_managementSayed Ahmed
 
A Comprehensive Beginners Guide To Cost Planning
A Comprehensive Beginners Guide To Cost PlanningA Comprehensive Beginners Guide To Cost Planning
A Comprehensive Beginners Guide To Cost PlanningPraveen Malik, PMP
 

What's hot (19)

Calculating ETC In 4 Different Scenarios
Calculating ETC In 4 Different ScenariosCalculating ETC In 4 Different Scenarios
Calculating ETC In 4 Different Scenarios
 
Calculating Estimate At Completion (EAC) Using 5 Different Formulas
Calculating Estimate At Completion (EAC) Using 5 Different FormulasCalculating Estimate At Completion (EAC) Using 5 Different Formulas
Calculating Estimate At Completion (EAC) Using 5 Different Formulas
 
Learn The Right Way To Apply TCPI Formulas In Project Management
Learn The Right Way To Apply TCPI Formulas In Project ManagementLearn The Right Way To Apply TCPI Formulas In Project Management
Learn The Right Way To Apply TCPI Formulas In Project Management
 
Earned value management
Earned value managementEarned value management
Earned value management
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSISPROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
 
Ppsi pertemuan-3
Ppsi pertemuan-3Ppsi pertemuan-3
Ppsi pertemuan-3
 
Earned value analysis
Earned value analysisEarned value analysis
Earned value analysis
 
101 - A Beginner's Guide To Earned Value Management
101 - A Beginner's Guide To Earned Value Management 101 - A Beginner's Guide To Earned Value Management
101 - A Beginner's Guide To Earned Value Management
 
CAPM study session 4
CAPM study session 4CAPM study session 4
CAPM study session 4
 
Long Range Mine Planning Using Mathematical Programming
Long Range Mine Planning Using Mathematical ProgrammingLong Range Mine Planning Using Mathematical Programming
Long Range Mine Planning Using Mathematical Programming
 
E2E - ERP integrated planning for Pay costs
E2E - ERP integrated planning for Pay costsE2E - ERP integrated planning for Pay costs
E2E - ERP integrated planning for Pay costs
 
PPP05 - Creating Preventive Maintenance Schedules (MCU)
PPP05 - Creating Preventive Maintenance Schedules (MCU)PPP05 - Creating Preventive Maintenance Schedules (MCU)
PPP05 - Creating Preventive Maintenance Schedules (MCU)
 
10 20150105 South-Sudan TopSheet for CON Calculation plus Contingencies Tende...
10 20150105 South-Sudan TopSheet for CON Calculation plus Contingencies Tende...10 20150105 South-Sudan TopSheet for CON Calculation plus Contingencies Tende...
10 20150105 South-Sudan TopSheet for CON Calculation plus Contingencies Tende...
 
SSRS BI Project
SSRS BI ProjectSSRS BI Project
SSRS BI Project
 
AOTB Accounting for Agile
AOTB Accounting for AgileAOTB Accounting for Agile
AOTB Accounting for Agile
 
Wind energy Project Strategy revised
Wind energy Project Strategy revisedWind energy Project Strategy revised
Wind energy Project Strategy revised
 
Lecture 06 project_cost_management
Lecture 06 project_cost_managementLecture 06 project_cost_management
Lecture 06 project_cost_management
 
A Comprehensive Beginners Guide To Cost Planning
A Comprehensive Beginners Guide To Cost PlanningA Comprehensive Beginners Guide To Cost Planning
A Comprehensive Beginners Guide To Cost Planning
 

Viewers also liked (16)

Session 7 4th edition PMP
Session 7 4th edition PMPSession 7 4th edition PMP
Session 7 4th edition PMP
 
Session 21 4th edition PMP
Session 21 4th edition PMPSession 21 4th edition PMP
Session 21 4th edition PMP
 
Session 15 4th edition PMP
Session 15 4th edition PMPSession 15 4th edition PMP
Session 15 4th edition PMP
 
Session 16 4th edition
Session 16 4th editionSession 16 4th edition
Session 16 4th edition
 
Session 19 4th edition PMP
Session  19 4th edition PMPSession  19 4th edition PMP
Session 19 4th edition PMP
 
Session 18 -2 PMP 4th edition
Session 18 -2  PMP 4th editionSession 18 -2  PMP 4th edition
Session 18 -2 PMP 4th edition
 
Session 8 4th edition PMP
Session 8 4th edition PMPSession 8 4th edition PMP
Session 8 4th edition PMP
 
Session 2 PMP 4TH edition
Session 2 PMP 4TH editionSession 2 PMP 4TH edition
Session 2 PMP 4TH edition
 
Session 13 4th edition PMP
Session 13 4th edition PMPSession 13 4th edition PMP
Session 13 4th edition PMP
 
Session 12 4th edition PMP
Session  12 4th edition PMPSession  12 4th edition PMP
Session 12 4th edition PMP
 
Session 20 4th edition PMP
Session 20 4th edition PMPSession 20 4th edition PMP
Session 20 4th edition PMP
 
Session 9 4th edition PMP
Session 9 4th edition PMPSession 9 4th edition PMP
Session 9 4th edition PMP
 
Session 18 4th edition PMP
Session 18 4th edition PMPSession 18 4th edition PMP
Session 18 4th edition PMP
 
Session 22 4th edition PMP
Session 22 4th edition PMPSession 22 4th edition PMP
Session 22 4th edition PMP
 
Session 14 4th edition PMP
Session  14 4th edition PMPSession  14 4th edition PMP
Session 14 4th edition PMP
 
Kanban (1)
Kanban (1)Kanban (1)
Kanban (1)
 

Similar to Session 10 4th edition PMP

1440 pmp exam question bank
1440 pmp exam question bank1440 pmp exam question bank
1440 pmp exam question bankBaskar El
 
1. A key objective of change control in configuration management i.docx
1. A key objective of change control in configuration management i.docx1. A key objective of change control in configuration management i.docx
1. A key objective of change control in configuration management i.docxdorishigh
 
Page 9Introduction to Project Management Principles and Practices.docx
Page 9Introduction to Project Management Principles and Practices.docxPage 9Introduction to Project Management Principles and Practices.docx
Page 9Introduction to Project Management Principles and Practices.docxalfred4lewis58146
 
L06 cost management
L06 cost managementL06 cost management
L06 cost managementAsa Chan
 
EVM Assessment Student Name Instruction
EVM Assessment Student Name         InstructionEVM Assessment Student Name         Instruction
EVM Assessment Student Name InstructionBetseyCalderon89
 
PMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdfPMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdfMoncefMakni1
 
PMP Training - 07 project cost management
PMP Training - 07 project cost managementPMP Training - 07 project cost management
PMP Training - 07 project cost managementejlp12
 
Part 11) You are providing a revie.docx
Part 11) You are providing a revie.docxPart 11) You are providing a revie.docx
Part 11) You are providing a revie.docxkarlhennesey
 
Question 1 Artifacts” in the Scrum terminology are the equiva.docx
Question 1 Artifacts” in the Scrum terminology are the equiva.docxQuestion 1 Artifacts” in the Scrum terminology are the equiva.docx
Question 1 Artifacts” in the Scrum terminology are the equiva.docxIRESH3
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost ManagementSerdar Temiz
 
7 cost managmenet
7 cost managmenet7 cost managmenet
7 cost managmenetAla Ibrahim
 
PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7Muzette Charles, PMP
 
1.A cumulative effort curve for a project generally has an S-shap.docx
1.A cumulative effort curve for a project generally has an S-shap.docx1.A cumulative effort curve for a project generally has an S-shap.docx
1.A cumulative effort curve for a project generally has an S-shap.docxjackiewalcutt
 
Devry proj 586 final exam set 3 new
Devry proj 586 final exam set 3 newDevry proj 586 final exam set 3 new
Devry proj 586 final exam set 3 newuopassignment
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost managementImran Jamil
 

Similar to Session 10 4th edition PMP (20)

1440 pmp exam question bank
1440 pmp exam question bank1440 pmp exam question bank
1440 pmp exam question bank
 
07 pmp cost management exam
07 pmp cost management exam07 pmp cost management exam
07 pmp cost management exam
 
Session 6 gdas pmp study group presentation
Session 6   gdas pmp study group presentationSession 6   gdas pmp study group presentation
Session 6 gdas pmp study group presentation
 
1. A key objective of change control in configuration management i.docx
1. A key objective of change control in configuration management i.docx1. A key objective of change control in configuration management i.docx
1. A key objective of change control in configuration management i.docx
 
Page 9Introduction to Project Management Principles and Practices.docx
Page 9Introduction to Project Management Principles and Practices.docxPage 9Introduction to Project Management Principles and Practices.docx
Page 9Introduction to Project Management Principles and Practices.docx
 
L06 cost management
L06 cost managementL06 cost management
L06 cost management
 
EVM Assessment Student Name Instruction
EVM Assessment Student Name         InstructionEVM Assessment Student Name         Instruction
EVM Assessment Student Name Instruction
 
Session 5 gdas pmp study group presentation
Session 5   gdas pmp study group presentationSession 5   gdas pmp study group presentation
Session 5 gdas pmp study group presentation
 
PMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdfPMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdf
 
Pmp cost chapter 7
Pmp cost chapter 7Pmp cost chapter 7
Pmp cost chapter 7
 
PMP Training - 07 project cost management
PMP Training - 07 project cost managementPMP Training - 07 project cost management
PMP Training - 07 project cost management
 
Part 11) You are providing a revie.docx
Part 11) You are providing a revie.docxPart 11) You are providing a revie.docx
Part 11) You are providing a revie.docx
 
150 PMP Questions
150 PMP Questions 150 PMP Questions
150 PMP Questions
 
Question 1 Artifacts” in the Scrum terminology are the equiva.docx
Question 1 Artifacts” in the Scrum terminology are the equiva.docxQuestion 1 Artifacts” in the Scrum terminology are the equiva.docx
Question 1 Artifacts” in the Scrum terminology are the equiva.docx
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
7 cost managmenet
7 cost managmenet7 cost managmenet
7 cost managmenet
 
PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7PMP M Charles_Spring2019_Week3_Chapter7
PMP M Charles_Spring2019_Week3_Chapter7
 
1.A cumulative effort curve for a project generally has an S-shap.docx
1.A cumulative effort curve for a project generally has an S-shap.docx1.A cumulative effort curve for a project generally has an S-shap.docx
1.A cumulative effort curve for a project generally has an S-shap.docx
 
Devry proj 586 final exam set 3 new
Devry proj 586 final exam set 3 newDevry proj 586 final exam set 3 new
Devry proj 586 final exam set 3 new
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost management
 

Recently uploaded

Reviewing and summarization of university ranking system to.pptx
Reviewing and summarization of university ranking system  to.pptxReviewing and summarization of university ranking system  to.pptx
Reviewing and summarization of university ranking system to.pptxAss.Prof. Dr. Mogeeb Mosleh
 
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceDelhi Call girls
 
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Hedda Bird
 
Strategic Management, Vision Mission, Internal Analsysis
Strategic Management, Vision Mission, Internal AnalsysisStrategic Management, Vision Mission, Internal Analsysis
Strategic Management, Vision Mission, Internal Analsysistanmayarora45
 
How Software Developers Destroy Business Value.pptx
How Software Developers Destroy Business Value.pptxHow Software Developers Destroy Business Value.pptx
How Software Developers Destroy Business Value.pptxAaron Stannard
 
Leaders enhance communication by actively listening, providing constructive f...
Leaders enhance communication by actively listening, providing constructive f...Leaders enhance communication by actively listening, providing constructive f...
Leaders enhance communication by actively listening, providing constructive f...Ram V Chary
 
Agile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxAgile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxalinstan901
 
Independent Escorts Vikaspuri / 9899900591 High Profile Escort Service in Delhi
Independent Escorts Vikaspuri  / 9899900591 High Profile Escort Service in DelhiIndependent Escorts Vikaspuri  / 9899900591 High Profile Escort Service in Delhi
Independent Escorts Vikaspuri / 9899900591 High Profile Escort Service in Delhiguptaswati8536
 
Beyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable developmentBeyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable developmentNimot Muili
 
Safety T fire missions army field Artillery
Safety T fire missions army field ArtillerySafety T fire missions army field Artillery
Safety T fire missions army field ArtilleryKennethSwanberg
 
internal analysis on strategic management
internal analysis on strategic managementinternal analysis on strategic management
internal analysis on strategic managementharfimakarim
 
International Ocean Transportation p.pdf
International Ocean Transportation p.pdfInternational Ocean Transportation p.pdf
International Ocean Transportation p.pdfAlejandromexEspino
 
Marketing Management 16th edition by Philip Kotler test bank.docx
Marketing Management 16th edition by Philip Kotler test bank.docxMarketing Management 16th edition by Philip Kotler test bank.docx
Marketing Management 16th edition by Philip Kotler test bank.docxssuserf63bd7
 

Recently uploaded (15)

Reviewing and summarization of university ranking system to.pptx
Reviewing and summarization of university ranking system  to.pptxReviewing and summarization of university ranking system  to.pptx
Reviewing and summarization of university ranking system to.pptx
 
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
 
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
 
Strategic Management, Vision Mission, Internal Analsysis
Strategic Management, Vision Mission, Internal AnalsysisStrategic Management, Vision Mission, Internal Analsysis
Strategic Management, Vision Mission, Internal Analsysis
 
How Software Developers Destroy Business Value.pptx
How Software Developers Destroy Business Value.pptxHow Software Developers Destroy Business Value.pptx
How Software Developers Destroy Business Value.pptx
 
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTECAbortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
 
Leaders enhance communication by actively listening, providing constructive f...
Leaders enhance communication by actively listening, providing constructive f...Leaders enhance communication by actively listening, providing constructive f...
Leaders enhance communication by actively listening, providing constructive f...
 
Agile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxAgile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptx
 
Independent Escorts Vikaspuri / 9899900591 High Profile Escort Service in Delhi
Independent Escorts Vikaspuri  / 9899900591 High Profile Escort Service in DelhiIndependent Escorts Vikaspuri  / 9899900591 High Profile Escort Service in Delhi
Independent Escorts Vikaspuri / 9899900591 High Profile Escort Service in Delhi
 
Intro_University_Ranking_Introduction.pptx
Intro_University_Ranking_Introduction.pptxIntro_University_Ranking_Introduction.pptx
Intro_University_Ranking_Introduction.pptx
 
Beyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable developmentBeyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable development
 
Safety T fire missions army field Artillery
Safety T fire missions army field ArtillerySafety T fire missions army field Artillery
Safety T fire missions army field Artillery
 
internal analysis on strategic management
internal analysis on strategic managementinternal analysis on strategic management
internal analysis on strategic management
 
International Ocean Transportation p.pdf
International Ocean Transportation p.pdfInternational Ocean Transportation p.pdf
International Ocean Transportation p.pdf
 
Marketing Management 16th edition by Philip Kotler test bank.docx
Marketing Management 16th edition by Philip Kotler test bank.docxMarketing Management 16th edition by Philip Kotler test bank.docx
Marketing Management 16th edition by Philip Kotler test bank.docx
 

Session 10 4th edition PMP

  • 1. 1- Half way through the executing processes of your project, a team member alerts you to a potential cost overrun for a specific deliverable. What do you do first? A ) Determine the projected actual cost. B ) Implement a change control process to track the change C ) Inform the customer. D ) Determine the cause of the overage
  • 2. 2- Which of the following represents the value of work we have actually completed? A ) Earned value B ) Planned value C ) Actual cost D ) Estimate to complete
  • 3. 3- While completing your project, you realized that you need to decrease the project costs. After researching your options, you came up with the following choices. Which choice would DECREASE project costs? A ) Change to component A from component B. component A costs more to purchase, but has a lower life cycle cost than B. B ) Change activity A to be completed by resource B instead of resource c. resource B is more experienced worker. C ) Move activities B and H to occur concurrently, and accept a 30 percent increase in the risk that five more resources will be needed later. D ) Remove a test from the project management plan.
  • 4. 4- If earned value (EV) is U.S.$300000, actual cost (AC) is U.S.$350000, and planned value (PV) is U.S. $375000, what does the schedule performance index (SPI) indicate? A ) You are progressing at 86% of the rate originally planned. B ) You are progressing at 125% of the rate originally planned. C ) You are progressing at 116% of the rate originally planned. D ) You are progressing at 80% of the rate originally planned.
  • 5. 5- The formula, EAC = BAC/CPI, assumes that: A ) All subsequent work will be completed at the planned expenditures. B ) All subsequent work will be completed at the planned expenditures, excluding the work packages currently under way C ) All subsequent work will be completed based upon the cost performance to-date D ) The cost performance cannot change during the project
  • 6. 6- What tool must project managers rely upon to accurately identify the costs associated with the project? A ) A bill of materials B ) A Gantt chart C ) A precedence diagram network D ) A work breakdown structure
  • 7. 7- If the Earned Value is equal to Actual Cost, it means: A-Project is on budget and on schedule B-Schedule Variance Index is 1 C-There is no schedule variance D-There is no cost variance
  • 8. 8-Suppose you have a budgeted cost of a project at $900,000. The project is to be completed in 9 months. After a month, you have completed 10% of the project at a total expense of $100,000. The planned completion should have been 15%. At the current progress rate, how much more money is required to complete the project? A) $ 800,000 B) $ 900,000 C) $ 1,000,000 D) $ 1,100,000