2. PERT Technique
Used to evaluate the effects of uncertainty
CPM & PERT are similar
CPM requires Single Estimate
PERT requires Three Estimates
2
Prof. Kanchana Devi
3. PERT Three Estimates are
Prof. Kanchana Devi
3
Most Likely Time
The time we would expect the task to take under
normal circumstances.“ m”
Optimistic Time
Shortest time in which we could expect to complete
the activity, barring the miracles.“a”
Pessimistic Time
Worst Possible time. “b”
4. Expected Duration
Prof. Kanchana Devi
4
PERT Combines the three estimates to form a
single expected duration, te
Formula for te is
te= a+4m+b
6
5. Calculate the expected duration
Prof. Kanchana Devi
5
Activity Optimistic(a) Most Likely(m)
Activity Duration
Pessimistic(b)
A 5 6 8
B 3 4 5
C 2 3 3
D 3.5 4 5
E 1 3 4
F 8 10 15
G 2 3 4
H 2 2 2.5
8. Activity Standard Deviation
Prof. Kanchana Devi
8
S = b-a which gives the degree of uncertainty
6
The activity standard deviation is proportional to
the difference between the optimistic and
pessimistic estimates.
Can be used as a ranking measure of the degree of
uncertainty or risk for each activity
11. Probability of Meeting or Missing
Target Date
Prof. Kanchana Devi
11
The PERT Technique uses the following three
step method for calculating the probability
of meeting or missing a target date:
Calculate SD of each project event
Calculate the Z value for each event that has a target
value
Convert Z values to a probability
12. Prof. Kanchana Devi
12
Note: To add two Standard Deviations we
must add their squares and then find the
square root of the sum.
The SD for event 3 depends on the activity B.
The SD for event 3 is therefore 0.33
For event 5 there are two possible paths, B+E
or F. The total SD for path B+E is
√(0.332+0.502) = 0.6 and For path F is 1.17
SD for event 5 is therefore the greater of two
1.17
13. Z- Value Formula
Prof. Kanchana Devi
13
Te is the Expected Date
T Target Date
S SD
Z = T - te
S
14. Calculate Z value –Event ‘4’
Prof. Kanchana Devi
14
(10-9.00)/0.53 = 1.8867
A Z-Value may be converted to the
probability of not meeting the target date by
using the graph given below
15. Converting Z values to
Probabilities
Prof. Kanchana Devi
15
A Z-value may be converted to the
probability of not meeting the target date by
using the graph.
Eg:
The Z-Value for the project completion (event 6)
is 1.23. Using graph this equates to a probability
of approximately 11%, that is, there is an 11%
risk of not meeting the target date of the end of
week 15.
16. Monte Carlo Simulation
Prof. Kanchana Devi
16
An alternative to PERT Technique
MC Simulation are a class of general analysis
techniques that are valuable to solve any
problem that is complex, nonlinear or for some
uncertain parameters.
It involves repeated random sampling to
compute the results.
Advantage:
Repeated computation of random numbers - easier
to use this technique when available as a computer
program
17. Steps – MC Simulation
Prof. Kanchana Devi
17
Step 1: Express the project completion time in terms of the
duration of the n-activities xi,i=1,n and their dependencies
as a precedence graph, d= f(x1,x2,….xn).
Step 2: Generate a set of random inputs, Xi1,Xi2, …Xin using
the specified probability distributions.
Step 3: Evaluate the project completion time expression
and store the result in di.
Step 4: Repeat steps 2 and 3 for the specified number of
times.
Step 5: Analyze the results di, i=1,n; summarize and display
using a histogram.