SlideShare a Scribd company logo
1 of 18
Download to read offline
SPM-UNIT III
RISK MANAGEMENT
Prof. Kanchana Devi
PERT Technique
 Used to evaluate the effects of uncertainty
 CPM & PERT are similar
 CPM requires Single Estimate
 PERT requires Three Estimates
2
Prof. Kanchana Devi
PERT Three Estimates are
Prof. Kanchana Devi
3
 Most Likely Time
 The time we would expect the task to take under
normal circumstances.“ m”
 Optimistic Time
 Shortest time in which we could expect to complete
the activity, barring the miracles.“a”
 Pessimistic Time
 Worst Possible time. “b”
Expected Duration
Prof. Kanchana Devi
4
 PERT Combines the three estimates to form a
single expected duration, te
 Formula for te is
te= a+4m+b
6
Calculate the expected duration
Prof. Kanchana Devi
5
Activity Optimistic(a) Most Likely(m)
Activity Duration
Pessimistic(b)
A 5 6 8
B 3 4 5
C 2 3 3
D 3.5 4 5
E 1 3 4
F 8 10 15
G 2 3 4
H 2 2 2.5
After Calculating Expected
Duration
Prof. Kanchana Devi
6
PERT Network after the
Prof. Kanchana Devi
7
Activity Standard Deviation
Prof. Kanchana Devi
8
 S = b-a which gives the degree of uncertainty
6
 The activity standard deviation is proportional to
the difference between the optimistic and
pessimistic estimates.
 Can be used as a ranking measure of the degree of
uncertainty or risk for each activity
Standard Deviation
Prof. Kanchana Devi
9
PERT With ‘SD’
Prof. Kanchana Devi
10
Probability of Meeting or Missing
Target Date
Prof. Kanchana Devi
11
 The PERT Technique uses the following three
step method for calculating the probability
of meeting or missing a target date:
 Calculate SD of each project event
 Calculate the Z value for each event that has a target
value
 Convert Z values to a probability
Prof. Kanchana Devi
12
 Note: To add two Standard Deviations we
must add their squares and then find the
square root of the sum.
 The SD for event 3 depends on the activity B.
The SD for event 3 is therefore 0.33
 For event 5 there are two possible paths, B+E
or F. The total SD for path B+E is
√(0.332+0.502) = 0.6 and For path F is 1.17
 SD for event 5 is therefore the greater of two
1.17
Z- Value Formula
Prof. Kanchana Devi
13
 Te  is the Expected Date
 T  Target Date
 S  SD
Z = T - te
S
Calculate Z value –Event ‘4’
Prof. Kanchana Devi
14
 (10-9.00)/0.53 = 1.8867
 A Z-Value may be converted to the
probability of not meeting the target date by
using the graph given below
Converting Z values to
Probabilities
Prof. Kanchana Devi
15
 A Z-value may be converted to the
probability of not meeting the target date by
using the graph.
 Eg:
 The Z-Value for the project completion (event 6)
is 1.23. Using graph this equates to a probability
of approximately 11%, that is, there is an 11%
risk of not meeting the target date of the end of
week 15.
Monte Carlo Simulation
Prof. Kanchana Devi
16
 An alternative to PERT Technique
 MC Simulation are a class of general analysis
techniques that are valuable to solve any
problem that is complex, nonlinear or for some
uncertain parameters.
 It involves repeated random sampling to
compute the results.
 Advantage:
 Repeated computation of random numbers - easier
to use this technique when available as a computer
program
Steps – MC Simulation
Prof. Kanchana Devi
17
 Step 1: Express the project completion time in terms of the
duration of the n-activities xi,i=1,n and their dependencies
as a precedence graph, d= f(x1,x2,….xn).
 Step 2: Generate a set of random inputs, Xi1,Xi2, …Xin using
the specified probability distributions.
 Step 3: Evaluate the project completion time expression
and store the result in di.
 Step 4: Repeat steps 2 and 3 for the specified number of
times.
 Step 5: Analyze the results di, i=1,n; summarize and display
using a histogram.
Histogram
Prof. Kanchana Devi
18

More Related Content

What's hot

Software project management
Software project managementSoftware project management
Software project management
R A Akerkar
 
Software estimation techniques
Software estimation techniquesSoftware estimation techniques
Software estimation techniques
Tan Tran
 
Project Management CH9 Project Scheduling
Project Management CH9 Project SchedulingProject Management CH9 Project Scheduling
Project Management CH9 Project Scheduling
Izah Asmadi
 

What's hot (20)

SPM Activity Planning Introduction
SPM Activity Planning IntroductionSPM Activity Planning Introduction
SPM Activity Planning Introduction
 
Spm unit iii-risk-resource allocation
Spm unit iii-risk-resource allocationSpm unit iii-risk-resource allocation
Spm unit iii-risk-resource allocation
 
Spm unit 4
Spm unit 4Spm unit 4
Spm unit 4
 
Software project management
Software project managementSoftware project management
Software project management
 
Spm unit 3
Spm unit 3Spm unit 3
Spm unit 3
 
Managing people and organizing teams
Managing people and organizing teamsManaging people and organizing teams
Managing people and organizing teams
 
Software estimation techniques
Software estimation techniquesSoftware estimation techniques
Software estimation techniques
 
Basic Software Effort Estimation
Basic Software Effort EstimationBasic Software Effort Estimation
Basic Software Effort Estimation
 
Spm unit iii-risk-intro
Spm unit iii-risk-introSpm unit iii-risk-intro
Spm unit iii-risk-intro
 
Software Project Management: Risk Management
Software Project Management: Risk ManagementSoftware Project Management: Risk Management
Software Project Management: Risk Management
 
Spm project planning
Spm project planning Spm project planning
Spm project planning
 
MG6088 SOFTWARE PROJECT MANAGEMENT
MG6088 SOFTWARE PROJECT MANAGEMENTMG6088 SOFTWARE PROJECT MANAGEMENT
MG6088 SOFTWARE PROJECT MANAGEMENT
 
PM Estimation techniques
PM Estimation techniquesPM Estimation techniques
PM Estimation techniques
 
Cocomo model
Cocomo modelCocomo model
Cocomo model
 
COCOMO Model in software project management
COCOMO Model in software project managementCOCOMO Model in software project management
COCOMO Model in software project management
 
History of software engineering
History of software engineeringHistory of software engineering
History of software engineering
 
Project Management CH9 Project Scheduling
Project Management CH9 Project SchedulingProject Management CH9 Project Scheduling
Project Management CH9 Project Scheduling
 
Adaptive software development (asd) a minimalist approach to complex software...
Adaptive software development (asd) a minimalist approach to complex software...Adaptive software development (asd) a minimalist approach to complex software...
Adaptive software development (asd) a minimalist approach to complex software...
 
Project Planning in Software Engineering
Project Planning in Software EngineeringProject Planning in Software Engineering
Project Planning in Software Engineering
 
software project management
software project managementsoftware project management
software project management
 

Similar to Spm unit iii-risk-pert

Applying the PERT Technique_UNIT III.pptx
Applying the PERT Technique_UNIT III.pptxApplying the PERT Technique_UNIT III.pptx
Applying the PERT Technique_UNIT III.pptx
sherrilsiddhardh
 
Ch-2 final exam documet compler design elements
Ch-2 final exam documet compler design elementsCh-2 final exam documet compler design elements
Ch-2 final exam documet compler design elements
MAHERMOHAMED27
 
!Business statistics tekst
!Business statistics tekst!Business statistics tekst
!Business statistics tekst
King Nisar
 
Parallel Algorithms K – means Clustering
Parallel Algorithms K – means ClusteringParallel Algorithms K – means Clustering
Parallel Algorithms K – means Clustering
Andreina Uzcategui
 

Similar to Spm unit iii-risk-pert (20)

Applying the PERT Technique_UNIT III.pptx
Applying the PERT Technique_UNIT III.pptxApplying the PERT Technique_UNIT III.pptx
Applying the PERT Technique_UNIT III.pptx
 
dynamic programming complete by Mumtaz Ali (03154103173)
dynamic programming complete by Mumtaz Ali (03154103173)dynamic programming complete by Mumtaz Ali (03154103173)
dynamic programming complete by Mumtaz Ali (03154103173)
 
Ch-2 final exam documet compler design elements
Ch-2 final exam documet compler design elementsCh-2 final exam documet compler design elements
Ch-2 final exam documet compler design elements
 
The Complexity Of Primality Testing
The Complexity Of Primality TestingThe Complexity Of Primality Testing
The Complexity Of Primality Testing
 
Pert
PertPert
Pert
 
Time and Space Complexity
Time and Space ComplexityTime and Space Complexity
Time and Space Complexity
 
Project Management Techniques
Project Management TechniquesProject Management Techniques
Project Management Techniques
 
Cpm module iii reference
Cpm module iii referenceCpm module iii reference
Cpm module iii reference
 
!Business statistics tekst
!Business statistics tekst!Business statistics tekst
!Business statistics tekst
 
Regression
RegressionRegression
Regression
 
Lec 10 pert estimating techniques
Lec 10 pert estimating techniquesLec 10 pert estimating techniques
Lec 10 pert estimating techniques
 
Data_Structure_and_Algorithms_Lecture_1.ppt
Data_Structure_and_Algorithms_Lecture_1.pptData_Structure_and_Algorithms_Lecture_1.ppt
Data_Structure_and_Algorithms_Lecture_1.ppt
 
Perspective in Informatics 3 - Assignment 2 - Answer Sheet
Perspective in Informatics 3 - Assignment 2 - Answer SheetPerspective in Informatics 3 - Assignment 2 - Answer Sheet
Perspective in Informatics 3 - Assignment 2 - Answer Sheet
 
Scientific calculator project in c language
Scientific calculator project in c languageScientific calculator project in c language
Scientific calculator project in c language
 
01 - DAA - PPT.pptx
01 - DAA - PPT.pptx01 - DAA - PPT.pptx
01 - DAA - PPT.pptx
 
Per tand project crashing
Per tand project crashingPer tand project crashing
Per tand project crashing
 
Data Structures Notes
Data Structures NotesData Structures Notes
Data Structures Notes
 
Introduction to computing Processing and performance.pdf
Introduction to computing Processing and performance.pdfIntroduction to computing Processing and performance.pdf
Introduction to computing Processing and performance.pdf
 
C-LOOP-Session-2.pptx
C-LOOP-Session-2.pptxC-LOOP-Session-2.pptx
C-LOOP-Session-2.pptx
 
Parallel Algorithms K – means Clustering
Parallel Algorithms K – means ClusteringParallel Algorithms K – means Clustering
Parallel Algorithms K – means Clustering
 

More from Kanchana Devi (10)

Spm unit v-software reliability-
Spm unit v-software reliability-Spm unit v-software reliability-
Spm unit v-software reliability-
 
Spm unit v-software maintenance-intro
Spm unit v-software maintenance-introSpm unit v-software maintenance-intro
Spm unit v-software maintenance-intro
 
Spm unit iii-configuration mgmt-responsibilities
Spm unit iii-configuration mgmt-responsibilitiesSpm unit iii-configuration mgmt-responsibilities
Spm unit iii-configuration mgmt-responsibilities
 
Spm unit iii-configuration mgmt-intro
Spm unit iii-configuration mgmt-introSpm unit iii-configuration mgmt-intro
Spm unit iii-configuration mgmt-intro
 
Spm unit iii-risk-working in teams
Spm unit iii-risk-working in teamsSpm unit iii-risk-working in teams
Spm unit iii-risk-working in teams
 
Spm unit iii-risk-monitoring & control1
Spm unit iii-risk-monitoring & control1Spm unit iii-risk-monitoring & control1
Spm unit iii-risk-monitoring & control1
 
Spm ap-network model-
Spm ap-network model-Spm ap-network model-
Spm ap-network model-
 
SPM Evaluation
SPM EvaluationSPM Evaluation
SPM Evaluation
 
Open source spm tools
Open source spm toolsOpen source spm tools
Open source spm tools
 
Software project management introduction
Software project management introductionSoftware project management introduction
Software project management introduction
 

Recently uploaded

Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Kandungan 087776558899
 
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
dollysharma2066
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
dharasingh5698
 
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoorTop Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
dharasingh5698
 

Recently uploaded (20)

Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
NFPA 5000 2024 standard .
NFPA 5000 2024 standard                                  .NFPA 5000 2024 standard                                  .
NFPA 5000 2024 standard .
 
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
Unit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdfUnit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdf
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoorTop Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank  Design by Working Stress - IS Method.pdfIntze Overhead Water Tank  Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
 

Spm unit iii-risk-pert

  • 2. PERT Technique  Used to evaluate the effects of uncertainty  CPM & PERT are similar  CPM requires Single Estimate  PERT requires Three Estimates 2 Prof. Kanchana Devi
  • 3. PERT Three Estimates are Prof. Kanchana Devi 3  Most Likely Time  The time we would expect the task to take under normal circumstances.“ m”  Optimistic Time  Shortest time in which we could expect to complete the activity, barring the miracles.“a”  Pessimistic Time  Worst Possible time. “b”
  • 4. Expected Duration Prof. Kanchana Devi 4  PERT Combines the three estimates to form a single expected duration, te  Formula for te is te= a+4m+b 6
  • 5. Calculate the expected duration Prof. Kanchana Devi 5 Activity Optimistic(a) Most Likely(m) Activity Duration Pessimistic(b) A 5 6 8 B 3 4 5 C 2 3 3 D 3.5 4 5 E 1 3 4 F 8 10 15 G 2 3 4 H 2 2 2.5
  • 7. PERT Network after the Prof. Kanchana Devi 7
  • 8. Activity Standard Deviation Prof. Kanchana Devi 8  S = b-a which gives the degree of uncertainty 6  The activity standard deviation is proportional to the difference between the optimistic and pessimistic estimates.  Can be used as a ranking measure of the degree of uncertainty or risk for each activity
  • 10. PERT With ‘SD’ Prof. Kanchana Devi 10
  • 11. Probability of Meeting or Missing Target Date Prof. Kanchana Devi 11  The PERT Technique uses the following three step method for calculating the probability of meeting or missing a target date:  Calculate SD of each project event  Calculate the Z value for each event that has a target value  Convert Z values to a probability
  • 12. Prof. Kanchana Devi 12  Note: To add two Standard Deviations we must add their squares and then find the square root of the sum.  The SD for event 3 depends on the activity B. The SD for event 3 is therefore 0.33  For event 5 there are two possible paths, B+E or F. The total SD for path B+E is √(0.332+0.502) = 0.6 and For path F is 1.17  SD for event 5 is therefore the greater of two 1.17
  • 13. Z- Value Formula Prof. Kanchana Devi 13  Te  is the Expected Date  T  Target Date  S  SD Z = T - te S
  • 14. Calculate Z value –Event ‘4’ Prof. Kanchana Devi 14  (10-9.00)/0.53 = 1.8867  A Z-Value may be converted to the probability of not meeting the target date by using the graph given below
  • 15. Converting Z values to Probabilities Prof. Kanchana Devi 15  A Z-value may be converted to the probability of not meeting the target date by using the graph.  Eg:  The Z-Value for the project completion (event 6) is 1.23. Using graph this equates to a probability of approximately 11%, that is, there is an 11% risk of not meeting the target date of the end of week 15.
  • 16. Monte Carlo Simulation Prof. Kanchana Devi 16  An alternative to PERT Technique  MC Simulation are a class of general analysis techniques that are valuable to solve any problem that is complex, nonlinear or for some uncertain parameters.  It involves repeated random sampling to compute the results.  Advantage:  Repeated computation of random numbers - easier to use this technique when available as a computer program
  • 17. Steps – MC Simulation Prof. Kanchana Devi 17  Step 1: Express the project completion time in terms of the duration of the n-activities xi,i=1,n and their dependencies as a precedence graph, d= f(x1,x2,….xn).  Step 2: Generate a set of random inputs, Xi1,Xi2, …Xin using the specified probability distributions.  Step 3: Evaluate the project completion time expression and store the result in di.  Step 4: Repeat steps 2 and 3 for the specified number of times.  Step 5: Analyze the results di, i=1,n; summarize and display using a histogram.