SlideShare a Scribd company logo
1 of 14
Download to read offline
Mr. Keshav R Pagar TOM I Mechanical Engineering
1Unit V: Velocity and Acceleration Analysis: Graphical Methods-I
THEORY OF MACHINE I
VELOCITY AND ACCELERATION ANALYSIS OF SIMPLE
MECHANISMS: GRAPHICAL METHODS-I
Syllabus
 Relative velocity method: Relative velocity of a point on a link, Angular velocity of a
link, Sliding velocity, Velocity polygons for simple mechanisms.
 Introduction
There are 3 Graphical methods to find velocity and acceleration of the mechanism.
1. Relative velocity and Acceleration Method
2. Instantaneous centre of rotation ICR
3. Kleins Construction Method
In this unit we are going to study the 1st
two methods i.e Relative velocity and
Acceleration Method and Instantaneous centre of rotation ICR
A. Relative Velocity and Acceleration Method
1. Relative Velocity Method:
The application of vectors for the relative velocity of two bodies moving along parallel
lines and inclined lines, as shown in Fig. (a) and (b) respectively.
Consider two bodies A and B moving along parallel lines in the same direction with
absolute velocities VA and VB such that VA > VB, as shown in Fig. (a). The relative
velocity of A with respect to B
VAB= Vector difference of VA and VB =
Mr. Keshav R Pagar TOM I Mechanical Engineering
2Unit V: Velocity and Acceleration Analysis: Graphical Methods-I
From Fig.(b), the relative velocity of A with respect to B (i.e. VAB) may be written in
the vector form as follows:
VAB= Relative velocity of A with respect to B =
Similarly, the relative velocity of B with respect to A (i.e. VBA) may be written in the
vector form as follows:
VBA= Relative velocity of B with respect to A =
1.1 Motion of a Link
Consider two points A and B on a rigid link AB, as shown in Fig. Let one of the
extreme point (B) of the link move relative to A , in a clockwise direction.
Since the distance from A to B remains the same, therefore there can be no relative
motion between A and B, along the line AB.
The relative motion of B with respect to A must be perpendicular to AB.
Mr. Keshav R Pagar TOM I Mechanical Engineering
3Unit V: Velocity and Acceleration Analysis: Graphical Methods-I
Hence velocity of any point on a link with respect to another point on the same
link is always perpendicular to the line joining these points on the configuration
(or space) diagram.
A machine or a mechanism is represented by a skeleton or a line diagram, commonly
known as configuration diagram.
The relative velocity of B with respect to A (i.e. VBA) is represented by the vector
ab and is perpendicular to the line AB as shown in Fig.(b).
Let ω = Angular velocity of the link AB about A .
We know that the velocity of the point B with respect to A ,
...(i)
Similarly, the velocity of any point C on AB with respect to A ,
...(ii)
From equations (i) and (ii),
Thus, we see from above equation, that the point c on the vector ab divides it in the
same ratio as C divides the link AB.
Mr. Keshav R Pagar TOM I Mechanical Engineering
4Unit V: Velocity and Acceleration Analysis: Graphical Methods-I
1.2 Rubbing Velocity at a Pin Joint
The links in a mechanism are mostly connected by means of pin joints.
The rubbing velocity is defined as the algebraic sum between the angular velocities
of the two links which are connected by pin joints, multiplied by the radius of the
pin.
Consider two links OA and OB connected by a pin joint at O as shown in Fig.
ω1= Angular velocity of the link OA or
the angular velocity of the point A with respect to O.
ω2= Angular velocity of the link OB or
the angular velocity of the point B with respect to O, and
r = Radius of the pin.
Rubbing velocity at the pin joint O
= (ω1 – ω2) *r, if the links move in the same direction
= (ω1 + ω2) *r, if the links move in the opposite direction
Note : When the pin connects one sliding member and the other turning member,
the angular velocity of the sliding member is zero. In such cases,
Rubbing velocity at the pin joint = ω*r
where ω = Angular velocity of the turning member, and
r = Radius of the pin.
FORMULAE:
1. Velocity of link V= Angular velocity of link * Length of link
Mr. Keshav R Pagar TOM I Mechanical Engineering
5Unit V: Velocity and Acceleration Analysis: Graphical Methods-I
V= ω*r
ω=V/r
2. Velocity of any point on a link (When there is a point on a link)
3. Each line in velocity diagram represents the velocity of that particular link
General Procedure to draw the velocity diagram by Relative Velocity Method
Step 1: Draw the Mechanism as per given length of link called configuration diagram,
or space diagram.
Step 2: Find the velocity of input link.
Step 3: Now the velocity diagram, Mark all fixed point on as a single point
Step 4: Draw the velocity of input link (with suitable scale) as per the direction of
angular velocity given in the configuration diagram from the marked point (step 3) of
velocity diagram.
Step 5: From the last point (Step 4) of the input link draw the line perpendicular to the
next link connecting to the last point of the input link
Step 6: Similarly draw the perpendicular lines (Parallel line in case of sliding motion
i.e motion of slider) from previously obtained points (that points may be fixed marked
point or obtained point during drawing)
Step 7: Determine the values that needs to be find.
Note:1. Solve this example on sheet or on drawing book with necessary drawing
equipment.
Numerical on Relative Velocity Method
Ex. In a four-bar chain ABCD, AD is fixed and is 150 mm long. The crank AB is 40 mm
long and rotates at 120 r.p.m. clockwise, while the link CD = 80 mm oscillates about
Mr. Keshav R Pagar TOM I Mechanical Engineering
6Unit V: Velocity and Acceleration Analysis: Graphical Methods-I
D. BC and AD are of equal length. Find the angular velocity of link CD when angle
BAD = 60°.
Soln
:- Given – 4 Bar Mechanism ABCD,
AB- Crank= 40mm, ⦟BAD=600
, NBA=120rpm (CW)
ωBA=
2∗𝛱∗𝑁
60
= 12.568 rad/sec
BC- Coupler =150mm,
CD- Follower=80mm,
DA- Fixed Link=150mm
To Find - ωCD= ?
Step 1: Draw the Mechanism as per given length of link,
Step 2: Find the velocity of input link
VBA= ωBA*AB = 12.568*0.04 = 0.503m/sec
Step 3: Now the velocity diagram,
As link AD is fixed, therefore points “a and d” are taken as one point in the
velocity diagram,
Step 4: Draw the velocity of input link with suitable scale
Here consider scale: 2cm=0.25m/sec
So, VBA =VB=0.503m/sec = 4.02 cm (Direction perpendicular to AB),
After drawing this point, you will get point “b”.
Mr. Keshav R Pagar TOM I Mechanical Engineering
7Unit V: Velocity and Acceleration Analysis: Graphical Methods-I
Step 5: from “b” point just draw perpendicular to link BC on both side of point
“b” in velocity diagram.
Step 6: draw a line perpendicular to CD from point d (marked fixed point) that
will intersect the previous line mark that point as “c”. (because the line BC & CD are
joined at C in configuration diagram).
Step 7: Determine the required value
The angular velocity of link CD
As we know the relation between ωCD= VCD/CD
For VCD form the velocity diagram measure the distance cd in mm
convert the value in m/sec from assumed scale.
So, VCD = 0.385m/s.
Then, ωCD= VCD/CD = 0.385/0.08 = 4.8 rad/s.
Ex. The crank and connecting rod of a theoretical steam engine are 0.5 m and 2 m long
respectively. The crank makes 180 r.p.m. in the clockwise direction. When it has turned
45° from the inner dead centre position, determine: 1. velocity of piston, 2. angular
velocity of connecting rod.
Soln
:- Solve in similar way as above example, just the velocity of slider is drawn as
same as the motion of slider from fixed point.(Because the slider is sliding on the
fixed surface.)
Sequence to draw velocity diagram:
Mr. Keshav R Pagar TOM I Mechanical Engineering
8Unit V: Velocity and Acceleration Analysis: Graphical Methods-I
1. Write the given data and terms to be find.
2. Draw Configuration diagram (space diagram) as given in example.
3. Calculate VA From given data. VBO = VB = ωBO × OB = 18.852 × 0.5 = 9.426 m/s
4. Mark all fixed point as a single point o.
5. Draw VB (i.e ob distance in velocity diagram) Perpendicular to OB from space
diagram by considering the scale.
6. Draw a line perpendicular to BP from “b” in velocity diagram.
7. For velocity of slider (i.e Point P) draw a parallel line to the motion of slider from
fixed point, it will intersect the previously drawn line mark that point “p”.
8. Name each vector which represents the velocity of each link.
9. Measure the length from velocity diagram to find the velocity of different links
of the mechanism by converting with suitable scale
Mr. Keshav R Pagar TOM I Mechanical Engineering
9Unit V: Velocity and Acceleration Analysis: Graphical Methods-I
Ans: VP = vector op = 8.15 m/s
Ex: In Fig. the angular velocity of the crank OA is 600 r.p.m. Determine the linear
velocity of the slider D and the angular velocity of the link BD, when the crank is
inclined at an angle of 75° to the vertical. The dimensions of various links are : OA =
28 mm ; AB = 44 mm ; BC 49 mm ; and BD = 46 mm. The centre distance between the
centres of rotation O and C is 65 mm. The path of travel of the slider is 11 mm below
the fixed point C. The slider moves along a horizontal path and OC is vertical.
Soln
:-
Sequence to draw velocity diagram:
Mr. Keshav R Pagar TOM I Mechanical Engineering
10Unit V: Velocity and Acceleration Analysis: Graphical Methods-I
1. Write the given data and terms to be find.
2. Draw Configuration diagram (space diagram) as given in example.
3. Calculate VA From given data. VAO = VA = ωAO × OA = 62.84 × 0.028 = 1.76 m/s
4. Mark all fixed point as a single point “o,c”
5. Draw VA (i.e “oa” distance in velocity diagram)Perpendicular to OA from space
diagram by considering the scale.
6. Draw a line perpendicular to AB from “a” in velocity diagram.
7. Draw line perpendicular to BC from “c” (Fixed marked point) in velocity diagram,
it will intersecting the previous line, mark the intersection point as “b”.
8. From the point “b” in velocity diagram draw perpendicular to line BD.
9. For velocity of slider (i.e Point D) draw a parallel line to the motion of slider from
fixed point, it will intersect the previously drawn line mark that point “d”.
10.Name each vector which represents the velocity of each link.
11.Measure the length from velocity diagram to find the velocity of different links of
the mechanism by converting with suitable scale.
Ans: VD = vector od = 1.6 m/s
Ex. In the toggle mechanism, as shown in Fig. the slider D is constrained to move on a
horizontal path. The crank OA is rotating in the counter-clockwise direction at a speed
Mr. Keshav R Pagar TOM I Mechanical Engineering
11Unit V: Velocity and Acceleration Analysis: Graphical Methods-I
of 180 r.p.m. The dimensions of various links are as follows : OA = 180 mm ; CB = 240
mm ; AB = 360 mm ; and BD = 540 mm. For the given configuration, find : 1. Velocity
of slider D, 2. Angular velocity of links AB, CB and BD.
Soln
:-
Sequence to draw velocity diagram:
1. Write the given data and terms to be find.
2. Draw Configuration diagram (space diagram) as given in example.
Mr. Keshav R Pagar TOM I Mechanical Engineering
12Unit V: Velocity and Acceleration Analysis: Graphical Methods-I
3. Calculate VA From given data. VAO = VA = ωAO × OA = 18.85 × 0.18 = 3.4 m/s
4. Mark all fixed point as a single point “o,c”
5. Draw VA (i.e “oa” distance in velocity diagram) Perpendicular to OA from space
diagram by considering the scale.
6. Draw a line perpendicular to AB from “a” in velocity diagram.
7. Draw line perpendicular to BC from “c” (Fixed marked point) in velocity diagram,
it will intersecting the previously drawn line, mark the intersection point as “b”.
8. From the point “b” in velocity diagram draw perpendicular to line BD.
9. For velocity of slider (i.e Point D) draw a parallel line to the motion of slider from
fixed point, it will intersect the previously drawn line mark that point “d”.
10.Name each vector which represents the velocity of each link.
11.Measure the length from velocity diagram to find the velocity of different links of
the mechanism by converting with suitable scale.
Mr. Keshav R Pagar TOM I Mechanical Engineering
13Unit V: Velocity and Acceleration Analysis: Graphical Methods-I
Ans: VD = vector cd = 2.05 m/s
Ex. The dimensions of the various links of a mechanism, as shown in Fig, are as follows
:AB = 30 mm ; BC = 80 mm ; CD = 45 mm ; and CE = 120 mm.
The crank AB rotates uniformly in the clockwise direction at 120 r.p.m. Draw the
velocity diagram for the given configuration of the mechanism and determine the
velocity of the slider E and angular velocities of the links BC, CD and CE.
Mr. Keshav R Pagar TOM I Mechanical Engineering
14Unit V: Velocity and Acceleration Analysis: Graphical Methods-I
Ans: VE=120 mm/s ;
Angular Velocities of the links BC, CD and CE are 2.8 rad/s ; 5.8 rad/s ; 2 rad/s
Ex: Fig, shows a toggle mechanism in which link D is constained to move in horizontal
direction. For the given configuration, find out : 1. velocities of points B and D; and 2.
angular velocities of links AB, BC, and BD. The rank OA rotates at 60 r.p.m. in
anticlockwise direction.
Ans. velocities of points B and D 0.9 m/s; 0.5 m/s;
Angular velocities of links AB, BC, and BD 0.0016 rad/s (ccw) 0.0075 rad/s
(ccw),0.0044 rad/s (ccw).
Take examples from any book an try to solve.

More Related Content

What's hot

Accelerations in Slider Crank mechanism
Accelerations in Slider Crank mechanismAccelerations in Slider Crank mechanism
Accelerations in Slider Crank mechanismAkshay shah
 
Velocity of mechasnism_by_graphical
Velocity of mechasnism_by_graphicalVelocity of mechasnism_by_graphical
Velocity of mechasnism_by_graphicaladitaya goel
 
INVERSION OF MECHANISM
INVERSION OF MECHANISMINVERSION OF MECHANISM
INVERSION OF MECHANISMCHMURLIDHAR
 
ICR Velocity Analysis Graphical Method, Theory of Machine
ICR Velocity Analysis Graphical Method, Theory of MachineICR Velocity Analysis Graphical Method, Theory of Machine
ICR Velocity Analysis Graphical Method, Theory of MachineKESHAV
 
009 relative acceleration
009 relative acceleration009 relative acceleration
009 relative accelerationphysics101
 
Kinematic analysis of mechanisms analytical methods
Kinematic analysis of mechanisms  analytical methodsKinematic analysis of mechanisms  analytical methods
Kinematic analysis of mechanisms analytical methodsajitkarpe1986
 
Chapter 3. velocity analysis (IC,GRAPHICAL AND RELATIVE VELOCITY METHOD)
Chapter 3. velocity analysis (IC,GRAPHICAL AND RELATIVE VELOCITY METHOD)Chapter 3. velocity analysis (IC,GRAPHICAL AND RELATIVE VELOCITY METHOD)
Chapter 3. velocity analysis (IC,GRAPHICAL AND RELATIVE VELOCITY METHOD)kidanemariam tesera
 
116 coriolis acceleration
116  coriolis acceleration116  coriolis acceleration
116 coriolis accelerationAravind Mohan
 
Chapter 1 Introduction to Mechanisms of Machinery
Chapter 1 Introduction to Mechanisms of Machinery Chapter 1 Introduction to Mechanisms of Machinery
Chapter 1 Introduction to Mechanisms of Machinery Biniam Tufa Alemu
 
Instantaneous center method
Instantaneous center methodInstantaneous center method
Instantaneous center methodRohit Singla
 
STEERING GEAR MECHANISMS (kinematics of machines)
STEERING GEAR MECHANISMS (kinematics of machines)STEERING GEAR MECHANISMS (kinematics of machines)
STEERING GEAR MECHANISMS (kinematics of machines)Jeet Amrutiya
 
Position analysis and dimensional synthesis
Position analysis and dimensional synthesisPosition analysis and dimensional synthesis
Position analysis and dimensional synthesisPreetshah1212
 
Synthesis of Mechanism
Synthesis of MechanismSynthesis of Mechanism
Synthesis of MechanismR A Shah
 
Mechanism synthesis, graphical
Mechanism synthesis, graphicalMechanism synthesis, graphical
Mechanism synthesis, graphicalMecanismos Ucr
 
Turning Moment Diagram and Flywheel
Turning Moment Diagram and FlywheelTurning Moment Diagram and Flywheel
Turning Moment Diagram and FlywheelRonak Soni
 
Velocity and acceleration analysis by graphical methods
Velocity and acceleration analysis by graphical methodsVelocity and acceleration analysis by graphical methods
Velocity and acceleration analysis by graphical methodsDr.Vikas Deulgaonkar
 

What's hot (20)

Accelerations in Slider Crank mechanism
Accelerations in Slider Crank mechanismAccelerations in Slider Crank mechanism
Accelerations in Slider Crank mechanism
 
Velocity of mechasnism_by_graphical
Velocity of mechasnism_by_graphicalVelocity of mechasnism_by_graphical
Velocity of mechasnism_by_graphical
 
Ch.08
Ch.08Ch.08
Ch.08
 
INVERSION OF MECHANISM
INVERSION OF MECHANISMINVERSION OF MECHANISM
INVERSION OF MECHANISM
 
ICR Velocity Analysis Graphical Method, Theory of Machine
ICR Velocity Analysis Graphical Method, Theory of MachineICR Velocity Analysis Graphical Method, Theory of Machine
ICR Velocity Analysis Graphical Method, Theory of Machine
 
009 relative acceleration
009 relative acceleration009 relative acceleration
009 relative acceleration
 
8.acceleration analysis
8.acceleration analysis8.acceleration analysis
8.acceleration analysis
 
Kinematic analysis of mechanisms analytical methods
Kinematic analysis of mechanisms  analytical methodsKinematic analysis of mechanisms  analytical methods
Kinematic analysis of mechanisms analytical methods
 
Chapter 3. velocity analysis (IC,GRAPHICAL AND RELATIVE VELOCITY METHOD)
Chapter 3. velocity analysis (IC,GRAPHICAL AND RELATIVE VELOCITY METHOD)Chapter 3. velocity analysis (IC,GRAPHICAL AND RELATIVE VELOCITY METHOD)
Chapter 3. velocity analysis (IC,GRAPHICAL AND RELATIVE VELOCITY METHOD)
 
116 coriolis acceleration
116  coriolis acceleration116  coriolis acceleration
116 coriolis acceleration
 
Chapter 1 Introduction to Mechanisms of Machinery
Chapter 1 Introduction to Mechanisms of Machinery Chapter 1 Introduction to Mechanisms of Machinery
Chapter 1 Introduction to Mechanisms of Machinery
 
Instantaneous center method
Instantaneous center methodInstantaneous center method
Instantaneous center method
 
STEERING GEAR MECHANISMS (kinematics of machines)
STEERING GEAR MECHANISMS (kinematics of machines)STEERING GEAR MECHANISMS (kinematics of machines)
STEERING GEAR MECHANISMS (kinematics of machines)
 
Position analysis and dimensional synthesis
Position analysis and dimensional synthesisPosition analysis and dimensional synthesis
Position analysis and dimensional synthesis
 
Synthesis of Mechanism
Synthesis of MechanismSynthesis of Mechanism
Synthesis of Mechanism
 
kinematic synthesis
kinematic synthesiskinematic synthesis
kinematic synthesis
 
Mechanism synthesis, graphical
Mechanism synthesis, graphicalMechanism synthesis, graphical
Mechanism synthesis, graphical
 
Introduction to Mechanisms
Introduction to MechanismsIntroduction to Mechanisms
Introduction to Mechanisms
 
Turning Moment Diagram and Flywheel
Turning Moment Diagram and FlywheelTurning Moment Diagram and Flywheel
Turning Moment Diagram and Flywheel
 
Velocity and acceleration analysis by graphical methods
Velocity and acceleration analysis by graphical methodsVelocity and acceleration analysis by graphical methods
Velocity and acceleration analysis by graphical methods
 

Similar to Relative velocity method, velocity & acceleration analysis of mechanism

Velo & accel dia by relative velo & accl method
Velo & accel dia by relative velo & accl methodVelo & accel dia by relative velo & accl method
Velo & accel dia by relative velo & accl methodUmesh Ravate
 
Chapter#3 Met 305 2-_velocity_relative
Chapter#3 Met 305 2-_velocity_relativeChapter#3 Met 305 2-_velocity_relative
Chapter#3 Met 305 2-_velocity_relativehotman1991
 
TOM (UNIT 1B AND UNIT 2A) PPTS.pptx
TOM (UNIT 1B AND UNIT 2A) PPTS.pptxTOM (UNIT 1B AND UNIT 2A) PPTS.pptx
TOM (UNIT 1B AND UNIT 2A) PPTS.pptxHarshit17591
 
Velocityofmechasnismbygraphical 130217105814-phpapp02 (1)
Velocityofmechasnismbygraphical 130217105814-phpapp02 (1)Velocityofmechasnismbygraphical 130217105814-phpapp02 (1)
Velocityofmechasnismbygraphical 130217105814-phpapp02 (1)MUHAMMAD USMAN SARWAR
 
Velocityofmechasnismbygraphical 130217105814-phpapp02
Velocityofmechasnismbygraphical 130217105814-phpapp02Velocityofmechasnismbygraphical 130217105814-phpapp02
Velocityofmechasnismbygraphical 130217105814-phpapp02MUHAMMAD USMAN SARWAR
 
3131906 VELOCITY AND ACCELERATION ANALYSIS
3131906 VELOCITY AND ACCELERATION ANALYSIS3131906 VELOCITY AND ACCELERATION ANALYSIS
3131906 VELOCITY AND ACCELERATION ANALYSISTakshil Gajjar
 
Velocity and Acceleration analysis in kinematics of mechanism
Velocity and Acceleration analysis in kinematics of mechanismVelocity and Acceleration analysis in kinematics of mechanism
Velocity and Acceleration analysis in kinematics of mechanismDr.R. SELVAM
 
relative acceleration diagram for a link
 relative acceleration diagram for a link relative acceleration diagram for a link
relative acceleration diagram for a linkDr.R. SELVAM
 
Theory of machines solution of exercise
Theory of machines solution of exerciseTheory of machines solution of exercise
Theory of machines solution of exerciseSaif al-din ali
 
Dynamics velocity diagrams
Dynamics velocity diagramsDynamics velocity diagrams
Dynamics velocity diagramsNasir Ahmad
 
Design of recumbent elliptical trainer
Design of  recumbent elliptical trainerDesign of  recumbent elliptical trainer
Design of recumbent elliptical trainerdaveson700
 
Relative velocities
Relative velocitiesRelative velocities
Relative velocitiesjani parth
 
Mechanics of Machines MET 305
Mechanics of Machines MET 305Mechanics of Machines MET 305
Mechanics of Machines MET 305hotman1991
 
4_6041824606606592995.pptx
4_6041824606606592995.pptx4_6041824606606592995.pptx
4_6041824606606592995.pptxAbrshWubishet
 

Similar to Relative velocity method, velocity & acceleration analysis of mechanism (20)

Velo & accel dia by relative velo & accl method
Velo & accel dia by relative velo & accl methodVelo & accel dia by relative velo & accl method
Velo & accel dia by relative velo & accl method
 
KOM-Unit-3.pptx
KOM-Unit-3.pptxKOM-Unit-3.pptx
KOM-Unit-3.pptx
 
Chapter#3 Met 305 2-_velocity_relative
Chapter#3 Met 305 2-_velocity_relativeChapter#3 Met 305 2-_velocity_relative
Chapter#3 Met 305 2-_velocity_relative
 
TOM (UNIT 1B AND UNIT 2A) PPTS.pptx
TOM (UNIT 1B AND UNIT 2A) PPTS.pptxTOM (UNIT 1B AND UNIT 2A) PPTS.pptx
TOM (UNIT 1B AND UNIT 2A) PPTS.pptx
 
Velocityofmechasnismbygraphical 130217105814-phpapp02 (1)
Velocityofmechasnismbygraphical 130217105814-phpapp02 (1)Velocityofmechasnismbygraphical 130217105814-phpapp02 (1)
Velocityofmechasnismbygraphical 130217105814-phpapp02 (1)
 
Velocityofmechasnismbygraphical 130217105814-phpapp02
Velocityofmechasnismbygraphical 130217105814-phpapp02Velocityofmechasnismbygraphical 130217105814-phpapp02
Velocityofmechasnismbygraphical 130217105814-phpapp02
 
3131906 VELOCITY AND ACCELERATION ANALYSIS
3131906 VELOCITY AND ACCELERATION ANALYSIS3131906 VELOCITY AND ACCELERATION ANALYSIS
3131906 VELOCITY AND ACCELERATION ANALYSIS
 
Module 2.pptx
Module 2.pptxModule 2.pptx
Module 2.pptx
 
Velocity and Acceleration analysis in kinematics of mechanism
Velocity and Acceleration analysis in kinematics of mechanismVelocity and Acceleration analysis in kinematics of mechanism
Velocity and Acceleration analysis in kinematics of mechanism
 
1 diagrams
1 diagrams1 diagrams
1 diagrams
 
relative acceleration diagram for a link
 relative acceleration diagram for a link relative acceleration diagram for a link
relative acceleration diagram for a link
 
Theory of machines solution of exercise
Theory of machines solution of exerciseTheory of machines solution of exercise
Theory of machines solution of exercise
 
Dynamics velocity diagrams
Dynamics velocity diagramsDynamics velocity diagrams
Dynamics velocity diagrams
 
Design of recumbent elliptical trainer
Design of  recumbent elliptical trainerDesign of  recumbent elliptical trainer
Design of recumbent elliptical trainer
 
KOM UNIT 2.1-2.pdf
KOM UNIT 2.1-2.pdfKOM UNIT 2.1-2.pdf
KOM UNIT 2.1-2.pdf
 
Geometric Construction 1.pptx
Geometric Construction 1.pptxGeometric Construction 1.pptx
Geometric Construction 1.pptx
 
Relative velocities
Relative velocitiesRelative velocities
Relative velocities
 
Mechanics of Machines MET 305
Mechanics of Machines MET 305Mechanics of Machines MET 305
Mechanics of Machines MET 305
 
4_6041824606606592995.pptx
4_6041824606606592995.pptx4_6041824606606592995.pptx
4_6041824606606592995.pptx
 
112
112112
112
 

Recently uploaded

THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONjhunlian
 
Robotics Group 10 (Control Schemes) cse.pdf
Robotics Group 10  (Control Schemes) cse.pdfRobotics Group 10  (Control Schemes) cse.pdf
Robotics Group 10 (Control Schemes) cse.pdfsahilsajad201
 
Industrial Applications of Centrifugal Compressors
Industrial Applications of Centrifugal CompressorsIndustrial Applications of Centrifugal Compressors
Industrial Applications of Centrifugal CompressorsAlirezaBagherian3
 
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...Sumanth A
 
Cost estimation approach: FP to COCOMO scenario based question
Cost estimation approach: FP to COCOMO scenario based questionCost estimation approach: FP to COCOMO scenario based question
Cost estimation approach: FP to COCOMO scenario based questionSneha Padhiar
 
Stork Webinar | APM Transformational planning, Tool Selection & Performance T...
Stork Webinar | APM Transformational planning, Tool Selection & Performance T...Stork Webinar | APM Transformational planning, Tool Selection & Performance T...
Stork Webinar | APM Transformational planning, Tool Selection & Performance T...Stork
 
CS 3251 Programming in c all unit notes pdf
CS 3251 Programming in c all unit notes pdfCS 3251 Programming in c all unit notes pdf
CS 3251 Programming in c all unit notes pdfBalamuruganV28
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catcherssdickerson1
 
Turn leadership mistakes into a better future.pptx
Turn leadership mistakes into a better future.pptxTurn leadership mistakes into a better future.pptx
Turn leadership mistakes into a better future.pptxStephen Sitton
 
Engineering Drawing section of solid
Engineering Drawing     section of solidEngineering Drawing     section of solid
Engineering Drawing section of solidnamansinghjarodiya
 
List of Accredited Concrete Batching Plant.pdf
List of Accredited Concrete Batching Plant.pdfList of Accredited Concrete Batching Plant.pdf
List of Accredited Concrete Batching Plant.pdfisabel213075
 
Ch10-Global Supply Chain - Cadena de Suministro.pdf
Ch10-Global Supply Chain - Cadena de Suministro.pdfCh10-Global Supply Chain - Cadena de Suministro.pdf
Ch10-Global Supply Chain - Cadena de Suministro.pdfChristianCDAM
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substationstephanwindworld
 
TEST CASE GENERATION GENERATION BLOCK BOX APPROACH
TEST CASE GENERATION GENERATION BLOCK BOX APPROACHTEST CASE GENERATION GENERATION BLOCK BOX APPROACH
TEST CASE GENERATION GENERATION BLOCK BOX APPROACHSneha Padhiar
 
Katarzyna Lipka-Sidor - BIM School Course
Katarzyna Lipka-Sidor - BIM School CourseKatarzyna Lipka-Sidor - BIM School Course
Katarzyna Lipka-Sidor - BIM School Coursebim.edu.pl
 
Virtual memory management in Operating System
Virtual memory management in Operating SystemVirtual memory management in Operating System
Virtual memory management in Operating SystemRashmi Bhat
 
Input Output Management in Operating System
Input Output Management in Operating SystemInput Output Management in Operating System
Input Output Management in Operating SystemRashmi Bhat
 
OOP concepts -in-Python programming language
OOP concepts -in-Python programming languageOOP concepts -in-Python programming language
OOP concepts -in-Python programming languageSmritiSharma901052
 
multiple access in wireless communication
multiple access in wireless communicationmultiple access in wireless communication
multiple access in wireless communicationpanditadesh123
 

Recently uploaded (20)

THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
 
Robotics Group 10 (Control Schemes) cse.pdf
Robotics Group 10  (Control Schemes) cse.pdfRobotics Group 10  (Control Schemes) cse.pdf
Robotics Group 10 (Control Schemes) cse.pdf
 
Industrial Applications of Centrifugal Compressors
Industrial Applications of Centrifugal CompressorsIndustrial Applications of Centrifugal Compressors
Industrial Applications of Centrifugal Compressors
 
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...
 
Cost estimation approach: FP to COCOMO scenario based question
Cost estimation approach: FP to COCOMO scenario based questionCost estimation approach: FP to COCOMO scenario based question
Cost estimation approach: FP to COCOMO scenario based question
 
Stork Webinar | APM Transformational planning, Tool Selection & Performance T...
Stork Webinar | APM Transformational planning, Tool Selection & Performance T...Stork Webinar | APM Transformational planning, Tool Selection & Performance T...
Stork Webinar | APM Transformational planning, Tool Selection & Performance T...
 
CS 3251 Programming in c all unit notes pdf
CS 3251 Programming in c all unit notes pdfCS 3251 Programming in c all unit notes pdf
CS 3251 Programming in c all unit notes pdf
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
 
Turn leadership mistakes into a better future.pptx
Turn leadership mistakes into a better future.pptxTurn leadership mistakes into a better future.pptx
Turn leadership mistakes into a better future.pptx
 
Engineering Drawing section of solid
Engineering Drawing     section of solidEngineering Drawing     section of solid
Engineering Drawing section of solid
 
List of Accredited Concrete Batching Plant.pdf
List of Accredited Concrete Batching Plant.pdfList of Accredited Concrete Batching Plant.pdf
List of Accredited Concrete Batching Plant.pdf
 
Designing pile caps according to ACI 318-19.pptx
Designing pile caps according to ACI 318-19.pptxDesigning pile caps according to ACI 318-19.pptx
Designing pile caps according to ACI 318-19.pptx
 
Ch10-Global Supply Chain - Cadena de Suministro.pdf
Ch10-Global Supply Chain - Cadena de Suministro.pdfCh10-Global Supply Chain - Cadena de Suministro.pdf
Ch10-Global Supply Chain - Cadena de Suministro.pdf
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substation
 
TEST CASE GENERATION GENERATION BLOCK BOX APPROACH
TEST CASE GENERATION GENERATION BLOCK BOX APPROACHTEST CASE GENERATION GENERATION BLOCK BOX APPROACH
TEST CASE GENERATION GENERATION BLOCK BOX APPROACH
 
Katarzyna Lipka-Sidor - BIM School Course
Katarzyna Lipka-Sidor - BIM School CourseKatarzyna Lipka-Sidor - BIM School Course
Katarzyna Lipka-Sidor - BIM School Course
 
Virtual memory management in Operating System
Virtual memory management in Operating SystemVirtual memory management in Operating System
Virtual memory management in Operating System
 
Input Output Management in Operating System
Input Output Management in Operating SystemInput Output Management in Operating System
Input Output Management in Operating System
 
OOP concepts -in-Python programming language
OOP concepts -in-Python programming languageOOP concepts -in-Python programming language
OOP concepts -in-Python programming language
 
multiple access in wireless communication
multiple access in wireless communicationmultiple access in wireless communication
multiple access in wireless communication
 

Relative velocity method, velocity & acceleration analysis of mechanism

  • 1. Mr. Keshav R Pagar TOM I Mechanical Engineering 1Unit V: Velocity and Acceleration Analysis: Graphical Methods-I THEORY OF MACHINE I VELOCITY AND ACCELERATION ANALYSIS OF SIMPLE MECHANISMS: GRAPHICAL METHODS-I Syllabus  Relative velocity method: Relative velocity of a point on a link, Angular velocity of a link, Sliding velocity, Velocity polygons for simple mechanisms.  Introduction There are 3 Graphical methods to find velocity and acceleration of the mechanism. 1. Relative velocity and Acceleration Method 2. Instantaneous centre of rotation ICR 3. Kleins Construction Method In this unit we are going to study the 1st two methods i.e Relative velocity and Acceleration Method and Instantaneous centre of rotation ICR A. Relative Velocity and Acceleration Method 1. Relative Velocity Method: The application of vectors for the relative velocity of two bodies moving along parallel lines and inclined lines, as shown in Fig. (a) and (b) respectively. Consider two bodies A and B moving along parallel lines in the same direction with absolute velocities VA and VB such that VA > VB, as shown in Fig. (a). The relative velocity of A with respect to B VAB= Vector difference of VA and VB =
  • 2. Mr. Keshav R Pagar TOM I Mechanical Engineering 2Unit V: Velocity and Acceleration Analysis: Graphical Methods-I From Fig.(b), the relative velocity of A with respect to B (i.e. VAB) may be written in the vector form as follows: VAB= Relative velocity of A with respect to B = Similarly, the relative velocity of B with respect to A (i.e. VBA) may be written in the vector form as follows: VBA= Relative velocity of B with respect to A = 1.1 Motion of a Link Consider two points A and B on a rigid link AB, as shown in Fig. Let one of the extreme point (B) of the link move relative to A , in a clockwise direction. Since the distance from A to B remains the same, therefore there can be no relative motion between A and B, along the line AB. The relative motion of B with respect to A must be perpendicular to AB.
  • 3. Mr. Keshav R Pagar TOM I Mechanical Engineering 3Unit V: Velocity and Acceleration Analysis: Graphical Methods-I Hence velocity of any point on a link with respect to another point on the same link is always perpendicular to the line joining these points on the configuration (or space) diagram. A machine or a mechanism is represented by a skeleton or a line diagram, commonly known as configuration diagram. The relative velocity of B with respect to A (i.e. VBA) is represented by the vector ab and is perpendicular to the line AB as shown in Fig.(b). Let ω = Angular velocity of the link AB about A . We know that the velocity of the point B with respect to A , ...(i) Similarly, the velocity of any point C on AB with respect to A , ...(ii) From equations (i) and (ii), Thus, we see from above equation, that the point c on the vector ab divides it in the same ratio as C divides the link AB.
  • 4. Mr. Keshav R Pagar TOM I Mechanical Engineering 4Unit V: Velocity and Acceleration Analysis: Graphical Methods-I 1.2 Rubbing Velocity at a Pin Joint The links in a mechanism are mostly connected by means of pin joints. The rubbing velocity is defined as the algebraic sum between the angular velocities of the two links which are connected by pin joints, multiplied by the radius of the pin. Consider two links OA and OB connected by a pin joint at O as shown in Fig. ω1= Angular velocity of the link OA or the angular velocity of the point A with respect to O. ω2= Angular velocity of the link OB or the angular velocity of the point B with respect to O, and r = Radius of the pin. Rubbing velocity at the pin joint O = (ω1 – ω2) *r, if the links move in the same direction = (ω1 + ω2) *r, if the links move in the opposite direction Note : When the pin connects one sliding member and the other turning member, the angular velocity of the sliding member is zero. In such cases, Rubbing velocity at the pin joint = ω*r where ω = Angular velocity of the turning member, and r = Radius of the pin. FORMULAE: 1. Velocity of link V= Angular velocity of link * Length of link
  • 5. Mr. Keshav R Pagar TOM I Mechanical Engineering 5Unit V: Velocity and Acceleration Analysis: Graphical Methods-I V= ω*r ω=V/r 2. Velocity of any point on a link (When there is a point on a link) 3. Each line in velocity diagram represents the velocity of that particular link General Procedure to draw the velocity diagram by Relative Velocity Method Step 1: Draw the Mechanism as per given length of link called configuration diagram, or space diagram. Step 2: Find the velocity of input link. Step 3: Now the velocity diagram, Mark all fixed point on as a single point Step 4: Draw the velocity of input link (with suitable scale) as per the direction of angular velocity given in the configuration diagram from the marked point (step 3) of velocity diagram. Step 5: From the last point (Step 4) of the input link draw the line perpendicular to the next link connecting to the last point of the input link Step 6: Similarly draw the perpendicular lines (Parallel line in case of sliding motion i.e motion of slider) from previously obtained points (that points may be fixed marked point or obtained point during drawing) Step 7: Determine the values that needs to be find. Note:1. Solve this example on sheet or on drawing book with necessary drawing equipment. Numerical on Relative Velocity Method Ex. In a four-bar chain ABCD, AD is fixed and is 150 mm long. The crank AB is 40 mm long and rotates at 120 r.p.m. clockwise, while the link CD = 80 mm oscillates about
  • 6. Mr. Keshav R Pagar TOM I Mechanical Engineering 6Unit V: Velocity and Acceleration Analysis: Graphical Methods-I D. BC and AD are of equal length. Find the angular velocity of link CD when angle BAD = 60°. Soln :- Given – 4 Bar Mechanism ABCD, AB- Crank= 40mm, ⦟BAD=600 , NBA=120rpm (CW) ωBA= 2∗𝛱∗𝑁 60 = 12.568 rad/sec BC- Coupler =150mm, CD- Follower=80mm, DA- Fixed Link=150mm To Find - ωCD= ? Step 1: Draw the Mechanism as per given length of link, Step 2: Find the velocity of input link VBA= ωBA*AB = 12.568*0.04 = 0.503m/sec Step 3: Now the velocity diagram, As link AD is fixed, therefore points “a and d” are taken as one point in the velocity diagram, Step 4: Draw the velocity of input link with suitable scale Here consider scale: 2cm=0.25m/sec So, VBA =VB=0.503m/sec = 4.02 cm (Direction perpendicular to AB), After drawing this point, you will get point “b”.
  • 7. Mr. Keshav R Pagar TOM I Mechanical Engineering 7Unit V: Velocity and Acceleration Analysis: Graphical Methods-I Step 5: from “b” point just draw perpendicular to link BC on both side of point “b” in velocity diagram. Step 6: draw a line perpendicular to CD from point d (marked fixed point) that will intersect the previous line mark that point as “c”. (because the line BC & CD are joined at C in configuration diagram). Step 7: Determine the required value The angular velocity of link CD As we know the relation between ωCD= VCD/CD For VCD form the velocity diagram measure the distance cd in mm convert the value in m/sec from assumed scale. So, VCD = 0.385m/s. Then, ωCD= VCD/CD = 0.385/0.08 = 4.8 rad/s. Ex. The crank and connecting rod of a theoretical steam engine are 0.5 m and 2 m long respectively. The crank makes 180 r.p.m. in the clockwise direction. When it has turned 45° from the inner dead centre position, determine: 1. velocity of piston, 2. angular velocity of connecting rod. Soln :- Solve in similar way as above example, just the velocity of slider is drawn as same as the motion of slider from fixed point.(Because the slider is sliding on the fixed surface.) Sequence to draw velocity diagram:
  • 8. Mr. Keshav R Pagar TOM I Mechanical Engineering 8Unit V: Velocity and Acceleration Analysis: Graphical Methods-I 1. Write the given data and terms to be find. 2. Draw Configuration diagram (space diagram) as given in example. 3. Calculate VA From given data. VBO = VB = ωBO × OB = 18.852 × 0.5 = 9.426 m/s 4. Mark all fixed point as a single point o. 5. Draw VB (i.e ob distance in velocity diagram) Perpendicular to OB from space diagram by considering the scale. 6. Draw a line perpendicular to BP from “b” in velocity diagram. 7. For velocity of slider (i.e Point P) draw a parallel line to the motion of slider from fixed point, it will intersect the previously drawn line mark that point “p”. 8. Name each vector which represents the velocity of each link. 9. Measure the length from velocity diagram to find the velocity of different links of the mechanism by converting with suitable scale
  • 9. Mr. Keshav R Pagar TOM I Mechanical Engineering 9Unit V: Velocity and Acceleration Analysis: Graphical Methods-I Ans: VP = vector op = 8.15 m/s Ex: In Fig. the angular velocity of the crank OA is 600 r.p.m. Determine the linear velocity of the slider D and the angular velocity of the link BD, when the crank is inclined at an angle of 75° to the vertical. The dimensions of various links are : OA = 28 mm ; AB = 44 mm ; BC 49 mm ; and BD = 46 mm. The centre distance between the centres of rotation O and C is 65 mm. The path of travel of the slider is 11 mm below the fixed point C. The slider moves along a horizontal path and OC is vertical. Soln :- Sequence to draw velocity diagram:
  • 10. Mr. Keshav R Pagar TOM I Mechanical Engineering 10Unit V: Velocity and Acceleration Analysis: Graphical Methods-I 1. Write the given data and terms to be find. 2. Draw Configuration diagram (space diagram) as given in example. 3. Calculate VA From given data. VAO = VA = ωAO × OA = 62.84 × 0.028 = 1.76 m/s 4. Mark all fixed point as a single point “o,c” 5. Draw VA (i.e “oa” distance in velocity diagram)Perpendicular to OA from space diagram by considering the scale. 6. Draw a line perpendicular to AB from “a” in velocity diagram. 7. Draw line perpendicular to BC from “c” (Fixed marked point) in velocity diagram, it will intersecting the previous line, mark the intersection point as “b”. 8. From the point “b” in velocity diagram draw perpendicular to line BD. 9. For velocity of slider (i.e Point D) draw a parallel line to the motion of slider from fixed point, it will intersect the previously drawn line mark that point “d”. 10.Name each vector which represents the velocity of each link. 11.Measure the length from velocity diagram to find the velocity of different links of the mechanism by converting with suitable scale. Ans: VD = vector od = 1.6 m/s Ex. In the toggle mechanism, as shown in Fig. the slider D is constrained to move on a horizontal path. The crank OA is rotating in the counter-clockwise direction at a speed
  • 11. Mr. Keshav R Pagar TOM I Mechanical Engineering 11Unit V: Velocity and Acceleration Analysis: Graphical Methods-I of 180 r.p.m. The dimensions of various links are as follows : OA = 180 mm ; CB = 240 mm ; AB = 360 mm ; and BD = 540 mm. For the given configuration, find : 1. Velocity of slider D, 2. Angular velocity of links AB, CB and BD. Soln :- Sequence to draw velocity diagram: 1. Write the given data and terms to be find. 2. Draw Configuration diagram (space diagram) as given in example.
  • 12. Mr. Keshav R Pagar TOM I Mechanical Engineering 12Unit V: Velocity and Acceleration Analysis: Graphical Methods-I 3. Calculate VA From given data. VAO = VA = ωAO × OA = 18.85 × 0.18 = 3.4 m/s 4. Mark all fixed point as a single point “o,c” 5. Draw VA (i.e “oa” distance in velocity diagram) Perpendicular to OA from space diagram by considering the scale. 6. Draw a line perpendicular to AB from “a” in velocity diagram. 7. Draw line perpendicular to BC from “c” (Fixed marked point) in velocity diagram, it will intersecting the previously drawn line, mark the intersection point as “b”. 8. From the point “b” in velocity diagram draw perpendicular to line BD. 9. For velocity of slider (i.e Point D) draw a parallel line to the motion of slider from fixed point, it will intersect the previously drawn line mark that point “d”. 10.Name each vector which represents the velocity of each link. 11.Measure the length from velocity diagram to find the velocity of different links of the mechanism by converting with suitable scale.
  • 13. Mr. Keshav R Pagar TOM I Mechanical Engineering 13Unit V: Velocity and Acceleration Analysis: Graphical Methods-I Ans: VD = vector cd = 2.05 m/s Ex. The dimensions of the various links of a mechanism, as shown in Fig, are as follows :AB = 30 mm ; BC = 80 mm ; CD = 45 mm ; and CE = 120 mm. The crank AB rotates uniformly in the clockwise direction at 120 r.p.m. Draw the velocity diagram for the given configuration of the mechanism and determine the velocity of the slider E and angular velocities of the links BC, CD and CE.
  • 14. Mr. Keshav R Pagar TOM I Mechanical Engineering 14Unit V: Velocity and Acceleration Analysis: Graphical Methods-I Ans: VE=120 mm/s ; Angular Velocities of the links BC, CD and CE are 2.8 rad/s ; 5.8 rad/s ; 2 rad/s Ex: Fig, shows a toggle mechanism in which link D is constained to move in horizontal direction. For the given configuration, find out : 1. velocities of points B and D; and 2. angular velocities of links AB, BC, and BD. The rank OA rotates at 60 r.p.m. in anticlockwise direction. Ans. velocities of points B and D 0.9 m/s; 0.5 m/s; Angular velocities of links AB, BC, and BD 0.0016 rad/s (ccw) 0.0075 rad/s (ccw),0.0044 rad/s (ccw). Take examples from any book an try to solve.