S.Balamurugan AP/Mech AAA College of Engg. & Tech.3/19/2018 1
Replacement & maintenance analysis
• Equipment's should be continuously monitored for efficient functioning. Otherwise
quality of products will be poor.
• Over the period of time, the cost of their operation & maintenance would
increases.
• So it is necessary to maintain the equipment in good operating conditions with
economical cost.
Replacement & maintenance analysis
• Successful company has to take the following decisions,
– Whether to replace the old equipment or to retain it by
taking the cost of maintenance & operation into account.
Reasons for Replacement
Physical Damage – Changes in physical condition of
the machine. This would lead to decline in value of service
given, increased in operation & maintenance cost
Obsolescence – Becoming out of date, due to
improvement in technology.
Facilities can’t able to meet the demand
» Replacement of the existing equipment with a new one.
» Augmenting the existing one with an additional equipment.
Machines are to be periodically replaced, otherwise it will
become uneconomical for production
Types of Maintenance
Preventive Maintenance
• Proactive Approach
• The periodical inspection &
service activities which are
aimed to detect potential
failures & perform minor
adjustments or repairs.
• This will prevent major
operating problems in future.
• Preventive maintenance is
planned in such a way that it
will not disturb the normal
operations hence no down
time cost of equipment.
Breakdown Maintenance
• Reactive Approach
• The repair which is generally
done after the equipment has
attained down state.
• Emergency nature which will
associated penalty in terms of
high maintenance cost & down
time of an equipment.
Engine Oil : To prevent engine corrosion, it is very important that the engine
maintains the amount of oil it is supposed to receive. Negligence in this aspect will
lead to a deteriorating engine performance, resulting in less mileage.
Maintenance Costs
Types of Replacement Problem
A. Replacement of assets that deteriorate with
time.(Due to gradual failure, or wear & tear
of the components of the machine)
1. Determination of economic life of an asset.
2. Replacement of an existing asset with a new
asset.
B. Simple probabilistic model for assets which
fail completely (Due to sudden failure).
(Electronic Items)
Determination Economic life of an Asset
• A firm is considering replacement of an equipment, whose first cost is Rs.4,000 and the scrap value
is negligible at the end of any year. Based on experience, it was found that the maintenance cost is
zero during the first year and it increases by Rs.200 every year thereafter.
i.When should the equipment be replaced if i = 0%, ii. When should the equipment be replaced if i = 12%
i. When should the equipment be replaced if i = 0%
Economic Life of the equipment = 6 Years
ii. When should the equipment be replaced if i = 12 %
C
Economic Life of the equipment = 7 Years
Concept of Challenger & Defender
If an existing equipment is considered for replacement with a new equipment,
then the existing equipment is known as the defender and the new equipment is known
as challenger
Replacement of an existing asset with a new asset
• In this method, represents the concept of comparison of replacement of
an existing asset with a new asset.
• Step 1 – Annual Equivalent cost of each alternative should be computed
first.
• Step 2 – The alternative which has the least cost should be selected as
the best alternative.
Sunk Cost
• It is the past cost of an equipment / asset.
• Assume a Machine purchased for Rs.5,00,000 about 3 years back, now it
is considered for replacement.
• The supplier of the new equipment will take the old one for Rs.3,00,000.
this value of the equipment should be taken for the analysis
Concept of Challenger & Defender
Two years ago, a machine was purchased at a cost of Rs.2, 00,000 to be useful for
eight years. Its salvage at the end of its life is Rs.25,000. The annual maintenance cost
is Rs. 25,000. The market value of the present machine is Rs.1,20,000.Now, a new
machine to cater to the need of the present machine is available at Rs. 1, 50,000 to be
useful for six years. Its annual maintenance cost is RS. 14,000. The salvage value of
the new machine is RS. 20,000. Using an interest rate of 12%, find whether it is worth
replacing the present machine with the new machine.
Alternative 1 – Present Machine – Defender (Annual Equivalent Cost) (Cost Dominated)
1,20,000 A A A A A A
-2 -1 0 1 2 3 4 5 6
2,00,000 25,000
AE(12%) = ( P - F ) (A/P, i, n) + F × i + A = ( P - F ) (A/P, 12%, 6) + F × i + A
= ( 1,20,000 – 25,000) (0.2432) + 25,000 (0.12) + 25,000 = Rs. 51,104.
Alternative 2 – New Machine – Challenger (Annual Equivalent Cost) (Cost Dominated)
AE(12%) = ( P - F ) (A/P, i, n) + F × i + A = ( P - F ) (A/P, 12%, 6) + F × i + A
= ( 1,50,000 – 20,000) (0.2432) + 20,000 (0.12) + 14,000 = Rs. 48,016.
It is suggested that the present machine is replaced with new machine.
S.Balamurugan AP/Mech AAA College of Engg. & Tech.3/19/2018 12
Simple probabilistic model for assets which fail
completely
• Electronic item fails all of a sudden.
• Failure may result in complete breakdown.
• To avoid the breakdown, we use the following
replacement policy.
– Individual Replacement policy - In this, an item
is replaced immediately after its failure
– Group Replacement policy - In this following
decisions are made
• At what equal intervals are all the items to be replaced
simultaneously with a provision to replace the items
individually which fail during a fixed group replacement
policy?
There are 10,000 bulbs in a decorative set. When any bulbs fail to be replaced, the cost of
replacing a bulb individually is Rs.Rs. 1 only. If all the bulbs are replaced at the same time, the
cost per bulb would be reduced to Rs.0.35. The percentage of bulbs surviving at the end of
month (t) i.e. S(t) and the probability of failures during the month (t) i.e. P(t) are given below.
Determine the optimal replacement policy.
t 0 1 2 3 4 5 6
S(t) 100 97 90 70 30 15 0
P(t) --- 0.03 0.07 0.20 0.40 0.15 0.15
Simple probabilistic model for assets which fail completely
Step 1 - Number of Bulbs replaced at the end of ith month (Ni) (i=0 to 6)
N0 = 10,000
N1 = N0 × P1 = 10,000 × 0.03 = 300
N2 = N0 × P2 + N1 × P1 = 10,000 × 0.07 + 300 × 0.03 = 709
N3 = N0 × P3 + N1 × P2 + N2 × P1 = 10,000 × 0.20 + 300 × 0.07 + 709 × 0.03 = 2042.27 = 2043
N4 = N0 × P4 + N1 × P3 + N2 × P2 + N3 × P1 = 10,000 × 0.40 + 300 × 0.20 + 709 × 0.07 + 2043 × 0.03 = 4170.92 = 4171
N5 = N0 × P5 + N1 × P4 + N2 × P3 + N3 × P2 + N4 × P1 = 10,000×0.15 + 300×0.40 + 709×0.20 + 2043×0.07 + 4171×0.03
= 2029.94 = 2030
N6 = N0 × P6 + N1 × P5 + N2 × P4 + N3 × P3 + N4 × P2 + N5 × P1 = 10,000×0.15 + 300×0.15 + 709×0.40 + 2043×0.20 +
4171×0.07 + 2030×0.03 = 2590.07 = 2591
Step 2 – Determination of Individual Replacement cost
Expected Life of Each Bulb = 𝑖 × Pi𝑛
𝑖=1 = 𝑖 × Pi6
𝑖=1
= 1 × 0.03 + 2 × 0.07 + 3 × 0.20 + 4 × 0.40 + 5 × 0.15 + 6 × 0.15
= 4.02 months
Average number of failures / month = 10,000 / 4.02 = 2487.56 = 2488 (Approximately)
Cost of Individual replacement = (No. of failures / month × Individual replacement cost / resistor)
= 2488 × 1 = Rs.2,488
Step 3 – Determination of Group Replacement cost
End of
month
A
Cost of replacing
10,000 bulbs at a
time (B) Rs.
Cost of replacing bulbs individually during
given replacement period
(C) Rs.
Total Cost
(D = B+C)
Rs.
Average
cost Rs.
(E= D/A)
1 10,000 × 0.35 = 3,500 300 × 1 = 300 3,800 3,800
2 3,500 (300+709) × 1 = 1,009 4,509 2254.5
3 3,500 (300+709+2043) × 1 = 3,052 6,552 2184
4 3,500 (300+709+2043+4171) × 1 = 7,223 10,723 2680.75
Average cost / Month is minimum for third month.
Minimum Group Replacement cost < Individual replacement cost
Group Replacement Policy is the Optimum replacement policy.

More Related Content

What's hot

A Study Report on Value Analysis and Value Engineering (VAVE)
A Study Report on Value Analysis and Value Engineering (VAVE)A Study Report on Value Analysis and Value Engineering (VAVE)
A Study Report on Value Analysis and Value Engineering (VAVE)Avijeet Suryavanshi
 
Energy management & audit
Energy management & auditEnergy management & audit
Energy management & auditPINAKI ROY
 
Work Study
Work StudyWork Study
Work Studyvishakeb
 
Value engineering Short Over view ppt
Value engineering Short Over view pptValue engineering Short Over view ppt
Value engineering Short Over view pptMashfiq Albartross
 
Maintenance Cost - by BOMBARDIER.pdf
Maintenance Cost - by BOMBARDIER.pdfMaintenance Cost - by BOMBARDIER.pdf
Maintenance Cost - by BOMBARDIER.pdfFaisalAfifAlhamdi
 
Replacement models in plant and operations
Replacement models in plant and operationsReplacement models in plant and operations
Replacement models in plant and operationsAbu Bashar
 
SELECTION OFMaterial handling EQUIPMENT FOR CONSTRUCTION PROJECT.pptx
SELECTION OFMaterial handling EQUIPMENT FOR CONSTRUCTION PROJECT.pptxSELECTION OFMaterial handling EQUIPMENT FOR CONSTRUCTION PROJECT.pptx
SELECTION OFMaterial handling EQUIPMENT FOR CONSTRUCTION PROJECT.pptxDIBYARANJAN MAHANTA
 
Spur gear problem and solution
Spur gear   problem and solutionSpur gear   problem and solution
Spur gear problem and solutiondodi mulya
 
Flexible manufacturing system(FMS).
Flexible manufacturing system(FMS).Flexible manufacturing system(FMS).
Flexible manufacturing system(FMS).Nitin Patil
 
different techniques to productivity improvement
different techniques to productivity improvementdifferent techniques to productivity improvement
different techniques to productivity improvementHemant Patil
 
Performance rating
Performance ratingPerformance rating
Performance ratingShivam Kumar
 
ME6503 - DESIGN OF MACHINE ELEMENTS UNIT - V NOTES
ME6503 - DESIGN OF MACHINE ELEMENTS UNIT - V NOTESME6503 - DESIGN OF MACHINE ELEMENTS UNIT - V NOTES
ME6503 - DESIGN OF MACHINE ELEMENTS UNIT - V NOTESASHOK KUMAR RAJENDRAN
 
Bus body fabrication- Design & Analysis
Bus body fabrication-  Design & AnalysisBus body fabrication-  Design & Analysis
Bus body fabrication- Design & AnalysisVIKAS SINGH
 
ME6601 - DESIGN OF TRANSMISSION SYSTEM NOTES AND QUESTION BANK
ME6601 - DESIGN OF TRANSMISSION SYSTEM NOTES AND QUESTION BANK ME6601 - DESIGN OF TRANSMISSION SYSTEM NOTES AND QUESTION BANK
ME6601 - DESIGN OF TRANSMISSION SYSTEM NOTES AND QUESTION BANK ASHOK KUMAR RAJENDRAN
 

What's hot (20)

A Study Report on Value Analysis and Value Engineering (VAVE)
A Study Report on Value Analysis and Value Engineering (VAVE)A Study Report on Value Analysis and Value Engineering (VAVE)
A Study Report on Value Analysis and Value Engineering (VAVE)
 
Energy management & audit
Energy management & auditEnergy management & audit
Energy management & audit
 
OR 14 15-unit_3
OR 14 15-unit_3OR 14 15-unit_3
OR 14 15-unit_3
 
Work Study
Work StudyWork Study
Work Study
 
Value engineering Short Over view ppt
Value engineering Short Over view pptValue engineering Short Over view ppt
Value engineering Short Over view ppt
 
Overhauling and its criteria
Overhauling and its criteriaOverhauling and its criteria
Overhauling and its criteria
 
Maintenance Cost - by BOMBARDIER.pdf
Maintenance Cost - by BOMBARDIER.pdfMaintenance Cost - by BOMBARDIER.pdf
Maintenance Cost - by BOMBARDIER.pdf
 
Value Engineering
Value EngineeringValue Engineering
Value Engineering
 
Replacement models in plant and operations
Replacement models in plant and operationsReplacement models in plant and operations
Replacement models in plant and operations
 
Introduction to FEA
Introduction to FEAIntroduction to FEA
Introduction to FEA
 
SELECTION OFMaterial handling EQUIPMENT FOR CONSTRUCTION PROJECT.pptx
SELECTION OFMaterial handling EQUIPMENT FOR CONSTRUCTION PROJECT.pptxSELECTION OFMaterial handling EQUIPMENT FOR CONSTRUCTION PROJECT.pptx
SELECTION OFMaterial handling EQUIPMENT FOR CONSTRUCTION PROJECT.pptx
 
Replacement analysis
Replacement analysisReplacement analysis
Replacement analysis
 
Spur gear problem and solution
Spur gear   problem and solutionSpur gear   problem and solution
Spur gear problem and solution
 
Flexible manufacturing system(FMS).
Flexible manufacturing system(FMS).Flexible manufacturing system(FMS).
Flexible manufacturing system(FMS).
 
different techniques to productivity improvement
different techniques to productivity improvementdifferent techniques to productivity improvement
different techniques to productivity improvement
 
Performance rating
Performance ratingPerformance rating
Performance rating
 
ME6503 - DESIGN OF MACHINE ELEMENTS UNIT - V NOTES
ME6503 - DESIGN OF MACHINE ELEMENTS UNIT - V NOTESME6503 - DESIGN OF MACHINE ELEMENTS UNIT - V NOTES
ME6503 - DESIGN OF MACHINE ELEMENTS UNIT - V NOTES
 
Work measurement
Work measurementWork measurement
Work measurement
 
Bus body fabrication- Design & Analysis
Bus body fabrication-  Design & AnalysisBus body fabrication-  Design & Analysis
Bus body fabrication- Design & Analysis
 
ME6601 - DESIGN OF TRANSMISSION SYSTEM NOTES AND QUESTION BANK
ME6601 - DESIGN OF TRANSMISSION SYSTEM NOTES AND QUESTION BANK ME6601 - DESIGN OF TRANSMISSION SYSTEM NOTES AND QUESTION BANK
ME6601 - DESIGN OF TRANSMISSION SYSTEM NOTES AND QUESTION BANK
 

Similar to Replacement & Maintenance Analysis

Applied Operation Research (AOR) Replacement Theory
Applied Operation Research (AOR) Replacement TheoryApplied Operation Research (AOR) Replacement Theory
Applied Operation Research (AOR) Replacement TheoryRekha Rani
 
Replacement theory
Replacement theoryReplacement theory
Replacement theoryR A Shah
 
Replacement theory
Replacement theoryReplacement theory
Replacement theoryVILAS ADOLE
 
REPLACEMENT DECISIONS.ppt
REPLACEMENT   DECISIONS.pptREPLACEMENT   DECISIONS.ppt
REPLACEMENT DECISIONS.pptJeanClaudeEid1
 
Unit iv replacement and maintenence analysis
Unit iv replacement and maintenence analysisUnit iv replacement and maintenence analysis
Unit iv replacement and maintenence analysisChandra Kumar S
 
Unit iv replacement and maintenence analysis
Unit iv replacement and maintenence analysisUnit iv replacement and maintenence analysis
Unit iv replacement and maintenence analysisDevalakshmanperumal1991
 
ISE 307 - CHAPTER 12.ppt
ISE 307 - CHAPTER 12.pptISE 307 - CHAPTER 12.ppt
ISE 307 - CHAPTER 12.pptgadha13
 
Lecture 5 - Replacement Problem for industrial equipments
Lecture 5 - Replacement Problem for industrial equipmentsLecture 5 - Replacement Problem for industrial equipments
Lecture 5 - Replacement Problem for industrial equipmentsSasiK25
 
MG 6863 ENGG ECONOMICS UNIT IV REPLACEMENT AND MAITENANCE ANALYSIS
MG 6863 ENGG ECONOMICS UNIT IV REPLACEMENT AND MAITENANCE ANALYSIS MG 6863 ENGG ECONOMICS UNIT IV REPLACEMENT AND MAITENANCE ANALYSIS
MG 6863 ENGG ECONOMICS UNIT IV REPLACEMENT AND MAITENANCE ANALYSIS Asha A
 
How to unlock productivity savings in mining operations part 2. "Show me the ...
How to unlock productivity savings in mining operations part 2. "Show me the ...How to unlock productivity savings in mining operations part 2. "Show me the ...
How to unlock productivity savings in mining operations part 2. "Show me the ...David Mallinson MAICD
 
Replacement models and maintenance analysis
Replacement models and maintenance analysisReplacement models and maintenance analysis
Replacement models and maintenance analysisAhsanKhan837024
 
9 Replacement problems.pptx .
9 Replacement problems.pptx                        .9 Replacement problems.pptx                        .
9 Replacement problems.pptx .Athar739197
 

Similar to Replacement & Maintenance Analysis (20)

Operations REsearch
Operations REsearchOperations REsearch
Operations REsearch
 
Applied Operation Research (AOR) Replacement Theory
Applied Operation Research (AOR) Replacement TheoryApplied Operation Research (AOR) Replacement Theory
Applied Operation Research (AOR) Replacement Theory
 
Replacement theory
Replacement theoryReplacement theory
Replacement theory
 
unit-6 (1).pdf
unit-6 (1).pdfunit-6 (1).pdf
unit-6 (1).pdf
 
Replacement theory
Replacement theoryReplacement theory
Replacement theory
 
Replacement Theory. by Dr. Babasaheb. J. Mohite
Replacement Theory. by  Dr. Babasaheb. J. MohiteReplacement Theory. by  Dr. Babasaheb. J. Mohite
Replacement Theory. by Dr. Babasaheb. J. Mohite
 
Chap5 engeco
Chap5 engecoChap5 engeco
Chap5 engeco
 
replacement model problems.pptx
replacement model problems.pptxreplacement model problems.pptx
replacement model problems.pptx
 
REPLACEMENT DECISIONS.ppt
REPLACEMENT   DECISIONS.pptREPLACEMENT   DECISIONS.ppt
REPLACEMENT DECISIONS.ppt
 
Unit iv replacement and maintenence analysis
Unit iv replacement and maintenence analysisUnit iv replacement and maintenence analysis
Unit iv replacement and maintenence analysis
 
Unit iv replacement and maintenence analysis
Unit iv replacement and maintenence analysisUnit iv replacement and maintenence analysis
Unit iv replacement and maintenence analysis
 
ISE 307 - CHAPTER 12.ppt
ISE 307 - CHAPTER 12.pptISE 307 - CHAPTER 12.ppt
ISE 307 - CHAPTER 12.ppt
 
Lecture 5 - Replacement Problem for industrial equipments
Lecture 5 - Replacement Problem for industrial equipmentsLecture 5 - Replacement Problem for industrial equipments
Lecture 5 - Replacement Problem for industrial equipments
 
replacementtheory.pptx
replacementtheory.pptxreplacementtheory.pptx
replacementtheory.pptx
 
MG 6863 ENGG ECONOMICS UNIT IV REPLACEMENT AND MAITENANCE ANALYSIS
MG 6863 ENGG ECONOMICS UNIT IV REPLACEMENT AND MAITENANCE ANALYSIS MG 6863 ENGG ECONOMICS UNIT IV REPLACEMENT AND MAITENANCE ANALYSIS
MG 6863 ENGG ECONOMICS UNIT IV REPLACEMENT AND MAITENANCE ANALYSIS
 
How to unlock productivity savings in mining operations part 2. "Show me the ...
How to unlock productivity savings in mining operations part 2. "Show me the ...How to unlock productivity savings in mining operations part 2. "Show me the ...
How to unlock productivity savings in mining operations part 2. "Show me the ...
 
Operation management problems
Operation management problemsOperation management problems
Operation management problems
 
Replacement models and maintenance analysis
Replacement models and maintenance analysisReplacement models and maintenance analysis
Replacement models and maintenance analysis
 
9 Replacement problems.pptx .
9 Replacement problems.pptx                        .9 Replacement problems.pptx                        .
9 Replacement problems.pptx .
 
Equipment Replacement Model1 modi
Equipment Replacement Model1 modiEquipment Replacement Model1 modi
Equipment Replacement Model1 modi
 

More from Balamurugan Subburaj

CELLULAR MANUFACTURING & FLEXIBLE MANUFACTURING SYSTEM - UNIT 5 - CAD & M
CELLULAR MANUFACTURING & FLEXIBLE MANUFACTURING SYSTEM - UNIT 5 - CAD & MCELLULAR MANUFACTURING & FLEXIBLE MANUFACTURING SYSTEM - UNIT 5 - CAD & M
CELLULAR MANUFACTURING & FLEXIBLE MANUFACTURING SYSTEM - UNIT 5 - CAD & MBalamurugan Subburaj
 
FUNDAMENTALS OF CNC & PART PROGRAMMING - UNIT - 4 CAD&M
FUNDAMENTALS OF CNC & PART PROGRAMMING - UNIT - 4 CAD&MFUNDAMENTALS OF CNC & PART PROGRAMMING - UNIT - 4 CAD&M
FUNDAMENTALS OF CNC & PART PROGRAMMING - UNIT - 4 CAD&MBalamurugan Subburaj
 
INTRODUCTION TO COMPUTER AIDED DESIGN & MANUFACTURING
INTRODUCTION TO COMPUTER AIDED DESIGN & MANUFACTURINGINTRODUCTION TO COMPUTER AIDED DESIGN & MANUFACTURING
INTRODUCTION TO COMPUTER AIDED DESIGN & MANUFACTURINGBalamurugan Subburaj
 
Energy, economic and environmental issues of power plants
Energy, economic and environmental issues of power plantsEnergy, economic and environmental issues of power plants
Energy, economic and environmental issues of power plantsBalamurugan Subburaj
 
DIESEL, GAS TURBINE & COMBINED CYCLE POWER PLANTS UNIT III
DIESEL, GAS TURBINE & COMBINED CYCLE POWER PLANTS UNIT IIIDIESEL, GAS TURBINE & COMBINED CYCLE POWER PLANTS UNIT III
DIESEL, GAS TURBINE & COMBINED CYCLE POWER PLANTS UNIT IIIBalamurugan Subburaj
 
COAL BASED POWER PLANT UNIT 1 - POWER PLANT ENGINEERING
COAL BASED POWER PLANT UNIT 1 - POWER PLANT ENGINEERINGCOAL BASED POWER PLANT UNIT 1 - POWER PLANT ENGINEERING
COAL BASED POWER PLANT UNIT 1 - POWER PLANT ENGINEERINGBalamurugan Subburaj
 
Cash Flow - Unit III Engineering Economics - MG6863
Cash Flow - Unit III Engineering Economics - MG6863Cash Flow - Unit III Engineering Economics - MG6863
Cash Flow - Unit III Engineering Economics - MG6863Balamurugan Subburaj
 

More from Balamurugan Subburaj (18)

CAD STANDARDS
CAD STANDARDSCAD STANDARDS
CAD STANDARDS
 
CELLULAR MANUFACTURING & FLEXIBLE MANUFACTURING SYSTEM - UNIT 5 - CAD & M
CELLULAR MANUFACTURING & FLEXIBLE MANUFACTURING SYSTEM - UNIT 5 - CAD & MCELLULAR MANUFACTURING & FLEXIBLE MANUFACTURING SYSTEM - UNIT 5 - CAD & M
CELLULAR MANUFACTURING & FLEXIBLE MANUFACTURING SYSTEM - UNIT 5 - CAD & M
 
FUNDAMENTALS OF CNC & PART PROGRAMMING - UNIT - 4 CAD&M
FUNDAMENTALS OF CNC & PART PROGRAMMING - UNIT - 4 CAD&MFUNDAMENTALS OF CNC & PART PROGRAMMING - UNIT - 4 CAD&M
FUNDAMENTALS OF CNC & PART PROGRAMMING - UNIT - 4 CAD&M
 
GEOMETRIC MODELING
GEOMETRIC MODELINGGEOMETRIC MODELING
GEOMETRIC MODELING
 
INTRODUCTION TO COMPUTER AIDED DESIGN & MANUFACTURING
INTRODUCTION TO COMPUTER AIDED DESIGN & MANUFACTURINGINTRODUCTION TO COMPUTER AIDED DESIGN & MANUFACTURING
INTRODUCTION TO COMPUTER AIDED DESIGN & MANUFACTURING
 
Manufacture of plastic components
Manufacture of plastic componentsManufacture of plastic components
Manufacture of plastic components
 
Sheet metal processes
Sheet metal processesSheet metal processes
Sheet metal processes
 
METAL FORMING PROCESS
METAL FORMING PROCESSMETAL FORMING PROCESS
METAL FORMING PROCESS
 
Welding - Joining Processes
Welding - Joining ProcessesWelding - Joining Processes
Welding - Joining Processes
 
METAL CASTING PROCESSES
METAL CASTING PROCESSESMETAL CASTING PROCESSES
METAL CASTING PROCESSES
 
Energy, economic and environmental issues of power plants
Energy, economic and environmental issues of power plantsEnergy, economic and environmental issues of power plants
Energy, economic and environmental issues of power plants
 
Power from renewable energy
Power from renewable energyPower from renewable energy
Power from renewable energy
 
NUCLEAR POWER PLANT
NUCLEAR POWER PLANTNUCLEAR POWER PLANT
NUCLEAR POWER PLANT
 
DIESEL, GAS TURBINE & COMBINED CYCLE POWER PLANTS UNIT III
DIESEL, GAS TURBINE & COMBINED CYCLE POWER PLANTS UNIT IIIDIESEL, GAS TURBINE & COMBINED CYCLE POWER PLANTS UNIT III
DIESEL, GAS TURBINE & COMBINED CYCLE POWER PLANTS UNIT III
 
COAL BASED POWER PLANT UNIT 1 - POWER PLANT ENGINEERING
COAL BASED POWER PLANT UNIT 1 - POWER PLANT ENGINEERINGCOAL BASED POWER PLANT UNIT 1 - POWER PLANT ENGINEERING
COAL BASED POWER PLANT UNIT 1 - POWER PLANT ENGINEERING
 
DEPRECIATION - UNIT V- MG6863
DEPRECIATION - UNIT V- MG6863DEPRECIATION - UNIT V- MG6863
DEPRECIATION - UNIT V- MG6863
 
Cash Flow - Unit III Engineering Economics - MG6863
Cash Flow - Unit III Engineering Economics - MG6863Cash Flow - Unit III Engineering Economics - MG6863
Cash Flow - Unit III Engineering Economics - MG6863
 
Value Engineering Unit 2 MG6863
Value Engineering Unit 2 MG6863Value Engineering Unit 2 MG6863
Value Engineering Unit 2 MG6863
 

Recently uploaded

Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for BeginnersSabitha Banu
 
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxINTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxHumphrey A Beña
 
Global Lehigh Strategic Initiatives (without descriptions)
Global Lehigh Strategic Initiatives (without descriptions)Global Lehigh Strategic Initiatives (without descriptions)
Global Lehigh Strategic Initiatives (without descriptions)cama23
 
What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPCeline George
 
Concurrency Control in Database Management system
Concurrency Control in Database Management systemConcurrency Control in Database Management system
Concurrency Control in Database Management systemChristalin Nelson
 
Music 9 - 4th quarter - Vocal Music of the Romantic Period.pptx
Music 9 - 4th quarter - Vocal Music of the Romantic Period.pptxMusic 9 - 4th quarter - Vocal Music of the Romantic Period.pptx
Music 9 - 4th quarter - Vocal Music of the Romantic Period.pptxleah joy valeriano
 
ICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdfICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdfVanessa Camilleri
 
Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Celine George
 
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptxAUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptxiammrhaywood
 
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...Nguyen Thanh Tu Collection
 
ROLES IN A STAGE PRODUCTION in arts.pptx
ROLES IN A STAGE PRODUCTION in arts.pptxROLES IN A STAGE PRODUCTION in arts.pptx
ROLES IN A STAGE PRODUCTION in arts.pptxVanesaIglesias10
 
How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17Celine George
 
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptxQ4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptxlancelewisportillo
 
4.16.24 Poverty and Precarity--Desmond.pptx
4.16.24 Poverty and Precarity--Desmond.pptx4.16.24 Poverty and Precarity--Desmond.pptx
4.16.24 Poverty and Precarity--Desmond.pptxmary850239
 
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONTHEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONHumphrey A Beña
 
Transaction Management in Database Management System
Transaction Management in Database Management SystemTransaction Management in Database Management System
Transaction Management in Database Management SystemChristalin Nelson
 
Keynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designKeynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designMIPLM
 
Barangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptxBarangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptxCarlos105
 

Recently uploaded (20)

Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for Beginners
 
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxINTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
 
Global Lehigh Strategic Initiatives (without descriptions)
Global Lehigh Strategic Initiatives (without descriptions)Global Lehigh Strategic Initiatives (without descriptions)
Global Lehigh Strategic Initiatives (without descriptions)
 
What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERP
 
Concurrency Control in Database Management system
Concurrency Control in Database Management systemConcurrency Control in Database Management system
Concurrency Control in Database Management system
 
Music 9 - 4th quarter - Vocal Music of the Romantic Period.pptx
Music 9 - 4th quarter - Vocal Music of the Romantic Period.pptxMusic 9 - 4th quarter - Vocal Music of the Romantic Period.pptx
Music 9 - 4th quarter - Vocal Music of the Romantic Period.pptx
 
ICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdfICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdf
 
Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17
 
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptxAUDIENCE THEORY -CULTIVATION THEORY -  GERBNER.pptx
AUDIENCE THEORY -CULTIVATION THEORY - GERBNER.pptx
 
FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptxFINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
 
Raw materials used in Herbal Cosmetics.pptx
Raw materials used in Herbal Cosmetics.pptxRaw materials used in Herbal Cosmetics.pptx
Raw materials used in Herbal Cosmetics.pptx
 
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
 
ROLES IN A STAGE PRODUCTION in arts.pptx
ROLES IN A STAGE PRODUCTION in arts.pptxROLES IN A STAGE PRODUCTION in arts.pptx
ROLES IN A STAGE PRODUCTION in arts.pptx
 
How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17
 
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptxQ4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
Q4-PPT-Music9_Lesson-1-Romantic-Opera.pptx
 
4.16.24 Poverty and Precarity--Desmond.pptx
4.16.24 Poverty and Precarity--Desmond.pptx4.16.24 Poverty and Precarity--Desmond.pptx
4.16.24 Poverty and Precarity--Desmond.pptx
 
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATIONTHEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
THEORIES OF ORGANIZATION-PUBLIC ADMINISTRATION
 
Transaction Management in Database Management System
Transaction Management in Database Management SystemTransaction Management in Database Management System
Transaction Management in Database Management System
 
Keynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designKeynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-design
 
Barangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptxBarangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptx
 

Replacement & Maintenance Analysis

  • 1. S.Balamurugan AP/Mech AAA College of Engg. & Tech.3/19/2018 1
  • 2. Replacement & maintenance analysis • Equipment's should be continuously monitored for efficient functioning. Otherwise quality of products will be poor. • Over the period of time, the cost of their operation & maintenance would increases. • So it is necessary to maintain the equipment in good operating conditions with economical cost.
  • 3. Replacement & maintenance analysis • Successful company has to take the following decisions, – Whether to replace the old equipment or to retain it by taking the cost of maintenance & operation into account. Reasons for Replacement Physical Damage – Changes in physical condition of the machine. This would lead to decline in value of service given, increased in operation & maintenance cost Obsolescence – Becoming out of date, due to improvement in technology. Facilities can’t able to meet the demand » Replacement of the existing equipment with a new one. » Augmenting the existing one with an additional equipment. Machines are to be periodically replaced, otherwise it will become uneconomical for production
  • 4. Types of Maintenance Preventive Maintenance • Proactive Approach • The periodical inspection & service activities which are aimed to detect potential failures & perform minor adjustments or repairs. • This will prevent major operating problems in future. • Preventive maintenance is planned in such a way that it will not disturb the normal operations hence no down time cost of equipment. Breakdown Maintenance • Reactive Approach • The repair which is generally done after the equipment has attained down state. • Emergency nature which will associated penalty in terms of high maintenance cost & down time of an equipment. Engine Oil : To prevent engine corrosion, it is very important that the engine maintains the amount of oil it is supposed to receive. Negligence in this aspect will lead to a deteriorating engine performance, resulting in less mileage.
  • 6. Types of Replacement Problem A. Replacement of assets that deteriorate with time.(Due to gradual failure, or wear & tear of the components of the machine) 1. Determination of economic life of an asset. 2. Replacement of an existing asset with a new asset. B. Simple probabilistic model for assets which fail completely (Due to sudden failure). (Electronic Items)
  • 7.
  • 8. Determination Economic life of an Asset • A firm is considering replacement of an equipment, whose first cost is Rs.4,000 and the scrap value is negligible at the end of any year. Based on experience, it was found that the maintenance cost is zero during the first year and it increases by Rs.200 every year thereafter. i.When should the equipment be replaced if i = 0%, ii. When should the equipment be replaced if i = 12% i. When should the equipment be replaced if i = 0% Economic Life of the equipment = 6 Years
  • 9. ii. When should the equipment be replaced if i = 12 % C Economic Life of the equipment = 7 Years
  • 10. Concept of Challenger & Defender If an existing equipment is considered for replacement with a new equipment, then the existing equipment is known as the defender and the new equipment is known as challenger
  • 11. Replacement of an existing asset with a new asset • In this method, represents the concept of comparison of replacement of an existing asset with a new asset. • Step 1 – Annual Equivalent cost of each alternative should be computed first. • Step 2 – The alternative which has the least cost should be selected as the best alternative. Sunk Cost • It is the past cost of an equipment / asset. • Assume a Machine purchased for Rs.5,00,000 about 3 years back, now it is considered for replacement. • The supplier of the new equipment will take the old one for Rs.3,00,000. this value of the equipment should be taken for the analysis
  • 12. Concept of Challenger & Defender Two years ago, a machine was purchased at a cost of Rs.2, 00,000 to be useful for eight years. Its salvage at the end of its life is Rs.25,000. The annual maintenance cost is Rs. 25,000. The market value of the present machine is Rs.1,20,000.Now, a new machine to cater to the need of the present machine is available at Rs. 1, 50,000 to be useful for six years. Its annual maintenance cost is RS. 14,000. The salvage value of the new machine is RS. 20,000. Using an interest rate of 12%, find whether it is worth replacing the present machine with the new machine. Alternative 1 – Present Machine – Defender (Annual Equivalent Cost) (Cost Dominated) 1,20,000 A A A A A A -2 -1 0 1 2 3 4 5 6 2,00,000 25,000 AE(12%) = ( P - F ) (A/P, i, n) + F × i + A = ( P - F ) (A/P, 12%, 6) + F × i + A = ( 1,20,000 – 25,000) (0.2432) + 25,000 (0.12) + 25,000 = Rs. 51,104. Alternative 2 – New Machine – Challenger (Annual Equivalent Cost) (Cost Dominated) AE(12%) = ( P - F ) (A/P, i, n) + F × i + A = ( P - F ) (A/P, 12%, 6) + F × i + A = ( 1,50,000 – 20,000) (0.2432) + 20,000 (0.12) + 14,000 = Rs. 48,016. It is suggested that the present machine is replaced with new machine. S.Balamurugan AP/Mech AAA College of Engg. & Tech.3/19/2018 12
  • 13. Simple probabilistic model for assets which fail completely • Electronic item fails all of a sudden. • Failure may result in complete breakdown. • To avoid the breakdown, we use the following replacement policy. – Individual Replacement policy - In this, an item is replaced immediately after its failure – Group Replacement policy - In this following decisions are made • At what equal intervals are all the items to be replaced simultaneously with a provision to replace the items individually which fail during a fixed group replacement policy?
  • 14. There are 10,000 bulbs in a decorative set. When any bulbs fail to be replaced, the cost of replacing a bulb individually is Rs.Rs. 1 only. If all the bulbs are replaced at the same time, the cost per bulb would be reduced to Rs.0.35. The percentage of bulbs surviving at the end of month (t) i.e. S(t) and the probability of failures during the month (t) i.e. P(t) are given below. Determine the optimal replacement policy. t 0 1 2 3 4 5 6 S(t) 100 97 90 70 30 15 0 P(t) --- 0.03 0.07 0.20 0.40 0.15 0.15 Simple probabilistic model for assets which fail completely Step 1 - Number of Bulbs replaced at the end of ith month (Ni) (i=0 to 6) N0 = 10,000 N1 = N0 × P1 = 10,000 × 0.03 = 300 N2 = N0 × P2 + N1 × P1 = 10,000 × 0.07 + 300 × 0.03 = 709 N3 = N0 × P3 + N1 × P2 + N2 × P1 = 10,000 × 0.20 + 300 × 0.07 + 709 × 0.03 = 2042.27 = 2043 N4 = N0 × P4 + N1 × P3 + N2 × P2 + N3 × P1 = 10,000 × 0.40 + 300 × 0.20 + 709 × 0.07 + 2043 × 0.03 = 4170.92 = 4171 N5 = N0 × P5 + N1 × P4 + N2 × P3 + N3 × P2 + N4 × P1 = 10,000×0.15 + 300×0.40 + 709×0.20 + 2043×0.07 + 4171×0.03 = 2029.94 = 2030 N6 = N0 × P6 + N1 × P5 + N2 × P4 + N3 × P3 + N4 × P2 + N5 × P1 = 10,000×0.15 + 300×0.15 + 709×0.40 + 2043×0.20 + 4171×0.07 + 2030×0.03 = 2590.07 = 2591
  • 15. Step 2 – Determination of Individual Replacement cost Expected Life of Each Bulb = 𝑖 × Pi𝑛 𝑖=1 = 𝑖 × Pi6 𝑖=1 = 1 × 0.03 + 2 × 0.07 + 3 × 0.20 + 4 × 0.40 + 5 × 0.15 + 6 × 0.15 = 4.02 months Average number of failures / month = 10,000 / 4.02 = 2487.56 = 2488 (Approximately) Cost of Individual replacement = (No. of failures / month × Individual replacement cost / resistor) = 2488 × 1 = Rs.2,488 Step 3 – Determination of Group Replacement cost End of month A Cost of replacing 10,000 bulbs at a time (B) Rs. Cost of replacing bulbs individually during given replacement period (C) Rs. Total Cost (D = B+C) Rs. Average cost Rs. (E= D/A) 1 10,000 × 0.35 = 3,500 300 × 1 = 300 3,800 3,800 2 3,500 (300+709) × 1 = 1,009 4,509 2254.5 3 3,500 (300+709+2043) × 1 = 3,052 6,552 2184 4 3,500 (300+709+2043+4171) × 1 = 7,223 10,723 2680.75 Average cost / Month is minimum for third month. Minimum Group Replacement cost < Individual replacement cost Group Replacement Policy is the Optimum replacement policy.