SAP ECM Overview
SAP Engineering Change Management(ECM) Training
BY
KMR Software Services
http://www.kmrsoft....
 SAP AG 2001
Change Management Process Triggered by Customer
Customer
Design
Engineer
Industrial
Engineer
Report change n...
 SAP AG 2001
Changes with History
?
_____
_____
_____
ECR/
ECO
Status before change
Status after change
• Release
control...
 SAP AG 2001
ECM: Definition of Chances
...
BOM Routing
Document
Material
Change
Linked Object Types
SAP Trainings by KMR...
 SAP AG 2001
Allocating Objects with the Structure Browser
Material
Document
BOM
Routing
SAP Trainings by KMR Software Se...
 SAP AG 2001
Sales
Service
Purchasing Product
engineering
Quality
Management. . .
Process
engineering
Request change
Crea...
 SAP AG 2001
Workflow for ECR/ECO Processing
• Workflow process is triggered by status changes
• Integrated office inbox ...
 SAP AG 2001
Workflow - Graphical Processing of Templates
Navigation
Area
Clipboard
Navigation
Area
Working
Area
SAP Trai...
 SAP AG 2001
Release Control for Engineering Changes
Release
key
Production
Simulation
Production
Planning
Costing
Genera...
 SAP AG 2001
Change Hierarchy
Structuring ECRs/ECOs
Different tasks on different levels
Lead. chg. master
Change packages...
 SAP AG 2001
Release Control in Hierarchies
Package
status
Release key Release key
Leading change master Leading change m...
 SAP AG 2001
• ECR /ECO header and object management record
level
• Settings in customizing for a particular object statu...
 SAP AG 2001
Up to Rel 4.0: „Valid-from‟ effectivity -> only one change status is
effective at a time
After Rel 4.0: „Val...
 SAP AG 2001
Trigger by Change Number
Release with the release key
Late package for leading change master
Date shift
Chan...
SAP Trainings by KMR Software Services Pvt Ltd.
Email : info@kmrsoft.com / kmrss.sap@gmail.com
Thanks
KMR Software Service...
Prochain SlideShare
Chargement dans…5
×

SAP Engineering Change Management(ECM)

13 810 vues

Publié le

SAP Engineering Change Management(ECM)

Publié dans : Formation

SAP Engineering Change Management(ECM)

  1. 1. 29 July 2014 SAP ECM Overview SAP Engineering Change Management(ECM) Training BY KMR Software Services http://www.kmrsoft.com Email : info@kmrsoft.com / kmrss.sap@gmail.com Ph: +91 9966003349 Skype : KMRSS.SAP SAP Trainings by KMR Software Services Pvt Ltd. Email : info@kmrsoft.com / kmrss.sap@gmail.com
  2. 2.  SAP AG 2001 Change Management Process Triggered by Customer Customer Design Engineer Industrial Engineer Report change notification / claim Check status Review change notification / claim Engineering Change Order Order Change Management  Simulation of changes  Apply changes to production SAP Trainings by KMR Software Services Pvt Ltd. Email : info@kmrsoft.com / kmrss.sap@gmail.com
  3. 3.  SAP AG 2001 Changes with History ? _____ _____ _____ ECR/ ECO Status before change Status after change • Release control • Effectivity parameters Documentation of change SAP Trainings by KMR Software Services Pvt Ltd. Email : info@kmrsoft.com / kmrss.sap@gmail.com
  4. 4.  SAP AG 2001 ECM: Definition of Chances ... BOM Routing Document Material Change Linked Object Types SAP Trainings by KMR Software Services Pvt Ltd. Email : info@kmrsoft.com / kmrss.sap@gmail.com
  5. 5.  SAP AG 2001 Allocating Objects with the Structure Browser Material Document BOM Routing SAP Trainings by KMR Software Services Pvt Ltd. Email : info@kmrsoft.com / kmrss.sap@gmail.com
  6. 6.  SAP AG 2001 Sales Service Purchasing Product engineering Quality Management. . . Process engineering Request change Create Eng. Change Request Enter objects Approve Eng. Ch. Request Convert Eng. Ch. Request to Eng. Change Order Complete Eng. Ch. Order Release changes . . . Check feasibility Change objects Processing of an Engineering Change Request / Engineering Change Order (ECR/ECO) Change department ECR/ ECO SAP Trainings by KMR Software Services Pvt Ltd. Email : info@kmrsoft.com / kmrss.sap@gmail.com
  7. 7.  SAP AG 2001 Workflow for ECR/ECO Processing • Workflow process is triggered by status changes • Integrated office inbox as communication window • Direct participation of the responsible specialists from all necessary areas of the enterprise • Several templates for ECR/ECO and the linked objects Status Object 1 Status Object n Status ECR/ ECO SAP Trainings by KMR Software Services Pvt Ltd. Email : info@kmrsoft.com / kmrss.sap@gmail.com
  8. 8.  SAP AG 2001 Workflow - Graphical Processing of Templates Navigation Area Clipboard Navigation Area Working Area SAP Trainings by KMR Software Services Pvt Ltd. Email : info@kmrsoft.com / kmrss.sap@gmail.com
  9. 9.  SAP AG 2001 Release Control for Engineering Changes Release key Production Simulation Production Planning Costing General Release • Release key in ECR/ECO is optional • Controls the release for various areas • Until released the change remains ineffective for the application SAP Trainings by KMR Software Services Pvt Ltd. Email : info@kmrsoft.com / kmrss.sap@gmail.com
  10. 10.  SAP AG 2001 Change Hierarchy Structuring ECRs/ECOs Different tasks on different levels Lead. chg. master Change packages Objects Status / workflow Release control Effectivity parameters SAP Trainings by KMR Software Services Pvt Ltd. Email : info@kmrsoft.com / kmrss.sap@gmail.com
  11. 11.  SAP AG 2001 Release Control in Hierarchies Package status Release key Release key Leading change master Leading change master Change package A Change package A Change package B Change package B Change package C Change package C Package status SAP Trainings by KMR Software Services Pvt Ltd. Email : info@kmrsoft.com / kmrss.sap@gmail.com
  12. 12.  SAP AG 2001 • ECR /ECO header and object management record level • Settings in customizing for a particular object status: digital signature - yes/no? • Cross checking (“multiple signature principle”) • Authority control Digital Signature Smart card SAP Trainings by KMR Software Services Pvt Ltd. Email : info@kmrsoft.com / kmrss.sap@gmail.com
  13. 13.  SAP AG 2001 Up to Rel 4.0: „Valid-from‟ effectivity -> only one change status is effective at a time After Rel 4.0: „Valid-from‟ effectivity plus new effectivity parameters -> more than one change status can be effective at a time Which effectivity parameters are supported?  DATE (standard) as single value or interval:  Open interval  Closed interval  SERIAL NUMBER (standard) as single value or interval :  Open interval  Closed interval  User-defined effectivity parameters, for example:  CUSTOMER  MODEL  COMBINATIONS of parameters, such as “CUSTOMER & DATE” Overview of Effectivity Parameters ( - ) # 4711 # 4712 # 4713 SAP Trainings by KMR Software Services Pvt Ltd. Email : info@kmrsoft.com / kmrss.sap@gmail.com
  14. 14.  SAP AG 2001 Trigger by Change Number Release with the release key Late package for leading change master Date shift Change hierarchy Change package SAP Trainings by KMR Software Services Pvt Ltd. Email : info@kmrsoft.com / kmrss.sap@gmail.com