SlideShare a Scribd company logo
1 of 69
NTPC GADARWADA – TRAINING
REPORT
-Himanshu Rajput
B Tech. 2nd year,
Dept. of Civil Engg.,
Indian Institute of technology
Kanpur10/6/17
OVERVIEW
CIVIL
WORK
Ash
dyke Weir Main
plant
Fabrication Erection Chimney
Site leveling
&
Infrastructure
Transportation
Flexible
pavement Rigid pavement
Bridge
Site
leveling
Drain &
Diversion
drain
Pre-
engineered
structure
Boundary
Wall
Coal
Handling
Plant
Water
Treatment
Plant
Cooling
tower
Field Quality
Assurance
Township
NTPC GA DA RWA DA LAYOUT
`Township
Main Plant
Ash Dyke
Water Reservoir
Fabrication yard
CT
CHP
WTP
switchyard
TESTING
TESTING OF CONCRETE
1) Compressive Testing Machine
• 1 set cast- 6 cubes, with frequency 50 𝑚3.
• Cube size 150*150*150 𝑚𝑚3
• Rate of loading 140kg/𝑐𝑚2 .min
• 3 days, 7 days, 28 days CT from the date
of casting
• 7 days- min. 70% strength
28 days- (Grade)+3
2 Fresh Concrete - Slump Test
• Slump is a measurement of concrete's workability, or fluidity.
• It's an indirect measurement of concrete consistency or
stiffness.
• The slump test is used to ensure uniformity for different
batches of similar concrete under field conditions and to
ascertain the effects of plasticizers on their introduction.
Core Cutter – Partially Destructive Test
• Diameter of core should be atleast 3 times greater the max nominal size of
course aggregate and not less than 2 times of MNS of CA.
• Cores to be tested within 7 days of coring.
• Cube strength = 1.25 * Cylinder strength
• to determine the compressive strength of in-place concrete as per the
standards of IS: 456.
REBOUND HAMMER- NDT
• Surface property test
• Harder the surface, greater is the rebound.
• Compressive strength
CEMENT
The OPC cement is available in 3 grades:
33 Grade
43 Grade
53 Grade
Ordinary Portland Cement
White Cement
White Cement and Grey Cement are usually compared on five terms which are as follows:
1. Raw Material: Grey colour of the cement is mainly due to high content of oxides of iron, manganese
and chromium which are present in limited amount in white cement.
2. Strength and Setting Time: Its setting behavior and strength development are essentially the same as
those expected in grey cement.
3. Fineness: White cement is usually finer than grey cement and thus, gives better finishing.
4. Cost: Due to more complex manufacturing process of white cement, it is expensive than grey cement.
In India, white cement is usually around Rs. 20 per kg costlier than grey cement.
5. Uses: White cement due to its whiteness is mainly used for architectural beauty, interior and exterior
decorations, floorings, ornamental concrete products such as idols while grey cement is mostly used for
construction purposes.
Portland Pozzolana Cement is ideally suited for the following
construction:
+ Hydraulic structures.
+ Mass concreting works.
+ Marine structures.
+ Masonry mortars and plastering.
+ Under aggressive conditions.
For PPC cement there is only one grade which gives a minimum
compressive strength of 33 MPa after 28 days when mixed with standard
sand.
Portland Pozollana Cement
FST needle
Testing of cement
Vicat Test
• IS 5513,IS 4031- Part 4 & 5
• Initial Setting Time
• Final Setting time
• Consistency
 400 gm cement + water (starting with 32%)
 Plunger – Dia= 10∓0.05 mm, Len=50∓1 mm
 Depth of Penetration = 5-7mm
 Consistency= (Quantity of water for 5-7 mm
penetration/Weight of cement) X 100
Standard consistency
plungerIST needle
Nominal & Design Mix of Concrete
Nominal Mix Concrete
• The wide use of concrete as construction materials has
led to the use of mixes of fixed proportion, which ensures
adequate strength. These mixes are called nominal mixes.
• They offer simplicity and Under normal circumstances,
has margin of strength above that specified.
• Nominal mix concrete may be used for concrete of
grades M5, M 7.5, M10, M15 and M20.
Design Mix Concrete
• The concrete mix produced under quality
control keeping in view the strength, durability,
and workability is called the design Mix.
• Others factors like compaction equipment's
available, curing method adopted, type of
cement, quality of fine and coarse aggregate
etc. have to be kept in mind before arriving at
the mix proportion.
• The design mix or controlled mix is being
used more and more in variety of important
structures, because of better strength, reduced
variability, leaner mixed with consequent
economy, as well as greater assurance of the
resultant quality.
If air content increase
slump increase and
hence water content is to
be decreased
If W/C increase water being
constant cement decreases hence no
of cement fines decreases and we
increase sand fines
T E S T I N G O F B R I C K S
S A M P L I N G
Sampling of 10 bricks from a lot
Brick making plant
1) Water absorption
2) Compression
3) Warpage
4) Efflorescence
Brick Testing
TESTING OF SOIL
Liquid Limit test (Cassagrande’s Apparatus)
 This test is done to determine the liquid limit of soil as per IS: 2720 (Part 5) – 1985.
 The liquid limit of fine-grained soil is the water content at which soil behaves
practically like a liquid, but has small shear
strength.
 About 120g of the specimen passing through 425µm IS Sieve is mixed thoroughly
with distilled water. Keep it for 24 hrs. in case of clayey soil.
 Revolution rate of crank= 2 rev./sec
Proctor Test
 This method covers the determination of the
relationship between the moisture content and
density of soils.
 Start with 4% then add 2% water each time.
 After weighing of proctor take some sample
for moisture content.
 Wet density gm/cc =weight of compacted soil
/ 944
 Dry density= wet density/(1+w)
 Plot MDD vs. OMC graph.
Core Cutter Test
 This test is done to determine the in-situ dry density
of soil by core cutter method as per IS: 2720 (Part
XXIX) – 1975.
 approximately 30cm square of the soil layer to be
tested should be exposed and levelled
 Wet density gm/cc =weight of compacted soil / Vol.
of core
 Dry density= wet density/(1+w)
TESTING OF STEEL
Bend –Rebend test
The reason for using this method is that the content of free nitrogen arises in the steel smelt at
high temperatures and when feeding it with nitrogen containing gases. If the content of free
nitrogen is too high, it will effect the ductility after cold-working and ageing.
Bending Rebending
Test piece A test piece of sufficient length is cut or sawn from the bar. If test pieces are taken
from welded fabrics they shall not contain any heat affected zones (HAZ).
Bending the test piece shall be bent over a mandrel not greater than 10 times dia of test piece.
The angle after unloading shall be 90°. The time to complete the bending shall be at least 1 sec.
Artificial ageing The bent test piece is artificially aged at +100 °C for two hours (2 h) in still air
furnace or half an hour in boiling water followed by free cooling in air, to ambient temperature.
As option a temperature of +250 °C for half an hour (0.5 h) can also be used.
Rebending The bent and aged test piece shall be rebent. The distance between the support
rollers shall allow the rebend to take place within the bent area until the angle after unloading is
reduced to less than 70°.
Inspection After rebending, no fracture, transverse or oblique cracks visible to the naked eye shall
occur on the test piece.
TEST PROCEDURE
REINFORCEMENT
Cold Water ducts
( CW ducts )
Mat – raft
Deck sheeting- permanent formwork
Steel analyzing Ribs-concrete gripping
rings
Chair
FOUNDATIONS
Shallow foundation
Raft FoundationCombined Footing
M25
Isolate footing Strip footing
Deep Foundation
 Bentonite powder + water is used for flushing
 Reqd. density 1.05 gm/𝑐𝑚3
Pile Foundation Bentonite Powder
FORMWORK & CURING
Formwork ( shuttering ) Curing with Gunny bags
ASH DYKE
ASH
Bottom Ash (20%)
Settles down; water
is then pumped
out
Fly Ash (80%)
High Concentrated
Slurry
Ash carrying pipe pedestal
+ water
& to dyke + water
Earth
Sand
Toe drain
Ash dyke Layout
Ash dyke section
Toe drain
sand
earth
Key / Cut-
off trench
Special features of Cut-off trench :-
To avoid piping effect – does not allow the water to seep thru the
bottom
To provide strength to the whole embankment (similar to shear key in
column)
To channel the seeped water to the sand embankment.
 Use of Bentonite:-
 To reduce the permeability of soil and hence make it impervious.
 Gives clayey effect to soil and reduce
seepage.
WEIR
Narmada weir
A weir is a barrier across the horizontal
width of the river that alters the flow
characteristics of the water and usually
results in a change in the vertical height of
the river level. There are many designs of
weir, but commonly water flows freely
over the top of the weir crest before
cascading down to a lower level
• Generally ogee shaped weirs are provided for the spillway of a storage
dam.
• The crest of the ogee weir is slightly rises and falls into parabolic form.
• Flow over ogee weir is also similar to flow over rectangular weir.
Ogee – Shaped weir
MAIN PLANT - FABRICATION
Cutting
Welding
Types of welding:-
1) Arc welding
i. Power supply used to create an electric arc b/w
electrode and base material.
ii. Generally SMAW: uses consumable electrode with
coating.
iii. GMAW or MIG welding: alongwith the electrode a
shielding gas (mixture of Ar & CO2 ) is also fed
2) Gas Welding
i. Focused high temperature flame is generated by gas
combustion to melt the workpiece and the filler.
ii. Most common : Oxy-fuel welding where acetylene
is combusted in oxygen.
Fabrication rods of two types:-
i. E6013 – thin plates (<20mm)
ii. E7018 – thick plates (upto 40mm)
NDT test for welding
Dye Penetration test
 Dye Penetrant is a NDT (Non Destructive Testing) method.
 kits come in 3 parts, usually in aerosol cans - A cleaner, a
penetrant, and a developer.
cleaner penetrant developer
 Blasting
• To remove the first layer mill scales
• Cu-Fe grit is used.
• 50 : 50 old and new grit.
• Safer & more environmental friendly than sand
• Swedish comparator is used to check the desired roughness.
Blasting
Before blasting
Cu-Fe grit
After blasting
 Painting
• Within 4-5 hours of blasting.
• Primer comes in powder/paste. Mixed with thinner in proper ratio.
• Layers of paints
i. Zinc Silicate primer (min. 75μ)(blue)
ii. Micaceous Iron Oxide (75 μ)( red) (MIO)
iii. Finish Coat (75 μ)
iv. Final Finish (25 μ)
MAIN PLANT - ERECTION
Turbo Generator foundation ( TG foundation )
• Foundation for vibrating machines
• Earthquake resisting
Chimney shell
Foundation
Pile
Raft
Reinforced Mat
shell
No reinforcement
M25 PPC
M30 OPC
S I T E L E V E L I N G
Total station is a theodolite with an Electronic Distance
Measurement Device. Total station has also been one of the reasons
behind the drastic change of technology in the surveying field.
Leveling Survey: This type of survey is used to determine
the vertical distances (elevations) and relative heights of points
with the help of an instrument known as level
level
TS theodolite
ROADS
RIGID PAVEMENT
A rigid pavement is constructed from cement
concrete or reinforced concrete slabs. Grouted
concrete roads are in the category of semi-
rigid pavements.
The design of rigid pavement is based on
providing a structural cement concrete slab of
sufficient strength to resists the loads from
traffic. The rigid pavement has rigidity and
high modulus of elasticity to distribute the
load over a relatively wide area of soil.
Minor variations in subgrade strength have
little influence on the structural capacity of a
rigid pavement. In the design of a rigid
pavement, the flexural strength of concrete is
the major factor and not the strength of
subgrade. Due to this property of pavement,
when the subgrade deflects beneath the rigid
pavement, the concrete slab is able to bridge
over the localized failures and areas of
inadequate support from subgrade because of
slab action.
M30
Paving quality concrete
(PQC)
Dry lean concrete (DLC)
Tie bars
Jointed plain concrete pavement (JPCP)
Dowel Bars (longitudinal)
Contraction Joint
To prevent cracks in slab due to contraction and
expansion
crack
Rubber lining
Flexible pavement
‫ם‬ Seal coat is a thin surface treatment used to water- proof
the surface and to provide skid resistance.
Tack coat is a very light application of asphalt emulsion
diluted with water. And It provides bonding between two
layers of binder course.
Prime coat is an application of low viscous cutback
bitumen to an absorbent surface like granular bases on which
binder layer is placed and provides bonding between two
layers.
Surface course is the layer directly in contact with traffic loads and are constructed with dense graded asphalt concrete.
Binder course purpose is to distribute load to the base course. Binder course requires lesser quality of mix as compared to
course above it.
Base course provides additional load distribution and contributes to the sub-surface drainage.
Sub-base course the primary functions are to provide structural support, improve drainage, and reduce the intrusion of
fines from the sub-grade in the pavement structure
Sub-grade The top soil or sub-grade is a layer of natural soil prepared to receive the stresses from the layers above
objectives of providing camber are:
Protection of the road surface, especially
for gravel and bituminous roads by
draining the unwanted water as quickly
as possible.
Protection of the subgrade by providing
good drainage conditions.
For safety considerations, as wet
pavement conditions are quite
undesirable from safe driving point of
view.
Shakkar river Bridge
Top plug
Pier / Column
Bearing
Deck beam
Pier cap
Post-cast simply
supported beam
Clam shell machine to dig earth
Causeway HTS wires and post-stressed
Trapezoidal drain
Rectangular drain
Diversion drain
Culvert
A culvert is a structure that allows water to
flow under a road, railroad, trail, or similar
obstruction from one side to the other side.
Typically embedded so as to be surrounded
by soil, a culvert may be made from
a pipe, reinforced concrete or other material
Sewer & Man
hole
Box –type culvert
Pre-engineered construction
1. The primary framing structure of a pre-engineered building is an assembly of I-shaped
members, often referred as I-beams. In pre-engineered buildings, the I beams used are
usually formed by welding together steel plates to form the I section. The I beams are
then field-assembled (e.g. bolted connections) to form the entire frame of the pre-
engineered building.
2. Pre-Engineered Buildings can be adapted to suit a wide variety of structural
applications, the greatest economy will be realized when utilizing standard details. An
efficiently designed Pre-Engineered Building can be lighter that the conventional steel
buildings by up to 30%
RAFTER - a beam forming part of the internal
framework of a roof.
Metal beam
pcc
sheeting
Boundary wall
Retaining wall ( RCC )
Loose soil
RCC column
Brick masonry
( English bond )
Pre-cast pre-stressed concrete slabs
M25
Coal Handling Plant ( CHP )
Turning Point (TP)
Wagon tippler
Not in gadarwada
WATER TREATMENT PLANT ( WTP )
Water reservoirSettling tank
Salt peter treatment of foundation – for soils
containing salts
Aerator
Bitumen coated
COOLING TOWERS
1. The cooling tower is one of the most important device in chemical industries for
example when the hot water come from heat exchanger we use the cooling tower to
cool it.
2. The purpose of cooling tower is to cool relatively warm water by contacting with
unsaturated air. The evaporation of water mainly provides cooling. In a typical
water cooling water tower, warm water flows countercurrent to an air stream.
3. Typically, the warm water enters the top of packed tower and cascades down
through the packing, leaving at the bottom.
Fill –
increase surface area
for evaporation
Made of plastic
fill
Cold water
Cold water channel
Wall to control speed of
flow
TOWNSHIP
Water body
stadium
D-type
C-type
B-type
Hospital
school
Shopping complex
1. Foundation
2. Plinth
3. DPC ( damped proof course)
4. Floor
5. Walls
6. Openings
7. Stairs
8. Roof
9. Surface finish
Plinth
Min grade M20
Plinth beam
A plinth is normally constructed just above the
ground level and immediately after the foundation. It
raises the floor above the ground level and herewith
prevents surface water from entering the building
Ground beam
Plinth beam advantage-
1.Prevent leaking of water into foundation - To prevent a house from settling it is critical that no water be leaked into
foundation. Being made of cement, plinth beam is impervious and therefore prevents water from rain, flooding, etc.
from leaking into foundation.
2. Provides support for walls - For load bearing houses, walls carry the weight of the house. Plinth beam provides solid
footing to raise those walls.
3. Holds house together - Since plinth beam sits across the periphery of the house, it provides binding force across
rooms. For example, without plinth beam it is possible for one of the rooms to settle thus creating uneven floor level.
Plinth beam prevents that from happening.
Damped Proof Course ( DPC ) min thickness 25mm
Damp proof course is a layer of water proofing material such as asphalt or waterproof cement.
Walls are constructed above the damp proof course. Damp proof course prevents surface water
from rising into the walls.
Dampness reduces the strength of the walls and creates unhealthy living conditions. Also it
affects the paint and plaster and increasing the cost of maintenance. Damp proofing layer is not
required where a plinth beam is constructed, because the plinth beam already performs like a
DPC.
Back filling & Plinth filling
Tempering and rammering of
soil
Sand filling
PCC
FILLING MATERIAL FREE FROM LUMPS, ROOTS, VEGETATION, HARMPUL SALTS, ORGANIC
MATERIALS ETC.
1 : 3 : 6 c : fa : ca
TYPES OF FLOORING
•CARPETS AND RUGS
•VINYL FLOORING
Vinyl composition tile (VCT) is a finished flooring material used primarily in commercial and
institutional applications.
Types of tiles-
a) Vitrified tiles - Vitrified tiles are ceramic tiles with high percentage of vitrification and less amount of water
absorption. Vitrification is nothing but a development of glass phase inside the tile during firing process.
b) Ceramic tiles- High wear resistance with low density.
c) Porcelain tiles
•GLASS FLOORING
Glass floors are made with transparent glass when it is useful to view something from above or below; whereas translucent
glass is used when there is no need to view through.
•WOODEN FLOORING
This type of flooring is generally use for special purpose floor example auditorium, hospital etc.
•STONE FLOORING
Marble- •Costliest and best marble is the Makrana white
•White base marble price ranges from Rs.30/- to Rs.400/- sq. ft.
Granite - Hardest type of stone- very difficult to cut and polish
Slate - Resistant to wearing, discoloring or fading
Kotah & Sandstone - used as hard flooring suited for pathways, factory sheds, offices
and other common spaces.
•BRICK FLOORING
White marble
granite
Kotah Stone
Walls & Openings
English bond
a bond used in brickwork consisting of
alternate courses of stretchers and headers.
column
Brick work
OPENINGS
Openings are normally provided in the walls as door, windows and
ventilators. Doors provide access; windows and ventilators provide light
and ventilation.
Lintels are constructed just above the openings. It is normally a stone
slab or a concrete slab.
Sill is the part of the wall that is just below the window.
Lintels are constructed to hold up the walls above the openings. In
earthquake prone areas a continuous lintel beam is provided all over the
walls.
jamb
soffit
Testing of Wood
Teak wood for door frames in
Guest house Digital Moisture meter – value
should not be greater than 12%
Stairs
Staircase parts formwork
ROOF
A flat roof is not truly flat but
angled slightly to allow for water
runoff. It is the cheapest to build
initially but will cost you much
more than other roof types in
maintenance costs.
M30- water
retaining
structure on
roof
Surface finish
Wet finishes
Plaster
Paint
Wallpaper
One of the major problems with wet finishes is
that considerable “drying out time” is required
for the building plus expansion shrinkage
problems with timber components.
Dry finishes
Plaster board
Timber panelling
Carpet
The greatest advantage of dry finishes when
compared to wet finishes is that no shrinkage will
occur during the dry out process
Internal Plastering one or two coats of sand and cement with a finish coat of gypsum plaster on
brick or block walls
Mortar plaster
Mortar
plaster
Gypsum
plaster
Plaster grooves-prevent
cracks1: 6 wall
1: 3 ceiling
Paint finish
objectives of painting are:-
Preservation
appearance
hygiene
A painting system for a given material usually consists of:-
Paint Primer Adheres well to the background and evens out the surface porosity. With ferrous
metals, controls rust. Care must be taken to choose suitable primer for the material to be
covered.
Undercoat Adheres to the primer, builds up the paint thickness and obliterates surface
irregularities. The undercoat should bring the surface to a suitable colour for receiving the
finishing coat. Two coats of undercoat are usually required.
Finish Adheres to the undercoat and provides a protective layer, colour and surface texture.
Important site machines
& tools
Excavator / power shovel
Concrete pump
Batching Plant
Bull Dozer
Back Hoe
Spreading earth and clearing landfills
Pneumatic type roller
Smooth type roller
Drag line
In wet soils
Hard rock below working surface
Hoe trowel Measuring tape
Plumb Bob
Wheel barrow Float Line level
DrillJack planePolisherPutty Knife
CONCLUSION
Overall, I had a fantastic experience while training with the engineers
of NTPC and JMC. I feel extremely fortunate to be a part of the
Maharatna company of India for a month. This summer training
helped me grow a lot and get a deeper look into the construction field.
The summer training program in NTPC is unique because of more
exposure we get in the company.
!!! THANKYOU !!!

More Related Content

What's hot

PROJECT ON Construction of a multistory building POWER POINT PRESENTATION
PROJECT ON Construction of a multistory building POWER POINT PRESENTATIONPROJECT ON Construction of a multistory building POWER POINT PRESENTATION
PROJECT ON Construction of a multistory building POWER POINT PRESENTATIONROHITASH ROJ
 
Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)AJAY SHAHU
 
Precast concrete construction
Precast concrete constructionPrecast concrete construction
Precast concrete constructionJenilPatel22
 
Summer Internship Presentation of Building
Summer Internship Presentation of Building Summer Internship Presentation of Building
Summer Internship Presentation of Building Self-employed
 
Residential building construction ppt
Residential building construction pptResidential building construction ppt
Residential building construction pptBeing Deepak
 
Construction work of a multi storied residential building
Construction work of a multi storied residential buildingConstruction work of a multi storied residential building
Construction work of a multi storied residential buildingShariful Haque Robin
 
Requirements of pdo sp 1279 &amp; 1282
Requirements of pdo sp 1279 &amp; 1282Requirements of pdo sp 1279 &amp; 1282
Requirements of pdo sp 1279 &amp; 1282Babu Arumugam
 
Concrete cast in_place_and_pre_cast_slab
Concrete cast in_place_and_pre_cast_slabConcrete cast in_place_and_pre_cast_slab
Concrete cast in_place_and_pre_cast_slabDivineGraceFernando
 
Formwork-Types and Their Advantages
Formwork-Types and Their AdvantagesFormwork-Types and Their Advantages
Formwork-Types and Their AdvantagesJay1997Singhania
 
Quality inspection of a concrete pavement feb2013 presentation1
Quality inspection of a concrete pavement feb2013 presentation1Quality inspection of a concrete pavement feb2013 presentation1
Quality inspection of a concrete pavement feb2013 presentation1Rodney_Wippenaar
 
Types of pavement construction procedure
Types of pavement construction procedureTypes of pavement construction procedure
Types of pavement construction procedureBhavik A Shah
 
PRESENTATION ON SUMMER INTERNSHIP ON MULTISTOREY BUILDING CONSTRUCTION
PRESENTATION ON SUMMER INTERNSHIP ON MULTISTOREY BUILDING CONSTRUCTION PRESENTATION ON SUMMER INTERNSHIP ON MULTISTOREY BUILDING CONSTRUCTION
PRESENTATION ON SUMMER INTERNSHIP ON MULTISTOREY BUILDING CONSTRUCTION Ved Jangid
 
Super-Structural Construction Work of a Six Storied Residential Building.
Super-Structural Construction Work of a Six Storied Residential Building.Super-Structural Construction Work of a Six Storied Residential Building.
Super-Structural Construction Work of a Six Storied Residential Building.Shariful Haque Robin
 

What's hot (20)

Summer training report
Summer training reportSummer training report
Summer training report
 
CHE :- 6 form work (MODULE 3)
CHE :- 6 form work (MODULE 3)CHE :- 6 form work (MODULE 3)
CHE :- 6 form work (MODULE 3)
 
PROJECT ON Construction of a multistory building POWER POINT PRESENTATION
PROJECT ON Construction of a multistory building POWER POINT PRESENTATIONPROJECT ON Construction of a multistory building POWER POINT PRESENTATION
PROJECT ON Construction of a multistory building POWER POINT PRESENTATION
 
Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)
 
Precast concrete construction
Precast concrete constructionPrecast concrete construction
Precast concrete construction
 
Boq piling works
Boq   piling worksBoq   piling works
Boq piling works
 
Summer Internship Presentation of Building
Summer Internship Presentation of Building Summer Internship Presentation of Building
Summer Internship Presentation of Building
 
Steel formwork
Steel formworkSteel formwork
Steel formwork
 
Residential building construction ppt
Residential building construction pptResidential building construction ppt
Residential building construction ppt
 
Construction work of a multi storied residential building
Construction work of a multi storied residential buildingConstruction work of a multi storied residential building
Construction work of a multi storied residential building
 
Requirements of pdo sp 1279 &amp; 1282
Requirements of pdo sp 1279 &amp; 1282Requirements of pdo sp 1279 &amp; 1282
Requirements of pdo sp 1279 &amp; 1282
 
Concrete cast in_place_and_pre_cast_slab
Concrete cast in_place_and_pre_cast_slabConcrete cast in_place_and_pre_cast_slab
Concrete cast in_place_and_pre_cast_slab
 
Construction of rigid pavement
Construction of rigid pavement Construction of rigid pavement
Construction of rigid pavement
 
Formwork-Types and Their Advantages
Formwork-Types and Their AdvantagesFormwork-Types and Their Advantages
Formwork-Types and Their Advantages
 
Quality inspection of a concrete pavement feb2013 presentation1
Quality inspection of a concrete pavement feb2013 presentation1Quality inspection of a concrete pavement feb2013 presentation1
Quality inspection of a concrete pavement feb2013 presentation1
 
Measurements in construction
Measurements in constructionMeasurements in construction
Measurements in construction
 
Types of pavement construction procedure
Types of pavement construction procedureTypes of pavement construction procedure
Types of pavement construction procedure
 
PRESENTATION ON SUMMER INTERNSHIP ON MULTISTOREY BUILDING CONSTRUCTION
PRESENTATION ON SUMMER INTERNSHIP ON MULTISTOREY BUILDING CONSTRUCTION PRESENTATION ON SUMMER INTERNSHIP ON MULTISTOREY BUILDING CONSTRUCTION
PRESENTATION ON SUMMER INTERNSHIP ON MULTISTOREY BUILDING CONSTRUCTION
 
Formwork
FormworkFormwork
Formwork
 
Super-Structural Construction Work of a Six Storied Residential Building.
Super-Structural Construction Work of a Six Storied Residential Building.Super-Structural Construction Work of a Six Storied Residential Building.
Super-Structural Construction Work of a Six Storied Residential Building.
 

Similar to Ntpc summer training 2017

Self compacting concrete (scc)
Self compacting concrete (scc)Self compacting concrete (scc)
Self compacting concrete (scc)y Sahaja
 
EXPERIMENTAL BEHAVIOUR OF SELF COMPACTING CONCRETE USING GGBS WITH PARTIAL RE...
EXPERIMENTAL BEHAVIOUR OF SELF COMPACTING CONCRETE USING GGBS WITH PARTIAL RE...EXPERIMENTAL BEHAVIOUR OF SELF COMPACTING CONCRETE USING GGBS WITH PARTIAL RE...
EXPERIMENTAL BEHAVIOUR OF SELF COMPACTING CONCRETE USING GGBS WITH PARTIAL RE...Ijripublishers Ijri
 
Cc road summer training ppt @akshay kumar
Cc road summer training ppt @akshay kumarCc road summer training ppt @akshay kumar
Cc road summer training ppt @akshay kumarAkshay kumar
 
special concrete and high performance concrete
special concrete and high performance concretespecial concrete and high performance concrete
special concrete and high performance concreteErankajKumar
 
Concrete Technology
Concrete TechnologyConcrete Technology
Concrete TechnologyLove Sharma
 
Influence of Micro Silica and GGBS on mechanical properties on high strength...
Influence of  Micro Silica and GGBS on mechanical properties on high strength...Influence of  Micro Silica and GGBS on mechanical properties on high strength...
Influence of Micro Silica and GGBS on mechanical properties on high strength...Harish kumar Lekkala
 
IRJET- Experimental Study on Mesh Confined Concrete Subjected to High Tempera...
IRJET- Experimental Study on Mesh Confined Concrete Subjected to High Tempera...IRJET- Experimental Study on Mesh Confined Concrete Subjected to High Tempera...
IRJET- Experimental Study on Mesh Confined Concrete Subjected to High Tempera...IRJET Journal
 
Experimental Study on Concrete with Partial Replacement of Cement with GGBS a...
Experimental Study on Concrete with Partial Replacement of Cement with GGBS a...Experimental Study on Concrete with Partial Replacement of Cement with GGBS a...
Experimental Study on Concrete with Partial Replacement of Cement with GGBS a...IRJET Journal
 
5 Must Know Types of Concrete Testing for Civil Engineers
5 Must Know Types of Concrete Testing for Civil Engineers5 Must Know Types of Concrete Testing for Civil Engineers
5 Must Know Types of Concrete Testing for Civil EngineersSHAZEBALIKHAN1
 
Presentation #BF2 (Blast Furnace #2)
Presentation #BF2 (Blast Furnace #2)Presentation #BF2 (Blast Furnace #2)
Presentation #BF2 (Blast Furnace #2)Dwaipayan Roy
 
selfcompactingconcretescc-160316004923.pptx
selfcompactingconcretescc-160316004923.pptxselfcompactingconcretescc-160316004923.pptx
selfcompactingconcretescc-160316004923.pptxARUNKUMARC39
 
PDL’s Construction Development (Technical) Training Session-I_Structural.pptx
PDL’s Construction Development (Technical) Training Session-I_Structural.pptxPDL’s Construction Development (Technical) Training Session-I_Structural.pptx
PDL’s Construction Development (Technical) Training Session-I_Structural.pptxChristopherThomas578171
 
Special concrete
Special concreteSpecial concrete
Special concreteshruthiv19
 
1.2_Basic Engineering_Day 4.pptx
1.2_Basic Engineering_Day 4.pptx1.2_Basic Engineering_Day 4.pptx
1.2_Basic Engineering_Day 4.pptxJanak82
 
IRJET- Experimental Investigation on Self Compacting Concrete by Replacing Na...
IRJET- Experimental Investigation on Self Compacting Concrete by Replacing Na...IRJET- Experimental Investigation on Self Compacting Concrete by Replacing Na...
IRJET- Experimental Investigation on Self Compacting Concrete by Replacing Na...IRJET Journal
 

Similar to Ntpc summer training 2017 (20)

Self compacting concrete (scc)
Self compacting concrete (scc)Self compacting concrete (scc)
Self compacting concrete (scc)
 
EXPERIMENTAL BEHAVIOUR OF SELF COMPACTING CONCRETE USING GGBS WITH PARTIAL RE...
EXPERIMENTAL BEHAVIOUR OF SELF COMPACTING CONCRETE USING GGBS WITH PARTIAL RE...EXPERIMENTAL BEHAVIOUR OF SELF COMPACTING CONCRETE USING GGBS WITH PARTIAL RE...
EXPERIMENTAL BEHAVIOUR OF SELF COMPACTING CONCRETE USING GGBS WITH PARTIAL RE...
 
Cement.pptx
Cement.pptxCement.pptx
Cement.pptx
 
Cc road summer training ppt @akshay kumar
Cc road summer training ppt @akshay kumarCc road summer training ppt @akshay kumar
Cc road summer training ppt @akshay kumar
 
special concrete and high performance concrete
special concrete and high performance concretespecial concrete and high performance concrete
special concrete and high performance concrete
 
Concrete Technology
Concrete TechnologyConcrete Technology
Concrete Technology
 
Influence of Micro Silica and GGBS on mechanical properties on high strength...
Influence of  Micro Silica and GGBS on mechanical properties on high strength...Influence of  Micro Silica and GGBS on mechanical properties on high strength...
Influence of Micro Silica and GGBS on mechanical properties on high strength...
 
IRJET- Experimental Study on Mesh Confined Concrete Subjected to High Tempera...
IRJET- Experimental Study on Mesh Confined Concrete Subjected to High Tempera...IRJET- Experimental Study on Mesh Confined Concrete Subjected to High Tempera...
IRJET- Experimental Study on Mesh Confined Concrete Subjected to High Tempera...
 
Experimental Study on Concrete with Partial Replacement of Cement with GGBS a...
Experimental Study on Concrete with Partial Replacement of Cement with GGBS a...Experimental Study on Concrete with Partial Replacement of Cement with GGBS a...
Experimental Study on Concrete with Partial Replacement of Cement with GGBS a...
 
5 Must Know Types of Concrete Testing for Civil Engineers
5 Must Know Types of Concrete Testing for Civil Engineers5 Must Know Types of Concrete Testing for Civil Engineers
5 Must Know Types of Concrete Testing for Civil Engineers
 
Topic 2
Topic 2Topic 2
Topic 2
 
Properties of concrete
Properties of concrete Properties of concrete
Properties of concrete
 
Presentation #BF2 (Blast Furnace #2)
Presentation #BF2 (Blast Furnace #2)Presentation #BF2 (Blast Furnace #2)
Presentation #BF2 (Blast Furnace #2)
 
Is 456 codal provisions
Is 456 codal provisionsIs 456 codal provisions
Is 456 codal provisions
 
selfcompactingconcretescc-160316004923.pptx
selfcompactingconcretescc-160316004923.pptxselfcompactingconcretescc-160316004923.pptx
selfcompactingconcretescc-160316004923.pptx
 
PDL’s Construction Development (Technical) Training Session-I_Structural.pptx
PDL’s Construction Development (Technical) Training Session-I_Structural.pptxPDL’s Construction Development (Technical) Training Session-I_Structural.pptx
PDL’s Construction Development (Technical) Training Session-I_Structural.pptx
 
Special concrete
Special concreteSpecial concrete
Special concrete
 
1.2_Basic Engineering_Day 4.pptx
1.2_Basic Engineering_Day 4.pptx1.2_Basic Engineering_Day 4.pptx
1.2_Basic Engineering_Day 4.pptx
 
IRJET- Experimental Investigation on Self Compacting Concrete by Replacing Na...
IRJET- Experimental Investigation on Self Compacting Concrete by Replacing Na...IRJET- Experimental Investigation on Self Compacting Concrete by Replacing Na...
IRJET- Experimental Investigation on Self Compacting Concrete by Replacing Na...
 
Concrete technology
Concrete technologyConcrete technology
Concrete technology
 

Recently uploaded

MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdfankushspencer015
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 

Recently uploaded (20)

MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 

Ntpc summer training 2017

  • 1. NTPC GADARWADA – TRAINING REPORT -Himanshu Rajput B Tech. 2nd year, Dept. of Civil Engg., Indian Institute of technology Kanpur10/6/17
  • 2. OVERVIEW CIVIL WORK Ash dyke Weir Main plant Fabrication Erection Chimney Site leveling & Infrastructure Transportation Flexible pavement Rigid pavement Bridge Site leveling Drain & Diversion drain Pre- engineered structure Boundary Wall Coal Handling Plant Water Treatment Plant Cooling tower Field Quality Assurance Township
  • 3. NTPC GA DA RWA DA LAYOUT `Township Main Plant Ash Dyke Water Reservoir Fabrication yard CT CHP WTP switchyard
  • 4. TESTING TESTING OF CONCRETE 1) Compressive Testing Machine • 1 set cast- 6 cubes, with frequency 50 𝑚3. • Cube size 150*150*150 𝑚𝑚3 • Rate of loading 140kg/𝑐𝑚2 .min • 3 days, 7 days, 28 days CT from the date of casting • 7 days- min. 70% strength 28 days- (Grade)+3
  • 5. 2 Fresh Concrete - Slump Test • Slump is a measurement of concrete's workability, or fluidity. • It's an indirect measurement of concrete consistency or stiffness. • The slump test is used to ensure uniformity for different batches of similar concrete under field conditions and to ascertain the effects of plasticizers on their introduction.
  • 6. Core Cutter – Partially Destructive Test • Diameter of core should be atleast 3 times greater the max nominal size of course aggregate and not less than 2 times of MNS of CA. • Cores to be tested within 7 days of coring. • Cube strength = 1.25 * Cylinder strength • to determine the compressive strength of in-place concrete as per the standards of IS: 456.
  • 7. REBOUND HAMMER- NDT • Surface property test • Harder the surface, greater is the rebound. • Compressive strength
  • 8. CEMENT The OPC cement is available in 3 grades: 33 Grade 43 Grade 53 Grade Ordinary Portland Cement White Cement White Cement and Grey Cement are usually compared on five terms which are as follows: 1. Raw Material: Grey colour of the cement is mainly due to high content of oxides of iron, manganese and chromium which are present in limited amount in white cement. 2. Strength and Setting Time: Its setting behavior and strength development are essentially the same as those expected in grey cement. 3. Fineness: White cement is usually finer than grey cement and thus, gives better finishing. 4. Cost: Due to more complex manufacturing process of white cement, it is expensive than grey cement. In India, white cement is usually around Rs. 20 per kg costlier than grey cement. 5. Uses: White cement due to its whiteness is mainly used for architectural beauty, interior and exterior decorations, floorings, ornamental concrete products such as idols while grey cement is mostly used for construction purposes.
  • 9. Portland Pozzolana Cement is ideally suited for the following construction: + Hydraulic structures. + Mass concreting works. + Marine structures. + Masonry mortars and plastering. + Under aggressive conditions. For PPC cement there is only one grade which gives a minimum compressive strength of 33 MPa after 28 days when mixed with standard sand. Portland Pozollana Cement
  • 10. FST needle Testing of cement Vicat Test • IS 5513,IS 4031- Part 4 & 5 • Initial Setting Time • Final Setting time • Consistency  400 gm cement + water (starting with 32%)  Plunger – Dia= 10∓0.05 mm, Len=50∓1 mm  Depth of Penetration = 5-7mm  Consistency= (Quantity of water for 5-7 mm penetration/Weight of cement) X 100 Standard consistency plungerIST needle
  • 11. Nominal & Design Mix of Concrete Nominal Mix Concrete • The wide use of concrete as construction materials has led to the use of mixes of fixed proportion, which ensures adequate strength. These mixes are called nominal mixes. • They offer simplicity and Under normal circumstances, has margin of strength above that specified. • Nominal mix concrete may be used for concrete of grades M5, M 7.5, M10, M15 and M20. Design Mix Concrete • The concrete mix produced under quality control keeping in view the strength, durability, and workability is called the design Mix. • Others factors like compaction equipment's available, curing method adopted, type of cement, quality of fine and coarse aggregate etc. have to be kept in mind before arriving at the mix proportion. • The design mix or controlled mix is being used more and more in variety of important structures, because of better strength, reduced variability, leaner mixed with consequent economy, as well as greater assurance of the resultant quality.
  • 12. If air content increase slump increase and hence water content is to be decreased If W/C increase water being constant cement decreases hence no of cement fines decreases and we increase sand fines
  • 13. T E S T I N G O F B R I C K S S A M P L I N G Sampling of 10 bricks from a lot Brick making plant
  • 14. 1) Water absorption 2) Compression 3) Warpage 4) Efflorescence Brick Testing
  • 15. TESTING OF SOIL Liquid Limit test (Cassagrande’s Apparatus)  This test is done to determine the liquid limit of soil as per IS: 2720 (Part 5) – 1985.  The liquid limit of fine-grained soil is the water content at which soil behaves practically like a liquid, but has small shear strength.  About 120g of the specimen passing through 425µm IS Sieve is mixed thoroughly with distilled water. Keep it for 24 hrs. in case of clayey soil.  Revolution rate of crank= 2 rev./sec
  • 16. Proctor Test  This method covers the determination of the relationship between the moisture content and density of soils.  Start with 4% then add 2% water each time.  After weighing of proctor take some sample for moisture content.  Wet density gm/cc =weight of compacted soil / 944  Dry density= wet density/(1+w)  Plot MDD vs. OMC graph.
  • 17. Core Cutter Test  This test is done to determine the in-situ dry density of soil by core cutter method as per IS: 2720 (Part XXIX) – 1975.  approximately 30cm square of the soil layer to be tested should be exposed and levelled  Wet density gm/cc =weight of compacted soil / Vol. of core  Dry density= wet density/(1+w)
  • 18. TESTING OF STEEL Bend –Rebend test The reason for using this method is that the content of free nitrogen arises in the steel smelt at high temperatures and when feeding it with nitrogen containing gases. If the content of free nitrogen is too high, it will effect the ductility after cold-working and ageing. Bending Rebending
  • 19. Test piece A test piece of sufficient length is cut or sawn from the bar. If test pieces are taken from welded fabrics they shall not contain any heat affected zones (HAZ). Bending the test piece shall be bent over a mandrel not greater than 10 times dia of test piece. The angle after unloading shall be 90°. The time to complete the bending shall be at least 1 sec. Artificial ageing The bent test piece is artificially aged at +100 °C for two hours (2 h) in still air furnace or half an hour in boiling water followed by free cooling in air, to ambient temperature. As option a temperature of +250 °C for half an hour (0.5 h) can also be used. Rebending The bent and aged test piece shall be rebent. The distance between the support rollers shall allow the rebend to take place within the bent area until the angle after unloading is reduced to less than 70°. Inspection After rebending, no fracture, transverse or oblique cracks visible to the naked eye shall occur on the test piece. TEST PROCEDURE
  • 20. REINFORCEMENT Cold Water ducts ( CW ducts ) Mat – raft
  • 21. Deck sheeting- permanent formwork Steel analyzing Ribs-concrete gripping rings Chair
  • 24. Deep Foundation  Bentonite powder + water is used for flushing  Reqd. density 1.05 gm/𝑐𝑚3 Pile Foundation Bentonite Powder
  • 25. FORMWORK & CURING Formwork ( shuttering ) Curing with Gunny bags
  • 26. ASH DYKE ASH Bottom Ash (20%) Settles down; water is then pumped out Fly Ash (80%) High Concentrated Slurry Ash carrying pipe pedestal + water & to dyke + water Earth Sand Toe drain
  • 27. Ash dyke Layout Ash dyke section Toe drain sand earth Key / Cut- off trench
  • 28. Special features of Cut-off trench :- To avoid piping effect – does not allow the water to seep thru the bottom To provide strength to the whole embankment (similar to shear key in column) To channel the seeped water to the sand embankment.  Use of Bentonite:-  To reduce the permeability of soil and hence make it impervious.  Gives clayey effect to soil and reduce seepage.
  • 29. WEIR Narmada weir A weir is a barrier across the horizontal width of the river that alters the flow characteristics of the water and usually results in a change in the vertical height of the river level. There are many designs of weir, but commonly water flows freely over the top of the weir crest before cascading down to a lower level
  • 30. • Generally ogee shaped weirs are provided for the spillway of a storage dam. • The crest of the ogee weir is slightly rises and falls into parabolic form. • Flow over ogee weir is also similar to flow over rectangular weir. Ogee – Shaped weir
  • 31. MAIN PLANT - FABRICATION Cutting
  • 32. Welding Types of welding:- 1) Arc welding i. Power supply used to create an electric arc b/w electrode and base material. ii. Generally SMAW: uses consumable electrode with coating. iii. GMAW or MIG welding: alongwith the electrode a shielding gas (mixture of Ar & CO2 ) is also fed 2) Gas Welding i. Focused high temperature flame is generated by gas combustion to melt the workpiece and the filler. ii. Most common : Oxy-fuel welding where acetylene is combusted in oxygen. Fabrication rods of two types:- i. E6013 – thin plates (<20mm) ii. E7018 – thick plates (upto 40mm)
  • 33. NDT test for welding Dye Penetration test  Dye Penetrant is a NDT (Non Destructive Testing) method.  kits come in 3 parts, usually in aerosol cans - A cleaner, a penetrant, and a developer. cleaner penetrant developer
  • 34.  Blasting • To remove the first layer mill scales • Cu-Fe grit is used. • 50 : 50 old and new grit. • Safer & more environmental friendly than sand • Swedish comparator is used to check the desired roughness. Blasting Before blasting Cu-Fe grit After blasting
  • 35.  Painting • Within 4-5 hours of blasting. • Primer comes in powder/paste. Mixed with thinner in proper ratio. • Layers of paints i. Zinc Silicate primer (min. 75μ)(blue) ii. Micaceous Iron Oxide (75 μ)( red) (MIO) iii. Finish Coat (75 μ) iv. Final Finish (25 μ)
  • 36. MAIN PLANT - ERECTION Turbo Generator foundation ( TG foundation ) • Foundation for vibrating machines • Earthquake resisting
  • 38. S I T E L E V E L I N G Total station is a theodolite with an Electronic Distance Measurement Device. Total station has also been one of the reasons behind the drastic change of technology in the surveying field. Leveling Survey: This type of survey is used to determine the vertical distances (elevations) and relative heights of points with the help of an instrument known as level level TS theodolite
  • 39. ROADS RIGID PAVEMENT A rigid pavement is constructed from cement concrete or reinforced concrete slabs. Grouted concrete roads are in the category of semi- rigid pavements. The design of rigid pavement is based on providing a structural cement concrete slab of sufficient strength to resists the loads from traffic. The rigid pavement has rigidity and high modulus of elasticity to distribute the load over a relatively wide area of soil. Minor variations in subgrade strength have little influence on the structural capacity of a rigid pavement. In the design of a rigid pavement, the flexural strength of concrete is the major factor and not the strength of subgrade. Due to this property of pavement, when the subgrade deflects beneath the rigid pavement, the concrete slab is able to bridge over the localized failures and areas of inadequate support from subgrade because of slab action. M30 Paving quality concrete (PQC) Dry lean concrete (DLC) Tie bars Jointed plain concrete pavement (JPCP)
  • 40. Dowel Bars (longitudinal) Contraction Joint To prevent cracks in slab due to contraction and expansion crack Rubber lining
  • 41. Flexible pavement ‫ם‬ Seal coat is a thin surface treatment used to water- proof the surface and to provide skid resistance. Tack coat is a very light application of asphalt emulsion diluted with water. And It provides bonding between two layers of binder course. Prime coat is an application of low viscous cutback bitumen to an absorbent surface like granular bases on which binder layer is placed and provides bonding between two layers. Surface course is the layer directly in contact with traffic loads and are constructed with dense graded asphalt concrete. Binder course purpose is to distribute load to the base course. Binder course requires lesser quality of mix as compared to course above it. Base course provides additional load distribution and contributes to the sub-surface drainage. Sub-base course the primary functions are to provide structural support, improve drainage, and reduce the intrusion of fines from the sub-grade in the pavement structure Sub-grade The top soil or sub-grade is a layer of natural soil prepared to receive the stresses from the layers above
  • 42. objectives of providing camber are: Protection of the road surface, especially for gravel and bituminous roads by draining the unwanted water as quickly as possible. Protection of the subgrade by providing good drainage conditions. For safety considerations, as wet pavement conditions are quite undesirable from safe driving point of view.
  • 43. Shakkar river Bridge Top plug Pier / Column Bearing Deck beam Pier cap Post-cast simply supported beam Clam shell machine to dig earth
  • 44. Causeway HTS wires and post-stressed
  • 46. Culvert A culvert is a structure that allows water to flow under a road, railroad, trail, or similar obstruction from one side to the other side. Typically embedded so as to be surrounded by soil, a culvert may be made from a pipe, reinforced concrete or other material Sewer & Man hole Box –type culvert
  • 47. Pre-engineered construction 1. The primary framing structure of a pre-engineered building is an assembly of I-shaped members, often referred as I-beams. In pre-engineered buildings, the I beams used are usually formed by welding together steel plates to form the I section. The I beams are then field-assembled (e.g. bolted connections) to form the entire frame of the pre- engineered building. 2. Pre-Engineered Buildings can be adapted to suit a wide variety of structural applications, the greatest economy will be realized when utilizing standard details. An efficiently designed Pre-Engineered Building can be lighter that the conventional steel buildings by up to 30% RAFTER - a beam forming part of the internal framework of a roof. Metal beam pcc sheeting
  • 48. Boundary wall Retaining wall ( RCC ) Loose soil RCC column Brick masonry ( English bond ) Pre-cast pre-stressed concrete slabs M25
  • 49. Coal Handling Plant ( CHP ) Turning Point (TP) Wagon tippler Not in gadarwada
  • 50. WATER TREATMENT PLANT ( WTP ) Water reservoirSettling tank Salt peter treatment of foundation – for soils containing salts Aerator Bitumen coated
  • 51. COOLING TOWERS 1. The cooling tower is one of the most important device in chemical industries for example when the hot water come from heat exchanger we use the cooling tower to cool it. 2. The purpose of cooling tower is to cool relatively warm water by contacting with unsaturated air. The evaporation of water mainly provides cooling. In a typical water cooling water tower, warm water flows countercurrent to an air stream. 3. Typically, the warm water enters the top of packed tower and cascades down through the packing, leaving at the bottom.
  • 52. Fill – increase surface area for evaporation Made of plastic fill Cold water Cold water channel Wall to control speed of flow
  • 54. 1. Foundation 2. Plinth 3. DPC ( damped proof course) 4. Floor 5. Walls 6. Openings 7. Stairs 8. Roof 9. Surface finish
  • 55. Plinth Min grade M20 Plinth beam A plinth is normally constructed just above the ground level and immediately after the foundation. It raises the floor above the ground level and herewith prevents surface water from entering the building Ground beam
  • 56. Plinth beam advantage- 1.Prevent leaking of water into foundation - To prevent a house from settling it is critical that no water be leaked into foundation. Being made of cement, plinth beam is impervious and therefore prevents water from rain, flooding, etc. from leaking into foundation. 2. Provides support for walls - For load bearing houses, walls carry the weight of the house. Plinth beam provides solid footing to raise those walls. 3. Holds house together - Since plinth beam sits across the periphery of the house, it provides binding force across rooms. For example, without plinth beam it is possible for one of the rooms to settle thus creating uneven floor level. Plinth beam prevents that from happening. Damped Proof Course ( DPC ) min thickness 25mm Damp proof course is a layer of water proofing material such as asphalt or waterproof cement. Walls are constructed above the damp proof course. Damp proof course prevents surface water from rising into the walls. Dampness reduces the strength of the walls and creates unhealthy living conditions. Also it affects the paint and plaster and increasing the cost of maintenance. Damp proofing layer is not required where a plinth beam is constructed, because the plinth beam already performs like a DPC.
  • 57. Back filling & Plinth filling Tempering and rammering of soil Sand filling PCC FILLING MATERIAL FREE FROM LUMPS, ROOTS, VEGETATION, HARMPUL SALTS, ORGANIC MATERIALS ETC. 1 : 3 : 6 c : fa : ca
  • 58. TYPES OF FLOORING •CARPETS AND RUGS •VINYL FLOORING Vinyl composition tile (VCT) is a finished flooring material used primarily in commercial and institutional applications. Types of tiles- a) Vitrified tiles - Vitrified tiles are ceramic tiles with high percentage of vitrification and less amount of water absorption. Vitrification is nothing but a development of glass phase inside the tile during firing process. b) Ceramic tiles- High wear resistance with low density. c) Porcelain tiles •GLASS FLOORING Glass floors are made with transparent glass when it is useful to view something from above or below; whereas translucent glass is used when there is no need to view through.
  • 59. •WOODEN FLOORING This type of flooring is generally use for special purpose floor example auditorium, hospital etc. •STONE FLOORING Marble- •Costliest and best marble is the Makrana white •White base marble price ranges from Rs.30/- to Rs.400/- sq. ft. Granite - Hardest type of stone- very difficult to cut and polish Slate - Resistant to wearing, discoloring or fading Kotah & Sandstone - used as hard flooring suited for pathways, factory sheds, offices and other common spaces. •BRICK FLOORING White marble granite Kotah Stone
  • 60. Walls & Openings English bond a bond used in brickwork consisting of alternate courses of stretchers and headers. column Brick work OPENINGS Openings are normally provided in the walls as door, windows and ventilators. Doors provide access; windows and ventilators provide light and ventilation. Lintels are constructed just above the openings. It is normally a stone slab or a concrete slab. Sill is the part of the wall that is just below the window. Lintels are constructed to hold up the walls above the openings. In earthquake prone areas a continuous lintel beam is provided all over the walls. jamb soffit
  • 61. Testing of Wood Teak wood for door frames in Guest house Digital Moisture meter – value should not be greater than 12%
  • 63. ROOF A flat roof is not truly flat but angled slightly to allow for water runoff. It is the cheapest to build initially but will cost you much more than other roof types in maintenance costs. M30- water retaining structure on roof
  • 64. Surface finish Wet finishes Plaster Paint Wallpaper One of the major problems with wet finishes is that considerable “drying out time” is required for the building plus expansion shrinkage problems with timber components. Dry finishes Plaster board Timber panelling Carpet The greatest advantage of dry finishes when compared to wet finishes is that no shrinkage will occur during the dry out process Internal Plastering one or two coats of sand and cement with a finish coat of gypsum plaster on brick or block walls Mortar plaster Mortar plaster Gypsum plaster Plaster grooves-prevent cracks1: 6 wall 1: 3 ceiling
  • 65. Paint finish objectives of painting are:- Preservation appearance hygiene A painting system for a given material usually consists of:- Paint Primer Adheres well to the background and evens out the surface porosity. With ferrous metals, controls rust. Care must be taken to choose suitable primer for the material to be covered. Undercoat Adheres to the primer, builds up the paint thickness and obliterates surface irregularities. The undercoat should bring the surface to a suitable colour for receiving the finishing coat. Two coats of undercoat are usually required. Finish Adheres to the undercoat and provides a protective layer, colour and surface texture.
  • 66. Important site machines & tools Excavator / power shovel Concrete pump Batching Plant
  • 67. Bull Dozer Back Hoe Spreading earth and clearing landfills Pneumatic type roller Smooth type roller Drag line In wet soils Hard rock below working surface
  • 68. Hoe trowel Measuring tape Plumb Bob Wheel barrow Float Line level DrillJack planePolisherPutty Knife
  • 69. CONCLUSION Overall, I had a fantastic experience while training with the engineers of NTPC and JMC. I feel extremely fortunate to be a part of the Maharatna company of India for a month. This summer training helped me grow a lot and get a deeper look into the construction field. The summer training program in NTPC is unique because of more exposure we get in the company. !!! THANKYOU !!!