Slide Sets to © 2005 by McGraw-Hill,18-1
Developed By:
Dr. Don Smith, P.E.
Department of Industrial
Engineering
Texas A&M University
College Station, Texas
Executive Summary Version
Chapter 18
Formalized Sensitivity
Analysis and
Expected Value
Decisions
Slide Sets to © 2005 by McGraw-Hill,18-2
LEARNING OBJECTIVESLEARNING OBJECTIVES
1. Sensitivity to
variation
2. Three estimates
3. Expected value
4. Expected value
of cash flows
5. Decision trees
Slide Sets to © 2005 by McGraw-Hill,18-3
Sct 18.1 Determining Sensitivity toSct 18.1 Determining Sensitivity to
Parameter VariationParameter Variation
A parameter is a variable or factor for which an
estimate or stated value is required to conduct the
analysis at hand.
 Examples:
 P, F, A;
 i, n;
 Future costs, salvages, etc.
 Sensitivity analysis
 Seeks to determine what parameters matter most in an
economic analysis
Slide Sets to © 2005 by McGraw-Hill,18-4
SensitivitySensitivity
 Sensitivity is concerned with variability
 Variance associated with input parameters
impact the output variable the most
 The MARR as a parameter
 Interest rates and other interest factors tend to be
more stable from project to project
The analyst can limit the range over which these
type of parameters vary
Slide Sets to © 2005 by McGraw-Hill,18-5
Visualizing the Impact of ParametersVisualizing the Impact of Parameters
 Plot the PW, AW, or ROR vs. input parameters
 Steps
Pre-select the desired input parameters
Select the probable range and increment of
variation for each parameter
Select the measure of worth
Compute the results for each parameter
Graphically display the results by plotting the
parameter vs. the measure of worth
Slide Sets to © 2005 by McGraw-Hill,18-6
ExampleExample
Low High
$PW
Parameter
Assume a parameter of interest (show on the X-axis). Vary that parameter from some low
value to an assumed high value. Plot the resultant values on the Y-axis.
Slide Sets to © 2005 by McGraw-Hill,18-7
Sensitivity of PW: Example 18.1Sensitivity of PW: Example 18.1
Year Cflow
0 -$80,000
1 $25,000
2 $23,000
3 $21,000
4 $19,000
5 $17,000
6 $15,000
7 $13,000
8 $11,000
9 $9,000
10 $7,000
MARR PW(i%)
10% $27,831.49
15% $11,510.26
20% -$962.36
25% -$10,711.51
Ex. 18.1 PW vs. MARR
-$15,000.00
-$10,000.00
-$5,000.00
$0.00
$5,000.00
$10,000.00
$15,000.00
$20,000.00
$25,000.00
$30,000.00
0% 10% 20% 30%
MARR
$-PW
One can better visualize the relationship on PW vs. a
selected range of discount rates. As the discount
rate increases from 10% to 25% the resultant PW is
substantially lowered at a rather accelerated rate.
Slide Sets to © 2005 by McGraw-Hill,18-8
Sensitivity of Several ParametersSensitivity of Several Parameters
 For several parameters with one alternative
Graph the percentage change for each parameter
vs. the measure of worth
One will plot the percent deviation from the most
likely estimate on the x-axis
 This type of plot results in what is termed a
spider plot
Slide Sets to © 2005 by McGraw-Hill,18-9
Spider Plot: Figure 18-3Spider Plot: Figure 18-3
Those plots with positive slope have a
positive correlation on the output variable:
Those plots with negative slope have a
inverse relationship with the output
variable
Slide Sets to © 2005 by McGraw-Hill,18-10
Sct 18.2 Formalized Sensitivity AnalysisSct 18.2 Formalized Sensitivity Analysis
Using Three EstimatesUsing Three Estimates
 Given an input parameter of interest
Provide three estimates for that parameter
 A pessimistic estimate, P
 A most likely estimate, ML
 An optimistic estimate, O
 Note: This approach comes from PERT/CPM
analysis and is based upon the beta
distribution
Slide Sets to © 2005 by McGraw-Hill,18-11
Three Estimates: Example 18.3Three Estimates: Example 18.3
 Three alternatives (A, B, C) with 4 Parameters
First cost, salvage value, AOC, and life
For each parameter we formulate
Parameter
P pessimistic estimate
ML most likely estimate
O optimistic estimate
See Table 18.2 and observe the dominance by
alternative B (cost problem so lower cost is preferred)
Slide Sets to © 2005 by McGraw-Hill,18-12
Example 18.3 -- SetupExample 18.3 -- Setup
Strategy First Cost SV AOC Life
Alt A.
P -20,000 0 -11,000 3
ML -20,000 0 -9,000 5
O -20,000 0 -5,000 8
Alt. B
P -15,000 500 -4,000 2
ML -15,000 1,000 -3,500 4
O -15,000 2,000 -2,000 7
Alt. C
P -30,000 3,000 -8,000 3
ML -30,000 3,000 -7,000 7
O -30,000 3,000 -3,500 9
Slide Sets to © 2005 by McGraw-Hill,18-13
Plot for Example 18.3Plot for Example 18.3
Ex. 18.3
$0
$5,000
$10,000
$15,000
$20,000
$25,000
1 2 3 4 5 6 7 8 9
Life - Years
A.Cost
Alt A
Alt B
Alt C
Observe the
dominance by
alternative B over A
and C. A plot like this
clearly shows the
relationships.
Slide Sets to © 2005 by McGraw-Hill,18-14
Sct 18.3 Economic Variability and TheSct 18.3 Economic Variability and The
Expected ValueExpected Value
 Expected Value
Long-run average based upon occurrence and
probability of occurrence
 Definition of Expected Value
1
( ) ( )
m
i i
i
E X X P X
=
= ∑
Xi = value of the variable X for i from 1 to m different values
P(Xi) = probability that a specific value of X will occur
Subject to:
1
( ) 1.0
m
i
i
P X
=
=∑ See Example 18.4
Slide Sets to © 2005 by McGraw-Hill,18-15
Sct 18.4 Expected Value Computations forSct 18.4 Expected Value Computations for
AlternativesAlternatives
 Two applications for use of Expected Value
(EV)
1. Prepare information for a more complete analysis
of an economic analysis
2. To evaluate expected utility of a fully formulated
alternative
 Examples 18.5 and 18.6 illustrate this
concept
Slide Sets to © 2005 by McGraw-Hill,18-16
Sect 18.5 Staged Evaluation ofSect 18.5 Staged Evaluation of
Alternatives Using Decision TreesAlternatives Using Decision Trees
 Some problems involve staged decisions that
occur in sequence
 Define the staged decisions and assign the
respective probabilities to the various defined
outcomes
 Useful tool for modeling such a process
involves Decision Trees
 The objective: Make Risk More Explicit
Slide Sets to © 2005 by McGraw-Hill,18-17
Decision Tree AttributesDecision Tree Attributes
 More than one stage of alternative selection
 Selection of an alternative at one stage that
leads to another stage
 Expected results from a decision at each
stage
 Probability estimates for each outcome
 Estimates of economic value (cost or
revenue) for each outcome
 Measure of worth as the selection criterion,
e.g. E(PW)
Slide Sets to © 2005 by McGraw-Hill,18-18
ExamplesExamples
60.0% 0
0 500000
FALSE Chance
500000 500000
40.0% 0
0 500000
Decision
1000000
30.0% 0.3
0 1000000
TRUE Chance
1000000 1000000
60.0% 0.6
0 1000000
10.0% 0.1
0 1000000
Example Tree
Lease
Buy
Good Outcome
Bad Outcome
Good Outcome
Really Bad Outcome
Fair Outcome
Decision
Node
Probability
Node
Marginal
Probabilities
Outcomes
Slide Sets to © 2005 by McGraw-Hill,18-19
Solving Decision TreesSolving Decision Trees
 Once designed, Decision Tree is solved by folding
back the tree
 First, define all of the decision and the decision
points
 Define the various outcomes given the decision
 Assign the probabilities to the mutually exclusive
outcomes emanating from each decision node
 See Example 18-8 for a comprehensive analysis
illustrating the decision tree approach
Slide Sets to © 2005 by McGraw-Hill,18-20
Important Points for Decision TreesImportant Points for Decision Trees
 Estimate the probabilities associated with
each outcome
 These probabilities must sum to 1 for each set
of outcomes (branches) that are possible from
a given decision
 Required economic information for each
decision alternative are investments and
estimated cash flows
Slide Sets to © 2005 by McGraw-Hill,18-21
Starting OutStarting Out
 Assuming the tree logic has been defined…
 Start at the top right of the tree
Determine the PW for each outcome branch
applying the time value of money
Calculate the expected value for each decision
alternative as:
At each decision node, select the best E( decision )
value
Continue moving to the left of the tree back to the
root in order to select the best alternative
Trace the best decision path back through the tree
( ) ( estimate)P(outcome)E decision outcome= ∑
Slide Sets to © 2005 by McGraw-Hill,18-22
Example 18.8Example 18.8
D 1
M a r k e t
S e ll
D 2
D 3
H ig h
L o w
9
1 4
1 4
0 .2
0 .5
0 .5
1 2
1 6
4
6
- 1
0 . 8
0 .2
0 .4
0 .4
0 .2
0 .8
0 .2
0 .4
0 .4
0 .2
- 3
- 3
6
- 2
2
P W o f
C F B T
( $ m i ll i o n )
1 .0 9
E x p e c t e d v a l u e s f o r e a c h
a lt e r n a t i v e ( c a l c u la t e d )
I n t .
N a t .
I n t .
N a t .
2
4 .2
4 .2
9
Slide Sets to © 2005 by McGraw-Hill,18-23
Chapter SummaryChapter Summary
The emphasis is on sensitivity to variation in one or more
parameters using a specific measure of worth.
 When two alternatives are compared compute and graph
the measure of worth for different values of the parameter
to determine when each alternative is better.
 When several parameters are expected to vary over a
predictable range, the measure of worth is plotted and
calculated using three estimates for a parameter:
 Most likely
 Pessimistic
 Optimistic
Slide Sets to © 2005 by McGraw-Hill,18-24
Summary - continuedSummary - continued
The combination of parameter and probability
estimates results in the expected value relations
E(X) = ∑(X)P(X)
This expression is also used to calculate
E(revenue), E(cost), E(cash flow) E(PW), and E(i)
for the entire cash flow sequence of an alternative.
 E9X0 is a measure of central tendency
Slide Sets to © 2005 by McGraw-Hill,18-25
Summary - continuedSummary - continued
 Decision trees are used to make a series of alternative
selections.
This is a way to explicitly take risk into account.
 It is necessary to make several types of estimates for a
decision tree:
 Outcomes for each possible decision, cash flows, and
probabilities.
 Expected value computations are coupled with those for the
measure of worth to “solve” the tree structure.
 Assist is identifying the best alternative stage-by-stage.
Slide Sets to © 2005 by McGraw-Hill,18-26
Chapter 18Chapter 18
End of SetEnd of Set

Contenu connexe

Tendances

Chapter 18 sensitivity analysis
Chapter 18   sensitivity analysisChapter 18   sensitivity analysis
Chapter 18 sensitivity analysisBich Lien Pham
 
Chapter 6&7 annual worth analysis & ror lo3b
Chapter 6&7  annual worth analysis & ror   lo3bChapter 6&7  annual worth analysis & ror   lo3b
Chapter 6&7 annual worth analysis & ror lo3bAbdulaziz AlSuwaidi
 
Chapter 11 replacement & retention decisions
Chapter 11   replacement & retention decisionsChapter 11   replacement & retention decisions
Chapter 11 replacement & retention decisionsBich Lien Pham
 
Chapter 6 annual worth analysis
Chapter 6   annual worth analysisChapter 6   annual worth analysis
Chapter 6 annual worth analysisBich Lien Pham
 
Chapter 5 present worth analysis
Chapter 5   present worth analysisChapter 5   present worth analysis
Chapter 5 present worth analysisBich Lien Pham
 
Chapter 3 combining factors
Chapter 3   combining factorsChapter 3   combining factors
Chapter 3 combining factorsBich Lien Pham
 
Chapter 13 breakeven analysis
Chapter 13   breakeven analysisChapter 13   breakeven analysis
Chapter 13 breakeven analysisBich Lien Pham
 
Chapter 17 after-tax economic analysis
Chapter 17   after-tax economic analysisChapter 17   after-tax economic analysis
Chapter 17 after-tax economic analysisBich Lien Pham
 
9. benefit cost analysis
9. benefit cost analysis9. benefit cost analysis
9. benefit cost analysisMohsin Siddique
 
Chapter 7 ror analysis for a single alternative
Chapter 7   ror analysis for a single alternativeChapter 7   ror analysis for a single alternative
Chapter 7 ror analysis for a single alternativeBich Lien Pham
 
Chapter 2 factors, effect of time & interest on money
Chapter 2   factors, effect of time & interest on moneyChapter 2   factors, effect of time & interest on money
Chapter 2 factors, effect of time & interest on moneyBich Lien Pham
 
Chapter 1 foundations of engineering economy
Chapter 1   foundations of engineering economyChapter 1   foundations of engineering economy
Chapter 1 foundations of engineering economyBich Lien Pham
 
Chapter 5 present worth analysis -with examples
Chapter 5   present worth analysis -with examplesChapter 5   present worth analysis -with examples
Chapter 5 present worth analysis -with examplesAbdulaziz AlSuwaidi
 
Comparison and selection among alternatives
Comparison and selection among alternativesComparison and selection among alternatives
Comparison and selection among alternativesNafis Ahmad
 
Chapter 4 nominal & effective interest rates
Chapter 4   nominal & effective interest ratesChapter 4   nominal & effective interest rates
Chapter 4 nominal & effective interest ratesBich Lien Pham
 
Lecture # 4 gradients factors and nominal and effective interest rates
Lecture # 4 gradients factors and nominal and effective interest ratesLecture # 4 gradients factors and nominal and effective interest rates
Lecture # 4 gradients factors and nominal and effective interest ratesBich Lien Pham
 
Cash Flow - Unit III Engineering Economics - MG6863
Cash Flow - Unit III Engineering Economics - MG6863Cash Flow - Unit III Engineering Economics - MG6863
Cash Flow - Unit III Engineering Economics - MG6863Balamurugan Subburaj
 
8. Rate of return analysis
8. Rate of return analysis8. Rate of return analysis
8. Rate of return analysisMohsin Siddique
 
Benefit-Cost (B-C) ratio analysis
Benefit-Cost (B-C) ratio analysisBenefit-Cost (B-C) ratio analysis
Benefit-Cost (B-C) ratio analysisNafis Ahmad
 

Tendances (20)

Chapter 18 sensitivity analysis
Chapter 18   sensitivity analysisChapter 18   sensitivity analysis
Chapter 18 sensitivity analysis
 
Chapter 6&7 annual worth analysis & ror lo3b
Chapter 6&7  annual worth analysis & ror   lo3bChapter 6&7  annual worth analysis & ror   lo3b
Chapter 6&7 annual worth analysis & ror lo3b
 
Chapter 11 replacement & retention decisions
Chapter 11   replacement & retention decisionsChapter 11   replacement & retention decisions
Chapter 11 replacement & retention decisions
 
Chapter 6 annual worth analysis
Chapter 6   annual worth analysisChapter 6   annual worth analysis
Chapter 6 annual worth analysis
 
Chapter 5 present worth analysis
Chapter 5   present worth analysisChapter 5   present worth analysis
Chapter 5 present worth analysis
 
Chapter 3 combining factors
Chapter 3   combining factorsChapter 3   combining factors
Chapter 3 combining factors
 
Chapter 13 breakeven analysis
Chapter 13   breakeven analysisChapter 13   breakeven analysis
Chapter 13 breakeven analysis
 
Chapter 17 after-tax economic analysis
Chapter 17   after-tax economic analysisChapter 17   after-tax economic analysis
Chapter 17 after-tax economic analysis
 
9. benefit cost analysis
9. benefit cost analysis9. benefit cost analysis
9. benefit cost analysis
 
Chapter 7 ror analysis for a single alternative
Chapter 7   ror analysis for a single alternativeChapter 7   ror analysis for a single alternative
Chapter 7 ror analysis for a single alternative
 
Chapter 2 factors, effect of time & interest on money
Chapter 2   factors, effect of time & interest on moneyChapter 2   factors, effect of time & interest on money
Chapter 2 factors, effect of time & interest on money
 
Chapter 1 foundations of engineering economy
Chapter 1   foundations of engineering economyChapter 1   foundations of engineering economy
Chapter 1 foundations of engineering economy
 
Chapter 5 present worth analysis -with examples
Chapter 5   present worth analysis -with examplesChapter 5   present worth analysis -with examples
Chapter 5 present worth analysis -with examples
 
Comparison and selection among alternatives
Comparison and selection among alternativesComparison and selection among alternatives
Comparison and selection among alternatives
 
Chapter 4 nominal & effective interest rates
Chapter 4   nominal & effective interest ratesChapter 4   nominal & effective interest rates
Chapter 4 nominal & effective interest rates
 
Lecture # 4 gradients factors and nominal and effective interest rates
Lecture # 4 gradients factors and nominal and effective interest ratesLecture # 4 gradients factors and nominal and effective interest rates
Lecture # 4 gradients factors and nominal and effective interest rates
 
Cash Flow - Unit III Engineering Economics - MG6863
Cash Flow - Unit III Engineering Economics - MG6863Cash Flow - Unit III Engineering Economics - MG6863
Cash Flow - Unit III Engineering Economics - MG6863
 
Engineering Economy
Engineering EconomyEngineering Economy
Engineering Economy
 
8. Rate of return analysis
8. Rate of return analysis8. Rate of return analysis
8. Rate of return analysis
 
Benefit-Cost (B-C) ratio analysis
Benefit-Cost (B-C) ratio analysisBenefit-Cost (B-C) ratio analysis
Benefit-Cost (B-C) ratio analysis
 

En vedette

Lecture # 8 depreciation ii
Lecture # 8 depreciation iiLecture # 8 depreciation ii
Lecture # 8 depreciation iiBich Lien Pham
 
Chapter 19 decision-making under risk
Chapter 19   decision-making under riskChapter 19   decision-making under risk
Chapter 19 decision-making under riskBich Lien Pham
 
Lecture # 13 investment alternatives i
Lecture # 13 investment alternatives iLecture # 13 investment alternatives i
Lecture # 13 investment alternatives iBich Lien Pham
 
Lecture # 12 measures of profitability ii
Lecture # 12 measures of profitability iiLecture # 12 measures of profitability ii
Lecture # 12 measures of profitability iiBich Lien Pham
 
Lecture # 4 gradients factors and nominal and effective interest rates
Lecture # 4 gradients factors and nominal and effective interest ratesLecture # 4 gradients factors and nominal and effective interest rates
Lecture # 4 gradients factors and nominal and effective interest ratesBich Lien Pham
 
Lecture # 1 foundation
Lecture # 1 foundationLecture # 1 foundation
Lecture # 1 foundationBich Lien Pham
 
Lecture # 2 time value of money
Lecture # 2 time value of moneyLecture # 2 time value of money
Lecture # 2 time value of moneyBich Lien Pham
 
Lecture # 5 cost estimation i
Lecture # 5 cost estimation iLecture # 5 cost estimation i
Lecture # 5 cost estimation iBich Lien Pham
 
Lecture # 2 time value of money
Lecture # 2 time value of moneyLecture # 2 time value of money
Lecture # 2 time value of moneyBich Lien Pham
 
Lecture # 11 measures of profitability i
Lecture # 11 measures of profitability iLecture # 11 measures of profitability i
Lecture # 11 measures of profitability iBich Lien Pham
 
Lecture # 10 eva and disposal of assets
Lecture # 10 eva and disposal of assetsLecture # 10 eva and disposal of assets
Lecture # 10 eva and disposal of assetsBich Lien Pham
 
Chapter 16 depreciation methods
Chapter 16   depreciation methodsChapter 16   depreciation methods
Chapter 16 depreciation methodsBich Lien Pham
 
Lecture # 6 cost estimation ii
Lecture # 6 cost estimation iiLecture # 6 cost estimation ii
Lecture # 6 cost estimation iiBich Lien Pham
 
Lecture # 5 cost estimation i
Lecture # 5 cost estimation iLecture # 5 cost estimation i
Lecture # 5 cost estimation iBich Lien Pham
 
Lecture # 3 compounding factors effects of inflation
Lecture # 3 compounding factors   effects of inflationLecture # 3 compounding factors   effects of inflation
Lecture # 3 compounding factors effects of inflationBich Lien Pham
 
Chapter 13 breakeven analysis
Chapter 13   breakeven analysisChapter 13   breakeven analysis
Chapter 13 breakeven analysisBich Lien Pham
 
Chapter 17 after-tax economic analysis
Chapter 17   after-tax economic analysisChapter 17   after-tax economic analysis
Chapter 17 after-tax economic analysisBich Lien Pham
 
Lecture # 3 compounding factors effects of inflation
Lecture # 3 compounding factors   effects of inflationLecture # 3 compounding factors   effects of inflation
Lecture # 3 compounding factors effects of inflationBich Lien Pham
 
Chapter 7 capital cost estimation
Chapter 7 capital cost estimationChapter 7 capital cost estimation
Chapter 7 capital cost estimationjose2424
 
Lecture # 7 depreciation i
Lecture # 7 depreciation iLecture # 7 depreciation i
Lecture # 7 depreciation iBich Lien Pham
 

En vedette (20)

Lecture # 8 depreciation ii
Lecture # 8 depreciation iiLecture # 8 depreciation ii
Lecture # 8 depreciation ii
 
Chapter 19 decision-making under risk
Chapter 19   decision-making under riskChapter 19   decision-making under risk
Chapter 19 decision-making under risk
 
Lecture # 13 investment alternatives i
Lecture # 13 investment alternatives iLecture # 13 investment alternatives i
Lecture # 13 investment alternatives i
 
Lecture # 12 measures of profitability ii
Lecture # 12 measures of profitability iiLecture # 12 measures of profitability ii
Lecture # 12 measures of profitability ii
 
Lecture # 4 gradients factors and nominal and effective interest rates
Lecture # 4 gradients factors and nominal and effective interest ratesLecture # 4 gradients factors and nominal and effective interest rates
Lecture # 4 gradients factors and nominal and effective interest rates
 
Lecture # 1 foundation
Lecture # 1 foundationLecture # 1 foundation
Lecture # 1 foundation
 
Lecture # 2 time value of money
Lecture # 2 time value of moneyLecture # 2 time value of money
Lecture # 2 time value of money
 
Lecture # 5 cost estimation i
Lecture # 5 cost estimation iLecture # 5 cost estimation i
Lecture # 5 cost estimation i
 
Lecture # 2 time value of money
Lecture # 2 time value of moneyLecture # 2 time value of money
Lecture # 2 time value of money
 
Lecture # 11 measures of profitability i
Lecture # 11 measures of profitability iLecture # 11 measures of profitability i
Lecture # 11 measures of profitability i
 
Lecture # 10 eva and disposal of assets
Lecture # 10 eva and disposal of assetsLecture # 10 eva and disposal of assets
Lecture # 10 eva and disposal of assets
 
Chapter 16 depreciation methods
Chapter 16   depreciation methodsChapter 16   depreciation methods
Chapter 16 depreciation methods
 
Lecture # 6 cost estimation ii
Lecture # 6 cost estimation iiLecture # 6 cost estimation ii
Lecture # 6 cost estimation ii
 
Lecture # 5 cost estimation i
Lecture # 5 cost estimation iLecture # 5 cost estimation i
Lecture # 5 cost estimation i
 
Lecture # 3 compounding factors effects of inflation
Lecture # 3 compounding factors   effects of inflationLecture # 3 compounding factors   effects of inflation
Lecture # 3 compounding factors effects of inflation
 
Chapter 13 breakeven analysis
Chapter 13   breakeven analysisChapter 13   breakeven analysis
Chapter 13 breakeven analysis
 
Chapter 17 after-tax economic analysis
Chapter 17   after-tax economic analysisChapter 17   after-tax economic analysis
Chapter 17 after-tax economic analysis
 
Lecture # 3 compounding factors effects of inflation
Lecture # 3 compounding factors   effects of inflationLecture # 3 compounding factors   effects of inflation
Lecture # 3 compounding factors effects of inflation
 
Chapter 7 capital cost estimation
Chapter 7 capital cost estimationChapter 7 capital cost estimation
Chapter 7 capital cost estimation
 
Lecture # 7 depreciation i
Lecture # 7 depreciation iLecture # 7 depreciation i
Lecture # 7 depreciation i
 

Similaire à Chapter 18 sensitivity analysis

Operations Management VTU BE Mechanical 2015 Solved paper
Operations Management VTU BE Mechanical 2015 Solved paperOperations Management VTU BE Mechanical 2015 Solved paper
Operations Management VTU BE Mechanical 2015 Solved paperSomashekar S.M
 
An Empirical Investigation Of The Arbitrage Pricing Theory
An Empirical Investigation Of The Arbitrage Pricing TheoryAn Empirical Investigation Of The Arbitrage Pricing Theory
An Empirical Investigation Of The Arbitrage Pricing TheoryAkhil Goyal
 
L. E. Peabody & Associates, Inc. - Power Plant Financial Risk Assessment
L. E. Peabody & Associates, Inc. - Power Plant Financial Risk AssessmentL. E. Peabody & Associates, Inc. - Power Plant Financial Risk Assessment
L. E. Peabody & Associates, Inc. - Power Plant Financial Risk AssessmentBrian Despard
 
Risk-Analysis.pdf
Risk-Analysis.pdfRisk-Analysis.pdf
Risk-Analysis.pdfMaheshBika
 
Chapter 19 decision-making under risk
Chapter 19   decision-making under riskChapter 19   decision-making under risk
Chapter 19 decision-making under riskBich Lien Pham
 
project planning demand Estimation II.pptx
project planning demand Estimation  II.pptxproject planning demand Estimation  II.pptx
project planning demand Estimation II.pptxtadegebreyesus
 
Managerial%20Economics.pptx
Managerial%20Economics.pptxManagerial%20Economics.pptx
Managerial%20Economics.pptxKomalSingh818576
 
Pricing and hedging GDP-linked bonds in incomplete markets
Pricing and hedging GDP-linked bonds in incomplete marketsPricing and hedging GDP-linked bonds in incomplete markets
Pricing and hedging GDP-linked bonds in incomplete marketsStavros A. Zenios
 
Risk Concept And Management 5
Risk Concept And Management 5Risk Concept And Management 5
Risk Concept And Management 5rajeevgupta
 
Increasing Capital Budgeting Insight Using Monte Carlo Simulation / War Gamin...
Increasing Capital Budgeting Insight Using Monte Carlo Simulation / War Gamin...Increasing Capital Budgeting Insight Using Monte Carlo Simulation / War Gamin...
Increasing Capital Budgeting Insight Using Monte Carlo Simulation / War Gamin...robertmckinney
 
Forecasting Methodology Used in Restructured Electricity Market: A Review
Forecasting Methodology Used in Restructured Electricity Market: A ReviewForecasting Methodology Used in Restructured Electricity Market: A Review
Forecasting Methodology Used in Restructured Electricity Market: A ReviewDr. Sudhir Kumar Srivastava
 
Affine Term Structure Model with Stochastic Market Price of Risk
Affine Term Structure Model with Stochastic Market Price of RiskAffine Term Structure Model with Stochastic Market Price of Risk
Affine Term Structure Model with Stochastic Market Price of RiskSwati Mital
 

Similaire à Chapter 18 sensitivity analysis (20)

APT_&_VaR[1]
APT_&_VaR[1]APT_&_VaR[1]
APT_&_VaR[1]
 
Operations Management VTU BE Mechanical 2015 Solved paper
Operations Management VTU BE Mechanical 2015 Solved paperOperations Management VTU BE Mechanical 2015 Solved paper
Operations Management VTU BE Mechanical 2015 Solved paper
 
Lo4b (nabil) breakeven analysis
Lo4b (nabil)   breakeven analysisLo4b (nabil)   breakeven analysis
Lo4b (nabil) breakeven analysis
 
Lo4b(arif)
Lo4b(arif)Lo4b(arif)
Lo4b(arif)
 
An Empirical Investigation Of The Arbitrage Pricing Theory
An Empirical Investigation Of The Arbitrage Pricing TheoryAn Empirical Investigation Of The Arbitrage Pricing Theory
An Empirical Investigation Of The Arbitrage Pricing Theory
 
L. E. Peabody & Associates, Inc. - Power Plant Financial Risk Assessment
L. E. Peabody & Associates, Inc. - Power Plant Financial Risk AssessmentL. E. Peabody & Associates, Inc. - Power Plant Financial Risk Assessment
L. E. Peabody & Associates, Inc. - Power Plant Financial Risk Assessment
 
Risk-Analysis.pdf
Risk-Analysis.pdfRisk-Analysis.pdf
Risk-Analysis.pdf
 
Acc102 chap18 publisher_power_point
Acc102  chap18 publisher_power_pointAcc102  chap18 publisher_power_point
Acc102 chap18 publisher_power_point
 
Chapter 19 decision-making under risk
Chapter 19   decision-making under riskChapter 19   decision-making under risk
Chapter 19 decision-making under risk
 
project planning demand Estimation II.pptx
project planning demand Estimation  II.pptxproject planning demand Estimation  II.pptx
project planning demand Estimation II.pptx
 
12834316.ppt
12834316.ppt12834316.ppt
12834316.ppt
 
Managerial%20Economics.pptx
Managerial%20Economics.pptxManagerial%20Economics.pptx
Managerial%20Economics.pptx
 
Pricing and hedging GDP-linked bonds in incomplete markets
Pricing and hedging GDP-linked bonds in incomplete marketsPricing and hedging GDP-linked bonds in incomplete markets
Pricing and hedging GDP-linked bonds in incomplete markets
 
IEEE2011
IEEE2011IEEE2011
IEEE2011
 
Risk Concept And Management 5
Risk Concept And Management 5Risk Concept And Management 5
Risk Concept And Management 5
 
Increasing Capital Budgeting Insight Using Monte Carlo Simulation / War Gamin...
Increasing Capital Budgeting Insight Using Monte Carlo Simulation / War Gamin...Increasing Capital Budgeting Insight Using Monte Carlo Simulation / War Gamin...
Increasing Capital Budgeting Insight Using Monte Carlo Simulation / War Gamin...
 
Forecasting Methodology Used in Restructured Electricity Market: A Review
Forecasting Methodology Used in Restructured Electricity Market: A ReviewForecasting Methodology Used in Restructured Electricity Market: A Review
Forecasting Methodology Used in Restructured Electricity Market: A Review
 
Demand Estimation
Demand EstimationDemand Estimation
Demand Estimation
 
Dividends and Stock Prices
Dividends and Stock Prices Dividends and Stock Prices
Dividends and Stock Prices
 
Affine Term Structure Model with Stochastic Market Price of Risk
Affine Term Structure Model with Stochastic Market Price of RiskAffine Term Structure Model with Stochastic Market Price of Risk
Affine Term Structure Model with Stochastic Market Price of Risk
 

Plus de Bich Lien Pham

Lecture # 9 taxes and eva
Lecture # 9 taxes and evaLecture # 9 taxes and eva
Lecture # 9 taxes and evaBich Lien Pham
 
Chapter 14 effects of inflation
Chapter 14   effects of inflationChapter 14   effects of inflation
Chapter 14 effects of inflationBich Lien Pham
 
Chapter 12 independent projects & budget limitation
Chapter 12   independent projects & budget limitationChapter 12   independent projects & budget limitation
Chapter 12 independent projects & budget limitationBich Lien Pham
 
Chapter 10 making choices & marr
Chapter 10   making choices & marrChapter 10   making choices & marr
Chapter 10 making choices & marrBich Lien Pham
 
Chapter 9 benefit & cost analysis
Chapter 9   benefit & cost analysisChapter 9   benefit & cost analysis
Chapter 9 benefit & cost analysisBich Lien Pham
 
Chapter 8 ror analysis for multiple alternatives
Chapter 8   ror analysis for multiple alternativesChapter 8   ror analysis for multiple alternatives
Chapter 8 ror analysis for multiple alternativesBich Lien Pham
 
Chapter 6 annual worth analysis
Chapter 6   annual worth analysisChapter 6   annual worth analysis
Chapter 6 annual worth analysisBich Lien Pham
 
Chapter 2 factors, effect of time & interest on money
Chapter 2   factors, effect of time & interest on moneyChapter 2   factors, effect of time & interest on money
Chapter 2 factors, effect of time & interest on moneyBich Lien Pham
 

Plus de Bich Lien Pham (8)

Lecture # 9 taxes and eva
Lecture # 9 taxes and evaLecture # 9 taxes and eva
Lecture # 9 taxes and eva
 
Chapter 14 effects of inflation
Chapter 14   effects of inflationChapter 14   effects of inflation
Chapter 14 effects of inflation
 
Chapter 12 independent projects & budget limitation
Chapter 12   independent projects & budget limitationChapter 12   independent projects & budget limitation
Chapter 12 independent projects & budget limitation
 
Chapter 10 making choices & marr
Chapter 10   making choices & marrChapter 10   making choices & marr
Chapter 10 making choices & marr
 
Chapter 9 benefit & cost analysis
Chapter 9   benefit & cost analysisChapter 9   benefit & cost analysis
Chapter 9 benefit & cost analysis
 
Chapter 8 ror analysis for multiple alternatives
Chapter 8   ror analysis for multiple alternativesChapter 8   ror analysis for multiple alternatives
Chapter 8 ror analysis for multiple alternatives
 
Chapter 6 annual worth analysis
Chapter 6   annual worth analysisChapter 6   annual worth analysis
Chapter 6 annual worth analysis
 
Chapter 2 factors, effect of time & interest on money
Chapter 2   factors, effect of time & interest on moneyChapter 2   factors, effect of time & interest on money
Chapter 2 factors, effect of time & interest on money
 

Dernier

Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessSeta Wicaksana
 
Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy Verified Accounts
 
Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMintel Group
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckHajeJanKamps
 
Appkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptxAppkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptxappkodes
 
PB Project 1: Exploring Your Personal Brand
PB Project 1: Exploring Your Personal BrandPB Project 1: Exploring Your Personal Brand
PB Project 1: Exploring Your Personal BrandSharisaBethune
 
Innovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfInnovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfrichard876048
 
Guide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFGuide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFChandresh Chudasama
 
1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdf1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdfShaun Heinrichs
 
Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Riya Pathan
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfRbc Rbcua
 
PSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationPSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationAnamaria Contreras
 
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCREnjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCRalexsharmaa01
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607dollysharma2066
 
Investment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy CheruiyotInvestment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy Cheruiyotictsugar
 
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaoncallgirls2057
 
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort ServiceCall US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Servicecallgirls2057
 
Financial-Statement-Analysis-of-Coca-cola-Company.pptx
Financial-Statement-Analysis-of-Coca-cola-Company.pptxFinancial-Statement-Analysis-of-Coca-cola-Company.pptx
Financial-Statement-Analysis-of-Coca-cola-Company.pptxsaniyaimamuddin
 

Dernier (20)

Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful Business
 
Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail Accounts
 
Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 Edition
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
 
Appkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptxAppkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptx
 
PB Project 1: Exploring Your Personal Brand
PB Project 1: Exploring Your Personal BrandPB Project 1: Exploring Your Personal Brand
PB Project 1: Exploring Your Personal Brand
 
Innovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfInnovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdf
 
Guide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFGuide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDF
 
1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdf1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdf
 
Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737
 
No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdf
 
PSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationPSCC - Capability Statement Presentation
PSCC - Capability Statement Presentation
 
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCREnjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
 
Investment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy CheruiyotInvestment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy Cheruiyot
 
Corporate Profile 47Billion Information Technology
Corporate Profile 47Billion Information TechnologyCorporate Profile 47Billion Information Technology
Corporate Profile 47Billion Information Technology
 
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
 
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort ServiceCall US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
 
Financial-Statement-Analysis-of-Coca-cola-Company.pptx
Financial-Statement-Analysis-of-Coca-cola-Company.pptxFinancial-Statement-Analysis-of-Coca-cola-Company.pptx
Financial-Statement-Analysis-of-Coca-cola-Company.pptx
 

Chapter 18 sensitivity analysis

  • 1. Slide Sets to © 2005 by McGraw-Hill,18-1 Developed By: Dr. Don Smith, P.E. Department of Industrial Engineering Texas A&M University College Station, Texas Executive Summary Version Chapter 18 Formalized Sensitivity Analysis and Expected Value Decisions
  • 2. Slide Sets to © 2005 by McGraw-Hill,18-2 LEARNING OBJECTIVESLEARNING OBJECTIVES 1. Sensitivity to variation 2. Three estimates 3. Expected value 4. Expected value of cash flows 5. Decision trees
  • 3. Slide Sets to © 2005 by McGraw-Hill,18-3 Sct 18.1 Determining Sensitivity toSct 18.1 Determining Sensitivity to Parameter VariationParameter Variation A parameter is a variable or factor for which an estimate or stated value is required to conduct the analysis at hand.  Examples:  P, F, A;  i, n;  Future costs, salvages, etc.  Sensitivity analysis  Seeks to determine what parameters matter most in an economic analysis
  • 4. Slide Sets to © 2005 by McGraw-Hill,18-4 SensitivitySensitivity  Sensitivity is concerned with variability  Variance associated with input parameters impact the output variable the most  The MARR as a parameter  Interest rates and other interest factors tend to be more stable from project to project The analyst can limit the range over which these type of parameters vary
  • 5. Slide Sets to © 2005 by McGraw-Hill,18-5 Visualizing the Impact of ParametersVisualizing the Impact of Parameters  Plot the PW, AW, or ROR vs. input parameters  Steps Pre-select the desired input parameters Select the probable range and increment of variation for each parameter Select the measure of worth Compute the results for each parameter Graphically display the results by plotting the parameter vs. the measure of worth
  • 6. Slide Sets to © 2005 by McGraw-Hill,18-6 ExampleExample Low High $PW Parameter Assume a parameter of interest (show on the X-axis). Vary that parameter from some low value to an assumed high value. Plot the resultant values on the Y-axis.
  • 7. Slide Sets to © 2005 by McGraw-Hill,18-7 Sensitivity of PW: Example 18.1Sensitivity of PW: Example 18.1 Year Cflow 0 -$80,000 1 $25,000 2 $23,000 3 $21,000 4 $19,000 5 $17,000 6 $15,000 7 $13,000 8 $11,000 9 $9,000 10 $7,000 MARR PW(i%) 10% $27,831.49 15% $11,510.26 20% -$962.36 25% -$10,711.51 Ex. 18.1 PW vs. MARR -$15,000.00 -$10,000.00 -$5,000.00 $0.00 $5,000.00 $10,000.00 $15,000.00 $20,000.00 $25,000.00 $30,000.00 0% 10% 20% 30% MARR $-PW One can better visualize the relationship on PW vs. a selected range of discount rates. As the discount rate increases from 10% to 25% the resultant PW is substantially lowered at a rather accelerated rate.
  • 8. Slide Sets to © 2005 by McGraw-Hill,18-8 Sensitivity of Several ParametersSensitivity of Several Parameters  For several parameters with one alternative Graph the percentage change for each parameter vs. the measure of worth One will plot the percent deviation from the most likely estimate on the x-axis  This type of plot results in what is termed a spider plot
  • 9. Slide Sets to © 2005 by McGraw-Hill,18-9 Spider Plot: Figure 18-3Spider Plot: Figure 18-3 Those plots with positive slope have a positive correlation on the output variable: Those plots with negative slope have a inverse relationship with the output variable
  • 10. Slide Sets to © 2005 by McGraw-Hill,18-10 Sct 18.2 Formalized Sensitivity AnalysisSct 18.2 Formalized Sensitivity Analysis Using Three EstimatesUsing Three Estimates  Given an input parameter of interest Provide three estimates for that parameter  A pessimistic estimate, P  A most likely estimate, ML  An optimistic estimate, O  Note: This approach comes from PERT/CPM analysis and is based upon the beta distribution
  • 11. Slide Sets to © 2005 by McGraw-Hill,18-11 Three Estimates: Example 18.3Three Estimates: Example 18.3  Three alternatives (A, B, C) with 4 Parameters First cost, salvage value, AOC, and life For each parameter we formulate Parameter P pessimistic estimate ML most likely estimate O optimistic estimate See Table 18.2 and observe the dominance by alternative B (cost problem so lower cost is preferred)
  • 12. Slide Sets to © 2005 by McGraw-Hill,18-12 Example 18.3 -- SetupExample 18.3 -- Setup Strategy First Cost SV AOC Life Alt A. P -20,000 0 -11,000 3 ML -20,000 0 -9,000 5 O -20,000 0 -5,000 8 Alt. B P -15,000 500 -4,000 2 ML -15,000 1,000 -3,500 4 O -15,000 2,000 -2,000 7 Alt. C P -30,000 3,000 -8,000 3 ML -30,000 3,000 -7,000 7 O -30,000 3,000 -3,500 9
  • 13. Slide Sets to © 2005 by McGraw-Hill,18-13 Plot for Example 18.3Plot for Example 18.3 Ex. 18.3 $0 $5,000 $10,000 $15,000 $20,000 $25,000 1 2 3 4 5 6 7 8 9 Life - Years A.Cost Alt A Alt B Alt C Observe the dominance by alternative B over A and C. A plot like this clearly shows the relationships.
  • 14. Slide Sets to © 2005 by McGraw-Hill,18-14 Sct 18.3 Economic Variability and TheSct 18.3 Economic Variability and The Expected ValueExpected Value  Expected Value Long-run average based upon occurrence and probability of occurrence  Definition of Expected Value 1 ( ) ( ) m i i i E X X P X = = ∑ Xi = value of the variable X for i from 1 to m different values P(Xi) = probability that a specific value of X will occur Subject to: 1 ( ) 1.0 m i i P X = =∑ See Example 18.4
  • 15. Slide Sets to © 2005 by McGraw-Hill,18-15 Sct 18.4 Expected Value Computations forSct 18.4 Expected Value Computations for AlternativesAlternatives  Two applications for use of Expected Value (EV) 1. Prepare information for a more complete analysis of an economic analysis 2. To evaluate expected utility of a fully formulated alternative  Examples 18.5 and 18.6 illustrate this concept
  • 16. Slide Sets to © 2005 by McGraw-Hill,18-16 Sect 18.5 Staged Evaluation ofSect 18.5 Staged Evaluation of Alternatives Using Decision TreesAlternatives Using Decision Trees  Some problems involve staged decisions that occur in sequence  Define the staged decisions and assign the respective probabilities to the various defined outcomes  Useful tool for modeling such a process involves Decision Trees  The objective: Make Risk More Explicit
  • 17. Slide Sets to © 2005 by McGraw-Hill,18-17 Decision Tree AttributesDecision Tree Attributes  More than one stage of alternative selection  Selection of an alternative at one stage that leads to another stage  Expected results from a decision at each stage  Probability estimates for each outcome  Estimates of economic value (cost or revenue) for each outcome  Measure of worth as the selection criterion, e.g. E(PW)
  • 18. Slide Sets to © 2005 by McGraw-Hill,18-18 ExamplesExamples 60.0% 0 0 500000 FALSE Chance 500000 500000 40.0% 0 0 500000 Decision 1000000 30.0% 0.3 0 1000000 TRUE Chance 1000000 1000000 60.0% 0.6 0 1000000 10.0% 0.1 0 1000000 Example Tree Lease Buy Good Outcome Bad Outcome Good Outcome Really Bad Outcome Fair Outcome Decision Node Probability Node Marginal Probabilities Outcomes
  • 19. Slide Sets to © 2005 by McGraw-Hill,18-19 Solving Decision TreesSolving Decision Trees  Once designed, Decision Tree is solved by folding back the tree  First, define all of the decision and the decision points  Define the various outcomes given the decision  Assign the probabilities to the mutually exclusive outcomes emanating from each decision node  See Example 18-8 for a comprehensive analysis illustrating the decision tree approach
  • 20. Slide Sets to © 2005 by McGraw-Hill,18-20 Important Points for Decision TreesImportant Points for Decision Trees  Estimate the probabilities associated with each outcome  These probabilities must sum to 1 for each set of outcomes (branches) that are possible from a given decision  Required economic information for each decision alternative are investments and estimated cash flows
  • 21. Slide Sets to © 2005 by McGraw-Hill,18-21 Starting OutStarting Out  Assuming the tree logic has been defined…  Start at the top right of the tree Determine the PW for each outcome branch applying the time value of money Calculate the expected value for each decision alternative as: At each decision node, select the best E( decision ) value Continue moving to the left of the tree back to the root in order to select the best alternative Trace the best decision path back through the tree ( ) ( estimate)P(outcome)E decision outcome= ∑
  • 22. Slide Sets to © 2005 by McGraw-Hill,18-22 Example 18.8Example 18.8 D 1 M a r k e t S e ll D 2 D 3 H ig h L o w 9 1 4 1 4 0 .2 0 .5 0 .5 1 2 1 6 4 6 - 1 0 . 8 0 .2 0 .4 0 .4 0 .2 0 .8 0 .2 0 .4 0 .4 0 .2 - 3 - 3 6 - 2 2 P W o f C F B T ( $ m i ll i o n ) 1 .0 9 E x p e c t e d v a l u e s f o r e a c h a lt e r n a t i v e ( c a l c u la t e d ) I n t . N a t . I n t . N a t . 2 4 .2 4 .2 9
  • 23. Slide Sets to © 2005 by McGraw-Hill,18-23 Chapter SummaryChapter Summary The emphasis is on sensitivity to variation in one or more parameters using a specific measure of worth.  When two alternatives are compared compute and graph the measure of worth for different values of the parameter to determine when each alternative is better.  When several parameters are expected to vary over a predictable range, the measure of worth is plotted and calculated using three estimates for a parameter:  Most likely  Pessimistic  Optimistic
  • 24. Slide Sets to © 2005 by McGraw-Hill,18-24 Summary - continuedSummary - continued The combination of parameter and probability estimates results in the expected value relations E(X) = ∑(X)P(X) This expression is also used to calculate E(revenue), E(cost), E(cash flow) E(PW), and E(i) for the entire cash flow sequence of an alternative.  E9X0 is a measure of central tendency
  • 25. Slide Sets to © 2005 by McGraw-Hill,18-25 Summary - continuedSummary - continued  Decision trees are used to make a series of alternative selections. This is a way to explicitly take risk into account.  It is necessary to make several types of estimates for a decision tree:  Outcomes for each possible decision, cash flows, and probabilities.  Expected value computations are coupled with those for the measure of worth to “solve” the tree structure.  Assist is identifying the best alternative stage-by-stage.
  • 26. Slide Sets to © 2005 by McGraw-Hill,18-26 Chapter 18Chapter 18 End of SetEnd of Set

Notes de l'éditeur

  1. At this point: 1. Introduce yourself - your students are likely to want to know something about your qualifications and interests - overall, where you are coming from. 2. Have students introduce themselves. Ask why they are taking this class. If you are fortunate enough to have a Polaroid camera, take pictures of each student for later posting on a class “board” so both they and you get to know each other. 3. Discuss both choice of textbook and development of syllabus. 4. If you are expecting students to work in teams, at east introduce the choice of team members. If at all possible, have students participate in a team building or team study exercise. It works wonders. Most student have been told to work in teams in prior classes, but have never examined exactly what a team is and how it works. One hour spent in a team building/examination exercise saves many hours and avoids many problems later on.