ODESSA MOBILE TECHNOLOGY PROJECT




                      Project Plan
                      Odessa Mobile
                      Technology Project
                      Author:          Debbie Whitson
                      Creation Date:   7/10/03
                      Last Revised:    7/10/03
                      Version:         1.0
ODESSA MOBILE TECHNOLOGY PROJECT
TABLE OF CONTENTS
INTRODUCTION.........................................................................................................................................................3
PURPOSE OF PLAN................................................................................................................................................... 3
BACKGROUND INFORMATION/AVAILABLE ALTERNATIVES........................................................................................3
PROJECT APPROACH................................................................................................................................................ 4
PHASE X: SECURE EQUIPMENT................................................................................................................................ 4
GOALS AND OBJECTIVES......................................................................................................................................5
BUSINESS GOALS AND OBJECTIVES.......................................................................................................................... 5
PROJECT GOALS AND OBJECTIVES........................................................................................................................... 5
SCOPE...........................................................................................................................................................................6
SCOPE DEFINITION.................................................................................................................................................. 6
ITEMS BEYOND SCOPE............................................................................................................................................ 7
PROJECTED BUDGET................................................................................................................................................ 7
RISK ASSESSMENT.................................................................................................................................................. 8
INITIAL PROJECT RISK ASSESSMENT........................................................................................................................ 9
MILESTONES......................................................................................................................................................... 12
ASSUMPTIONS..........................................................................................................................................................13
PROJECT ASSUMPTIONS......................................................................................................................................... 13
CONSTRAINTS..........................................................................................................................................................14
PROJECT CONSTRAINTS......................................................................................................................................... 14
RELATED PROJECTS .............................................................................................................................................. 14
CRITICAL PROJECT BARRIERS................................................................................................................................ 14
PROJECT MANAGEMENT APPROACH.............................................................................................................15
PROJECT TIMELINE................................................................................................................................................ 15
PROJECT ROLES AND RESPONSIBILITIES................................................................................................................. 15
ISSUE MANAGEMENT............................................................................................................................................. 17
COMMUNICATIONS PLAN....................................................................................................................................... 18
ATTACHMENTS/APPENDICES.............................................................................................................................20

APPROVALS..............................................................................................................................................................21
SIGN-OFF SHEET................................................................................................................................................... 21




                                                                                                                                                                              2
INTRODUCTION


  Purpose of Plan

     The Odessa Mobile Technology Project Plan will provide a definition of the
     project, including the project’s goals and objectives. Additionally, the Plan will
     serve as an agreement between the following parties: Project Sponsor, Steering
     Committee, Project Manager, Project Team, and other personnel associated with
     and/or affected by the project.

     The Project Plan defines the following:

     −   Project purpose
     −   Business and project goals and objectives
     −   Scope and expectations
     −   Roles and responsibilities
     −   Assumptions and constraints
     −   Project management approach
     −   Ground rules for the project
     −   Project budget
     −   Project timeline
     −   The conceptual design of new technology

  Background Information/Available Alternatives

     Debbie: This section should describe the work you have done to date, the
     choices you had with regard to hardware/software, and an explanation of how
     you arrived at the decision to use L3 and Tiburon.




                                                                                      3
Project Approach

  This section should outline the way you will roll out the technology, including the
  highest level milestones.

  For example:

        Phase I:      Secure agreement with vendors (L3 and Tiburon)
        Phase II:     Order/Install Equipment
        Phase III:    Install/Test Software
        Phase IV:     Conduct Hardware/Software Testing
        Phase V:      Conduct Training
        Phase VI:     Implement ARS/AFR

Phase X: Secure Equipment


  Define the phases in more detail.




                                                                                    4
GOALS AND OBJECTIVES

  Business Goals and Objectives

     The business goals and objectives for this project will focus on implementing
     mobile technology that:

     − Improves officer, firefighter and citizen safety.
     − Facilitates coordination and information sharing both internal and external to
       the participating organizations.
     − Enhances the ability and effectiveness of staff to perform their jobs.
     − Facilitates coordinated crime prevention and reduction.
     − Provides high levels of data security.
     − Provides an open, flexible, reliable technology base for the future.
     − Facilitates the electronic capture of data at its source.
     − Is easy to use.
     − Eliminate redundant data entry throughout the organization.

  Project Goals and Objectives

     Sample project goals and objectives:

     − Ensure that end users have input into the design process.
     − Accomplish project business goals and objectives within defined budget and
       time parameters.
     − Minimize impact to standard business operations within the affected units.
     − Craft a favorable and secure agreement between the Department and the
       selected vendor.




                                                                                        5
SCOPE


 Scope Definition

     The Project will introduce new mobile technology; including the following:

     −   35 mobile devices
     −   Digital CAD dispatch software
     −   Car to car messaging
     −   Internet access (?)
     −   Automated field reporting software
     −   GPS/AVL for automated dispatch

     Including the following interfaces:

     − CAD
     − RMS
     − AFR
     − TLETS/NCIC/NLETS

     Desired Enhancements
     − Any?




                                                                                  6
Items Beyond Scope

  The project does not include the following:

    − Devices in supervisor vehicles
    − Desktop hardware upgrade or replacement
    − Printers

Projected Budget

  Define the project budget and insert it here:




                                                  7
Risk Assessment

  The initial Risk Assessment (following page) attempts to identify, characterize,
  prioritize and document a mitigation approach relative to those risks which can
  be identified prior to the start of the project.

  The Risk Assessment will be continuously monitored and updated throughout
  the life of the project, with monthly assessments included in the status report
  (see Communications Plan) and open to amendment by the Project Manager.

  Because mitigation approaches must be agreed upon by project leadership
  (based on the assessed impact of the risk, the project’s ability to accept the risk,
  and the feasibility of mitigating the risk), it is necessary to allocate time into each
  Steering Committee meeting, dedicated to identifying new risks and discussing
  mitigation strategies.

  The Project Manager will convey amendments and recommended contingencies
  to the Steering Committee monthly, or more frequently, as conditions may
  warrant.




                                                                                        8
Initial Project Risk Assessment

          Risk                     Risk Level           Likelihood          Mitigation Strategy
                                     L/M/H               of Event
Project Size
Person Hours                 H: Over 20,000            Certainty     Assigned Project Manager,
                                                                     engaged consultant,
                                                                     comprehensive project
                                                                     management approach and
                                                                     communications plan
Estimated Project            H: Over 12 months         Certainty     Created comprehensive project
Schedule                                                             timeline with frequent baseline
                                                                     reviews
Team Size at Peak            H: Over 15 members        Certainty     Comprehensive communications
                                                                     plan, frequent meetings, tight
                                                                     project management oversight
Number of Interfaces to      H: Over 3                 Certainty     Develop interface control
Existing Systems Affected                                            document immediately
Project Definition
Narrow Knowledge Level       M: Knowledgeable of       Likely        Assigned Project Manager(s) to
of Users                     user area only                          assess global implications
Available documentation      M: More than 75%          Likely        Balance of information to be
clouds establishment of      complete/current                        gathered by consultant
baseline
Project Scope Creep          L: Scope generally        Unlikely      Scope intially defined in project
                             defined, subject to                     plan, reviewed monthly by three
                             revision                                groups (Project Manager and
                                                                     Steering Committee) to prevent
                                                                     undetected scope creep
Consultant Project           L: Well defined           Unlikely      Included in project plan, subject to
Deliverables unclear                                                 amendment
Vendor Project               M: Estimated, not         Somewhat      Included in project plan, subject to
Deliverables                 clearly defined           likely        amendment



Cost Estimates Unrealistic   L: Thoroughly predicted   Unlikely      Included in project plan, subject to
                             by industry experts                     amendment as new details
                             using proven practices                  regarding project scope are
                             to 15% margin of error                  revealed
Timeline Estimates           M: Timeline assumes       Somewhat      Timeline reviewed monthly by
Unrealistic                  no derailment             likely        three groups (Project Manager
                                                                     and Steering Committee) to
                                                                     prevent undetected timeline
                                                                     departures



Number of Team Members       L: Team well versed in    Unlikely      Project Manager and consultant to
Unknowledgeable of           business operations                     identify knowledge gaps and
Business                     impacted by technology                  provide training, as necessary
Project Leadership
                                                                                                    9
Risk                    Risk Level           Likelihood          Mitigation Strategy
                                      L/M/H             of Event
Steering Committee          L: Identified and         Unlikely      Frequently seek feedback to
existence                   enthusiastic                            ensure continued support
Absence of Commitment       L: Understands value &    Unlikely      Frequently seek feedback to
Level/Attitude of           supports project                        ensure continued support
Management
Absence of Commitment       L: Understands value &    Unlikely      Frequently seek feedback to
Level/Attitude of Users     supports project                        ensure continued support
Absence of Mid-             L: Most understand        Unlikely      Frequently seek feedback to
Management Commitment       value & support project                 ensure continued support
Project Staffing
Project Team Availability   M: Distributed team       Somewhat      Continuous review of project
                            makes availability        likely        momentum by all levels.
                            questionable                            Consultant to identify any impacts
                                                                    caused by unavailability. If
                                                                    necessary, increase
                                                                    committmment by participants to
                                                                    full time status
Physical Location of Team   M: Team is dispersed      Likely        Use of Intranet project website,
prevents effective          among several sites                     comprehensive Communications
management                                                          Plan
Project Team’s Shared       M: Some have worked       Somewhat      Comprehensive Communications
Work Experience creates     together before           likely        Plan
poor working relationship
Weak User Participation     L: Users are part-time    Unlikely      User Group Participants
on Project Team             team members                            coordinated by full time employee
Project Management
Procurement                 L: Procurement            Unlikely      N/A
Methodology Used foreign    Methodology familiar to
to team                     team
Change Management           L: Well-defined           Unlikely      N/A
Procedures undefined
Quality Management          L: Well-defined and       Unlikely      N/A
Procedures unclear          accepted
Software Vendor
Number of Times Team        H: Never                  Certainty     A comprehensive vendor
Has Done Prior Work with                                            evaluation and selection process
Vendor Creates Foreign                                              (incorporated into Project Plan) will
Relationship                                                        be employed to predict and define
                                                                    the relationship between the
                                                                    department and the vendor
Team’s Lack of Knowledge    M: Conceptual             Somewhat      Comprehensive vendor evaluation
of Package                  understanding             likely        and selection process incorporated
                                                                    into Project Plan will assist the
                                                                    team in better understanding the
                                                                    package offering(s)




                                                                                                    10
Risk                    Risk Level          Likelihood          Mitigation Strategy
                                    L/M/H              of Event
Poor Functional Match of    L: Minimal               Unlikely      Although a package has not yet
Package to Initial System   customization required                 been selected, the Consultant has
Requirements                                                       compared the initial requirements
                                                                   with available functionality and
                                                                   determined that a functional match
                                                                   to the initial requirements is very
                                                                   likely. Vendor selection will be
                                                                   based, in part, on how well the
                                                                   proposed application matches
                                                                   defined functional specifications.
Team’s Involvement in       L: High involvement in   Unlikely      Comprehensive vendor evaluation
Package Selection Impacts   selection                              and selection process incorporated
Success of Implementation                                          into Project Plan




                                                                                                 11
Milestones

  The following represent key project milestones, with estimated completion dates:

     Milestone                               Estimated Completion Date
     Phase I: XXX
     Initial Steering Committee Meeting                     00/00/2003




                                                                                 12
ASSUMPTIONS


 Project Assumptions

   The following assumptions were made in preparing the Project Plan:
   −   OPD employees are willing to change business operations to take advantage
       of the functionality offered by the new mobile technology.

   − Management will ensure that project team members are available as needed
     to complete project tasks and objectives.

   − The Steering Committee will participate in the timely execution of the Project
     Plan (i.e., timely approval cycles and meeting when required).

   − Failure to identify changes to draft deliverables within the time specified in
     the project timeline will result in project delays.

   − Project team members will adhere to the Communications Plan.

   − Mid and upper management will foster support and “buy-in” of project goals
     and objectives.

   −   The City will ensure the existence of a technological infrastructure that can
       support the new mobile technology.

   − All project participants will abide by the guidelines identified within this plan.

   − The Project Plan may change as new information and issues are revealed.




                                                                                          13
CONSTRAINTS


 Project Constraints

    The following represent known project constraints:

    − Project funding sources are limited, with no contingency.
    − Due to the nature of law enforcement, resource availability is inconsistent.

 Related Projects

    None known.

 Critical Project Barriers

    Unlike risks, critical project barriers are insurmountable issues that can be
    destructive to a project’s initiative. In this project, the following are possible
    critical barriers:

    − Removal of project funding
    − Natural disasters or acts of war

    Should any of these events occur, the Project Plan would become invalid.




                                                                                         14
PROJECT MANAGEMENT APPROACH

 Project Timeline
    Insert here

 Project Roles and Responsibilities

      Role                     Responsibilities                            Participant(s)
                    Ultimate decision-maker and tie-breaker       Insert Name
  Project           Provide project oversight and guidance
  Sponsor           Review/approve some project elements


                    Commits department resources                  Insert Names
  Steering          Approves major funding and resource
  Committee          allocation strategies, and significant
                     changes to funding/resource allocation
                    Resolves conflicts and issues
                    Provides direction to the Project Manager
                    Review project deliverables




  Project           Manages project in accordance to the          Debbie Whitson
  Manager            project plan
                    Serves as liaison to the Steering Committee
                    Receive guidance from Steering Committee
                    Supervises consultants
                    Supervise vendor(s)
                    Provide overall project direction
                    Direct/lead team members toward project
                     objectives
                    Handle problem resolution
                    Manages the project budget

  Project           Understand the user needs and business        To be identified by Steering
  Participants       processes of their area                       Committee
                    Act as consumer advocate in representing
                     their area
                    Communicate project goals, status and
                     progress throughout the project to
                     personnel in their area
                    Review and approve project deliverables
                    Creates or helps create work products
                    Coordinates participation of work groups,
                     individuals and stakeholders
                    Provide knowledge and recommendations
                    Helps identify and remove project barriers
                    Assure quality of products that will meet
                     the project goals and objectives
                    Identify risks and issues and help in
                     resolutions
                                                                                                  15
Role                 Responsibilities                      Participant(s)
Subject      Lend expertise and guidance as needed   To be identified by Steering
Matter                                                Committee
Experts




                                                                                     16
Issue Management

The information contained within the Project Plan will likely change as the project
   progresses. While change is both certain and required, it is important to note
   that any changes to the Project Plan will impact at least one of three critical
   success factors: Available Time, Available Resources (Financial, Personnel), or
   Project Quality. The decision by which to make modifications to the Project Plan
   (including project scope and resources) should be coordinated using the
   following process:

      Step 1:   As soon as a change which impacts project scope, schedule,
                staffing or spending is identified, the Project Manager will
                document the issue.

      Step 2:   The Project Manager will review the change and determine the
                associated impact to the project and will forward the issue, along
                with a recommendation, to the Steering Committee for review and
                decision.

      Step 3:   Upon receipt, the Steering Committee should reach a consensus
                opinion on whether to approve, reject or modify the request based
                upon the information contained within the project website, the
                Project Manager’s recommendation and their own judgment.
                Should the Steering Committee be unable to reach consensus on
                the approval or denial of a change, the issue will be forwarded to
                the Project Sponsor, with a written summation of the issue, for
                ultimate resolution.

      Step 4:   If required under the decision matrix or due to a lack of consensus,
                the Project Sponsor shall review the issue(s) and render a final
                decision on the approval or denial of a change.

      Step 5:   Following an approval or denial (by the Steering Committee or
                Project Sponsor), the Project Manager will notify the original
                requestor of the action taken. There is no appeal process.




                                                                                      17
Communications Plan

     Disseminating knowledge about the project is essential to the project’s success.
     Project participants desire knowledge of what the status of the project is and how
     they are affected. Furthermore, they are anxious to participate. The more that
     people are educated about the progress of the project and how it will help them
     in the future, the more they are likely to participate and benefit.

     This plan provides a framework for informing, involving, and obtaining buy-in
     from all participants throughout the duration of the project.

     Audience This communication plan is for the following audiences:

     −   Project Sponsor
     −   Steering Committee
     −   Project Manager
     −   User Group Participants
     −   Subject Matter Experts

     Communications Methodology The communications methodology utilizes
     three directions for effective communication:

            Top-Down It is absolutely crucial that all participants in this project sense
            the executive support and guidance for this effort. The executive
            leadership of the organization needs to speak with a unified, enthusiastic
            voice about the project and what it holds for everyone involved. This will
            be 'hands-on' change management, if it is to be successful. Not only will
            the executives need to speak directly to all levels of the organization, they
            will also need to listen directly to all levels of the organization, as well.

            The transition from the project management practices of today to the
            practices envisioned for tomorrow will be driven by a sure and convinced
            leadership focused on a vision and guided by clearly defined, strategic,
            measurable goals.


            Bottom-Up To ensure the buy-in and confidence of the personnel
            involved in bringing the proposed changes to reality, it will be important to
            communicate the way in which the solutions were created. If the
            perception in the organization is that only the Steering Committee created
            the proposed changes, resistance is likely to occur. However, if it is
            understood that all participants were consulted, acceptance seems more
            promising.




                                                                                        18
Middle-Out Full support at all levels, where the changes will have to be
      implemented, is important to sustainable improvement. At this level (as
      with all levels), there must be an effort to find and communicate the
      specific benefits of the changes. People need a personal stake in the
      success of the project management practices.

Communications Outreach The following is a list of communication events that
are established for this project:

      Monthly Status Reports The Project Manager shall provide monthly
      written status reports to the Steering Committee. The reports shall include
      the following information tracked against the Project Plan:

      -   Summary of tasks completed in previous month
      -   Summary of tasks scheduled for completion in the next month
      -   Summary of issue status and resolutions

      Monthly Steering Committee Meeting These status meetings are held
      at least once per month and are coordinated by the Project Manager.
      Every member of the Steering Committee participates in the meeting. The
      Project Manager sends the status report to each member of the team prior
      to the meeting time so everyone can review it in advance.

      Bi-Monthly Project Team Status Meeting These status meetings are
      held every other month. Every member of the Project Team will be invited
      to participate in the meeting. Project Manager sends the status report to
      each member of the team prior to the meeting so everyone can review it
      in advance.

      Website Use User Group Participants and Subject Matter Experts may be
      updated monthly at the discretion of the Project Manager. Information will
      be posted to the project’s website.




                                                                                 19
ATTACHMENTS/APPENDICES

 Appendices/Attachments may be included in a hardcopy form




                                                             20
APPROVALS


 Sign-off Sheet



 I have read the above Project Plan and will abide by its terms and conditions
 and pledge my full commitment and support for the Project Plan.


 Project Sponsor:

                                                                   Date
 Project Manager:

                                                                   Date

 Steering Committee:

                                                                   Date
 Steering Committee:

                                                                   Date
 Steering Committee:

                                                                   Date
 Steering Committee:

                                                                   Date
 Steering Committee:

                                                                   Date
 Steering Committee:

                                                                   Date
 Steering Committee:

                                                                   Date
 Steering Committee:

                                                                   Date
 Steering Committee:

                                                                   Date
 Steering Committee:

                                                                   Date
 Steering Committee:

                                                                   Date
 Steering Committee:
                                                                                 21
Date
Steering Committee:

                      Date
Steering Committee:

                      Date
Steering Committee:

                      Date




                             22

Contenu connexe

Tendances

Marketing aspects of Feasibility Study
Marketing aspects of Feasibility StudyMarketing aspects of Feasibility Study
Marketing aspects of Feasibility StudyJeziel Camarillo
 
Chapter 4 Market feasibility study
Chapter 4 Market feasibility studyChapter 4 Market feasibility study
Chapter 4 Market feasibility studyAbd ELRahman ALFar
 
Angel's Boutique Business Plan
Angel's Boutique Business PlanAngel's Boutique Business Plan
Angel's Boutique Business Planmauryyn
 
An Introduction to Feasibility studies
An Introduction to Feasibility studiesAn Introduction to Feasibility studies
An Introduction to Feasibility studiesRobert Topley
 
Philippines Micro Small Medium Enterprises (MSMEs)
Philippines Micro Small Medium Enterprises (MSMEs) Philippines Micro Small Medium Enterprises (MSMEs)
Philippines Micro Small Medium Enterprises (MSMEs) Jo Balucanag - Bitonio
 
Events management team job roles
Events management team job rolesEvents management team job roles
Events management team job rolesAshleighG
 
SOCIO ECONOMIC BUSINESS PLAN
SOCIO ECONOMIC BUSINESS PLANSOCIO ECONOMIC BUSINESS PLAN
SOCIO ECONOMIC BUSINESS PLANpraveensureshpai
 
Chap 5 Estimating Project Times
Chap 5 Estimating Project TimesChap 5 Estimating Project Times
Chap 5 Estimating Project Timesproject management
 
Related Literature and Related Studies
Related Literature and Related StudiesRelated Literature and Related Studies
Related Literature and Related StudiesJenny Reyes
 
An Event Proposal: Wedding Anniversary Proposal
An Event Proposal: Wedding Anniversary ProposalAn Event Proposal: Wedding Anniversary Proposal
An Event Proposal: Wedding Anniversary Proposalchristian magallanes
 

Tendances (20)

Feasibility study
Feasibility studyFeasibility study
Feasibility study
 
Marketing aspects of Feasibility Study
Marketing aspects of Feasibility StudyMarketing aspects of Feasibility Study
Marketing aspects of Feasibility Study
 
Project Charter
Project CharterProject Charter
Project Charter
 
Chapter 4 Market feasibility study
Chapter 4 Market feasibility studyChapter 4 Market feasibility study
Chapter 4 Market feasibility study
 
Feasibility Study (Veggie Bread)
Feasibility Study (Veggie Bread)Feasibility Study (Veggie Bread)
Feasibility Study (Veggie Bread)
 
Questionnaire checklist
Questionnaire checklistQuestionnaire checklist
Questionnaire checklist
 
Angel's Boutique Business Plan
Angel's Boutique Business PlanAngel's Boutique Business Plan
Angel's Boutique Business Plan
 
An Introduction to Feasibility studies
An Introduction to Feasibility studiesAn Introduction to Feasibility studies
An Introduction to Feasibility studies
 
Philippines Micro Small Medium Enterprises (MSMEs)
Philippines Micro Small Medium Enterprises (MSMEs) Philippines Micro Small Medium Enterprises (MSMEs)
Philippines Micro Small Medium Enterprises (MSMEs)
 
The case analysis
The case analysisThe case analysis
The case analysis
 
How to write a statement problem
How to write a statement problemHow to write a statement problem
How to write a statement problem
 
Chapters 1 5
Chapters 1 5Chapters 1 5
Chapters 1 5
 
Events management team job roles
Events management team job rolesEvents management team job roles
Events management team job roles
 
Career plan example
Career plan exampleCareer plan example
Career plan example
 
SOCIO ECONOMIC BUSINESS PLAN
SOCIO ECONOMIC BUSINESS PLANSOCIO ECONOMIC BUSINESS PLAN
SOCIO ECONOMIC BUSINESS PLAN
 
Concept Paper Best Examples
Concept Paper Best ExamplesConcept Paper Best Examples
Concept Paper Best Examples
 
Chap 5 Estimating Project Times
Chap 5 Estimating Project TimesChap 5 Estimating Project Times
Chap 5 Estimating Project Times
 
BUSINESS PROPONENTS
BUSINESS PROPONENTSBUSINESS PROPONENTS
BUSINESS PROPONENTS
 
Related Literature and Related Studies
Related Literature and Related StudiesRelated Literature and Related Studies
Related Literature and Related Studies
 
An Event Proposal: Wedding Anniversary Proposal
An Event Proposal: Wedding Anniversary ProposalAn Event Proposal: Wedding Anniversary Proposal
An Event Proposal: Wedding Anniversary Proposal
 

En vedette

Project Plan for Tote Bag
Project Plan for Tote BagProject Plan for Tote Bag
Project Plan for Tote BagCristina Santos
 
Practical Guide to Useful Project Management Plan
Practical Guide to Useful Project Management PlanPractical Guide to Useful Project Management Plan
Practical Guide to Useful Project Management PlanDmitriy Nizhebetskiy
 
Poder LAtino Reconocimiento
Poder LAtino ReconocimientoPoder LAtino Reconocimiento
Poder LAtino ReconocimientoMaria Santiago
 
how to write a simple business plan
how to write a simple business planhow to write a simple business plan
how to write a simple business planTendayi Kunaka
 
El Economista entrevista a José Antonio Llorente
El Economista entrevista a José Antonio LlorenteEl Economista entrevista a José Antonio Llorente
El Economista entrevista a José Antonio LlorenteLLYC
 
School Tuckshop
School TuckshopSchool Tuckshop
School TuckshopH Anderson
 
DRY DOCK BUSINESS PLAN 2015 LEITH HUB
DRY DOCK BUSINESS PLAN 2015 LEITH HUBDRY DOCK BUSINESS PLAN 2015 LEITH HUB
DRY DOCK BUSINESS PLAN 2015 LEITH HUBsandra marshall
 
Home Based Business Opportunities Financial Success
Home Based Business Opportunities Financial SuccessHome Based Business Opportunities Financial Success
Home Based Business Opportunities Financial SuccessCacey Taylor
 
Example of business plan by a nfte student
Example of business plan by a nfte studentExample of business plan by a nfte student
Example of business plan by a nfte studentaletom78
 
Example of Company Performance Analysis
Example of Company Performance AnalysisExample of Company Performance Analysis
Example of Company Performance AnalysisSeredup Maya
 
10 Project Proposal Writing
10 Project Proposal Writing10 Project Proposal Writing
10 Project Proposal WritingTony
 
Business Plan Sample - Edit for reddit
Business Plan Sample - Edit for redditBusiness Plan Sample - Edit for reddit
Business Plan Sample - Edit for redditMarcus Aurelius
 
Apple background of company
Apple background of companyApple background of company
Apple background of companyaroneb
 

En vedette (20)

Project Plan for Tote Bag
Project Plan for Tote BagProject Plan for Tote Bag
Project Plan for Tote Bag
 
Project plan
Project planProject plan
Project plan
 
Practical Guide to Useful Project Management Plan
Practical Guide to Useful Project Management PlanPractical Guide to Useful Project Management Plan
Practical Guide to Useful Project Management Plan
 
example of a project plan
example of a project planexample of a project plan
example of a project plan
 
business plan of jute bag
business plan of jute bagbusiness plan of jute bag
business plan of jute bag
 
Poder LAtino Reconocimiento
Poder LAtino ReconocimientoPoder LAtino Reconocimiento
Poder LAtino Reconocimiento
 
The inside job
The inside jobThe inside job
The inside job
 
how to write a simple business plan
how to write a simple business planhow to write a simple business plan
how to write a simple business plan
 
RPL case
RPL caseRPL case
RPL case
 
El Economista entrevista a José Antonio Llorente
El Economista entrevista a José Antonio LlorenteEl Economista entrevista a José Antonio Llorente
El Economista entrevista a José Antonio Llorente
 
School Tuckshop
School TuckshopSchool Tuckshop
School Tuckshop
 
Di confusionesortograficas 191115
Di confusionesortograficas 191115Di confusionesortograficas 191115
Di confusionesortograficas 191115
 
DRY DOCK BUSINESS PLAN 2015 LEITH HUB
DRY DOCK BUSINESS PLAN 2015 LEITH HUBDRY DOCK BUSINESS PLAN 2015 LEITH HUB
DRY DOCK BUSINESS PLAN 2015 LEITH HUB
 
Home Based Business Opportunities Financial Success
Home Based Business Opportunities Financial SuccessHome Based Business Opportunities Financial Success
Home Based Business Opportunities Financial Success
 
Example of business plan by a nfte student
Example of business plan by a nfte studentExample of business plan by a nfte student
Example of business plan by a nfte student
 
Show and tell
Show and tellShow and tell
Show and tell
 
Example of Company Performance Analysis
Example of Company Performance AnalysisExample of Company Performance Analysis
Example of Company Performance Analysis
 
10 Project Proposal Writing
10 Project Proposal Writing10 Project Proposal Writing
10 Project Proposal Writing
 
Business Plan Sample - Edit for reddit
Business Plan Sample - Edit for redditBusiness Plan Sample - Edit for reddit
Business Plan Sample - Edit for reddit
 
Apple background of company
Apple background of companyApple background of company
Apple background of company
 

Similaire à Sample project plan

Sample Project Plan-1.doc
Sample Project Plan-1.docSample Project Plan-1.doc
Sample Project Plan-1.docAShestopalov
 
IT Application Development - with SDLC.pptx
IT Application Development - with SDLC.pptxIT Application Development - with SDLC.pptx
IT Application Development - with SDLC.pptxdjualaja88
 
Arvind Pal_Resume
Arvind Pal_ResumeArvind Pal_Resume
Arvind Pal_ResumeArvind Pal
 
Indonesia Truck Entry Project Proposal (1) [Autosaved].pptx
Indonesia Truck Entry Project Proposal (1) [Autosaved].pptxIndonesia Truck Entry Project Proposal (1) [Autosaved].pptx
Indonesia Truck Entry Project Proposal (1) [Autosaved].pptxbidyut13
 
CPIN 269 Final Documentation
CPIN 269 Final DocumentationCPIN 269 Final Documentation
CPIN 269 Final DocumentationJennifer Cordes
 
Introducton of event-driven edited.pptx
Introducton of event-driven edited.pptxIntroducton of event-driven edited.pptx
Introducton of event-driven edited.pptxkristinatemen
 
Project management-plan
Project management-planProject management-plan
Project management-planTran Tien
 
PROJECT MANAGEMENT PLAN TEMPLATE This Project Mana.docx
PROJECT MANAGEMENT PLAN TEMPLATE This Project Mana.docxPROJECT MANAGEMENT PLAN TEMPLATE This Project Mana.docx
PROJECT MANAGEMENT PLAN TEMPLATE This Project Mana.docxwkyra78
 
Project NameYour Full NameCourse Number and Name (As i.docx
Project NameYour Full NameCourse Number and Name (As i.docxProject NameYour Full NameCourse Number and Name (As i.docx
Project NameYour Full NameCourse Number and Name (As i.docxwkyra78
 
VoIP Implementation WBSTask NameDurationStart DateEnd DatePredeces.docx
VoIP Implementation WBSTask NameDurationStart DateEnd DatePredeces.docxVoIP Implementation WBSTask NameDurationStart DateEnd DatePredeces.docx
VoIP Implementation WBSTask NameDurationStart DateEnd DatePredeces.docxjessiehampson
 
Project Planning in Software Engineering
Project Planning in Software EngineeringProject Planning in Software Engineering
Project Planning in Software EngineeringFáber D. Giraldo
 
Software Development: Fixed Price Model Features
Software Development: Fixed Price Model FeaturesSoftware Development: Fixed Price Model Features
Software Development: Fixed Price Model FeaturesVladimir Tursin
 
Checklist to cost your software development accurately in 2022
Checklist to cost your software development accurately in 2022Checklist to cost your software development accurately in 2022
Checklist to cost your software development accurately in 2022IndusNetMarketing
 
Software project management- Software Engineering
Software project management- Software EngineeringSoftware project management- Software Engineering
Software project management- Software EngineeringMuhammad Yousuf Abdul Qadir
 
COUC 515Logic Model Template· Resources – required in order fo.docx
COUC 515Logic Model Template· Resources – required in order fo.docxCOUC 515Logic Model Template· Resources – required in order fo.docx
COUC 515Logic Model Template· Resources – required in order fo.docxmelvinjrobinson2199
 
Vignash Naidu Portfolio
Vignash Naidu PortfolioVignash Naidu Portfolio
Vignash Naidu Portfoliovignash
 

Similaire à Sample project plan (20)

Sample Project Plan-1.doc
Sample Project Plan-1.docSample Project Plan-1.doc
Sample Project Plan-1.doc
 
project plan
project planproject plan
project plan
 
IT Application Development - with SDLC.pptx
IT Application Development - with SDLC.pptxIT Application Development - with SDLC.pptx
IT Application Development - with SDLC.pptx
 
Arvind Pal_Resume
Arvind Pal_ResumeArvind Pal_Resume
Arvind Pal_Resume
 
Indonesia Truck Entry Project Proposal (1) [Autosaved].pptx
Indonesia Truck Entry Project Proposal (1) [Autosaved].pptxIndonesia Truck Entry Project Proposal (1) [Autosaved].pptx
Indonesia Truck Entry Project Proposal (1) [Autosaved].pptx
 
CPIN 269 Final Documentation
CPIN 269 Final DocumentationCPIN 269 Final Documentation
CPIN 269 Final Documentation
 
Introducton of event-driven edited.pptx
Introducton of event-driven edited.pptxIntroducton of event-driven edited.pptx
Introducton of event-driven edited.pptx
 
Project management-plan
Project management-planProject management-plan
Project management-plan
 
PROJECT MANAGEMENT PLAN TEMPLATE This Project Mana.docx
PROJECT MANAGEMENT PLAN TEMPLATE This Project Mana.docxPROJECT MANAGEMENT PLAN TEMPLATE This Project Mana.docx
PROJECT MANAGEMENT PLAN TEMPLATE This Project Mana.docx
 
Softwareproject planning
Softwareproject planningSoftwareproject planning
Softwareproject planning
 
Project NameYour Full NameCourse Number and Name (As i.docx
Project NameYour Full NameCourse Number and Name (As i.docxProject NameYour Full NameCourse Number and Name (As i.docx
Project NameYour Full NameCourse Number and Name (As i.docx
 
VoIP Implementation WBSTask NameDurationStart DateEnd DatePredeces.docx
VoIP Implementation WBSTask NameDurationStart DateEnd DatePredeces.docxVoIP Implementation WBSTask NameDurationStart DateEnd DatePredeces.docx
VoIP Implementation WBSTask NameDurationStart DateEnd DatePredeces.docx
 
IT Fundamentals
IT FundamentalsIT Fundamentals
IT Fundamentals
 
Report
ReportReport
Report
 
Project Planning in Software Engineering
Project Planning in Software EngineeringProject Planning in Software Engineering
Project Planning in Software Engineering
 
Software Development: Fixed Price Model Features
Software Development: Fixed Price Model FeaturesSoftware Development: Fixed Price Model Features
Software Development: Fixed Price Model Features
 
Checklist to cost your software development accurately in 2022
Checklist to cost your software development accurately in 2022Checklist to cost your software development accurately in 2022
Checklist to cost your software development accurately in 2022
 
Software project management- Software Engineering
Software project management- Software EngineeringSoftware project management- Software Engineering
Software project management- Software Engineering
 
COUC 515Logic Model Template· Resources – required in order fo.docx
COUC 515Logic Model Template· Resources – required in order fo.docxCOUC 515Logic Model Template· Resources – required in order fo.docx
COUC 515Logic Model Template· Resources – required in order fo.docx
 
Vignash Naidu Portfolio
Vignash Naidu PortfolioVignash Naidu Portfolio
Vignash Naidu Portfolio
 

Dernier

Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckHajeJanKamps
 
Innovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfInnovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfrichard876048
 
PSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationPSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationAnamaria Contreras
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesKeppelCorporation
 
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!Doge Mining Website
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCRashishs7044
 
Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy Verified Accounts
 
PB Project 1: Exploring Your Personal Brand
PB Project 1: Exploring Your Personal BrandPB Project 1: Exploring Your Personal Brand
PB Project 1: Exploring Your Personal BrandSharisaBethune
 
Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMintel Group
 
Financial-Statement-Analysis-of-Coca-cola-Company.pptx
Financial-Statement-Analysis-of-Coca-cola-Company.pptxFinancial-Statement-Analysis-of-Coca-cola-Company.pptx
Financial-Statement-Analysis-of-Coca-cola-Company.pptxsaniyaimamuddin
 
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort ServiceCall US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Servicecallgirls2057
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMVoces Mineras
 
Appkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptxAppkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptxappkodes
 
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCRashishs7044
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCRashishs7044
 
Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Riya Pathan
 
International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...ssuserf63bd7
 
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCRashishs7044
 

Dernier (20)

Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
 
Innovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfInnovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdf
 
PSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationPSCC - Capability Statement Presentation
PSCC - Capability Statement Presentation
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation Slides
 
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
 
Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail Accounts
 
PB Project 1: Exploring Your Personal Brand
PB Project 1: Exploring Your Personal BrandPB Project 1: Exploring Your Personal Brand
PB Project 1: Exploring Your Personal Brand
 
Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 Edition
 
Financial-Statement-Analysis-of-Coca-cola-Company.pptx
Financial-Statement-Analysis-of-Coca-cola-Company.pptxFinancial-Statement-Analysis-of-Coca-cola-Company.pptx
Financial-Statement-Analysis-of-Coca-cola-Company.pptx
 
Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)
 
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort ServiceCall US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQM
 
Appkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptxAppkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptx
 
Call Us ➥9319373153▻Call Girls In North Goa
Call Us ➥9319373153▻Call Girls In North GoaCall Us ➥9319373153▻Call Girls In North Goa
Call Us ➥9319373153▻Call Girls In North Goa
 
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
 
Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737
 
International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...
 
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
 

Sample project plan

  • 1. ODESSA MOBILE TECHNOLOGY PROJECT Project Plan Odessa Mobile Technology Project Author: Debbie Whitson Creation Date: 7/10/03 Last Revised: 7/10/03 Version: 1.0
  • 2. ODESSA MOBILE TECHNOLOGY PROJECT TABLE OF CONTENTS INTRODUCTION.........................................................................................................................................................3 PURPOSE OF PLAN................................................................................................................................................... 3 BACKGROUND INFORMATION/AVAILABLE ALTERNATIVES........................................................................................3 PROJECT APPROACH................................................................................................................................................ 4 PHASE X: SECURE EQUIPMENT................................................................................................................................ 4 GOALS AND OBJECTIVES......................................................................................................................................5 BUSINESS GOALS AND OBJECTIVES.......................................................................................................................... 5 PROJECT GOALS AND OBJECTIVES........................................................................................................................... 5 SCOPE...........................................................................................................................................................................6 SCOPE DEFINITION.................................................................................................................................................. 6 ITEMS BEYOND SCOPE............................................................................................................................................ 7 PROJECTED BUDGET................................................................................................................................................ 7 RISK ASSESSMENT.................................................................................................................................................. 8 INITIAL PROJECT RISK ASSESSMENT........................................................................................................................ 9 MILESTONES......................................................................................................................................................... 12 ASSUMPTIONS..........................................................................................................................................................13 PROJECT ASSUMPTIONS......................................................................................................................................... 13 CONSTRAINTS..........................................................................................................................................................14 PROJECT CONSTRAINTS......................................................................................................................................... 14 RELATED PROJECTS .............................................................................................................................................. 14 CRITICAL PROJECT BARRIERS................................................................................................................................ 14 PROJECT MANAGEMENT APPROACH.............................................................................................................15 PROJECT TIMELINE................................................................................................................................................ 15 PROJECT ROLES AND RESPONSIBILITIES................................................................................................................. 15 ISSUE MANAGEMENT............................................................................................................................................. 17 COMMUNICATIONS PLAN....................................................................................................................................... 18 ATTACHMENTS/APPENDICES.............................................................................................................................20 APPROVALS..............................................................................................................................................................21 SIGN-OFF SHEET................................................................................................................................................... 21 2
  • 3. INTRODUCTION Purpose of Plan The Odessa Mobile Technology Project Plan will provide a definition of the project, including the project’s goals and objectives. Additionally, the Plan will serve as an agreement between the following parties: Project Sponsor, Steering Committee, Project Manager, Project Team, and other personnel associated with and/or affected by the project. The Project Plan defines the following: − Project purpose − Business and project goals and objectives − Scope and expectations − Roles and responsibilities − Assumptions and constraints − Project management approach − Ground rules for the project − Project budget − Project timeline − The conceptual design of new technology Background Information/Available Alternatives Debbie: This section should describe the work you have done to date, the choices you had with regard to hardware/software, and an explanation of how you arrived at the decision to use L3 and Tiburon. 3
  • 4. Project Approach This section should outline the way you will roll out the technology, including the highest level milestones. For example: Phase I: Secure agreement with vendors (L3 and Tiburon) Phase II: Order/Install Equipment Phase III: Install/Test Software Phase IV: Conduct Hardware/Software Testing Phase V: Conduct Training Phase VI: Implement ARS/AFR Phase X: Secure Equipment Define the phases in more detail. 4
  • 5. GOALS AND OBJECTIVES Business Goals and Objectives The business goals and objectives for this project will focus on implementing mobile technology that: − Improves officer, firefighter and citizen safety. − Facilitates coordination and information sharing both internal and external to the participating organizations. − Enhances the ability and effectiveness of staff to perform their jobs. − Facilitates coordinated crime prevention and reduction. − Provides high levels of data security. − Provides an open, flexible, reliable technology base for the future. − Facilitates the electronic capture of data at its source. − Is easy to use. − Eliminate redundant data entry throughout the organization. Project Goals and Objectives Sample project goals and objectives: − Ensure that end users have input into the design process. − Accomplish project business goals and objectives within defined budget and time parameters. − Minimize impact to standard business operations within the affected units. − Craft a favorable and secure agreement between the Department and the selected vendor. 5
  • 6. SCOPE Scope Definition The Project will introduce new mobile technology; including the following: − 35 mobile devices − Digital CAD dispatch software − Car to car messaging − Internet access (?) − Automated field reporting software − GPS/AVL for automated dispatch Including the following interfaces: − CAD − RMS − AFR − TLETS/NCIC/NLETS Desired Enhancements − Any? 6
  • 7. Items Beyond Scope The project does not include the following: − Devices in supervisor vehicles − Desktop hardware upgrade or replacement − Printers Projected Budget Define the project budget and insert it here: 7
  • 8. Risk Assessment The initial Risk Assessment (following page) attempts to identify, characterize, prioritize and document a mitigation approach relative to those risks which can be identified prior to the start of the project. The Risk Assessment will be continuously monitored and updated throughout the life of the project, with monthly assessments included in the status report (see Communications Plan) and open to amendment by the Project Manager. Because mitigation approaches must be agreed upon by project leadership (based on the assessed impact of the risk, the project’s ability to accept the risk, and the feasibility of mitigating the risk), it is necessary to allocate time into each Steering Committee meeting, dedicated to identifying new risks and discussing mitigation strategies. The Project Manager will convey amendments and recommended contingencies to the Steering Committee monthly, or more frequently, as conditions may warrant. 8
  • 9. Initial Project Risk Assessment Risk Risk Level Likelihood Mitigation Strategy L/M/H of Event Project Size Person Hours H: Over 20,000 Certainty Assigned Project Manager, engaged consultant, comprehensive project management approach and communications plan Estimated Project H: Over 12 months Certainty Created comprehensive project Schedule timeline with frequent baseline reviews Team Size at Peak H: Over 15 members Certainty Comprehensive communications plan, frequent meetings, tight project management oversight Number of Interfaces to H: Over 3 Certainty Develop interface control Existing Systems Affected document immediately Project Definition Narrow Knowledge Level M: Knowledgeable of Likely Assigned Project Manager(s) to of Users user area only assess global implications Available documentation M: More than 75% Likely Balance of information to be clouds establishment of complete/current gathered by consultant baseline Project Scope Creep L: Scope generally Unlikely Scope intially defined in project defined, subject to plan, reviewed monthly by three revision groups (Project Manager and Steering Committee) to prevent undetected scope creep Consultant Project L: Well defined Unlikely Included in project plan, subject to Deliverables unclear amendment Vendor Project M: Estimated, not Somewhat Included in project plan, subject to Deliverables clearly defined likely amendment Cost Estimates Unrealistic L: Thoroughly predicted Unlikely Included in project plan, subject to by industry experts amendment as new details using proven practices regarding project scope are to 15% margin of error revealed Timeline Estimates M: Timeline assumes Somewhat Timeline reviewed monthly by Unrealistic no derailment likely three groups (Project Manager and Steering Committee) to prevent undetected timeline departures Number of Team Members L: Team well versed in Unlikely Project Manager and consultant to Unknowledgeable of business operations identify knowledge gaps and Business impacted by technology provide training, as necessary Project Leadership 9
  • 10. Risk Risk Level Likelihood Mitigation Strategy L/M/H of Event Steering Committee L: Identified and Unlikely Frequently seek feedback to existence enthusiastic ensure continued support Absence of Commitment L: Understands value & Unlikely Frequently seek feedback to Level/Attitude of supports project ensure continued support Management Absence of Commitment L: Understands value & Unlikely Frequently seek feedback to Level/Attitude of Users supports project ensure continued support Absence of Mid- L: Most understand Unlikely Frequently seek feedback to Management Commitment value & support project ensure continued support Project Staffing Project Team Availability M: Distributed team Somewhat Continuous review of project makes availability likely momentum by all levels. questionable Consultant to identify any impacts caused by unavailability. If necessary, increase committmment by participants to full time status Physical Location of Team M: Team is dispersed Likely Use of Intranet project website, prevents effective among several sites comprehensive Communications management Plan Project Team’s Shared M: Some have worked Somewhat Comprehensive Communications Work Experience creates together before likely Plan poor working relationship Weak User Participation L: Users are part-time Unlikely User Group Participants on Project Team team members coordinated by full time employee Project Management Procurement L: Procurement Unlikely N/A Methodology Used foreign Methodology familiar to to team team Change Management L: Well-defined Unlikely N/A Procedures undefined Quality Management L: Well-defined and Unlikely N/A Procedures unclear accepted Software Vendor Number of Times Team H: Never Certainty A comprehensive vendor Has Done Prior Work with evaluation and selection process Vendor Creates Foreign (incorporated into Project Plan) will Relationship be employed to predict and define the relationship between the department and the vendor Team’s Lack of Knowledge M: Conceptual Somewhat Comprehensive vendor evaluation of Package understanding likely and selection process incorporated into Project Plan will assist the team in better understanding the package offering(s) 10
  • 11. Risk Risk Level Likelihood Mitigation Strategy L/M/H of Event Poor Functional Match of L: Minimal Unlikely Although a package has not yet Package to Initial System customization required been selected, the Consultant has Requirements compared the initial requirements with available functionality and determined that a functional match to the initial requirements is very likely. Vendor selection will be based, in part, on how well the proposed application matches defined functional specifications. Team’s Involvement in L: High involvement in Unlikely Comprehensive vendor evaluation Package Selection Impacts selection and selection process incorporated Success of Implementation into Project Plan 11
  • 12. Milestones The following represent key project milestones, with estimated completion dates: Milestone Estimated Completion Date Phase I: XXX Initial Steering Committee Meeting 00/00/2003 12
  • 13. ASSUMPTIONS Project Assumptions The following assumptions were made in preparing the Project Plan: − OPD employees are willing to change business operations to take advantage of the functionality offered by the new mobile technology. − Management will ensure that project team members are available as needed to complete project tasks and objectives. − The Steering Committee will participate in the timely execution of the Project Plan (i.e., timely approval cycles and meeting when required). − Failure to identify changes to draft deliverables within the time specified in the project timeline will result in project delays. − Project team members will adhere to the Communications Plan. − Mid and upper management will foster support and “buy-in” of project goals and objectives. − The City will ensure the existence of a technological infrastructure that can support the new mobile technology. − All project participants will abide by the guidelines identified within this plan. − The Project Plan may change as new information and issues are revealed. 13
  • 14. CONSTRAINTS Project Constraints The following represent known project constraints: − Project funding sources are limited, with no contingency. − Due to the nature of law enforcement, resource availability is inconsistent. Related Projects None known. Critical Project Barriers Unlike risks, critical project barriers are insurmountable issues that can be destructive to a project’s initiative. In this project, the following are possible critical barriers: − Removal of project funding − Natural disasters or acts of war Should any of these events occur, the Project Plan would become invalid. 14
  • 15. PROJECT MANAGEMENT APPROACH Project Timeline Insert here Project Roles and Responsibilities Role Responsibilities Participant(s)  Ultimate decision-maker and tie-breaker Insert Name Project  Provide project oversight and guidance Sponsor  Review/approve some project elements  Commits department resources Insert Names Steering  Approves major funding and resource Committee allocation strategies, and significant changes to funding/resource allocation  Resolves conflicts and issues  Provides direction to the Project Manager  Review project deliverables Project  Manages project in accordance to the Debbie Whitson Manager project plan  Serves as liaison to the Steering Committee  Receive guidance from Steering Committee  Supervises consultants  Supervise vendor(s)  Provide overall project direction  Direct/lead team members toward project objectives  Handle problem resolution  Manages the project budget Project  Understand the user needs and business To be identified by Steering Participants processes of their area Committee  Act as consumer advocate in representing their area  Communicate project goals, status and progress throughout the project to personnel in their area  Review and approve project deliverables  Creates or helps create work products  Coordinates participation of work groups, individuals and stakeholders  Provide knowledge and recommendations  Helps identify and remove project barriers  Assure quality of products that will meet the project goals and objectives  Identify risks and issues and help in resolutions 15
  • 16. Role Responsibilities Participant(s) Subject  Lend expertise and guidance as needed To be identified by Steering Matter Committee Experts 16
  • 17. Issue Management The information contained within the Project Plan will likely change as the project progresses. While change is both certain and required, it is important to note that any changes to the Project Plan will impact at least one of three critical success factors: Available Time, Available Resources (Financial, Personnel), or Project Quality. The decision by which to make modifications to the Project Plan (including project scope and resources) should be coordinated using the following process: Step 1: As soon as a change which impacts project scope, schedule, staffing or spending is identified, the Project Manager will document the issue. Step 2: The Project Manager will review the change and determine the associated impact to the project and will forward the issue, along with a recommendation, to the Steering Committee for review and decision. Step 3: Upon receipt, the Steering Committee should reach a consensus opinion on whether to approve, reject or modify the request based upon the information contained within the project website, the Project Manager’s recommendation and their own judgment. Should the Steering Committee be unable to reach consensus on the approval or denial of a change, the issue will be forwarded to the Project Sponsor, with a written summation of the issue, for ultimate resolution. Step 4: If required under the decision matrix or due to a lack of consensus, the Project Sponsor shall review the issue(s) and render a final decision on the approval or denial of a change. Step 5: Following an approval or denial (by the Steering Committee or Project Sponsor), the Project Manager will notify the original requestor of the action taken. There is no appeal process. 17
  • 18. Communications Plan Disseminating knowledge about the project is essential to the project’s success. Project participants desire knowledge of what the status of the project is and how they are affected. Furthermore, they are anxious to participate. The more that people are educated about the progress of the project and how it will help them in the future, the more they are likely to participate and benefit. This plan provides a framework for informing, involving, and obtaining buy-in from all participants throughout the duration of the project. Audience This communication plan is for the following audiences: − Project Sponsor − Steering Committee − Project Manager − User Group Participants − Subject Matter Experts Communications Methodology The communications methodology utilizes three directions for effective communication: Top-Down It is absolutely crucial that all participants in this project sense the executive support and guidance for this effort. The executive leadership of the organization needs to speak with a unified, enthusiastic voice about the project and what it holds for everyone involved. This will be 'hands-on' change management, if it is to be successful. Not only will the executives need to speak directly to all levels of the organization, they will also need to listen directly to all levels of the organization, as well. The transition from the project management practices of today to the practices envisioned for tomorrow will be driven by a sure and convinced leadership focused on a vision and guided by clearly defined, strategic, measurable goals. Bottom-Up To ensure the buy-in and confidence of the personnel involved in bringing the proposed changes to reality, it will be important to communicate the way in which the solutions were created. If the perception in the organization is that only the Steering Committee created the proposed changes, resistance is likely to occur. However, if it is understood that all participants were consulted, acceptance seems more promising. 18
  • 19. Middle-Out Full support at all levels, where the changes will have to be implemented, is important to sustainable improvement. At this level (as with all levels), there must be an effort to find and communicate the specific benefits of the changes. People need a personal stake in the success of the project management practices. Communications Outreach The following is a list of communication events that are established for this project: Monthly Status Reports The Project Manager shall provide monthly written status reports to the Steering Committee. The reports shall include the following information tracked against the Project Plan: - Summary of tasks completed in previous month - Summary of tasks scheduled for completion in the next month - Summary of issue status and resolutions Monthly Steering Committee Meeting These status meetings are held at least once per month and are coordinated by the Project Manager. Every member of the Steering Committee participates in the meeting. The Project Manager sends the status report to each member of the team prior to the meeting time so everyone can review it in advance. Bi-Monthly Project Team Status Meeting These status meetings are held every other month. Every member of the Project Team will be invited to participate in the meeting. Project Manager sends the status report to each member of the team prior to the meeting so everyone can review it in advance. Website Use User Group Participants and Subject Matter Experts may be updated monthly at the discretion of the Project Manager. Information will be posted to the project’s website. 19
  • 20. ATTACHMENTS/APPENDICES Appendices/Attachments may be included in a hardcopy form 20
  • 21. APPROVALS Sign-off Sheet I have read the above Project Plan and will abide by its terms and conditions and pledge my full commitment and support for the Project Plan. Project Sponsor: Date Project Manager: Date Steering Committee: Date Steering Committee: Date Steering Committee: Date Steering Committee: Date Steering Committee: Date Steering Committee: Date Steering Committee: Date Steering Committee: Date Steering Committee: Date Steering Committee: Date Steering Committee: Date Steering Committee: 21
  • 22. Date Steering Committee: Date Steering Committee: Date Steering Committee: Date 22