2. /
Case for change
Allow for the best use of the existing infrastructure.
Stepping stone to future aspirations – 10 years ahead
of HS2
Need to address current capacity issues at Liverpool
Lime Street
Take advantage of need for renewals to improve
capacity and flexibility now
Investment will help support the wider growth
agenda for Liverpool City Region
3. /
Opportunity and growth
Growth deal and long term rail strategy
enhance connectivity, support growth, can’t stand still
limited investment over past 35 years, which led to tightening
capacity constraints
present limitations of infrastructure causing a barrier
Specific Issues
current two and three car configurations over capacity at peak times
throat on the approach to Lime Street constrained due to current
layout
This will deliver extra capacity to support implementation of Northern
Hub, Halton Curve and aspirations for HS2 and better
Connectivity across the north.
4. /
Benefits
Investment in transport is an investment in economic
growth
Improved capacity
potential for 3 additional services per hour
passenger average currently 55,000 per day
additional platforms help to support potential increase
Wider platforms with more capacity and safer access
to trains
16-Jan-15 4
5. /
Key considerations
Impact of any disruption on Liverpool City Region
Major events planner
Business
Movement of passengers
Transportation plan
Noise and potential disturbance to neighbours
Communications approach
Communications sub group to be established with
Merseytravel, Liverpool City Region and train operators
Lessons learnt and best practice
16-Jan-15 5
11. /16-Jan-15 11
What is proposed
10 remodelled platforms and track
extend platforms 2 and 3 to allow for 8 car trains and
Pendolino trains in times of perturbation
reduce and/or realign of platforms 4-6
create two new platforms between the existing platforms 7
and 8
extend platform 9
New signals, points and equipment
New signals controlled from Manchester ROC
12. /
Options, impact, considerations
Options
Impact on the city
Functionality of the station
Hours of access and timing
Passengers handling and service provision
Risk of restarting services
Safety
Cost
Extent of the closure
Minimise disruption
there will be an impact
management of passengers
13. /
Joint working and engagement
Joint working with Liverpool City region
Merseytravel
LEP
Combine authority
Joint work across rail industry
workshops timetable planning
options appraisal workshop
early assurance panel
joint communications delivery