Presentation Design of Computer aided design of power transformer
Our group members:
Mizanur Rahman khan
Reg:09208025
Md. Soriful Islam Rasel
Reg:09208008
Md. Toukir Ahmed
Reg:09208005
M.K. Masud Hasan
Reg:09208031
Abstract
The main objective of this thesis is to design
of a Power Transformer using computer program.
Six different problems of designing transformer
have been solved which are varied from 600 VA to
5 MVA. These problems have been solved by
developing a computer program by the authors
according to the standard assumed values and
principles of the power transformer design.
Introduction
Transformer is an electrical device which
electric power in one circuit is
transformed into electric power of the
same frequency in another circuit.
It can rise or lower the voltage in a
circuit but with a corresponding
decrease or increase in current
Theory and principles
A transformer works on the
principle of electromagnetic
induction, according to
faradey’s law. Whenever a
closed conductor is placed
into a varying magnetic
field, a potential difference
is developed across the
terminals of the conductor. This phenomenon is
known as electromagnetic induction. This is the basic
principle of working of any transformer.
Open circuit test or no-load test
From this test, we can determine core loss and no-load current (I0) of
the transformer.
The high-voltage side is generally kept open because the current in
high-voltage winding is less compared to that on low-voltage
winding.
In low-voltage side, a voltmeter, an ammeter and a wattmeter are
connected to measure the input voltage, no-load current and the
core loss of the transformer.
W=V1I0cosѳ0
IW=I0cosѳ0
Iµ=I0sinѳ0
Fig : Open Circuit Test
Short circuit or impedance test
The main purpose of this test is to compute the
following:
Equivalent impedance of the transformer referred to
primary and secondary.
Cu loss of the transformer at any desired load.
Total voltage drop of the transformer referred to primary
and secondary.
Figure : Short Circuit Test
Voltage regulation
• With constant voltage applied in primary, the
secondary terminal voltage will decrease due to voltage
drop across its internal resistance and leakage
reactance.
• Let 0V2 and V2 be the secondary terminal voltages at no
load and on load respectively. The difference 0V2 – V2 is
known as inherent voltage regulation of the
transformer.
•Voltage regulation down:
•Voltage regulation up:
Voltage regulation
The secondary terminal voltage not only depends
on load current but also on the power factor of the
load. The regulation is said to be at full load
provided V2 is determined for full load and at
specified power factor condition. V2 drops more
and more with increasing load current. For lagging
power factor load,
V2<E2, the voltage regulation is positive.
For, leading power factor load,
V2>E2, the voltage regulation is negative.
Core or Iron Loss
From the Nippon Steel Corporation book Core loss for 27-M-4
Grade core. Figure shows core loss vs. flux density.
If we include with handling factor and Total weight of core we
can found Total core or iron loss. That we have been shown our
thesis book
Copper Loss
The loss of power in the form I2R due to
the resistances of the primary and secondary
windings is known as copper losses. The copper
loss also depends on the magnitude of currents
flowing through the windings. The total Cu loss
is given by
Copper losses are determined on the basis of R01 or
R02 which is determined from short circuit test.
Since the standard operating temperature of
electrical machine is taken as 75 °C, it is then
corrected to 75 °C.
Magnetisation Curve
From the Nippon Steel Corporation book
Magnetising curve for 27-M-4 Grade core. Figure
shows flux density (T) vs exciting power (VA/kg)
Efficiency
Due to the losses in a transformer, its output power is less
than the input power.
Power output = Power input – Total losses
Power input = Power output + Total losses
= Power output + Pi + PCu
The ratio of power output to power input of any device is
called its efficiency (η).
Tank Design
The tank dimensions and profile are decided
in a layout drawing drawn to scale considering
electrical clearances, magnetic
clearances, transport size limits and
manufacturability. The design of stiffeners is a very
important aspect of tank design. An effective
stiffening arrangement can reduce the tank plate
thickness. The stiffeners are designed in such a way
that the tank weight is minimum, and at the same
time it should be able to withstand the specified
loads.
Transformer cooling
Transformer is non-ideal device that is a
practical transformer does not provide 100%
efficiency. Transformer windings are made by
inductive coils, but a little resistive part is also
present in those windings. So, as per the Ohm’s
law, that is V=IR, a decent amount of voltage drop
will take place across those windings. It is known as
the copper loss of the transformer. By the heating
action, this amount of energy is directly converted
into equivalent amount of heat energy. For better
efficiency transformer cooling is required.
Conservator Design
Transformer conservator is considered as one of
the important transformer accessories. As the name
implies, a transformer conservator conserves some
amount of transformer insulating oil. , transformer
conservator is an air tight metallic cylindrical drum
which is fitted above the transformer main oil tank. A
pipeline is provided to create a connection of
transformer main tank and
conservator and this pipeline
usually acts as the circulating
path for the insulating oil.
This conservator tank is
partially filled with insulating oil.
Parallel operation of Transformer
In several power transmission and
distribution sector, parallel operations of
transformers are effectively done. As the name
implies, parallel operation of transformer is
achieved by connecting two or more power
transformers in parallel with each other. So, in
case of parallel operation, the primary windings of
the transformers are connected to a common
voltage source and the secondary windings are
connected to a common load. This is a simple
definition of parallel operation of transformers.
Condition for parallel operation
Primary windings should be suitable for the
supply system voltage and frequency.
The transformers should be properly connected
with regard to polarity.
The voltage ratings of both primaries and
secondaries should be identical.
The percentage impedence should be equal in
magnetude and have the same X/R ratio in order
to avoid calculating currents and operation at
different power factor.
Design procedure of transformer
Voltage per turn : Et=k√Q where Q is
the rated KVA
The Value of ‘K’ for aluminum-wound
transformer may b taken between 0.32
to 0.35
For our calculation, let us
assume, k=0.33
Therefore, Et=0.33√100=3.3
Design procedure of transformer
value of frequency as :
Et= 4.44 × 50 × Bm × Ag × 0.97 × 10-4
For determine the core diameter
Ag=K1πd2/4
is the rated frequency which is 50 Hz
Bm=is the maximum flux density in tesla
Ag=is the gross core area in sq cm
0.97=is the stacking factor
The approximate value of K1 may be assume as follows:
For steps 6:the approximate value of k1=0.92
For steps 7:the approximate value of k2=0.925
For steps 8:the approximate value of k3=0.93
For steps 9:the approximate value of k4=0.935
For steps 10:the approximate value of k5=0.94
For steps 11:the approximate value of k6=0.945
According to the advance engineering
design computer aided design is the most
important part of whole design
Problem- 1. 100 KVA, 11000 / 433 V, 50 Hz, 3
Phase Delta / Star connected, Core Type, ON cooled
Power Transformer.
Output
MATLAB coding
HV Side design values
Ph-Voltage in HV winding=11000V
Ph-Current in HV winding=3.03A
Conductor diameter in LV winding=1.700mm
Conductor Area in HV winding=2.270mm
Current density in HV winding=1.335A/sq mm
For Aluminium wound transformer K=0.33
EMF/Turn = 3.30
Turns in HV winding=3344T
5.00 Percent Turns towards Tapping=167T
Total Turns in HV winding=3511T
Assume number of coil per phase=4
Turns per c oil=878T
Gap between HV to yoke a top & bottom=25.00mm
Gap between two tap coil=10.00mm
Gap between plain coil=7.00mm
Assume no of layer=17
Turns per layer=53T
Axial length of HV coil=103.00mm
Radial build of HV coil=35.00mm
Total axial length of 4 coil=412.00mm
Inside diameter of coil in HV winding=187.00mm
Outside diameter of coil in HV winding=257.00mm
LV Side design values
Ph-Voltage in LV winding=250V
Ph-Current in LV winding=133.34A
Conductor diameter in LV winding=10.640mm
Gap between to LV coil to yoke=10.00mm
Strip size=11.00 X 5.00 X 2 no in parallel A
Area of strip=108.280mm
Current density in LV winding=1.231A/sq mm
Turns in LV winding=76T
Assume no of layer=02
Turns per layer=38T
Radial build of LV coil=23.00mm
Inside diameter of coil in LV winding=121.00mm
Outside diameter of coil in LV winding=167.00mmm
Length of LV coil with packing=470.00mm
Weight of LV Aluminium
Mean Diameter of coil=144.000mm
Mean Length of turns=453.000mm
Total Length of conductor=34428.000mm
Specific gravity of aluminium=2.760g/cc
Bare weight of conductor for 1 ph=10.289kgs
Bare weight of conductor for 3 ph=30.867kgs
Weight of the covered conductor=33.000kg
(Considering a coverage of 7 percent for LV strip
Mean Diameter of coil=222.000mm
Mean Length of turns=697.434mm
Total Length of conductor=2448828.748mm
Specific gravity of aluminium=2.760g/cc
Bare weight of conductor for 1ph=15.341kgs
Bare weight of conductor for 3ph=46.023kgs
Weight of the covered conductor=52.000kg
(Considering a coverage of 14 percent for HV
strip)
Weight of HV Aluminium
Resistance of HV site at 75 Deg-C=35.449ohm
Copper loss at 1 Ph of HV site at 75 Deg-C=325.516W
Copper loss at 3 Ph of HV site at 75 Deg-C=976.549W
Resistance of LV site at 75 Deg-C=0.011ohm
Copper loss at 1Ph of LV site at 75 Deg-C=195.023W
Copper loss at 3Ph of LV site at 75 Deg-C=585.069W
Total Copper loss 3Ph at 75 Deg-C=1561.617W
Approximate stray loss for 100.000 KVA=100.000W
Load loss as rated load=1662W
Load loss(maximum)=1762W
Winding Resistance and Load Loss
No Load Loss
From the figure for 1.561 tesla Flax density
loss=0.911W/kg
Assume Handeling Factor=25percent
(ON account of sliting, shearing, knotching,air
gap and human error during assemling)
Calculated No Load loss=226W
From the figure for 1.561 tesla Flax Magnetizing
power=1.463VA/kg
Per phase Magnetizing Current=0.386 A
Assume ddd towads 200 percent Handeling
Factor
(for stress developed
duringsliting, shearing, knotching and thikness
variation.)
Magnetizing Current=1.159A
Histeresis and eddy Current=0.301A
No load Current=1.197A
No load Currentat 100 perct. Voltage as a perct. of
Full load current=0.898percent
No Load Current at 100 percent voltage
From the figure for 1.757 tesla Flax Magnetizing
power=4.289 VA/kg
Per phase Magnetizing Current=1.006A
Assume dddtowads200percentHandelingFactor
(for stress developed during
sliting, shearing, knotching and thikness variation.)
Magnetizing Current=3.019A
Hysteresis and eddy Current=0.267A
No load Current=3.031A
No load Current at 112.5 perct. Voltage as a perct.
Of Full load current=2.273percent
No Load Current at 112.5 percent voltage
Performance Calculations
Efficiency at Unity PF and Full Load: 98.15
percent
Efficiency at 0.8 pf:
At 100 percent Ld: 97.70 percent, 75 percent
Ld:98.10 percent and5 0percent Ld:98.42 percent
Max Efficiency=98.79 percent occur at Load
=36.84 parcent
Mean Daimeter of LV & HV coil=183.0000mm,
Average stack Length of LV & HV
coil=453.0000mm
Reactance= 4.31 percent, Resistance= 1.66
percent, Impedance= 4.62 percent
Regulation: at FL and0.8pf=3.94percent, at FL
and UPF=1.75percent
Tank: Length = 847 mm, Width = 337 mm, Height = 901 mm and
Volume=0.257m^3
Tank : Surface area for walls side=2.3680 sq.m andTemp-Rise=56is reduced to
40deg-C
Unit length of each tube=0.5900m, Surface length of elliptical tube =0.1620 m
and No of Tubes =36
Tank Weight:
Side sheet ( 3 mm) =52 kg, Bottom sheet ( 5 mm)=11kg, Top sheet( 5
mm)=15kg
Base Channel=7kg, Tank Flange=7kg, Stiffeners on all 4s ides=10kg
Conservator and its supports=10kg, LV box=3kg, HV Busing adopter=4kg
Explosion Vent=4kg, Lifting lugs=2kg, Elliptical tube=39kg
Radiators Header=20kg, Miscellaneous items=4kg, Total weight of
Tank=187kg
Volume of Oil in the tank=186.181litres
Volume of Oil in (Radiator + Header)=( 19.0 + 5.0)=24.0litres
Volume of Oil in the Conservator (Length= 508.0 mm, Diameter= 235.0
mm)=8.0litres
Volume of Oil in LV box and HV box=3.0&4.0litres
Total Volume of Oil in the transformer=226.00litresor193.00kg
Weight: HV-Wdg( 52.00)+ LV-Wdg( 33.00)+(Core + Yoke)( 197.98 ) Kg
Weight(Approx.): Insulation= 15.0 kg, Core Fittings=30.0kg, Other
misc.=3.0kg
Total weight =735.68kg, Kg/KVA = 7.357
TANK Design and Weights
Other 5 Problems
Problem- 2. 600 VA, 240 / 12 V, 50 Hz, 1
Phase, Delta / Star connected, Core Type, ON cooled
Power Transformer.
Problem- 3. 1 KVA, 240 / 12 V, 50 Hz, 1
Phase Delta / Star connected, Core Type, ON cooled
Power Transformer.
Problem- 4. 630 KVA, 11000 / 440 V, 50 Hz, 3
Phase Delta / Star connected, Core Type, ON cooled
Power Transformer:
Problem- 5. 2 MVA, 33000 / 11000 V, 50 Hz, 3
Phase Delta / Star connected, Core Type, ON cooled
Power Transformer:
Problem- 6. 5 MVA, 33000 / 11000 V, 50 Hz, 3
Phase Delta / Star connected, Core Type, ON cooled
Power Transformer.
Discussion and Conclusion
We have designed transformer according to
the proposed specification including primary
coil, number of turns, secondary coil, core
diameter, step width, core stack, core area, flux
density, coil diameter, winding details, loss, no load
current, tank, conservator, oil and weights etc. As
such, the derivation of various equations
involved, explanation for the assumptions made in
employing the approximate formula.
Suggestion for Future work
For batter results about transformer design
need to internship. If anyone did an
internship, they will have the value of
specification and assume value those we
assumed. They will know about how to design a
transformer practically.
We did not create the software as a professional
one rather we have developed it. It is need to
create a software that if give the values of rating
and shown the output values.