Company Name
        IQ/OQ Qualification Protocol of Bag Sealer
        Edition: 1.00
        Page 1 of 13


                      IQ/OQ Qualification Protocol for Bag sealer



                                            Bag Sealer XXX
                                        Equipment Number:01234


         Applies to                                           Supersedes -
         Matrix
         Section                                              Copy no. -




         References :
         User Requirement for Bags sealers used in Washing and Sterilization areas. Doc. Number XXX.
         Validation Plan (VPL) – Washing and Sterilization Document number: XXXX.
         Monthly calibration check on Bag Sealer. Doc. Number: XXXXX
         Operational & Maintenance Instructions Bag Sealer. Doc. Number : XXXX
         Enclosures :
         Tests Plan (PT01) – Training Requirements (page 1 0f 3)
         Tests Plan (PT01) –Installation Requirements (page 1,2 and 3 0f 4)
         Tests Plan (PT03) – Operational Requirements (page 4 0f 4)


         Prepared by department no.: XXX
TP-01
         Validation Improvement Specialist
                                                     (date)        Fatima Grangeiro Landim (FGL)



         Reviewed and Approved by:

         Quality Control Labs Manager
                                                     (date)         QC Manager


         Validation Manager
                                                     (dato)        Validation Manager



         Quality Assurance Manager
                                                     (date)        Quality Assurance Officer
Company Name
IQ/OQ Qualification Protocol of Bag Sealer
Edition: 1.00
Page 2 of 13

                  Table of Contents

                  1    Purpose and Scope..............................................................................3
                       1.1 Out of Scope .................................................................................3
                  2    Responsibilities ....................................................................................3
                  3    Definitions and Abbreviations ............................................................... 5
                  4    Equipment Description .........................................................................5
                       4.1 System Functional Requirements..................................................6
                       4.2 Autoclaves bags ............................................................................7
                       4.3 System technical data ...................................................................7
                  5    Test Plans Order ..................................................................................7
                  6    Conclusion ........................................................................................... 8
                  7    Test Plans ............................................................................................ 8
                  8    Deviation (non-conformance) Report....................................................1
                  9    Attachments .........................................................................................3
Company Name
IQ/OQ Qualification Protocol of Bag Sealer
Edition: 1.00
Page 3 of 13



                  1 Purpose and Scope
                  The purpose of this Qualification protocol is establishing documented evidence that
                  the Bag sealer is installed and operated in accordance with User Requirements and
                  GMP requirements.
                  This Qualification Protocol includes compilation of data and defines the test
                  plans/checks to be performed to verify that the Bag Sealer is installed and operates
                  as specified.
                  The highest goal of the Bag sealer qualification activities is to make sure that all the
                  packaging materials (bags/barrier system integrity) is attained and will remain so
                  until opened by the users of sterile materials (e.g. loads such as: utensils, gowning,
                  glassware etc.)
                  The scope of this document covers all areas of the IQ/OQ qualification to be accom-
                  plished to ensure functionality of the Bag Sealer.


                  1.1 Out of Scope

                  The scope of work upon which the testing and inspection for the Bag sealer docu-
                  mented in this qualification protocol, will not cover any performance verification test-
                  ing. Performance verification tests for the system will be covered in a independent
                  Performance Qualification Protocol.
                         Calibration of temperature element on the bag sealer (attach calibration cer-
                          tificate of the vendor);
                         Calibration of force for the Bag sealer (performed each time the device is
                          turned on);
                         Calibration date and results will be document in a Test plan;
                         Checking whether sealing of many bags in a row will affect the quality of the
                          sealing;
                      


                  2 Responsibilities
                  It is the responsibility of the author of this Protocol

                     That the contents of the Qualification protocol are complete and unambiguous;
                     To ensure consistency between the objective of the protocol and the actual con-
                      tents.
                     That the technical contents and methods are correct so that the protocol is ade-
                      quate for the specified validation.
Company Name
IQ/OQ Qualification Protocol of Bag Sealer
Edition: 1.00
Page 4 of 13
                     Any documentation referent to the Bag sealer is correct (to eg. part numbers,
                      batch numbers and documents).

                  It is the responsibility of end user (or customer)

                         Agrees with the contents, method and acceptance criteria established in the
                          Qualification Protocol;
                         Agrees that any actions chosen to remedy non-conformities are acceptable
                          and must be fully documented;
                         To review drafted Protocol and to ensure consistency between the objective
                          of the protocol and the actual contents.
                         To review the final Qualification Report for this Qualification Protocol; for l
                          and report.
                         To review all non-conformities (if applicable) for this Qualification Protocol.

                  It is the responsibility of the data reviewer

                         Verification that the data and any comments in the test plan are registered
                          according to “Good Documentation practice”.
                         Verification that the test results conform to acceptance criteria and appropri-
                          ate non-conformance reports have been generated, approved and closed (if
                          applicable);
                         Signing of test plans after test completion – all testes plans being reviewed
                          must be signed and dated by reviewer.

                  It is the responsibility of the test executor

                         Executing the test following in accordance with pre-approved test plans;
                         Registration of observations and collection of data in accordance with “Good
                          Documentation Practice”;
                         Signing of test plans after test completion (all tests must be signed and dated
                          in the time of the execution);
                         Documenting all non-conformities and signing for it;
                         If re–test is required (after non-conformities), the non-conformities report
                          must be signed again by the executor.

                  It is the responsibility of Validation and QA

                         To ensure compliance with current procedures for validation.
                         That documents and data meet the requirements for validation documents,
                          cGMP requirements and registration-related requirements.
                         To ensure consistency between the objective of the protocol and the actual
                          contents.
                         To ensure correct transfer of requirements from the URS/FRS to test plan.
                         To ensure correct choice of test plans.
Company Name
IQ/OQ Qualification Protocol of Bag Sealer
Edition: 1.00
Page 5 of 13
                           To review, comment (if applicable) and approve final protocol and report;
                           Review and approval of all non-conformities;

      Initials   Department                         Responsibility           Title
      FGL        QC Microbiology dept. Number       Author                   Validation Specialist
                 XXX

      FGL        QC Microbiology dept. Number       Executor                 Validation specialist
                 XXX

      XXX        QC Microbiology dept. Number       Review and Approval      QC Manager
                 XXX

      XXXXX      Validation Manager dept.           Review Approval          Validation Manager
                 number Y

      XXX        QA dept. Number XXX                Review Approval          QA Officer



                  3 Definitions and Abbreviations
      Abbreviation     Full text/ Explanation

      QA               Quality Assurance

      CR               Change Request

      TP                  Qualification Test Plan
      Ph. Eur.         European Pharmacopoeia
      CCA              Critical Component Assessment
      VP               Validation Plan
      IQ/OQ            IQ and OQ Qualification
      PQ               Performance Qualification
      URS              User Requirement Specification
      USP              U.S. Pharmacopoeia



                  4 Equipment Description
                  The Bag sealer device is used for sealing of autoclave bags made of paper and
                  plastic multi layer foil supplied by the Qualified supplier BVCT.S.A.
                  The sealing device (Bag sealer) accommodates every material and its design guar-
                  antees an optimum sealing security and seal seam strength.
Company Name
IQ/OQ Qualification Protocol of Bag Sealer
Edition: 1.00
Page 6 of 13
                  Tag Number for the Bag sealer is 968ADC.It is located in room 65, building 9.


                  4.1 System Functional Requirements

                  The bag sealer (sealing device) contains two teflon-coated heating elements, which are
                  mounted on springs. Coated heating elements converts electricity into heat through the
                  process of joule heating.
                  The autoclave bags are then inserted in the device with the plastic side upwards.
                  During the sealing process, the heated sides of the autoclave bags should be
                  pressed against each other by a small roller. Refer to picture below:




                  Sealing of autoclave bags.

                       After the sealing process is completed, a small printer connected to the Bag sealer has
                       the function of printing out the following data:
                       1. Date of sealing;
                       2. Expiration date;
                       3. ID user;
                       4. Batch number of the sealed material;
                       5. Autoclave number (information entered before in the sealing device by operator);
                       6. Process parameter (temperature, contact pressure).
                       7. Bag sealer serial number.

                  When the autoclave bag is inserted in bag sealer (sealing device) a conveyor belt is
                  activated by a mechanical sensor. The sealed autoclave bag is then taken out on
                  the right side of the bag sealer. If a new autoclave bag is not inserted within 30
                  seconds, the conveyor belt will automatically stop.
                  The temperature of the heating elements is regulated by use of a microprocessor
                  which continuously regulates the temperature up and down with respect to the set
                  point.
Company Name
IQ/OQ Qualification Protocol of Bag Sealer
Edition: 1.00
Page 7 of 13
                  An optimum seal seam can be guaranteed if such critical parameters as sealing
                  temperature and pressure are correctly set and adjusted to the material to be
                  sealed.


                  4.2 Autoclaves bags

    Types                                       Dimensions
    Steribag XXX Bags                           30cm X 50cm
    Steribag YYYBags                            20cm X 40cm
    Steribag TTT.bags                           15cm X 20cm


                  4.3     System technical data

    Technical data                              Description
    Type of Device                              Bag sealer
    Process course                              Automatic/reproducible
    Sealing speed/time                          10 m/min (33 ft./min)
    Sealing temperature                         Max. 220°C (max. 428°F)

    Seal width                                  12 mm
    Contact pressure                            100 N* (1 Pa = 1 N/m²)/
    Sealing distance from edge                  5 - 30 mm
    Tolerance of sealing temperature            ± 2%


                  5 Test Plans Order
                  The test plans must describe all prerequisites to be executed and documented in this Quali-
                  fication protocol.
                  The objective of t ordering the tests plans is that some tests require, that certain prerequi-
                  sites have been fulfilled, before the test can be performed with a valid result.
                  One such prerequisite could be that another test plan has already been performed/ docu-
                  mented and approved.

                  Test plans have been ordered in the sequence in which they must be performed. A test plan
                  with a given “Test plan order” number should not be performed before the ones with a lower
                  numbers.
                  Some test plans do not have any bindings to each other and can be performed simultane-
                  ously. Such test plans have been given the same ordering number.

                  Before starting a test, the Test Responsible must simply check this table, and verify that all
                  test plans with a lower ordering number have been approved.
Company Name
IQ/OQ Qualification Protocol of Bag Sealer
Edition: 1.00
Page 8 of 13




    Test plan order       TP No.                      Title

             1                       TP-01            Training Requirements
             2                       TP-02            Prerequisites
             3                       TP-03            Installation Qualification tests.
             4                       TP-04            Operational Qualification tests.




                  6 Conclusion
                  The IQ/OQ qualification Protocol is completed when all tests are carried out. Any
                  validation non-conformity records are approved and closed by the qualified person-
                  nel described in the Responsibility matrix section 2 of this protocol.
                  The final Qualification Report must been prepared describing the test sequence of
                  events its outcomes and any non-conformities (if applicable).The qualification report
                  must include a comprehensive explanation of all test results and a final conclusion
                  certifying that the device it is ready for production use.




                  7 Test Plans
Company Name
    IQ/OQ Qualification Protocol of Bag Sealer Tests Plans.
    Edition: 1.00
                                                                    Enclosure


Test Plans (TP-01) Training requirements
The purpose of the test is to verify that each person who will perform the IQ/OQ tests has received training to have enough knowledge and skills to
perform all the tests approved in this Qualification Protocol.

* Copy of the training record for the person executing this Protocol must be attached to the executed Protocol.

 Test no.           Req.       C/Q        Acceptance criteria                                      Acceptance      Attachment     Date/Init
                    no.                                                                            criteria met:   number (if
                                                                                                   Yes / No        applicable)*
                                          The person who carries through the tests have been
  1.                   N/A         Q      trained/read in Validation Plan for Bag Sealer
                                          document number: 3245.Ed.1.
                                          The person who carries through the tests have been
  2.                   N/A         Q      trained/read in Validation Master Plan document
                                          number: 3245.Ed.1.
                                          The person who carries through the tests have been
  3.                   N/A         Q      trained/read in Qualification of Equipment and Facili-
                                          ties document number: 3245.Ed.1.
                                          The person who carries through the tests have been
                                          trained in training courses Root causes analyses ,
  4.                   N/A         Q
                                          non –conformities reports, good test and documenta-
                                          tion practice.
Company Name
       IQ/OQ Qualification Protocol of Bag Sealer Tests Plans.
       Edition: 1.00
                                                           Enclosure

Test Plan (TP-02) Pre requisites


Test no.               Req.       C/Q        Acceptance criteria                                         Acceptance      Attachment     Date/Init
                       no.                                                                               criteria met:   number (if
                                                                                                         Yes / No        applicable)*
                                              Copy of Qualification Documents supplied by the
  5.                   N/A        Q           Manufacturer to be attached to the executed Proto-
                                              col (Manual first page only).
                                              Verify if the bag sealer is installed according to Sup-
  6.                   N/A        Q           plier Installation Instructions in the Wash & Steriliza-
                                              tion Area.
                                             Verify the status of calibration of bag sealer instru-
                                             ments. Calibration Certificate must be supplied by the
  7.                   N/A        Q
                                             Manufacturer and attached to the executed Proto-
                                             col.
                                             Log book for the Bag sealer present during the instal-
  8.                   N/A        Q          lation activities. Log book ( copy of first page ) at-
                                             tached to the executed Protocol.
Company Name
         IQ/OQ Qualification Protocol of Bag Sealer Tests Plans.
         Edition: 1.00
                                                             Enclosure

Test Plan (TP-02) Pre requisites


 Test no.                Req.       C/Q        Acceptance criteria                                   Acceptance      Attachment     Date/Init
                         no.                                                                         criteria met:   number (if
                                                                                                     Yes / No        applicable)*
                                               User Requirement specification for the Bag sealer
   9.                    N/A        Q          reviewed and approved (copy of URS first page only
                                               attached to the executed Protocol).
                                               Validation Plan for the Bag sealer reviewed and ap-
   10.                   N/A        Q          proved (copy of VP first page only attached to the
                                               executed Protocol).
                                               Operation and Maintenance Instructions for the Bag
   11.                   N/A        Q          sealer (draft only) to be attached to the executed
                                               Protocol.
Company Name
        IQ/OQ Qualification Protocol of Bag Sealer Tests Plans.
        Edition: 1.00
                                                                          Enclosure


Test Plan (TP-03) Installation Qualification Tests.


 Test       Req. no.    C/Q     Acceptance criteria                Acceptance criteria met: Yes / No                       Attachment     Date/Init
 no.                                                                                                                       number (if
                                                                                                                           applicable)*

                                                                   Equipment ID/serial number:__________________________


                                 Equipment is marked with          Equipment TAG number:__________________________
   1.       URS1        Q        brand, model, ID- and TAG
                                 number.                           Equipment Brand:_______________________________


                                                                   Equipment Fabrication date:____________


                                 System can function with AC
   2.       URS2        Q        100-127V or AC 220-240V at
                                 60 Hertz.
                                 Display turns on when power
   3.       URS3        Q
                                 is switch on.
                                 After power failure it must be
                                 possible to continue operating
   4.       URS4        Q        the bag sealer, without have to
                                 do a reinstallation of the pro-
                                 gram.
                                 Printer and keyboard are
   5.       URS5        Q
                                 plugging in to the bag sealer.
                                 Print quality: Bag sealer can
                                 switch between colour- and
   6.       URS6        Q
                                 letter code.
Company Name
         IQ/OQ Qualification Protocol of Bag Sealer Tests Plans.
         Edition: 1.00
                                                       Enclosure

Test Plan (TP-03) Installation Qualification tests.


 Test no.                Req.       C/Q       Acceptance criteria                                     Acceptance         Attachment     Date/Init
                         no.                                                                          criteria met:      number (if
                                                                                                      Yes / No           applicable)*
                                              Keyboard works and the typed text is displayed cor-
   7.                    URS7       Q
                                              rectly on the display
                                               Bag sealer complies with current local requirements
   8.                    URS8       Q
                                               concerning health and safety.
                                                                                            o
                                              Temperature range of the Bag sealer: 80 – 220 C.
   9.                    URS9       Q

                                               Copy of the calibration certificate must be attached
                                               to executed protocol (Refer to Test Plan (TP-02) Pre   Last calibration
   10.                   URS10      Q
                                               requisites).                                           date________
Company Name
        IQ/OQ Qualification Protocol of Bag Sealer Tests Plans.
        Edition: 1.00
                                                      Enclosure

Test Plan (TP-03) Installation Qualification tests.


 Test no.               Req.       C/Q       Acceptance criteria                                    Acceptance      Attachment     Date/Init
                        no.                                                                         criteria met:   number (if
                                                                                                    Yes / No        applicable)*
                                              Calibration sticker of the temperature elements at-
   1.                   URS11      Q
                                              tached to the Bag sealer.
                                              Provide documented evidence that is possible to
   2.                   URS12      Q          calibrate the temperature elements on the bag seal-
                                              ers.
                                             Give documented evidence that the design of the
   3.                   URS13      Q         Bag Sealers comply with the general specification
                                             requirements.
Company Name
        IQ/OQ Qualification Protocol of Bag Sealer Tests Plans.
        Edition: 1.00
                                                      Enclosure


Test Plan (TP-04) Operational Qualification tests.


 Test no.               Req.       C/Q       Acceptance criteria                                    Acceptance      Attachment     Date/Init
                        no.                                                                         criteria met:   number (if
                                                                                                    Yes / No        applicable)*
   1.                   URS14      Q          Display turns on when power is switch on.

   2.                   URS15      Q
                                              Bag sealer must automatically pulls the paper bag
                                              through the device.
                                             Keyboard is working and the typed text is displayed
   3.                   URS16      Q
                                             correctly on the display.
                                             Sealing quality: Bag sealer must produce a visual
   4.                   URS17      Q
                                             regularly weld, without damaging bag.
                                             The text typed in Bag sealer is printed on autoclave
                                             bag, and text include:
                                                  Date of sterilization;
                                                  Date of expiration;
   5.                   URS18      Q              Lot number;
                                                  User ID.
                                                  Date is stated in the correct format YYYY-
                                                      MM-DD (YYYY= Year, MM= Month, DD=
                                                      Day).
Company Name
Qualification Protocol of Bag Sealer XXX
Edition: 1.00
Page 1 of 3



                  8 Deviation (non-conformance) Report

 Non–conformance/Deviation Report
 Protocol number :

 Number of deviation:
 Deviation description :




 Signed by:                                Date:     Init:

 Reason and proposal of corrective action:




 Signed by:                                Date:     Init:
Company Name
Qualification Protocol of Bag Sealer XXX
Edition: 1.00
Page 2 of 3


 Conclusion:




 Signed by:                                Date:   Init:

 QA Approved by:                           Date:   Init:
Company Name
Qualification Protocol of Bag Sealer XXX
Edition: 1.00
Page 3 of 3

                  9 Attachments
                  Record the details of each attachment made to this executed protocol.
                  Each attachment must be signed and dated, and the pages numbered un-
                  der the page X of Y convention (including Protocol number):
 Attachment                                                              Initial & date
                                                 Number of pages
 number :              Description




 Signed by:                                   Date:                  Initial:
Company name
Qualification Protocol of Bag Sealer
Edition: 1.00
Page 1 of 1




                                        Change History
Edition      Effective date Description of change        Revised without
                                                         changes
                                                         Date / Sign.

1.0          January 2011      Initial version

Contenu connexe

Tendances

Understanding the Medical device Single Audit Program (MDSAP) & How to Prepar...
Understanding the Medical device Single Audit Program (MDSAP) & How to Prepar...Understanding the Medical device Single Audit Program (MDSAP) & How to Prepar...
Understanding the Medical device Single Audit Program (MDSAP) & How to Prepar...Greenlight Guru
 
GMP- APQR training
GMP- APQR  trainingGMP- APQR  training
GMP- APQR trainingAmsavel Vel
 
cleaning validation for SSP.pptx
cleaning validation for SSP.pptxcleaning validation for SSP.pptx
cleaning validation for SSP.pptxSurafelKebede5
 
Canadaapprovalprocess final13june2012-130116090730-phpapp01
Canadaapprovalprocess final13june2012-130116090730-phpapp01Canadaapprovalprocess final13june2012-130116090730-phpapp01
Canadaapprovalprocess final13june2012-130116090730-phpapp01Frank Ferguson
 
Cleaning validation a complete know how
Cleaning validation a complete know howCleaning validation a complete know how
Cleaning validation a complete know howSambhujyoti Das
 
Pharmaceutical Quality Management System
Pharmaceutical Quality Management SystemPharmaceutical Quality Management System
Pharmaceutical Quality Management SystemSyed Muhammad Danish
 
Supplemental new drug application
Supplemental new drug applicationSupplemental new drug application
Supplemental new drug applicationgarimasaini33
 
21 CFR 820 and 801 pptx.pdf
21 CFR 820 and 801 pptx.pdf21 CFR 820 and 801 pptx.pdf
21 CFR 820 and 801 pptx.pdfBhavikaAPatel
 
Good Manufacturing Practices (GMP)- Purpose and Principles
Good Manufacturing Practices (GMP)- Purpose and PrinciplesGood Manufacturing Practices (GMP)- Purpose and Principles
Good Manufacturing Practices (GMP)- Purpose and PrinciplesImran Malik
 
Auditing of microbiology laboratory
Auditing of microbiology laboratoryAuditing of microbiology laboratory
Auditing of microbiology laboratoryNikita Amane
 
GMP Guidelines for Nutraceuticals - Indian And European
GMP Guidelines for Nutraceuticals - Indian And EuropeanGMP Guidelines for Nutraceuticals - Indian And European
GMP Guidelines for Nutraceuticals - Indian And EuropeanVarshaJindaniya
 
20210413 nvfg acs iso14155 13_apr2021
20210413 nvfg acs iso14155 13_apr202120210413 nvfg acs iso14155 13_apr2021
20210413 nvfg acs iso14155 13_apr2021Annet Visscher
 
Pharmaceutcal Industry Development.pptx
Pharmaceutcal Industry Development.pptxPharmaceutcal Industry Development.pptx
Pharmaceutcal Industry Development.pptxVitthal Mane
 

Tendances (20)

Understanding the Medical device Single Audit Program (MDSAP) & How to Prepar...
Understanding the Medical device Single Audit Program (MDSAP) & How to Prepar...Understanding the Medical device Single Audit Program (MDSAP) & How to Prepar...
Understanding the Medical device Single Audit Program (MDSAP) & How to Prepar...
 
GMP- APQR training
GMP- APQR  trainingGMP- APQR  training
GMP- APQR training
 
Good Laboratory Practice (GLP)
Good Laboratory Practice (GLP)Good Laboratory Practice (GLP)
Good Laboratory Practice (GLP)
 
cleaning validation for SSP.pptx
cleaning validation for SSP.pptxcleaning validation for SSP.pptx
cleaning validation for SSP.pptx
 
Canadaapprovalprocess final13june2012-130116090730-phpapp01
Canadaapprovalprocess final13june2012-130116090730-phpapp01Canadaapprovalprocess final13june2012-130116090730-phpapp01
Canadaapprovalprocess final13june2012-130116090730-phpapp01
 
Gmp Guidelines by HCP
Gmp Guidelines by HCPGmp Guidelines by HCP
Gmp Guidelines by HCP
 
Cleaning validation a complete know how
Cleaning validation a complete know howCleaning validation a complete know how
Cleaning validation a complete know how
 
Installation Qualification.pdf
Installation Qualification.pdfInstallation Qualification.pdf
Installation Qualification.pdf
 
calulation of yields, production record review,change control
calulation of yields, production record review,change control calulation of yields, production record review,change control
calulation of yields, production record review,change control
 
Doc1 copy
Doc1   copyDoc1   copy
Doc1 copy
 
Pharmaceutical Quality Management System
Pharmaceutical Quality Management SystemPharmaceutical Quality Management System
Pharmaceutical Quality Management System
 
Supplemental new drug application
Supplemental new drug applicationSupplemental new drug application
Supplemental new drug application
 
Line clearance ppt
Line clearance pptLine clearance ppt
Line clearance ppt
 
Iso13485 ppt
Iso13485 pptIso13485 ppt
Iso13485 ppt
 
21 CFR 820 and 801 pptx.pdf
21 CFR 820 and 801 pptx.pdf21 CFR 820 and 801 pptx.pdf
21 CFR 820 and 801 pptx.pdf
 
Good Manufacturing Practices (GMP)- Purpose and Principles
Good Manufacturing Practices (GMP)- Purpose and PrinciplesGood Manufacturing Practices (GMP)- Purpose and Principles
Good Manufacturing Practices (GMP)- Purpose and Principles
 
Auditing of microbiology laboratory
Auditing of microbiology laboratoryAuditing of microbiology laboratory
Auditing of microbiology laboratory
 
GMP Guidelines for Nutraceuticals - Indian And European
GMP Guidelines for Nutraceuticals - Indian And EuropeanGMP Guidelines for Nutraceuticals - Indian And European
GMP Guidelines for Nutraceuticals - Indian And European
 
20210413 nvfg acs iso14155 13_apr2021
20210413 nvfg acs iso14155 13_apr202120210413 nvfg acs iso14155 13_apr2021
20210413 nvfg acs iso14155 13_apr2021
 
Pharmaceutcal Industry Development.pptx
Pharmaceutcal Industry Development.pptxPharmaceutcal Industry Development.pptx
Pharmaceutcal Industry Development.pptx
 

En vedette (15)

Concept of URS,DQ,IQ,OQ,PQ
Concept of URS,DQ,IQ,OQ,PQConcept of URS,DQ,IQ,OQ,PQ
Concept of URS,DQ,IQ,OQ,PQ
 
Equipment validation of fbd
Equipment validation of fbdEquipment validation of fbd
Equipment validation of fbd
 
Validation boot camp 4
Validation boot camp 4Validation boot camp 4
Validation boot camp 4
 
instrument validation
instrument validationinstrument validation
instrument validation
 
1 5 equipment-qualification
1 5 equipment-qualification1 5 equipment-qualification
1 5 equipment-qualification
 
Dr. ajmal nasir
Dr. ajmal nasirDr. ajmal nasir
Dr. ajmal nasir
 
Equipment qualification
Equipment qualificationEquipment qualification
Equipment qualification
 
Process Validation & Verification (V&V) for Medical Devices
Process Validation & Verification (V&V) for Medical DevicesProcess Validation & Verification (V&V) for Medical Devices
Process Validation & Verification (V&V) for Medical Devices
 
A Lifecycle Approach to Process Validation
A Lifecycle Approach to Process ValidationA Lifecycle Approach to Process Validation
A Lifecycle Approach to Process Validation
 
Equipment Qualification
Equipment QualificationEquipment Qualification
Equipment Qualification
 
Validation based protocol
Validation based protocolValidation based protocol
Validation based protocol
 
Process validation of capsules
Process validation of capsulesProcess validation of capsules
Process validation of capsules
 
Validation Master Plan
Validation Master PlanValidation Master Plan
Validation Master Plan
 
PROCESS VALIDATION
PROCESS VALIDATIONPROCESS VALIDATION
PROCESS VALIDATION
 
EQUIPMENT VALIDATION : HOT AIR OVEN
EQUIPMENT VALIDATION : HOT AIR OVENEQUIPMENT VALIDATION : HOT AIR OVEN
EQUIPMENT VALIDATION : HOT AIR OVEN
 

Similaire à Qualification Of Bag Sealer.Finalpdf.

validationksd-140930004558-phpapp01 (1).pdf
validationksd-140930004558-phpapp01 (1).pdfvalidationksd-140930004558-phpapp01 (1).pdf
validationksd-140930004558-phpapp01 (1).pdfAkashChaudhary749568
 
Instrument qualification
Instrument qualificationInstrument qualification
Instrument qualificationArti Thakkar
 
b.Types of validation.gayathri - gayathri murali.pptx
b.Types of validation.gayathri - gayathri murali.pptxb.Types of validation.gayathri - gayathri murali.pptx
b.Types of validation.gayathri - gayathri murali.pptxAarthi358332
 
Pharmaceutical Qualification & Validation
Pharmaceutical Qualification & ValidationPharmaceutical Qualification & Validation
Pharmaceutical Qualification & ValidationPharmaceutical
 
validation ppt.pptx
 validation ppt.pptx validation ppt.pptx
validation ppt.pptxPawanDhamala1
 
EQUIPMENT QUALIFICATION.pptx
EQUIPMENT QUALIFICATION.pptxEQUIPMENT QUALIFICATION.pptx
EQUIPMENT QUALIFICATION.pptxRamkumar906213
 
EQUIPMENT QUALIFICATION.pptx
EQUIPMENT QUALIFICATION.pptxEQUIPMENT QUALIFICATION.pptx
EQUIPMENT QUALIFICATION.pptxRamkumar906213
 
validationmasterplan-180918073044 (3).pdf
validationmasterplan-180918073044 (3).pdfvalidationmasterplan-180918073044 (3).pdf
validationmasterplan-180918073044 (3).pdfabdo badr
 
Validation master plan
Validation master planValidation master plan
Validation master planDr. Amsavel A
 
validationandcalibrationmasterplan-190223191733.pptx
validationandcalibrationmasterplan-190223191733.pptxvalidationandcalibrationmasterplan-190223191733.pptx
validationandcalibrationmasterplan-190223191733.pptxTanmayPanigrahy
 
Equipment qualification & validation of autoclave, dry heat sterilization and...
Equipment qualification & validation of autoclave, dry heat sterilization and...Equipment qualification & validation of autoclave, dry heat sterilization and...
Equipment qualification & validation of autoclave, dry heat sterilization and...Malla Reddy College of Pharmacy
 
validation and verification of medical device.pptx
validation and verification of medical device.pptxvalidation and verification of medical device.pptx
validation and verification of medical device.pptxGargiVaghela
 
Validation and calibration master plan
Validation and calibration master planValidation and calibration master plan
Validation and calibration master planBharatlal Sain
 
Managing Validation.3
Managing Validation.3Managing Validation.3
Managing Validation.3nenalandim
 
QA QC Overview CPOU_Final Rev 1
QA QC Overview CPOU_Final Rev 1QA QC Overview CPOU_Final Rev 1
QA QC Overview CPOU_Final Rev 1Thomas Wilson
 

Similaire à Qualification Of Bag Sealer.Finalpdf. (20)

validationksd-140930004558-phpapp01 (1).pdf
validationksd-140930004558-phpapp01 (1).pdfvalidationksd-140930004558-phpapp01 (1).pdf
validationksd-140930004558-phpapp01 (1).pdf
 
Validation
ValidationValidation
Validation
 
Instrument qualification
Instrument qualificationInstrument qualification
Instrument qualification
 
Jatin validation
Jatin validationJatin validation
Jatin validation
 
b.Types of validation.gayathri - gayathri murali.pptx
b.Types of validation.gayathri - gayathri murali.pptxb.Types of validation.gayathri - gayathri murali.pptx
b.Types of validation.gayathri - gayathri murali.pptx
 
Pharmaceutical Qualification & Validation
Pharmaceutical Qualification & ValidationPharmaceutical Qualification & Validation
Pharmaceutical Qualification & Validation
 
PHARMACEUTICAL VALIADATION
PHARMACEUTICAL VALIADATIONPHARMACEUTICAL VALIADATION
PHARMACEUTICAL VALIADATION
 
validation ppt.pptx
 validation ppt.pptx validation ppt.pptx
validation ppt.pptx
 
EQUIPMENT QUALIFICATION.pptx
EQUIPMENT QUALIFICATION.pptxEQUIPMENT QUALIFICATION.pptx
EQUIPMENT QUALIFICATION.pptx
 
EQUIPMENT QUALIFICATION.pptx
EQUIPMENT QUALIFICATION.pptxEQUIPMENT QUALIFICATION.pptx
EQUIPMENT QUALIFICATION.pptx
 
validationmasterplan-180918073044 (3).pdf
validationmasterplan-180918073044 (3).pdfvalidationmasterplan-180918073044 (3).pdf
validationmasterplan-180918073044 (3).pdf
 
Validation master plan
Validation master planValidation master plan
Validation master plan
 
validationandcalibrationmasterplan-190223191733.pptx
validationandcalibrationmasterplan-190223191733.pptxvalidationandcalibrationmasterplan-190223191733.pptx
validationandcalibrationmasterplan-190223191733.pptx
 
Equipment qualification & validation of autoclave, dry heat sterilization and...
Equipment qualification & validation of autoclave, dry heat sterilization and...Equipment qualification & validation of autoclave, dry heat sterilization and...
Equipment qualification & validation of autoclave, dry heat sterilization and...
 
Validation ksd
Validation ksdValidation ksd
Validation ksd
 
Qualification for validation
Qualification for validationQualification for validation
Qualification for validation
 
validation and verification of medical device.pptx
validation and verification of medical device.pptxvalidation and verification of medical device.pptx
validation and verification of medical device.pptx
 
Validation and calibration master plan
Validation and calibration master planValidation and calibration master plan
Validation and calibration master plan
 
Managing Validation.3
Managing Validation.3Managing Validation.3
Managing Validation.3
 
QA QC Overview CPOU_Final Rev 1
QA QC Overview CPOU_Final Rev 1QA QC Overview CPOU_Final Rev 1
QA QC Overview CPOU_Final Rev 1
 

Qualification Of Bag Sealer.Finalpdf.

  • 1. Company Name IQ/OQ Qualification Protocol of Bag Sealer Edition: 1.00 Page 1 of 13 IQ/OQ Qualification Protocol for Bag sealer Bag Sealer XXX Equipment Number:01234 Applies to Supersedes - Matrix Section Copy no. - References : User Requirement for Bags sealers used in Washing and Sterilization areas. Doc. Number XXX. Validation Plan (VPL) – Washing and Sterilization Document number: XXXX. Monthly calibration check on Bag Sealer. Doc. Number: XXXXX Operational & Maintenance Instructions Bag Sealer. Doc. Number : XXXX Enclosures : Tests Plan (PT01) – Training Requirements (page 1 0f 3) Tests Plan (PT01) –Installation Requirements (page 1,2 and 3 0f 4) Tests Plan (PT03) – Operational Requirements (page 4 0f 4) Prepared by department no.: XXX TP-01 Validation Improvement Specialist (date) Fatima Grangeiro Landim (FGL) Reviewed and Approved by: Quality Control Labs Manager (date) QC Manager Validation Manager (dato) Validation Manager Quality Assurance Manager (date) Quality Assurance Officer
  • 2. Company Name IQ/OQ Qualification Protocol of Bag Sealer Edition: 1.00 Page 2 of 13 Table of Contents 1 Purpose and Scope..............................................................................3 1.1 Out of Scope .................................................................................3 2 Responsibilities ....................................................................................3 3 Definitions and Abbreviations ............................................................... 5 4 Equipment Description .........................................................................5 4.1 System Functional Requirements..................................................6 4.2 Autoclaves bags ............................................................................7 4.3 System technical data ...................................................................7 5 Test Plans Order ..................................................................................7 6 Conclusion ........................................................................................... 8 7 Test Plans ............................................................................................ 8 8 Deviation (non-conformance) Report....................................................1 9 Attachments .........................................................................................3
  • 3. Company Name IQ/OQ Qualification Protocol of Bag Sealer Edition: 1.00 Page 3 of 13 1 Purpose and Scope The purpose of this Qualification protocol is establishing documented evidence that the Bag sealer is installed and operated in accordance with User Requirements and GMP requirements. This Qualification Protocol includes compilation of data and defines the test plans/checks to be performed to verify that the Bag Sealer is installed and operates as specified. The highest goal of the Bag sealer qualification activities is to make sure that all the packaging materials (bags/barrier system integrity) is attained and will remain so until opened by the users of sterile materials (e.g. loads such as: utensils, gowning, glassware etc.) The scope of this document covers all areas of the IQ/OQ qualification to be accom- plished to ensure functionality of the Bag Sealer. 1.1 Out of Scope The scope of work upon which the testing and inspection for the Bag sealer docu- mented in this qualification protocol, will not cover any performance verification test- ing. Performance verification tests for the system will be covered in a independent Performance Qualification Protocol.  Calibration of temperature element on the bag sealer (attach calibration cer- tificate of the vendor);  Calibration of force for the Bag sealer (performed each time the device is turned on);  Calibration date and results will be document in a Test plan;  Checking whether sealing of many bags in a row will affect the quality of the sealing;  2 Responsibilities It is the responsibility of the author of this Protocol  That the contents of the Qualification protocol are complete and unambiguous;  To ensure consistency between the objective of the protocol and the actual con- tents.  That the technical contents and methods are correct so that the protocol is ade- quate for the specified validation.
  • 4. Company Name IQ/OQ Qualification Protocol of Bag Sealer Edition: 1.00 Page 4 of 13  Any documentation referent to the Bag sealer is correct (to eg. part numbers, batch numbers and documents). It is the responsibility of end user (or customer)  Agrees with the contents, method and acceptance criteria established in the Qualification Protocol;  Agrees that any actions chosen to remedy non-conformities are acceptable and must be fully documented;  To review drafted Protocol and to ensure consistency between the objective of the protocol and the actual contents.  To review the final Qualification Report for this Qualification Protocol; for l and report.  To review all non-conformities (if applicable) for this Qualification Protocol. It is the responsibility of the data reviewer  Verification that the data and any comments in the test plan are registered according to “Good Documentation practice”.  Verification that the test results conform to acceptance criteria and appropri- ate non-conformance reports have been generated, approved and closed (if applicable);  Signing of test plans after test completion – all testes plans being reviewed must be signed and dated by reviewer. It is the responsibility of the test executor  Executing the test following in accordance with pre-approved test plans;  Registration of observations and collection of data in accordance with “Good Documentation Practice”;  Signing of test plans after test completion (all tests must be signed and dated in the time of the execution);  Documenting all non-conformities and signing for it;  If re–test is required (after non-conformities), the non-conformities report must be signed again by the executor. It is the responsibility of Validation and QA  To ensure compliance with current procedures for validation.  That documents and data meet the requirements for validation documents, cGMP requirements and registration-related requirements.  To ensure consistency between the objective of the protocol and the actual contents.  To ensure correct transfer of requirements from the URS/FRS to test plan.  To ensure correct choice of test plans.
  • 5. Company Name IQ/OQ Qualification Protocol of Bag Sealer Edition: 1.00 Page 5 of 13  To review, comment (if applicable) and approve final protocol and report;  Review and approval of all non-conformities; Initials Department Responsibility Title FGL QC Microbiology dept. Number Author Validation Specialist XXX FGL QC Microbiology dept. Number Executor Validation specialist XXX XXX QC Microbiology dept. Number Review and Approval QC Manager XXX XXXXX Validation Manager dept. Review Approval Validation Manager number Y XXX QA dept. Number XXX Review Approval QA Officer 3 Definitions and Abbreviations Abbreviation Full text/ Explanation QA Quality Assurance CR Change Request TP Qualification Test Plan Ph. Eur. European Pharmacopoeia CCA Critical Component Assessment VP Validation Plan IQ/OQ IQ and OQ Qualification PQ Performance Qualification URS User Requirement Specification USP U.S. Pharmacopoeia 4 Equipment Description The Bag sealer device is used for sealing of autoclave bags made of paper and plastic multi layer foil supplied by the Qualified supplier BVCT.S.A. The sealing device (Bag sealer) accommodates every material and its design guar- antees an optimum sealing security and seal seam strength.
  • 6. Company Name IQ/OQ Qualification Protocol of Bag Sealer Edition: 1.00 Page 6 of 13 Tag Number for the Bag sealer is 968ADC.It is located in room 65, building 9. 4.1 System Functional Requirements The bag sealer (sealing device) contains two teflon-coated heating elements, which are mounted on springs. Coated heating elements converts electricity into heat through the process of joule heating. The autoclave bags are then inserted in the device with the plastic side upwards. During the sealing process, the heated sides of the autoclave bags should be pressed against each other by a small roller. Refer to picture below: Sealing of autoclave bags. After the sealing process is completed, a small printer connected to the Bag sealer has the function of printing out the following data: 1. Date of sealing; 2. Expiration date; 3. ID user; 4. Batch number of the sealed material; 5. Autoclave number (information entered before in the sealing device by operator); 6. Process parameter (temperature, contact pressure). 7. Bag sealer serial number. When the autoclave bag is inserted in bag sealer (sealing device) a conveyor belt is activated by a mechanical sensor. The sealed autoclave bag is then taken out on the right side of the bag sealer. If a new autoclave bag is not inserted within 30 seconds, the conveyor belt will automatically stop. The temperature of the heating elements is regulated by use of a microprocessor which continuously regulates the temperature up and down with respect to the set point.
  • 7. Company Name IQ/OQ Qualification Protocol of Bag Sealer Edition: 1.00 Page 7 of 13 An optimum seal seam can be guaranteed if such critical parameters as sealing temperature and pressure are correctly set and adjusted to the material to be sealed. 4.2 Autoclaves bags Types Dimensions Steribag XXX Bags 30cm X 50cm Steribag YYYBags 20cm X 40cm Steribag TTT.bags 15cm X 20cm 4.3 System technical data Technical data Description Type of Device Bag sealer Process course Automatic/reproducible Sealing speed/time 10 m/min (33 ft./min) Sealing temperature Max. 220°C (max. 428°F) Seal width 12 mm Contact pressure 100 N* (1 Pa = 1 N/m²)/ Sealing distance from edge 5 - 30 mm Tolerance of sealing temperature ± 2% 5 Test Plans Order The test plans must describe all prerequisites to be executed and documented in this Quali- fication protocol. The objective of t ordering the tests plans is that some tests require, that certain prerequi- sites have been fulfilled, before the test can be performed with a valid result. One such prerequisite could be that another test plan has already been performed/ docu- mented and approved. Test plans have been ordered in the sequence in which they must be performed. A test plan with a given “Test plan order” number should not be performed before the ones with a lower numbers. Some test plans do not have any bindings to each other and can be performed simultane- ously. Such test plans have been given the same ordering number. Before starting a test, the Test Responsible must simply check this table, and verify that all test plans with a lower ordering number have been approved.
  • 8. Company Name IQ/OQ Qualification Protocol of Bag Sealer Edition: 1.00 Page 8 of 13 Test plan order TP No. Title 1 TP-01 Training Requirements 2 TP-02 Prerequisites 3 TP-03 Installation Qualification tests. 4 TP-04 Operational Qualification tests. 6 Conclusion The IQ/OQ qualification Protocol is completed when all tests are carried out. Any validation non-conformity records are approved and closed by the qualified person- nel described in the Responsibility matrix section 2 of this protocol. The final Qualification Report must been prepared describing the test sequence of events its outcomes and any non-conformities (if applicable).The qualification report must include a comprehensive explanation of all test results and a final conclusion certifying that the device it is ready for production use. 7 Test Plans
  • 9. Company Name IQ/OQ Qualification Protocol of Bag Sealer Tests Plans. Edition: 1.00 Enclosure Test Plans (TP-01) Training requirements The purpose of the test is to verify that each person who will perform the IQ/OQ tests has received training to have enough knowledge and skills to perform all the tests approved in this Qualification Protocol. * Copy of the training record for the person executing this Protocol must be attached to the executed Protocol. Test no. Req. C/Q Acceptance criteria Acceptance Attachment Date/Init no. criteria met: number (if Yes / No applicable)* The person who carries through the tests have been 1. N/A Q trained/read in Validation Plan for Bag Sealer document number: 3245.Ed.1. The person who carries through the tests have been 2. N/A Q trained/read in Validation Master Plan document number: 3245.Ed.1. The person who carries through the tests have been 3. N/A Q trained/read in Qualification of Equipment and Facili- ties document number: 3245.Ed.1. The person who carries through the tests have been trained in training courses Root causes analyses , 4. N/A Q non –conformities reports, good test and documenta- tion practice.
  • 10. Company Name IQ/OQ Qualification Protocol of Bag Sealer Tests Plans. Edition: 1.00 Enclosure Test Plan (TP-02) Pre requisites Test no. Req. C/Q Acceptance criteria Acceptance Attachment Date/Init no. criteria met: number (if Yes / No applicable)* Copy of Qualification Documents supplied by the 5. N/A Q Manufacturer to be attached to the executed Proto- col (Manual first page only). Verify if the bag sealer is installed according to Sup- 6. N/A Q plier Installation Instructions in the Wash & Steriliza- tion Area. Verify the status of calibration of bag sealer instru- ments. Calibration Certificate must be supplied by the 7. N/A Q Manufacturer and attached to the executed Proto- col. Log book for the Bag sealer present during the instal- 8. N/A Q lation activities. Log book ( copy of first page ) at- tached to the executed Protocol.
  • 11. Company Name IQ/OQ Qualification Protocol of Bag Sealer Tests Plans. Edition: 1.00 Enclosure Test Plan (TP-02) Pre requisites Test no. Req. C/Q Acceptance criteria Acceptance Attachment Date/Init no. criteria met: number (if Yes / No applicable)* User Requirement specification for the Bag sealer 9. N/A Q reviewed and approved (copy of URS first page only attached to the executed Protocol). Validation Plan for the Bag sealer reviewed and ap- 10. N/A Q proved (copy of VP first page only attached to the executed Protocol). Operation and Maintenance Instructions for the Bag 11. N/A Q sealer (draft only) to be attached to the executed Protocol.
  • 12. Company Name IQ/OQ Qualification Protocol of Bag Sealer Tests Plans. Edition: 1.00 Enclosure Test Plan (TP-03) Installation Qualification Tests. Test Req. no. C/Q Acceptance criteria Acceptance criteria met: Yes / No Attachment Date/Init no. number (if applicable)* Equipment ID/serial number:__________________________ Equipment is marked with Equipment TAG number:__________________________ 1. URS1 Q brand, model, ID- and TAG number. Equipment Brand:_______________________________ Equipment Fabrication date:____________ System can function with AC 2. URS2 Q 100-127V or AC 220-240V at 60 Hertz. Display turns on when power 3. URS3 Q is switch on. After power failure it must be possible to continue operating 4. URS4 Q the bag sealer, without have to do a reinstallation of the pro- gram. Printer and keyboard are 5. URS5 Q plugging in to the bag sealer. Print quality: Bag sealer can switch between colour- and 6. URS6 Q letter code.
  • 13. Company Name IQ/OQ Qualification Protocol of Bag Sealer Tests Plans. Edition: 1.00 Enclosure Test Plan (TP-03) Installation Qualification tests. Test no. Req. C/Q Acceptance criteria Acceptance Attachment Date/Init no. criteria met: number (if Yes / No applicable)* Keyboard works and the typed text is displayed cor- 7. URS7 Q rectly on the display Bag sealer complies with current local requirements 8. URS8 Q concerning health and safety. o Temperature range of the Bag sealer: 80 – 220 C. 9. URS9 Q Copy of the calibration certificate must be attached to executed protocol (Refer to Test Plan (TP-02) Pre Last calibration 10. URS10 Q requisites). date________
  • 14. Company Name IQ/OQ Qualification Protocol of Bag Sealer Tests Plans. Edition: 1.00 Enclosure Test Plan (TP-03) Installation Qualification tests. Test no. Req. C/Q Acceptance criteria Acceptance Attachment Date/Init no. criteria met: number (if Yes / No applicable)* Calibration sticker of the temperature elements at- 1. URS11 Q tached to the Bag sealer. Provide documented evidence that is possible to 2. URS12 Q calibrate the temperature elements on the bag seal- ers. Give documented evidence that the design of the 3. URS13 Q Bag Sealers comply with the general specification requirements.
  • 15. Company Name IQ/OQ Qualification Protocol of Bag Sealer Tests Plans. Edition: 1.00 Enclosure Test Plan (TP-04) Operational Qualification tests. Test no. Req. C/Q Acceptance criteria Acceptance Attachment Date/Init no. criteria met: number (if Yes / No applicable)* 1. URS14 Q Display turns on when power is switch on. 2. URS15 Q Bag sealer must automatically pulls the paper bag through the device. Keyboard is working and the typed text is displayed 3. URS16 Q correctly on the display. Sealing quality: Bag sealer must produce a visual 4. URS17 Q regularly weld, without damaging bag. The text typed in Bag sealer is printed on autoclave bag, and text include:  Date of sterilization;  Date of expiration; 5. URS18 Q  Lot number;  User ID.  Date is stated in the correct format YYYY- MM-DD (YYYY= Year, MM= Month, DD= Day).
  • 16. Company Name Qualification Protocol of Bag Sealer XXX Edition: 1.00 Page 1 of 3 8 Deviation (non-conformance) Report Non–conformance/Deviation Report Protocol number : Number of deviation: Deviation description : Signed by: Date: Init: Reason and proposal of corrective action: Signed by: Date: Init:
  • 17. Company Name Qualification Protocol of Bag Sealer XXX Edition: 1.00 Page 2 of 3 Conclusion: Signed by: Date: Init: QA Approved by: Date: Init:
  • 18. Company Name Qualification Protocol of Bag Sealer XXX Edition: 1.00 Page 3 of 3 9 Attachments Record the details of each attachment made to this executed protocol. Each attachment must be signed and dated, and the pages numbered un- der the page X of Y convention (including Protocol number): Attachment Initial & date Number of pages number : Description Signed by: Date: Initial:
  • 19. Company name Qualification Protocol of Bag Sealer Edition: 1.00 Page 1 of 1 Change History Edition Effective date Description of change Revised without changes Date / Sign. 1.0 January 2011 Initial version