SlideShare une entreprise Scribd logo
1  sur  69
STEAM TURBINE
CONTENT
I. Introdution
II. Working principle
III. Construction
IV. Operation
What is the Turbine?What is the Turbine?
TURBINE is a power machine to drive working machine such asTURBINE is a power machine to drive working machine such as
compressor, pump, electrical generator.compressor, pump, electrical generator.
 Steam TurbineSteam Turbine
 Gas TurbineGas Turbine
 Water TurbineWater Turbine
Steam TurbineSteam Turbine
Gas TurbineGas Turbine
Water TurbineWater Turbine
 Steam turbines are made in a variety of sizes ranging fromSteam turbines are made in a variety of sizes ranging from
small <0.75 kW (<1 hp) units (rare) used as mechanical drivessmall <0.75 kW (<1 hp) units (rare) used as mechanical drives
for pumps, compressors and other shaft driven equipment, tofor pumps, compressors and other shaft driven equipment, to
1 500 000 kW (1.51 500 000 kW (1.5 GWGW; 2 000 000 hp) turbines used to; 2 000 000 hp) turbines used to
generate electricity.generate electricity.
 Selection of steam turbine type depend on the overall processSelection of steam turbine type depend on the overall process
requirement and configuration as well as project/ operationrequirement and configuration as well as project/ operation
cost reason.cost reason.
Parts and equipmentParts and equipment
 Steam turbine can be classified as theSteam turbine can be classified as the
following:following:
• By steam supply and exhaust conditions:By steam supply and exhaust conditions:
 Back pressure Turbine or none condensing turbine.Back pressure Turbine or none condensing turbine.
 Condensing Turbine.Condensing Turbine.
 Extraction Steam Turbine.Extraction Steam Turbine.
 Induction Steam TurbineInduction Steam Turbine
 Reheat Steam TurbineReheat Steam Turbine
• By Blades and Stages design:By Blades and Stages design:
 Impulse TurbineImpulse Turbine
 Reaction Turbine.Reaction Turbine.
Non-Condensing Steam Turbine:Non-Condensing Steam Turbine:
Non-condensing or back pressure turbines are most widely usedNon-condensing or back pressure turbines are most widely used
for process steam applications. The exhaust pressure is controlledfor process steam applications. The exhaust pressure is controlled
by a regulating valve to suit the needs of the process steamby a regulating valve to suit the needs of the process steam
pressure.pressure.
Condensing Steam TurbineCondensing Steam Turbine
Condensing turbines are most commonly found in electricalCondensing turbines are most commonly found in electrical
power plants. These turbines exhaust steam from a boiler in apower plants. These turbines exhaust steam from a boiler in a
partially condensed state, typically of a quality near 90%, at apartially condensed state, typically of a quality near 90%, at a
pressure well below atmospheric to a condenser.pressure well below atmospheric to a condenser.
Extraction Steam Turbine:Extraction Steam Turbine:
In an extracting type turbine, steam is released from variousIn an extracting type turbine, steam is released from various
stages of the turbine, and used for industrial process needs or sentstages of the turbine, and used for industrial process needs or sent
to boiler feed water heater to improve overall cycle efficiency.to boiler feed water heater to improve overall cycle efficiency.
Extraction flows may be controlled with a valve, or leftExtraction flows may be controlled with a valve, or left
uncontrolled.uncontrolled...
Induction Steam TurbineInduction Steam Turbine
Induction turbines introduce low pressure steam at anInduction turbines introduce low pressure steam at an
intermediate stage to produce additional power.intermediate stage to produce additional power.
Reheat Steam TurbineReheat Steam Turbine
In a reheat turbine, steam flow exits from a high pressure sectionIn a reheat turbine, steam flow exits from a high pressure section
of the turbine and is returned to the boiler where additionalof the turbine and is returned to the boiler where additional
superheat is added. The steam then goes back into ansuperheat is added. The steam then goes back into an
intermediate pressure section of the turbine and continues itsintermediate pressure section of the turbine and continues its
expansion. Using reheat in a cycle increases the work outputexpansion. Using reheat in a cycle increases the work output
from the turbine and also the expansion reaches conclusionfrom the turbine and also the expansion reaches conclusion
before the steam condenses, there by minimizing the erosion ofbefore the steam condenses, there by minimizing the erosion of
Impulse & Reaction TurbinesImpulse & Reaction Turbines
Impulse TurbinesImpulse Turbines
Impulse Steam TurbineImpulse Steam Turbine
 On Impulse Turbine a thermal expansion take place only in theOn Impulse Turbine a thermal expansion take place only in the
nozzles and static energy is converted to the kinetic energynozzles and static energy is converted to the kinetic energy
 There is no pressure different at inlet and outlet of blades onThere is no pressure different at inlet and outlet of blades on
the rotor, because the thermal expansion only in the nozzles. Itthe rotor, because the thermal expansion only in the nozzles. It
means no thrust force acting on the rotor disc.means no thrust force acting on the rotor disc.
Reaction Steam TurbineReaction Steam Turbine
Reaction stage
Thermal expansion occurs both in the nozzles and blades. The impulse force
comes from the kinetic energy which is converted in the nozzles, and
reaction force created in the blades comes due to decreasing steam pressure.
These two forces produce the rotation torque of the blades on the rotor. On
this type, differential pressure between the inlet and outlet of blades
generates thrust force to turbine shaft. Therefore, to reduce the thrust force
acting on the shaft, shaft diameter is equal to the diameter of the blade root,
and blades are mounted on shaft directly.
Impulse and Reaction TurbineImpulse and Reaction Turbine
Actually, Steam turbine using in the refineries are combined impulse andActually, Steam turbine using in the refineries are combined impulse and
reaction to get more advantages and less disadvantagesreaction to get more advantages and less disadvantages
NozzleNozzle
Thrust & Radial bearingsThrust & Radial bearings
Journal BearingJournal Bearing
Self Equalizing tilting padSelf Equalizing tilting pad
Sealing ProblemSealing Problem
Labyrinth effectivenessLabyrinth effectiveness
Sealing of Steam TurbineSealing of Steam Turbine
Monitoring systemMonitoring system
Function of Trip Throttle Valve (TTV)Function of Trip Throttle Valve (TTV)
 Adjustment of steam flow to turbine duringAdjustment of steam flow to turbine during
start-up.start-up.
 Close valve quickly as the pressure ofClose valve quickly as the pressure of
control oil lose due to interlock trip ofcontrol oil lose due to interlock trip of
turbine or push the button trip.turbine or push the button trip.
 Partial stroke test of TTV.Partial stroke test of TTV.
Trip Valve and Control ValveTrip Valve and Control Valve
Trip ValveTrip Valve
Trip Throttle ValveTrip Throttle Valve
Trip Throttle ValveTrip Throttle Valve
Throttle valve operationThrottle valve operation
 Condensing system(Cond)Condensing system(Cond)
• Air in condenser is sucked by steam ejector and send to inter coolerAir in condenser is sucked by steam ejector and send to inter cooler
together with ejector driving steam. In inter cooler steam is cooltogether with ejector driving steam. In inter cooler steam is cool
down by condensed water and convert to water and returns todown by condensed water and convert to water and returns to
condeser through siphon tube.condeser through siphon tube.
• Air in inter cooler is suck again by steam ejector and send to afterAir in inter cooler is suck again by steam ejector and send to after
cooler and only water in after cooler return to condenser throughcooler and only water in after cooler return to condenser through
steam trap and air goes to outside.steam trap and air goes to outside.
Assume that:
- Steam stream meets all the conditions about pressure and
temperatue before to be taken to turbine.
- All the systems including: electrical, control, pneumatic system,
closed cooling water system, condensate system, feed water
system, boiler) in normal operation condition. No more failure on
the devices
The steps for starting turbine as following:
Start-up Procedure
OPERATION
1. Placing the turbine lubrication oil system in service:
- Start one duty pump and place the remain in spare
- Test change over
- Check parameter: pressure,temperature, condition of cooler,
filter..
2. Running turning gear system:
- Turning gear is done before start up and after shutdown turbine.
- The turning gear times depend on the outage duration of turbine
(start up) or metal temperature (shutdown), may be from severe
hours to one day in case of start up.
Less than one day: 2 hours
Up to7 days: 6 hours
Up to 30 days: 12 hours
Over 30 days: 24 hours
Normally, a motor is used for turning gear. The turning speed varies
from above ten rpm to hundred rpm.
3. Placing the turbine governing system (or EHC)
in service:
- Start the hydraulic pump, check header pressure
- Check condition of valve and pipe is not abnormal
- Trip test (by push Emergency stop button)
- Setting initial loading (for generator driven) or no-load
speed (compressor or pump driven) and loading limiter
(gradient)
4. Pre-runup checks of turbine valves
- In order to detect valve malfunction before steam admitted to the
turbine
- If having any problem in valve operation , it must be repaired
before turbine start up
- The valves are tested including stop valves and control valves
- During the valve checks, the turbine isolating valves close to
prevent steam flow through the turbine. Once valve completely
checked, these valve open to allow steam flow to the emergency
stop valve.
5. Place the condensate cooling water (ccw) system
in service:
-Start ccw pump, check the parameters
-Place the condensate cleaning system in service
-Place vacumn the primary system (for water box) in service
(if installed)
-Monitoring parameters..
6. Place the gland sealing steam system in service:
- To sealing turbine before pulling condensate vacumn
- Before start up, gland sealing steam is extracted from the
live steam system ( or auxiliary steam systeam) and
decreased both pressure and temperature (pressure: sligher
than atmospheric about 30-40 mbar, temperature: different
from metal temperature about 50oC)
- Check the gland steam condenser in normal condition
7. Pulling condenser vacumn:
Doing before start up:
-To reduce the tendency of the LP turbine exhause to overheat
-To prevent excessive flow – induced vibration of moving
blades in the turbine last stage
Activities:
-Start the vacumn pumps or ejectors.
-Monitoring the condensate pressure below 150 mbara
8. Placing the LP turbine exhaust cooling system in
service:
- Supply the cooling spray water to protect the LP turbine last
stages, condensate tubes from overheating when turbine
exhaust temperature is high.
- The control valve will open and closing base on exhaust
temperature.
9. Turbine warm-up
-To reduce thermal stress caused by temperature different
between live steam and turbine metal
-Normally, a control valve is used to extract steam from live
steam and taken to the turbine. The temperature rising of
turbine metal is limited and depend on the initial turbine metal
temperature, may from 30-100o
C/hour.
-After temperature different between live steam and turbine
metal below 50o
C, can finish warm-up step.
10. Start - up turbine:
Base on initial turbine metal temperature, can classify 3 start up
modes:
- Cold start: Turbine metal temperature < 150o
C
- Warm start: Turbine metal temperature :150o
C - 410o
C
- Hot start: Turbine metal temperature > 410o
C
Before start up, operators must carefully check performance of all the
system concerned are normal and ready, example: vacumn pressure,
lube oil pressure and temperature, position of drain valve….
-Setting the speed target, run up rate, initial loading, holding speed,
warm up time.. base on mismatch diagram. Carefully check in case of
auto-setting.
-Press start button to run up turbine.
-The control valve will slowly open and steam flow to the turbine for
rotary
-Turning gear disengaged and turbine run up base on start up curve.
Start up curve
Start up on DCS
Monitoring in operation:
- Critical speed
- Shaft eccentricity
- Thermal stress
- Shaft vibration
- Differential Expansion
- Temperature: lube oil temperature, bearing metal temperature
- Turbine exhaust hood: Vacumn, temperature,
- Steam qualities: Silica, conductivity, pH
STEAM TURBINE BASIC
STEAM TURBINE BASIC
STEAM TURBINE BASIC
STEAM TURBINE BASIC
STEAM TURBINE BASIC
STEAM TURBINE BASIC

Contenu connexe

Tendances

[PPT] on Steam Turbine
[PPT] on Steam Turbine[PPT] on Steam Turbine
[PPT] on Steam TurbineSumit Sharma
 
STEAM TURBINES Governing System & TROUBLE SHOOTING
STEAM TURBINES Governing System & TROUBLE SHOOTINGSTEAM TURBINES Governing System & TROUBLE SHOOTING
STEAM TURBINES Governing System & TROUBLE SHOOTINGAshish Kumar Jain
 
centrifugal compressors overview
centrifugal compressors overviewcentrifugal compressors overview
centrifugal compressors overviewUsman Ali
 
Turbine-Over-Hauling-Procedure - Siemens - Recommends Birkosit
Turbine-Over-Hauling-Procedure - Siemens - Recommends BirkositTurbine-Over-Hauling-Procedure - Siemens - Recommends Birkosit
Turbine-Over-Hauling-Procedure - Siemens - Recommends BirkositProject Sales Corp
 
Steam turbine introduction & maintenance ppt
Steam turbine introduction & maintenance pptSteam turbine introduction & maintenance ppt
Steam turbine introduction & maintenance pptBiswajit Mohanty
 
Steam turbine - Machine components
Steam turbine - Machine componentsSteam turbine - Machine components
Steam turbine - Machine componentsAnaseem Hanini
 
Steam turbine and its types
Steam turbine and its typesSteam turbine and its types
Steam turbine and its typesSanila Khalid
 
Steam turbine power plant
Steam turbine power plantSteam turbine power plant
Steam turbine power plantTarek Erin
 
BASIC PARTS OF STEAM TURBINE
BASIC PARTS OF STEAM TURBINEBASIC PARTS OF STEAM TURBINE
BASIC PARTS OF STEAM TURBINESONAM PALJOR
 
Mini project ppt on working of steam turbine and its auxiliaries
Mini project ppt on working of steam turbine and its auxiliariesMini project ppt on working of steam turbine and its auxiliaries
Mini project ppt on working of steam turbine and its auxiliariesjyotishmathi college
 
Turbine Governing System
Turbine Governing SystemTurbine Governing System
Turbine Governing SystemSalil Vaidya
 
Pulverized coal fired boiler startup procedure
Pulverized coal fired boiler startup procedurePulverized coal fired boiler startup procedure
Pulverized coal fired boiler startup procedureAshvani Shukla
 
Thermal Power Plant Simulator, Cold, warm and Hot rolling of Steam Turbine
Thermal Power Plant Simulator, Cold, warm and Hot rolling of Steam TurbineThermal Power Plant Simulator, Cold, warm and Hot rolling of Steam Turbine
Thermal Power Plant Simulator, Cold, warm and Hot rolling of Steam TurbineManohar Tatwawadi
 
INTRODUCTION TO GOVERNING
INTRODUCTION TO GOVERNINGINTRODUCTION TO GOVERNING
INTRODUCTION TO GOVERNINGSURAJ KUMAR
 

Tendances (20)

[PPT] on Steam Turbine
[PPT] on Steam Turbine[PPT] on Steam Turbine
[PPT] on Steam Turbine
 
STEAM TURBINES Governing System & TROUBLE SHOOTING
STEAM TURBINES Governing System & TROUBLE SHOOTINGSTEAM TURBINES Governing System & TROUBLE SHOOTING
STEAM TURBINES Governing System & TROUBLE SHOOTING
 
centrifugal compressors overview
centrifugal compressors overviewcentrifugal compressors overview
centrifugal compressors overview
 
Turbine-Over-Hauling-Procedure - Siemens - Recommends Birkosit
Turbine-Over-Hauling-Procedure - Siemens - Recommends BirkositTurbine-Over-Hauling-Procedure - Siemens - Recommends Birkosit
Turbine-Over-Hauling-Procedure - Siemens - Recommends Birkosit
 
Gas turbine
Gas turbine Gas turbine
Gas turbine
 
Steam turbine introduction & maintenance ppt
Steam turbine introduction & maintenance pptSteam turbine introduction & maintenance ppt
Steam turbine introduction & maintenance ppt
 
Steam turbine - Machine components
Steam turbine - Machine componentsSteam turbine - Machine components
Steam turbine - Machine components
 
Steam turbine and its types
Steam turbine and its typesSteam turbine and its types
Steam turbine and its types
 
Gas turbine
Gas turbine Gas turbine
Gas turbine
 
Steam turbine power plant
Steam turbine power plantSteam turbine power plant
Steam turbine power plant
 
BASIC PARTS OF STEAM TURBINE
BASIC PARTS OF STEAM TURBINEBASIC PARTS OF STEAM TURBINE
BASIC PARTS OF STEAM TURBINE
 
Mini project ppt on working of steam turbine and its auxiliaries
Mini project ppt on working of steam turbine and its auxiliariesMini project ppt on working of steam turbine and its auxiliaries
Mini project ppt on working of steam turbine and its auxiliaries
 
Turbine Governing System
Turbine Governing SystemTurbine Governing System
Turbine Governing System
 
Reciprocating Compressor
Reciprocating CompressorReciprocating Compressor
Reciprocating Compressor
 
Pulverized coal fired boiler startup procedure
Pulverized coal fired boiler startup procedurePulverized coal fired boiler startup procedure
Pulverized coal fired boiler startup procedure
 
Thermal Power Plant Simulator, Cold, warm and Hot rolling of Steam Turbine
Thermal Power Plant Simulator, Cold, warm and Hot rolling of Steam TurbineThermal Power Plant Simulator, Cold, warm and Hot rolling of Steam Turbine
Thermal Power Plant Simulator, Cold, warm and Hot rolling of Steam Turbine
 
Steam turbine
Steam turbineSteam turbine
Steam turbine
 
Turbine safety protection
Turbine safety protectionTurbine safety protection
Turbine safety protection
 
INTRODUCTION TO GOVERNING
INTRODUCTION TO GOVERNINGINTRODUCTION TO GOVERNING
INTRODUCTION TO GOVERNING
 
Condensate system
Condensate systemCondensate system
Condensate system
 

En vedette

Steam Turbine Fundamentals
Steam Turbine FundamentalsSteam Turbine Fundamentals
Steam Turbine FundamentalsJosh Lowndes
 
Steam Turbines
Steam Turbines Steam Turbines
Steam Turbines Amir Ayad
 
Types of turbine & thier application
Types of turbine & thier applicationTypes of turbine & thier application
Types of turbine & thier applicationdaudsangeenkhan
 
Basic Mechanical Engineering-Steam turbines
Basic Mechanical Engineering-Steam turbines  Basic Mechanical Engineering-Steam turbines
Basic Mechanical Engineering-Steam turbines Steve M S
 
steam turbine turbine interlocks for (KWU turbine)
steam turbine turbine interlocks for (KWU turbine)steam turbine turbine interlocks for (KWU turbine)
steam turbine turbine interlocks for (KWU turbine)Billa ParameswaraRao
 
STUDY AND ANALYSIS OF STEAM TURBINE AND TURBINE LOSSES
STUDY AND ANALYSIS OF STEAM TURBINE AND TURBINE LOSSESSTUDY AND ANALYSIS OF STEAM TURBINE AND TURBINE LOSSES
STUDY AND ANALYSIS OF STEAM TURBINE AND TURBINE LOSSESMohammed Sameer
 
Gas Turbine Training Power Point -Sample
Gas Turbine Training Power Point -SampleGas Turbine Training Power Point -Sample
Gas Turbine Training Power Point -SampleAli Rafiei
 
Maintainence OF STEAM TURBINE
Maintainence OF STEAM TURBINEMaintainence OF STEAM TURBINE
Maintainence OF STEAM TURBINESAI SHARATH GAMPA
 
Steam turbine
Steam turbineSteam turbine
Steam turbinewatbN kh
 
How to Improve Steam Turbine Head Rate and Increase Output
How to Improve Steam Turbine Head Rate and Increase OutputHow to Improve Steam Turbine Head Rate and Increase Output
How to Improve Steam Turbine Head Rate and Increase OutputMargaret Harrison
 
Steam turbine
Steam turbineSteam turbine
Steam turbineNathan
 
condensate system
condensate systemcondensate system
condensate systemvikrantdesh
 
660 mw turbo generator &amp; its auxiliaries
660 mw turbo generator &amp; its auxiliaries660 mw turbo generator &amp; its auxiliaries
660 mw turbo generator &amp; its auxiliariesAshvani Shukla
 

En vedette (20)

Steam Turbine Fundamentals
Steam Turbine FundamentalsSteam Turbine Fundamentals
Steam Turbine Fundamentals
 
Steam Turbines
Steam Turbines Steam Turbines
Steam Turbines
 
Types of turbine & thier application
Types of turbine & thier applicationTypes of turbine & thier application
Types of turbine & thier application
 
Steam Turbines Basics
Steam Turbines BasicsSteam Turbines Basics
Steam Turbines Basics
 
Ppt of turbine
Ppt of turbinePpt of turbine
Ppt of turbine
 
Basic Mechanical Engineering-Steam turbines
Basic Mechanical Engineering-Steam turbines  Basic Mechanical Engineering-Steam turbines
Basic Mechanical Engineering-Steam turbines
 
Steam turbine
Steam turbineSteam turbine
Steam turbine
 
Steam turbine and its types
Steam turbine and its typesSteam turbine and its types
Steam turbine and its types
 
Steam turbine
Steam turbine Steam turbine
Steam turbine
 
Steam Turbines
Steam TurbinesSteam Turbines
Steam Turbines
 
steam turbine turbine interlocks for (KWU turbine)
steam turbine turbine interlocks for (KWU turbine)steam turbine turbine interlocks for (KWU turbine)
steam turbine turbine interlocks for (KWU turbine)
 
STUDY AND ANALYSIS OF STEAM TURBINE AND TURBINE LOSSES
STUDY AND ANALYSIS OF STEAM TURBINE AND TURBINE LOSSESSTUDY AND ANALYSIS OF STEAM TURBINE AND TURBINE LOSSES
STUDY AND ANALYSIS OF STEAM TURBINE AND TURBINE LOSSES
 
Gas Turbine Training Power Point -Sample
Gas Turbine Training Power Point -SampleGas Turbine Training Power Point -Sample
Gas Turbine Training Power Point -Sample
 
Maintainence OF STEAM TURBINE
Maintainence OF STEAM TURBINEMaintainence OF STEAM TURBINE
Maintainence OF STEAM TURBINE
 
Steam turbine
Steam turbineSteam turbine
Steam turbine
 
Steam turbine
Steam turbineSteam turbine
Steam turbine
 
How to Improve Steam Turbine Head Rate and Increase Output
How to Improve Steam Turbine Head Rate and Increase OutputHow to Improve Steam Turbine Head Rate and Increase Output
How to Improve Steam Turbine Head Rate and Increase Output
 
Steam turbine
Steam turbineSteam turbine
Steam turbine
 
condensate system
condensate systemcondensate system
condensate system
 
660 mw turbo generator &amp; its auxiliaries
660 mw turbo generator &amp; its auxiliaries660 mw turbo generator &amp; its auxiliaries
660 mw turbo generator &amp; its auxiliaries
 

Similaire à STEAM TURBINE BASIC

Steam Turbine_edit.pptx
Steam Turbine_edit.pptxSteam Turbine_edit.pptx
Steam Turbine_edit.pptxKrishhGupta
 
TG_AUX_TRG_PowerPoint Presentation 3.ppt
TG_AUX_TRG_PowerPoint Presentation 3.pptTG_AUX_TRG_PowerPoint Presentation 3.ppt
TG_AUX_TRG_PowerPoint Presentation 3.pptsoumenmandal47
 
Turbine
TurbineTurbine
TurbineHelp+
 
Steam turbine
Steam turbineSteam turbine
Steam turbinenell0511
 
STEAM AND GAS TURBINES ppt
STEAM AND GAS TURBINES pptSTEAM AND GAS TURBINES ppt
STEAM AND GAS TURBINES pptANKIT GUPTA
 
Turbomachinery Turbine pump Compressor.ppt
Turbomachinery Turbine pump Compressor.pptTurbomachinery Turbine pump Compressor.ppt
Turbomachinery Turbine pump Compressor.pptsbpatalescoe
 
UNIT-III_Steam_Turbine (1).pdf
UNIT-III_Steam_Turbine (1).pdfUNIT-III_Steam_Turbine (1).pdf
UNIT-III_Steam_Turbine (1).pdfManivannan727901
 
Power plant engineering chapter 2
Power plant engineering chapter 2Power plant engineering chapter 2
Power plant engineering chapter 2swathi1995vangaram
 
thermal power plant suratgarh ppt
thermal power plant suratgarh ppt thermal power plant suratgarh ppt
thermal power plant suratgarh ppt Yogesh Singh Takhar
 
MODULE-V_STEAM TURBINES.pptx
MODULE-V_STEAM TURBINES.pptxMODULE-V_STEAM TURBINES.pptx
MODULE-V_STEAM TURBINES.pptxDhruvBagade
 

Similaire à STEAM TURBINE BASIC (20)

steam turbine.pptx
steam turbine.pptxsteam turbine.pptx
steam turbine.pptx
 
Steam Turbine.pdf
Steam Turbine.pdfSteam Turbine.pdf
Steam Turbine.pdf
 
Energy Centre
Energy CentreEnergy Centre
Energy Centre
 
Steam Turbine_edit.pptx
Steam Turbine_edit.pptxSteam Turbine_edit.pptx
Steam Turbine_edit.pptx
 
steam turbines
steam turbinessteam turbines
steam turbines
 
TG_AUX_TRG_PowerPoint Presentation 3.ppt
TG_AUX_TRG_PowerPoint Presentation 3.pptTG_AUX_TRG_PowerPoint Presentation 3.ppt
TG_AUX_TRG_PowerPoint Presentation 3.ppt
 
Turbine
TurbineTurbine
Turbine
 
Steam turbine
Steam turbineSteam turbine
Steam turbine
 
bhel_report_STM
bhel_report_STMbhel_report_STM
bhel_report_STM
 
Steam turbine
Steam turbineSteam turbine
Steam turbine
 
STEAM AND GAS TURBINES ppt
STEAM AND GAS TURBINES pptSTEAM AND GAS TURBINES ppt
STEAM AND GAS TURBINES ppt
 
BHEL training ppt
BHEL training pptBHEL training ppt
BHEL training ppt
 
Steam turbine basics
Steam turbine basicsSteam turbine basics
Steam turbine basics
 
Turbomachinery Turbine pump Compressor.ppt
Turbomachinery Turbine pump Compressor.pptTurbomachinery Turbine pump Compressor.ppt
Turbomachinery Turbine pump Compressor.ppt
 
Ppt
PptPpt
Ppt
 
UNIT-III_Steam_Turbine (1).pdf
UNIT-III_Steam_Turbine (1).pdfUNIT-III_Steam_Turbine (1).pdf
UNIT-III_Steam_Turbine (1).pdf
 
Power plant engineering chapter 2
Power plant engineering chapter 2Power plant engineering chapter 2
Power plant engineering chapter 2
 
thermal power plant suratgarh ppt
thermal power plant suratgarh ppt thermal power plant suratgarh ppt
thermal power plant suratgarh ppt
 
MODULE-V_STEAM TURBINES.pptx
MODULE-V_STEAM TURBINES.pptxMODULE-V_STEAM TURBINES.pptx
MODULE-V_STEAM TURBINES.pptx
 
Steam power plant
Steam power plantSteam power plant
Steam power plant
 

Dernier

complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptSAURABHKUMAR892774
 
Input Output Management in Operating System
Input Output Management in Operating SystemInput Output Management in Operating System
Input Output Management in Operating SystemRashmi Bhat
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
11. Properties of Liquid Fuels in Energy Engineering.pdf
11. Properties of Liquid Fuels in Energy Engineering.pdf11. Properties of Liquid Fuels in Energy Engineering.pdf
11. Properties of Liquid Fuels in Energy Engineering.pdfHafizMudaserAhmad
 
Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - GuideGOPINATHS437943
 
Risk Management in Engineering Construction Project
Risk Management in Engineering Construction ProjectRisk Management in Engineering Construction Project
Risk Management in Engineering Construction ProjectErbil Polytechnic University
 
National Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdfNational Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdfRajuKanojiya4
 
Ch10-Global Supply Chain - Cadena de Suministro.pdf
Ch10-Global Supply Chain - Cadena de Suministro.pdfCh10-Global Supply Chain - Cadena de Suministro.pdf
Ch10-Global Supply Chain - Cadena de Suministro.pdfChristianCDAM
 
Crystal Structure analysis and detailed information pptx
Crystal Structure analysis and detailed information pptxCrystal Structure analysis and detailed information pptx
Crystal Structure analysis and detailed information pptxachiever3003
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Industrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.pptIndustrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.pptNarmatha D
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)Dr SOUNDIRARAJ N
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
"Exploring the Essential Functions and Design Considerations of Spillways in ...
"Exploring the Essential Functions and Design Considerations of Spillways in ..."Exploring the Essential Functions and Design Considerations of Spillways in ...
"Exploring the Essential Functions and Design Considerations of Spillways in ...Erbil Polytechnic University
 
Main Memory Management in Operating System
Main Memory Management in Operating SystemMain Memory Management in Operating System
Main Memory Management in Operating SystemRashmi Bhat
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catcherssdickerson1
 
multiple access in wireless communication
multiple access in wireless communicationmultiple access in wireless communication
multiple access in wireless communicationpanditadesh123
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 

Dernier (20)

complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.ppt
 
Input Output Management in Operating System
Input Output Management in Operating SystemInput Output Management in Operating System
Input Output Management in Operating System
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
11. Properties of Liquid Fuels in Energy Engineering.pdf
11. Properties of Liquid Fuels in Energy Engineering.pdf11. Properties of Liquid Fuels in Energy Engineering.pdf
11. Properties of Liquid Fuels in Energy Engineering.pdf
 
Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - Guide
 
Risk Management in Engineering Construction Project
Risk Management in Engineering Construction ProjectRisk Management in Engineering Construction Project
Risk Management in Engineering Construction Project
 
National Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdfNational Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdf
 
Ch10-Global Supply Chain - Cadena de Suministro.pdf
Ch10-Global Supply Chain - Cadena de Suministro.pdfCh10-Global Supply Chain - Cadena de Suministro.pdf
Ch10-Global Supply Chain - Cadena de Suministro.pdf
 
Crystal Structure analysis and detailed information pptx
Crystal Structure analysis and detailed information pptxCrystal Structure analysis and detailed information pptx
Crystal Structure analysis and detailed information pptx
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Industrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.pptIndustrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.ppt
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
"Exploring the Essential Functions and Design Considerations of Spillways in ...
"Exploring the Essential Functions and Design Considerations of Spillways in ..."Exploring the Essential Functions and Design Considerations of Spillways in ...
"Exploring the Essential Functions and Design Considerations of Spillways in ...
 
Main Memory Management in Operating System
Main Memory Management in Operating SystemMain Memory Management in Operating System
Main Memory Management in Operating System
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
 
multiple access in wireless communication
multiple access in wireless communicationmultiple access in wireless communication
multiple access in wireless communication
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 

STEAM TURBINE BASIC

  • 2. CONTENT I. Introdution II. Working principle III. Construction IV. Operation
  • 3. What is the Turbine?What is the Turbine? TURBINE is a power machine to drive working machine such asTURBINE is a power machine to drive working machine such as compressor, pump, electrical generator.compressor, pump, electrical generator.  Steam TurbineSteam Turbine  Gas TurbineGas Turbine  Water TurbineWater Turbine
  • 7.  Steam turbines are made in a variety of sizes ranging fromSteam turbines are made in a variety of sizes ranging from small <0.75 kW (<1 hp) units (rare) used as mechanical drivessmall <0.75 kW (<1 hp) units (rare) used as mechanical drives for pumps, compressors and other shaft driven equipment, tofor pumps, compressors and other shaft driven equipment, to 1 500 000 kW (1.51 500 000 kW (1.5 GWGW; 2 000 000 hp) turbines used to; 2 000 000 hp) turbines used to generate electricity.generate electricity.  Selection of steam turbine type depend on the overall processSelection of steam turbine type depend on the overall process requirement and configuration as well as project/ operationrequirement and configuration as well as project/ operation cost reason.cost reason.
  • 8.
  • 9.
  • 10. Parts and equipmentParts and equipment
  • 11.  Steam turbine can be classified as theSteam turbine can be classified as the following:following: • By steam supply and exhaust conditions:By steam supply and exhaust conditions:  Back pressure Turbine or none condensing turbine.Back pressure Turbine or none condensing turbine.  Condensing Turbine.Condensing Turbine.  Extraction Steam Turbine.Extraction Steam Turbine.  Induction Steam TurbineInduction Steam Turbine  Reheat Steam TurbineReheat Steam Turbine • By Blades and Stages design:By Blades and Stages design:  Impulse TurbineImpulse Turbine  Reaction Turbine.Reaction Turbine.
  • 12. Non-Condensing Steam Turbine:Non-Condensing Steam Turbine: Non-condensing or back pressure turbines are most widely usedNon-condensing or back pressure turbines are most widely used for process steam applications. The exhaust pressure is controlledfor process steam applications. The exhaust pressure is controlled by a regulating valve to suit the needs of the process steamby a regulating valve to suit the needs of the process steam pressure.pressure.
  • 13. Condensing Steam TurbineCondensing Steam Turbine Condensing turbines are most commonly found in electricalCondensing turbines are most commonly found in electrical power plants. These turbines exhaust steam from a boiler in apower plants. These turbines exhaust steam from a boiler in a partially condensed state, typically of a quality near 90%, at apartially condensed state, typically of a quality near 90%, at a pressure well below atmospheric to a condenser.pressure well below atmospheric to a condenser.
  • 14. Extraction Steam Turbine:Extraction Steam Turbine: In an extracting type turbine, steam is released from variousIn an extracting type turbine, steam is released from various stages of the turbine, and used for industrial process needs or sentstages of the turbine, and used for industrial process needs or sent to boiler feed water heater to improve overall cycle efficiency.to boiler feed water heater to improve overall cycle efficiency. Extraction flows may be controlled with a valve, or leftExtraction flows may be controlled with a valve, or left uncontrolled.uncontrolled...
  • 15. Induction Steam TurbineInduction Steam Turbine Induction turbines introduce low pressure steam at anInduction turbines introduce low pressure steam at an intermediate stage to produce additional power.intermediate stage to produce additional power.
  • 16. Reheat Steam TurbineReheat Steam Turbine In a reheat turbine, steam flow exits from a high pressure sectionIn a reheat turbine, steam flow exits from a high pressure section of the turbine and is returned to the boiler where additionalof the turbine and is returned to the boiler where additional superheat is added. The steam then goes back into ansuperheat is added. The steam then goes back into an intermediate pressure section of the turbine and continues itsintermediate pressure section of the turbine and continues its expansion. Using reheat in a cycle increases the work outputexpansion. Using reheat in a cycle increases the work output from the turbine and also the expansion reaches conclusionfrom the turbine and also the expansion reaches conclusion before the steam condenses, there by minimizing the erosion ofbefore the steam condenses, there by minimizing the erosion of
  • 17. Impulse & Reaction TurbinesImpulse & Reaction Turbines
  • 19. Impulse Steam TurbineImpulse Steam Turbine  On Impulse Turbine a thermal expansion take place only in theOn Impulse Turbine a thermal expansion take place only in the nozzles and static energy is converted to the kinetic energynozzles and static energy is converted to the kinetic energy  There is no pressure different at inlet and outlet of blades onThere is no pressure different at inlet and outlet of blades on the rotor, because the thermal expansion only in the nozzles. Itthe rotor, because the thermal expansion only in the nozzles. It means no thrust force acting on the rotor disc.means no thrust force acting on the rotor disc.
  • 20. Reaction Steam TurbineReaction Steam Turbine Reaction stage Thermal expansion occurs both in the nozzles and blades. The impulse force comes from the kinetic energy which is converted in the nozzles, and reaction force created in the blades comes due to decreasing steam pressure. These two forces produce the rotation torque of the blades on the rotor. On this type, differential pressure between the inlet and outlet of blades generates thrust force to turbine shaft. Therefore, to reduce the thrust force acting on the shaft, shaft diameter is equal to the diameter of the blade root, and blades are mounted on shaft directly.
  • 21. Impulse and Reaction TurbineImpulse and Reaction Turbine
  • 22. Actually, Steam turbine using in the refineries are combined impulse andActually, Steam turbine using in the refineries are combined impulse and reaction to get more advantages and less disadvantagesreaction to get more advantages and less disadvantages
  • 24.
  • 25.
  • 26.
  • 27.
  • 28.
  • 29.
  • 30.
  • 31. Thrust & Radial bearingsThrust & Radial bearings
  • 33.
  • 34.
  • 35. Self Equalizing tilting padSelf Equalizing tilting pad
  • 38. Sealing of Steam TurbineSealing of Steam Turbine
  • 40. Function of Trip Throttle Valve (TTV)Function of Trip Throttle Valve (TTV)  Adjustment of steam flow to turbine duringAdjustment of steam flow to turbine during start-up.start-up.  Close valve quickly as the pressure ofClose valve quickly as the pressure of control oil lose due to interlock trip ofcontrol oil lose due to interlock trip of turbine or push the button trip.turbine or push the button trip.  Partial stroke test of TTV.Partial stroke test of TTV.
  • 41. Trip Valve and Control ValveTrip Valve and Control Valve
  • 43. Trip Throttle ValveTrip Throttle Valve
  • 44. Trip Throttle ValveTrip Throttle Valve
  • 46.
  • 47.  Condensing system(Cond)Condensing system(Cond) • Air in condenser is sucked by steam ejector and send to inter coolerAir in condenser is sucked by steam ejector and send to inter cooler together with ejector driving steam. In inter cooler steam is cooltogether with ejector driving steam. In inter cooler steam is cool down by condensed water and convert to water and returns todown by condensed water and convert to water and returns to condeser through siphon tube.condeser through siphon tube. • Air in inter cooler is suck again by steam ejector and send to afterAir in inter cooler is suck again by steam ejector and send to after cooler and only water in after cooler return to condenser throughcooler and only water in after cooler return to condenser through steam trap and air goes to outside.steam trap and air goes to outside.
  • 48. Assume that: - Steam stream meets all the conditions about pressure and temperatue before to be taken to turbine. - All the systems including: electrical, control, pneumatic system, closed cooling water system, condensate system, feed water system, boiler) in normal operation condition. No more failure on the devices The steps for starting turbine as following: Start-up Procedure OPERATION
  • 49. 1. Placing the turbine lubrication oil system in service: - Start one duty pump and place the remain in spare - Test change over - Check parameter: pressure,temperature, condition of cooler, filter..
  • 50. 2. Running turning gear system: - Turning gear is done before start up and after shutdown turbine. - The turning gear times depend on the outage duration of turbine (start up) or metal temperature (shutdown), may be from severe hours to one day in case of start up. Less than one day: 2 hours Up to7 days: 6 hours Up to 30 days: 12 hours Over 30 days: 24 hours Normally, a motor is used for turning gear. The turning speed varies from above ten rpm to hundred rpm.
  • 51. 3. Placing the turbine governing system (or EHC) in service: - Start the hydraulic pump, check header pressure - Check condition of valve and pipe is not abnormal - Trip test (by push Emergency stop button) - Setting initial loading (for generator driven) or no-load speed (compressor or pump driven) and loading limiter (gradient)
  • 52. 4. Pre-runup checks of turbine valves - In order to detect valve malfunction before steam admitted to the turbine - If having any problem in valve operation , it must be repaired before turbine start up - The valves are tested including stop valves and control valves - During the valve checks, the turbine isolating valves close to prevent steam flow through the turbine. Once valve completely checked, these valve open to allow steam flow to the emergency stop valve.
  • 53. 5. Place the condensate cooling water (ccw) system in service: -Start ccw pump, check the parameters -Place the condensate cleaning system in service -Place vacumn the primary system (for water box) in service (if installed) -Monitoring parameters..
  • 54. 6. Place the gland sealing steam system in service: - To sealing turbine before pulling condensate vacumn - Before start up, gland sealing steam is extracted from the live steam system ( or auxiliary steam systeam) and decreased both pressure and temperature (pressure: sligher than atmospheric about 30-40 mbar, temperature: different from metal temperature about 50oC) - Check the gland steam condenser in normal condition
  • 55. 7. Pulling condenser vacumn: Doing before start up: -To reduce the tendency of the LP turbine exhause to overheat -To prevent excessive flow – induced vibration of moving blades in the turbine last stage Activities: -Start the vacumn pumps or ejectors. -Monitoring the condensate pressure below 150 mbara
  • 56. 8. Placing the LP turbine exhaust cooling system in service: - Supply the cooling spray water to protect the LP turbine last stages, condensate tubes from overheating when turbine exhaust temperature is high. - The control valve will open and closing base on exhaust temperature.
  • 57. 9. Turbine warm-up -To reduce thermal stress caused by temperature different between live steam and turbine metal -Normally, a control valve is used to extract steam from live steam and taken to the turbine. The temperature rising of turbine metal is limited and depend on the initial turbine metal temperature, may from 30-100o C/hour. -After temperature different between live steam and turbine metal below 50o C, can finish warm-up step.
  • 58. 10. Start - up turbine: Base on initial turbine metal temperature, can classify 3 start up modes: - Cold start: Turbine metal temperature < 150o C - Warm start: Turbine metal temperature :150o C - 410o C - Hot start: Turbine metal temperature > 410o C
  • 59. Before start up, operators must carefully check performance of all the system concerned are normal and ready, example: vacumn pressure, lube oil pressure and temperature, position of drain valve…. -Setting the speed target, run up rate, initial loading, holding speed, warm up time.. base on mismatch diagram. Carefully check in case of auto-setting. -Press start button to run up turbine. -The control valve will slowly open and steam flow to the turbine for rotary -Turning gear disengaged and turbine run up base on start up curve.
  • 61.
  • 62. Start up on DCS
  • 63. Monitoring in operation: - Critical speed - Shaft eccentricity - Thermal stress - Shaft vibration - Differential Expansion - Temperature: lube oil temperature, bearing metal temperature - Turbine exhaust hood: Vacumn, temperature, - Steam qualities: Silica, conductivity, pH