SlideShare a Scribd company logo
1 of 17
PROJECT FINANCE
PRESENTATION ON VHTRL AND BWSL
• PRATIK SAVLA-135
• ADITYA SHETH-171
• SAGAR SRIVASTAVA-155
• RITESH TRIPATHI-161
• RAHUL SIRSAT-149
• VISHAL WAVAL -169
ABOUT VHTRL
 First State Highway project developed on PPP in INDIA.
 SPV constituted named Vadodara Halol Toll Road Company Limited (VHTRL) .
 PPP structure-
 The VHTR project is developed under the Built, Own, Operate and Transfer (BOOT) basis.
 VHTRL was promoted by the GoG and IL&FS.
 Consortium of Punj Lloyd Limited and IRCON International Limited as contractors.
 Construction-
 included the design and completion of the road, pavement, cross drainage system, bridges, toll
facilities, medians, separators, road furniture, and horticultural aspects.
 Management Operation & maintenance-
 This includes toll collection, operating the toll plaza, traffic regulation and maintenance of the
facility.
 VHTRL is entitled to earn from advertisements, hoardings and other commercial activities at
the project site.
 ROI for IL&FS-
 The concession period is for a period of 30 years.
 In case VHTRL was unable to recover the total cost of the project, including a 20% return,
within 30 years, the concession period shall be extended by GoG for a period of 2 years at a
time until the total project cost and returns have been recovered by VHTRL.
PROCESS ANALYSIS OF VHTRL
 Inception-
• The GoG wanted to upgrade the Vadodara to Halol section of State Highway 87.
• need felt for improving efficiencies and attracting private capital for infrastructure
development
• positive environment for private sector participation
 Feasibility-
• After signing the MoA, a consulting firm was elected by GoG and IL&FS through a
competitive bidding process.
• undertaken a preliminary technical-economic feasibility study.
• GoG approved widening and strengthening of the existing two lane road to four lanes with the
provision of service roads.
• Investment recovery was recommended in the form of toll collections.
 Procurement-
• GoG entitled VHTRL the exclusive right and authority, during the concession period:
• To develop, design, engineer, finance, procure and construct the highway project
• Upon completion of construction to manage, operate and maintain the highway project.
• To demand, collect, retain and appropriate toll from the users of the facility and apply the same
to recover the total cost of the project.
• Appointed a contractor through a transparent international competitive bidding process.
The lowest price was the net present value (NPV)
1.fixed price of construction;
2.interest during construction;
3.costs during the concession period on routine maintenance, periodic maintenance
(renewal and overlay), toll systems, and toll augmentation
 Development
• Development of 31.7Km stretch in single phase was completed 4 months ahead of schedule (
18 months was schedule time )
• Environmental and Social Impact Assessment
rehabilitation of 300 affected families
Actually ONLY 10
World Bank as a 'best practice'
 Delivery-
• The toll operations commenced in October 2000
Four major items of operation:-
-Routine Maintenance (continuous)
-Periodic Overlay (every five years)
-Periodic Renewal (every fifteen years)
-Toll Operation and Management (once a year)
Risk allocation in VHTRL
• Land acquisition delay
-vacant possession to the concessionaire was a condition precedent under the agreement
• Permission delay
-Government had to facilitate approvals and permits, it was the private developer’s
responsibility to obtain the same
• Design risk
- to adhere to the performance standards and technical specifications. The contractor would
need to bear any additional costs due to rectification of construction due to non compliance
with the technical specifications.
• Revenue risk
-on account of a shortfall in traffic projections is borne by the Private Developer. However,
additional revenue streams in the form of development rights also possible at the discretion of the
GoG.
• Construction risk
-The complete construction was to be accomplished within 18 months. The increase in project cost
due to any delay had to be absorbed by the Concessionaire due to the fixed cost nature of the
contract
• Financial risk
-Any increase in the projected capital cost was to be borne by the private developer. However,
the developer was protected, in situations where the increase was beyond its control, with the
provision for extending the concession period till a 20% return was achieved.
• Political risk
-Comprehensive insurance package and GoG to at least pay compensation to meet all project
costs including takeout of lenders and other investors.
KEY LEARNINGS
• Pre-development market assessment is critical:
since such preparations can impact the long term objectives of the project.
• Competitive bidding can ensure a “better deal”
not only brings in the best private sector capabilities, but also allows the government to get
the best possible financial terms by ensuring competition and a level playing field.
• innovative financing mechanisms:
VHTR was one of the first projects to utilize several innovative financing methods. Deep
Discount Bonds financing , cumulative convertible preference shares and long term loans
from IL & FS.
• Environmentally and Socially responsive development framework: The VHTRL was the first
project that introduced Environmental and Social Safeguards measures as part of the
contractual obligation of the developer
ENVIRONMENTAL RISK ASSESSMENT
• One of the key features of this project
• Extent of resettlement
-earlier resettlement and rehabilitation of about 300 project affected families later reduced
to 10, having residential and/or commercial structures within the proposed right of way
• voluntary relocation
-of temples, schools, and environmental infrastructure
• additional facilities
-as pedestrian subways and compound walls and provided additional houses for the
relocation of communities
• minimize the negative impact
-to enhance the community benefits 550 trees were planted along the road, a noise barrier at
sensitive receptors
BWSL
• 8-Lane Bridge with 2-lanes dedicated for buses.
• Financial Implications
• Length of bridge 5.6 Km Width-2.5 Meters.
• Eco friendly material for supported Cable stayed bridge.
• Toll collection.
• About Seshadri Srinivasan.
Need for the Project
 Reduces travel time between Bandra and Worli during peak hours from 60–90 minutes to 20–
30 minutes.
 Mahim Causeway was the only road connecting the western suburbs to Mumbai's central
business district.
 Highly recommended project for Metropolitan city.
 It connects to Mumbai's arterial Annie Besant Road.
ENVIROMENTAL RISK
1) Impact on the Livelihood of Local Communities
2) Impact on water
3)Effect on Flora and Fauna
4)The Impact of Additional Traffic – Congestion in South Mumbai.
5) Impact on soil .
THANK YOU

More Related Content

What's hot

Public private partnership in development of road network
Public private partnership in development of road networkPublic private partnership in development of road network
Public private partnership in development of road networkGokul K Prasad
 
Presentation transport economics 17_may2106
Presentation transport economics 17_may2106Presentation transport economics 17_may2106
Presentation transport economics 17_may2106Sok-Tharath CHREUNG
 
Analytical comparision of BOT,BOOT and PPP models
 Analytical comparision of BOT,BOOT and PPP models Analytical comparision of BOT,BOOT and PPP models
Analytical comparision of BOT,BOOT and PPP modelsBhavin Sharma
 
Build - Operate - Transfer
Build - Operate - TransferBuild - Operate - Transfer
Build - Operate - TransferKshitij Gupta
 
Unit 1 basics of construction
Unit 1 basics of constructionUnit 1 basics of construction
Unit 1 basics of constructionSANJEEV Wazir
 
Bot(build operate transfr)
Bot(build operate transfr)Bot(build operate transfr)
Bot(build operate transfr)Kritika Garg
 
traffic characteristics
traffic characteristicstraffic characteristics
traffic characteristicskamariya keyur
 
time cost trade off
 time cost trade off time cost trade off
time cost trade offbriankirui9
 
Importance and Classification of Road
Importance and Classification of RoadImportance and Classification of Road
Importance and Classification of RoadShrikant Ingale
 
Design of flexible pavement
Design of flexible pavementDesign of flexible pavement
Design of flexible pavementBhavik A Shah
 
Report on airport engineering
Report on airport engineeringReport on airport engineering
Report on airport engineeringAbhishekChavan63
 
Understanding the Difference Between EPC and EPCM Contracts
Understanding the Difference Between EPC and EPCM ContractsUnderstanding the Difference Between EPC and EPCM Contracts
Understanding the Difference Between EPC and EPCM ContractsUGL Engineering
 
Project formulation and appraisal
Project formulation and appraisalProject formulation and appraisal
Project formulation and appraisalSurya C D
 

What's hot (20)

Public private partnership in development of road network
Public private partnership in development of road networkPublic private partnership in development of road network
Public private partnership in development of road network
 
WORKS MANAGEMENT IN CPWD PART-I
WORKS MANAGEMENT IN CPWD PART-IWORKS MANAGEMENT IN CPWD PART-I
WORKS MANAGEMENT IN CPWD PART-I
 
Construction equipment
Construction equipmentConstruction equipment
Construction equipment
 
Detailed project report
Detailed project reportDetailed project report
Detailed project report
 
Presentation transport economics 17_may2106
Presentation transport economics 17_may2106Presentation transport economics 17_may2106
Presentation transport economics 17_may2106
 
Analytical comparision of BOT,BOOT and PPP models
 Analytical comparision of BOT,BOOT and PPP models Analytical comparision of BOT,BOOT and PPP models
Analytical comparision of BOT,BOOT and PPP models
 
Build - Operate - Transfer
Build - Operate - TransferBuild - Operate - Transfer
Build - Operate - Transfer
 
Valuation
ValuationValuation
Valuation
 
Unit 1 basics of construction
Unit 1 basics of constructionUnit 1 basics of construction
Unit 1 basics of construction
 
Valuation
ValuationValuation
Valuation
 
Bot(build operate transfr)
Bot(build operate transfr)Bot(build operate transfr)
Bot(build operate transfr)
 
traffic characteristics
traffic characteristicstraffic characteristics
traffic characteristics
 
time cost trade off
 time cost trade off time cost trade off
time cost trade off
 
Importance and Classification of Road
Importance and Classification of RoadImportance and Classification of Road
Importance and Classification of Road
 
Design of flexible pavement
Design of flexible pavementDesign of flexible pavement
Design of flexible pavement
 
Concrete equipment
Concrete equipmentConcrete equipment
Concrete equipment
 
Module 2:Resource Management,Construction Equipments,Materials Inventory by D...
Module 2:Resource Management,Construction Equipments,Materials Inventory by D...Module 2:Resource Management,Construction Equipments,Materials Inventory by D...
Module 2:Resource Management,Construction Equipments,Materials Inventory by D...
 
Report on airport engineering
Report on airport engineeringReport on airport engineering
Report on airport engineering
 
Understanding the Difference Between EPC and EPCM Contracts
Understanding the Difference Between EPC and EPCM ContractsUnderstanding the Difference Between EPC and EPCM Contracts
Understanding the Difference Between EPC and EPCM Contracts
 
Project formulation and appraisal
Project formulation and appraisalProject formulation and appraisal
Project formulation and appraisal
 

Viewers also liked

Project Financing
Project FinancingProject Financing
Project Financingkhankm
 
An introduction to project finance
An introduction to project financeAn introduction to project finance
An introduction to project financeAnurag Jaiswal
 
Project financing methods
Project financing methodsProject financing methods
Project financing methodsDaniel Oskooei
 
Financing of the Project
Financing of the ProjectFinancing of the Project
Financing of the ProjectDilip Pandey
 
Bandra Worli Sea Link #BWSL
Bandra Worli Sea Link #BWSLBandra Worli Sea Link #BWSL
Bandra Worli Sea Link #BWSLPriyanka Dalal
 
Project management
Project managementProject management
Project managementAnish Jojan
 
Project management book for mba
Project management book for mbaProject management book for mba
Project management book for mbaBikramjit Singh
 
Bandra Worli sea link
Bandra Worli sea linkBandra Worli sea link
Bandra Worli sea linkUnni Krishnan
 
Managerial Performance
Managerial PerformanceManagerial Performance
Managerial PerformanceCreatingdemand
 
Bandra Worli Bridge
Bandra Worli BridgeBandra Worli Bridge
Bandra Worli Bridgederebail2008
 
Public Private Partnership
Public Private PartnershipPublic Private Partnership
Public Private PartnershipMASIT MACEDONIA
 
Project Manager
Project ManagerProject Manager
Project ManagerParvez Ali
 
Managerial appraisal
Managerial appraisalManagerial appraisal
Managerial appraisalvavaparu
 
Development finance impact project
Development finance impact projectDevelopment finance impact project
Development finance impact projectAbel Owotemu, PMP
 
Public-Private- Partnership Projects - What, Why & How Is Risk Allocated
Public-Private- Partnership Projects - What, Why & How Is Risk AllocatedPublic-Private- Partnership Projects - What, Why & How Is Risk Allocated
Public-Private- Partnership Projects - What, Why & How Is Risk Allocatedm_l_u
 

Viewers also liked (20)

Project Financing
Project FinancingProject Financing
Project Financing
 
Project financing
Project financingProject financing
Project financing
 
An introduction to project finance
An introduction to project financeAn introduction to project finance
An introduction to project finance
 
Project financing methods
Project financing methodsProject financing methods
Project financing methods
 
Financing of the Project
Financing of the ProjectFinancing of the Project
Financing of the Project
 
MEFA I UNIT MATERIAL
MEFA I UNIT MATERIALMEFA I UNIT MATERIAL
MEFA I UNIT MATERIAL
 
Bandra Worli Sea Link #BWSL
Bandra Worli Sea Link #BWSLBandra Worli Sea Link #BWSL
Bandra Worli Sea Link #BWSL
 
Project management
Project managementProject management
Project management
 
Project management book for mba
Project management book for mbaProject management book for mba
Project management book for mba
 
Bandra Worli sea link
Bandra Worli sea linkBandra Worli sea link
Bandra Worli sea link
 
Managerial Performance
Managerial PerformanceManagerial Performance
Managerial Performance
 
Bandra Worli Bridge
Bandra Worli BridgeBandra Worli Bridge
Bandra Worli Bridge
 
Msmed act, 2006
Msmed act, 2006Msmed act, 2006
Msmed act, 2006
 
Public Private Partnership
Public Private PartnershipPublic Private Partnership
Public Private Partnership
 
Project Manager
Project ManagerProject Manager
Project Manager
 
Managerial appraisal
Managerial appraisalManagerial appraisal
Managerial appraisal
 
Development finance impact project
Development finance impact projectDevelopment finance impact project
Development finance impact project
 
Bandra worli sealink pdf
Bandra worli sealink pdfBandra worli sealink pdf
Bandra worli sealink pdf
 
Bandra worli sea link
Bandra worli sea linkBandra worli sea link
Bandra worli sea link
 
Public-Private- Partnership Projects - What, Why & How Is Risk Allocated
Public-Private- Partnership Projects - What, Why & How Is Risk AllocatedPublic-Private- Partnership Projects - What, Why & How Is Risk Allocated
Public-Private- Partnership Projects - What, Why & How Is Risk Allocated
 

Similar to Project finance ppt final

projectfinancingandpublicprivatepartnershipppp-191120191032.pdf
projectfinancingandpublicprivatepartnershipppp-191120191032.pdfprojectfinancingandpublicprivatepartnershipppp-191120191032.pdf
projectfinancingandpublicprivatepartnershipppp-191120191032.pdfSeshukumar53
 
Project financing and public private partnership (ppp)
Project financing and public private partnership (ppp)Project financing and public private partnership (ppp)
Project financing and public private partnership (ppp)M. Asim U Khan
 
Public private partnership
Public private partnershipPublic private partnership
Public private partnershipAnkit GAJJAR
 
mumbai metro PPP model.pptx
mumbai metro PPP model.pptxmumbai metro PPP model.pptx
mumbai metro PPP model.pptxTwinkleVincent2
 
Aba forum division_4_aurora_light_rail_presentation_shresta_2012_11_27
Aba forum division_4_aurora_light_rail_presentation_shresta_2012_11_27Aba forum division_4_aurora_light_rail_presentation_shresta_2012_11_27
Aba forum division_4_aurora_light_rail_presentation_shresta_2012_11_27Roland_Nikles
 
Private and Public Partnerships Move Mainstream
Private and Public Partnerships Move MainstreamPrivate and Public Partnerships Move Mainstream
Private and Public Partnerships Move MainstreamKerry Carey
 
Geology 198 Investments and Risk Management.pptx
Geology 198 Investments and Risk Management.pptxGeology 198 Investments and Risk Management.pptx
Geology 198 Investments and Risk Management.pptxRonniePenarroyo
 
Aurecon_IndII IRF Presentation Nov 2014 Expressway Development - LinkedIn
Aurecon_IndII IRF Presentation Nov 2014 Expressway Development - LinkedInAurecon_IndII IRF Presentation Nov 2014 Expressway Development - LinkedIn
Aurecon_IndII IRF Presentation Nov 2014 Expressway Development - LinkedInSteve Richards
 
The PPP model- Delhi Gurgaon Expressway.
The PPP model- Delhi Gurgaon Expressway.The PPP model- Delhi Gurgaon Expressway.
The PPP model- Delhi Gurgaon Expressway.TwinkleVincent2
 
Amritsar Inter City Bus Terminal PPP Structure and Risk mitigation matrix
Amritsar Inter City Bus Terminal PPP Structure and Risk mitigation matrixAmritsar Inter City Bus Terminal PPP Structure and Risk mitigation matrix
Amritsar Inter City Bus Terminal PPP Structure and Risk mitigation matrixNISHCHAY SAXENA
 
Freight corridor (global experieces)
Freight corridor (global experieces)Freight corridor (global experieces)
Freight corridor (global experieces)Hemant Mishra
 
2 risk lender assume (j drew) hsbc (1)
2  risk lender assume (j drew) hsbc (1)2  risk lender assume (j drew) hsbc (1)
2 risk lender assume (j drew) hsbc (1)Anish Bhatnagar
 
Infrastructure Projects and Construction contracts in ppp
Infrastructure Projects and Construction contracts in pppInfrastructure Projects and Construction contracts in ppp
Infrastructure Projects and Construction contracts in pppChhabiYadav2
 
Manjunathan.M ENS 301.pptx
Manjunathan.M ENS 301.pptxManjunathan.M ENS 301.pptx
Manjunathan.M ENS 301.pptxVASANTHKUMARK4
 
Financial and technical assistance of a project
Financial and technical assistance of a projectFinancial and technical assistance of a project
Financial and technical assistance of a projectAnuja Chavan
 
P3s for Puerto Rico - 17 May 2023 - Updated.pptx
P3s for Puerto Rico  - 17 May 2023 - Updated.pptxP3s for Puerto Rico  - 17 May 2023 - Updated.pptx
P3s for Puerto Rico - 17 May 2023 - Updated.pptxMarc Joffe
 
1915Canakkale Bridge
1915Canakkale Bridge1915Canakkale Bridge
1915Canakkale BridgeZeynepUla2
 
Alberta Transportation's First Design-Build (DB) Project - Stony Plain Road I...
Alberta Transportation's First Design-Build (DB) Project - Stony Plain Road I...Alberta Transportation's First Design-Build (DB) Project - Stony Plain Road I...
Alberta Transportation's First Design-Build (DB) Project - Stony Plain Road I...AamerShakoor
 

Similar to Project finance ppt final (20)

projectfinancingandpublicprivatepartnershipppp-191120191032.pdf
projectfinancingandpublicprivatepartnershipppp-191120191032.pdfprojectfinancingandpublicprivatepartnershipppp-191120191032.pdf
projectfinancingandpublicprivatepartnershipppp-191120191032.pdf
 
Project financing and public private partnership (ppp)
Project financing and public private partnership (ppp)Project financing and public private partnership (ppp)
Project financing and public private partnership (ppp)
 
Public private partnership
Public private partnershipPublic private partnership
Public private partnership
 
mumbai metro PPP model.pptx
mumbai metro PPP model.pptxmumbai metro PPP model.pptx
mumbai metro PPP model.pptx
 
Aba forum division_4_aurora_light_rail_presentation_shresta_2012_11_27
Aba forum division_4_aurora_light_rail_presentation_shresta_2012_11_27Aba forum division_4_aurora_light_rail_presentation_shresta_2012_11_27
Aba forum division_4_aurora_light_rail_presentation_shresta_2012_11_27
 
Private and Public Partnerships Move Mainstream
Private and Public Partnerships Move MainstreamPrivate and Public Partnerships Move Mainstream
Private and Public Partnerships Move Mainstream
 
Geology 198 Investments and Risk Management.pptx
Geology 198 Investments and Risk Management.pptxGeology 198 Investments and Risk Management.pptx
Geology 198 Investments and Risk Management.pptx
 
Aurecon_IndII IRF Presentation Nov 2014 Expressway Development - LinkedIn
Aurecon_IndII IRF Presentation Nov 2014 Expressway Development - LinkedInAurecon_IndII IRF Presentation Nov 2014 Expressway Development - LinkedIn
Aurecon_IndII IRF Presentation Nov 2014 Expressway Development - LinkedIn
 
The PPP model- Delhi Gurgaon Expressway.
The PPP model- Delhi Gurgaon Expressway.The PPP model- Delhi Gurgaon Expressway.
The PPP model- Delhi Gurgaon Expressway.
 
Amritsar Inter City Bus Terminal PPP Structure and Risk mitigation matrix
Amritsar Inter City Bus Terminal PPP Structure and Risk mitigation matrixAmritsar Inter City Bus Terminal PPP Structure and Risk mitigation matrix
Amritsar Inter City Bus Terminal PPP Structure and Risk mitigation matrix
 
Freight corridor (global experieces)
Freight corridor (global experieces)Freight corridor (global experieces)
Freight corridor (global experieces)
 
2 risk lender assume (j drew) hsbc (1)
2  risk lender assume (j drew) hsbc (1)2  risk lender assume (j drew) hsbc (1)
2 risk lender assume (j drew) hsbc (1)
 
Infrastructure Projects and Construction contracts in ppp
Infrastructure Projects and Construction contracts in pppInfrastructure Projects and Construction contracts in ppp
Infrastructure Projects and Construction contracts in ppp
 
TURNKEY PROJECT.pptx
TURNKEY PROJECT.pptxTURNKEY PROJECT.pptx
TURNKEY PROJECT.pptx
 
Manjunathan.M ENS 301.pptx
Manjunathan.M ENS 301.pptxManjunathan.M ENS 301.pptx
Manjunathan.M ENS 301.pptx
 
Financial and technical assistance of a project
Financial and technical assistance of a projectFinancial and technical assistance of a project
Financial and technical assistance of a project
 
P3s for Puerto Rico - 17 May 2023 - Updated.pptx
P3s for Puerto Rico  - 17 May 2023 - Updated.pptxP3s for Puerto Rico  - 17 May 2023 - Updated.pptx
P3s for Puerto Rico - 17 May 2023 - Updated.pptx
 
1915Canakkale Bridge
1915Canakkale Bridge1915Canakkale Bridge
1915Canakkale Bridge
 
Alberta Transportation's First Design-Build (DB) Project - Stony Plain Road I...
Alberta Transportation's First Design-Build (DB) Project - Stony Plain Road I...Alberta Transportation's First Design-Build (DB) Project - Stony Plain Road I...
Alberta Transportation's First Design-Build (DB) Project - Stony Plain Road I...
 
Cba makassar port (english)
Cba makassar port (english)Cba makassar port (english)
Cba makassar port (english)
 

More from Sagar Srivastava

Possible Financing Options for Projects in India
Possible Financing Options for Projects in IndiaPossible Financing Options for Projects in India
Possible Financing Options for Projects in IndiaSagar Srivastava
 
Public Private Patnership
Public Private Patnership Public Private Patnership
Public Private Patnership Sagar Srivastava
 
Reliance pipava and lupin gavis m&a
Reliance pipava and lupin gavis m&aReliance pipava and lupin gavis m&a
Reliance pipava and lupin gavis m&aSagar Srivastava
 
Ariel vs Surf excel Brand comparison.
Ariel vs Surf excel Brand comparison. Ariel vs Surf excel Brand comparison.
Ariel vs Surf excel Brand comparison. Sagar Srivastava
 
TRADE RELATED INTELLECTUAL PROPERTY RIGHTS
TRADE RELATED INTELLECTUAL PROPERTY RIGHTS TRADE RELATED INTELLECTUAL PROPERTY RIGHTS
TRADE RELATED INTELLECTUAL PROPERTY RIGHTS Sagar Srivastava
 
International business ppt on cases studies on JV of godrej & p&g and allianc...
International business ppt on cases studies on JV of godrej & p&g and allianc...International business ppt on cases studies on JV of godrej & p&g and allianc...
International business ppt on cases studies on JV of godrej & p&g and allianc...Sagar Srivastava
 
Airtel -Bangladesh and Africa
Airtel -Bangladesh and AfricaAirtel -Bangladesh and Africa
Airtel -Bangladesh and AfricaSagar Srivastava
 
Ranbaxy laboratories limited
Ranbaxy laboratories limitedRanbaxy laboratories limited
Ranbaxy laboratories limitedSagar Srivastava
 
Scheduling and how scheduling in best buses
Scheduling and how scheduling in best busesScheduling and how scheduling in best buses
Scheduling and how scheduling in best busesSagar Srivastava
 
Trends in marketing of movies 2014
Trends in marketing of movies 2014Trends in marketing of movies 2014
Trends in marketing of movies 2014Sagar Srivastava
 

More from Sagar Srivastava (14)

Possible Financing Options for Projects in India
Possible Financing Options for Projects in IndiaPossible Financing Options for Projects in India
Possible Financing Options for Projects in India
 
Public Private Patnership
Public Private Patnership Public Private Patnership
Public Private Patnership
 
Reliance pipava and lupin gavis m&a
Reliance pipava and lupin gavis m&aReliance pipava and lupin gavis m&a
Reliance pipava and lupin gavis m&a
 
Ariel vs Surf excel Brand comparison.
Ariel vs Surf excel Brand comparison. Ariel vs Surf excel Brand comparison.
Ariel vs Surf excel Brand comparison.
 
TRADE RELATED INTELLECTUAL PROPERTY RIGHTS
TRADE RELATED INTELLECTUAL PROPERTY RIGHTS TRADE RELATED INTELLECTUAL PROPERTY RIGHTS
TRADE RELATED INTELLECTUAL PROPERTY RIGHTS
 
FERA TO FEMA
FERA TO FEMA FERA TO FEMA
FERA TO FEMA
 
International business ppt on cases studies on JV of godrej & p&g and allianc...
International business ppt on cases studies on JV of godrej & p&g and allianc...International business ppt on cases studies on JV of godrej & p&g and allianc...
International business ppt on cases studies on JV of godrej & p&g and allianc...
 
Merger and analysis ppt
Merger and analysis pptMerger and analysis ppt
Merger and analysis ppt
 
Airtel -Bangladesh and Africa
Airtel -Bangladesh and AfricaAirtel -Bangladesh and Africa
Airtel -Bangladesh and Africa
 
Ranbaxy laboratories limited
Ranbaxy laboratories limitedRanbaxy laboratories limited
Ranbaxy laboratories limited
 
Scheduling and how scheduling in best buses
Scheduling and how scheduling in best busesScheduling and how scheduling in best buses
Scheduling and how scheduling in best buses
 
Business law
Business lawBusiness law
Business law
 
ONGC
ONGCONGC
ONGC
 
Trends in marketing of movies 2014
Trends in marketing of movies 2014Trends in marketing of movies 2014
Trends in marketing of movies 2014
 

Recently uploaded

Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3JemimahLaneBuaron
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsTechSoup
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfJayanti Pande
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfagholdier
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfAdmir Softic
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
9548086042 for call girls in Indira Nagar with room service
9548086042  for call girls in Indira Nagar  with room service9548086042  for call girls in Indira Nagar  with room service
9548086042 for call girls in Indira Nagar with room servicediscovermytutordmt
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactPECB
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Sapana Sha
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Celine George
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdfQucHHunhnh
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 

Recently uploaded (20)

Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The Basics
 
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptxINDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
Advance Mobile Application Development class 07
Advance Mobile Application Development class 07Advance Mobile Application Development class 07
Advance Mobile Application Development class 07
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
9548086042 for call girls in Indira Nagar with room service
9548086042  for call girls in Indira Nagar  with room service9548086042  for call girls in Indira Nagar  with room service
9548086042 for call girls in Indira Nagar with room service
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 

Project finance ppt final

  • 2. • PRATIK SAVLA-135 • ADITYA SHETH-171 • SAGAR SRIVASTAVA-155 • RITESH TRIPATHI-161 • RAHUL SIRSAT-149 • VISHAL WAVAL -169
  • 3. ABOUT VHTRL  First State Highway project developed on PPP in INDIA.  SPV constituted named Vadodara Halol Toll Road Company Limited (VHTRL) .  PPP structure-  The VHTR project is developed under the Built, Own, Operate and Transfer (BOOT) basis.  VHTRL was promoted by the GoG and IL&FS.  Consortium of Punj Lloyd Limited and IRCON International Limited as contractors.  Construction-  included the design and completion of the road, pavement, cross drainage system, bridges, toll facilities, medians, separators, road furniture, and horticultural aspects.
  • 4.  Management Operation & maintenance-  This includes toll collection, operating the toll plaza, traffic regulation and maintenance of the facility.  VHTRL is entitled to earn from advertisements, hoardings and other commercial activities at the project site.  ROI for IL&FS-  The concession period is for a period of 30 years.  In case VHTRL was unable to recover the total cost of the project, including a 20% return, within 30 years, the concession period shall be extended by GoG for a period of 2 years at a time until the total project cost and returns have been recovered by VHTRL.
  • 5.
  • 6. PROCESS ANALYSIS OF VHTRL  Inception- • The GoG wanted to upgrade the Vadodara to Halol section of State Highway 87. • need felt for improving efficiencies and attracting private capital for infrastructure development • positive environment for private sector participation  Feasibility- • After signing the MoA, a consulting firm was elected by GoG and IL&FS through a competitive bidding process. • undertaken a preliminary technical-economic feasibility study. • GoG approved widening and strengthening of the existing two lane road to four lanes with the provision of service roads. • Investment recovery was recommended in the form of toll collections.
  • 7.  Procurement- • GoG entitled VHTRL the exclusive right and authority, during the concession period: • To develop, design, engineer, finance, procure and construct the highway project • Upon completion of construction to manage, operate and maintain the highway project. • To demand, collect, retain and appropriate toll from the users of the facility and apply the same to recover the total cost of the project. • Appointed a contractor through a transparent international competitive bidding process. The lowest price was the net present value (NPV) 1.fixed price of construction; 2.interest during construction; 3.costs during the concession period on routine maintenance, periodic maintenance (renewal and overlay), toll systems, and toll augmentation
  • 8.  Development • Development of 31.7Km stretch in single phase was completed 4 months ahead of schedule ( 18 months was schedule time ) • Environmental and Social Impact Assessment rehabilitation of 300 affected families Actually ONLY 10 World Bank as a 'best practice'  Delivery- • The toll operations commenced in October 2000 Four major items of operation:- -Routine Maintenance (continuous) -Periodic Overlay (every five years) -Periodic Renewal (every fifteen years) -Toll Operation and Management (once a year)
  • 9. Risk allocation in VHTRL • Land acquisition delay -vacant possession to the concessionaire was a condition precedent under the agreement • Permission delay -Government had to facilitate approvals and permits, it was the private developer’s responsibility to obtain the same • Design risk - to adhere to the performance standards and technical specifications. The contractor would need to bear any additional costs due to rectification of construction due to non compliance with the technical specifications.
  • 10. • Revenue risk -on account of a shortfall in traffic projections is borne by the Private Developer. However, additional revenue streams in the form of development rights also possible at the discretion of the GoG. • Construction risk -The complete construction was to be accomplished within 18 months. The increase in project cost due to any delay had to be absorbed by the Concessionaire due to the fixed cost nature of the contract • Financial risk -Any increase in the projected capital cost was to be borne by the private developer. However, the developer was protected, in situations where the increase was beyond its control, with the provision for extending the concession period till a 20% return was achieved. • Political risk -Comprehensive insurance package and GoG to at least pay compensation to meet all project costs including takeout of lenders and other investors.
  • 11. KEY LEARNINGS • Pre-development market assessment is critical: since such preparations can impact the long term objectives of the project. • Competitive bidding can ensure a “better deal” not only brings in the best private sector capabilities, but also allows the government to get the best possible financial terms by ensuring competition and a level playing field. • innovative financing mechanisms: VHTR was one of the first projects to utilize several innovative financing methods. Deep Discount Bonds financing , cumulative convertible preference shares and long term loans from IL & FS. • Environmentally and Socially responsive development framework: The VHTRL was the first project that introduced Environmental and Social Safeguards measures as part of the contractual obligation of the developer
  • 12. ENVIRONMENTAL RISK ASSESSMENT • One of the key features of this project • Extent of resettlement -earlier resettlement and rehabilitation of about 300 project affected families later reduced to 10, having residential and/or commercial structures within the proposed right of way • voluntary relocation -of temples, schools, and environmental infrastructure • additional facilities -as pedestrian subways and compound walls and provided additional houses for the relocation of communities • minimize the negative impact -to enhance the community benefits 550 trees were planted along the road, a noise barrier at sensitive receptors
  • 13. BWSL • 8-Lane Bridge with 2-lanes dedicated for buses. • Financial Implications • Length of bridge 5.6 Km Width-2.5 Meters. • Eco friendly material for supported Cable stayed bridge. • Toll collection. • About Seshadri Srinivasan.
  • 14. Need for the Project  Reduces travel time between Bandra and Worli during peak hours from 60–90 minutes to 20– 30 minutes.  Mahim Causeway was the only road connecting the western suburbs to Mumbai's central business district.  Highly recommended project for Metropolitan city.  It connects to Mumbai's arterial Annie Besant Road.
  • 15. ENVIROMENTAL RISK 1) Impact on the Livelihood of Local Communities 2) Impact on water 3)Effect on Flora and Fauna
  • 16. 4)The Impact of Additional Traffic – Congestion in South Mumbai. 5) Impact on soil .