Project Time
management
BY: OMER ALSAYED OMER
MBA, PMP, B.Sc.(Civil Eng.) : PMO manager EWU-DIU
quote
It is useless to desire more
time if you are already
wasting what little you
have.”
-– James Allen
“
Project Scope Management processes
• establishing the
policies, procedures,
and documentation for
planning, developing,
managing, executing,
and controlling the
project schedule.
6.1 Plan Schedule
Management
• identifying and
documenting the
specific actions to be
performed to produce
the project deliverables.
6.2 Define Activities
• identifying and
documenting
relationships among the
project activities.
6.3 Sequence
Activities
• estimating the type and
quantities of material,
human resources,
equipment, or supplies
required to perform
each activity.
6.4 Estimate Activity
Resources
• estimating the number
of work periods needed
to complete individual
activities with estimated
resources.
6.5 Estimate Activity
Durations
• analyzing activity
sequences, durations,
resource requirements,
and schedule
constraints to create
the project schedule
model.
6.6 Develop Schedule
• monitoring the status of
project activities to
update project progress
and manage changes
to the schedule
baseline to achieve the
plan.
6.7 Control Schedule
Project Management Process Group
and Knowledge Area Mapping
Knowledge Area Initiating Planning Executing M& C Closing
4. Project Integration Management
4Develop
Project Charter
4.2 Develop Project
Management Plan
4.3 Direct & Manage Project
Work
4.4 Monitor & Control Project Work
4.5 Perform Integrated Change Control
4.6 Close Project
or Phase
5. Project Scope Management
5Plan Scope Management
5.2 Collect Requirements
5.3 Define Scope
5.4 Create WBS
5.5 Validate Scope
5.6 Control Scope
6. Project Time Management
6Plan Schedule Management
6.2 Define Activities
6.3 Sequence Activities
6.4 Estimate Activity Resources
6.5 Estimate Activity Durations
6.6 Develop Schedule
6.7 Control Schedule
7. Project Cost Management
7Plan Cost Management
7.2 Estimate Costs
7.3 Determine Budget
7.4 Control Costs
8. Project Quality Management 8Plan Quality Management 8.2 Perform Quality Assurance 8.3 Control Quality
9. Project Human Resource
Management
9.1 Plan Human Resource
Management
9.2 Acquire Project Team
9.3 Develop Project Team
9.4 Manage Project Team
10. Project Communications
Management
10Plan Communications Management 10.2 Manage Communications 10.3 Control Communications
11. Project Risk Management
11Plan Risk Management
11.2 Identify Risks
11.3 Perform Qualitative Risk Analysis
11.4 Perform Quantitative Risk Analysis
11.5 Plan Risk Responses
11.6 Control Risks
12. Project Procurement
Management
12Plan Procurement Management 12.2 Conduct Procurements 12.3 Control Procurements
12.4 Close
Procurements
13. Project Stakeholder
Management
13Identify
Stakeholders
13.2 Plan Stakeholder
Management
13.3 Manage Stakeholder
Engagement
13.4 Control Stakeholder
Engagement
OSO OCT 2013
Planning M& C
schedule terms
Scheduling Tool.
• A tool that provides schedule component names, definitions,
structural relationships, and formats that support the
application of a scheduling method.
Schedule Model.
• A representation of the plan for executing the project’s
activities including durations, dependencies, and other
planning information, used to produce a project schedule
along with other scheduling artifacts.
Schedule Data.
• The collection of information for describing and controlling
the schedule.
Scheduling
method(ex.CPM)
Scheduling
Tool
Schedule
Model
Project
schedule
6.1 Plan Schedule Management
Plan Schedule Management is the process of establishing the policies, procedures,
and documentation for:
provides guidance and direction on how the project
schedule will be managed throughout the project
planning, developing, managing, executing, controlling
the project schedule
6.1 Plan Schedule Management:
Inputs, Tools & Techniques, and Outputs
Inputs
Project management plan
Project charter
Enterprise environmental
factors
Organizational process
assets
T&T
Expert judgment
Analytical techniques
Meetings
Outputs
Schedule management
plan
4 Integration 5 Scope 6 Time 7 Cost 8 Quality 9 H. Resource 10 Commn. 11 Risk 12 Procurement 13 S/holders
EEF
OPA
Enterprise/
Organization
6.1 Plan Schedule
Management
Schedule management
plan
6.2 Define
Activities
OSOOCT2013
4.1 Develop
Project charter
Project charter
6.1 Plan Schedule Management
Data Flow Diagram
6.3 Sequence
Activities
6.4 Estimate
Activity Res.
4.2 Develop
Project M Plan
Project M Plan 6.5 Estimate
Activity Durations
6.6 Develop
Schedule
11.2 Identify
Risks
11.4 Perform
Quantitative
Risk Analysis
6.1 Plan Schedule Management :
Inputs
Project management plan
• Scope baseline. project scope statement and the work breakdown structure (WBS) details used for defining
activities, duration estimation, and schedule management; and
• Other scheduling related cost, risk, and communications decisions
Project charter
• summary milestone schedule and project approval requirements that will influence the management of the
project schedule
Enterprise environmental factors
• Organizational culture and structure can all influence schedule management;
• Resource availability and skills that may influence schedule planning;
• Project management software provides the scheduling tool and alternative possibilities for managing the
schedule;
• Published commercial information, such as resource productivity information, is often available from
commercial databases that track;
• Organizational work authorization systems
Organizational process assets
• Monitoring and reporting tools to be used;
• Historical information;
• Schedule control tools;
• Existing formal and informal schedule control related policies, procedures, and guidelines;
• Templates;
• Project closure guidelines;
• Change control procedures; and
• Risk control procedures including risk categories, probability definition and impact, and probability and impact
matrix.
6.1.2 Plan Schedule Management: Tools and Techniques
6.1.2.2 Analytical Techniques
PSM process may involve choosing strategic options to estimate and schedule the project such as:
◦ scheduling methodology,
◦ scheduling tools and techniques,
◦ estimating approaches,
◦ formats,
◦ project management software.
detail ways to fast track or crash
Organizational policies and procedures influence scheduling techniques
rolling wave planning
leads and lags
alternatives analysis
methods for reviewing schedule performance
6.1.2 Plan Schedule Management: OUTPUTS
6.1.3.1 Schedule Management Plan
establishes the criteria and the activities for developing, monitoring, and controlling the
schedule.
Project schedule model
development.
•The scheduling methodology and the scheduling tool
Level of accuracy. •The acceptable range used in determining realistic activity duration estimates (+contingencies).
Units of measure. •Each unit used in measurements (staff hours, weeks ,meters)
Organizational procedures links.
•The WBS provides the framework for the schedule management plan, allowing for consistency
with the estimates and resulting schedules.
Project schedule model
maintenance.
•The process used to update the status and record progress
Control thresholds. •Variance thresholds for monitoring schedule performance.
Rules of performance
measurement.
•EVM rules or other physical measurement rules of performance measurement are set. (% CALC)
Reporting formats. •The formats and frequency for the various schedule reports are defined.
Process descriptions. •Descriptions of each of the schedule management processes are documented
6.2 Define Activities
identifying and documenting the specific actions to be performed to produce
the project deliverables.
to break down work
packages into activities
that provide a basis for:
 estimating,
 scheduling,
 executing,
 monitoring,
 Controlling
the project work
Inputs
Schedule management
plan
Scope baseline
Enterprise
environmental factors
Organizational process
assets
T&T
Decomposition
Rolling wave planning
Expert judgment
Outputs
Activity list
Activity attributes
Milestone list
4 Integration 5 Scope 6 Time 7 Cost 8 Quality 9 H. Resource 10 Commn. 11 Risk 12 Procurement 13 S/holders
EEF
OPA
Enterprise/
Organization
6.1 Plan Schedule
Management
Schedule M plan
6.2 Define
Activities
OSOOCT2013
5.4 Create WBS
Scope baseline
6.2 Define Activities
Data Flow Diagram
6.3 Sequence
Activities
6.4 Estimate
Activity Res.
6.5 Estimate
Activity Durations
6.6 Develop
Schedule
Activity list
Activity attributes
Milestone list
6.2.1 Define Activities: Inputs
6.2.1.1 Schedule Management Plan:
•prescribed level of detail necessary to manage the work
6.2.1.2 Scope Baseline
•WBS, deliverables, constraints, and assumptions documented
6.2.1.3 Enterprise Environmental Factors
•Organizational cultures and structure,
•Published commercial information from commercial databases, and
•Project management information system (PMIS).
6.2.1.4 Organizational Process Assets
•Lessons learned knowledge base containing historical information
•Standardized processes,
•Templates that contain a standard activity list
•Existing formal and informal activity planning-related policies, procedures, and guidelines (scheduling methodology)
6.2.2 Define Activities:
Tools and Techniques
6.2.2.1 Decomposition
• dividing and subdividing the project scope and project deliverables into smaller, more manageable parts.
• Activities represent the effort needed to complete a work package.
• The Define Activities process defines the final outputs as activities rather than deliverables, as done in
the Create WBS process
6.2.2.2 Rolling Wave Planning
• an iterative planning technique in which the work to be accomplished in the near term is planned in detail, while
the work in the future is planned at a higher level.
• It is a form of progressive elaboration
6.2.2.3 Expert Judgment
• who are experienced and skilled in developing detailed project scope statements, the WBS, and project schedules
6.2.3 Define Activities: Outputs
6.2.3.1 Activity List
• comprehensive list that includes all schedule activities required on the project.
• The activity list also includes the activity identifier and a scope of work description for each activity in sufficient detail.
• Each activity should have a unique title that describes its place in the schedule, even if that activity title is displayed outside the context of the project
schedule.
6.2.3.2 Activity Attributes
• identifying the multiple components associated with each activity.
• the activity identifier (ID), WBS ID, and activity label or name,
• activity codes, activity description, predecessor activities, successor activities, logical relationships, leads and lags, resource requirements, imposed dates,
constraints, and assumptions.
• person responsible, geographic area, calendar, type (LOE),
• used for schedule development and for selecting, ordering, and sorting the planned schedule activities in various ways within reports.
6.2.3.3 Milestone List
• MS is a significant point or event in a project (zero duration).
• A milestone list is a list identifying all project milestones (mandatory, or optional)
• Milestones are similar to regular schedule activities, with the same structure and
6.3 Sequence Activities
identifying and documenting RELATIONSHIPS among the project activities
defines the logical
sequence of work
to obtain the
greatest efficiency
given all project
constraints
Inputs
Schedule management plan
Activity list
Activity attributes
Milestone list
Project scope statement
Enterprise environmental
factors
Organizational process assets
T&T
Precedence diagramming
method (PDM)
Dependency determination
Leads and lags
Outputs
Project schedule network
diagrams
Project documents updates
4 Integration 5 Scope 6 Time 7 Cost 8 Quality 9 H. Resource 10 Commn. 11 Risk 12 Procurement 13 S/holders
EEF
OPA
Enterprise/
Organization
6.1 Plan Schedule
Management
Schedule M plan
6.2 Define
Activities
OSOOCT2013
5.3 Define
Scope
Project scope
statement
6.3 Sequence Activities
Data Flow Diagram
6.3 Sequence
Activities
6.6 Develop
Schedule
Activity list
Activity attributes
Milestone list
Project documents
updates
Project schedule
network diagrams
Project documents
 Activity lists,
 Activity attributes,
 Milestone list, and
 Risk register.
6.3.1 Sequence Activities: Inputs
6.3.1.1 Schedule Management
Plan:
• identifies the scheduling method and tool to be used for the project, which will guide how the
activities may be sequenced
6.3.1.2 Activity List • contains all schedule activities required on the project, dependencies and other constraints
6.3.1.3 Activity Attributes • describe a necessary sequence of events or defined predecessor or successor relationships
6.3.1.4 Milestone List • scheduled dates for specific milestones, which may influence the way activities are sequenced
6.3.1.5 Project Scope Statement
• contains the product scope description (product characteristics), deliverables, project
constraints, and project assumptions
6.2.1.3 Enterprise Environmental
Factors
• Government or industry standards,
• Project management information system (PMIS),
• Scheduling tool, and
• Company work authorization systems.
6.2.1.4 Organizational Process
Assets
• project files used for scheduling methodology, existing formal and informal activity
planning-related policies, procedures, and guidelines, templates. Related activity attributes
information in templates can also contain additional descriptive information
6.3.2 Sequence Activities: Tools and Techniques
6.3.2.1 Precedence Diagramming Method
technique used for constructing a schedule model in which activities are represented by nodes
and are graphically linked by one or more logical relationships to show the sequence in which
the activities are to be performed.
Activity-on-node (AON) is one method of representing a precedence diagram
Finish-to-start (FS).
• successor activity cannot start until
• predecessor activity has finished.
• Example: The awards ceremony (successor) cannot start until the race (predecessor) has finished.
Finish-to-finish (FF).
• successor activity cannot finish until
• predecessor activity has finished.
• Example: Writing a document (predecessor) is required to finish before editing the document (successor)
can finish.
Start-to-start (SS).
• successor activity cannot start until
• predecessor activity has started.
• Example: Level concrete (successor) cannot begin until pour foundation (predecessor) begins.
Start-to-finish (SF).
• successor activity cannot finish until
• predecessor activity has started.
• Example: The first security guard shift (successor) cannot finish until the second security guard shift
(predecessor) starts
6.3.2 Sequence Activities: Tools and Techniques
6.3.2.1 Precedence Diagramming Method
Finish
-to-
Start
(FS).
Finish
-to-
Finish
(FF).
Start
-to-
Start
(SS).
6.3.2 Sequence Activities: Tools and Techniques
6.3.2.2 Dependency Determination
MANDATORY DEPENDENCIES
(HARD LOGIC).
◦ legally or contractually required or inherent in
the nature of the work.
◦ often involve physical limitations:
◦ erect the superstructure >> after the foundation has been
built
◦ a prototype has to be built >> before it can be tested.
◦ Technical dependencies may not be mandatory.
DISCRETIONARY DEPENDENCIES
(SOFT /PREFERRED LOGIC).
◦ established based on knowledge of best
practices within a particular application area or
some unusual aspect of the project where a
specific sequence is desired, even though there
may be other acceptable sequences.
◦ Discretionary dependencies should be fully
documented (create arbitrary total float values
and can limit later scheduling options).
◦ fast tracking >> should be reviewed and
considered for modification or removal.
6.3.2 Sequence Activities: Tools and Techniques
6.3.2.2 Dependency Determination
EXTERNAL DEPENDENCIES.
relationship between project activities and
non-project activities.
usually outside the project team’s control.
For example, the testing activity in a software
project may be dependent on the delivery of
hardware from an external source, or
governmental environmental hearings may
need to be held before site preparation can
begin on a construction project.
INTERNAL DEPENDENCIES.
a precedence relationship between project
activities and are generally inside the project
team’s control.
For example, if the team cannot test a
machine until they assemble it, this is an
internal mandatory dependency.
6.3.2 Sequence Activities: Tools and Techniques
6.3.2.3 Leads and Lags
LEAD
A lead is the amount of time whereby a
successor activity can be ADVANCED with
respect to a predecessor activity.
LAG
A lag is the amount of time whereby a
successor activity will be DELAYED with
respect to a predecessor activity.
F-S :lag -2w
landscaping
punch list completion
2w
S-S lag :15 days
editing the draft
punch list completion
15
days
6.3.3 Sequence Activities: OUTPUTS
6.3.3.1 Project Schedule Network Diagrams
Graphical representation of the logical relationships (dependencies).
It can include full project details, or have one or more summary activities.
A summary narrative can accompany the diagram and describe the basic approach used to
sequence the activities.
Any unusual activity sequences within the network should be fully described within the
narrative.
Start
A
B
C
D
Finish
6.4 Estimate Activity Resources
estimating the TYPE & QUANTITIES of material, human resources, equipment, or supplies required
to perform each activity
identifies the type,
quantity, &
characteristics of
resources required
to complete the
activity which
allows more
accurate cost and
duration estimates
Inputs
Schedule management plan
Activity list
Activity attributes
Resource calendars
Risk register
Activity cost estimates
Enterprise environmental factors
Organizational process assets
T&T
Expert judgment
Alternative analysis
Published estimating data
Bottom-up estimating
Project management software
Outputs
Activity resource requirements
Resource breakdown structure
Project documents updates
4 Integration 5 Scope 6 Time 7 Cost 8 Quality 9 H. Resource 10 Commn. 11 Risk 12 Procurement 13 S/holders
EEF
OPA
Enterprise/
Organization
6.1 Plan Schedule
Management
Schedule M plan
6.2 Define
Activities
OSOOCT2013
7.2 Estimate
Costs
Activity cost
estimates
6.4 Estimate Activity Resources
Data Flow Diagram
6.4 Estimate
Activity Resource
6.6 Develop Schedule
Activity list
Activity attributes
Project documents
updates
Resource breakdown
structure Project documents
 Activity list,
 Activity attributes, and
 Resource calendars.
Resource
calendars
11.2 Identify Risks
Risk register
9.2 Acquire
Project Team
12.2 Conduct
Procurements
Activity resource
requirements
9.1 Plan HRM
6.6 Estimate Activity
Durations
6.4.1 Estimate Activity Resources: Inputs
6.4.1.1 Schedule Management
Plan:
•identifies the level of accuracy and the units of measure for the resources to be estimated
6.4.1.2 Activity List • identifies the activities which will need resources
6.4.1.3 Activity Attributes
•provide the primary data input for use in estimating those resources required for each
activity in the activity list
6.4.1.4 Resource Calendars •identifies the working days and shifts on which each specific resource is available
6.4.1.5 Risk Register • Risk events may impact resource selection and availability
6.4.1.6 Activity Cost Estimates •The cost of resources may impact resource selection
6.4.1.7 Enterprise
Environmental Factors
• resource location, availability, and skills
6.4.1.8 Organizational Process
Assets
• Policies and procedures regarding staffing,
• Policies and procedures relating to rental and purchase of supplies and equipment,
• Historical information regarding types of resources used for similar work
6.4.2 Estimate Activity Resources:
Tools and Techniques6.4.2.1ExpertJudgment
•assess the
resource-
related
inputs to this
process.
6.4.2.2AlternativeAnalysis
•using various
levels of
resource
capability or
skills,
•different size
or type of
machines,
•different
tools
•Make rent-
or-buy
6.4.2.3PublishedEstimatingData
•updated
production
rates and
unit costs of
resources for
an extensive
array of
labor trades,
material,
and
equipment
6.4.2.4Bottom-UpEstimating
•aggregating
the
estimates of
the lower-
level
components
of the WBS.
6.4.2.5ProjectManagementSoftware
•scheduling
software
tool, has the
capability to
help plan,
organize,
and manage
resource
pools and
develop
resource
estimates
6.4.3 Estimate Activity Resources: Outputs
6.4.3.1 Activity
Resource
Requirements
• types and quantities of resources required for each activity in
a work package.
• These requirements then can be aggregated to determine the
estimated resources for each work package and each work
period
6.4.3.2 Resource
Breakdown Structure
• hierarchical representation of resources by category and type
Project EWR
Human
resource
Project
Controls
Admin & Fin Construction
Materials
Construction
Mat’l
E/M Mat’l Consumables.
Equipment
Plants Vehicles Machineries
6.5 Estimate Activity Durations
estimating the NUMBER of work PERIODS needed to complete individual activities with
estimated resources
provides the
amount of TIME
each activity will
take to complete,
which is a major
input into the
Develop Schedule
process
•Activity duration
estimates
•Project documents
updates
Outputs
•Expert judgment
•Analogous estimating
•Parametric estimating
•Three-point estimating
•Group decision-making
techniques
• Reserve analysis
T&T
• Schedule
management plan
• Activity list
• Activity attributes
• Activity resource
requirements
• Resource calendars
• Project scope
statement
• Risk register
• Resource breakdown
structure
•Enterprise
environmental factors
•Organizational process
assets
Inputs
4 Integration 5 Scope 6 Time 7 Cost 8 Quality 9 H. Resource 10 Commn. 11 Risk 12 Procurement 13 S/holders
EEF
OPA
Enterprise/
Organization
6.1 Plan Schedule
Management
Schedule M plan
6.2 Define Activities
OSOOCT2013
5.3 Define Scope
Project scope
statement
6.5 Estimate Activity Durations
Data Flow Diagram
6.4 Estimate Activity
Resource
6.6 Develop Schedule
Activity list
Activity attributes
Project documents updates
Resource breakdown
structure
Project documents
 Activity attributes
 Assumptions made in
developing the activity
duration estimate
Resource
calendars
11.2 Identify Risks
Risk register
9.2 Acquire
Project Team
12.2 Conduct
Procurements
Activity resource
requirements
11.2 Identify Risks
6.5 Estimate Activity
Durations
Activity duration estimates
6.5.1 Estimate Activity Durations: Inputs
Senior draughtsman
1 hours/sheet
1 No.
Junior draughtsman
4 hours/sheet
4 No.
6.5.1 Estimate Activity Durations: Inputs
6.5.1.4 Activity Resource
Requirements
• the level to which the resources assigned to the activity meet the requirements will significantly
influence the duration of most activities
6.5.1.5 Resource Calendars • availability of specific resources, type of resources, and resources with specific attributes.
6.5.1.6 Project Scope Statement
• assumptions (Existing conditions, Availability of information, and Length of the reporting periods).
• Constraints (Available skilled resources, and Contract terms and requirements).
6.5.1.7 Risk Register • provides the list of risks, along with the results of risk analysis and risk response planning.
6.5.1.8 Resource Breakdown
Structure
• provides a hierarchical structure of the identified resources by resource category and resource
type.
6.5.1.9 Enterprise Environmental
Factors
• Duration estimating databases and other reference data,
• Productivity metrics,
• Published commercial information, and
• Location of team members.
6.5.1.10 Organizational Process
Assets
• Historical duration information,
• Project calendars,
• Scheduling methodology, and
• Lessons learned.
6.5.2 Estimate Activity Durations:
Tools and Techniques
6.5.2.1 EXPERT JUDGMENT 6.5.2.2 ANALOGOUS ESTIMATING
uses parameters from a previous, similar
project, such as duration, budget, size, weight,
and complexity, as the basis for estimating the
same parameter or measure for a future
project.
less costly ,time
less accurate
Provide/recommended duration estimate
information (from prior similar projects).
Determine whether to combine methods of
estimating and how to reconcile differences
between them.
6.5.2 Estimate Activity Durations:
Tools and Techniques
6.5.2.3 PARAMETRIC ESTIMATING 6.5.2.4 THREE-POINT ESTIMATING
The accuracy of single-point activity duration
estimates may be improved by considering
estimation uncertainty and risk.
approximate range for an activity’s duration:
◦ tM (Most likely): given the resources likely to
be assigned, their productivity, realistic
expectations of availability for the activity,
dependencies on other participants, and
interruptions.
◦ tO (Optimistic). best-case scenario for the
activity.
◦ tP (Pessimistic). the worst-case scenario for
the activity.
algorithm is used to calculate cost or duration
based on historical data and project
parameters.
Parametric estimating uses a statistical
relationship between historical data and other
variables
This technique can produce higher levels of
accuracy depending upon the sophistication
and underlying data built into the model.
A. Duration of design project =
No of drawings X No of labor hours per drawing
tE = (tO + tM + tP) / 3 (Triangular Distribution)
tE = (tO + 4tM + tP) / 6 (Beta Distribution)
6.5.2 Estimate Activity Durations:
Tools and Techniques
6.5.2.5 GROUP DECISION-MAKING TECHNIQUES 6.5.2.6 RESERVE ANALYSIS
Duration estimates may include contingency reserves
(time reserves or buffers), into the project schedule to
account for schedule uncertainty. (“known-unknowns,”
, %AD, a fixed number of work periods, or may be
developed by using quantitative analysis
Contingency reserves may be separated from the
individual activities and aggregated into buffers.
As more precise information about the project
becomes available, the contingency reserve may be
used, reduced, or eliminated.
Management reserves “unknown-unknowns” are a
specified amount of the project duration withheld for
management control purposes and are reserved for
unforeseen work that is within scope of the project.
Team-based approaches, such as
brainstorming, the Delphi or nominal group
techniques, are useful for engaging team
members to improve estimate ACCURACY and
commitment to the emerging estimates.
6.5.3 Estimate Activity Durations: Outputs
6.5.3.1 Activity Duration Estimates
quantitative assessments of the likely number of time periods that are required to complete an
activity.
2 weeks ± 2 days, (8 to 12 weeks assuming a five-day workweek);
15 % probability of exceeding three weeks
6.6 Develop Schedule
ANALYZING activity sequences, durations, resource requirements, and schedule
constraints to create the project schedule model.
scheduling tool
• schedule activities,
• durations,
• resources,
• resource availabilities,
• logical relationships
schedule
model
6.6 Develop Schedule
• Schedule baseline
• Project schedule
• Schedule data
• Project calendars
• Project management plan updates
• Project documents updates
Outputs
• Schedule network analysis
• Critical path method
• Critical chain method
• Resource optimization techniques
• Modeling techniques
• Leads and lags
• Schedule compression
• Scheduling tool
T&T
• Schedule management plan
• Activity list
• Activity attributes
• Project schedule network
diagrams
• Activity resource requirements
• Resource calendars
• Activity duration estimates
• Project scope statement
• Risk register
• Project staff assignments
• Resource breakdown structure
• Enterprise environmental factors
• Organizational process assets
Inputs
4 Integration 5 Scope 6 Time 7 Cost 8 Quality 9 H. Resource 10 Commn. 11 Risk 12 Procurement 13 S/holders
EEF
OPA
Enterprise/
Organization
6.1 Plan Schedule
Management
Schedule M plan
6.2 Define Activities
OSO OCT 2013
6.6 Develop Schedule
Data Flow Diagram
5.3 Define Scope
Project scope statement 6.4 Estimate Act. Resource
6.6 Develop Schedule
Activity list
Activity attributes
Project documents (u)
Resource breakdown
structure
Project documents
 Activity resource requirements.
 Activity attributes
 Risk register
11.2 Identify Risks
Risk register
9.2 Acquire
Project Team
12.2 Conduct
Procurements
Activity resource
requirements
6.5 Estimate Activity
Durations
Activity duration estimates
Project m. plan updates
6.3 Sequence Activities
Project schedule network
diagrams
Project staff assignments
Resource calendars
Schedule baseline
Project schedule
Project calendars
6.7 Control Schedule
4.2 Develop Project
Management Plan
7.2 Estimate Costs
7.3 Determine Budget
12.1 Plan Procurement
Management
Schedule data  Schedule baseline
 Schedule management plan
6.6.1 Develop Schedule: Inputs
6.6.1.1 Schedule
Management Plan:
• Identifies the scheduling method and tool used to create the schedule, and
how the schedule is to be calculated.
6.6.1.2 Activity List • identifies the activities that will be included in the schedule model
6.6.1.3 Activity Attributes • provide the details used to build the schedule model
6.6.1.4 Project Schedule
Network Diagrams
• Contain the logical relationships of predecessors and successors that will be
used to calculate the schedule
6.6.1.5 Activity Resource
Requirements
• identify the types and quantities of resources required for each activity used to
create the schedule model
6.6.1.6 Resource Calendars • contain information on the availability of resources during the project
6.6.1.7 Activity Duration
Estimates
• contain the quantitative assessments of the likely number of work periods that
will be required to complete an activity that will be used to calculate the
schedule
6.6.1 Develop Schedule: Inputs
6.6.1.8 Project Scope
Statement
• contains assumptions and constraints that can impact the development of the
project schedule.
6.6.1.9 Risk Register
• provides the details of all identified risks and their characteristics that affect
the schedule model.
6.6.1.10 Project Staff
Assignments
• specify which resources are assigned to each activity.
6.6.1.11 Resource
Breakdown Structure
• provides the details by which resource analysis and organizational reporting
can be done.
6.2.1.3 Enterprise
Environmental Factors
• Standards,
• Communication channels
• Scheduling tool to be used in developing the schedule model.
6.2.1.4 Organizational
Process Assets
• scheduling methodology and project calendar(s)
6.6.2 Develop Schedule: Tools and Techniques
6.6.2.1 Schedule Network Analysis
technique generates the project schedule model ,employs various analytical techniques to calculate the
early and late start and finish dates for the uncompleted portions of project activities:
critical path
method
critical chain
method
what-if
analysis
resource
optimization
techniques
6.6.2 Develop Schedule: Tools and Techniques
6.6.2.2 Critical Path Method
a method used to estimate the MINIMUM project duration and determine the amount of
scheduling flexibility on the logical network paths within the schedule model.
calculates the early start, early finish, late start, and late finish dates for all activities (without
regard for any resource limitations) by performing a forward and backward pass analysis
 The critical path is the sequence of activities that represents the LONGEST path through a
project, which determines the SHORTEST possible project duration.
CPM is used to calculate the amount of scheduling FLEXIBILITY (the amount of time that a
schedule activity can be delayed or extended from its early start date without delaying the
project finish date or violating a schedule constraint, and is termed “TOTAL FLOAT.”
6.6.2 Develop Schedule: Tools and Techniques
6.6.2.2 Critical Path Method
A
1 0 5
1 5 5
<ACTIVITY NAME>
LS TF LF
ES DU EF
C
6 0 15
6 10 15
D
16 0 30
16 15 30
B
11 5 15
6 5 10START
FINISH
6.6.2 Develop Schedule: Tools and Techniques
6.6.2.3 Critical Chain Method
CCM is a schedule method that allows to place buffers on any project schedule path to account for limited
resources and project uncertainties.
It is developed from the critical path method approach and considers the effects of resource allocation,
resource optimization, resource leveling, and activity duration uncertainty on the critical path determined
using the critical path method.
The critical chain method uses activities with durations that do not include safety margins, logical
relationships, and resource availability with statistically determined buffers composed of the aggregated
safety margins of activities at specified points on the project schedule path to account for limited resources
and project uncertainties.
The resource-constrained critical path is known as the critical chain.
6.6.2 Develop Schedule: Tools and Techniques
6.6.2.3 Critical Chain Method
A
C D
B
START
FINISH
E
G
F
FB
FB
PB
Critical Chain LINK
NON Critical Chain LINK
duration buffers: • non-work schedule activities to manage uncertainty.
project buffer: • at the end of the critical chain protects the target finish date from slippage along the critical chain.
feeding buffers:
• at point where a chain of dependent activities that are not on the critical chain feeds into the critical chain.
(protect CC from slippage along the FC)
6.6.2 Develop Schedule: Tools and Techniques
6.6.2.4 Resource Optimization Techniques
RESOURCE LEVELING:
◦ A technique in which start and finish dates are
ADJUSTED based on resource constraints with
the goal of balancing demand for resources with
the available supply.
◦ Resource leveling can be used when shared or
critically required resources are only available at
certain times, or in limited quantities, or over-
allocated,
◦ Resource leveling can often cause the original
critical path to change, usually to increase
A
C
B
START
DAY-1 DAY-2 DAY-3
2
1 1
A CBSTART
DAY-1 DAY-2 DAY-3
1
1 1
1
6.6.2 Develop Schedule: Tools and Techniques
6.6.2.4 Resource Optimization Techniques
RESOURCE SMOOTHING
A technique that adjusts the activities of a
schedule model such that the requirements
for resources on the project DO NOT exceed
certain predefined resource limits.
the project’s critical path is NOT CHANGED and
the completion date may not be delayed
(opposed to resource leveling).
activities may only be delayed within their free
and total float.
not be able to optimize all resources
A
C
B
START
DAY-1 DAY-2 DAY-3
2
1 1
1 DAY
1 DAY
1 DAY
A
C
B
START
DAY-1 DAY-2 DAY-3
1
1 1
2 DAY
1 DAY
1 DAY
1
6.6.2 Develop Schedule: Tools and Techniques
6.6.2.5 Modeling Techniques
WHAT-IF SCENARIO ANALYSIS.
process of evaluating scenarios in order to predict their
effect, positively or negatively, on project objectives.
“What if the situation represented by scenario ‘X’
happens?”
A schedule network analysis is performed using the
schedule to compute the different scenarios, (delaying a
major component delivery) The outcome of the what-if
scenario analysis can be used to assess the feasibility
of the project schedule under adverse conditions, and in
preparing contingency and response plans to overcome or
mitigate the impact of unexpected situations.
SIMULATION
Simulation involves calculating multiple project
durations with different sets of activity
assumptions, usually using probability
distributions constructed from the three-point
estimates to account for uncertainty. The most
common simulation technique is Monte Carlo
analysis, in which a distribution of possible
activity durations is defined for each activity
and used to calculate a distribution of possible
outcomes for the total project
6.6.2 Develop Schedule: Tools and Techniques
6.6.2.7 Schedule Compression
CRASHING
A technique used to shorten the schedule duration
for the least incremental cost by ADDING resources.
◦ approving overtime, bringing in additional resources, or paying
to expedite delivery to activities on the critical path.
Crashing works only for activities on the critical path
where additional resources will shorten the
activity’s duration.
Crashing does not always produce a viable
alternative and may result in increased risk and/or
cost.
FAST TRACKING
technique in which activities or phases normally
done in SEQUENCE are performed in PARALLEL for
at least a portion of their duration.
Fast tracking may result in rework and increased
risk.
Fast tracking only works if activities can be
overlapped to shorten the project duration
techniques used to shorten the duration without reducing scope, to meet schedule constraints, imposed dates, or other objectives
foundation
Arch Design
foundation
DAY-1 DAY-2 DAY-3 DAY-4 DAY-5
Arch Design
6.6.3 Develop Schedule: Outputs
6.6.3.1 Schedule Baseline
approved version (by the appropriate stakeholders ) of a schedule model that can be CHANGED ONLY
through formal change control procedures and is used as a basis for comparison to actual results.
During monitoring and controlling, the approved baseline dates are compared to the actual start and finish
dates to determine whether variances have occurred.
6.6.3 Develop Schedule: Outputs
6.6.3.2 Project Schedule
The project schedule is an output of a schedule model that presents linked activities with planned dates, durations, milestones, and
resources. (minimum includes a planned start date and planned finish date for each activity).
If resource planning is done at an early stage, then the project schedule remains preliminary until resource assignments have been
confirmed and scheduled start and finish dates are established.
This process usually occurs no later than the completion of the project management plan
The project schedule presentation may be presented in summary form, or in detail (tabular form, graphically):
◦ Bar charts (Gantt charts)
◦ Milestone charts
◦ Project schedule network diagrams.
◦ in the activity-on-node diagram format showing activities and relationships without a time scale, sometimes referred to as a pure logic
diagram,
2013
Design
CONSTRUCTION
•21/3/2013
•1/8/2013
DecOctSepAugJulyJuneAprilMarchFebJan May Nov
•1/11/2013
EQUIPMENT INSTALLATION
•1/1/2013
•1/3/2013
TESTING & COMMISSIONING
EXT. W. & FINISHING
Bar charts (Gantt charts)
HANDOVER
MS
3
MS
1
MS
2
EQPT RP
START
A • ES …
• EF ..
B • ES …
• EF ..
C • ES …
• EF ..
MS
Milestone
• only identify the scheduled start or
completion of major deliverables and key
external interfaces
HAMMOCK
•more comprehensive summary activity between
milestones or across multiple interdependent work
packages, and is displayed in bar chart reports
network
diagrams
•in the activity-on-node diagram format showing
activities and relationships without a time scale,
sometimes referred to as a pure logic diagram
6.6.3 Develop Schedule: Outputs
6.6.3.2 Project Schedule
6.6.3 Develop Schedule: Outputs
6.6.3.3 Schedule Data & 6.6.3.4 Project Calendars
6.6.3.3 SCHEDULE DATA
collection of information for describing
and controlling the schedule includes
at least :
◦ milestones, schedule activities, activity
attributes, assumptions and constraints.
◦ supporting detail includes:
◦ Resource requirements by time period (resource
histogram)
◦ Alternative schedules (best-case or worst-case, not
resource-leveled, or resource-leveled)
◦ Scheduling of contingency reserves.
6.6.3.4 PROJECT CALENDARS
working days and shifts that are available for
scheduled activities.
It distinguishes time periods that are available
to complete scheduled activities from time
periods that are not available.
A schedule model may require more than one
project calendar to allow for different work
periods for some activities to calculate the
project schedule.
6.7 Control Schedule
MONITORING the status of project activities to update project progress and manage
changes to the schedule baseline to achieve the plan.
provides the
means to
recognize
deviation from the
plan and take
corrective and
preventive actions
and thus minimize
risk.
Inputs
Project management plan
Project schedule
Work performance data
Project calendars
Schedule data
Organizational process
assets
T&T
Performance reviews
Project management software
Resource optimization
techniques
Modeling techniques
Leads and lags
Schedule compression
Scheduling tool
Outputs
Work performance information
Schedule forecasts
Change requests
Project management plan
updates
Project documents updates
Organizational process assets
updates
6.7 Control Schedule
Data Flow Diagram
6.7 Control Schedule
Agile approach
COMPARING the total amount of work delivered and accepted against the estimates of work
completed for the elapsed time cycle,
Conducting RETROSPECTIVE reviews (scheduled reviews to record lessons learned) for correcting
processes and improving, if required,
REPRIORITIZING the remaining work plan (backlog),
Determining the RATE at which the deliverables are produced, validated, and accepted (velocity) in
given time per iteration (agreed work cycle duration, typically two weeks or one month),
Determining that the project schedule has CHANGED & Managing the actual changes as they occur.
6.7 Control Schedule
6.7.1 Control Schedule: Inputs
6.7.1.1 Project
Management
Plan
• how the schedule will be managed and
controlled.
• schedule baseline -reference -compare with
actual - change, corrective action, or preventive
action
6.7.1.2 Project
Schedule
• the most recent version with notations to indicate
updates, completed activities, and started
activities.
6.7.1.3 Work
Performance
Data
• project progress information (actual duration,
remaining duration, and physical percent
complete)
6.7. 2 Control Schedule : Tools and Techniques
6.7.2.1 Performance Reviews
Trend analysis
•examines project performance over time to determine whether performance is improving or deteriorating (Using
Graphical analysis techniques).
Critical path method
•Comparing the progress along the critical path.
•The variance on the critical path will have a direct impact on the project end date.
•Evaluating the progress of activities on near critical paths can identify schedule risk.
Earned value management
•SV and SPI are used to assess the magnitude of variation to the original schedule baseline.
•The total float and early finish variances are also essential planning components
•determining the cause and degree of variance relative to baseline
•estimating the implications of those variances for future work to completion
•deciding whether corrective or preventive action is required.
Performance reviews measure, compare, and analyze schedule performance
6.7. 2 Control Schedule : Tools and Techniques
6.7.2.2-7
6.7.2.2 Project Management Software
• provides the ability to track planned vs. actual, to report variances ,progress , forecast.
6.7.2.3 Resource Optimization Techniques
• involve the scheduling of activities and the resources required taking into consideration both the resource availability and the project time.
6.7.2.4 Modeling Techniques
• review various scenarios guided by risk monitoring to bring the schedule model into alignment with the project management plan and
approved baseline.
6.7.2.5 Leads and Lags
• applied during network analysis to find ways to bring project activities that are behind into alignment with the plan.
6.7.2.6 Schedule Compression
• find ways to bring project activities that are behind into alignment with the plan by fast tracking or crashing schedule for the remaining work.
6.7.2.7 Scheduling Tool
• perform schedule network analysis to generate an updated project schedule.
6.7.3 Control Schedule: Outputs
6.7.3.1 Work Performance Information
• SV and SPI time performance indicators for WBS components, are documented and communicated to stakeholders.
6.7.3.2 Schedule Forecasts
• estimates or predictions of conditions and events in the project’s future based on information and knowledge available
6.7.3.3 Change Requests
• Schedule variance analysis, along with review of progress reports, results of performance measures, and modifications to the project scope or project
schedule may result in change requests to the schedule baseline, scope baseline, and/or other components of the project management plan.
6.7.3.4 Project Management Plan Updates
• Schedule baseline.
• Project Schedule
• Risk Register
6.7.3.6 Organizational Process Assets Updates
• Causes of variances
• Corrective action chosen and the reasons
• Other types of lessons learned from project schedule control.

Contenu connexe

Tendances

PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1Anand Bobade
 
Project time management
Project time managementProject time management
Project time managementJivan Nepali
 
Project Time Management
Project Time Management Project Time Management
Project Time Management Waqar Ali
 
Project Management Presentation material
Project Management Presentation material Project Management Presentation material
Project Management Presentation material Abdel Rahman okasha
 
A brief on project time management
A brief on project time managementA brief on project time management
A brief on project time managementImran Jamil
 
Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Agus Suhanto
 
Time Management within IT Project Management
Time Management within IT Project ManagementTime Management within IT Project Management
Time Management within IT Project Managementrielaantonio
 
06 project time management
06  project time management06  project time management
06 project time managementAla Ibrahim
 
Monitoring of project implementation
Monitoring of project implementationMonitoring of project implementation
Monitoring of project implementationDejened
 
Microsoft_Project_101_How_to_Build_a_Project_Plan.
Microsoft_Project_101_How_to_Build_a_Project_Plan.Microsoft_Project_101_How_to_Build_a_Project_Plan.
Microsoft_Project_101_How_to_Build_a_Project_Plan.TURKI , PMP
 
The Project Management Process - Week 9 Performance Management
The Project Management Process - Week 9   Performance ManagementThe Project Management Process - Week 9   Performance Management
The Project Management Process - Week 9 Performance ManagementCraig Brown
 

Tendances (20)

PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1
 
Project time management
Project time managementProject time management
Project time management
 
Project Time Management
Project Time Management Project Time Management
Project Time Management
 
Project Management Presentation material
Project Management Presentation material Project Management Presentation material
Project Management Presentation material
 
A brief on project time management
A brief on project time managementA brief on project time management
A brief on project time management
 
Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6
 
Time Management within IT Project Management
Time Management within IT Project ManagementTime Management within IT Project Management
Time Management within IT Project Management
 
PMP PMBok 5th ch 5 scope management
PMP PMBok 5th ch 5 scope managementPMP PMBok 5th ch 5 scope management
PMP PMBok 5th ch 5 scope management
 
Project Management
Project ManagementProject Management
Project Management
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 
Project Management Steps
Project Management StepsProject Management Steps
Project Management Steps
 
Project Management
Project ManagementProject Management
Project Management
 
05 project scope management
05 project scope management05 project scope management
05 project scope management
 
Project management
Project managementProject management
Project management
 
06 project time management
06  project time management06  project time management
06 project time management
 
Project time management
Project time managementProject time management
Project time management
 
Project engineer
Project engineerProject engineer
Project engineer
 
Monitoring of project implementation
Monitoring of project implementationMonitoring of project implementation
Monitoring of project implementation
 
Microsoft_Project_101_How_to_Build_a_Project_Plan.
Microsoft_Project_101_How_to_Build_a_Project_Plan.Microsoft_Project_101_How_to_Build_a_Project_Plan.
Microsoft_Project_101_How_to_Build_a_Project_Plan.
 
The Project Management Process - Week 9 Performance Management
The Project Management Process - Week 9   Performance ManagementThe Project Management Process - Week 9   Performance Management
The Project Management Process - Week 9 Performance Management
 

En vedette

Project Time Management - PMBOK 5th Edition
Project  Time Management - PMBOK 5th EditionProject  Time Management - PMBOK 5th Edition
Project Time Management - PMBOK 5th Editionpankajsh10
 
Design &amp; Development Of A Schedule Management Plan Presentation
Design &amp; Development Of A Schedule Management Plan PresentationDesign &amp; Development Of A Schedule Management Plan Presentation
Design &amp; Development Of A Schedule Management Plan PresentationChris Carson
 
10 me667 chap2 project management
10 me667 chap2 project management10 me667 chap2 project management
10 me667 chap2 project managementPavan Kumar
 
PMI-PBA 商業分析讀書會 20150725
PMI-PBA 商業分析讀書會 20150725PMI-PBA 商業分析讀書會 20150725
PMI-PBA 商業分析讀書會 20150725moris lee
 
Workflow Management Software with IBM Lotus Notes, Business Process Managemen...
Workflow Management Software with IBM Lotus Notes, Business Process Managemen...Workflow Management Software with IBM Lotus Notes, Business Process Managemen...
Workflow Management Software with IBM Lotus Notes, Business Process Managemen...GBS PAVONE Groupware GmbH
 
Pmbok 5cartulinas
Pmbok 5cartulinasPmbok 5cartulinas
Pmbok 5cartulinasPedro Arcas
 
Project design and management
Project design and managementProject design and management
Project design and managementAndrew Zolnai
 
Web project management
Web project managementWeb project management
Web project managementSavaş Şakar
 
Web Project Management for Small Projects
Web Project Management for Small ProjectsWeb Project Management for Small Projects
Web Project Management for Small Projectscwarren
 
Pmp pmbok 5 updates vs pmbok 4
Pmp pmbok 5 updates vs pmbok 4Pmp pmbok 5 updates vs pmbok 4
Pmp pmbok 5 updates vs pmbok 4Hujaj Khan
 
Web Project Management Todcon2008
Web Project Management Todcon2008Web Project Management Todcon2008
Web Project Management Todcon2008Jesse Rodgers
 
Rohit demo sap ps_module_training
Rohit demo sap ps_module_trainingRohit demo sap ps_module_training
Rohit demo sap ps_module_trainingmultimediasunil
 
PMBOOK 5
PMBOOK 5PMBOOK 5
PMBOOK 5neleka
 
Project management
Project managementProject management
Project managementSameer Kumar
 
Critical Chain Project Management & Theory of Constraints
Critical Chain Project Management & Theory of ConstraintsCritical Chain Project Management & Theory of Constraints
Critical Chain Project Management & Theory of ConstraintsAbhay Kumar
 

En vedette (20)

Project Time Management - PMBOK 5th Edition
Project  Time Management - PMBOK 5th EditionProject  Time Management - PMBOK 5th Edition
Project Time Management - PMBOK 5th Edition
 
09 project human resources management pmbok 5th
09 project human resources management pmbok 5th09 project human resources management pmbok 5th
09 project human resources management pmbok 5th
 
07 project cost management
07 project cost management07 project cost management
07 project cost management
 
Saving time with CCPM
Saving time with CCPMSaving time with CCPM
Saving time with CCPM
 
Design &amp; Development Of A Schedule Management Plan Presentation
Design &amp; Development Of A Schedule Management Plan PresentationDesign &amp; Development Of A Schedule Management Plan Presentation
Design &amp; Development Of A Schedule Management Plan Presentation
 
10 me667 chap2 project management
10 me667 chap2 project management10 me667 chap2 project management
10 me667 chap2 project management
 
PMI-PBA 商業分析讀書會 20150725
PMI-PBA 商業分析讀書會 20150725PMI-PBA 商業分析讀書會 20150725
PMI-PBA 商業分析讀書會 20150725
 
Workflow Management Software with IBM Lotus Notes, Business Process Managemen...
Workflow Management Software with IBM Lotus Notes, Business Process Managemen...Workflow Management Software with IBM Lotus Notes, Business Process Managemen...
Workflow Management Software with IBM Lotus Notes, Business Process Managemen...
 
Pmbok 5cartulinas
Pmbok 5cartulinasPmbok 5cartulinas
Pmbok 5cartulinas
 
Project design and management
Project design and managementProject design and management
Project design and management
 
Web project management
Web project managementWeb project management
Web project management
 
Web Project Management for Small Projects
Web Project Management for Small ProjectsWeb Project Management for Small Projects
Web Project Management for Small Projects
 
Pmp pmbok 5 updates vs pmbok 4
Pmp pmbok 5 updates vs pmbok 4Pmp pmbok 5 updates vs pmbok 4
Pmp pmbok 5 updates vs pmbok 4
 
Pm training 1 18
Pm training 1 18Pm training 1 18
Pm training 1 18
 
Web Project Management Todcon2008
Web Project Management Todcon2008Web Project Management Todcon2008
Web Project Management Todcon2008
 
Rohit demo sap ps_module_training
Rohit demo sap ps_module_trainingRohit demo sap ps_module_training
Rohit demo sap ps_module_training
 
PMBOOK 5
PMBOOK 5PMBOOK 5
PMBOOK 5
 
Project management
Project managementProject management
Project management
 
Critical Chain Project Management & Theory of Constraints
Critical Chain Project Management & Theory of ConstraintsCritical Chain Project Management & Theory of Constraints
Critical Chain Project Management & Theory of Constraints
 
Projectmanagement Meets Web 2.0
Projectmanagement Meets Web 2.0Projectmanagement Meets Web 2.0
Projectmanagement Meets Web 2.0
 

Similaire à 06 project time management m

Online PMP Training Material for PMP Exam - Time Management Knowledge Area
Online PMP Training Material for PMP Exam - Time Management Knowledge AreaOnline PMP Training Material for PMP Exam - Time Management Knowledge Area
Online PMP Training Material for PMP Exam - Time Management Knowledge AreaGlobalSkillup
 
PMP-Schedule Management area
PMP-Schedule Management areaPMP-Schedule Management area
PMP-Schedule Management areaZaur Ahmadov, PMP
 
Topic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdfTopic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdfHuyNguyen657394
 
schedule Management v4
 schedule Management v4 schedule Management v4
schedule Management v4Qussay Karam
 
software (1).pptx
software (1).pptxsoftware (1).pptx
software (1).pptxayanadamtew
 
projectplanningandprojectworkplan-130828212658-phpapp02 (1).pdf
projectplanningandprojectworkplan-130828212658-phpapp02 (1).pdfprojectplanningandprojectworkplan-130828212658-phpapp02 (1).pdf
projectplanningandprojectworkplan-130828212658-phpapp02 (1).pdfJyotiYadav916744
 
Pmbok 5th planning process group part two
Pmbok 5th planning process group part twoPmbok 5th planning process group part two
Pmbok 5th planning process group part twoHossam Maghrabi
 
DISE - Introduction to Project Management
DISE - Introduction to Project ManagementDISE - Introduction to Project Management
DISE - Introduction to Project ManagementRasan Samarasinghe
 
NCV 3 Project Management Hands-On Support Slide Show - Module 5
NCV 3 Project Management Hands-On Support Slide Show - Module 5NCV 3 Project Management Hands-On Support Slide Show - Module 5
NCV 3 Project Management Hands-On Support Slide Show - Module 5Future Managers
 
9.2 Estimate Activity Resources
9.2 Estimate Activity Resources9.2 Estimate Activity Resources
9.2 Estimate Activity ResourcesDavidMcLachlan1
 
06- PROJECT SCHEDULE MANAGEMENT (PMBOK Ch - 06).pptx
06-  PROJECT SCHEDULE MANAGEMENT (PMBOK Ch - 06).pptx06-  PROJECT SCHEDULE MANAGEMENT (PMBOK Ch - 06).pptx
06- PROJECT SCHEDULE MANAGEMENT (PMBOK Ch - 06).pptxWajihAnsari7
 

Similaire à 06 project time management m (20)

Online PMP Training Material for PMP Exam - Time Management Knowledge Area
Online PMP Training Material for PMP Exam - Time Management Knowledge AreaOnline PMP Training Material for PMP Exam - Time Management Knowledge Area
Online PMP Training Material for PMP Exam - Time Management Knowledge Area
 
6.5 Develop Schedule
6.5 Develop Schedule6.5 Develop Schedule
6.5 Develop Schedule
 
PMP-Schedule Management area
PMP-Schedule Management areaPMP-Schedule Management area
PMP-Schedule Management area
 
Topic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdfTopic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdf
 
Session 8 4th edition PMP
Session 8 4th edition PMPSession 8 4th edition PMP
Session 8 4th edition PMP
 
PMP_Project Time Management
PMP_Project Time ManagementPMP_Project Time Management
PMP_Project Time Management
 
Time Masterclass
Time MasterclassTime Masterclass
Time Masterclass
 
schedule Management v4
 schedule Management v4 schedule Management v4
schedule Management v4
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 
software (1).pptx
software (1).pptxsoftware (1).pptx
software (1).pptx
 
projectplanningandprojectworkplan-130828212658-phpapp02 (1).pdf
projectplanningandprojectworkplan-130828212658-phpapp02 (1).pdfprojectplanningandprojectworkplan-130828212658-phpapp02 (1).pdf
projectplanningandprojectworkplan-130828212658-phpapp02 (1).pdf
 
Project planning and project work plan
Project planning and project work planProject planning and project work plan
Project planning and project work plan
 
Pmbok 5th planning process group part two
Pmbok 5th planning process group part twoPmbok 5th planning process group part two
Pmbok 5th planning process group part two
 
DISE - Introduction to Project Management
DISE - Introduction to Project ManagementDISE - Introduction to Project Management
DISE - Introduction to Project Management
 
Time management
Time managementTime management
Time management
 
CAPM Week 2 Chapter 6
CAPM Week 2 Chapter 6CAPM Week 2 Chapter 6
CAPM Week 2 Chapter 6
 
NCV 3 Project Management Hands-On Support Slide Show - Module 5
NCV 3 Project Management Hands-On Support Slide Show - Module 5NCV 3 Project Management Hands-On Support Slide Show - Module 5
NCV 3 Project Management Hands-On Support Slide Show - Module 5
 
9.2 Estimate Activity Resources
9.2 Estimate Activity Resources9.2 Estimate Activity Resources
9.2 Estimate Activity Resources
 
6.3 Sequence Activities
6.3 Sequence Activities6.3 Sequence Activities
6.3 Sequence Activities
 
06- PROJECT SCHEDULE MANAGEMENT (PMBOK Ch - 06).pptx
06-  PROJECT SCHEDULE MANAGEMENT (PMBOK Ch - 06).pptx06-  PROJECT SCHEDULE MANAGEMENT (PMBOK Ch - 06).pptx
06- PROJECT SCHEDULE MANAGEMENT (PMBOK Ch - 06).pptx
 

Plus de Omer Alsayed PhD,MBA, PMP®

Project stakeholders management arabic ادارة المعنيين في المشروع
Project stakeholders management arabic ادارة المعنيين في المشروعProject stakeholders management arabic ادارة المعنيين في المشروع
Project stakeholders management arabic ادارة المعنيين في المشروعOmer Alsayed PhD,MBA, PMP®
 
برنامج حصاد المياه خطوة نحو تنمية الموارد الطبيعية
برنامج حصاد المياه  خطوة نحو تنمية الموارد الطبيعيةبرنامج حصاد المياه  خطوة نحو تنمية الموارد الطبيعية
برنامج حصاد المياه خطوة نحو تنمية الموارد الطبيعيةOmer Alsayed PhD,MBA, PMP®
 
09 PMP Project Human Resources Management PMBOK 5th edittion
09 PMP Project Human Resources Management PMBOK 5th edittion09 PMP Project Human Resources Management PMBOK 5th edittion
09 PMP Project Human Resources Management PMBOK 5th edittionOmer Alsayed PhD,MBA, PMP®
 
09 Project Human Resources management based on PMBOK5
09 Project Human Resources management based on PMBOK5 09 Project Human Resources management based on PMBOK5
09 Project Human Resources management based on PMBOK5 Omer Alsayed PhD,MBA, PMP®
 
وأحسن الناس من بين الورى رجل
وأحسن الناس من بين الورى رجلوأحسن الناس من بين الورى رجل
وأحسن الناس من بين الورى رجلOmer Alsayed PhD,MBA, PMP®
 
Project risk management for water harvesting in Darfur إدارة مخاطر المشروعات ...
Project risk management for water harvesting in Darfur إدارة مخاطر المشروعات ...Project risk management for water harvesting in Darfur إدارة مخاطر المشروعات ...
Project risk management for water harvesting in Darfur إدارة مخاطر المشروعات ...Omer Alsayed PhD,MBA, PMP®
 

Plus de Omer Alsayed PhD,MBA, PMP® (20)

Project stakeholders management arabic ادارة المعنيين في المشروع
Project stakeholders management arabic ادارة المعنيين في المشروعProject stakeholders management arabic ادارة المعنيين في المشروع
Project stakeholders management arabic ادارة المعنيين في المشروع
 
برنامج حصاد المياه خطوة نحو تنمية الموارد الطبيعية
برنامج حصاد المياه  خطوة نحو تنمية الموارد الطبيعيةبرنامج حصاد المياه  خطوة نحو تنمية الموارد الطبيعية
برنامج حصاد المياه خطوة نحو تنمية الموارد الطبيعية
 
08 project quality management
08 project quality management08 project quality management
08 project quality management
 
09 project human res 2014
09 project human res 201409 project human res 2014
09 project human res 2014
 
13 project stakeholders management
13 project stakeholders management13 project stakeholders management
13 project stakeholders management
 
12 project procurement management
12 project procurement management12 project procurement management
12 project procurement management
 
11 project risk management
11 project risk management11 project risk management
11 project risk management
 
09 project human res 2014
09 project human res 201409 project human res 2014
09 project human res 2014
 
Practical project management 12 feb 2014
Practical project management 12 feb 2014Practical project management 12 feb 2014
Practical project management 12 feb 2014
 
05 project scope management
05 project scope management05 project scope management
05 project scope management
 
Practical project management based on PMBOK5
Practical project management based on PMBOK5Practical project management based on PMBOK5
Practical project management based on PMBOK5
 
09 PMP Project Human Resources Management PMBOK 5th edittion
09 PMP Project Human Resources Management PMBOK 5th edittion09 PMP Project Human Resources Management PMBOK 5th edittion
09 PMP Project Human Resources Management PMBOK 5th edittion
 
09 Project Human Resources management based on PMBOK5
09 Project Human Resources management based on PMBOK5 09 Project Human Resources management based on PMBOK5
09 Project Human Resources management based on PMBOK5
 
وأحسن الناس من بين الورى رجل
وأحسن الناس من بين الورى رجلوأحسن الناس من بين الورى رجل
وأحسن الناس من بين الورى رجل
 
Project risk management for water harvesting in Darfur إدارة مخاطر المشروعات ...
Project risk management for water harvesting in Darfur إدارة مخاطر المشروعات ...Project risk management for water harvesting in Darfur إدارة مخاطر المشروعات ...
Project risk management for water harvesting in Darfur إدارة مخاطر المشروعات ...
 
No one can ride your back
No one can ride your backNo one can ride your back
No one can ride your back
 
المدود
المدودالمدود
المدود
 
Tajweed slides
Tajweed slidesTajweed slides
Tajweed slides
 
Salah
SalahSalah
Salah
 
Presentation rech ar
Presentation rech arPresentation rech ar
Presentation rech ar
 

Dernier

WSMM Media and Entertainment Feb_March_Final.pdf
WSMM Media and Entertainment Feb_March_Final.pdfWSMM Media and Entertainment Feb_March_Final.pdf
WSMM Media and Entertainment Feb_March_Final.pdfJamesConcepcion7
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMVoces Mineras
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Anamaria Contreras
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03DallasHaselhorst
 
Effective Strategies for Maximizing Your Profit When Selling Gold Jewelry
Effective Strategies for Maximizing Your Profit When Selling Gold JewelryEffective Strategies for Maximizing Your Profit When Selling Gold Jewelry
Effective Strategies for Maximizing Your Profit When Selling Gold JewelryWhittensFineJewelry1
 
Go for Rakhi Bazaar and Pick the Latest Bhaiya Bhabhi Rakhi.pptx
Go for Rakhi Bazaar and Pick the Latest Bhaiya Bhabhi Rakhi.pptxGo for Rakhi Bazaar and Pick the Latest Bhaiya Bhabhi Rakhi.pptx
Go for Rakhi Bazaar and Pick the Latest Bhaiya Bhabhi Rakhi.pptxRakhi Bazaar
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfRbc Rbcua
 
Intermediate Accounting, Volume 2, 13th Canadian Edition by Donald E. Kieso t...
Intermediate Accounting, Volume 2, 13th Canadian Edition by Donald E. Kieso t...Intermediate Accounting, Volume 2, 13th Canadian Edition by Donald E. Kieso t...
Intermediate Accounting, Volume 2, 13th Canadian Edition by Donald E. Kieso t...ssuserf63bd7
 
Appkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptxAppkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptxappkodes
 
Welding Electrode Making Machine By Deccan Dynamics
Welding Electrode Making Machine By Deccan DynamicsWelding Electrode Making Machine By Deccan Dynamics
Welding Electrode Making Machine By Deccan DynamicsIndiaMART InterMESH Limited
 
NAB Show Exhibitor List 2024 - Exhibitors Data
NAB Show Exhibitor List 2024 - Exhibitors DataNAB Show Exhibitor List 2024 - Exhibitors Data
NAB Show Exhibitor List 2024 - Exhibitors DataExhibitors Data
 
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxmbikashkanyari
 
Darshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfDarshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfShashank Mehta
 
Onemonitar Android Spy App Features: Explore Advanced Monitoring Capabilities
Onemonitar Android Spy App Features: Explore Advanced Monitoring CapabilitiesOnemonitar Android Spy App Features: Explore Advanced Monitoring Capabilities
Onemonitar Android Spy App Features: Explore Advanced Monitoring CapabilitiesOne Monitar
 
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdf
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdftrending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdf
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdfMintel Group
 
Supercharge Your eCommerce Stores-acowebs
Supercharge Your eCommerce Stores-acowebsSupercharge Your eCommerce Stores-acowebs
Supercharge Your eCommerce Stores-acowebsGOKUL JS
 
EUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exportersEUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exportersPeter Horsten
 
Jewish Resources in the Family Resource Centre
Jewish Resources in the Family Resource CentreJewish Resources in the Family Resource Centre
Jewish Resources in the Family Resource CentreNZSG
 
Send Files | Sendbig.comSend Files | Sendbig.com
Send Files | Sendbig.comSend Files | Sendbig.comSend Files | Sendbig.comSend Files | Sendbig.com
Send Files | Sendbig.comSend Files | Sendbig.comSendBig4
 

Dernier (20)

WSMM Media and Entertainment Feb_March_Final.pdf
WSMM Media and Entertainment Feb_March_Final.pdfWSMM Media and Entertainment Feb_March_Final.pdf
WSMM Media and Entertainment Feb_March_Final.pdf
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQM
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03
 
Effective Strategies for Maximizing Your Profit When Selling Gold Jewelry
Effective Strategies for Maximizing Your Profit When Selling Gold JewelryEffective Strategies for Maximizing Your Profit When Selling Gold Jewelry
Effective Strategies for Maximizing Your Profit When Selling Gold Jewelry
 
Go for Rakhi Bazaar and Pick the Latest Bhaiya Bhabhi Rakhi.pptx
Go for Rakhi Bazaar and Pick the Latest Bhaiya Bhabhi Rakhi.pptxGo for Rakhi Bazaar and Pick the Latest Bhaiya Bhabhi Rakhi.pptx
Go for Rakhi Bazaar and Pick the Latest Bhaiya Bhabhi Rakhi.pptx
 
WAM Corporate Presentation April 12 2024.pdf
WAM Corporate Presentation April 12 2024.pdfWAM Corporate Presentation April 12 2024.pdf
WAM Corporate Presentation April 12 2024.pdf
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdf
 
Intermediate Accounting, Volume 2, 13th Canadian Edition by Donald E. Kieso t...
Intermediate Accounting, Volume 2, 13th Canadian Edition by Donald E. Kieso t...Intermediate Accounting, Volume 2, 13th Canadian Edition by Donald E. Kieso t...
Intermediate Accounting, Volume 2, 13th Canadian Edition by Donald E. Kieso t...
 
Appkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptxAppkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptx
 
Welding Electrode Making Machine By Deccan Dynamics
Welding Electrode Making Machine By Deccan DynamicsWelding Electrode Making Machine By Deccan Dynamics
Welding Electrode Making Machine By Deccan Dynamics
 
NAB Show Exhibitor List 2024 - Exhibitors Data
NAB Show Exhibitor List 2024 - Exhibitors DataNAB Show Exhibitor List 2024 - Exhibitors Data
NAB Show Exhibitor List 2024 - Exhibitors Data
 
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
 
Darshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfDarshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdf
 
Onemonitar Android Spy App Features: Explore Advanced Monitoring Capabilities
Onemonitar Android Spy App Features: Explore Advanced Monitoring CapabilitiesOnemonitar Android Spy App Features: Explore Advanced Monitoring Capabilities
Onemonitar Android Spy App Features: Explore Advanced Monitoring Capabilities
 
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdf
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdftrending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdf
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdf
 
Supercharge Your eCommerce Stores-acowebs
Supercharge Your eCommerce Stores-acowebsSupercharge Your eCommerce Stores-acowebs
Supercharge Your eCommerce Stores-acowebs
 
EUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exportersEUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exporters
 
Jewish Resources in the Family Resource Centre
Jewish Resources in the Family Resource CentreJewish Resources in the Family Resource Centre
Jewish Resources in the Family Resource Centre
 
Send Files | Sendbig.comSend Files | Sendbig.com
Send Files | Sendbig.comSend Files | Sendbig.comSend Files | Sendbig.comSend Files | Sendbig.com
Send Files | Sendbig.comSend Files | Sendbig.com
 

06 project time management m

  • 1. Project Time management BY: OMER ALSAYED OMER MBA, PMP, B.Sc.(Civil Eng.) : PMO manager EWU-DIU
  • 2. quote It is useless to desire more time if you are already wasting what little you have.” -– James Allen “
  • 3. Project Scope Management processes • establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule. 6.1 Plan Schedule Management • identifying and documenting the specific actions to be performed to produce the project deliverables. 6.2 Define Activities • identifying and documenting relationships among the project activities. 6.3 Sequence Activities • estimating the type and quantities of material, human resources, equipment, or supplies required to perform each activity. 6.4 Estimate Activity Resources • estimating the number of work periods needed to complete individual activities with estimated resources. 6.5 Estimate Activity Durations • analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule model. 6.6 Develop Schedule • monitoring the status of project activities to update project progress and manage changes to the schedule baseline to achieve the plan. 6.7 Control Schedule
  • 4. Project Management Process Group and Knowledge Area Mapping Knowledge Area Initiating Planning Executing M& C Closing 4. Project Integration Management 4Develop Project Charter 4.2 Develop Project Management Plan 4.3 Direct & Manage Project Work 4.4 Monitor & Control Project Work 4.5 Perform Integrated Change Control 4.6 Close Project or Phase 5. Project Scope Management 5Plan Scope Management 5.2 Collect Requirements 5.3 Define Scope 5.4 Create WBS 5.5 Validate Scope 5.6 Control Scope 6. Project Time Management 6Plan Schedule Management 6.2 Define Activities 6.3 Sequence Activities 6.4 Estimate Activity Resources 6.5 Estimate Activity Durations 6.6 Develop Schedule 6.7 Control Schedule 7. Project Cost Management 7Plan Cost Management 7.2 Estimate Costs 7.3 Determine Budget 7.4 Control Costs 8. Project Quality Management 8Plan Quality Management 8.2 Perform Quality Assurance 8.3 Control Quality 9. Project Human Resource Management 9.1 Plan Human Resource Management 9.2 Acquire Project Team 9.3 Develop Project Team 9.4 Manage Project Team 10. Project Communications Management 10Plan Communications Management 10.2 Manage Communications 10.3 Control Communications 11. Project Risk Management 11Plan Risk Management 11.2 Identify Risks 11.3 Perform Qualitative Risk Analysis 11.4 Perform Quantitative Risk Analysis 11.5 Plan Risk Responses 11.6 Control Risks 12. Project Procurement Management 12Plan Procurement Management 12.2 Conduct Procurements 12.3 Control Procurements 12.4 Close Procurements 13. Project Stakeholder Management 13Identify Stakeholders 13.2 Plan Stakeholder Management 13.3 Manage Stakeholder Engagement 13.4 Control Stakeholder Engagement OSO OCT 2013 Planning M& C
  • 5. schedule terms Scheduling Tool. • A tool that provides schedule component names, definitions, structural relationships, and formats that support the application of a scheduling method. Schedule Model. • A representation of the plan for executing the project’s activities including durations, dependencies, and other planning information, used to produce a project schedule along with other scheduling artifacts. Schedule Data. • The collection of information for describing and controlling the schedule. Scheduling method(ex.CPM) Scheduling Tool Schedule Model Project schedule
  • 6. 6.1 Plan Schedule Management Plan Schedule Management is the process of establishing the policies, procedures, and documentation for: provides guidance and direction on how the project schedule will be managed throughout the project planning, developing, managing, executing, controlling the project schedule
  • 7. 6.1 Plan Schedule Management: Inputs, Tools & Techniques, and Outputs Inputs Project management plan Project charter Enterprise environmental factors Organizational process assets T&T Expert judgment Analytical techniques Meetings Outputs Schedule management plan
  • 8. 4 Integration 5 Scope 6 Time 7 Cost 8 Quality 9 H. Resource 10 Commn. 11 Risk 12 Procurement 13 S/holders EEF OPA Enterprise/ Organization 6.1 Plan Schedule Management Schedule management plan 6.2 Define Activities OSOOCT2013 4.1 Develop Project charter Project charter 6.1 Plan Schedule Management Data Flow Diagram 6.3 Sequence Activities 6.4 Estimate Activity Res. 4.2 Develop Project M Plan Project M Plan 6.5 Estimate Activity Durations 6.6 Develop Schedule 11.2 Identify Risks 11.4 Perform Quantitative Risk Analysis
  • 9. 6.1 Plan Schedule Management : Inputs Project management plan • Scope baseline. project scope statement and the work breakdown structure (WBS) details used for defining activities, duration estimation, and schedule management; and • Other scheduling related cost, risk, and communications decisions Project charter • summary milestone schedule and project approval requirements that will influence the management of the project schedule Enterprise environmental factors • Organizational culture and structure can all influence schedule management; • Resource availability and skills that may influence schedule planning; • Project management software provides the scheduling tool and alternative possibilities for managing the schedule; • Published commercial information, such as resource productivity information, is often available from commercial databases that track; • Organizational work authorization systems Organizational process assets • Monitoring and reporting tools to be used; • Historical information; • Schedule control tools; • Existing formal and informal schedule control related policies, procedures, and guidelines; • Templates; • Project closure guidelines; • Change control procedures; and • Risk control procedures including risk categories, probability definition and impact, and probability and impact matrix.
  • 10. 6.1.2 Plan Schedule Management: Tools and Techniques 6.1.2.2 Analytical Techniques PSM process may involve choosing strategic options to estimate and schedule the project such as: ◦ scheduling methodology, ◦ scheduling tools and techniques, ◦ estimating approaches, ◦ formats, ◦ project management software. detail ways to fast track or crash Organizational policies and procedures influence scheduling techniques rolling wave planning leads and lags alternatives analysis methods for reviewing schedule performance
  • 11. 6.1.2 Plan Schedule Management: OUTPUTS 6.1.3.1 Schedule Management Plan establishes the criteria and the activities for developing, monitoring, and controlling the schedule. Project schedule model development. •The scheduling methodology and the scheduling tool Level of accuracy. •The acceptable range used in determining realistic activity duration estimates (+contingencies). Units of measure. •Each unit used in measurements (staff hours, weeks ,meters) Organizational procedures links. •The WBS provides the framework for the schedule management plan, allowing for consistency with the estimates and resulting schedules. Project schedule model maintenance. •The process used to update the status and record progress Control thresholds. •Variance thresholds for monitoring schedule performance. Rules of performance measurement. •EVM rules or other physical measurement rules of performance measurement are set. (% CALC) Reporting formats. •The formats and frequency for the various schedule reports are defined. Process descriptions. •Descriptions of each of the schedule management processes are documented
  • 12. 6.2 Define Activities identifying and documenting the specific actions to be performed to produce the project deliverables. to break down work packages into activities that provide a basis for:  estimating,  scheduling,  executing,  monitoring,  Controlling the project work Inputs Schedule management plan Scope baseline Enterprise environmental factors Organizational process assets T&T Decomposition Rolling wave planning Expert judgment Outputs Activity list Activity attributes Milestone list
  • 13. 4 Integration 5 Scope 6 Time 7 Cost 8 Quality 9 H. Resource 10 Commn. 11 Risk 12 Procurement 13 S/holders EEF OPA Enterprise/ Organization 6.1 Plan Schedule Management Schedule M plan 6.2 Define Activities OSOOCT2013 5.4 Create WBS Scope baseline 6.2 Define Activities Data Flow Diagram 6.3 Sequence Activities 6.4 Estimate Activity Res. 6.5 Estimate Activity Durations 6.6 Develop Schedule Activity list Activity attributes Milestone list
  • 14. 6.2.1 Define Activities: Inputs 6.2.1.1 Schedule Management Plan: •prescribed level of detail necessary to manage the work 6.2.1.2 Scope Baseline •WBS, deliverables, constraints, and assumptions documented 6.2.1.3 Enterprise Environmental Factors •Organizational cultures and structure, •Published commercial information from commercial databases, and •Project management information system (PMIS). 6.2.1.4 Organizational Process Assets •Lessons learned knowledge base containing historical information •Standardized processes, •Templates that contain a standard activity list •Existing formal and informal activity planning-related policies, procedures, and guidelines (scheduling methodology)
  • 15. 6.2.2 Define Activities: Tools and Techniques 6.2.2.1 Decomposition • dividing and subdividing the project scope and project deliverables into smaller, more manageable parts. • Activities represent the effort needed to complete a work package. • The Define Activities process defines the final outputs as activities rather than deliverables, as done in the Create WBS process 6.2.2.2 Rolling Wave Planning • an iterative planning technique in which the work to be accomplished in the near term is planned in detail, while the work in the future is planned at a higher level. • It is a form of progressive elaboration 6.2.2.3 Expert Judgment • who are experienced and skilled in developing detailed project scope statements, the WBS, and project schedules
  • 16. 6.2.3 Define Activities: Outputs 6.2.3.1 Activity List • comprehensive list that includes all schedule activities required on the project. • The activity list also includes the activity identifier and a scope of work description for each activity in sufficient detail. • Each activity should have a unique title that describes its place in the schedule, even if that activity title is displayed outside the context of the project schedule. 6.2.3.2 Activity Attributes • identifying the multiple components associated with each activity. • the activity identifier (ID), WBS ID, and activity label or name, • activity codes, activity description, predecessor activities, successor activities, logical relationships, leads and lags, resource requirements, imposed dates, constraints, and assumptions. • person responsible, geographic area, calendar, type (LOE), • used for schedule development and for selecting, ordering, and sorting the planned schedule activities in various ways within reports. 6.2.3.3 Milestone List • MS is a significant point or event in a project (zero duration). • A milestone list is a list identifying all project milestones (mandatory, or optional) • Milestones are similar to regular schedule activities, with the same structure and
  • 17. 6.3 Sequence Activities identifying and documenting RELATIONSHIPS among the project activities defines the logical sequence of work to obtain the greatest efficiency given all project constraints Inputs Schedule management plan Activity list Activity attributes Milestone list Project scope statement Enterprise environmental factors Organizational process assets T&T Precedence diagramming method (PDM) Dependency determination Leads and lags Outputs Project schedule network diagrams Project documents updates
  • 18. 4 Integration 5 Scope 6 Time 7 Cost 8 Quality 9 H. Resource 10 Commn. 11 Risk 12 Procurement 13 S/holders EEF OPA Enterprise/ Organization 6.1 Plan Schedule Management Schedule M plan 6.2 Define Activities OSOOCT2013 5.3 Define Scope Project scope statement 6.3 Sequence Activities Data Flow Diagram 6.3 Sequence Activities 6.6 Develop Schedule Activity list Activity attributes Milestone list Project documents updates Project schedule network diagrams Project documents  Activity lists,  Activity attributes,  Milestone list, and  Risk register.
  • 19. 6.3.1 Sequence Activities: Inputs 6.3.1.1 Schedule Management Plan: • identifies the scheduling method and tool to be used for the project, which will guide how the activities may be sequenced 6.3.1.2 Activity List • contains all schedule activities required on the project, dependencies and other constraints 6.3.1.3 Activity Attributes • describe a necessary sequence of events or defined predecessor or successor relationships 6.3.1.4 Milestone List • scheduled dates for specific milestones, which may influence the way activities are sequenced 6.3.1.5 Project Scope Statement • contains the product scope description (product characteristics), deliverables, project constraints, and project assumptions 6.2.1.3 Enterprise Environmental Factors • Government or industry standards, • Project management information system (PMIS), • Scheduling tool, and • Company work authorization systems. 6.2.1.4 Organizational Process Assets • project files used for scheduling methodology, existing formal and informal activity planning-related policies, procedures, and guidelines, templates. Related activity attributes information in templates can also contain additional descriptive information
  • 20. 6.3.2 Sequence Activities: Tools and Techniques 6.3.2.1 Precedence Diagramming Method technique used for constructing a schedule model in which activities are represented by nodes and are graphically linked by one or more logical relationships to show the sequence in which the activities are to be performed. Activity-on-node (AON) is one method of representing a precedence diagram Finish-to-start (FS). • successor activity cannot start until • predecessor activity has finished. • Example: The awards ceremony (successor) cannot start until the race (predecessor) has finished. Finish-to-finish (FF). • successor activity cannot finish until • predecessor activity has finished. • Example: Writing a document (predecessor) is required to finish before editing the document (successor) can finish. Start-to-start (SS). • successor activity cannot start until • predecessor activity has started. • Example: Level concrete (successor) cannot begin until pour foundation (predecessor) begins. Start-to-finish (SF). • successor activity cannot finish until • predecessor activity has started. • Example: The first security guard shift (successor) cannot finish until the second security guard shift (predecessor) starts
  • 21. 6.3.2 Sequence Activities: Tools and Techniques 6.3.2.1 Precedence Diagramming Method Finish -to- Start (FS). Finish -to- Finish (FF). Start -to- Start (SS).
  • 22. 6.3.2 Sequence Activities: Tools and Techniques 6.3.2.2 Dependency Determination MANDATORY DEPENDENCIES (HARD LOGIC). ◦ legally or contractually required or inherent in the nature of the work. ◦ often involve physical limitations: ◦ erect the superstructure >> after the foundation has been built ◦ a prototype has to be built >> before it can be tested. ◦ Technical dependencies may not be mandatory. DISCRETIONARY DEPENDENCIES (SOFT /PREFERRED LOGIC). ◦ established based on knowledge of best practices within a particular application area or some unusual aspect of the project where a specific sequence is desired, even though there may be other acceptable sequences. ◦ Discretionary dependencies should be fully documented (create arbitrary total float values and can limit later scheduling options). ◦ fast tracking >> should be reviewed and considered for modification or removal.
  • 23. 6.3.2 Sequence Activities: Tools and Techniques 6.3.2.2 Dependency Determination EXTERNAL DEPENDENCIES. relationship between project activities and non-project activities. usually outside the project team’s control. For example, the testing activity in a software project may be dependent on the delivery of hardware from an external source, or governmental environmental hearings may need to be held before site preparation can begin on a construction project. INTERNAL DEPENDENCIES. a precedence relationship between project activities and are generally inside the project team’s control. For example, if the team cannot test a machine until they assemble it, this is an internal mandatory dependency.
  • 24. 6.3.2 Sequence Activities: Tools and Techniques 6.3.2.3 Leads and Lags LEAD A lead is the amount of time whereby a successor activity can be ADVANCED with respect to a predecessor activity. LAG A lag is the amount of time whereby a successor activity will be DELAYED with respect to a predecessor activity. F-S :lag -2w landscaping punch list completion 2w S-S lag :15 days editing the draft punch list completion 15 days
  • 25. 6.3.3 Sequence Activities: OUTPUTS 6.3.3.1 Project Schedule Network Diagrams Graphical representation of the logical relationships (dependencies). It can include full project details, or have one or more summary activities. A summary narrative can accompany the diagram and describe the basic approach used to sequence the activities. Any unusual activity sequences within the network should be fully described within the narrative. Start A B C D Finish
  • 26. 6.4 Estimate Activity Resources estimating the TYPE & QUANTITIES of material, human resources, equipment, or supplies required to perform each activity identifies the type, quantity, & characteristics of resources required to complete the activity which allows more accurate cost and duration estimates Inputs Schedule management plan Activity list Activity attributes Resource calendars Risk register Activity cost estimates Enterprise environmental factors Organizational process assets T&T Expert judgment Alternative analysis Published estimating data Bottom-up estimating Project management software Outputs Activity resource requirements Resource breakdown structure Project documents updates
  • 27. 4 Integration 5 Scope 6 Time 7 Cost 8 Quality 9 H. Resource 10 Commn. 11 Risk 12 Procurement 13 S/holders EEF OPA Enterprise/ Organization 6.1 Plan Schedule Management Schedule M plan 6.2 Define Activities OSOOCT2013 7.2 Estimate Costs Activity cost estimates 6.4 Estimate Activity Resources Data Flow Diagram 6.4 Estimate Activity Resource 6.6 Develop Schedule Activity list Activity attributes Project documents updates Resource breakdown structure Project documents  Activity list,  Activity attributes, and  Resource calendars. Resource calendars 11.2 Identify Risks Risk register 9.2 Acquire Project Team 12.2 Conduct Procurements Activity resource requirements 9.1 Plan HRM 6.6 Estimate Activity Durations
  • 28. 6.4.1 Estimate Activity Resources: Inputs 6.4.1.1 Schedule Management Plan: •identifies the level of accuracy and the units of measure for the resources to be estimated 6.4.1.2 Activity List • identifies the activities which will need resources 6.4.1.3 Activity Attributes •provide the primary data input for use in estimating those resources required for each activity in the activity list 6.4.1.4 Resource Calendars •identifies the working days and shifts on which each specific resource is available 6.4.1.5 Risk Register • Risk events may impact resource selection and availability 6.4.1.6 Activity Cost Estimates •The cost of resources may impact resource selection 6.4.1.7 Enterprise Environmental Factors • resource location, availability, and skills 6.4.1.8 Organizational Process Assets • Policies and procedures regarding staffing, • Policies and procedures relating to rental and purchase of supplies and equipment, • Historical information regarding types of resources used for similar work
  • 29. 6.4.2 Estimate Activity Resources: Tools and Techniques6.4.2.1ExpertJudgment •assess the resource- related inputs to this process. 6.4.2.2AlternativeAnalysis •using various levels of resource capability or skills, •different size or type of machines, •different tools •Make rent- or-buy 6.4.2.3PublishedEstimatingData •updated production rates and unit costs of resources for an extensive array of labor trades, material, and equipment 6.4.2.4Bottom-UpEstimating •aggregating the estimates of the lower- level components of the WBS. 6.4.2.5ProjectManagementSoftware •scheduling software tool, has the capability to help plan, organize, and manage resource pools and develop resource estimates
  • 30. 6.4.3 Estimate Activity Resources: Outputs 6.4.3.1 Activity Resource Requirements • types and quantities of resources required for each activity in a work package. • These requirements then can be aggregated to determine the estimated resources for each work package and each work period 6.4.3.2 Resource Breakdown Structure • hierarchical representation of resources by category and type Project EWR Human resource Project Controls Admin & Fin Construction Materials Construction Mat’l E/M Mat’l Consumables. Equipment Plants Vehicles Machineries
  • 31. 6.5 Estimate Activity Durations estimating the NUMBER of work PERIODS needed to complete individual activities with estimated resources provides the amount of TIME each activity will take to complete, which is a major input into the Develop Schedule process •Activity duration estimates •Project documents updates Outputs •Expert judgment •Analogous estimating •Parametric estimating •Three-point estimating •Group decision-making techniques • Reserve analysis T&T • Schedule management plan • Activity list • Activity attributes • Activity resource requirements • Resource calendars • Project scope statement • Risk register • Resource breakdown structure •Enterprise environmental factors •Organizational process assets Inputs
  • 32. 4 Integration 5 Scope 6 Time 7 Cost 8 Quality 9 H. Resource 10 Commn. 11 Risk 12 Procurement 13 S/holders EEF OPA Enterprise/ Organization 6.1 Plan Schedule Management Schedule M plan 6.2 Define Activities OSOOCT2013 5.3 Define Scope Project scope statement 6.5 Estimate Activity Durations Data Flow Diagram 6.4 Estimate Activity Resource 6.6 Develop Schedule Activity list Activity attributes Project documents updates Resource breakdown structure Project documents  Activity attributes  Assumptions made in developing the activity duration estimate Resource calendars 11.2 Identify Risks Risk register 9.2 Acquire Project Team 12.2 Conduct Procurements Activity resource requirements 11.2 Identify Risks 6.5 Estimate Activity Durations Activity duration estimates
  • 33. 6.5.1 Estimate Activity Durations: Inputs Senior draughtsman 1 hours/sheet 1 No. Junior draughtsman 4 hours/sheet 4 No.
  • 34. 6.5.1 Estimate Activity Durations: Inputs 6.5.1.4 Activity Resource Requirements • the level to which the resources assigned to the activity meet the requirements will significantly influence the duration of most activities 6.5.1.5 Resource Calendars • availability of specific resources, type of resources, and resources with specific attributes. 6.5.1.6 Project Scope Statement • assumptions (Existing conditions, Availability of information, and Length of the reporting periods). • Constraints (Available skilled resources, and Contract terms and requirements). 6.5.1.7 Risk Register • provides the list of risks, along with the results of risk analysis and risk response planning. 6.5.1.8 Resource Breakdown Structure • provides a hierarchical structure of the identified resources by resource category and resource type. 6.5.1.9 Enterprise Environmental Factors • Duration estimating databases and other reference data, • Productivity metrics, • Published commercial information, and • Location of team members. 6.5.1.10 Organizational Process Assets • Historical duration information, • Project calendars, • Scheduling methodology, and • Lessons learned.
  • 35. 6.5.2 Estimate Activity Durations: Tools and Techniques 6.5.2.1 EXPERT JUDGMENT 6.5.2.2 ANALOGOUS ESTIMATING uses parameters from a previous, similar project, such as duration, budget, size, weight, and complexity, as the basis for estimating the same parameter or measure for a future project. less costly ,time less accurate Provide/recommended duration estimate information (from prior similar projects). Determine whether to combine methods of estimating and how to reconcile differences between them.
  • 36. 6.5.2 Estimate Activity Durations: Tools and Techniques 6.5.2.3 PARAMETRIC ESTIMATING 6.5.2.4 THREE-POINT ESTIMATING The accuracy of single-point activity duration estimates may be improved by considering estimation uncertainty and risk. approximate range for an activity’s duration: ◦ tM (Most likely): given the resources likely to be assigned, their productivity, realistic expectations of availability for the activity, dependencies on other participants, and interruptions. ◦ tO (Optimistic). best-case scenario for the activity. ◦ tP (Pessimistic). the worst-case scenario for the activity. algorithm is used to calculate cost or duration based on historical data and project parameters. Parametric estimating uses a statistical relationship between historical data and other variables This technique can produce higher levels of accuracy depending upon the sophistication and underlying data built into the model. A. Duration of design project = No of drawings X No of labor hours per drawing tE = (tO + tM + tP) / 3 (Triangular Distribution) tE = (tO + 4tM + tP) / 6 (Beta Distribution)
  • 37. 6.5.2 Estimate Activity Durations: Tools and Techniques 6.5.2.5 GROUP DECISION-MAKING TECHNIQUES 6.5.2.6 RESERVE ANALYSIS Duration estimates may include contingency reserves (time reserves or buffers), into the project schedule to account for schedule uncertainty. (“known-unknowns,” , %AD, a fixed number of work periods, or may be developed by using quantitative analysis Contingency reserves may be separated from the individual activities and aggregated into buffers. As more precise information about the project becomes available, the contingency reserve may be used, reduced, or eliminated. Management reserves “unknown-unknowns” are a specified amount of the project duration withheld for management control purposes and are reserved for unforeseen work that is within scope of the project. Team-based approaches, such as brainstorming, the Delphi or nominal group techniques, are useful for engaging team members to improve estimate ACCURACY and commitment to the emerging estimates.
  • 38. 6.5.3 Estimate Activity Durations: Outputs 6.5.3.1 Activity Duration Estimates quantitative assessments of the likely number of time periods that are required to complete an activity. 2 weeks ± 2 days, (8 to 12 weeks assuming a five-day workweek); 15 % probability of exceeding three weeks
  • 39. 6.6 Develop Schedule ANALYZING activity sequences, durations, resource requirements, and schedule constraints to create the project schedule model. scheduling tool • schedule activities, • durations, • resources, • resource availabilities, • logical relationships schedule model
  • 40. 6.6 Develop Schedule • Schedule baseline • Project schedule • Schedule data • Project calendars • Project management plan updates • Project documents updates Outputs • Schedule network analysis • Critical path method • Critical chain method • Resource optimization techniques • Modeling techniques • Leads and lags • Schedule compression • Scheduling tool T&T • Schedule management plan • Activity list • Activity attributes • Project schedule network diagrams • Activity resource requirements • Resource calendars • Activity duration estimates • Project scope statement • Risk register • Project staff assignments • Resource breakdown structure • Enterprise environmental factors • Organizational process assets Inputs
  • 41. 4 Integration 5 Scope 6 Time 7 Cost 8 Quality 9 H. Resource 10 Commn. 11 Risk 12 Procurement 13 S/holders EEF OPA Enterprise/ Organization 6.1 Plan Schedule Management Schedule M plan 6.2 Define Activities OSO OCT 2013 6.6 Develop Schedule Data Flow Diagram 5.3 Define Scope Project scope statement 6.4 Estimate Act. Resource 6.6 Develop Schedule Activity list Activity attributes Project documents (u) Resource breakdown structure Project documents  Activity resource requirements.  Activity attributes  Risk register 11.2 Identify Risks Risk register 9.2 Acquire Project Team 12.2 Conduct Procurements Activity resource requirements 6.5 Estimate Activity Durations Activity duration estimates Project m. plan updates 6.3 Sequence Activities Project schedule network diagrams Project staff assignments Resource calendars Schedule baseline Project schedule Project calendars 6.7 Control Schedule 4.2 Develop Project Management Plan 7.2 Estimate Costs 7.3 Determine Budget 12.1 Plan Procurement Management Schedule data  Schedule baseline  Schedule management plan
  • 42. 6.6.1 Develop Schedule: Inputs 6.6.1.1 Schedule Management Plan: • Identifies the scheduling method and tool used to create the schedule, and how the schedule is to be calculated. 6.6.1.2 Activity List • identifies the activities that will be included in the schedule model 6.6.1.3 Activity Attributes • provide the details used to build the schedule model 6.6.1.4 Project Schedule Network Diagrams • Contain the logical relationships of predecessors and successors that will be used to calculate the schedule 6.6.1.5 Activity Resource Requirements • identify the types and quantities of resources required for each activity used to create the schedule model 6.6.1.6 Resource Calendars • contain information on the availability of resources during the project 6.6.1.7 Activity Duration Estimates • contain the quantitative assessments of the likely number of work periods that will be required to complete an activity that will be used to calculate the schedule
  • 43. 6.6.1 Develop Schedule: Inputs 6.6.1.8 Project Scope Statement • contains assumptions and constraints that can impact the development of the project schedule. 6.6.1.9 Risk Register • provides the details of all identified risks and their characteristics that affect the schedule model. 6.6.1.10 Project Staff Assignments • specify which resources are assigned to each activity. 6.6.1.11 Resource Breakdown Structure • provides the details by which resource analysis and organizational reporting can be done. 6.2.1.3 Enterprise Environmental Factors • Standards, • Communication channels • Scheduling tool to be used in developing the schedule model. 6.2.1.4 Organizational Process Assets • scheduling methodology and project calendar(s)
  • 44. 6.6.2 Develop Schedule: Tools and Techniques 6.6.2.1 Schedule Network Analysis technique generates the project schedule model ,employs various analytical techniques to calculate the early and late start and finish dates for the uncompleted portions of project activities: critical path method critical chain method what-if analysis resource optimization techniques
  • 45. 6.6.2 Develop Schedule: Tools and Techniques 6.6.2.2 Critical Path Method a method used to estimate the MINIMUM project duration and determine the amount of scheduling flexibility on the logical network paths within the schedule model. calculates the early start, early finish, late start, and late finish dates for all activities (without regard for any resource limitations) by performing a forward and backward pass analysis  The critical path is the sequence of activities that represents the LONGEST path through a project, which determines the SHORTEST possible project duration. CPM is used to calculate the amount of scheduling FLEXIBILITY (the amount of time that a schedule activity can be delayed or extended from its early start date without delaying the project finish date or violating a schedule constraint, and is termed “TOTAL FLOAT.”
  • 46. 6.6.2 Develop Schedule: Tools and Techniques 6.6.2.2 Critical Path Method A 1 0 5 1 5 5 <ACTIVITY NAME> LS TF LF ES DU EF C 6 0 15 6 10 15 D 16 0 30 16 15 30 B 11 5 15 6 5 10START FINISH
  • 47. 6.6.2 Develop Schedule: Tools and Techniques 6.6.2.3 Critical Chain Method CCM is a schedule method that allows to place buffers on any project schedule path to account for limited resources and project uncertainties. It is developed from the critical path method approach and considers the effects of resource allocation, resource optimization, resource leveling, and activity duration uncertainty on the critical path determined using the critical path method. The critical chain method uses activities with durations that do not include safety margins, logical relationships, and resource availability with statistically determined buffers composed of the aggregated safety margins of activities at specified points on the project schedule path to account for limited resources and project uncertainties. The resource-constrained critical path is known as the critical chain.
  • 48. 6.6.2 Develop Schedule: Tools and Techniques 6.6.2.3 Critical Chain Method A C D B START FINISH E G F FB FB PB Critical Chain LINK NON Critical Chain LINK duration buffers: • non-work schedule activities to manage uncertainty. project buffer: • at the end of the critical chain protects the target finish date from slippage along the critical chain. feeding buffers: • at point where a chain of dependent activities that are not on the critical chain feeds into the critical chain. (protect CC from slippage along the FC)
  • 49. 6.6.2 Develop Schedule: Tools and Techniques 6.6.2.4 Resource Optimization Techniques RESOURCE LEVELING: ◦ A technique in which start and finish dates are ADJUSTED based on resource constraints with the goal of balancing demand for resources with the available supply. ◦ Resource leveling can be used when shared or critically required resources are only available at certain times, or in limited quantities, or over- allocated, ◦ Resource leveling can often cause the original critical path to change, usually to increase A C B START DAY-1 DAY-2 DAY-3 2 1 1 A CBSTART DAY-1 DAY-2 DAY-3 1 1 1 1
  • 50. 6.6.2 Develop Schedule: Tools and Techniques 6.6.2.4 Resource Optimization Techniques RESOURCE SMOOTHING A technique that adjusts the activities of a schedule model such that the requirements for resources on the project DO NOT exceed certain predefined resource limits. the project’s critical path is NOT CHANGED and the completion date may not be delayed (opposed to resource leveling). activities may only be delayed within their free and total float. not be able to optimize all resources A C B START DAY-1 DAY-2 DAY-3 2 1 1 1 DAY 1 DAY 1 DAY A C B START DAY-1 DAY-2 DAY-3 1 1 1 2 DAY 1 DAY 1 DAY 1
  • 51. 6.6.2 Develop Schedule: Tools and Techniques 6.6.2.5 Modeling Techniques WHAT-IF SCENARIO ANALYSIS. process of evaluating scenarios in order to predict their effect, positively or negatively, on project objectives. “What if the situation represented by scenario ‘X’ happens?” A schedule network analysis is performed using the schedule to compute the different scenarios, (delaying a major component delivery) The outcome of the what-if scenario analysis can be used to assess the feasibility of the project schedule under adverse conditions, and in preparing contingency and response plans to overcome or mitigate the impact of unexpected situations. SIMULATION Simulation involves calculating multiple project durations with different sets of activity assumptions, usually using probability distributions constructed from the three-point estimates to account for uncertainty. The most common simulation technique is Monte Carlo analysis, in which a distribution of possible activity durations is defined for each activity and used to calculate a distribution of possible outcomes for the total project
  • 52. 6.6.2 Develop Schedule: Tools and Techniques 6.6.2.7 Schedule Compression CRASHING A technique used to shorten the schedule duration for the least incremental cost by ADDING resources. ◦ approving overtime, bringing in additional resources, or paying to expedite delivery to activities on the critical path. Crashing works only for activities on the critical path where additional resources will shorten the activity’s duration. Crashing does not always produce a viable alternative and may result in increased risk and/or cost. FAST TRACKING technique in which activities or phases normally done in SEQUENCE are performed in PARALLEL for at least a portion of their duration. Fast tracking may result in rework and increased risk. Fast tracking only works if activities can be overlapped to shorten the project duration techniques used to shorten the duration without reducing scope, to meet schedule constraints, imposed dates, or other objectives foundation Arch Design foundation DAY-1 DAY-2 DAY-3 DAY-4 DAY-5 Arch Design
  • 53. 6.6.3 Develop Schedule: Outputs 6.6.3.1 Schedule Baseline approved version (by the appropriate stakeholders ) of a schedule model that can be CHANGED ONLY through formal change control procedures and is used as a basis for comparison to actual results. During monitoring and controlling, the approved baseline dates are compared to the actual start and finish dates to determine whether variances have occurred.
  • 54. 6.6.3 Develop Schedule: Outputs 6.6.3.2 Project Schedule The project schedule is an output of a schedule model that presents linked activities with planned dates, durations, milestones, and resources. (minimum includes a planned start date and planned finish date for each activity). If resource planning is done at an early stage, then the project schedule remains preliminary until resource assignments have been confirmed and scheduled start and finish dates are established. This process usually occurs no later than the completion of the project management plan The project schedule presentation may be presented in summary form, or in detail (tabular form, graphically): ◦ Bar charts (Gantt charts) ◦ Milestone charts ◦ Project schedule network diagrams. ◦ in the activity-on-node diagram format showing activities and relationships without a time scale, sometimes referred to as a pure logic diagram,
  • 55. 2013 Design CONSTRUCTION •21/3/2013 •1/8/2013 DecOctSepAugJulyJuneAprilMarchFebJan May Nov •1/11/2013 EQUIPMENT INSTALLATION •1/1/2013 •1/3/2013 TESTING & COMMISSIONING EXT. W. & FINISHING Bar charts (Gantt charts) HANDOVER MS 3 MS 1 MS 2 EQPT RP START A • ES … • EF .. B • ES … • EF .. C • ES … • EF .. MS Milestone • only identify the scheduled start or completion of major deliverables and key external interfaces HAMMOCK •more comprehensive summary activity between milestones or across multiple interdependent work packages, and is displayed in bar chart reports network diagrams •in the activity-on-node diagram format showing activities and relationships without a time scale, sometimes referred to as a pure logic diagram
  • 56. 6.6.3 Develop Schedule: Outputs 6.6.3.2 Project Schedule
  • 57. 6.6.3 Develop Schedule: Outputs 6.6.3.3 Schedule Data & 6.6.3.4 Project Calendars 6.6.3.3 SCHEDULE DATA collection of information for describing and controlling the schedule includes at least : ◦ milestones, schedule activities, activity attributes, assumptions and constraints. ◦ supporting detail includes: ◦ Resource requirements by time period (resource histogram) ◦ Alternative schedules (best-case or worst-case, not resource-leveled, or resource-leveled) ◦ Scheduling of contingency reserves. 6.6.3.4 PROJECT CALENDARS working days and shifts that are available for scheduled activities. It distinguishes time periods that are available to complete scheduled activities from time periods that are not available. A schedule model may require more than one project calendar to allow for different work periods for some activities to calculate the project schedule.
  • 58. 6.7 Control Schedule MONITORING the status of project activities to update project progress and manage changes to the schedule baseline to achieve the plan. provides the means to recognize deviation from the plan and take corrective and preventive actions and thus minimize risk. Inputs Project management plan Project schedule Work performance data Project calendars Schedule data Organizational process assets T&T Performance reviews Project management software Resource optimization techniques Modeling techniques Leads and lags Schedule compression Scheduling tool Outputs Work performance information Schedule forecasts Change requests Project management plan updates Project documents updates Organizational process assets updates
  • 60. 6.7 Control Schedule Agile approach COMPARING the total amount of work delivered and accepted against the estimates of work completed for the elapsed time cycle, Conducting RETROSPECTIVE reviews (scheduled reviews to record lessons learned) for correcting processes and improving, if required, REPRIORITIZING the remaining work plan (backlog), Determining the RATE at which the deliverables are produced, validated, and accepted (velocity) in given time per iteration (agreed work cycle duration, typically two weeks or one month), Determining that the project schedule has CHANGED & Managing the actual changes as they occur.
  • 61. 6.7 Control Schedule 6.7.1 Control Schedule: Inputs 6.7.1.1 Project Management Plan • how the schedule will be managed and controlled. • schedule baseline -reference -compare with actual - change, corrective action, or preventive action 6.7.1.2 Project Schedule • the most recent version with notations to indicate updates, completed activities, and started activities. 6.7.1.3 Work Performance Data • project progress information (actual duration, remaining duration, and physical percent complete)
  • 62. 6.7. 2 Control Schedule : Tools and Techniques 6.7.2.1 Performance Reviews Trend analysis •examines project performance over time to determine whether performance is improving or deteriorating (Using Graphical analysis techniques). Critical path method •Comparing the progress along the critical path. •The variance on the critical path will have a direct impact on the project end date. •Evaluating the progress of activities on near critical paths can identify schedule risk. Earned value management •SV and SPI are used to assess the magnitude of variation to the original schedule baseline. •The total float and early finish variances are also essential planning components •determining the cause and degree of variance relative to baseline •estimating the implications of those variances for future work to completion •deciding whether corrective or preventive action is required. Performance reviews measure, compare, and analyze schedule performance
  • 63. 6.7. 2 Control Schedule : Tools and Techniques 6.7.2.2-7 6.7.2.2 Project Management Software • provides the ability to track planned vs. actual, to report variances ,progress , forecast. 6.7.2.3 Resource Optimization Techniques • involve the scheduling of activities and the resources required taking into consideration both the resource availability and the project time. 6.7.2.4 Modeling Techniques • review various scenarios guided by risk monitoring to bring the schedule model into alignment with the project management plan and approved baseline. 6.7.2.5 Leads and Lags • applied during network analysis to find ways to bring project activities that are behind into alignment with the plan. 6.7.2.6 Schedule Compression • find ways to bring project activities that are behind into alignment with the plan by fast tracking or crashing schedule for the remaining work. 6.7.2.7 Scheduling Tool • perform schedule network analysis to generate an updated project schedule.
  • 64. 6.7.3 Control Schedule: Outputs 6.7.3.1 Work Performance Information • SV and SPI time performance indicators for WBS components, are documented and communicated to stakeholders. 6.7.3.2 Schedule Forecasts • estimates or predictions of conditions and events in the project’s future based on information and knowledge available 6.7.3.3 Change Requests • Schedule variance analysis, along with review of progress reports, results of performance measures, and modifications to the project scope or project schedule may result in change requests to the schedule baseline, scope baseline, and/or other components of the project management plan. 6.7.3.4 Project Management Plan Updates • Schedule baseline. • Project Schedule • Risk Register 6.7.3.6 Organizational Process Assets Updates • Causes of variances • Corrective action chosen and the reasons • Other types of lessons learned from project schedule control.