Hit the Roadway Running - Streamlining
DOT Project Costs using PCM
Prepare...
Types of Projects
■ Flood Control Program
■ TxDOT Pass-through Finance Projects*
* Presentation focus
Modules Used in Pass-through Projects
■ Companies
■ RFIs
■ Daily Reports*
■ Notepads
■ Corr Received
■ Submittals
■ Commit...
What is a Pass-through Finance Project?
■ Pass-through financing allows local communities to fund
upfront costs for constr...
Project Team
■ Engineering Consultant/Construction Manager (CM)
■ Bexar County Public Works Construction Administration
En...
TxDOT Procedures
■ Daily Requirements
▪ TxDOT 1257 Work Report form must be filled out daily
— Records the quantity of eac...
PCM Module Translation
■ TxDOT 1257 Work Report = Materials Delivery
■ Time Statement = Daily Report custom fields
■ Month...
Customizations to PCM
■ Custom fields in Daily Report for Time Statement
■ Time Statement report
■ Renamed Materials modul...
Project Quantities Module (Materials)
■ Contractor’s contract entered as line item based Committed
Contract
■ Materials ge...
DEMO
This is a subtitle or bulleted list
Daily Report Module
■ Inspectors (hired by CM) use Daily Report module
■ Inspectors fill out 1257, then record work perfor...
TXDot 1257 Work Report
DEMO
This is a subtitle or bulleted list
Project Quantity Reports
■ Quantities not yet Requisitioned report
▪ Used at end-of-month Project Meeting, for everyone to...
Payment Requisitions
■ Generated monthly
■ Project Quantities (aka materials) are “gotten” into each
payment requisition
■...
DEMO
This is a subtitle or bulleted list
Change Orders
■ Line item based, like the Contract
■ Added to the monthly estimate as an additional line for each
change i...
Questions?
This is a subtitle or bulleted list
Please complete the session
evaluation
We appreciate your feedback and insight
You may complete the session evaluation eit...
■ Our purpose is to inform and educate our members on current and future
functionality of Oracle Primavera products, while...
Prochain SlideShare
Chargement dans…5
×

Hit the Roadway Running - Streamlining DOT project costs using PCM

246 vues

Publié le

Referenced: www.p6academy.com
Source: http://coll15.mapyourshow.com

Bexar County Public Works Division in San Antonio, TX is using PCM to manage their Texas Department of Transportation (TxDOT) State Highway Pass-Through projects. Bexar County currently has three active Pass-Through projects using PCM, with five more anticipated in FY2015. TxDOT maintains oversight to ensure projects are managed and constructed in accordance with their procedures. PCM has been effectively implemented at Bexar County to fulfill these requirements. The County uses PCM to manage all aspects of these projects: communication, cost control, and reporting. Using Materials and Daily Reports to track pay item progress, monthly estimates are automatically generated in the Payment Requisition module and tracked in the Cost Worksheet. The ease of information accessibility and the satisfaction of TxDOT audits demonstrate PCM’s success.

Publié dans : Business
  • Soyez le premier à commenter

  • Soyez le premier à aimer ceci

Hit the Roadway Running - Streamlining DOT project costs using PCM

  1. 1. REMINDER Check in on the COLLABORATE mobile app Hit the Roadway Running - Streamlining DOT Project Costs using PCM Prepared by: Donna Coleman Senior Consultant/President Samsara Project Technology, LLC Bexar County Public Works Department San Antonio, TX Session ID#: 201300
  2. 2. Types of Projects ■ Flood Control Program ■ TxDOT Pass-through Finance Projects* * Presentation focus
  3. 3. Modules Used in Pass-through Projects ■ Companies ■ RFIs ■ Daily Reports* ■ Notepads ■ Corr Received ■ Submittals ■ Committed Contracts* ■ Materials Delivery* ■ Payment Requisitions* ■ Change Orders* ■ Cost Worksheet* * Modules to be discussed
  4. 4. What is a Pass-through Finance Project? ■ Pass-through financing allows local communities to fund upfront costs for constructing a state highway project. The state then reimburses a portion of the project cost to the community over time by paying a fee for each vehicle that drives on the new highway. Projects must be on the state highway system to be eligible to be developed under this program.
  5. 5. Project Team ■ Engineering Consultant/Construction Manager (CM) ■ Bexar County Public Works Construction Administration Engineer ■ Bexar County Public Works Project Manager ■ Contractor
  6. 6. TxDOT Procedures ■ Daily Requirements ▪ TxDOT 1257 Work Report form must be filled out daily — Records the quantity of each pay item completed — One 1257 per Contract pay item — Location of Work Performed and how Quantity was determined ■ Monthly Requirements ▪ Monthly Estimate — Every line must have a unique number — Every item must have a TxDOT Cost Element associated ▪ Time Statement — Identifies every Work and Non-Work day in calendar year
  7. 7. PCM Module Translation ■ TxDOT 1257 Work Report = Materials Delivery ■ Time Statement = Daily Report custom fields ■ Monthly Estimate = Payment Requisition
  8. 8. Customizations to PCM ■ Custom fields in Daily Report for Time Statement ■ Time Statement report ■ Renamed Materials module to Project Quantities ■ Renamed Materials tab in Daily Reports - Project Quantities ■ Custom Project Quantity Reports ■ Custom Monthly Estimate form (Payment Requisition)
  9. 9. Project Quantities Module (Materials) ■ Contractor’s contract entered as line item based Committed Contract ■ Materials generated from Contract as Project Quantity “folders” ■ Delivery Tickets (renamed Completed Progress) entered via Daily Report
  10. 10. DEMO This is a subtitle or bulleted list
  11. 11. Daily Report Module ■ Inspectors (hired by CM) use Daily Report module ■ Inspectors fill out 1257, then record work performed using Project Quantities tab within Daily Report ■ 1257 is scanned and attached on Attachments tab of the corresponding quantity entered
  12. 12. TXDot 1257 Work Report
  13. 13. DEMO This is a subtitle or bulleted list
  14. 14. Project Quantity Reports ■ Quantities not yet Requisitioned report ▪ Used at end-of-month Project Meeting, for everyone to agree on quantities ▪ Used prior to generating monthly estimate ■ “Jim Brannan report” ▪ Prompt for criteria on TxDOT item codes, then reports which payment requisitions quantities have been applied/invoiced and date it was created
  15. 15. Payment Requisitions ■ Generated monthly ■ Project Quantities (aka materials) are “gotten” into each payment requisition ■ Invoice is built automatically for Contractor’s payment
  16. 16. DEMO This is a subtitle or bulleted list
  17. 17. Change Orders ■ Line item based, like the Contract ■ Added to the monthly estimate as an additional line for each change item ■ New estimate line items renumbered to sort under each change’s original contract pay item ■ Project Quantity folders created manually to allow quantities for each new change line item
  18. 18. Questions? This is a subtitle or bulleted list
  19. 19. Please complete the session evaluation We appreciate your feedback and insight You may complete the session evaluation either on paper or online via the mobile app
  20. 20. ■ Our purpose is to inform and educate our members on current and future functionality of Oracle Primavera products, while offering a forum for peers to share their experience and knowledge in the use of Primavera. ■ Educational opportunities across the Primavera product suite ■ Online Learning Series August 17th – September 4th ■ Call for presentation opening April 27th ■ Monthly Community Calls ■ 3rd Thursday of the month at 1:00 pm ET ■ Networking with other users within the Primavera community ■ Partnering with Oracle Primavera to meet the needs of our diverse membership. ■ Membership is open to anyone with an interest in the Oracle Primavera products, with no dues for membership. All members can vote on matters brought before the OPSIG. Membership requests may be reviewed by the OPSIG board. OPSIG is the home for Primavera Users

×