Streamline collection and approval of status updates with oracle primavera ppt
- 1. 1 Copyright © 2012, Oracle and/or its affiliates. All rights
reserved.
Insert Information Protection Policy Classification from Slide 8
- 2. 2 Copyright © 2012, Oracle and/or its affiliates. All rights
reserved.
Insert Information Protection Policy Classification from Slide 8
Streamline collection and approval of status
updates with Oracle Primavera
Eileen Schurmann
- 3. 3 Copyright © 2012, Oracle and/or its affiliates. All rights
reserved.
Insert Information Protection Policy Classification from Slide 8
How do you collect
status today?
- 4. 4 Copyright © 2012, Oracle and/or its affiliates. All rights
reserved.
Insert Information Protection Policy Classification from Slide 8
E-mail
- 5. 5 Copyright © 2012, Oracle and/or its affiliates. All rights
reserved.
Insert Information Protection Policy Classification from Slide 8
Hand
written
- 6. 6 Copyright © 2012, Oracle and/or its affiliates. All rights
reserved.
Insert Information Protection Policy Classification from Slide 8
Conversations
- 7. 7 Copyright © 2012, Oracle and/or its affiliates. All rights
reserved.
Insert Information Protection Policy Classification from Slide 8
Then What?
- 8. 8 Copyright © 2012, Oracle and/or its affiliates. All rights
reserved.
Insert Information Protection Policy Classification from Slide 8
Scrub
Data
- 9. 9 Copyright © 2012, Oracle and/or its affiliates. All rights
reserved.
Insert Information Protection Policy Classification from Slide 8
Enter
data
- 10. 10 Copyright © 2012, Oracle and/or its affiliates. All rights
reserved.
Insert Information Protection Policy Classification from Slide 8
Time
consuming
- 11. 11 Copyright © 2012, Oracle and/or its affiliates. All rights
reserved.
Insert Information Protection Policy Classification from Slide 8
Out of
date
- 12. 12 Copyright © 2012, Oracle and/or its affiliates. All rights
reserved.
Insert Information Protection Policy Classification from Slide 8
What could PMs be doing?
- 13. 13 Copyright © 2012, Oracle and/or its affiliates. All rights
reserved.
Insert Information Protection Policy Classification from Slide 8
Manage projects
Solving problems
Identifying trends
- 14. 14 Copyright © 2012, Oracle and/or its affiliates. All rights
reserved.
Insert Information Protection Policy Classification from Slide 8
3 Choices: Web, Email, Mobile
- 15. 15 Copyright © 2012, Oracle and/or its affiliates. All rights
reserved.
Insert Information Protection Policy Classification from Slide 8
Door number 1: Web
- 16. 16 Copyright © 2012, Oracle and/or its affiliates. All rights
reserved.
Insert Information Protection Policy Classification from Slide 8
16
Team Member Web Interface
- 17. 17 Copyright © 2012, Oracle and/or its affiliates. All rights
reserved.
Insert Information Protection Policy Classification from Slide 8
…and it
looks
GREAT
on a
tablet
- 18. 18 Copyright © 2012, Oracle and/or its affiliates. All rights
reserved.
Insert Information Protection Policy Classification from Slide 8
508 Compliant!
- 19. 19 Copyright © 2012, Oracle and/or its affiliates. All rights
reserved.
Insert Information Protection Policy Classification from Slide 8
All Languages
- 20. 20 Copyright © 2012, Oracle and/or its affiliates. All rights
reserved.
Insert Information Protection Policy Classification from Slide 8
Door number 2: Email
- 21. 21 Copyright © 2012, Oracle and/or its affiliates. All rights
reserved.
Insert Information Protection Policy Classification from Slide 8
Request tasks
Limit which tasks to status with the following options:
• Task Status
• Time Period
• Project ID & Project Name
- 22. 22 Copyright © 2012, Oracle and/or its affiliates. All rights
reserved.
Insert Information Protection Policy Classification from Slide 8
Receive & update tasks
- 23. 23 Copyright © 2012, Oracle and/or its affiliates. All rights
reserved.
Insert Information Protection Policy Classification from Slide 8
Receive confirmation
- 24. 24 Copyright © 2012, Oracle and/or its affiliates. All rights
reserved.
Insert Information Protection Policy Classification from Slide 8
Door number 3: mobile
- 25. 25 Copyright © 2012, Oracle and/or its affiliates. All rights
reserved.
Insert Information Protection Policy Classification from Slide 8 25
Simple list of responsible work
- 26. 26 Copyright © 2012, Oracle and/or its affiliates. All rights
reserved.
Insert Information Protection Policy Classification from Slide 8 26
Collect accurate status
- 27. 27 Copyright © 2012, Oracle and/or its affiliates. All rights
reserved.
Insert Information Protection Policy Classification from Slide 8
Facilitate communication
- 28. 28 Copyright © 2012, Oracle and/or its affiliates. All rights
reserved.
Insert Information Protection Policy Classification from Slide 8
Coming in faster than ever before
- 29. 29 Copyright © 2012, Oracle and/or its affiliates. All rights
reserved.
Insert Information Protection Policy Classification from Slide 8
Is it right?
- 30. 30 Copyright © 2012, Oracle and/or its affiliates. All rights
reserved.
Insert Information Protection Policy Classification from Slide 8
“No way,
they will mess up
everything!”
- 31. 31 Copyright © 2012, Oracle and/or its affiliates. All rights
reserved.
Insert Information Protection Policy Classification from Slide 8
Control
- 32. 32 Copyright © 2012, Oracle and/or its affiliates. All rights
reserved.
Insert Information Protection Policy Classification from Slide 8
32
Project Preferences
- 33. 33 Copyright © 2012, Oracle and/or its affiliates. All rights
reserved.
Insert Information Protection Policy Classification from Slide 8
Stage it
- 34. 34 Copyright © 2012, Oracle and/or its affiliates. All rights
reserved.
Insert Information Protection Policy Classification from Slide 8
Review it
- 35. 35 Copyright © 2012, Oracle and/or its affiliates. All rights
reserved.
Insert Information Protection Policy Classification from Slide 8
Approval
- 36. 36 Copyright © 2012, Oracle and/or its affiliates. All rights
reserved.
Insert Information Protection Policy Classification from Slide 8
Update History Tab
- 37. 37 Copyright © 2012, Oracle and/or its affiliates. All rights
reserved.
Insert Information Protection Policy Classification from Slide 8
Time to your PM’s
- 38. 38 Copyright © 2012, Oracle and/or its affiliates. All rights
reserved.
Insert Information Protection Policy Classification from Slide 8
Manage projects
Solving problems
Identifying trends
- 39. 39 Copyright © 2012, Oracle and/or its affiliates. All rights
reserved.
Insert Information Protection Policy Classification from Slide 8
Q&A