Technical guides for owner/manager of an air conditioning
                    system : volume 4


AN AUDITAC PROPOSED PRELIMINARY
   AUDIT METHODOLOGY FOR AIR-
     CONDITIONING FACILITIES
Team

                                   France (Project coordinator)
                                    Armines - Mines de Paris

                          Austria
                                                                        Slovenia
                  Austrian Energy Agency
                                                                  University of Ljubljana

                          Belgium                                            UK
                     Université de Liège                           Association of Building
                                                                        Engineers
                            Italy                                            BRE
                    Politecnico di Torino                            (Building Research
                                                                     Establishment Ltd)
                         Portugal
                     University of Porto                              Welsh School of
                                                                       Architecture

                                Eurovent-Certification



Authors of this volume
Jerome ADNOT (Armines, France)
Daniela BORY (Armines, France)
Vincenc BUTALA (University of Ljubljana)
Ian KNIGHT (Welsh School of Architecture, UK)
Marco MASOERO (Politecnico di Torino)
Simon MUHIC (University of Ljubljana)
Chiara SILVI (Politecnico di Torino)

  The sole responsibility for the content of this publication lies with the authors. It does not
represent the opinion of the European Communities. The European Commission is not
responsible for any use that may be made of the information contained therein.
AN AUDITAC PROPOSED PRELIMINARY AUDIT METHODOLOGY FOR
               AIR-CONDITIONING FACILITIES
In this brochure we present a typical procedure for a preliminary audit for air-conditioning
facilities.

Preliminary audit is a first step of the audit procedure where the auditor has a first
approach with the plant. This procedure is very important for the comprehension of the
design of the plant and its use. The auditor will be able, at the end of the procedure, to
identify preliminary energy saving opportunities. Some easy energy saving actions can
be made operational immediately after the preliminary audit, whereas other potential
actions may require normally a more detailed analysis, in order to assess their
effectiveness and their economic performance. The actions requiring a deeper analysis
of the system are best performed during the subsequent detailed audit.



The preliminary audit structure
In a preliminary audit procedure one detects the errors in the AC systems through data
gathering, visual detection and with measurements. Preliminary audit involves an
interview of the site operating staff, a review of facility utility bills and other operating
data, and a walk-through of the facility (to become familiar with the building operation
and to identify obvious areas of energy waste or inefficiency). Typically, only major
problem areas will be discovered during this type of audit. This level of detail, while not
sufficient to take all improvement decisions, is adequate to prioritize energy efficiency
projects and determine the need for a more detailed audit.

Preliminary audit activities should include the following sequential steps:

       • Identify the air-conditioning system type(s) in use in the building
       • Evaluate the conditions of use and the operational state of the system
       • Find out and describe the possible impact of improvements to this system
       • Write up a preliminary audit report

The preliminary audit is less expensive than the detailed one, but is nonetheless an
important study that can yield a very useful estimate of savings potential and a list of
low-cost savings opportunities, through improvements in operational and maintenance
practices. The preliminary audit information will be used to underpin the more detailed
audit, if the energy saving potentials appear to warrant further auditing activity.

The first step of the preliminary audit process should be the collection of information.
The information may be collected on the structural and mechanical components that
affect building energy use and the operational characteristics of the facility. Much of this
information can be collected prior to the site visit. Evaluating energy use and systems
before going on-site helps identify potential savings and makes best use of time spent
on-site.

The preliminary audit consists of three distinct steps:

     Step 1: preliminary data collection and evaluation,
     Step 2: site visit,
     Step 3: analysis and reporting.

       Step1: Preliminary Data Collection and Evaluation
A pre-site review of building systems and their operation should generate a list of
specific questions and issues to be discussed during the actual visit to the facility. This
preparation will help ensure the most effective use of on-site time and minimize
disruptions to building personnel. A thorough pre-site review will also reduce the time
required to complete the on-site portion of the audit.

The first task is to collect and review two years worth of utility energy data for electricity.
The air-conditioning system consumption data should be provided if the system energy
is measured separately. This information is used to analyse operational characteristics,
calculate some energy benchmarks for comparison to averages, estimate savings
potential, set an energy reduction target, and establish a baseline to monitor the
effectiveness of implemented measures.

The building manager should provide occupancy schedules, operation and maintenance
practices, and plans that may have an impact on energy consumption. This kind of
information can help identify times when building systems such as lighting, recirculating
pumps or outside air ventilation can be turned off and temperatures set back. The
building manager should ideally also provide documentation for all the above
information. If the data are not available, or they don't correspond to reality, then the first
action should be to help to collect the data.

Analysing Energy Data
If the A/C system energy consumption is available separately, then a Cooling Energy
Index (CEI) could be calculated to compare energy consumption to similar building types
or to track consumption from year to year in the same building. The CEI consist of
calculated ratios based on the annual consumption and the area (gross or conditioned
square meters) of the building. CEI is a good indicator of the relative potential for energy
savings. A comparatively low CEI indicates less potential for large energy savings. By
tracking the CEI using a rolling 12-month block, building performance can be evaluated
based on increasing or decreasing energy use trends. This method requires a minimum
of two years of energy consumption data to establish the trend line and values including
weather correction.
Caution has to be used in benchmarking in order to compare comparable values
between different buildings. The best benchmark method would take into account
different parameters (weather, sector, air control factors etc.). Actually, there are few air-
conditioning benchmark references and often general benchmarks (all thermal energy
use, or all electricity use) are most commonly used and available. In that case it is more
difficult to track air conditioning specifically. However when metering is periodic
(monthly, e.g.) it becomes possible to estimate the additional electricity use related with
hot weather.

Looking at Loads for cooling
Cooling loads include occupants, lighting, office equipment, appliances, solar gains and
specific processes. High loads are in general easy to detect and the energy
management efforts should be focused in these areas. High loads may reveal
opportunities to reduce consumption by making improvements to the air conditioning
equipment, temperature controls, the building envelope, or to other systems which are
affected by operation. After utility use has been allocated, the auditor should prepare a
list of the major energy-using systems in the building and estimate the time when each
system is in operation throughout the year. The list will help identify how each system
uses energy and potential savings. Building systems can then be targeted for more
detailed data collection. One of the easiest ways to evaluate energy data is to watch for
the trends in use, demand, or costs over time. Either graphing two or more years of
monthly data on one graph or graphing only the annual totals for several years can help.

Building Profile
Obtaining mechanical, architectural, and electrical drawings and specifications for the
original building as well as for any additions or remodelling work that may have been
done is the first step to creating a building profile. Any past energy audits or studies
should be reviewed. The auditor can use this information to develop a building profile
narrative that includes age, occupancy, description, and existing conditions of
architectural, mechanical, and electrical systems. The profile should note the major
energy-consuming equipment or systems and identify systems and components that are
inherently inefficient. A site sketch of the building(s) surveyed should also be made. The
sketch should show the relative location and outline of each building; the name of each
building; year of construction of each building and additions; dimensions of each building
and additions; location and identification numbers of utility meters; central plant; and
orientation of the complex.

While completing the pre-site visit review, the auditor should note areas of particular
interest and write down any questions about the lighting systems and controls, HVAC
zone controls, or setback operation. Other questions may regard equipment
maintenance practices. At this point the auditor should discuss preliminary observations
with the building manager or operator. The building manager or operator should be
asked about their interest in particular conservation projects or planned changes to the
building or its systems. The audit should be scheduled when key systems are in
operation and when the building operator can take part.

Some AUDITAC tools (Case Study database, AC-Cost spreadsheet and Customer
Advising      Tool)    will      become        available     from       our      website
(http://www.energyagency.at/(en)/projekte/auditac.htm) to support this activity.
Step2: The Site Visit
The site visit will be spent inspecting actual systems and answering specific questions
from the preliminary review. The amount of time required will vary depending on the
completeness of the preliminary information collected, the complexity of the building and
systems, and the need for testing equipment.

Having several copies of a simple floor plan of the building will be useful for notes during
the site visit. A separate copy should be made for noting information on locations of
HVAC equipment and controls, heating zones, light levels, and other energy-related
systems. If architectural drawings are not available, emergency fire exit plans are usually
posted on each floor; these plans are a good alternative for a basic floor plan.

Prior to touring the facility, the auditor and building manager should review the auditor's
energy consumption profiles.

Step3: Analysis and Reporting
Post-site work is a necessary and important step to ensure the preliminary audit will be
useful. The auditor needs to evaluate the information gathered during the site visit,
research possible Energy Conservation Opportunities (ECO’s), organize the audit into a
comprehensive report, and make recommendations on improvements. The report from
the preliminary audit, with possible ECO’s, should be used as the basic input for
subsequent more detailed audits.

This brochure includes an extensive list of ECOs for air-conditioned buildings covering
three major aspects:

•   ENVELOPE AND LOADS
•   PLANT
•   OPERATION AND MAINTENANCE (O&M)

The “O&M” ECO’s include all actions that may in general be implemented in a building,
HVAC system, or facility management scheme. The costs involved in implementing
“O&M” ECO’s are generally limited if not negligible, application is therefore normally
recommended, provided their technical feasibility is assessed.

“Plant” ECO’s, on the contrary, can involve radical intervention on the HVAC system.
Their applicability should therefore be carefully assessed both from the
technical and economical standpoint. For this purpose, a review of the main cost-benefit
evaluation methods is presented in this report.

In the “Envelope and Loads” categories, ECO’s aimed at reducing the building cooling
load are listed. These ECO’s may be either of the operational type, or may involve
renovation work on the building envelope. Therefore, the evaluation methods may be
similar to those normally applied either to category “O&M” or “Plant”.
Several of the ECO’s of each of the above categories may be effectively implemented
with the aid of a Building Energy Management System (BEMS). Use of BEMS is
highlighted in a specific column of the ECO list.


Energy conservation opportunities (ECO) for air-conditioned buildings
                                   ENVELOPE AND LOADS
CODE                                               ECO                                               BEMS
                                                                                                     control
         SOLAR GAIN REDUCTION / DAYLIGHT CONTROL IMPROVEMENT
 E1.1                                       Install window film or tinted glass

 E1.2                               Install shutters, blinds, shades, screens or drapes

 E1.3                        Operate shutters, blinds, shades, screens or drapes                       Y
 E1.4                                 Replace internal blinds with external systems

 E1.5                               Close off balconies to make sunspace/greenhouse

 E1.6                                       Modify vegetation to save energy

 E1.7                                         Maintain windows and doors

         VENTILATION / AIR MOVEMENT / AIR LEAKAGE IMPROVEMENT
 E2.1              Generate possibility to close/open windows and doors to match climate              Y/N
 E2.2                             Ensure proper ventilation of attic spaces                            Y
 E2.3                             Optimise air convection paths in shafts and stairwells

 E2.4                                    Correct excessive envelope air leakage

 E2.5                                Roller shutter cases – Insulate and seal air leaks

 E2.6                       Generate possibility of night time cooling through overventilation

 E2.7               Add automatic door closing system between conditioned and unconditioned spaces

 E2.8                      Replace doors with improved design in order to reduce air leakage

                      ENVELOPE INSULATION IMPROVEMENT
 E3.1                                  Upgrade insulation of flat roofs externally

 E3.2                                            Upgrade attic insulation

 E3.3                               Add insulation to exterior walls by filling cavities

 E3.4                                   Add insulation to exterior wall externally

 E3.5                                  Add insulation to basement wall externally

 E3.6                             Upgrade insulation of ground floor above crawl space

 E3.7                              Locate and minimize the effect of thermal bridges

 E3.8                          Cover, insulate or convert unnecessary windows and doors

 E3.9                              Use double or triple glazing replacement windows

                  OTHER ACTIONS AIMED AT LOAD REDUCTION
E4.1                             Reduce effective height of room

E4.2                              Use appropriate colour exterior

E4.3                          Employ evaporative cooling roof spray

E4.4   Provide means of reducing electrical peak demand through load shedding               Y
E4.5         Replace electrical equipment with Energy Star or low consumption types

E4.6                 Replace lighting equipment with low consumption types

E4.7       Modify lighting switches according to daylight contribution to different areas

E4.8     Introduce daylight / occupation sensors to operate lighting switches               Y
E4.9            Move equipment (copiers, printers, etc.) to non conditioned zones
PLANT
CODE                                                    ECO                                                        BEMS
                                                                                                                   control
                         BEMS AND CONTROLS / MISCELLANEOUS
P1.1                                                    Install BEMS system
P1.2                             Define best location for new electrical and cooling energy meters
P1.3                          Modify controls in order to sequence heating and cooling                               Y
P1.4       Modify control system in order to adjust internal set point values to external climatic conditions        Y
P1.5                       Generate the possibility to adopt variable speed control strategy                         Y
P1.6                                                Use class 1 electrical motors
P1.7                              Reduce power consumption of auxiliary equipment                                   Y/N
                           COOLING EQUIPMENT / FREE COOLING
P2.1    Minimise adverse external influences (direct sunlight, air flow obstructions, etc.) on cooling tower and     Y
                            air cooled condenser (AHU, packaged, split, VRF systems)
P2.2                                  Reduce compressor power or fit a smaller compressor
P2.3                                            Split the load among various chillers
P2.4                         Repipe chillers or compressors in series or parallel to optimise circuiting
P2.5                                 Improve central chiller / refrigeration control                                 Y
P2.6                                  Replace or upgrade cooling equipment and heat pumps
P2.7                            Consider feeding condenser with natural water sources                                Y
P2.8                                          Apply evaporative cooling                                              Y
P2.9                                   Consider using ground water for cooling                                       Y
P2.10               Consider indirect free cooling using the existing cooling tower (free chilling)                  Y
P2.11                 Consider Indirect free cooling using outdoor air-to-water heat exchangers                      Y
P2.12                     Consider the possibility of using waste heat for absorption system                         Y
P2.13        Consider cool storage applications (chilled water, water ice, other phase changing materials)           Y
P2.14                          Consider using condenser rejection heat for air reheating                             Y
               AIR HANDLING / HEAT RECOVERY / AIR DISTRIBUTION
P3.1                                      Reduce motor size (fan power) when oversized
P3.2                                              Relocate motor out of air stream
P3.3                                    Use the best class of fans identified by EUROVENT
P3.4                                                 Use the best class of AHU
P3.5                               Consider applying chemical (dessicant (?)) de-humidification
P3.6                                            Apply variable flow rate fan control
P3.7                                                Consider conversion to VAV


P3.8                  Exhaust (cool) conditioned air over condensers and through cooling towers                       Y
P3.9                                      Introduce exhaust air heat recovery                                         Y
P3.10                              Consider applying demand-controlled ventilation                                    Y
P3.11                        Generate possibility to increase outdoor air flow rate (direct free cooling)
P3.12                                               Replace ducts when leaking
P3.13                            Modify ductwork to reduce pressure losses
P3.14      Install back-draught or positive closure damper in ventilation exhaust system   Y
              WATER HANDLING / WATER DISTRIBUTION
P4.1                                     Use the best class of pumps
P4.2                             Modify pipework to reduce pressure losses
P4.3                          Convert 3-pipe system to 2-pipe or 4-pipe system
P4.4                   Install separate pumping to match zone requirements                 Y
P4.5                             Install variable volume pumping                           Y
                                   TERMINAL UNITS
P5.1                         Consider applying chilled ceilings or chilled beams
P5.2                 Consider introducing re-cool coils in zones with high cooling loads
P5.3                                Increase heat exchanger surface areas
P5.4                                  Consider displacement ventilation
P5.5               Install localised HVAC system (in case of local discomfort)             Y
        SYSTEM REPLACEMENT (IN SPECIFIC LIMITED ZONES)
P6.1                         Consider water loop heat pump systems                         Y
P6.2                         Consider VRF (Variable Refrigerant Flow) systems
O&M
CODE                                                    ECO                                                       BEMS
                                                                                                                  control
                                        FACILITY MANAGEMENT
O1.1                               Generate instructions (“user guide”) targeted to the occupants
O1.2                                             Hire or appoint an energy manager
O1.3                               Train building operators in energy – efficient O&M activities
O1.4                         Introduce an energy – efficient objective as a clause in each O&M contract
O1.5    Introduce benchmarks, metering and tracking as a clause in each O&M contract, with indication of values in graphs
                                                           and tables
O1.6    Update documentation on system / building and O&M procedures to maintain continuity and reduce troubleshooting
                                                              costs
O1.7                      Check if O&M staff are equipped with state – of – the – art diagnostic tools

                                       GENERAL HVAC SYSTEM
O2.1    Use an energy accounting system to locate savings opportunities and to positively identify savings made     Y
                                               through improvements

                                       Shut off A/C equipment when not needed                                        Y
O2.2
O2.3                                     Shut off auxiliaries when not required                                     Y/N
O2.4                                   Maintain proper system control set points                                     Y
O2.5                         Adjust internal set point values to external climatic conditions                        Y
O2.6                                        Implement pre-occupancy cycle                                            Y
O2.7                                         Sequence heating and cooling                                            Y
O2.8                                     Adopt variable speed control strategy                                       Y
                                          COOLING EQUIPMENT
O3.1                                    Shut chiller plant off when not required                                     Y
O3.2                                      Sequence operation of multiple units                                       Y
O3.3                                    Operate chillers or compressors in series or parallel
O3.4                                Track and optimize chillers operation schedule                                   Y
O3.5                  Maintain proper starting frequency and running time of (reversible) chillers                   Y
O3.6                                      Improve part load operation control                                        Y
O3.7                          Maintain proper evaporating and condensing temperatures                                Y
O3.8                           Raise chilled water temperature and suction gas pressure                              Y
O3.9                              Lower condensing water temperature and pressures                                   Y
O3.10                       Check sensor functioning and placement for (reversible) chillers                         Y
O3.11                              Maintain efficient defrosting (reversible chillers)                               Y
O3.12                                 Maintain proper heat source/sink flow rates                                    Y
O3.13                        Maintain functioning of (reversible) chiller expansion device                           Y
O3.14                                  Check (reversible) chiller stand-by losses                                    Y
O3.15                                      Maintain full charge of refrigerant                                      Y/N
O3.16                      Clean finned tube evaporator / condenser air side and straighten damaged fins
O3.17                                            Clean condenser tubes periodically
O3.18                                       Repair or upgrade insulation on chiller
O3.19                      Clean and maintain cooling tower circuits and heat exchanger surfaces
O3.20               Apply indirect free cooling using the existing cooling tower (free chilling)                      Y
           FLUID (AIR AND WATER) HANDLING AND DISTRIBUTION
O4.1           Consider modifying the supply air temperature (all–air and air–and–water systems)                      Y
O4.2                          Perform night time overventilation where appropriate                                    Y
O4.3                                Shut off coil circulators when not required                                       Y
O4.4                                               Replace mixing dampers
O4.5                                      Adjust fan belts (AHU, packaged systems)
O4.6                                    Eliminate air leaks (AHU, packaged systems)
O4.7                            Increase outdoor air flow rate (direct free cooling)                                 Y
O4.8                                    Adjust/balance ventilation system                                            Y
O4.9                                   Reduce air flow rate to actual needs                                         Y/N
O4.10                           Check maintenance protocol in order to reduce pressure losses
O4.11                                             Reduce air leakage in ducts
O4.12                                                  Clean fan blades
O4.13                                                   Maintain drives
O4.14                                          Clean or replace filters regularly


O4.15                                   Repair/upgrade duct, pipe and tank insulation
O4.16   Consider the possibility to increase the water outlet – inlet temperature difference and reduce the flow rate for
                                                   pumping power reduction
O4.17                                  Balance hydronic distribution system                                             Y
O4.18                              Bleed air from hydronic distribution system                                        Y
O4.19                            Switch off circulation pumps when not required                                       Y
O4.20                             Maintain proper water level in expansion tank                                       Y
O4.21                                                 Repair water leaks
O4.22                                Reduce water flow rates to actual needs                                        Y/N

Contenu connexe

Tendances

UNDP_Energy Audits_2015
UNDP_Energy Audits_2015UNDP_Energy Audits_2015
UNDP_Energy Audits_2015UNDPhr
 
Introduction to energy audit part 2
Introduction to energy audit part 2Introduction to energy audit part 2
Introduction to energy audit part 2ZAINI ABDUL WAHAB
 
Energy Audit of a Food Industry
Energy Audit of a Food IndustryEnergy Audit of a Food Industry
Energy Audit of a Food IndustryIJMER
 
Energy audit report presentation
Energy audit report presentationEnergy audit report presentation
Energy audit report presentationKyambadde Francisco
 
2: Introduction to Energy Audit Methods in Water Supply
2: Introduction to Energy Audit Methods in Water Supply2: Introduction to Energy Audit Methods in Water Supply
2: Introduction to Energy Audit Methods in Water SupplyAlliance To Save Energy
 
Ambicales Energy Audit
Ambicales Energy AuditAmbicales Energy Audit
Ambicales Energy AuditAmbicales
 
Energy Audit
Energy AuditEnergy Audit
Energy Auditmmmm
 
Energy audit by Qazi Arsalan Hamid-Dy Manager Technical KESC
Energy audit by Qazi Arsalan Hamid-Dy Manager Technical KESCEnergy audit by Qazi Arsalan Hamid-Dy Manager Technical KESC
Energy audit by Qazi Arsalan Hamid-Dy Manager Technical KESCQazi Arsalan Hamid
 
Energy Management Audit
Energy Management AuditEnergy Management Audit
Energy Management Auditalnaidu305
 
Energy Audit in WASAs of Punjab
Energy Audit in WASAs of Punjab Energy Audit in WASAs of Punjab
Energy Audit in WASAs of Punjab Abid Hussainy
 
Mandatory Energy Audit for Designated Consumers (BEE)
Mandatory Energy Audit for Designated Consumers (BEE)Mandatory Energy Audit for Designated Consumers (BEE)
Mandatory Energy Audit for Designated Consumers (BEE)ravindradatar
 
Energy Audit Basics and Principles
Energy Audit Basics and Principles Energy Audit Basics and Principles
Energy Audit Basics and Principles RCREEE
 

Tendances (18)

UNDP_Energy Audits_2015
UNDP_Energy Audits_2015UNDP_Energy Audits_2015
UNDP_Energy Audits_2015
 
Introduction to energy audit part 2
Introduction to energy audit part 2Introduction to energy audit part 2
Introduction to energy audit part 2
 
Energy Audit of a Food Industry
Energy Audit of a Food IndustryEnergy Audit of a Food Industry
Energy Audit of a Food Industry
 
Energy audit ppt
Energy audit  pptEnergy audit  ppt
Energy audit ppt
 
Energy audit report presentation
Energy audit report presentationEnergy audit report presentation
Energy audit report presentation
 
2: Introduction to Energy Audit Methods in Water Supply
2: Introduction to Energy Audit Methods in Water Supply2: Introduction to Energy Audit Methods in Water Supply
2: Introduction to Energy Audit Methods in Water Supply
 
Ambicales Energy Audit
Ambicales Energy AuditAmbicales Energy Audit
Ambicales Energy Audit
 
Reasdfg
ReasdfgReasdfg
Reasdfg
 
energy audit
energy auditenergy audit
energy audit
 
Energy Audit
Energy AuditEnergy Audit
Energy Audit
 
Energy management and audit
Energy management and auditEnergy management and audit
Energy management and audit
 
Energy audit by Qazi Arsalan Hamid-Dy Manager Technical KESC
Energy audit by Qazi Arsalan Hamid-Dy Manager Technical KESCEnergy audit by Qazi Arsalan Hamid-Dy Manager Technical KESC
Energy audit by Qazi Arsalan Hamid-Dy Manager Technical KESC
 
Energy Management Audit
Energy Management AuditEnergy Management Audit
Energy Management Audit
 
Energy Audit in WASAs of Punjab
Energy Audit in WASAs of Punjab Energy Audit in WASAs of Punjab
Energy Audit in WASAs of Punjab
 
Mandatory Energy Audit for Designated Consumers (BEE)
Mandatory Energy Audit for Designated Consumers (BEE)Mandatory Energy Audit for Designated Consumers (BEE)
Mandatory Energy Audit for Designated Consumers (BEE)
 
Energy Audit Basics and Principles
Energy Audit Basics and Principles Energy Audit Basics and Principles
Energy Audit Basics and Principles
 
Energy audit
Energy auditEnergy audit
Energy audit
 
Energy Manager Training Website
Energy Manager Training WebsiteEnergy Manager Training Website
Energy Manager Training Website
 

En vedette

Personal best simplified knsv
Personal best simplified knsvPersonal best simplified knsv
Personal best simplified knsvThai Le
 
Auditac tg3 system recognition for field visit
Auditac tg3 system recognition for field visitAuditac tg3 system recognition for field visit
Auditac tg3 system recognition for field visitRoyal Mail
 
Audit ac tech guide for owner manager of acs vol 1 are you sure you are not p...
Audit ac tech guide for owner manager of acs vol 1 are you sure you are not p...Audit ac tech guide for owner manager of acs vol 1 are you sure you are not p...
Audit ac tech guide for owner manager of acs vol 1 are you sure you are not p...Royal Mail
 
Retailer x distribution centre walkround energy survey april 2010
Retailer x distribution centre walkround energy survey april 2010Retailer x distribution centre walkround energy survey april 2010
Retailer x distribution centre walkround energy survey april 2010Royal Mail
 
Green bridge phil evans energy saving booklet 2012
Green bridge phil evans energy saving booklet 2012Green bridge phil evans energy saving booklet 2012
Green bridge phil evans energy saving booklet 2012Royal Mail
 
Auditac tg7 benchmarking guide for ac based on elec bills
Auditac  tg7 benchmarking guide for ac based on elec billsAuditac  tg7 benchmarking guide for ac based on elec bills
Auditac tg7 benchmarking guide for ac based on elec billsRoyal Mail
 
Phil Evans CV April 2012
Phil Evans CV April 2012Phil Evans CV April 2012
Phil Evans CV April 2012Royal Mail
 
Tg 2 auditing of acs and epbd
Tg 2 auditing of acs and epbdTg 2 auditing of acs and epbd
Tg 2 auditing of acs and epbdRoyal Mail
 
Auditac tg 5 energy conservation opportunities
Auditac  tg 5 energy conservation opportunitiesAuditac  tg 5 energy conservation opportunities
Auditac tg 5 energy conservation opportunitiesRoyal Mail
 

En vedette (9)

Personal best simplified knsv
Personal best simplified knsvPersonal best simplified knsv
Personal best simplified knsv
 
Auditac tg3 system recognition for field visit
Auditac tg3 system recognition for field visitAuditac tg3 system recognition for field visit
Auditac tg3 system recognition for field visit
 
Audit ac tech guide for owner manager of acs vol 1 are you sure you are not p...
Audit ac tech guide for owner manager of acs vol 1 are you sure you are not p...Audit ac tech guide for owner manager of acs vol 1 are you sure you are not p...
Audit ac tech guide for owner manager of acs vol 1 are you sure you are not p...
 
Retailer x distribution centre walkround energy survey april 2010
Retailer x distribution centre walkround energy survey april 2010Retailer x distribution centre walkround energy survey april 2010
Retailer x distribution centre walkround energy survey april 2010
 
Green bridge phil evans energy saving booklet 2012
Green bridge phil evans energy saving booklet 2012Green bridge phil evans energy saving booklet 2012
Green bridge phil evans energy saving booklet 2012
 
Auditac tg7 benchmarking guide for ac based on elec bills
Auditac  tg7 benchmarking guide for ac based on elec billsAuditac  tg7 benchmarking guide for ac based on elec bills
Auditac tg7 benchmarking guide for ac based on elec bills
 
Phil Evans CV April 2012
Phil Evans CV April 2012Phil Evans CV April 2012
Phil Evans CV April 2012
 
Tg 2 auditing of acs and epbd
Tg 2 auditing of acs and epbdTg 2 auditing of acs and epbd
Tg 2 auditing of acs and epbd
 
Auditac tg 5 energy conservation opportunities
Auditac  tg 5 energy conservation opportunitiesAuditac  tg 5 energy conservation opportunities
Auditac tg 5 energy conservation opportunities
 

Similaire à Technical guide for air conditioning system audits

Auditac tg 9 how to integrate eneff and aci with full benefit in the structur...
Auditac tg 9 how to integrate eneff and aci with full benefit in the structur...Auditac tg 9 how to integrate eneff and aci with full benefit in the structur...
Auditac tg 9 how to integrate eneff and aci with full benefit in the structur...Royal Mail
 
17_ACaseStudy.pdf
17_ACaseStudy.pdf17_ACaseStudy.pdf
17_ACaseStudy.pdfpurushukpc1
 
Case Study: Energy Audit
Case Study: Energy AuditCase Study: Energy Audit
Case Study: Energy AuditIRJET Journal
 
Energy planing and auditing
Energy planing and auditingEnergy planing and auditing
Energy planing and auditingprabinshrestha77
 
Energy management &amp & audit
Energy management &amp & auditEnergy management &amp & audit
Energy management &amp & auditSagar Joshi
 
Green Building Awareness HVAC
Green Building Awareness HVAC Green Building Awareness HVAC
Green Building Awareness HVAC AKSHAY SHARMA
 
IRJET - Energy Audit and Electrical Power Consumption of ADIT College
IRJET - Energy Audit and Electrical Power Consumption of ADIT CollegeIRJET - Energy Audit and Electrical Power Consumption of ADIT College
IRJET - Energy Audit and Electrical Power Consumption of ADIT CollegeIRJET Journal
 
Energy management and audit
Energy management and auditEnergy management and audit
Energy management and auditEr Chaitu Lodha
 
Industrial energy auditing and reporting
Industrial energy auditing and reportingIndustrial energy auditing and reporting
Industrial energy auditing and reportingVignesh Sekar
 
Retrofitting Buildings to Achieve Energy Efficiency
Retrofitting Buildings to Achieve Energy EfficiencyRetrofitting Buildings to Achieve Energy Efficiency
Retrofitting Buildings to Achieve Energy EfficiencyDivya Kothari
 
Industrial energy efficiency techniques and energy management (1)
Industrial energy efficiency techniques and energy management (1)Industrial energy efficiency techniques and energy management (1)
Industrial energy efficiency techniques and energy management (1)Anish Maman
 
Heat Load Calculation and Coordination of Multispecialty Hospital Using Revit...
Heat Load Calculation and Coordination of Multispecialty Hospital Using Revit...Heat Load Calculation and Coordination of Multispecialty Hospital Using Revit...
Heat Load Calculation and Coordination of Multispecialty Hospital Using Revit...IRJET Journal
 
Energy management & audit
Energy management & auditEnergy management & audit
Energy management & auditSalman Jailani
 
Energy management & audit
Energy management & auditEnergy management & audit
Energy management & auditPINAKI ROY
 
Papai projet
Papai projetPapai projet
Papai projetpapai13
 
Optimization of Organic Rankine Cycle’s thermal efficiency based on Grey rela...
Optimization of Organic Rankine Cycle’s thermal efficiency based on Grey rela...Optimization of Organic Rankine Cycle’s thermal efficiency based on Grey rela...
Optimization of Organic Rankine Cycle’s thermal efficiency based on Grey rela...IRJET Journal
 
Energy Auditing.pptx
Energy Auditing.pptxEnergy Auditing.pptx
Energy Auditing.pptxMoaz27
 

Similaire à Technical guide for air conditioning system audits (20)

Auditac tg 9 how to integrate eneff and aci with full benefit in the structur...
Auditac tg 9 how to integrate eneff and aci with full benefit in the structur...Auditac tg 9 how to integrate eneff and aci with full benefit in the structur...
Auditac tg 9 how to integrate eneff and aci with full benefit in the structur...
 
17_ACaseStudy.pdf
17_ACaseStudy.pdf17_ACaseStudy.pdf
17_ACaseStudy.pdf
 
Energy audit
Energy auditEnergy audit
Energy audit
 
Case Study: Energy Audit
Case Study: Energy AuditCase Study: Energy Audit
Case Study: Energy Audit
 
Energy planing and auditing
Energy planing and auditingEnergy planing and auditing
Energy planing and auditing
 
Energy management &amp & audit
Energy management &amp & auditEnergy management &amp & audit
Energy management &amp & audit
 
Green Building Awareness HVAC
Green Building Awareness HVAC Green Building Awareness HVAC
Green Building Awareness HVAC
 
IRJET - Energy Audit and Electrical Power Consumption of ADIT College
IRJET - Energy Audit and Electrical Power Consumption of ADIT CollegeIRJET - Energy Audit and Electrical Power Consumption of ADIT College
IRJET - Energy Audit and Electrical Power Consumption of ADIT College
 
Energy management and audit
Energy management and auditEnergy management and audit
Energy management and audit
 
UNIT 1.pptx
UNIT 1.pptxUNIT 1.pptx
UNIT 1.pptx
 
Industrial energy auditing and reporting
Industrial energy auditing and reportingIndustrial energy auditing and reporting
Industrial energy auditing and reporting
 
Retrofitting Buildings to Achieve Energy Efficiency
Retrofitting Buildings to Achieve Energy EfficiencyRetrofitting Buildings to Achieve Energy Efficiency
Retrofitting Buildings to Achieve Energy Efficiency
 
Industrial energy efficiency techniques and energy management (1)
Industrial energy efficiency techniques and energy management (1)Industrial energy efficiency techniques and energy management (1)
Industrial energy efficiency techniques and energy management (1)
 
Energy audit
Energy auditEnergy audit
Energy audit
 
Heat Load Calculation and Coordination of Multispecialty Hospital Using Revit...
Heat Load Calculation and Coordination of Multispecialty Hospital Using Revit...Heat Load Calculation and Coordination of Multispecialty Hospital Using Revit...
Heat Load Calculation and Coordination of Multispecialty Hospital Using Revit...
 
Energy management & audit
Energy management & auditEnergy management & audit
Energy management & audit
 
Energy management & audit
Energy management & auditEnergy management & audit
Energy management & audit
 
Papai projet
Papai projetPapai projet
Papai projet
 
Optimization of Organic Rankine Cycle’s thermal efficiency based on Grey rela...
Optimization of Organic Rankine Cycle’s thermal efficiency based on Grey rela...Optimization of Organic Rankine Cycle’s thermal efficiency based on Grey rela...
Optimization of Organic Rankine Cycle’s thermal efficiency based on Grey rela...
 
Energy Auditing.pptx
Energy Auditing.pptxEnergy Auditing.pptx
Energy Auditing.pptx
 

Plus de Royal Mail

Sample energy survey overview
Sample energy survey overviewSample energy survey overview
Sample energy survey overviewRoyal Mail
 
Managing energy consumption to improve forecasting checklist
Managing energy consumption to improve forecasting checklistManaging energy consumption to improve forecasting checklist
Managing energy consumption to improve forecasting checklistRoyal Mail
 
Comfortable energy reduction checklist
Comfortable energy reduction checklistComfortable energy reduction checklist
Comfortable energy reduction checklistRoyal Mail
 
Best practice checklist
Best practice checklistBest practice checklist
Best practice checklistRoyal Mail
 
Carbon footprinting checklist
Carbon footprinting checklistCarbon footprinting checklist
Carbon footprinting checklistRoyal Mail
 
Marcus evans workshop presentation
Marcus evans workshop presentationMarcus evans workshop presentation
Marcus evans workshop presentationRoyal Mail
 
Luxury flats energy survey report
Luxury flats energy survey reportLuxury flats energy survey report
Luxury flats energy survey reportRoyal Mail
 
Purpose pyramid sept 2011
Purpose pyramid sept 2011Purpose pyramid sept 2011
Purpose pyramid sept 2011Royal Mail
 
Sample building energy performance proposal jan 2012
Sample building energy performance proposal jan 2012Sample building energy performance proposal jan 2012
Sample building energy performance proposal jan 2012Royal Mail
 
Phil Evans CV January 2012
Phil Evans CV January 2012Phil Evans CV January 2012
Phil Evans CV January 2012Royal Mail
 
Auditac tg4 prelim audit methodology for ac
Auditac tg4 prelim audit methodology for acAuditac tg4 prelim audit methodology for ac
Auditac tg4 prelim audit methodology for acRoyal Mail
 
Auditac tg 5 energy conservation opportunities
Auditac  tg 5 energy conservation opportunitiesAuditac  tg 5 energy conservation opportunities
Auditac tg 5 energy conservation opportunitiesRoyal Mail
 
Auditac tg 6 how to benefit from eurovent cert database and retrieve past eq...
Auditac  tg 6 how to benefit from eurovent cert database and retrieve past eq...Auditac  tg 6 how to benefit from eurovent cert database and retrieve past eq...
Auditac tg 6 how to benefit from eurovent cert database and retrieve past eq...Royal Mail
 
Auditac tg8 how manufacturers could help auditors
Auditac tg8 how manufacturers could help auditorsAuditac tg8 how manufacturers could help auditors
Auditac tg8 how manufacturers could help auditorsRoyal Mail
 
Auditac tg10 case studies
Auditac  tg10 case studiesAuditac  tg10 case studies
Auditac tg10 case studiesRoyal Mail
 
Auditac carbon and cooling in uk office environments dunn knight
Auditac carbon and cooling in uk office environments dunn knightAuditac carbon and cooling in uk office environments dunn knight
Auditac carbon and cooling in uk office environments dunn knightRoyal Mail
 
Sample energy saving proposal
Sample energy saving proposalSample energy saving proposal
Sample energy saving proposalRoyal Mail
 
Retailer x distribution centre walkround energy survey april 2010
Retailer x distribution centre walkround energy survey april 2010Retailer x distribution centre walkround energy survey april 2010
Retailer x distribution centre walkround energy survey april 2010Royal Mail
 

Plus de Royal Mail (18)

Sample energy survey overview
Sample energy survey overviewSample energy survey overview
Sample energy survey overview
 
Managing energy consumption to improve forecasting checklist
Managing energy consumption to improve forecasting checklistManaging energy consumption to improve forecasting checklist
Managing energy consumption to improve forecasting checklist
 
Comfortable energy reduction checklist
Comfortable energy reduction checklistComfortable energy reduction checklist
Comfortable energy reduction checklist
 
Best practice checklist
Best practice checklistBest practice checklist
Best practice checklist
 
Carbon footprinting checklist
Carbon footprinting checklistCarbon footprinting checklist
Carbon footprinting checklist
 
Marcus evans workshop presentation
Marcus evans workshop presentationMarcus evans workshop presentation
Marcus evans workshop presentation
 
Luxury flats energy survey report
Luxury flats energy survey reportLuxury flats energy survey report
Luxury flats energy survey report
 
Purpose pyramid sept 2011
Purpose pyramid sept 2011Purpose pyramid sept 2011
Purpose pyramid sept 2011
 
Sample building energy performance proposal jan 2012
Sample building energy performance proposal jan 2012Sample building energy performance proposal jan 2012
Sample building energy performance proposal jan 2012
 
Phil Evans CV January 2012
Phil Evans CV January 2012Phil Evans CV January 2012
Phil Evans CV January 2012
 
Auditac tg4 prelim audit methodology for ac
Auditac tg4 prelim audit methodology for acAuditac tg4 prelim audit methodology for ac
Auditac tg4 prelim audit methodology for ac
 
Auditac tg 5 energy conservation opportunities
Auditac  tg 5 energy conservation opportunitiesAuditac  tg 5 energy conservation opportunities
Auditac tg 5 energy conservation opportunities
 
Auditac tg 6 how to benefit from eurovent cert database and retrieve past eq...
Auditac  tg 6 how to benefit from eurovent cert database and retrieve past eq...Auditac  tg 6 how to benefit from eurovent cert database and retrieve past eq...
Auditac tg 6 how to benefit from eurovent cert database and retrieve past eq...
 
Auditac tg8 how manufacturers could help auditors
Auditac tg8 how manufacturers could help auditorsAuditac tg8 how manufacturers could help auditors
Auditac tg8 how manufacturers could help auditors
 
Auditac tg10 case studies
Auditac  tg10 case studiesAuditac  tg10 case studies
Auditac tg10 case studies
 
Auditac carbon and cooling in uk office environments dunn knight
Auditac carbon and cooling in uk office environments dunn knightAuditac carbon and cooling in uk office environments dunn knight
Auditac carbon and cooling in uk office environments dunn knight
 
Sample energy saving proposal
Sample energy saving proposalSample energy saving proposal
Sample energy saving proposal
 
Retailer x distribution centre walkround energy survey april 2010
Retailer x distribution centre walkround energy survey april 2010Retailer x distribution centre walkround energy survey april 2010
Retailer x distribution centre walkround energy survey april 2010
 

Dernier

How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.Curtis Poe
 
Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 3652toLead Limited
 
How to write a Business Continuity Plan
How to write a Business Continuity PlanHow to write a Business Continuity Plan
How to write a Business Continuity PlanDatabarracks
 
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptxThe Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptxLoriGlavin3
 
Generative AI for Technical Writer or Information Developers
Generative AI for Technical Writer or Information DevelopersGenerative AI for Technical Writer or Information Developers
Generative AI for Technical Writer or Information DevelopersRaghuram Pandurangan
 
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024BookNet Canada
 
Rise of the Machines: Known As Drones...
Rise of the Machines: Known As Drones...Rise of the Machines: Known As Drones...
Rise of the Machines: Known As Drones...Rick Flair
 
"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr BaganFwdays
 
From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .Alan Dix
 
Dev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebDev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebUiPathCommunity
 
WordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your BrandWordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your Brandgvaughan
 
Sample pptx for embedding into website for demo
Sample pptx for embedding into website for demoSample pptx for embedding into website for demo
Sample pptx for embedding into website for demoHarshalMandlekar2
 
TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024Lonnie McRorey
 
A Journey Into the Emotions of Software Developers
A Journey Into the Emotions of Software DevelopersA Journey Into the Emotions of Software Developers
A Journey Into the Emotions of Software DevelopersNicole Novielli
 
Time Series Foundation Models - current state and future directions
Time Series Foundation Models - current state and future directionsTime Series Foundation Models - current state and future directions
Time Series Foundation Models - current state and future directionsNathaniel Shimoni
 
SALESFORCE EDUCATION CLOUD | FEXLE SERVICES
SALESFORCE EDUCATION CLOUD | FEXLE SERVICESSALESFORCE EDUCATION CLOUD | FEXLE SERVICES
SALESFORCE EDUCATION CLOUD | FEXLE SERVICESmohitsingh558521
 
DevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsDevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsSergiu Bodiu
 
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptxThe Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptxLoriGlavin3
 
Moving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdfMoving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdfLoriGlavin3
 
"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii SoldatenkoFwdays
 

Dernier (20)

How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.
 
Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365Ensuring Technical Readiness For Copilot in Microsoft 365
Ensuring Technical Readiness For Copilot in Microsoft 365
 
How to write a Business Continuity Plan
How to write a Business Continuity PlanHow to write a Business Continuity Plan
How to write a Business Continuity Plan
 
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptxThe Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
 
Generative AI for Technical Writer or Information Developers
Generative AI for Technical Writer or Information DevelopersGenerative AI for Technical Writer or Information Developers
Generative AI for Technical Writer or Information Developers
 
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
 
Rise of the Machines: Known As Drones...
Rise of the Machines: Known As Drones...Rise of the Machines: Known As Drones...
Rise of the Machines: Known As Drones...
 
"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan
 
From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .
 
Dev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebDev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio Web
 
WordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your BrandWordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your Brand
 
Sample pptx for embedding into website for demo
Sample pptx for embedding into website for demoSample pptx for embedding into website for demo
Sample pptx for embedding into website for demo
 
TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024
 
A Journey Into the Emotions of Software Developers
A Journey Into the Emotions of Software DevelopersA Journey Into the Emotions of Software Developers
A Journey Into the Emotions of Software Developers
 
Time Series Foundation Models - current state and future directions
Time Series Foundation Models - current state and future directionsTime Series Foundation Models - current state and future directions
Time Series Foundation Models - current state and future directions
 
SALESFORCE EDUCATION CLOUD | FEXLE SERVICES
SALESFORCE EDUCATION CLOUD | FEXLE SERVICESSALESFORCE EDUCATION CLOUD | FEXLE SERVICES
SALESFORCE EDUCATION CLOUD | FEXLE SERVICES
 
DevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsDevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platforms
 
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptxThe Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
 
Moving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdfMoving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdf
 
"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko
 

Technical guide for air conditioning system audits

  • 1. Technical guides for owner/manager of an air conditioning system : volume 4 AN AUDITAC PROPOSED PRELIMINARY AUDIT METHODOLOGY FOR AIR- CONDITIONING FACILITIES
  • 2. Team France (Project coordinator) Armines - Mines de Paris Austria Slovenia Austrian Energy Agency University of Ljubljana Belgium UK Université de Liège Association of Building Engineers Italy BRE Politecnico di Torino (Building Research Establishment Ltd) Portugal University of Porto Welsh School of Architecture Eurovent-Certification Authors of this volume Jerome ADNOT (Armines, France) Daniela BORY (Armines, France) Vincenc BUTALA (University of Ljubljana) Ian KNIGHT (Welsh School of Architecture, UK) Marco MASOERO (Politecnico di Torino) Simon MUHIC (University of Ljubljana) Chiara SILVI (Politecnico di Torino) The sole responsibility for the content of this publication lies with the authors. It does not represent the opinion of the European Communities. The European Commission is not responsible for any use that may be made of the information contained therein.
  • 3. AN AUDITAC PROPOSED PRELIMINARY AUDIT METHODOLOGY FOR AIR-CONDITIONING FACILITIES In this brochure we present a typical procedure for a preliminary audit for air-conditioning facilities. Preliminary audit is a first step of the audit procedure where the auditor has a first approach with the plant. This procedure is very important for the comprehension of the design of the plant and its use. The auditor will be able, at the end of the procedure, to identify preliminary energy saving opportunities. Some easy energy saving actions can be made operational immediately after the preliminary audit, whereas other potential actions may require normally a more detailed analysis, in order to assess their effectiveness and their economic performance. The actions requiring a deeper analysis of the system are best performed during the subsequent detailed audit. The preliminary audit structure In a preliminary audit procedure one detects the errors in the AC systems through data gathering, visual detection and with measurements. Preliminary audit involves an interview of the site operating staff, a review of facility utility bills and other operating data, and a walk-through of the facility (to become familiar with the building operation and to identify obvious areas of energy waste or inefficiency). Typically, only major problem areas will be discovered during this type of audit. This level of detail, while not sufficient to take all improvement decisions, is adequate to prioritize energy efficiency projects and determine the need for a more detailed audit. Preliminary audit activities should include the following sequential steps: • Identify the air-conditioning system type(s) in use in the building • Evaluate the conditions of use and the operational state of the system • Find out and describe the possible impact of improvements to this system • Write up a preliminary audit report The preliminary audit is less expensive than the detailed one, but is nonetheless an important study that can yield a very useful estimate of savings potential and a list of low-cost savings opportunities, through improvements in operational and maintenance practices. The preliminary audit information will be used to underpin the more detailed audit, if the energy saving potentials appear to warrant further auditing activity. The first step of the preliminary audit process should be the collection of information. The information may be collected on the structural and mechanical components that affect building energy use and the operational characteristics of the facility. Much of this information can be collected prior to the site visit. Evaluating energy use and systems
  • 4. before going on-site helps identify potential savings and makes best use of time spent on-site. The preliminary audit consists of three distinct steps: Step 1: preliminary data collection and evaluation, Step 2: site visit, Step 3: analysis and reporting. Step1: Preliminary Data Collection and Evaluation A pre-site review of building systems and their operation should generate a list of specific questions and issues to be discussed during the actual visit to the facility. This preparation will help ensure the most effective use of on-site time and minimize disruptions to building personnel. A thorough pre-site review will also reduce the time required to complete the on-site portion of the audit. The first task is to collect and review two years worth of utility energy data for electricity. The air-conditioning system consumption data should be provided if the system energy is measured separately. This information is used to analyse operational characteristics, calculate some energy benchmarks for comparison to averages, estimate savings potential, set an energy reduction target, and establish a baseline to monitor the effectiveness of implemented measures. The building manager should provide occupancy schedules, operation and maintenance practices, and plans that may have an impact on energy consumption. This kind of information can help identify times when building systems such as lighting, recirculating pumps or outside air ventilation can be turned off and temperatures set back. The building manager should ideally also provide documentation for all the above information. If the data are not available, or they don't correspond to reality, then the first action should be to help to collect the data. Analysing Energy Data If the A/C system energy consumption is available separately, then a Cooling Energy Index (CEI) could be calculated to compare energy consumption to similar building types or to track consumption from year to year in the same building. The CEI consist of calculated ratios based on the annual consumption and the area (gross or conditioned square meters) of the building. CEI is a good indicator of the relative potential for energy savings. A comparatively low CEI indicates less potential for large energy savings. By tracking the CEI using a rolling 12-month block, building performance can be evaluated based on increasing or decreasing energy use trends. This method requires a minimum of two years of energy consumption data to establish the trend line and values including weather correction. Caution has to be used in benchmarking in order to compare comparable values between different buildings. The best benchmark method would take into account different parameters (weather, sector, air control factors etc.). Actually, there are few air- conditioning benchmark references and often general benchmarks (all thermal energy
  • 5. use, or all electricity use) are most commonly used and available. In that case it is more difficult to track air conditioning specifically. However when metering is periodic (monthly, e.g.) it becomes possible to estimate the additional electricity use related with hot weather. Looking at Loads for cooling Cooling loads include occupants, lighting, office equipment, appliances, solar gains and specific processes. High loads are in general easy to detect and the energy management efforts should be focused in these areas. High loads may reveal opportunities to reduce consumption by making improvements to the air conditioning equipment, temperature controls, the building envelope, or to other systems which are affected by operation. After utility use has been allocated, the auditor should prepare a list of the major energy-using systems in the building and estimate the time when each system is in operation throughout the year. The list will help identify how each system uses energy and potential savings. Building systems can then be targeted for more detailed data collection. One of the easiest ways to evaluate energy data is to watch for the trends in use, demand, or costs over time. Either graphing two or more years of monthly data on one graph or graphing only the annual totals for several years can help. Building Profile Obtaining mechanical, architectural, and electrical drawings and specifications for the original building as well as for any additions or remodelling work that may have been done is the first step to creating a building profile. Any past energy audits or studies should be reviewed. The auditor can use this information to develop a building profile narrative that includes age, occupancy, description, and existing conditions of architectural, mechanical, and electrical systems. The profile should note the major energy-consuming equipment or systems and identify systems and components that are inherently inefficient. A site sketch of the building(s) surveyed should also be made. The sketch should show the relative location and outline of each building; the name of each building; year of construction of each building and additions; dimensions of each building and additions; location and identification numbers of utility meters; central plant; and orientation of the complex. While completing the pre-site visit review, the auditor should note areas of particular interest and write down any questions about the lighting systems and controls, HVAC zone controls, or setback operation. Other questions may regard equipment maintenance practices. At this point the auditor should discuss preliminary observations with the building manager or operator. The building manager or operator should be asked about their interest in particular conservation projects or planned changes to the building or its systems. The audit should be scheduled when key systems are in operation and when the building operator can take part. Some AUDITAC tools (Case Study database, AC-Cost spreadsheet and Customer Advising Tool) will become available from our website (http://www.energyagency.at/(en)/projekte/auditac.htm) to support this activity.
  • 6. Step2: The Site Visit The site visit will be spent inspecting actual systems and answering specific questions from the preliminary review. The amount of time required will vary depending on the completeness of the preliminary information collected, the complexity of the building and systems, and the need for testing equipment. Having several copies of a simple floor plan of the building will be useful for notes during the site visit. A separate copy should be made for noting information on locations of HVAC equipment and controls, heating zones, light levels, and other energy-related systems. If architectural drawings are not available, emergency fire exit plans are usually posted on each floor; these plans are a good alternative for a basic floor plan. Prior to touring the facility, the auditor and building manager should review the auditor's energy consumption profiles. Step3: Analysis and Reporting Post-site work is a necessary and important step to ensure the preliminary audit will be useful. The auditor needs to evaluate the information gathered during the site visit, research possible Energy Conservation Opportunities (ECO’s), organize the audit into a comprehensive report, and make recommendations on improvements. The report from the preliminary audit, with possible ECO’s, should be used as the basic input for subsequent more detailed audits. This brochure includes an extensive list of ECOs for air-conditioned buildings covering three major aspects: • ENVELOPE AND LOADS • PLANT • OPERATION AND MAINTENANCE (O&M) The “O&M” ECO’s include all actions that may in general be implemented in a building, HVAC system, or facility management scheme. The costs involved in implementing “O&M” ECO’s are generally limited if not negligible, application is therefore normally recommended, provided their technical feasibility is assessed. “Plant” ECO’s, on the contrary, can involve radical intervention on the HVAC system. Their applicability should therefore be carefully assessed both from the technical and economical standpoint. For this purpose, a review of the main cost-benefit evaluation methods is presented in this report. In the “Envelope and Loads” categories, ECO’s aimed at reducing the building cooling load are listed. These ECO’s may be either of the operational type, or may involve renovation work on the building envelope. Therefore, the evaluation methods may be similar to those normally applied either to category “O&M” or “Plant”.
  • 7. Several of the ECO’s of each of the above categories may be effectively implemented with the aid of a Building Energy Management System (BEMS). Use of BEMS is highlighted in a specific column of the ECO list. Energy conservation opportunities (ECO) for air-conditioned buildings ENVELOPE AND LOADS CODE ECO BEMS control SOLAR GAIN REDUCTION / DAYLIGHT CONTROL IMPROVEMENT E1.1 Install window film or tinted glass E1.2 Install shutters, blinds, shades, screens or drapes E1.3 Operate shutters, blinds, shades, screens or drapes Y E1.4 Replace internal blinds with external systems E1.5 Close off balconies to make sunspace/greenhouse E1.6 Modify vegetation to save energy E1.7 Maintain windows and doors VENTILATION / AIR MOVEMENT / AIR LEAKAGE IMPROVEMENT E2.1 Generate possibility to close/open windows and doors to match climate Y/N E2.2 Ensure proper ventilation of attic spaces Y E2.3 Optimise air convection paths in shafts and stairwells E2.4 Correct excessive envelope air leakage E2.5 Roller shutter cases – Insulate and seal air leaks E2.6 Generate possibility of night time cooling through overventilation E2.7 Add automatic door closing system between conditioned and unconditioned spaces E2.8 Replace doors with improved design in order to reduce air leakage ENVELOPE INSULATION IMPROVEMENT E3.1 Upgrade insulation of flat roofs externally E3.2 Upgrade attic insulation E3.3 Add insulation to exterior walls by filling cavities E3.4 Add insulation to exterior wall externally E3.5 Add insulation to basement wall externally E3.6 Upgrade insulation of ground floor above crawl space E3.7 Locate and minimize the effect of thermal bridges E3.8 Cover, insulate or convert unnecessary windows and doors E3.9 Use double or triple glazing replacement windows OTHER ACTIONS AIMED AT LOAD REDUCTION
  • 8. E4.1 Reduce effective height of room E4.2 Use appropriate colour exterior E4.3 Employ evaporative cooling roof spray E4.4 Provide means of reducing electrical peak demand through load shedding Y E4.5 Replace electrical equipment with Energy Star or low consumption types E4.6 Replace lighting equipment with low consumption types E4.7 Modify lighting switches according to daylight contribution to different areas E4.8 Introduce daylight / occupation sensors to operate lighting switches Y E4.9 Move equipment (copiers, printers, etc.) to non conditioned zones
  • 9. PLANT CODE ECO BEMS control BEMS AND CONTROLS / MISCELLANEOUS P1.1 Install BEMS system P1.2 Define best location for new electrical and cooling energy meters P1.3 Modify controls in order to sequence heating and cooling Y P1.4 Modify control system in order to adjust internal set point values to external climatic conditions Y P1.5 Generate the possibility to adopt variable speed control strategy Y P1.6 Use class 1 electrical motors P1.7 Reduce power consumption of auxiliary equipment Y/N COOLING EQUIPMENT / FREE COOLING P2.1 Minimise adverse external influences (direct sunlight, air flow obstructions, etc.) on cooling tower and Y air cooled condenser (AHU, packaged, split, VRF systems) P2.2 Reduce compressor power or fit a smaller compressor P2.3 Split the load among various chillers P2.4 Repipe chillers or compressors in series or parallel to optimise circuiting P2.5 Improve central chiller / refrigeration control Y P2.6 Replace or upgrade cooling equipment and heat pumps P2.7 Consider feeding condenser with natural water sources Y P2.8 Apply evaporative cooling Y P2.9 Consider using ground water for cooling Y P2.10 Consider indirect free cooling using the existing cooling tower (free chilling) Y P2.11 Consider Indirect free cooling using outdoor air-to-water heat exchangers Y P2.12 Consider the possibility of using waste heat for absorption system Y P2.13 Consider cool storage applications (chilled water, water ice, other phase changing materials) Y P2.14 Consider using condenser rejection heat for air reheating Y AIR HANDLING / HEAT RECOVERY / AIR DISTRIBUTION P3.1 Reduce motor size (fan power) when oversized P3.2 Relocate motor out of air stream P3.3 Use the best class of fans identified by EUROVENT P3.4 Use the best class of AHU P3.5 Consider applying chemical (dessicant (?)) de-humidification P3.6 Apply variable flow rate fan control P3.7 Consider conversion to VAV P3.8 Exhaust (cool) conditioned air over condensers and through cooling towers Y P3.9 Introduce exhaust air heat recovery Y P3.10 Consider applying demand-controlled ventilation Y P3.11 Generate possibility to increase outdoor air flow rate (direct free cooling) P3.12 Replace ducts when leaking
  • 10. P3.13 Modify ductwork to reduce pressure losses P3.14 Install back-draught or positive closure damper in ventilation exhaust system Y WATER HANDLING / WATER DISTRIBUTION P4.1 Use the best class of pumps P4.2 Modify pipework to reduce pressure losses P4.3 Convert 3-pipe system to 2-pipe or 4-pipe system P4.4 Install separate pumping to match zone requirements Y P4.5 Install variable volume pumping Y TERMINAL UNITS P5.1 Consider applying chilled ceilings or chilled beams P5.2 Consider introducing re-cool coils in zones with high cooling loads P5.3 Increase heat exchanger surface areas P5.4 Consider displacement ventilation P5.5 Install localised HVAC system (in case of local discomfort) Y SYSTEM REPLACEMENT (IN SPECIFIC LIMITED ZONES) P6.1 Consider water loop heat pump systems Y P6.2 Consider VRF (Variable Refrigerant Flow) systems
  • 11. O&M CODE ECO BEMS control FACILITY MANAGEMENT O1.1 Generate instructions (“user guide”) targeted to the occupants O1.2 Hire or appoint an energy manager O1.3 Train building operators in energy – efficient O&M activities O1.4 Introduce an energy – efficient objective as a clause in each O&M contract O1.5 Introduce benchmarks, metering and tracking as a clause in each O&M contract, with indication of values in graphs and tables O1.6 Update documentation on system / building and O&M procedures to maintain continuity and reduce troubleshooting costs O1.7 Check if O&M staff are equipped with state – of – the – art diagnostic tools GENERAL HVAC SYSTEM O2.1 Use an energy accounting system to locate savings opportunities and to positively identify savings made Y through improvements Shut off A/C equipment when not needed Y O2.2 O2.3 Shut off auxiliaries when not required Y/N O2.4 Maintain proper system control set points Y O2.5 Adjust internal set point values to external climatic conditions Y O2.6 Implement pre-occupancy cycle Y O2.7 Sequence heating and cooling Y O2.8 Adopt variable speed control strategy Y COOLING EQUIPMENT O3.1 Shut chiller plant off when not required Y O3.2 Sequence operation of multiple units Y O3.3 Operate chillers or compressors in series or parallel O3.4 Track and optimize chillers operation schedule Y O3.5 Maintain proper starting frequency and running time of (reversible) chillers Y O3.6 Improve part load operation control Y O3.7 Maintain proper evaporating and condensing temperatures Y O3.8 Raise chilled water temperature and suction gas pressure Y O3.9 Lower condensing water temperature and pressures Y O3.10 Check sensor functioning and placement for (reversible) chillers Y O3.11 Maintain efficient defrosting (reversible chillers) Y O3.12 Maintain proper heat source/sink flow rates Y O3.13 Maintain functioning of (reversible) chiller expansion device Y O3.14 Check (reversible) chiller stand-by losses Y O3.15 Maintain full charge of refrigerant Y/N O3.16 Clean finned tube evaporator / condenser air side and straighten damaged fins O3.17 Clean condenser tubes periodically
  • 12. O3.18 Repair or upgrade insulation on chiller O3.19 Clean and maintain cooling tower circuits and heat exchanger surfaces O3.20 Apply indirect free cooling using the existing cooling tower (free chilling) Y FLUID (AIR AND WATER) HANDLING AND DISTRIBUTION O4.1 Consider modifying the supply air temperature (all–air and air–and–water systems) Y O4.2 Perform night time overventilation where appropriate Y O4.3 Shut off coil circulators when not required Y O4.4 Replace mixing dampers O4.5 Adjust fan belts (AHU, packaged systems) O4.6 Eliminate air leaks (AHU, packaged systems) O4.7 Increase outdoor air flow rate (direct free cooling) Y O4.8 Adjust/balance ventilation system Y O4.9 Reduce air flow rate to actual needs Y/N O4.10 Check maintenance protocol in order to reduce pressure losses O4.11 Reduce air leakage in ducts O4.12 Clean fan blades O4.13 Maintain drives O4.14 Clean or replace filters regularly O4.15 Repair/upgrade duct, pipe and tank insulation O4.16 Consider the possibility to increase the water outlet – inlet temperature difference and reduce the flow rate for pumping power reduction O4.17 Balance hydronic distribution system Y O4.18 Bleed air from hydronic distribution system Y O4.19 Switch off circulation pumps when not required Y O4.20 Maintain proper water level in expansion tank Y O4.21 Repair water leaks O4.22 Reduce water flow rates to actual needs Y/N