2. You are managing a project to build a database and need to acquire information from the
stakeholders of the project. The team is using brainstorming, focus groups, interviews,
questionnaires, and benchmarking to understand and document the stakeholders' needs.
The methods the team is using are representative of which tool and technique?
A. Data gathering
B. Data analysis
C. Decision making
D. Data representation
HINT: Which tool and technique is used to acquire information in the Collect Requirements
process?
Question
3. The correct answer is A.
The project described in the scenario is in the Collect Requirements process, where project
stakeholders' needs and requirements are determined and documented. A tool and technique
used in the Collect Requirements process to elicit requirements from stakeholders is data
gathering. Data gathering includes brainstorming, focus groups, interviews, questionnaires,
surveys, and benchmarking.
Answer
4. All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge
(PMBOK® Guide) standard.
Stop by at free.pm-exam-simulator.com/ and try the
PM Exam Simulator free for 7 days.
We are a trusted and experienced education provider.