15. Clue is determine complexity factor ( for eg: due to requirement and technology)
16.
17. It is easier to estimate in ideal time than in ‘actual ‘/ ‘elapsed’ time, because need to consider all the factors that affect elapsed time at the same time you are estimating.What is your office timings? What is your focus factor?
18.
19. Three levels of planning Release plan -> Product back log Sprint / iteration plan -> Sprint back log Daily plan -> Daily Scrum / stand up meeting
25. What is the ‘focus factor’ ( from history, Available days ÷ Story points completed
26. Velocity - use historical, very difficult in initial sprints, forecast it. best in range, total number of story points can be completed in a sprint