SlideShare une entreprise Scribd logo
1  sur  10
Télécharger pour lire hors ligne
// How Traditional Risk Reporting
                Has Let Us Down



        Dr. Dan Patterson, PMP
         CEO & President, Acumen

            November 2012




                 +1 512 291 6261 // info@projectacumen.com
                               www.projectacumen.com
Table of Contents
Introduction ..................................................................................................................... 3
What is Project Risk Analysis? ......................................................................................... 3
How Can I Interpret the Results When I Don’t Even Understand the Inputs? .................... 4
   Cost/Schedule Basis .................................................................................................... 4
   Uncertainties ............................................................................................................... 4
          Figure 1– Schedule Uncertainty ............................................................................ 4
   Risk Events .................................................................................................................. 5
   Risk Reporting ............................................................................................................. 5
   Risk Histogram ............................................................................................................ 5
          Figure 2 – Risk Histogram .................................................................................... 6
Risk Tornado .................................................................................................................... 7
          Figure 3- Schedule Contribution Factor™ in the Tornado Chart ........................... 9
Conclusions ................................................................................................................... 10




+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                                        2
Introduction
As project management software tools have evolved, project risk analysis has gained a
reputation for being overly complicated and disconnected from the real world of
successful project execution.

I cannot count the number of times I have walked into a project risk workshop and been
presented with the likes of, “Do we really have to sit through this in order to determine
we are not going to finish on time?” or, “Oh yes, but this is just a theoretical model—the
real world does not work against P50 dates.” However, perception always shifts after
the risk analysis delivers true value and insight.

This white paper discusses reporting techniques and new ways of interpreting risk
analysis results that actually enable the project team to make proactive changes in
reducing their risk exposure and increasing their chance of successful on-time, on-
budget completion.


What is Project Risk Analysis?
Cost/schedule risk analysis is based on the simple premise of accounting for the
uncertainty and discrete risk events that have not yet been taken into account in the
base (deterministic) project plan. The goal of the project risk analysis is to provide
insight into the potential impact uncertainty and risk events will have during execution.

Traditional planning assumes finite durations and costs. These finite values are
unrealistic when forecasting a completion date or cost several years in the future.
Rates, quantities, scope, and manpower are all examples of variables that can impact
the realism of even the best-laid plan. Add to the mix, the potential presence of risk
events (threats or opportunities) and you start to wonder why so much emphasis is
given in generating a CPM schedule that inevitably turns out to be wrong! By capturing
these uncertainties and risk events through simulation (such as Monte Carlo) we are
able to better predict ranges of project costs and durations as well as gain confidence
in the likelihood of achieving the established plan.

In simplified terms, a Monte Carlo simulation is nothing more than CPM analysis
conducted hundreds and hundreds of times while taking into account the impact of
different combinations of uncertainty and risk events. The results, if interpreted
properly, actually provide impressive insight not possible through traditional CPM
scheduling alone.

The true key to a successful project risk analysis is not the cleverness of the risk model,
but the accurate interpretation of the results.




+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                       3
How Can I Interpret the Results When I Don’t Even Understand the Inputs?
Before we examine the various reporting techniques, it is worth touching on one of the
horrors of risk analysis—the accurate capture of uncertainty and risk inputs. Using
inaccurate or incomplete information at this step will render a risk model useless.

There are three moving parts to a project risk model that need to be established:

Cost/Schedule Basis
The best risk model in the world is arguably worthless if the underlying schedule is not
structurally sound. A sound schedule must have free-flowing logic, relevant level of
detail, and realistic completion dates not driven by management or political
considerations. A CPM schedule should reflect what is possible based upon
established work durations and sequences of work. This realism can push dates out of
alignment with project goals, but risk analysis can help get a project on track (see
schedule acceleration).

Uncertainties
Uncertainties are often driven by scope or work complexity, e.g., missing vendor
estimates or projects new to the company. Historically, cost and schedule uncertainty
has been modeled using 3-point estimates such as triangular, uniform, trigen, beta-pert
and other weird and wonderful distribution types. These distributions are important, but
a project team is never truly going to be able to differentiate between such distribution
types when trying to estimate uncertainties. Based on hundreds of successful risk
workshops, the solution is this: keep it real and keep it simple when interviewing a
project team capturing uncertainty ranges. Certainly take advantage of the distribution
types, but only when and where relevant.

Uncertainty should be treated as a measure of team buy-in into the cost estimate or
schedule. Simple reports such as a pie chart showing activities the team has rated as
being realistic, aggressive, or conservative is a very effective means of understanding
the team’s confidence and consensus.




                                Figure 1– Schedule Uncertainty
+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                       4
Risk Events
Risk events are often captured by a project team, but less often truly integrated into a
risk model. Ironically, risk events have a bigger impact on risk results than uncertainty
and schedule basis combined.

The importance of accurately capturing inputs cannot be overstated. About 80% of
model development should be focused on this process. A risk model is only as sound
as its inputs.

Risk Reporting
Today there are numerous types of risk reports: risk histograms, risk tornadoes, scatter
charts, sensitivity diagrams, fish-bone diagrams, and many more.

Continuing the idea of ‘keeping it real’, risk reports can be categorized into two camps:

    •   The ‘What’ report: What is my risk exposure? What is my confidence level?
        What is my range of outcomes?
    •   The ‘Why’ report: What are the risk drivers? Why is the confidence level high or
        low? What is the plan going forward and why is that the best option?

Risk Histogram
Risk histograms show a distribution of results from a Monte Carlo simulation. Run 1,000
iterations and, in theory, a risk histogram will show 1,000 different bars—one bar for
each of the different results. Increase the increment of the bar widths to say weeks or
months and the risk histogram starts to take a more common form of 10-20
weekly/monthly bars showing a non-cumulative distribution of results. Overlay on top of
this the cumulative set of results (in an ordered list) and you can then report P-dates
and P-costs – dates and costs against any given confidence level. These P values are
based on an ordered set of results from the risk analysis.

Figure 2 shows an example of a risk histogram reporting. The P0 (12/4/2013) result is
the best-case scenario. The P100 (2/11/2014) is the worst-case scenario.




+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                       5
Figure 2 – Risk Histogram

The histogram can also be used to report confidence level, or the probability of
achieving a given date. Figure 2 shows that the confidence level for the current
schedule finish date is only 5%. So is this a risky schedule?

The truth is, from this single metric, there is no way to know. Confidence level reporting
is a widely misused and skewed metric for reporting risk. In our example, the
confidence level of 5% would suggest we only have a 5% chance of finishing on time
and a 95% chance of being late. While this interpretation is indeed correct, what this
does not answer is how late are the 95% instances? Looking at the difference between
the worse case (P100) and the deterministic date, the worst overrun is actually only 56
days later than the schedule date.



+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                       6
Compare this with the remaining duration of the project (655 days) and the 56 days of
uncertainty indicates a relatively low degree of risk exposure.

The Risk Range Factor™
The risk range factor is a metric showing the degree of uncertainty relative to the
amount of remaining duration. In our example, the total risk range (P100 - P0) is 69
days. Compare that to the remaining duration (655 days) and the Risk Range Factor™
is 11% meaning the remaining variability in completion date represents only 11% of the
total remaining duration of the project.

The Risk Range Factor™ is a more meaningful way to measure risk exposure than the
traditional confidence level as shown in the example above. In fact, the confidence level
measurement is actually more a reflection of logic complexity than it is a measurement
of risk exposure.

Still in disbelief? Take a simple two-activities-in-parallel schedule and apply a +/- 5-day
uncertainty spread to both activities (each having 20-day deterministic durations) and
run a simple Monte Carlo simulation. You might expect the confidence level to be 50%,
but its not even close! The chance of both activities finishing on time is actually
50%*50% = 25%. Extrapolate this out across tens of activities with multiple paths and
the confidence level quickly diminishes to single digits.


Contingency
Contingency is defined as the difference between a deterministic value and a given P
value. Figure 2 shows that in order to be 50% confident, adding 16 days of contingency
to the project is necessary. Contingency is not the best way to manage risk, it is simply
moving the goal posts in order to lower expectations knowing the project will slip by 16
days. Instead, contingency should be used as the basis for a schedule acceleration or
compression in order to increase the chances of achieving the goal date.

In summary, risk histograms are excellent tools for reporting risk exposure, but need to
be used appropriately. Focus on the likes of risk range, contingency (within the context
of a given confidence level), and the Risk Range Factor™, which give a meaningful
context as to the size of the risk exposure relative to how much work is left in the
project. Be very wary of using confidence level as a primary means of reporting risk

Risk Tornado
The risk tornado chart is used to report key risk drivers. Historically focus has been
given to metrics such as criticality, which reports how many times an activity falls on
the critical path. The idea is that the more times the activity falls on the critical path, the
more often it is going to be a risk driver. The drawback of looking at just criticality is
that while it reports frequency of being on the critical path, it does not give any
indication of the size or degree of impact on the critical path or finish date of the
project. An activity can have a high criticality but only have a couple of days’ impact on
the project. This is not as concerning as an activity that only falls on the critical path
30% of the time, but when it does has a six-month impact on the project finish date.

+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                       7
This problem led to the development of one of the most misunderstood risk metrics—
Schedule Sensitivity Index. Schedule sensitivity is a combined measure of how often
and how big an impact an activity has on a given date. It is represented as a
percentage and is calculated as:

     SSI = (Criticality Index x Task Standard Deviation) / Project Standard Deviation

In layman’s terms, it is the correlation between the amount of uncertainty of an activity
and that of the project completion. All very well in theory, but try explaining this
percentage-based metric to a project manager or worse, a project sanction board
looking to invest millions of dollars in a project. Often the percentage is thought to be
how often the activity is the biggest driver, or perhaps how much the activity
contributes to a schedule overrun. Neither are correct. Attempt to defend its usefulness
in terms of correlation to overall schedule delay and the audience is lost. Time and time
again, SSI proves to be an unrelatable statistic for a project team that only wants to
know the average impact Activity X has on the schedule.

A better approach is to use a metric called Schedule Contribution Factor™. This
meaningful risk metric reports risk drivers in true cost and schedule terms and
differentiates between uncertainty and risk events in terms of contribution.
Schedule Contribution reports the biggest risk drivers in a schedule and reports
contribution to risk in terms of duration. Further, it separates contribution from
uncertainty and contribution from risk events in order to clarify whether it is the activity
scope/certainty or indeed a risk event impacting the activity that causes it to become a
key risk driver.

Figure 3 shows an example where the overall P50 risk exposure is 88 days and the top
five drivers are listed in rank order. Site clearance is, on average, having a 28 day
contribution to this 88 day risk exposure. Interestingly, only one of the 28 days is
actually due to schedule uncertainty with the remainder coming from a risk event
associated with hiring sufficient labor. In other words, while site clearance is the largest
risk contributor, sharpening our pencil on the accuracy of the duration estimate will not
fix the problem; in reality, the issue lies in not being able to hire sufficient labor (Risk
#42).

In a similar manner, the second two biggest risk-driving activities are both largely
impacted by the same risk, fabrication yard constraints (risk #9).




+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                       8
Figure 3- Schedule Contribution Factor™ in the Tornado Chart

Having this type of direct insight into the true risk drivers as well as being able to
understand the root cause of these drivers is a huge step forward in risk reporting.

Tornado charts are an excellent means of reporting where cost and schedule risk hot
spots are, but require special care in choosing the metrics used in the charts. Criticality
is a useful measure for understanding how stable the critical path is, but does little to
report the degree of impact on the project. Traditional measures such as Duration and
Schedule Sensitivity Index make matters more complex without giving better insight.
Instead, consider more meaningful metrics such as the Schedule Contribution Factor™,
which not only reports in actual duration/cost terms, but also differentiates between
contribution from uncertainty and risk events.




+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                       9
Conclusions
Project risk analysis is indisputably valuable as long as the information generated helps
the project team understand the risk exposure and helps them to pinpoint and reduce
the key drivers. Using the likes of risk histograms for reporting context-based metrics
such as Risk Range Factor™ helps give a project team a true sense of exposure.
Combine this with metrics such as the Schedule Contribution Factor™ and for the first
time, you can then also understand not only what activities and risks are causing the
risk exposure, but also how much of an impact they are having. Risk models do not
need to be complicated to be meaningful.




+1 512 291 6261 // info@projectacumen.com
www.projectacumen.com                       10

Contenu connexe

Tendances

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planningGlen Alleman
 
Continuous Risk Management
Continuous Risk ManagementContinuous Risk Management
Continuous Risk ManagementGlen Alleman
 
Cure for Cost and Schedule Growth
Cure for Cost and Schedule GrowthCure for Cost and Schedule Growth
Cure for Cost and Schedule GrowthGlen Alleman
 
Increasing the probability of program success
Increasing the probability of program successIncreasing the probability of program success
Increasing the probability of program successGlen Alleman
 
Benchmarking Execution Performance and Earned Value
Benchmarking Execution Performance and Earned ValueBenchmarking Execution Performance and Earned Value
Benchmarking Execution Performance and Earned ValueAcumen
 
Probabilistic Cost, Schedule, and Risk management
Probabilistic Cost, Schedule, and Risk managementProbabilistic Cost, Schedule, and Risk management
Probabilistic Cost, Schedule, and Risk managementGlen Alleman
 
Schedule analysis what could possibly go wrong - Oracle Primavera Collaborat...
Schedule analysis what could possibly go wrong  - Oracle Primavera Collaborat...Schedule analysis what could possibly go wrong  - Oracle Primavera Collaborat...
Schedule analysis what could possibly go wrong - Oracle Primavera Collaborat...p6academy
 
Applying risk radar (v2)
Applying risk radar (v2)Applying risk radar (v2)
Applying risk radar (v2)Glen Alleman
 
Why Scheduling Mustn't Be Allowed to Become an Extinct Science
Why Scheduling Mustn't Be Allowed to Become an Extinct ScienceWhy Scheduling Mustn't Be Allowed to Become an Extinct Science
Why Scheduling Mustn't Be Allowed to Become an Extinct ScienceAcumen
 
Technical Risk Management
Technical Risk ManagementTechnical Risk Management
Technical Risk ManagementGlen Alleman
 
Assessing Enterprise Project Risk
Assessing Enterprise Project RiskAssessing Enterprise Project Risk
Assessing Enterprise Project RiskGlen Alleman
 
Risk Management in Five Easy Pieces
Risk Management in Five Easy PiecesRisk Management in Five Easy Pieces
Risk Management in Five Easy PiecesGlen Alleman
 
Establishing schedule margin using monte carlo simulation
Establishing schedule margin using monte carlo simulation Establishing schedule margin using monte carlo simulation
Establishing schedule margin using monte carlo simulation Glen Alleman
 
Primavera Monte Carlo[1]
Primavera Monte Carlo[1]Primavera Monte Carlo[1]
Primavera Monte Carlo[1]Mihai Buta
 

Tendances (20)

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planning
 
Continuous Risk Management
Continuous Risk ManagementContinuous Risk Management
Continuous Risk Management
 
Cure for Cost and Schedule Growth
Cure for Cost and Schedule GrowthCure for Cost and Schedule Growth
Cure for Cost and Schedule Growth
 
Increasing the probability of program success
Increasing the probability of program successIncreasing the probability of program success
Increasing the probability of program success
 
Benchmarking Execution Performance and Earned Value
Benchmarking Execution Performance and Earned ValueBenchmarking Execution Performance and Earned Value
Benchmarking Execution Performance and Earned Value
 
Probabilistic Cost, Schedule, and Risk management
Probabilistic Cost, Schedule, and Risk managementProbabilistic Cost, Schedule, and Risk management
Probabilistic Cost, Schedule, and Risk management
 
Schedule analysis what could possibly go wrong - Oracle Primavera Collaborat...
Schedule analysis what could possibly go wrong  - Oracle Primavera Collaborat...Schedule analysis what could possibly go wrong  - Oracle Primavera Collaborat...
Schedule analysis what could possibly go wrong - Oracle Primavera Collaborat...
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
Risk Management
Risk ManagementRisk Management
Risk Management
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
What is risk?
What is risk?What is risk?
What is risk?
 
Applying risk radar (v2)
Applying risk radar (v2)Applying risk radar (v2)
Applying risk radar (v2)
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
Why Scheduling Mustn't Be Allowed to Become an Extinct Science
Why Scheduling Mustn't Be Allowed to Become an Extinct ScienceWhy Scheduling Mustn't Be Allowed to Become an Extinct Science
Why Scheduling Mustn't Be Allowed to Become an Extinct Science
 
Technical Risk Management
Technical Risk ManagementTechnical Risk Management
Technical Risk Management
 
Assessing Enterprise Project Risk
Assessing Enterprise Project RiskAssessing Enterprise Project Risk
Assessing Enterprise Project Risk
 
Risk Management in Five Easy Pieces
Risk Management in Five Easy PiecesRisk Management in Five Easy Pieces
Risk Management in Five Easy Pieces
 
Software Engineering
Software EngineeringSoftware Engineering
Software Engineering
 
Establishing schedule margin using monte carlo simulation
Establishing schedule margin using monte carlo simulation Establishing schedule margin using monte carlo simulation
Establishing schedule margin using monte carlo simulation
 
Primavera Monte Carlo[1]
Primavera Monte Carlo[1]Primavera Monte Carlo[1]
Primavera Monte Carlo[1]
 

Similaire à How Traditional Risk Reporting Has Let Us Down

Measuring Risk Exposure through Risk Range Certainty
Measuring Risk Exposure through Risk Range CertaintyMeasuring Risk Exposure through Risk Range Certainty
Measuring Risk Exposure through Risk Range CertaintyAcumen
 
The Art and Science Behind Successful Risk Workshops
The Art and Science Behind Successful Risk WorkshopsThe Art and Science Behind Successful Risk Workshops
The Art and Science Behind Successful Risk WorkshopsAcumen
 
Quantification of Risks in Project Management
Quantification of Risks in Project ManagementQuantification of Risks in Project Management
Quantification of Risks in Project ManagementVenkatesh Ganapathy
 
Risk management (final review)
Risk management (final review)Risk management (final review)
Risk management (final review)Glen Alleman
 
Adopting the Quadratic Mean Process to Quantify the Qualitative Risk Analysis
Adopting the Quadratic Mean Process to Quantify the Qualitative Risk AnalysisAdopting the Quadratic Mean Process to Quantify the Qualitative Risk Analysis
Adopting the Quadratic Mean Process to Quantify the Qualitative Risk AnalysisRicardo Viana Vargas
 
Risk management 4th in a series
Risk management 4th in a seriesRisk management 4th in a series
Risk management 4th in a seriesGlen Alleman
 
Building Risk Tolerance into the Program Plan and Schedule
Building Risk Tolerance into the Program Plan and ScheduleBuilding Risk Tolerance into the Program Plan and Schedule
Building Risk Tolerance into the Program Plan and ScheduleGlen Alleman
 
Event and Non-Event Risk - PMP/CAPM from PMI
Event and Non-Event Risk  - PMP/CAPM from PMIEvent and Non-Event Risk  - PMP/CAPM from PMI
Event and Non-Event Risk - PMP/CAPM from PMIMudassir Iqbal
 
Risky Business
Risky BusinessRisky Business
Risky Business3gamma
 
Risk management of the performance measurement baseline
Risk management of the performance measurement baselineRisk management of the performance measurement baseline
Risk management of the performance measurement baselineGlen Alleman
 
Acumen Risk: Brochure
Acumen Risk: BrochureAcumen Risk: Brochure
Acumen Risk: BrochureCisco
 
Building a risk tolerant integrated master schedule
Building a risk tolerant integrated master scheduleBuilding a risk tolerant integrated master schedule
Building a risk tolerant integrated master scheduleGlen Alleman
 
اهم برزنتيشن لجنك2222
اهم برزنتيشن لجنك2222اهم برزنتيشن لجنك2222
اهم برزنتيشن لجنك2222nashaat algrara
 
Programmatic risk management workshop (slides)
Programmatic risk management workshop (slides)Programmatic risk management workshop (slides)
Programmatic risk management workshop (slides)Glen Alleman
 
Cost Risk Analysis (CRA) by Pedram Daneshmand 19-Jan-2011
Cost Risk Analysis (CRA) by Pedram Daneshmand 19-Jan-2011Cost Risk Analysis (CRA) by Pedram Daneshmand 19-Jan-2011
Cost Risk Analysis (CRA) by Pedram Daneshmand 19-Jan-2011Pedram Danesh-Mand
 
IntroductionThe standards of venture risk administration can be .docx
IntroductionThe standards of venture risk administration can be .docxIntroductionThe standards of venture risk administration can be .docx
IntroductionThe standards of venture risk administration can be .docxmariuse18nolet
 
Risk Scorecard PowerPoint Presentation Slides
Risk Scorecard PowerPoint Presentation Slides Risk Scorecard PowerPoint Presentation Slides
Risk Scorecard PowerPoint Presentation Slides SlideTeam
 

Similaire à How Traditional Risk Reporting Has Let Us Down (20)

Measuring Risk Exposure through Risk Range Certainty
Measuring Risk Exposure through Risk Range CertaintyMeasuring Risk Exposure through Risk Range Certainty
Measuring Risk Exposure through Risk Range Certainty
 
The Art and Science Behind Successful Risk Workshops
The Art and Science Behind Successful Risk WorkshopsThe Art and Science Behind Successful Risk Workshops
The Art and Science Behind Successful Risk Workshops
 
Quantification of Risks in Project Management
Quantification of Risks in Project ManagementQuantification of Risks in Project Management
Quantification of Risks in Project Management
 
Risk management (final review)
Risk management (final review)Risk management (final review)
Risk management (final review)
 
Adopting the Quadratic Mean Process to Quantify the Qualitative Risk Analysis
Adopting the Quadratic Mean Process to Quantify the Qualitative Risk AnalysisAdopting the Quadratic Mean Process to Quantify the Qualitative Risk Analysis
Adopting the Quadratic Mean Process to Quantify the Qualitative Risk Analysis
 
Risk management 4th in a series
Risk management 4th in a seriesRisk management 4th in a series
Risk management 4th in a series
 
Stephen cresswell risk are we missing a trick - 25th june
Stephen cresswell   risk are we missing a trick - 25th juneStephen cresswell   risk are we missing a trick - 25th june
Stephen cresswell risk are we missing a trick - 25th june
 
Building Risk Tolerance into the Program Plan and Schedule
Building Risk Tolerance into the Program Plan and ScheduleBuilding Risk Tolerance into the Program Plan and Schedule
Building Risk Tolerance into the Program Plan and Schedule
 
Event and Non-Event Risk - PMP/CAPM from PMI
Event and Non-Event Risk  - PMP/CAPM from PMIEvent and Non-Event Risk  - PMP/CAPM from PMI
Event and Non-Event Risk - PMP/CAPM from PMI
 
Risky Business
Risky BusinessRisky Business
Risky Business
 
8. project risk management
8. project risk management8. project risk management
8. project risk management
 
Project Management 08
Project Management 08Project Management 08
Project Management 08
 
Risk management of the performance measurement baseline
Risk management of the performance measurement baselineRisk management of the performance measurement baseline
Risk management of the performance measurement baseline
 
Acumen Risk: Brochure
Acumen Risk: BrochureAcumen Risk: Brochure
Acumen Risk: Brochure
 
Building a risk tolerant integrated master schedule
Building a risk tolerant integrated master scheduleBuilding a risk tolerant integrated master schedule
Building a risk tolerant integrated master schedule
 
اهم برزنتيشن لجنك2222
اهم برزنتيشن لجنك2222اهم برزنتيشن لجنك2222
اهم برزنتيشن لجنك2222
 
Programmatic risk management workshop (slides)
Programmatic risk management workshop (slides)Programmatic risk management workshop (slides)
Programmatic risk management workshop (slides)
 
Cost Risk Analysis (CRA) by Pedram Daneshmand 19-Jan-2011
Cost Risk Analysis (CRA) by Pedram Daneshmand 19-Jan-2011Cost Risk Analysis (CRA) by Pedram Daneshmand 19-Jan-2011
Cost Risk Analysis (CRA) by Pedram Daneshmand 19-Jan-2011
 
IntroductionThe standards of venture risk administration can be .docx
IntroductionThe standards of venture risk administration can be .docxIntroductionThe standards of venture risk administration can be .docx
IntroductionThe standards of venture risk administration can be .docx
 
Risk Scorecard PowerPoint Presentation Slides
Risk Scorecard PowerPoint Presentation Slides Risk Scorecard PowerPoint Presentation Slides
Risk Scorecard PowerPoint Presentation Slides
 

Plus de Acumen

Simplifiying cost and schedule risk analysis with acumen risk
Simplifiying cost and schedule risk analysis with acumen riskSimplifiying cost and schedule risk analysis with acumen risk
Simplifiying cost and schedule risk analysis with acumen riskAcumen
 
Fuse Customer Perspectives: Oil & Gas / Energy
Fuse Customer Perspectives: Oil & Gas / EnergyFuse Customer Perspectives: Oil & Gas / Energy
Fuse Customer Perspectives: Oil & Gas / EnergyAcumen
 
Acumen Fuse World Tour 2012
Acumen Fuse World Tour 2012Acumen Fuse World Tour 2012
Acumen Fuse World Tour 2012Acumen
 
Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?Acumen
 
Meet or Exceed Schedule Expectations through Intelligent Acceleration
Meet or Exceed Schedule Expectations through Intelligent AccelerationMeet or Exceed Schedule Expectations through Intelligent Acceleration
Meet or Exceed Schedule Expectations through Intelligent AccelerationAcumen
 
Dr. McNatty Webinar: An Introduction to Acumen 360
Dr. McNatty Webinar: An Introduction to Acumen 360Dr. McNatty Webinar: An Introduction to Acumen 360
Dr. McNatty Webinar: An Introduction to Acumen 360Acumen
 
PMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
PMICOS Webinar: Building a Sound Schedule in an Enterprise EnvironmentPMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
PMICOS Webinar: Building a Sound Schedule in an Enterprise EnvironmentAcumen
 
Smarter Project Analysis and Improved Project Performance
Smarter Project Analysis and Improved Project PerformanceSmarter Project Analysis and Improved Project Performance
Smarter Project Analysis and Improved Project PerformanceAcumen
 
Meeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance StandardsMeeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance StandardsAcumen
 
Acumen Fuse & Customer Case Study
Acumen Fuse & Customer Case StudyAcumen Fuse & Customer Case Study
Acumen Fuse & Customer Case StudyAcumen
 
Acumen & ARES: Simplified Cost & Schedule Integration
Acumen & ARES: Simplified Cost & Schedule IntegrationAcumen & ARES: Simplified Cost & Schedule Integration
Acumen & ARES: Simplified Cost & Schedule IntegrationAcumen
 
2011 Acumen Annual Summit Keynote
2011 Acumen Annual Summit Keynote2011 Acumen Annual Summit Keynote
2011 Acumen Annual Summit KeynoteAcumen
 
Calgary Breakfast Seminar: Predict and Influence Project Success
Calgary Breakfast Seminar: Predict and Influence Project SuccessCalgary Breakfast Seminar: Predict and Influence Project Success
Calgary Breakfast Seminar: Predict and Influence Project SuccessAcumen
 
Intelligent Project Acceleration: An Introduction to Acumen 360
Intelligent Project Acceleration: An Introduction to Acumen 360Intelligent Project Acceleration: An Introduction to Acumen 360
Intelligent Project Acceleration: An Introduction to Acumen 360Acumen
 
Advanced Project Analysis: An Introduction to Fuse 3.0
Advanced Project Analysis: An Introduction to Fuse 3.0Advanced Project Analysis: An Introduction to Fuse 3.0
Advanced Project Analysis: An Introduction to Fuse 3.0Acumen
 
Successful Dispute Resolution
Successful Dispute ResolutionSuccessful Dispute Resolution
Successful Dispute ResolutionAcumen
 
Achieving the Unachievable: Aligning a Project with Stakeholder Expectations
Achieving the Unachievable: Aligning a Project with Stakeholder ExpectationsAchieving the Unachievable: Aligning a Project with Stakeholder Expectations
Achieving the Unachievable: Aligning a Project with Stakeholder ExpectationsAcumen
 
Advanced Project Analysis and Project Benchmarking with Acumen Cloud™
Advanced Project Analysis and Project Benchmarking with Acumen Cloud™Advanced Project Analysis and Project Benchmarking with Acumen Cloud™
Advanced Project Analysis and Project Benchmarking with Acumen Cloud™Acumen
 
Fuse Customer Perspectives Webinar: EPC
Fuse Customer Perspectives Webinar: EPCFuse Customer Perspectives Webinar: EPC
Fuse Customer Perspectives Webinar: EPCAcumen
 
Fuse Customer Perspectives Webinar: Project Compliance
Fuse Customer Perspectives Webinar: Project ComplianceFuse Customer Perspectives Webinar: Project Compliance
Fuse Customer Perspectives Webinar: Project ComplianceAcumen
 

Plus de Acumen (20)

Simplifiying cost and schedule risk analysis with acumen risk
Simplifiying cost and schedule risk analysis with acumen riskSimplifiying cost and schedule risk analysis with acumen risk
Simplifiying cost and schedule risk analysis with acumen risk
 
Fuse Customer Perspectives: Oil & Gas / Energy
Fuse Customer Perspectives: Oil & Gas / EnergyFuse Customer Perspectives: Oil & Gas / Energy
Fuse Customer Perspectives: Oil & Gas / Energy
 
Acumen Fuse World Tour 2012
Acumen Fuse World Tour 2012Acumen Fuse World Tour 2012
Acumen Fuse World Tour 2012
 
Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?
 
Meet or Exceed Schedule Expectations through Intelligent Acceleration
Meet or Exceed Schedule Expectations through Intelligent AccelerationMeet or Exceed Schedule Expectations through Intelligent Acceleration
Meet or Exceed Schedule Expectations through Intelligent Acceleration
 
Dr. McNatty Webinar: An Introduction to Acumen 360
Dr. McNatty Webinar: An Introduction to Acumen 360Dr. McNatty Webinar: An Introduction to Acumen 360
Dr. McNatty Webinar: An Introduction to Acumen 360
 
PMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
PMICOS Webinar: Building a Sound Schedule in an Enterprise EnvironmentPMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
PMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
 
Smarter Project Analysis and Improved Project Performance
Smarter Project Analysis and Improved Project PerformanceSmarter Project Analysis and Improved Project Performance
Smarter Project Analysis and Improved Project Performance
 
Meeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance StandardsMeeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance Standards
 
Acumen Fuse & Customer Case Study
Acumen Fuse & Customer Case StudyAcumen Fuse & Customer Case Study
Acumen Fuse & Customer Case Study
 
Acumen & ARES: Simplified Cost & Schedule Integration
Acumen & ARES: Simplified Cost & Schedule IntegrationAcumen & ARES: Simplified Cost & Schedule Integration
Acumen & ARES: Simplified Cost & Schedule Integration
 
2011 Acumen Annual Summit Keynote
2011 Acumen Annual Summit Keynote2011 Acumen Annual Summit Keynote
2011 Acumen Annual Summit Keynote
 
Calgary Breakfast Seminar: Predict and Influence Project Success
Calgary Breakfast Seminar: Predict and Influence Project SuccessCalgary Breakfast Seminar: Predict and Influence Project Success
Calgary Breakfast Seminar: Predict and Influence Project Success
 
Intelligent Project Acceleration: An Introduction to Acumen 360
Intelligent Project Acceleration: An Introduction to Acumen 360Intelligent Project Acceleration: An Introduction to Acumen 360
Intelligent Project Acceleration: An Introduction to Acumen 360
 
Advanced Project Analysis: An Introduction to Fuse 3.0
Advanced Project Analysis: An Introduction to Fuse 3.0Advanced Project Analysis: An Introduction to Fuse 3.0
Advanced Project Analysis: An Introduction to Fuse 3.0
 
Successful Dispute Resolution
Successful Dispute ResolutionSuccessful Dispute Resolution
Successful Dispute Resolution
 
Achieving the Unachievable: Aligning a Project with Stakeholder Expectations
Achieving the Unachievable: Aligning a Project with Stakeholder ExpectationsAchieving the Unachievable: Aligning a Project with Stakeholder Expectations
Achieving the Unachievable: Aligning a Project with Stakeholder Expectations
 
Advanced Project Analysis and Project Benchmarking with Acumen Cloud™
Advanced Project Analysis and Project Benchmarking with Acumen Cloud™Advanced Project Analysis and Project Benchmarking with Acumen Cloud™
Advanced Project Analysis and Project Benchmarking with Acumen Cloud™
 
Fuse Customer Perspectives Webinar: EPC
Fuse Customer Perspectives Webinar: EPCFuse Customer Perspectives Webinar: EPC
Fuse Customer Perspectives Webinar: EPC
 
Fuse Customer Perspectives Webinar: Project Compliance
Fuse Customer Perspectives Webinar: Project ComplianceFuse Customer Perspectives Webinar: Project Compliance
Fuse Customer Perspectives Webinar: Project Compliance
 

Dernier

Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy Verified Accounts
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607dollysharma2066
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesKeppelCorporation
 
IoT Insurance Observatory: summary 2024
IoT Insurance Observatory:  summary 2024IoT Insurance Observatory:  summary 2024
IoT Insurance Observatory: summary 2024Matteo Carbone
 
Marketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent ChirchirMarketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent Chirchirictsugar
 
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...ictsugar
 
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxContemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxMarkAnthonyAurellano
 
Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMintel Group
 
Case study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailCase study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailAriel592675
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfRbc Rbcua
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckHajeJanKamps
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03DallasHaselhorst
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCRashishs7044
 
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu MenzaYouth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menzaictsugar
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMVoces Mineras
 
PSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationPSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationAnamaria Contreras
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Seta Wicaksana
 

Dernier (20)

Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail Accounts
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
 
Call Us ➥9319373153▻Call Girls In North Goa
Call Us ➥9319373153▻Call Girls In North GoaCall Us ➥9319373153▻Call Girls In North Goa
Call Us ➥9319373153▻Call Girls In North Goa
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation Slides
 
IoT Insurance Observatory: summary 2024
IoT Insurance Observatory:  summary 2024IoT Insurance Observatory:  summary 2024
IoT Insurance Observatory: summary 2024
 
Marketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent ChirchirMarketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent Chirchir
 
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
 
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxContemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
 
Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 Edition
 
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCREnjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
 
Case study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailCase study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detail
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdf
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
 
Corporate Profile 47Billion Information Technology
Corporate Profile 47Billion Information TechnologyCorporate Profile 47Billion Information Technology
Corporate Profile 47Billion Information Technology
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
 
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu MenzaYouth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQM
 
PSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationPSCC - Capability Statement Presentation
PSCC - Capability Statement Presentation
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...
 

How Traditional Risk Reporting Has Let Us Down

  • 1. // How Traditional Risk Reporting Has Let Us Down Dr. Dan Patterson, PMP CEO & President, Acumen November 2012 +1 512 291 6261 // info@projectacumen.com www.projectacumen.com
  • 2. Table of Contents Introduction ..................................................................................................................... 3 What is Project Risk Analysis? ......................................................................................... 3 How Can I Interpret the Results When I Don’t Even Understand the Inputs? .................... 4 Cost/Schedule Basis .................................................................................................... 4 Uncertainties ............................................................................................................... 4 Figure 1– Schedule Uncertainty ............................................................................ 4 Risk Events .................................................................................................................. 5 Risk Reporting ............................................................................................................. 5 Risk Histogram ............................................................................................................ 5 Figure 2 – Risk Histogram .................................................................................... 6 Risk Tornado .................................................................................................................... 7 Figure 3- Schedule Contribution Factor™ in the Tornado Chart ........................... 9 Conclusions ................................................................................................................... 10 +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 2
  • 3. Introduction As project management software tools have evolved, project risk analysis has gained a reputation for being overly complicated and disconnected from the real world of successful project execution. I cannot count the number of times I have walked into a project risk workshop and been presented with the likes of, “Do we really have to sit through this in order to determine we are not going to finish on time?” or, “Oh yes, but this is just a theoretical model—the real world does not work against P50 dates.” However, perception always shifts after the risk analysis delivers true value and insight. This white paper discusses reporting techniques and new ways of interpreting risk analysis results that actually enable the project team to make proactive changes in reducing their risk exposure and increasing their chance of successful on-time, on- budget completion. What is Project Risk Analysis? Cost/schedule risk analysis is based on the simple premise of accounting for the uncertainty and discrete risk events that have not yet been taken into account in the base (deterministic) project plan. The goal of the project risk analysis is to provide insight into the potential impact uncertainty and risk events will have during execution. Traditional planning assumes finite durations and costs. These finite values are unrealistic when forecasting a completion date or cost several years in the future. Rates, quantities, scope, and manpower are all examples of variables that can impact the realism of even the best-laid plan. Add to the mix, the potential presence of risk events (threats or opportunities) and you start to wonder why so much emphasis is given in generating a CPM schedule that inevitably turns out to be wrong! By capturing these uncertainties and risk events through simulation (such as Monte Carlo) we are able to better predict ranges of project costs and durations as well as gain confidence in the likelihood of achieving the established plan. In simplified terms, a Monte Carlo simulation is nothing more than CPM analysis conducted hundreds and hundreds of times while taking into account the impact of different combinations of uncertainty and risk events. The results, if interpreted properly, actually provide impressive insight not possible through traditional CPM scheduling alone. The true key to a successful project risk analysis is not the cleverness of the risk model, but the accurate interpretation of the results. +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 3
  • 4. How Can I Interpret the Results When I Don’t Even Understand the Inputs? Before we examine the various reporting techniques, it is worth touching on one of the horrors of risk analysis—the accurate capture of uncertainty and risk inputs. Using inaccurate or incomplete information at this step will render a risk model useless. There are three moving parts to a project risk model that need to be established: Cost/Schedule Basis The best risk model in the world is arguably worthless if the underlying schedule is not structurally sound. A sound schedule must have free-flowing logic, relevant level of detail, and realistic completion dates not driven by management or political considerations. A CPM schedule should reflect what is possible based upon established work durations and sequences of work. This realism can push dates out of alignment with project goals, but risk analysis can help get a project on track (see schedule acceleration). Uncertainties Uncertainties are often driven by scope or work complexity, e.g., missing vendor estimates or projects new to the company. Historically, cost and schedule uncertainty has been modeled using 3-point estimates such as triangular, uniform, trigen, beta-pert and other weird and wonderful distribution types. These distributions are important, but a project team is never truly going to be able to differentiate between such distribution types when trying to estimate uncertainties. Based on hundreds of successful risk workshops, the solution is this: keep it real and keep it simple when interviewing a project team capturing uncertainty ranges. Certainly take advantage of the distribution types, but only when and where relevant. Uncertainty should be treated as a measure of team buy-in into the cost estimate or schedule. Simple reports such as a pie chart showing activities the team has rated as being realistic, aggressive, or conservative is a very effective means of understanding the team’s confidence and consensus. Figure 1– Schedule Uncertainty +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 4
  • 5. Risk Events Risk events are often captured by a project team, but less often truly integrated into a risk model. Ironically, risk events have a bigger impact on risk results than uncertainty and schedule basis combined. The importance of accurately capturing inputs cannot be overstated. About 80% of model development should be focused on this process. A risk model is only as sound as its inputs. Risk Reporting Today there are numerous types of risk reports: risk histograms, risk tornadoes, scatter charts, sensitivity diagrams, fish-bone diagrams, and many more. Continuing the idea of ‘keeping it real’, risk reports can be categorized into two camps: • The ‘What’ report: What is my risk exposure? What is my confidence level? What is my range of outcomes? • The ‘Why’ report: What are the risk drivers? Why is the confidence level high or low? What is the plan going forward and why is that the best option? Risk Histogram Risk histograms show a distribution of results from a Monte Carlo simulation. Run 1,000 iterations and, in theory, a risk histogram will show 1,000 different bars—one bar for each of the different results. Increase the increment of the bar widths to say weeks or months and the risk histogram starts to take a more common form of 10-20 weekly/monthly bars showing a non-cumulative distribution of results. Overlay on top of this the cumulative set of results (in an ordered list) and you can then report P-dates and P-costs – dates and costs against any given confidence level. These P values are based on an ordered set of results from the risk analysis. Figure 2 shows an example of a risk histogram reporting. The P0 (12/4/2013) result is the best-case scenario. The P100 (2/11/2014) is the worst-case scenario. +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 5
  • 6. Figure 2 – Risk Histogram The histogram can also be used to report confidence level, or the probability of achieving a given date. Figure 2 shows that the confidence level for the current schedule finish date is only 5%. So is this a risky schedule? The truth is, from this single metric, there is no way to know. Confidence level reporting is a widely misused and skewed metric for reporting risk. In our example, the confidence level of 5% would suggest we only have a 5% chance of finishing on time and a 95% chance of being late. While this interpretation is indeed correct, what this does not answer is how late are the 95% instances? Looking at the difference between the worse case (P100) and the deterministic date, the worst overrun is actually only 56 days later than the schedule date. +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 6
  • 7. Compare this with the remaining duration of the project (655 days) and the 56 days of uncertainty indicates a relatively low degree of risk exposure. The Risk Range Factor™ The risk range factor is a metric showing the degree of uncertainty relative to the amount of remaining duration. In our example, the total risk range (P100 - P0) is 69 days. Compare that to the remaining duration (655 days) and the Risk Range Factor™ is 11% meaning the remaining variability in completion date represents only 11% of the total remaining duration of the project. The Risk Range Factor™ is a more meaningful way to measure risk exposure than the traditional confidence level as shown in the example above. In fact, the confidence level measurement is actually more a reflection of logic complexity than it is a measurement of risk exposure. Still in disbelief? Take a simple two-activities-in-parallel schedule and apply a +/- 5-day uncertainty spread to both activities (each having 20-day deterministic durations) and run a simple Monte Carlo simulation. You might expect the confidence level to be 50%, but its not even close! The chance of both activities finishing on time is actually 50%*50% = 25%. Extrapolate this out across tens of activities with multiple paths and the confidence level quickly diminishes to single digits. Contingency Contingency is defined as the difference between a deterministic value and a given P value. Figure 2 shows that in order to be 50% confident, adding 16 days of contingency to the project is necessary. Contingency is not the best way to manage risk, it is simply moving the goal posts in order to lower expectations knowing the project will slip by 16 days. Instead, contingency should be used as the basis for a schedule acceleration or compression in order to increase the chances of achieving the goal date. In summary, risk histograms are excellent tools for reporting risk exposure, but need to be used appropriately. Focus on the likes of risk range, contingency (within the context of a given confidence level), and the Risk Range Factor™, which give a meaningful context as to the size of the risk exposure relative to how much work is left in the project. Be very wary of using confidence level as a primary means of reporting risk Risk Tornado The risk tornado chart is used to report key risk drivers. Historically focus has been given to metrics such as criticality, which reports how many times an activity falls on the critical path. The idea is that the more times the activity falls on the critical path, the more often it is going to be a risk driver. The drawback of looking at just criticality is that while it reports frequency of being on the critical path, it does not give any indication of the size or degree of impact on the critical path or finish date of the project. An activity can have a high criticality but only have a couple of days’ impact on the project. This is not as concerning as an activity that only falls on the critical path 30% of the time, but when it does has a six-month impact on the project finish date. +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 7
  • 8. This problem led to the development of one of the most misunderstood risk metrics— Schedule Sensitivity Index. Schedule sensitivity is a combined measure of how often and how big an impact an activity has on a given date. It is represented as a percentage and is calculated as: SSI = (Criticality Index x Task Standard Deviation) / Project Standard Deviation In layman’s terms, it is the correlation between the amount of uncertainty of an activity and that of the project completion. All very well in theory, but try explaining this percentage-based metric to a project manager or worse, a project sanction board looking to invest millions of dollars in a project. Often the percentage is thought to be how often the activity is the biggest driver, or perhaps how much the activity contributes to a schedule overrun. Neither are correct. Attempt to defend its usefulness in terms of correlation to overall schedule delay and the audience is lost. Time and time again, SSI proves to be an unrelatable statistic for a project team that only wants to know the average impact Activity X has on the schedule. A better approach is to use a metric called Schedule Contribution Factor™. This meaningful risk metric reports risk drivers in true cost and schedule terms and differentiates between uncertainty and risk events in terms of contribution. Schedule Contribution reports the biggest risk drivers in a schedule and reports contribution to risk in terms of duration. Further, it separates contribution from uncertainty and contribution from risk events in order to clarify whether it is the activity scope/certainty or indeed a risk event impacting the activity that causes it to become a key risk driver. Figure 3 shows an example where the overall P50 risk exposure is 88 days and the top five drivers are listed in rank order. Site clearance is, on average, having a 28 day contribution to this 88 day risk exposure. Interestingly, only one of the 28 days is actually due to schedule uncertainty with the remainder coming from a risk event associated with hiring sufficient labor. In other words, while site clearance is the largest risk contributor, sharpening our pencil on the accuracy of the duration estimate will not fix the problem; in reality, the issue lies in not being able to hire sufficient labor (Risk #42). In a similar manner, the second two biggest risk-driving activities are both largely impacted by the same risk, fabrication yard constraints (risk #9). +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 8
  • 9. Figure 3- Schedule Contribution Factor™ in the Tornado Chart Having this type of direct insight into the true risk drivers as well as being able to understand the root cause of these drivers is a huge step forward in risk reporting. Tornado charts are an excellent means of reporting where cost and schedule risk hot spots are, but require special care in choosing the metrics used in the charts. Criticality is a useful measure for understanding how stable the critical path is, but does little to report the degree of impact on the project. Traditional measures such as Duration and Schedule Sensitivity Index make matters more complex without giving better insight. Instead, consider more meaningful metrics such as the Schedule Contribution Factor™, which not only reports in actual duration/cost terms, but also differentiates between contribution from uncertainty and risk events. +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 9
  • 10. Conclusions Project risk analysis is indisputably valuable as long as the information generated helps the project team understand the risk exposure and helps them to pinpoint and reduce the key drivers. Using the likes of risk histograms for reporting context-based metrics such as Risk Range Factor™ helps give a project team a true sense of exposure. Combine this with metrics such as the Schedule Contribution Factor™ and for the first time, you can then also understand not only what activities and risks are causing the risk exposure, but also how much of an impact they are having. Risk models do not need to be complicated to be meaningful. +1 512 291 6261 // info@projectacumen.com www.projectacumen.com 10