Arab Republic of Egypt
      Ministry of Electricity & Energy
New and Renewable Energy Authority“ NREA
    Technical and Financial Evaluation




             Prepared By

       Dr. sabry M. Aly Mokhymar
               Octber
Technical and Financial Evaluation


  Tender Invitation
  Opening The Technical Specification Documents
  Verification from Tender Documents TDs
  contents
  Technical evaluation for the submitted TDs
  Opening The Financial Documents
  Financial evaluation for the submitted TDs
  Evaluation Methods
Technical and Financial Evaluation

                               . Tender Invitation:
     There are two way for tender invitation or its announcements as:
st   way (With Prequalification _PQ):
      NREA announce at the local and international newspaper to recall the Pre-
      Qualification (PQ)'s documentation of the companies which could share in the
      project's competition. In the announcement it must be clear the final date to
      submit all of the PQ documents and the final date to open the tender's
      envelops. After tender opening the technical and financial evaluation for the
      prequalification documents should be started. after finish the evaluation and
      selection of the qualified companies, NREA should send a circular letters to
      the selected companies. Also, NREA invite the qualified companies to buy
      TD from the NREA premises to prepare and submit its TD for the nominated
      wind project. In the instruction to the tenderers' there are the final date to
      submit TD and its opening date. The qualified companies must submit two
      TD the st one is the technical documents and the nd one is the financial
      documents where the last one shouldn't be opened except for the successful
      technical documentation.
. Tender Invitation (contd.)

nd way (Without Prequalification _PQ):

 The same procedure as the st way but
 without submit PQ i.e. every company just
 submit its TD for implementation a wind farm
 capacity ( ) MW with a nominated Wind
 turbines technology as pitch or active
 pitch…etc.
. Opening The Technical Specification
                 Documents:
A technical evaluation's committee should be
hold to nominate the successful technical
tender. Technical Tender should be opening In
the specific date or day in the attendance with
the companies' representatives. The committee
must sure from some documents as (letter of
guarantee and its value). An institutional or
legal document must be documented and
singed from each representative.
. Verification from TD contents

A Verification to the TD documents
according to its instructions:

  The committee must be sure from the completeness for
  all of TD specially letter of guarantee and letter of
  interest. All of the companies must obey the instruction
  of TD but if any company can't obey These instructions,
  it should be rejected. The next point must be check also:
. Verification from TD contents (contd.)

Completeness for all of TD
Every paper must be singed and stamped
TD include the letter of Guarantee with its
nominated value and letter of interest
Ready for any clarification or any
comments form NREA.
Verification from the next documents:
. Verification from TD contents (contd.)

Demand Documentations to be Submitted With the
Offers:
    Company's or contractor's organization chart.
    Project's organization chart for the total period of
    project's time schedule including the responsibilities
    for each person and his CV's.
    List of components which could be manufactured in
    Egypt.
    Financial Status for each company or contractor
    Describe the contractor's experience specially for the
    same projects
. Verification from TD contents (contd.)


Demand Documentations to be Submitted With the Offers
(contd.) :
        Spread sheet including the number of WECS with the
        model in the TD with a specific numbers should be
        implemented for a period as one or two years tell the
        dated of submission for TD. Or a specific spread sheet
        for the WEC's major components eg. (Gearbox-
        generators, high speed shaft…etcs) with a specific
        numbers should be implemented for a period as one or
        two years before the submission of TD
     WEC's Type certificate or its equivalent (eg. Design
     certificate, proto type test report, or other…etc) with
     IEC code and it must be verified and signed from GL or
     any from its equivalent international institutions
. Verification from TD contents (contd.)


     Demand Documentations to be Submitted With the
     Offers (contd.) :

 •     Quality assurance certificate
       List of Codes and Standards
       Noise level characteristics for the submitted WECs.
       Mechanism for clean or dust elimination.
       List for all of the components with the specific life time
       Agreement for Guaranteed availability not less than
       through the guarantee period
       Annual energy production's calculations for the wind farm
       Proposed Wind Farm Lay Out
       Guaranteed Power Curve for the submitted WECs
. Verification from TD contents (contd.)


  Demand Documentations to be Submitted With the
  Offers (contd.) :

        Protection Procedures for all of the components
        from any Electrical shocks
         List for the proposed spare parts
        List for the proposed tools and instrumentations for
        work shops
        Planning for acceptance certificates' tests for the
        manufacturers including list with its tasks according
        to the acceptance test.
        Proposed Training program in Egypt or at company
. Verification from TD contents (contd.)


  Demand Documentations to be Submitted With
  the Offers (contd.) :

     After sale services
     Description for CMS (control monitoring system)
     Work Plan and Time schedule
     Proposed plane for project implementation
     Components origin and data about the factory which
     the components are manufactured or assembly inside
     it
. Technical evaluation for the submitted TDs :

  Analyze and evaluate the technical points and its demands with the
  nominated specifications for TD. We must be sure from any wrong
  not accept with the technical demands or sure from any deviations
  for the technical specification and get a clarification for it if any.
  Analyze and evaluate for programs of the training and the inspection
  or commissioning 's in Egypt or outside of Egypt.
  Check the availability and logic of time schedule
  Check the spare parts and its availability in the local market
  Check and verify the Annual energy production's calculations for the
  wind farm for each company
  The final result should be as (yes for technically accepted
  companies & no for technically rejected companies)
. Opening The Financial Documents:


NREA should open the financial documentation for just
the accepted technical tender. A financial evaluation's
committee should be hold to nominate the successful
financial tender. The financial tender should be opening
In the specific date or day in the attendance with the
companies' representatives, where every value of each
tender should be announced in the same time. An
institutional or legal document must be documented and
singed from each representative.
. Financial evaluation for the submitted TDs :


                   Calculation adjustments

  The committee must check the prices schedules for each company
  with correction for any wrong calculations if any


                Financial Check for each TDs

  Check for every items' price and if any item is not found i.e there is
  no evaluation for this item, so the highest price for this item form the
  other offers should be added for this company at the nominated
  schedule. And recalculate its contract price according to the
  modified total price.
Evaluation Methods

   Financial evaluation methods
There are tow methods to get this
evaluation:
   st method:
    according to the annual energy for each
    company as:
    we must calculate the value of the next
    equation
               =
Evaluation Methods (Contd.)

                          Where
En: meaning the annual generated energy from the offer (n)
Emax : meaning the maximum annual generated energy from
the offers
The final arrangement for the offers should be as the next
equation:


     Tender Price Evaluated = TD price
                                 Kn
        The highest the level (the winner)
            The lower price is found.
Evaluation Methods (Contd.)

                          The nd method

After adjustment for all calculations and final review for the
financial offers the next procedures should be done:

          calculated the total annual energy for each offer

          calculated the KWH price for      years or     years
          according to the life time of the wind farm

                    The highest the level (the winner)
                    The lower price for KWH is found
Technical and financial_evaluation
Technical and financial_evaluation

More Related Content

What's hot

Cost estimates & contract documents ce224 pdf
Cost estimates & contract documents   ce224 pdfCost estimates & contract documents   ce224 pdf
Cost estimates & contract documents ce224 pdfSaqib Imran
 
PPT on Construction Costing
PPT on Construction CostingPPT on Construction Costing
PPT on Construction CostingManish Kandpal
 
Wb consultant 4a
Wb consultant 4aWb consultant 4a
Wb consultant 4aJoy Irman
 
Guide_for_Determining_Adequacy_of_Contractor_Incurred_Cost_Proposal
Guide_for_Determining_Adequacy_of_Contractor_Incurred_Cost_ProposalGuide_for_Determining_Adequacy_of_Contractor_Incurred_Cost_Proposal
Guide_for_Determining_Adequacy_of_Contractor_Incurred_Cost_ProposalTodd McAdams, CPA, CGMA, MAcc
 
Contract monitoring & evaluation
Contract monitoring & evaluationContract monitoring & evaluation
Contract monitoring & evaluationjama osman
 
Purpose and importance of estimate
Purpose and importance of estimatePurpose and importance of estimate
Purpose and importance of estimateArpit Sethia
 
Estimation and Costing
Estimation and CostingEstimation and Costing
Estimation and CostingSakshi Kirar
 
Sample cost control training proposal
Sample cost control training proposalSample cost control training proposal
Sample cost control training proposalSadegh Yazdani
 
Cost Engineering Introduction
Cost Engineering IntroductionCost Engineering Introduction
Cost Engineering IntroductionLeendertdegeus
 
1 regatta quay rehab boq 20120420 blank
1 regatta quay rehab boq 20120420 blank 1 regatta quay rehab boq 20120420 blank
1 regatta quay rehab boq 20120420 blank Thomas Magatu
 
Tenders contract -arti
Tenders contract -artiTenders contract -arti
Tenders contract -artijagadish108
 
Project cost stimating
Project cost stimatingProject cost stimating
Project cost stimatinghatim ahmed
 

What's hot (20)

TEA checklist
TEA checklistTEA checklist
TEA checklist
 
Cost estimates & contract documents ce224 pdf
Cost estimates & contract documents   ce224 pdfCost estimates & contract documents   ce224 pdf
Cost estimates & contract documents ce224 pdf
 
PPT on Construction Costing
PPT on Construction CostingPPT on Construction Costing
PPT on Construction Costing
 
Wb consultant 4a
Wb consultant 4aWb consultant 4a
Wb consultant 4a
 
Ppv ppt
Ppv pptPpv ppt
Ppv ppt
 
Contract costing
Contract costingContract costing
Contract costing
 
Guide_for_Determining_Adequacy_of_Contractor_Incurred_Cost_Proposal
Guide_for_Determining_Adequacy_of_Contractor_Incurred_Cost_ProposalGuide_for_Determining_Adequacy_of_Contractor_Incurred_Cost_Proposal
Guide_for_Determining_Adequacy_of_Contractor_Incurred_Cost_Proposal
 
ESTIMATING AND COSTING
ESTIMATING AND COSTINGESTIMATING AND COSTING
ESTIMATING AND COSTING
 
Contract monitoring & evaluation
Contract monitoring & evaluationContract monitoring & evaluation
Contract monitoring & evaluation
 
Purpose and importance of estimate
Purpose and importance of estimatePurpose and importance of estimate
Purpose and importance of estimate
 
Estimation and Costing
Estimation and CostingEstimation and Costing
Estimation and Costing
 
Sample cost control training proposal
Sample cost control training proposalSample cost control training proposal
Sample cost control training proposal
 
Rate analysis brief
Rate analysis briefRate analysis brief
Rate analysis brief
 
Cost Engineering Introduction
Cost Engineering IntroductionCost Engineering Introduction
Cost Engineering Introduction
 
1 regatta quay rehab boq 20120420 blank
1 regatta quay rehab boq 20120420 blank 1 regatta quay rehab boq 20120420 blank
1 regatta quay rehab boq 20120420 blank
 
Tenders contract -arti
Tenders contract -artiTenders contract -arti
Tenders contract -arti
 
Contract Costing
Contract CostingContract Costing
Contract Costing
 
Approximate estimate
Approximate estimateApproximate estimate
Approximate estimate
 
Project cost stimating
Project cost stimatingProject cost stimating
Project cost stimating
 
5. cost estimation
5. cost estimation5. cost estimation
5. cost estimation
 

Viewers also liked

Wind Energy in the southern Mediterranean, the case of Egypt
Wind Energy in the southern Mediterranean, the case of EgyptWind Energy in the southern Mediterranean, the case of Egypt
Wind Energy in the southern Mediterranean, the case of EgyptPARIS
 
Control scheme for a stand alone wind energy convertion system
Control scheme for a stand alone wind energy convertion systemControl scheme for a stand alone wind energy convertion system
Control scheme for a stand alone wind energy convertion systemshashank chelpuri
 
Presentation on Solar energy, Wind energy and Nuclear energy.
Presentation on Solar energy, Wind energy and Nuclear energy.Presentation on Solar energy, Wind energy and Nuclear energy.
Presentation on Solar energy, Wind energy and Nuclear energy.Ishan Trivedi
 
Overview of Wind Energy
Overview of Wind EnergyOverview of Wind Energy
Overview of Wind EnergyJerilene
 
wind energy Seminar
 wind energy Seminar wind energy Seminar
wind energy Seminarashine288
 
Wind Power Point Presentation
Wind Power Point PresentationWind Power Point Presentation
Wind Power Point PresentationKurt Kublbeck
 

Viewers also liked (9)

Wind Energy in the southern Mediterranean, the case of Egypt
Wind Energy in the southern Mediterranean, the case of EgyptWind Energy in the southern Mediterranean, the case of Egypt
Wind Energy in the southern Mediterranean, the case of Egypt
 
Wind power
Wind powerWind power
Wind power
 
Control scheme for a stand alone wind energy convertion system
Control scheme for a stand alone wind energy convertion systemControl scheme for a stand alone wind energy convertion system
Control scheme for a stand alone wind energy convertion system
 
Presentation on Solar energy, Wind energy and Nuclear energy.
Presentation on Solar energy, Wind energy and Nuclear energy.Presentation on Solar energy, Wind energy and Nuclear energy.
Presentation on Solar energy, Wind energy and Nuclear energy.
 
Overview of Wind Energy
Overview of Wind EnergyOverview of Wind Energy
Overview of Wind Energy
 
wind energy Seminar
 wind energy Seminar wind energy Seminar
wind energy Seminar
 
Wind energy basics
Wind energy basicsWind energy basics
Wind energy basics
 
Wind Power Point Presentation
Wind Power Point PresentationWind Power Point Presentation
Wind Power Point Presentation
 
Wind Energy
Wind EnergyWind Energy
Wind Energy
 

Similar to Technical and financial_evaluation

Mechanisms to implement wind energy projects “egyptian experience”
Mechanisms to implement wind energy projects “egyptian experience”Mechanisms to implement wind energy projects “egyptian experience”
Mechanisms to implement wind energy projects “egyptian experience”RCREEE
 
Measurement 4:presentation slides
Measurement 4:presentation slidesMeasurement 4:presentation slides
Measurement 4:presentation slides마 이환
 
SPECS-Guidelines-Presentation.pdf
SPECS-Guidelines-Presentation.pdfSPECS-Guidelines-Presentation.pdf
SPECS-Guidelines-Presentation.pdfApoorvaR18
 
Session 18 tender preparation & evaluation
Session 18   tender preparation & evaluationSession 18   tender preparation & evaluation
Session 18 tender preparation & evaluationChirag Jain
 
Ntpc limited development of 750 mw( 6 x125 mw each )
Ntpc limited  development of 750 mw( 6 x125 mw each )Ntpc limited  development of 750 mw( 6 x125 mw each )
Ntpc limited development of 750 mw( 6 x125 mw each )Lawrence George
 
2021-10-13 Procurement Process-Day 01.pptx
2021-10-13 Procurement Process-Day 01.pptx2021-10-13 Procurement Process-Day 01.pptx
2021-10-13 Procurement Process-Day 01.pptxRiazMuhammad35
 
1 ITT- PG3.ppt
1 ITT- PG3.ppt1 ITT- PG3.ppt
1 ITT- PG3.pptHumayun29
 
Definitions Tamil nadu tenders act.pptx
Definitions Tamil nadu tenders act.pptxDefinitions Tamil nadu tenders act.pptx
Definitions Tamil nadu tenders act.pptxPradeep513562
 
HNSciCloud Info Day, 7 Sept 2016, Request for Tenders Presentation by Christo...
HNSciCloud Info Day, 7 Sept 2016, Request for Tenders Presentation by Christo...HNSciCloud Info Day, 7 Sept 2016, Request for Tenders Presentation by Christo...
HNSciCloud Info Day, 7 Sept 2016, Request for Tenders Presentation by Christo...Helix Nebula The Science Cloud
 
Procurement of goods , GFR provisions
Procurement of goods , GFR provisionsProcurement of goods , GFR provisions
Procurement of goods , GFR provisionsAvinash Kumar Gupta
 
Tendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final DraftTendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final DraftMuneesh Methwani
 
Rf s for supply of 5000 mw of round the-clock power - re + thermal power
Rf s for supply of 5000 mw of round the-clock power - re + thermal powerRf s for supply of 5000 mw of round the-clock power - re + thermal power
Rf s for supply of 5000 mw of round the-clock power - re + thermal powerPratap Malempati
 

Similar to Technical and financial_evaluation (20)

Mechanisms to implement wind energy projects “egyptian experience”
Mechanisms to implement wind energy projects “egyptian experience”Mechanisms to implement wind energy projects “egyptian experience”
Mechanisms to implement wind energy projects “egyptian experience”
 
Tendering process cvc_guidelines
Tendering process cvc_guidelinesTendering process cvc_guidelines
Tendering process cvc_guidelines
 
Final tender chp
Final tender chpFinal tender chp
Final tender chp
 
Measurement 4:presentation slides
Measurement 4:presentation slidesMeasurement 4:presentation slides
Measurement 4:presentation slides
 
SPECS-Guidelines-Presentation.pdf
SPECS-Guidelines-Presentation.pdfSPECS-Guidelines-Presentation.pdf
SPECS-Guidelines-Presentation.pdf
 
Session 18 tender preparation & evaluation
Session 18   tender preparation & evaluationSession 18   tender preparation & evaluation
Session 18 tender preparation & evaluation
 
Ntpc limited development of 750 mw( 6 x125 mw each )
Ntpc limited  development of 750 mw( 6 x125 mw each )Ntpc limited  development of 750 mw( 6 x125 mw each )
Ntpc limited development of 750 mw( 6 x125 mw each )
 
Tanmay presentation
Tanmay presentationTanmay presentation
Tanmay presentation
 
2021-10-13 Procurement Process-Day 01.pptx
2021-10-13 Procurement Process-Day 01.pptx2021-10-13 Procurement Process-Day 01.pptx
2021-10-13 Procurement Process-Day 01.pptx
 
1 ITT- PG3.ppt
1 ITT- PG3.ppt1 ITT- PG3.ppt
1 ITT- PG3.ppt
 
Definitions Tamil nadu tenders act.pptx
Definitions Tamil nadu tenders act.pptxDefinitions Tamil nadu tenders act.pptx
Definitions Tamil nadu tenders act.pptx
 
Tenders
TendersTenders
Tenders
 
TBCB_29032019.pptx
TBCB_29032019.pptxTBCB_29032019.pptx
TBCB_29032019.pptx
 
Tender document latest boiler
Tender document latest boilerTender document latest boiler
Tender document latest boiler
 
Chapter 2 [compatibility mode]
Chapter 2 [compatibility mode]Chapter 2 [compatibility mode]
Chapter 2 [compatibility mode]
 
Chapter 2 [compatibility mode]
Chapter 2 [compatibility mode]Chapter 2 [compatibility mode]
Chapter 2 [compatibility mode]
 
HNSciCloud Info Day, 7 Sept 2016, Request for Tenders Presentation by Christo...
HNSciCloud Info Day, 7 Sept 2016, Request for Tenders Presentation by Christo...HNSciCloud Info Day, 7 Sept 2016, Request for Tenders Presentation by Christo...
HNSciCloud Info Day, 7 Sept 2016, Request for Tenders Presentation by Christo...
 
Procurement of goods , GFR provisions
Procurement of goods , GFR provisionsProcurement of goods , GFR provisions
Procurement of goods , GFR provisions
 
Tendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final DraftTendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final Draft
 
Rf s for supply of 5000 mw of round the-clock power - re + thermal power
Rf s for supply of 5000 mw of round the-clock power - re + thermal powerRf s for supply of 5000 mw of round the-clock power - re + thermal power
Rf s for supply of 5000 mw of round the-clock power - re + thermal power
 

More from RCREEE

Gender challenges in clean energy sector can network
Gender challenges in clean energy sector can networkGender challenges in clean energy sector can network
Gender challenges in clean energy sector can networkRCREEE
 
Climate and energy policies advocacy of youth in the arab world
Climate and energy policies advocacy of youth in the arab worldClimate and energy policies advocacy of youth in the arab world
Climate and energy policies advocacy of youth in the arab worldRCREEE
 
Women in energy a world full of opportunities lcec
Women in energy a world full of opportunities  lcecWomen in energy a world full of opportunities  lcec
Women in energy a world full of opportunities lcecRCREEE
 
Women and sustainability in green mind
Women and sustainability in green mindWomen and sustainability in green mind
Women and sustainability in green mindRCREEE
 
Energy entrepreneurship artik energy
Energy entrepreneurship  artik energyEnergy entrepreneurship  artik energy
Energy entrepreneurship artik energyRCREEE
 
The women behind ewb kuwait
The women behind ewb kuwaitThe women behind ewb kuwait
The women behind ewb kuwaitRCREEE
 
Women in Energy in Jordan Challenges, Opportunities and the Way Forward JREEE...
Women in Energy in Jordan Challenges, Opportunities and the Way Forward JREEE...Women in Energy in Jordan Challenges, Opportunities and the Way Forward JREEE...
Women in Energy in Jordan Challenges, Opportunities and the Way Forward JREEE...RCREEE
 
Women in energy sector in the mena region rcreee
Women in energy sector in the mena region rcreeeWomen in energy sector in the mena region rcreee
Women in energy sector in the mena region rcreeeRCREEE
 
Awakening diversity in the clean energy sector a key point to achieve sustai...
Awakening diversity in the clean energy sector  a key point to achieve sustai...Awakening diversity in the clean energy sector  a key point to achieve sustai...
Awakening diversity in the clean energy sector a key point to achieve sustai...RCREEE
 
Mitigating environmental impact in non renewable energy the role of women
Mitigating environmental impact in non renewable energy the role of womenMitigating environmental impact in non renewable energy the role of women
Mitigating environmental impact in non renewable energy the role of womenRCREEE
 
HLPD in Vienna_Key Messages
HLPD in Vienna_Key MessagesHLPD in Vienna_Key Messages
HLPD in Vienna_Key MessagesRCREEE
 
HLPD_Setting the scene
HLPD_Setting the sceneHLPD_Setting the scene
HLPD_Setting the sceneRCREEE
 
EU-Egypt Energy Cooperation: A successful model
EU-Egypt Energy Cooperation: A successful modelEU-Egypt Energy Cooperation: A successful model
EU-Egypt Energy Cooperation: A successful modelRCREEE
 
EU sustainable development policies& cooperation
EU sustainable development policies& cooperationEU sustainable development policies& cooperation
EU sustainable development policies& cooperationRCREEE
 
EU support to the Energy sector in Jordan
EU support to the Energy sector in JordanEU support to the Energy sector in Jordan
EU support to the Energy sector in JordanRCREEE
 
Global Energy Interconnection Enhances Renewable Energy Development & Regiona...
Global Energy Interconnection Enhances Renewable Energy Development & Regiona...Global Energy Interconnection Enhances Renewable Energy Development & Regiona...
Global Energy Interconnection Enhances Renewable Energy Development & Regiona...RCREEE
 
Netherlands Support to Sustainable Arab Development
Netherlands Support to Sustainable Arab DevelopmentNetherlands Support to Sustainable Arab Development
Netherlands Support to Sustainable Arab DevelopmentRCREEE
 
Report summary on Intended Nationnally determined contributions -Comprehensiv...
Report summary on Intended Nationnally determined contributions -Comprehensiv...Report summary on Intended Nationnally determined contributions -Comprehensiv...
Report summary on Intended Nationnally determined contributions -Comprehensiv...RCREEE
 
Energy productivity as a new paradigm for sustainable energy transitions
Energy productivity as a new paradigm for sustainable energy transitionsEnergy productivity as a new paradigm for sustainable energy transitions
Energy productivity as a new paradigm for sustainable energy transitionsRCREEE
 
Arab Region Progress in Sustainable Energy Challenges and Opportunities
Arab Region Progress in Sustainable Energy Challenges and OpportunitiesArab Region Progress in Sustainable Energy Challenges and Opportunities
Arab Region Progress in Sustainable Energy Challenges and OpportunitiesRCREEE
 

More from RCREEE (20)

Gender challenges in clean energy sector can network
Gender challenges in clean energy sector can networkGender challenges in clean energy sector can network
Gender challenges in clean energy sector can network
 
Climate and energy policies advocacy of youth in the arab world
Climate and energy policies advocacy of youth in the arab worldClimate and energy policies advocacy of youth in the arab world
Climate and energy policies advocacy of youth in the arab world
 
Women in energy a world full of opportunities lcec
Women in energy a world full of opportunities  lcecWomen in energy a world full of opportunities  lcec
Women in energy a world full of opportunities lcec
 
Women and sustainability in green mind
Women and sustainability in green mindWomen and sustainability in green mind
Women and sustainability in green mind
 
Energy entrepreneurship artik energy
Energy entrepreneurship  artik energyEnergy entrepreneurship  artik energy
Energy entrepreneurship artik energy
 
The women behind ewb kuwait
The women behind ewb kuwaitThe women behind ewb kuwait
The women behind ewb kuwait
 
Women in Energy in Jordan Challenges, Opportunities and the Way Forward JREEE...
Women in Energy in Jordan Challenges, Opportunities and the Way Forward JREEE...Women in Energy in Jordan Challenges, Opportunities and the Way Forward JREEE...
Women in Energy in Jordan Challenges, Opportunities and the Way Forward JREEE...
 
Women in energy sector in the mena region rcreee
Women in energy sector in the mena region rcreeeWomen in energy sector in the mena region rcreee
Women in energy sector in the mena region rcreee
 
Awakening diversity in the clean energy sector a key point to achieve sustai...
Awakening diversity in the clean energy sector  a key point to achieve sustai...Awakening diversity in the clean energy sector  a key point to achieve sustai...
Awakening diversity in the clean energy sector a key point to achieve sustai...
 
Mitigating environmental impact in non renewable energy the role of women
Mitigating environmental impact in non renewable energy the role of womenMitigating environmental impact in non renewable energy the role of women
Mitigating environmental impact in non renewable energy the role of women
 
HLPD in Vienna_Key Messages
HLPD in Vienna_Key MessagesHLPD in Vienna_Key Messages
HLPD in Vienna_Key Messages
 
HLPD_Setting the scene
HLPD_Setting the sceneHLPD_Setting the scene
HLPD_Setting the scene
 
EU-Egypt Energy Cooperation: A successful model
EU-Egypt Energy Cooperation: A successful modelEU-Egypt Energy Cooperation: A successful model
EU-Egypt Energy Cooperation: A successful model
 
EU sustainable development policies& cooperation
EU sustainable development policies& cooperationEU sustainable development policies& cooperation
EU sustainable development policies& cooperation
 
EU support to the Energy sector in Jordan
EU support to the Energy sector in JordanEU support to the Energy sector in Jordan
EU support to the Energy sector in Jordan
 
Global Energy Interconnection Enhances Renewable Energy Development & Regiona...
Global Energy Interconnection Enhances Renewable Energy Development & Regiona...Global Energy Interconnection Enhances Renewable Energy Development & Regiona...
Global Energy Interconnection Enhances Renewable Energy Development & Regiona...
 
Netherlands Support to Sustainable Arab Development
Netherlands Support to Sustainable Arab DevelopmentNetherlands Support to Sustainable Arab Development
Netherlands Support to Sustainable Arab Development
 
Report summary on Intended Nationnally determined contributions -Comprehensiv...
Report summary on Intended Nationnally determined contributions -Comprehensiv...Report summary on Intended Nationnally determined contributions -Comprehensiv...
Report summary on Intended Nationnally determined contributions -Comprehensiv...
 
Energy productivity as a new paradigm for sustainable energy transitions
Energy productivity as a new paradigm for sustainable energy transitionsEnergy productivity as a new paradigm for sustainable energy transitions
Energy productivity as a new paradigm for sustainable energy transitions
 
Arab Region Progress in Sustainable Energy Challenges and Opportunities
Arab Region Progress in Sustainable Energy Challenges and OpportunitiesArab Region Progress in Sustainable Energy Challenges and Opportunities
Arab Region Progress in Sustainable Energy Challenges and Opportunities
 

Technical and financial_evaluation

  • 1. Arab Republic of Egypt Ministry of Electricity & Energy New and Renewable Energy Authority“ NREA Technical and Financial Evaluation Prepared By Dr. sabry M. Aly Mokhymar Octber
  • 2. Technical and Financial Evaluation Tender Invitation Opening The Technical Specification Documents Verification from Tender Documents TDs contents Technical evaluation for the submitted TDs Opening The Financial Documents Financial evaluation for the submitted TDs Evaluation Methods
  • 3. Technical and Financial Evaluation . Tender Invitation: There are two way for tender invitation or its announcements as: st way (With Prequalification _PQ): NREA announce at the local and international newspaper to recall the Pre- Qualification (PQ)'s documentation of the companies which could share in the project's competition. In the announcement it must be clear the final date to submit all of the PQ documents and the final date to open the tender's envelops. After tender opening the technical and financial evaluation for the prequalification documents should be started. after finish the evaluation and selection of the qualified companies, NREA should send a circular letters to the selected companies. Also, NREA invite the qualified companies to buy TD from the NREA premises to prepare and submit its TD for the nominated wind project. In the instruction to the tenderers' there are the final date to submit TD and its opening date. The qualified companies must submit two TD the st one is the technical documents and the nd one is the financial documents where the last one shouldn't be opened except for the successful technical documentation.
  • 4. . Tender Invitation (contd.) nd way (Without Prequalification _PQ): The same procedure as the st way but without submit PQ i.e. every company just submit its TD for implementation a wind farm capacity ( ) MW with a nominated Wind turbines technology as pitch or active pitch…etc.
  • 5. . Opening The Technical Specification Documents: A technical evaluation's committee should be hold to nominate the successful technical tender. Technical Tender should be opening In the specific date or day in the attendance with the companies' representatives. The committee must sure from some documents as (letter of guarantee and its value). An institutional or legal document must be documented and singed from each representative.
  • 6. . Verification from TD contents A Verification to the TD documents according to its instructions: The committee must be sure from the completeness for all of TD specially letter of guarantee and letter of interest. All of the companies must obey the instruction of TD but if any company can't obey These instructions, it should be rejected. The next point must be check also:
  • 7. . Verification from TD contents (contd.) Completeness for all of TD Every paper must be singed and stamped TD include the letter of Guarantee with its nominated value and letter of interest Ready for any clarification or any comments form NREA. Verification from the next documents:
  • 8. . Verification from TD contents (contd.) Demand Documentations to be Submitted With the Offers: Company's or contractor's organization chart. Project's organization chart for the total period of project's time schedule including the responsibilities for each person and his CV's. List of components which could be manufactured in Egypt. Financial Status for each company or contractor Describe the contractor's experience specially for the same projects
  • 9. . Verification from TD contents (contd.) Demand Documentations to be Submitted With the Offers (contd.) : Spread sheet including the number of WECS with the model in the TD with a specific numbers should be implemented for a period as one or two years tell the dated of submission for TD. Or a specific spread sheet for the WEC's major components eg. (Gearbox- generators, high speed shaft…etcs) with a specific numbers should be implemented for a period as one or two years before the submission of TD WEC's Type certificate or its equivalent (eg. Design certificate, proto type test report, or other…etc) with IEC code and it must be verified and signed from GL or any from its equivalent international institutions
  • 10. . Verification from TD contents (contd.) Demand Documentations to be Submitted With the Offers (contd.) : • Quality assurance certificate List of Codes and Standards Noise level characteristics for the submitted WECs. Mechanism for clean or dust elimination. List for all of the components with the specific life time Agreement for Guaranteed availability not less than through the guarantee period Annual energy production's calculations for the wind farm Proposed Wind Farm Lay Out Guaranteed Power Curve for the submitted WECs
  • 11. . Verification from TD contents (contd.) Demand Documentations to be Submitted With the Offers (contd.) : Protection Procedures for all of the components from any Electrical shocks List for the proposed spare parts List for the proposed tools and instrumentations for work shops Planning for acceptance certificates' tests for the manufacturers including list with its tasks according to the acceptance test. Proposed Training program in Egypt or at company
  • 12. . Verification from TD contents (contd.) Demand Documentations to be Submitted With the Offers (contd.) : After sale services Description for CMS (control monitoring system) Work Plan and Time schedule Proposed plane for project implementation Components origin and data about the factory which the components are manufactured or assembly inside it
  • 13. . Technical evaluation for the submitted TDs : Analyze and evaluate the technical points and its demands with the nominated specifications for TD. We must be sure from any wrong not accept with the technical demands or sure from any deviations for the technical specification and get a clarification for it if any. Analyze and evaluate for programs of the training and the inspection or commissioning 's in Egypt or outside of Egypt. Check the availability and logic of time schedule Check the spare parts and its availability in the local market Check and verify the Annual energy production's calculations for the wind farm for each company The final result should be as (yes for technically accepted companies & no for technically rejected companies)
  • 14. . Opening The Financial Documents: NREA should open the financial documentation for just the accepted technical tender. A financial evaluation's committee should be hold to nominate the successful financial tender. The financial tender should be opening In the specific date or day in the attendance with the companies' representatives, where every value of each tender should be announced in the same time. An institutional or legal document must be documented and singed from each representative.
  • 15. . Financial evaluation for the submitted TDs : Calculation adjustments The committee must check the prices schedules for each company with correction for any wrong calculations if any Financial Check for each TDs Check for every items' price and if any item is not found i.e there is no evaluation for this item, so the highest price for this item form the other offers should be added for this company at the nominated schedule. And recalculate its contract price according to the modified total price.
  • 16. Evaluation Methods Financial evaluation methods There are tow methods to get this evaluation: st method: according to the annual energy for each company as: we must calculate the value of the next equation =
  • 17. Evaluation Methods (Contd.) Where En: meaning the annual generated energy from the offer (n) Emax : meaning the maximum annual generated energy from the offers The final arrangement for the offers should be as the next equation: Tender Price Evaluated = TD price Kn The highest the level (the winner) The lower price is found.
  • 18. Evaluation Methods (Contd.) The nd method After adjustment for all calculations and final review for the financial offers the next procedures should be done: calculated the total annual energy for each offer calculated the KWH price for years or years according to the life time of the wind farm The highest the level (the winner) The lower price for KWH is found