Name of coordinating beneficiary (CO): Veiligheidsregio Zuid-Holland Zuid (Safety Region South-Holland South), NETHERLANDS

Name of associated beneficiary (AB1): Municipality of Mirandela, PORTUGAL

Name of associated beneficiary (AB2): Municipality of Aveiro, PORTUGAL

Name of associated beneficiary (AB3): Tallinn City Government, ESTONIA

Name of associated beneficiary (AB4): Stara Zagora Regional Economic Development Agency (SZREDA), BULGARIA

Publié dans : Business
  • Soyez le premier à commenter

  • Soyez le premier à aimer ceci

Promoting and Implementing Strategies for risk Management and Assessment PRISMA

  1. 1. PRISMAPromoting and implementing strategies for risk management and assessment Kick-off meeting ECHO Brussels, January 17th 2013 Nico van Os / Tim te Pas
  2. 2. The project partners
  3. 3. Duration & budget• Duration: 18 months• from 01/01/2013 to 30/06/2014• Estimated eligible costs : €652.298,-• Max. contribution EU : €489.224,-
  4. 4. 5 risks to mitigate
  5. 5. The project objectives1. Testing MiSRaR’s cross-sectoral implementation of the risk management strategies2. Promoting risk management and knowledge exchange on risk assessment and risk management
  6. 6. Deliverables & deadlinesEach partner will make a:1. Stakeholder assessment 1-3-20132. Declaration of principles 1-4-20133. Risk assessment report 1-9-20134. Policy memorandum on risk management strategy 1-1-20145. Risk management plan 1-3-2014
  7. 7. Deliverables & deadlinesMeetings:1. Kick-off meeting (29 & 30 January 2013)2. 4 Partner advice and counseling meetings (2013-1 / 2013-5 /2013-9 / 2014-1)3. Meetings with local partners (5 x 6)4. Steering committee (2013-1 / 2013-9)5. Project evaluation meeting (2014/6)