21. NEXT STEPS
JUNE LIBRARY BOARD MEETING:
Presentation of comments and recommendations by LEED Commissioning Agent
Written review comments on the Building and Site Design Development submittal given to the
Design Team by the Owner:
DPW
Library
BREC
LEED CxA
Presentation and Submittal of Design Development Documents for Independence Plaza and Service
Yard (Shared Work) by the Design Team
BEYOND THE JUNE BOARD MEETING:
Design Team meets with DPW, Library, BREC, and LEED CxA to review comments
Construction Documents Phase begins with the incorporation of review comments into the design
Written review comments on the Plaza and Service Yard Design Development submittal given to the
Design Team by July 1st by the Owner:
DPW
Library
BREC
LEED CxA
Finalize Scope of Work and Opinion of Probable Cost
Leadership Team Meetings
Develop Add Alternates for Bidding
NEXT STEPS