SlideShare a Scribd company logo
1 of 27
Download to read offline
N YSE Am ex : UR G         TSX : UR E



                          Ur-Energy is an Advanced Pre-Production
                                  Junior Mining Company
                            Focused on development of low-cost
                            uranium production properties in the
                                      United States.
                                           Corporate Objectives:
                                           • Low Cost U.S. Uranium Production
                                           • Resource Growth
                                           • Strategic Opportunities




Corporate P resentation
Decem ber 2011
Disclaimer
This presentation contains “forward-looking statements,” within the meaning of applicable securities laws, regarding events or conditions that may occur
in the future. Such statements include without limitation the long term effects on the uranium market of events in Japan in 2011 including supply and
demand projection; the Company’s timeframe for events leading to and culminating in the commencement of production at Lost Creek; the technical
and economic viability of the Lost Creek Project (including the projections contained in the preliminary analysis of economics of the Lost Creek Project);
receipt of (and related timing of) Record of Decision from the U.S. Bureau of Land Management, and all other necessary permits related to the Lost
Creek Project; the Lost Creek Project will advance to production and the production timeline; production rates, timetables and methods of recovery at
the Lost Creek Project; the Company’s procurement and construction plans at the Lost Creek Project; the ability to complete additional favorable
uranium sales agreements; the potential of exploration targets on the LC North and LC South and on the Lost Creek Project area outside the current
Lost Creek resource area; and the further exploration, development and permitting of exploration projects including Lost Soldier, the exploration
properties in Nebraska, and Screech Lake. With regard to discussion of the potential of exploration targets, at LC North, LC South and on the Lost
Creek Project outside the current resource area, it should be noted that there has been insufficient exploration yet to define a mineral resource at these
exploration targets. Further, it is uncertain if additional exploration will result in the exploration targets being delineated as a mineral resource. These
statements are based on current expectations that, while considered reasonable by management at this time, inherently involve a number of significant
business, economic and competitive risks, uncertainties and contingencies. Numerous factors could cause actual events to differ materially from those
in the forward-looking statements. Factors that could cause such differences, without limiting the generality of the following, include: risks inherent in
exploration activities; volatility and sensitivity to market prices for uranium; volatility and sensitivity to capital market fluctuations; the impact of
exploration competition; the ability to raise funds through private or public equity financings; imprecision in resource and reserve estimates;
environmental and safety risks including increased regulatory burdens; unexpected geological or hydrological conditions; a possible deterioration in
political support for nuclear energy; changes in government regulations and policies, including trade laws and policies; demand for nuclear power;
weather and other natural phenomena; delays in obtaining or failures to obtain required governmental, environmental or other project approvals; and
other exploration, development, operating, financial market and regulatory risks. Although Ur-Energy Inc. believes that the assumptions inherent in the
forward-looking statements are reasonable, undue reliance should not be placed on these statements, which only apply as of the date of this
presentation. Ur-Energy Inc. disclaims any intention or obligation to update or revise any forward-looking statement, whether as a result of new
information, future events or otherwise.

Cautionary Note Regarding Projections: Similarly, this presentation also may contain projections relating to an extended future period and,
accordingly, the estimates and assumptions underlying the projections are inherently highly uncertain, based on events that have not taken place, and
are subject to significant economic, financial, regulatory, competitive and other uncertainties and contingencies beyond the control of Ur-Energy Inc.
Further, given the nature of the Company's business and industry that is subject to a number of significant risk factors, there can be no assurance that
the projections can be or will be realized. It is probable that the actual results and outcomes will differ, possibly materially, from those projected.

The attention of investors is drawn to the Risk Factors set out in the Company's Annual Information Form and Annual Report on Form 40-F, dated
March 17, 2011, which are filed, respectively, with the regulatory authorities in Canada on SEDAR and with the U.S. Securities and Exchange
Commission on EDGAR. (www.sedar.com and http://www.sec.gov/edgar.shtml)

Cautionary Note to U.S. Investors Concerning Estimates of Measured, Indicated or Inferred Resources: the information presented uses the
terms "measured", "indicated" and "inferred" mineral resources. United States investors are advised that while such terms are recognized and required
by Canadian regulations, the United States Securities and Exchange Commission does not recognize these terms. United States investors are
cautioned not to assume that all or any part of measured or indicated mineral resources will ever be converted into mineral reserves. United States
investors are also cautioned not to assume that all or any part of an inferred mineral resource exists, or is economically or legally minable.

John Cooper, SME Registered Member, a Professional Geologist, and Qualified Person as defined by National Instrument 43-101, reviewed
the technical information contained in this presentation.



                                                                          2                  N YSE Am ex : UR G                         TSX : UR E
Ur-Energy At A Glance
   Advanced Pre-Production Project at Lost Creek, Wyoming
          4-Years invested in the regulatory process
          One approval remaining

   Low-Cost Uranium Production Center that will be Cash-Flow
   Positive in Current Market

   Expanding Resources through Exploration and Acquisition

   Low Technical, Political and Regulatory Risk Strategy




See Disclaimer re Forward-looking Statements and Projections (slide 2)



                                                                         3   N YSE Am ex : UR G   TSX : UR E
Ur-Energy’s Market Position
Share Capital & Cash Position
                                                         NYSE Amex: URG
As of 10/24/11
Shares Outstanding                  103.7M
Stock Options & RSUs                  6.5M
Fully Diluted                       110.2M

Market Cap (12/14/11)               C$96.4M

Cash (09/30/11)                     C$28.8M
Debt                                   $0
Cash per share (09/30/11)   ~C$0.30
Share price (12/14/11)        C$0.92                     TSX: URE
52 Week Range           C$.75 - $3.35
Avg. Daily Volume           ~560,000
(3-mo URG & URE 12/14/11)

Member of Russell 3000 & 2000 and S&P/TSX SmallCap
Indexes

Geographical Distribution as of 6/30/11
United States         ~48%
Canada                ~38%
Other                 ~14%

                                                     4        N YSE Am ex : UR G   TSX : UR E
Analyst Coverage

United States
GVC Capital                             Mike Shonstrom (Denver, CO)                      1 303-321-2392
Rodman & Renshaw                        Wayne Atwell (New York, NY)                      1 212-356-0513

Canada
Dundee Securities                       David A. Talbot (Toronto, ON)                     1   416-350-3082
Haywood Securities                      Geordie Mark (Vancouver, BC)                      1   604-697-6112
Raymond James                           Bart Jaworski (Vancouver, BC)                     1   604-659-8282
RBC Capital                             Adam Schatzker (Toronto, ON)                      1   416-842-7850

Australia
Resource Capital Research               Trent Allen (Sydney, NSW)                         61 2-9252-9405




Ur-Energy Inc is followed by the analysts listed above. This list, including the firms and individual analysts at these firms,
is subject to change at any time without notice. Please note that any opinions, estimates, forecasts, conclusions or
recommendations regarding Ur-Energy Inc's performance made by these analysts are theirs alone and do not represent
opinions, estimates, forecasts, conclusions, recommendations or predictions of Ur-Energy Inc or its management. Ur-
Energy Inc does not by its reference above or in any other manner imply its endorsement of or concurrence with such
information, conclusions or recommendations.




                                                         5                N YSE Am ex : UR G                     TSX : UR E
The US Uranium Market
      The US produces ~ 4M lbs of uranium/yr1
      The US consumes 55M lbs of uranium/yr1 contributing 20% of US electricity
      In 2010, the 10-year forward cumulative unfilled uranium requirement of US
      utilities was 274M lbs2
      Ur-Energy is well positioned to capitalize on this opportunity




                                                         Chart from U.S . Energy Information Administration
 1 – Northwest Mining Association
 2 – U.S. Energy Information Administration
See Disclaimer re Forward-looking Statements and Projections (slide 2)


                                                                            6                   N YSE Am ex : UR G   TSX : UR E
Post-Fukushima Nuclear Remains Positive*

        HEU Agreement to expire 2013
               Provides 13% of world and 45% of US annual supply

        63 reactors remain under construction

        Russia, China and India represent 50% of new builds and have
        reaffirmed support for nuclear power

        Saudi Arabia & the United Kingdom have announced plans to build
        24 new reactors combined

        October 2011 Nuclear Energy Institute survey shows two-thirds of
        Americans support nuclear energy



  *According to World Nuclear Association

  See Disclaimer re Forward-looking Statements and Projections (slide 2)


                                                                           7   N YSE Am ex : UR G   TSX : UR E
Growth of Nuclear Will Continue
                     Historically, growth of nuclear power continued despite major accidents
                     Growth expected to continue beyond Fukushima at 10 reactors per year
                                                                                                                  10 years, 10.2
                                                                                                                  reactors per
                                                                                                                  year
Number of Reactors




                                                                              22 years, 4
                                                                              reactors per
                                                                              year



                                                  8 years, 21.9
                                                  reactors per
                                                  year

                                                                                             Fukushima
                              13 years,
                              11.3reactors                         Chernobyl
                              per year
                                                          Three Mile Island




                     Source: W orld Nuclear Association                        See Disclaimer re Forward-looking Statements and Projections (slide 2)


                                                                       8              N YSE Am ex : UR G                           TSX : UR E
Supply/Demand Imbalance Grows
  How will supply be able to expand to the extent necessary to meet growing demand
  levels in the post Fukushima environment of uncertainty and low prices?

          More damage done to uranium supply than uranium demand
          HEU Program expires in 2013 with no extension being considered




Source: UxC Uranium M arket Outlook                See Disclaimer re Forward-looking Statements and Projections (slide 2)


                                            9             N YSE Am ex : UR G                           TSX : UR E
Experienced Management Team
                                     Board of Directors

                                        Ex ecutive Directors
      Wayne W. Heili, President & Chief Executive Officer (Metallurgical Engineer)
      Jeffrey T. Klenda*, Board Chairman, Executive Director (Mining Finance)

                                    Non-Ex ecutive Directors
      W. William Boberg*, Former President & CEO (Professional Geologist)
      James M. Franklin*, Chair-Technical Committee (Professional Geologist)
      Paul Macdonell*, Chair-Compensation and Corp. Governance & Nominating Committees
                       (Senior Federal Mediator)
      Thomas H. Parker, Chair-Audit Committee (Professional Engineer)

                                                Officers
      Roger L. Smith, Chief Financial Officer & Chief Administrative Officer(CPA & MBA)
      Steven M. Hatten, VP Operations (Mining Engineer)
      John W. Cash, VP Regulatory Affairs, Geology & Exploration (Geologist & Geophysicist)
      Penne A. Goplerud, Corporate Secretary & General Counsel (JD)

* Founding Directors




                                               10             N YSE Am ex : UR G              TSX : UR E
Industry Leading Team
Highly Experienced Technical and Management
Professionals

93 Years of Direct Uranium Production Experience
  ISR operations experience – Nebraska, Texas & Wyoming




                            11        N YSE Am ex : UR G   TSX : UR E
ISR – Low Impact Mining




     CAMECO Smith Ranch ISR Mine
      Powder River Basin, Wyoming


                 12       N YSE Am ex : UR G   TSX : UR E
In-Situ Recovery (ISR) Uranium Mining




                           Environmentally sound production method
                           Well understood by Wyoming state regulators
                           Cost effective, low capital costs
See Disclaimer re Forward-looking Statements and Projections (slide 2)


                                                                         13   N YSE Am ex : UR G   TSX : UR E
Ur-Energy’s Wyoming Projects




             14   N YSE Am ex : UR G   TSX : UR E
Lost Creek Property
Exploration targets within the Lost
Creek Project and adjoining projects
provide potential of additional
resources U3O8
Lost Creek Project – 4,254 acres
Adjoining Projects – 29,540 acres
Historic Drilling on Adjoining Projects
     Multiple roll fronts defined by
     725 drill holes
     50-60 mineralized holes on LC
        Property with grades similar to
        Lost Creek resource
Additional drilling of 2000-3000 holes
recommended at a cost of US$15M -
20M (~US$7,500/hole)
                                                                    These exploration targets are conceptual in nature. There has been insufficient
                                                                    exploration to define a mineral resource outside the current Lost Creek
See Disclaimer re Forward-looking Statements and Projections        resource. It is uncertain if further exploration will result in the new target areas
(slide 2)                                                           outside the Lost Creek resource being delineated as a mineral resource.



                                                               15                   N YSE Am ex : UR G                                 TSX : UR E
Lost Creek

Rio Tinto Sweetwater Mill – 3 miles south
 (NRC Licensed Conventional Uranium Mill on Standby)




                                                                    JK


                                            NYSE Amex: URG   TSX: URE
Lost Creek Project – Moving Towards Production
       Discovered in the1970s
               563 drill holes                                      Leach Efficiency -    80%
                                                                    Industry Avg. -      ~70%
       Ur- Energy: 2005-2010                                        (Recovery Rate)
               1,096 drill holes                                    Pump Test Results - >30-50gpm
               728,757 ft (222,125 meters)                          Industry Avg. -       15gpm
                                                                    (Good Porosity = Cost Savings)
       2011 Drilling program
              Discovery of ore grade
              mineralization within M & N
              horizons


     NI 43-101 Resource from Prelim inary Assessm ent Lost
     Creek Property Sw eetw ater County W yom ing – TR EC &
     Behre Dolbear (M arch 16, 2011) (posted on SEDAR )

     Measured – 2.54 Mt @ 0.052% (2.7 Mlbs eU3O8)
     Indicated – 2.2 Mt @ 0.060% (2.6 Mlbs eU3O8)
     Inferred – 0.77 Mt @0.051% (0.8 Mlbs eU3O8)
     * Based on grade cutoff of 0.02 percent eU3O8 and a grade x
     thickness cutoff of 0.3 GT.
  See Disclaimers (slide 2)



                                                               17   N YSE Am ex : UR G       TSX : UR E
Lost Creek Preliminary Assessment
       2011 PA* Confirms Robust Economics
              Estimates Operating Costs less than US$20 / lb
                       Lowest Quartile of all Uranium Producers

              Production Rate: 1M lbs U3O8 per year
              Estimates Total P roduction Cost at US$42.65/ lb
                       Includes capital recovery

              Project Internal Rate of Return (I RR ) at 91%
              Pre-Production Capital Costs of Only US$35M Rem aining
                       Lowest Quartile of all developing uranium production facilities
                       Includes 1M lb/yr plant, 2 disposal wells, initial wellfield and 10% contingency
                       Total project Capital Cost of US$59M

  Cautionary Statement: This PA is preliminary in nature, and includes inferred mineral resources that are considered too speculative geologically to have the
  economic considerations applied to them that would enable them to be categorized as mineral reserves. The estimated mineral recovery used in this PA is
  based on both site-specific laboratory recovery data as well as URE personnel and industry experience at similar facilities. There can be no assurance that
  recovery at this level will be achieved.
                                                                                   * N I 43-101 P relim inary Assessm ent Lost Creek P roperty Sw eetw ater
 See Disclaimer re Forward-looking Statements and Projections (slide 2)            County W yom ing – TR EC & Behre Dolbear (M arch 16, 2011)
                                                                                   (posted on SEDAR )



                                                                              18                    N YSE Am ex : UR G                            TSX : UR E
US$24M in CapEx Completed
 Mine Units 1 & 2 Delineated
     MU #1 Monitor Well Ring Completed

 Plant Engineering Completed

 Drilled and Tested Class I UIC
 Well

 Ordered Key Plant Equipment              Ur-Energy’s Ion Exchange Columns

     Ion Exchange Columns
     Elution Columns
     Filter Presses

 Design/Build of Header House
 Building



                                           Interior of Ur-Energy’s Prototype Header House

                                19       N YSE Am ex : UR G                TSX : UR E
Lost Creek Infrastructure Advantage
  Lost Creek Processing Plant
  Model = Cost Savings
     Expandable Resource Base
     No need for Satellite facilities

  Hub & Spoke (multi-Satellite)
  Model Not Preferred
     Permitting Intensive
     Capital Intensive
     Higher Operating Costs
     Requires Large Resource Base
     Additional Transportation Cost

  Common Development Requirements
     Production Permits
     On-site Recovery Plant
     Wastewater Disposal Capacity

                                                                  See Disclaimer (slide 2)

                                        20   N YSE Am ex : UR G        TSX : UR E
Lost Creek Path to Production
     Site Permitting Started in 2006
     Granted Licenses and Permits
             Wyoming DEQ Permit to Mine
             US NRC License
             WDEQ Class I UIC Permit (water disposal well)
             EPA Aquifer Exemption

       One Remaining Regulatory Approval Needed
             US Bureau of Land Management Plan of Operations
             Environmental review process underway
             Record of Decision anticipated to be complete early summer 2012

       Construction
              6 – 9 month build-out

       First Production
              Planned for second quarter 2013
See Disclaimer re Forward-looking Statements and Projections (slide 2)



                                                                         21   N YSE Am ex : UR G   TSX : UR E
Lost Soldier – 12.2M M&I lbs U3O8
     Can be licensed with NRC as
     amendment to Lost Creek
     license
    M & I resource average
    17.2 ft @ 0.065% U3O8
     Average 240 feet deep
     Leach efficiency 49% - 84%

 Over 3700 drill holes define deposit
 17 monitor/pump test wells installed

                                                                                   (From Figure 16-2, Technical Report on the Lost Soldier Project, Wyoming, C.
                                                                                   Stewart Wallis, RPA, July 10, 2006 - posted on SEDAR)

 NI 43-101 Compliant Resource
 Measured & Indicated (M & I) – 9.4 Mt @ 0.065% (12.2 Mlbs U3O8)
 Inferred – 1.6 Mt @0.055% (1.8 Mlbs U3O8)
  (Technical Report on the Lost Soldier Project, Wyoming, C. Stewart Wallis, Roscoe Postle Associates Inc., July 10, 2006 - Posted on SEDAR)

  See Disclaimer re Forward-looking Statements and Projections (slide 2)



                                                                              22                     N YSE Am ex : UR G                             TSX : UR E
Screech Lake, Thelon Basin, NWT
         Completed Audio-Magnetotelluric Geophysical Survey,
         and Soil Gas Hydrocarbon and Enzyme Leach Soil
         Geochemistry Analyses to Better Define Drill Target

                                                                                 MegaTEM Survey




      Screech
       Lake



 See Disclaimer re Forward-looking Statements and Projections (slide 2)              0            4
                                                                                         Kilometers
                                                                          23   N YSE Am ex : UR G     TSX : UR E
Ur-Energy’s Strong Position
       Advanced Development at Lost Creek
             Permitting Process Nearing Completion

       Low Cost Production Will Equal Strong Cash Flow
             ~US$20/lb direct operating cost
             Uranium Term Market is above $60/lb

       Uranium Friendly Mining Jurisdictions

       Experienced Technical & Managerial Team

       Strong Balance Sheet
               C$28.8Million (09/30/11)

See Disclaimer re Forward-looking Statements and Projections (slide 2)



                                                                         24   N YSE Am ex : UR G   TSX : UR E
Future Growth Opportunities
     Exploration Properties in Western Nebraska
     Resource Expansion through ongoing exploration efforts
           Increase Minable Resources that will be Accessible to the Lost
           Creek Processing Plant

     Growth in the Production Profile
           Development of Currently Held Properties
           Acquisitions of New Properties
           Strategic Alliances

     Monetizing Historic Databases


See Disclaimer re Forward-looking Statements and Projections (slide 2)



                                                                         25   N YSE Am ex : UR G   TSX : UR E
Ur-Energy – Right Now!
      Technical, Political and Regulatory Certainty

      Advanced Pre-Production Project at Lost Creek
             Low-Cost Uranium Production Center that will be Cash-Flow
             Positive in Today’s Market
             Plant Construction Planned to Begin Summer 2012
             Initial Production Rate of 1M lbs/year

      Signed Initial Long Term Uranium Sales Agreement
             De-Risking Company Exposure to Volatile Marketplace

      Re-Rating Likely as Ur-Energy nears Production


See Disclaimer re Forward-looking Statements and Projections (slide 2)



                                                                         26   N YSE Am ex : UR G   TSX : UR E
Ur-Energy - The Right People. The Right Projects. Right Now.
     For more information, please contact:
       Wayne Heili, President, Chief Executive Officer & Director
       Jeff Klenda, Board Chairman & Director
       Rich Boberg, Director of Public Relations


     By Mail:            Ur-Energy Corporate Office
                          10758 W. Centennial Rd., Ste. 200
                          Littleton, CO 80127 USA

     By Phone:           Office (720) 981-4588
                          Toll-Free (866) 981-4588
                          Fax (720) 981-5643

     By E-mail:          wayne.heili@ur-energyusa.com
                          jeff.klenda@ur-energyusa.com
                          rich.boberg@ur-energyusa.com




                                       27         NYSE Amex:: URG
                                                  N YSE Am ex UR G   TSX::URE
                                                                     TSX UR E

More Related Content

What's hot

Dalradian corporate presentation feb 5 2013_web
Dalradian corporate presentation feb 5 2013_webDalradian corporate presentation feb 5 2013_web
Dalradian corporate presentation feb 5 2013_web
DalradianResource
 
ROMARCO Corporate Presentation - October 2012
ROMARCO Corporate Presentation - October 2012ROMARCO Corporate Presentation - October 2012
ROMARCO Corporate Presentation - October 2012
Romarco Minerals Inc.
 
ROMARCO Corporate Presentation - NOVEMBER 2012
ROMARCO Corporate Presentation - NOVEMBER 2012ROMARCO Corporate Presentation - NOVEMBER 2012
ROMARCO Corporate Presentation - NOVEMBER 2012
Romarco Minerals Inc.
 
Ure corporate presentation final (final) 20140301
Ure corporate presentation final (final) 20140301Ure corporate presentation final (final) 20140301
Ure corporate presentation final (final) 20140301
Urenergy
 

What's hot (18)

Dalradian corporate presentation feb 5 2013_web
Dalradian corporate presentation feb 5 2013_webDalradian corporate presentation feb 5 2013_web
Dalradian corporate presentation feb 5 2013_web
 
ROMARCO Corporate Presentation - October 2012
ROMARCO Corporate Presentation - October 2012ROMARCO Corporate Presentation - October 2012
ROMARCO Corporate Presentation - October 2012
 
Scientific Metals Investor Presentation
Scientific Metals Investor PresentationScientific Metals Investor Presentation
Scientific Metals Investor Presentation
 
Solaris Resources - April 2021
Solaris Resources - April 2021Solaris Resources - April 2021
Solaris Resources - April 2021
 
Solaris Resources - April 2021
Solaris Resources  - April 2021Solaris Resources  - April 2021
Solaris Resources - April 2021
 
Solaris Resources - May 2021
Solaris Resources - May 2021Solaris Resources - May 2021
Solaris Resources - May 2021
 
June 2012 Ur-Energy Corporate Presentation
June 2012 Ur-Energy Corporate PresentationJune 2012 Ur-Energy Corporate Presentation
June 2012 Ur-Energy Corporate Presentation
 
August 2011 Ur-Energy Corporate Presentation
August 2011 Ur-Energy Corporate PresentationAugust 2011 Ur-Energy Corporate Presentation
August 2011 Ur-Energy Corporate Presentation
 
ROMARCO Corporate Presentation - NOVEMBER 2012
ROMARCO Corporate Presentation - NOVEMBER 2012ROMARCO Corporate Presentation - NOVEMBER 2012
ROMARCO Corporate Presentation - NOVEMBER 2012
 
Silver One - Corporate Presentation - November 2021 short
Silver One - Corporate Presentation - November 2021 shortSilver One - Corporate Presentation - November 2021 short
Silver One - Corporate Presentation - November 2021 short
 
Ure corporate presentation final (final) 20140301
Ure corporate presentation final (final) 20140301Ure corporate presentation final (final) 20140301
Ure corporate presentation final (final) 20140301
 
Solaris Resources - October 2021
Solaris Resources - October 2021Solaris Resources - October 2021
Solaris Resources - October 2021
 
Mundoro_Capital_Corporate presentation_Jan2021
Mundoro_Capital_Corporate presentation_Jan2021Mundoro_Capital_Corporate presentation_Jan2021
Mundoro_Capital_Corporate presentation_Jan2021
 
TNR Gold Investor Presentation - Building The Green Energy Metals Royalty and...
TNR Gold Investor Presentation - Building The Green Energy Metals Royalty and...TNR Gold Investor Presentation - Building The Green Energy Metals Royalty and...
TNR Gold Investor Presentation - Building The Green Energy Metals Royalty and...
 
20120710 ure corporate presentation (july 2012)
20120710 ure corporate presentation  (july 2012)20120710 ure corporate presentation  (july 2012)
20120710 ure corporate presentation (july 2012)
 
Fortune Bay Corp. Corporate Presentation Dec. 2021
Fortune Bay Corp. Corporate Presentation Dec. 2021Fortune Bay Corp. Corporate Presentation Dec. 2021
Fortune Bay Corp. Corporate Presentation Dec. 2021
 
Solaris Resources - March 2022
Solaris Resources - March 2022Solaris Resources - March 2022
Solaris Resources - March 2022
 
Ur-Energy October 2013 Corporate Presentation
Ur-Energy October 2013 Corporate PresentationUr-Energy October 2013 Corporate Presentation
Ur-Energy October 2013 Corporate Presentation
 

Viewers also liked

TransAmerica Life - Social Media Workshop
TransAmerica Life - Social Media WorkshopTransAmerica Life - Social Media Workshop
TransAmerica Life - Social Media Workshop
BWEST Interactive
 
Presentatie Doorwerkgever
Presentatie DoorwerkgeverPresentatie Doorwerkgever
Presentatie Doorwerkgever
annelous
 
Worthwhile Technology Foundations
Worthwhile Technology FoundationsWorthwhile Technology Foundations
Worthwhile Technology Foundations
Will Koffel
 
The American Revolution
The American RevolutionThe American Revolution
The American Revolution
prestonade
 
Legacy Unforgettable
Legacy UnforgettableLegacy Unforgettable
Legacy Unforgettable
guest9c64df3
 

Viewers also liked (20)

WordCampEDU Scriblio 2009-02-02
WordCampEDU Scriblio 2009-02-02WordCampEDU Scriblio 2009-02-02
WordCampEDU Scriblio 2009-02-02
 
Internship presentation on Feb 22
Internship presentation on Feb 22Internship presentation on Feb 22
Internship presentation on Feb 22
 
Ccc@Eccbr08 Iis Hanft
Ccc@Eccbr08 Iis HanftCcc@Eccbr08 Iis Hanft
Ccc@Eccbr08 Iis Hanft
 
Vireb may10
Vireb may10Vireb may10
Vireb may10
 
Microservices Cloud Club 2015-02-26
Microservices Cloud Club 2015-02-26Microservices Cloud Club 2015-02-26
Microservices Cloud Club 2015-02-26
 
TransAmerica Life - Social Media Workshop
TransAmerica Life - Social Media WorkshopTransAmerica Life - Social Media Workshop
TransAmerica Life - Social Media Workshop
 
Presentatie Doorwerkgever
Presentatie DoorwerkgeverPresentatie Doorwerkgever
Presentatie Doorwerkgever
 
David kenneth waldman's_2012_cv_mayv31
David kenneth waldman's_2012_cv_mayv31David kenneth waldman's_2012_cv_mayv31
David kenneth waldman's_2012_cv_mayv31
 
May 2012 Ur-Energy Corporate Presentation
May 2012 Ur-Energy Corporate PresentationMay 2012 Ur-Energy Corporate Presentation
May 2012 Ur-Energy Corporate Presentation
 
Drush make - Install Drupal like a Pro
Drush make - Install Drupal like a ProDrush make - Install Drupal like a Pro
Drush make - Install Drupal like a Pro
 
Worthwhile Technology Foundations
Worthwhile Technology FoundationsWorthwhile Technology Foundations
Worthwhile Technology Foundations
 
20110207 ure corporate presentation (february 2011)
20110207 ure corporate presentation (february 2011)20110207 ure corporate presentation (february 2011)
20110207 ure corporate presentation (february 2011)
 
20110207 ure corporate presentation (february 2011)
20110207 ure corporate presentation (february 2011)20110207 ure corporate presentation (february 2011)
20110207 ure corporate presentation (february 2011)
 
Kellett Yellowknife Sept-24
Kellett Yellowknife Sept-24Kellett Yellowknife Sept-24
Kellett Yellowknife Sept-24
 
ACH 216 Lecture 03 (Whos Who)
ACH 216 Lecture 03 (Whos Who)ACH 216 Lecture 03 (Whos Who)
ACH 216 Lecture 03 (Whos Who)
 
The American Revolution
The American RevolutionThe American Revolution
The American Revolution
 
Interconcept Solutions Business Presentation
Interconcept Solutions Business PresentationInterconcept Solutions Business Presentation
Interconcept Solutions Business Presentation
 
Ur-Energy September 2013 Corporate Presentation
Ur-Energy September 2013 Corporate PresentationUr-Energy September 2013 Corporate Presentation
Ur-Energy September 2013 Corporate Presentation
 
Q3
Q3Q3
Q3
 
Legacy Unforgettable
Legacy UnforgettableLegacy Unforgettable
Legacy Unforgettable
 

Similar to December 2012 Ur-Energy Corporate Presentaion

August 2011 Ur-Energy Corporate Presentation (NRC Licnese Update)
August 2011 Ur-Energy Corporate Presentation (NRC Licnese Update)August 2011 Ur-Energy Corporate Presentation (NRC Licnese Update)
August 2011 Ur-Energy Corporate Presentation (NRC Licnese Update)
Rich Boberg, SHRM-SCP, SPHR, PHRca
 

Similar to December 2012 Ur-Energy Corporate Presentaion (20)

20111020 ure corporate presentation (october 2011) +wdeq
20111020  ure corporate presentation (october 2011) +wdeq20111020  ure corporate presentation (october 2011) +wdeq
20111020 ure corporate presentation (october 2011) +wdeq
 
March 2012 PDAC Corporate Presentation
March 2012 PDAC Corporate PresentationMarch 2012 PDAC Corporate Presentation
March 2012 PDAC Corporate Presentation
 
February 2012 Ur-Energy Corporate Presentation
February 2012 Ur-Energy Corporate PresentationFebruary 2012 Ur-Energy Corporate Presentation
February 2012 Ur-Energy Corporate Presentation
 
20110310 ure corporate presentation (march 2011)
20110310 ure corporate presentation (march 2011)20110310 ure corporate presentation (march 2011)
20110310 ure corporate presentation (march 2011)
 
December_2011
December_2011December_2011
December_2011
 
20120808 ure corporate presentation (august 2012 final)
20120808 ure corporate presentation  (august 2012 final)20120808 ure corporate presentation  (august 2012 final)
20120808 ure corporate presentation (august 2012 final)
 
October 2011 Ur-Energy Corporate Presentation
October 2011 Ur-Energy Corporate PresentationOctober 2011 Ur-Energy Corporate Presentation
October 2011 Ur-Energy Corporate Presentation
 
20110225 ure corporate presentation (february 2011)
20110225 ure corporate presentation (february 2011)20110225 ure corporate presentation (february 2011)
20110225 ure corporate presentation (february 2011)
 
Ur-Energy December 2012 Presentation
Ur-Energy December 2012 PresentationUr-Energy December 2012 Presentation
Ur-Energy December 2012 Presentation
 
November 2012 Ur-Energy Corporate Presentation
November 2012 Ur-Energy Corporate PresentationNovember 2012 Ur-Energy Corporate Presentation
November 2012 Ur-Energy Corporate Presentation
 
September 2012 Corporate Presentation
September 2012 Corporate PresentationSeptember 2012 Corporate Presentation
September 2012 Corporate Presentation
 
20110602 ure corporate presentation (june 2011)
20110602 ure corporate presentation (june 2011)20110602 ure corporate presentation (june 2011)
20110602 ure corporate presentation (june 2011)
 
August 2011 Ur-Energy Corporate Presentation (NRC Licnese Update)
August 2011 Ur-Energy Corporate Presentation (NRC Licnese Update)August 2011 Ur-Energy Corporate Presentation (NRC Licnese Update)
August 2011 Ur-Energy Corporate Presentation (NRC Licnese Update)
 
September 2011 Ur-Energy Corporate Presentation
September 2011 Ur-Energy Corporate PresentationSeptember 2011 Ur-Energy Corporate Presentation
September 2011 Ur-Energy Corporate Presentation
 
20121005 ure corporate presentation (october 2012 final)
20121005 ure corporate presentation  (october 2012 final)20121005 ure corporate presentation  (october 2012 final)
20121005 ure corporate presentation (october 2012 final)
 
20110203 ure corporate presentation (february 2011)
20110203 ure corporate presentation (february 2011)20110203 ure corporate presentation (february 2011)
20110203 ure corporate presentation (february 2011)
 
Rhr ppt mrz11
Rhr ppt mrz11Rhr ppt mrz11
Rhr ppt mrz11
 
WKM November Presentation
WKM November PresentationWKM November Presentation
WKM November Presentation
 
20110329 ure corporate presentation (march 2011)
20110329 ure corporate presentation (march 2011)20110329 ure corporate presentation (march 2011)
20110329 ure corporate presentation (march 2011)
 
August 2012 Ur-Energy Corporate Presentation
August 2012 Ur-Energy Corporate PresentationAugust 2012 Ur-Energy Corporate Presentation
August 2012 Ur-Energy Corporate Presentation
 

More from Rich Boberg, SHRM-SCP, SPHR, PHRca

More from Rich Boberg, SHRM-SCP, SPHR, PHRca (20)

Ur-Energy March 2016 Corporate Presentation
Ur-Energy March 2016 Corporate PresentationUr-Energy March 2016 Corporate Presentation
Ur-Energy March 2016 Corporate Presentation
 
Ur-Energy 2015 Year End Webcast and Teleconference
Ur-Energy 2015 Year End Webcast and TeleconferenceUr-Energy 2015 Year End Webcast and Teleconference
Ur-Energy 2015 Year End Webcast and Teleconference
 
Ur-Energy 2015 Year End Webcast and Teleconference
Ur-Energy 2015 Year End Webcast and TeleconferenceUr-Energy 2015 Year End Webcast and Teleconference
Ur-Energy 2015 Year End Webcast and Teleconference
 
Ur-Energy February 2016 Corporate Presentation
Ur-Energy February 2016 Corporate PresentationUr-Energy February 2016 Corporate Presentation
Ur-Energy February 2016 Corporate Presentation
 
Ur-Energy January 2016 Corporate Presentation
Ur-Energy January 2016 Corporate PresentationUr-Energy January 2016 Corporate Presentation
Ur-Energy January 2016 Corporate Presentation
 
Ur-Energy December 2015 Corporate Presentation
Ur-Energy December 2015 Corporate PresentationUr-Energy December 2015 Corporate Presentation
Ur-Energy December 2015 Corporate Presentation
 
Ur-Energy November 2015 Corporate Presentation
Ur-Energy November 2015 Corporate PresentationUr-Energy November 2015 Corporate Presentation
Ur-Energy November 2015 Corporate Presentation
 
Ur-Energy 2015 Third Quarter Webcast and Teleconference
Ur-Energy 2015 Third Quarter Webcast and TeleconferenceUr-Energy 2015 Third Quarter Webcast and Teleconference
Ur-Energy 2015 Third Quarter Webcast and Teleconference
 
Ur-Energy October 2015 Corporate Presentation
Ur-Energy October 2015 Corporate PresentationUr-Energy October 2015 Corporate Presentation
Ur-Energy October 2015 Corporate Presentation
 
Ur-Energy September 2015 Corporate Presentation
Ur-Energy September 2015 Corporate PresentationUr-Energy September 2015 Corporate Presentation
Ur-Energy September 2015 Corporate Presentation
 
Ur-Energy 2015 2Q Webcast and Teleconference Presentation
Ur-Energy 2015 2Q Webcast and Teleconference PresentationUr-Energy 2015 2Q Webcast and Teleconference Presentation
Ur-Energy 2015 2Q Webcast and Teleconference Presentation
 
Ur-Energy August 2015 Corporate Presentation
Ur-Energy August 2015 Corporate PresentationUr-Energy August 2015 Corporate Presentation
Ur-Energy August 2015 Corporate Presentation
 
Ur-Energy August 2015 Corporate Presentation
Ur-Energy August 2015 Corporate PresentationUr-Energy August 2015 Corporate Presentation
Ur-Energy August 2015 Corporate Presentation
 
Ur-Energy Second Quarter 2015 Teleconference and Webcast
Ur-Energy Second Quarter 2015 Teleconference and WebcastUr-Energy Second Quarter 2015 Teleconference and Webcast
Ur-Energy Second Quarter 2015 Teleconference and Webcast
 
June 2015 Corporate Presentation
June 2015 Corporate PresentationJune 2015 Corporate Presentation
June 2015 Corporate Presentation
 
Ur-Energy July 2013 Corporate Presentation
Ur-Energy July 2013 Corporate PresentationUr-Energy July 2013 Corporate Presentation
Ur-Energy July 2013 Corporate Presentation
 
Ur-Energy June 2013 Corporate Presentation
Ur-Energy June 2013 Corporate PresentationUr-Energy June 2013 Corporate Presentation
Ur-Energy June 2013 Corporate Presentation
 
Ur-Energy May 2013 Corporate Presentation
Ur-Energy May 2013 Corporate PresentationUr-Energy May 2013 Corporate Presentation
Ur-Energy May 2013 Corporate Presentation
 
Ur-Energy April 2013 Corporate Presentation
Ur-Energy April 2013 Corporate PresentationUr-Energy April 2013 Corporate Presentation
Ur-Energy April 2013 Corporate Presentation
 
Ur-Energy April 2013 Corporate Presentation
Ur-Energy April 2013 Corporate PresentationUr-Energy April 2013 Corporate Presentation
Ur-Energy April 2013 Corporate Presentation
 

Recently uploaded

+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
?#DUbAI#??##{{(☎️+971_581248768%)**%*]'#abortion pills for sale in dubai@
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Safe Software
 
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Victor Rentea
 

Recently uploaded (20)

AWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of TerraformAWS Community Day CPH - Three problems of Terraform
AWS Community Day CPH - Three problems of Terraform
 
Ransomware_Q4_2023. The report. [EN].pdf
Ransomware_Q4_2023. The report. [EN].pdfRansomware_Q4_2023. The report. [EN].pdf
Ransomware_Q4_2023. The report. [EN].pdf
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdf
 
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWEREMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
EMPOWERMENT TECHNOLOGY GRADE 11 QUARTER 2 REVIEWER
 
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, AdobeApidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
Apidays New York 2024 - Scaling API-first by Ian Reasor and Radu Cotescu, Adobe
 
FWD Group - Insurer Innovation Award 2024
FWD Group - Insurer Innovation Award 2024FWD Group - Insurer Innovation Award 2024
FWD Group - Insurer Innovation Award 2024
 
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...
Apidays New York 2024 - Accelerating FinTech Innovation by Vasa Krishnan, Fin...
 
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
 
Corporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptxCorporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptx
 
Cyberprint. Dark Pink Apt Group [EN].pdf
Cyberprint. Dark Pink Apt Group [EN].pdfCyberprint. Dark Pink Apt Group [EN].pdf
Cyberprint. Dark Pink Apt Group [EN].pdf
 
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...
Apidays New York 2024 - Passkeys: Developing APIs to enable passwordless auth...
 
Manulife - Insurer Transformation Award 2024
Manulife - Insurer Transformation Award 2024Manulife - Insurer Transformation Award 2024
Manulife - Insurer Transformation Award 2024
 
MS Copilot expands with MS Graph connectors
MS Copilot expands with MS Graph connectorsMS Copilot expands with MS Graph connectors
MS Copilot expands with MS Graph connectors
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
 
2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...
 
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
 
CNIC Information System with Pakdata Cf In Pakistan
CNIC Information System with Pakdata Cf In PakistanCNIC Information System with Pakdata Cf In Pakistan
CNIC Information System with Pakdata Cf In Pakistan
 
DBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor PresentationDBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor Presentation
 
Strategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherStrategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a Fresher
 
Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...
 

December 2012 Ur-Energy Corporate Presentaion

  • 1. N YSE Am ex : UR G TSX : UR E Ur-Energy is an Advanced Pre-Production Junior Mining Company Focused on development of low-cost uranium production properties in the United States. Corporate Objectives: • Low Cost U.S. Uranium Production • Resource Growth • Strategic Opportunities Corporate P resentation Decem ber 2011
  • 2. Disclaimer This presentation contains “forward-looking statements,” within the meaning of applicable securities laws, regarding events or conditions that may occur in the future. Such statements include without limitation the long term effects on the uranium market of events in Japan in 2011 including supply and demand projection; the Company’s timeframe for events leading to and culminating in the commencement of production at Lost Creek; the technical and economic viability of the Lost Creek Project (including the projections contained in the preliminary analysis of economics of the Lost Creek Project); receipt of (and related timing of) Record of Decision from the U.S. Bureau of Land Management, and all other necessary permits related to the Lost Creek Project; the Lost Creek Project will advance to production and the production timeline; production rates, timetables and methods of recovery at the Lost Creek Project; the Company’s procurement and construction plans at the Lost Creek Project; the ability to complete additional favorable uranium sales agreements; the potential of exploration targets on the LC North and LC South and on the Lost Creek Project area outside the current Lost Creek resource area; and the further exploration, development and permitting of exploration projects including Lost Soldier, the exploration properties in Nebraska, and Screech Lake. With regard to discussion of the potential of exploration targets, at LC North, LC South and on the Lost Creek Project outside the current resource area, it should be noted that there has been insufficient exploration yet to define a mineral resource at these exploration targets. Further, it is uncertain if additional exploration will result in the exploration targets being delineated as a mineral resource. These statements are based on current expectations that, while considered reasonable by management at this time, inherently involve a number of significant business, economic and competitive risks, uncertainties and contingencies. Numerous factors could cause actual events to differ materially from those in the forward-looking statements. Factors that could cause such differences, without limiting the generality of the following, include: risks inherent in exploration activities; volatility and sensitivity to market prices for uranium; volatility and sensitivity to capital market fluctuations; the impact of exploration competition; the ability to raise funds through private or public equity financings; imprecision in resource and reserve estimates; environmental and safety risks including increased regulatory burdens; unexpected geological or hydrological conditions; a possible deterioration in political support for nuclear energy; changes in government regulations and policies, including trade laws and policies; demand for nuclear power; weather and other natural phenomena; delays in obtaining or failures to obtain required governmental, environmental or other project approvals; and other exploration, development, operating, financial market and regulatory risks. Although Ur-Energy Inc. believes that the assumptions inherent in the forward-looking statements are reasonable, undue reliance should not be placed on these statements, which only apply as of the date of this presentation. Ur-Energy Inc. disclaims any intention or obligation to update or revise any forward-looking statement, whether as a result of new information, future events or otherwise. Cautionary Note Regarding Projections: Similarly, this presentation also may contain projections relating to an extended future period and, accordingly, the estimates and assumptions underlying the projections are inherently highly uncertain, based on events that have not taken place, and are subject to significant economic, financial, regulatory, competitive and other uncertainties and contingencies beyond the control of Ur-Energy Inc. Further, given the nature of the Company's business and industry that is subject to a number of significant risk factors, there can be no assurance that the projections can be or will be realized. It is probable that the actual results and outcomes will differ, possibly materially, from those projected. The attention of investors is drawn to the Risk Factors set out in the Company's Annual Information Form and Annual Report on Form 40-F, dated March 17, 2011, which are filed, respectively, with the regulatory authorities in Canada on SEDAR and with the U.S. Securities and Exchange Commission on EDGAR. (www.sedar.com and http://www.sec.gov/edgar.shtml) Cautionary Note to U.S. Investors Concerning Estimates of Measured, Indicated or Inferred Resources: the information presented uses the terms "measured", "indicated" and "inferred" mineral resources. United States investors are advised that while such terms are recognized and required by Canadian regulations, the United States Securities and Exchange Commission does not recognize these terms. United States investors are cautioned not to assume that all or any part of measured or indicated mineral resources will ever be converted into mineral reserves. United States investors are also cautioned not to assume that all or any part of an inferred mineral resource exists, or is economically or legally minable. John Cooper, SME Registered Member, a Professional Geologist, and Qualified Person as defined by National Instrument 43-101, reviewed the technical information contained in this presentation. 2 N YSE Am ex : UR G TSX : UR E
  • 3. Ur-Energy At A Glance Advanced Pre-Production Project at Lost Creek, Wyoming 4-Years invested in the regulatory process One approval remaining Low-Cost Uranium Production Center that will be Cash-Flow Positive in Current Market Expanding Resources through Exploration and Acquisition Low Technical, Political and Regulatory Risk Strategy See Disclaimer re Forward-looking Statements and Projections (slide 2) 3 N YSE Am ex : UR G TSX : UR E
  • 4. Ur-Energy’s Market Position Share Capital & Cash Position NYSE Amex: URG As of 10/24/11 Shares Outstanding 103.7M Stock Options & RSUs 6.5M Fully Diluted 110.2M Market Cap (12/14/11) C$96.4M Cash (09/30/11) C$28.8M Debt $0 Cash per share (09/30/11) ~C$0.30 Share price (12/14/11) C$0.92 TSX: URE 52 Week Range C$.75 - $3.35 Avg. Daily Volume ~560,000 (3-mo URG & URE 12/14/11) Member of Russell 3000 & 2000 and S&P/TSX SmallCap Indexes Geographical Distribution as of 6/30/11 United States ~48% Canada ~38% Other ~14% 4 N YSE Am ex : UR G TSX : UR E
  • 5. Analyst Coverage United States GVC Capital Mike Shonstrom (Denver, CO) 1 303-321-2392 Rodman & Renshaw Wayne Atwell (New York, NY) 1 212-356-0513 Canada Dundee Securities David A. Talbot (Toronto, ON) 1 416-350-3082 Haywood Securities Geordie Mark (Vancouver, BC) 1 604-697-6112 Raymond James Bart Jaworski (Vancouver, BC) 1 604-659-8282 RBC Capital Adam Schatzker (Toronto, ON) 1 416-842-7850 Australia Resource Capital Research Trent Allen (Sydney, NSW) 61 2-9252-9405 Ur-Energy Inc is followed by the analysts listed above. This list, including the firms and individual analysts at these firms, is subject to change at any time without notice. Please note that any opinions, estimates, forecasts, conclusions or recommendations regarding Ur-Energy Inc's performance made by these analysts are theirs alone and do not represent opinions, estimates, forecasts, conclusions, recommendations or predictions of Ur-Energy Inc or its management. Ur- Energy Inc does not by its reference above or in any other manner imply its endorsement of or concurrence with such information, conclusions or recommendations. 5 N YSE Am ex : UR G TSX : UR E
  • 6. The US Uranium Market The US produces ~ 4M lbs of uranium/yr1 The US consumes 55M lbs of uranium/yr1 contributing 20% of US electricity In 2010, the 10-year forward cumulative unfilled uranium requirement of US utilities was 274M lbs2 Ur-Energy is well positioned to capitalize on this opportunity Chart from U.S . Energy Information Administration 1 – Northwest Mining Association 2 – U.S. Energy Information Administration See Disclaimer re Forward-looking Statements and Projections (slide 2) 6 N YSE Am ex : UR G TSX : UR E
  • 7. Post-Fukushima Nuclear Remains Positive* HEU Agreement to expire 2013 Provides 13% of world and 45% of US annual supply 63 reactors remain under construction Russia, China and India represent 50% of new builds and have reaffirmed support for nuclear power Saudi Arabia & the United Kingdom have announced plans to build 24 new reactors combined October 2011 Nuclear Energy Institute survey shows two-thirds of Americans support nuclear energy *According to World Nuclear Association See Disclaimer re Forward-looking Statements and Projections (slide 2) 7 N YSE Am ex : UR G TSX : UR E
  • 8. Growth of Nuclear Will Continue Historically, growth of nuclear power continued despite major accidents Growth expected to continue beyond Fukushima at 10 reactors per year 10 years, 10.2 reactors per year Number of Reactors 22 years, 4 reactors per year 8 years, 21.9 reactors per year Fukushima 13 years, 11.3reactors Chernobyl per year Three Mile Island Source: W orld Nuclear Association See Disclaimer re Forward-looking Statements and Projections (slide 2) 8 N YSE Am ex : UR G TSX : UR E
  • 9. Supply/Demand Imbalance Grows How will supply be able to expand to the extent necessary to meet growing demand levels in the post Fukushima environment of uncertainty and low prices? More damage done to uranium supply than uranium demand HEU Program expires in 2013 with no extension being considered Source: UxC Uranium M arket Outlook See Disclaimer re Forward-looking Statements and Projections (slide 2) 9 N YSE Am ex : UR G TSX : UR E
  • 10. Experienced Management Team Board of Directors Ex ecutive Directors Wayne W. Heili, President & Chief Executive Officer (Metallurgical Engineer) Jeffrey T. Klenda*, Board Chairman, Executive Director (Mining Finance) Non-Ex ecutive Directors W. William Boberg*, Former President & CEO (Professional Geologist) James M. Franklin*, Chair-Technical Committee (Professional Geologist) Paul Macdonell*, Chair-Compensation and Corp. Governance & Nominating Committees (Senior Federal Mediator) Thomas H. Parker, Chair-Audit Committee (Professional Engineer) Officers Roger L. Smith, Chief Financial Officer & Chief Administrative Officer(CPA & MBA) Steven M. Hatten, VP Operations (Mining Engineer) John W. Cash, VP Regulatory Affairs, Geology & Exploration (Geologist & Geophysicist) Penne A. Goplerud, Corporate Secretary & General Counsel (JD) * Founding Directors 10 N YSE Am ex : UR G TSX : UR E
  • 11. Industry Leading Team Highly Experienced Technical and Management Professionals 93 Years of Direct Uranium Production Experience ISR operations experience – Nebraska, Texas & Wyoming 11 N YSE Am ex : UR G TSX : UR E
  • 12. ISR – Low Impact Mining CAMECO Smith Ranch ISR Mine Powder River Basin, Wyoming 12 N YSE Am ex : UR G TSX : UR E
  • 13. In-Situ Recovery (ISR) Uranium Mining Environmentally sound production method Well understood by Wyoming state regulators Cost effective, low capital costs See Disclaimer re Forward-looking Statements and Projections (slide 2) 13 N YSE Am ex : UR G TSX : UR E
  • 14. Ur-Energy’s Wyoming Projects 14 N YSE Am ex : UR G TSX : UR E
  • 15. Lost Creek Property Exploration targets within the Lost Creek Project and adjoining projects provide potential of additional resources U3O8 Lost Creek Project – 4,254 acres Adjoining Projects – 29,540 acres Historic Drilling on Adjoining Projects Multiple roll fronts defined by 725 drill holes 50-60 mineralized holes on LC Property with grades similar to Lost Creek resource Additional drilling of 2000-3000 holes recommended at a cost of US$15M - 20M (~US$7,500/hole) These exploration targets are conceptual in nature. There has been insufficient exploration to define a mineral resource outside the current Lost Creek See Disclaimer re Forward-looking Statements and Projections resource. It is uncertain if further exploration will result in the new target areas (slide 2) outside the Lost Creek resource being delineated as a mineral resource. 15 N YSE Am ex : UR G TSX : UR E
  • 16. Lost Creek Rio Tinto Sweetwater Mill – 3 miles south (NRC Licensed Conventional Uranium Mill on Standby) JK NYSE Amex: URG TSX: URE
  • 17. Lost Creek Project – Moving Towards Production Discovered in the1970s 563 drill holes Leach Efficiency - 80% Industry Avg. - ~70% Ur- Energy: 2005-2010 (Recovery Rate) 1,096 drill holes Pump Test Results - >30-50gpm 728,757 ft (222,125 meters) Industry Avg. - 15gpm (Good Porosity = Cost Savings) 2011 Drilling program Discovery of ore grade mineralization within M & N horizons NI 43-101 Resource from Prelim inary Assessm ent Lost Creek Property Sw eetw ater County W yom ing – TR EC & Behre Dolbear (M arch 16, 2011) (posted on SEDAR ) Measured – 2.54 Mt @ 0.052% (2.7 Mlbs eU3O8) Indicated – 2.2 Mt @ 0.060% (2.6 Mlbs eU3O8) Inferred – 0.77 Mt @0.051% (0.8 Mlbs eU3O8) * Based on grade cutoff of 0.02 percent eU3O8 and a grade x thickness cutoff of 0.3 GT. See Disclaimers (slide 2) 17 N YSE Am ex : UR G TSX : UR E
  • 18. Lost Creek Preliminary Assessment 2011 PA* Confirms Robust Economics Estimates Operating Costs less than US$20 / lb Lowest Quartile of all Uranium Producers Production Rate: 1M lbs U3O8 per year Estimates Total P roduction Cost at US$42.65/ lb Includes capital recovery Project Internal Rate of Return (I RR ) at 91% Pre-Production Capital Costs of Only US$35M Rem aining Lowest Quartile of all developing uranium production facilities Includes 1M lb/yr plant, 2 disposal wells, initial wellfield and 10% contingency Total project Capital Cost of US$59M Cautionary Statement: This PA is preliminary in nature, and includes inferred mineral resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves. The estimated mineral recovery used in this PA is based on both site-specific laboratory recovery data as well as URE personnel and industry experience at similar facilities. There can be no assurance that recovery at this level will be achieved. * N I 43-101 P relim inary Assessm ent Lost Creek P roperty Sw eetw ater See Disclaimer re Forward-looking Statements and Projections (slide 2) County W yom ing – TR EC & Behre Dolbear (M arch 16, 2011) (posted on SEDAR ) 18 N YSE Am ex : UR G TSX : UR E
  • 19. US$24M in CapEx Completed Mine Units 1 & 2 Delineated MU #1 Monitor Well Ring Completed Plant Engineering Completed Drilled and Tested Class I UIC Well Ordered Key Plant Equipment Ur-Energy’s Ion Exchange Columns Ion Exchange Columns Elution Columns Filter Presses Design/Build of Header House Building Interior of Ur-Energy’s Prototype Header House 19 N YSE Am ex : UR G TSX : UR E
  • 20. Lost Creek Infrastructure Advantage Lost Creek Processing Plant Model = Cost Savings Expandable Resource Base No need for Satellite facilities Hub & Spoke (multi-Satellite) Model Not Preferred Permitting Intensive Capital Intensive Higher Operating Costs Requires Large Resource Base Additional Transportation Cost Common Development Requirements Production Permits On-site Recovery Plant Wastewater Disposal Capacity See Disclaimer (slide 2) 20 N YSE Am ex : UR G TSX : UR E
  • 21. Lost Creek Path to Production Site Permitting Started in 2006 Granted Licenses and Permits Wyoming DEQ Permit to Mine US NRC License WDEQ Class I UIC Permit (water disposal well) EPA Aquifer Exemption One Remaining Regulatory Approval Needed US Bureau of Land Management Plan of Operations Environmental review process underway Record of Decision anticipated to be complete early summer 2012 Construction 6 – 9 month build-out First Production Planned for second quarter 2013 See Disclaimer re Forward-looking Statements and Projections (slide 2) 21 N YSE Am ex : UR G TSX : UR E
  • 22. Lost Soldier – 12.2M M&I lbs U3O8 Can be licensed with NRC as amendment to Lost Creek license M & I resource average 17.2 ft @ 0.065% U3O8 Average 240 feet deep Leach efficiency 49% - 84% Over 3700 drill holes define deposit 17 monitor/pump test wells installed (From Figure 16-2, Technical Report on the Lost Soldier Project, Wyoming, C. Stewart Wallis, RPA, July 10, 2006 - posted on SEDAR) NI 43-101 Compliant Resource Measured & Indicated (M & I) – 9.4 Mt @ 0.065% (12.2 Mlbs U3O8) Inferred – 1.6 Mt @0.055% (1.8 Mlbs U3O8) (Technical Report on the Lost Soldier Project, Wyoming, C. Stewart Wallis, Roscoe Postle Associates Inc., July 10, 2006 - Posted on SEDAR) See Disclaimer re Forward-looking Statements and Projections (slide 2) 22 N YSE Am ex : UR G TSX : UR E
  • 23. Screech Lake, Thelon Basin, NWT Completed Audio-Magnetotelluric Geophysical Survey, and Soil Gas Hydrocarbon and Enzyme Leach Soil Geochemistry Analyses to Better Define Drill Target MegaTEM Survey Screech Lake See Disclaimer re Forward-looking Statements and Projections (slide 2) 0 4 Kilometers 23 N YSE Am ex : UR G TSX : UR E
  • 24. Ur-Energy’s Strong Position Advanced Development at Lost Creek Permitting Process Nearing Completion Low Cost Production Will Equal Strong Cash Flow ~US$20/lb direct operating cost Uranium Term Market is above $60/lb Uranium Friendly Mining Jurisdictions Experienced Technical & Managerial Team Strong Balance Sheet C$28.8Million (09/30/11) See Disclaimer re Forward-looking Statements and Projections (slide 2) 24 N YSE Am ex : UR G TSX : UR E
  • 25. Future Growth Opportunities Exploration Properties in Western Nebraska Resource Expansion through ongoing exploration efforts Increase Minable Resources that will be Accessible to the Lost Creek Processing Plant Growth in the Production Profile Development of Currently Held Properties Acquisitions of New Properties Strategic Alliances Monetizing Historic Databases See Disclaimer re Forward-looking Statements and Projections (slide 2) 25 N YSE Am ex : UR G TSX : UR E
  • 26. Ur-Energy – Right Now! Technical, Political and Regulatory Certainty Advanced Pre-Production Project at Lost Creek Low-Cost Uranium Production Center that will be Cash-Flow Positive in Today’s Market Plant Construction Planned to Begin Summer 2012 Initial Production Rate of 1M lbs/year Signed Initial Long Term Uranium Sales Agreement De-Risking Company Exposure to Volatile Marketplace Re-Rating Likely as Ur-Energy nears Production See Disclaimer re Forward-looking Statements and Projections (slide 2) 26 N YSE Am ex : UR G TSX : UR E
  • 27. Ur-Energy - The Right People. The Right Projects. Right Now.  For more information, please contact: Wayne Heili, President, Chief Executive Officer & Director Jeff Klenda, Board Chairman & Director Rich Boberg, Director of Public Relations  By Mail: Ur-Energy Corporate Office 10758 W. Centennial Rd., Ste. 200 Littleton, CO 80127 USA  By Phone: Office (720) 981-4588 Toll-Free (866) 981-4588 Fax (720) 981-5643  By E-mail: wayne.heili@ur-energyusa.com jeff.klenda@ur-energyusa.com rich.boberg@ur-energyusa.com 27 NYSE Amex:: URG N YSE Am ex UR G TSX::URE TSX UR E