3. Introduction to CRISP
The UK Experience & lessons learnt
The Australian Experience & lessons learnt
4. Cycling Popularity
London 500,000 cyclists / day (2006)
Sydney 120,000 cyclists / day (2005)
London - 23% increase in 1 year (2003-2004)
Sydney - 23% increase in 4 years (2001–2005)
Cycling in the UK!
5.
6. Introduction
Mayor of London’s Transport Strategy 2001
Task Force established in 2002 → London Cycle Network Plus (LCN+) Program
Cycle Route Implementation and Stakeholder Plan (CRISP) → to satisfy these objectives
2004 → London Cycling Action Plan (LCAP) formalised
Total of 286 CRISP Reports
950km of Cycle Routes
Lengths between 0.5km and 15km
7. What is a CRISP?
(Cycle Route Implementation and Stakeholder Plan)
The Purpose of a CRISP Study
Main aims of the CRISP process are to:
Raise the profile of cycling
Substantially increase levels of cycling
Improve the quality of the network
Provide a cohesive network and a coherent approach to
implementation
Provide the optimal route for cyclists
Include stakeholders at an early stage
Provide a costed program and encourage long term project planning
Prioritise work along the Link
Tackle the tough issues along the Link
8. CRISP Team
Consultant – guidance and engineering experience
Council Cycling Officer – Strategic viewpoint of local authority
Local Stakeholder – local knowledge
Transport for London – Viewpoint of TLRN
LCN+ - strategic view of entire network
9. The CRISP Process
1. Pre-CRIM Report
2. Cycle Route Inspection Meeting (CRIM)
3. CRISP Report – DRAFT for consultation with the CRISP Team
4. CRISP Report - FINAL
13. Nathan Parish – UK Example
A406 CRISP Study
CRISP Process
14. Nathan Parish – UK Example
A406 CRISP Study
CRISP Process
Stage 1 : Pre-CRIM Report
15. Nathan Parish – UK Example
A406 CRISP Study
CRISP Process
Stage 1 : Pre-CRIM Report
Introduces study
Describes route
Questionnaire results
Identifies stakeholders
16. Nathan Parish – UK Example
A406 CRISP Study
CRISP Process
Stage 1 : Pre-CRIM Report
Introduces study
Describes route
Questionnaire results
Identifies stakeholders
Lessons Learned
Questionnaire response rate
17. Nathan Parish – UK Example
A406 CRISP Study
CRISP Process
Stage 1 : Pre-CRIM Report
Stage 2 : CRIM
18. Nathan Parish – UK Example
A406 CRISP Study
CRISP Process
Stage 1 : Pre-CRIM Report
Stage 2 : CRIM
Pre-CRIM meeting
CRIM
Record of CRIM
19. Nathan Parish – UK Example
A406 CRISP Study
CRISP Process
Stage 1 : Pre-CRIM Report
Stage 2 : CRIM
Pre-CRIM meeting
CRIM
Record of CRIM
Lessons Learned
Stakeholder attendance
20. Nathan Parish – UK Example
A406 CRISP Study
CRISP Process
Stage 1 : Pre-CRIM Report
Stage 2 : CRIM
Stage 3 : Draft CRISP Report
21. Nathan Parish – UK Example
A406 CRISP Study
CRISP Process
Stage 1 : Pre-CRIM Report
Stage 2 : CRIM
Stage 3 : Draft CRISP Report
Data sheets
Budget construction costs
Proposed programme
22. Nathan Parish – UK Example
A406 CRISP Study
CRISP Process
Stage 1 : Pre-CRIM Report
Stage 2 : CRIM
Stage 3 : Draft CRISP Report
Data sheets
23. Nathan Parish – UK Example
A406 CRISP Study
CRISP Process
Stage 1 : Pre-CRIM Report
Stage 2 : CRIM
Stage 3 : Draft CRISP Report
24. Nathan Parish – UK Example
A406 CRISP Study
CRISP Process
Stage 1 : Pre-CRIM Report
Stage 2 : CRIM
Stage 3 : Draft CRISP Report
Data sheets
Budget construction costs
Proposed programme
Lessons learned
Minute taker
Proposed programme
25. Nathan Parish – UK Example
A406 CRISP Study
CRISP Process
Stage 1 : Pre-CRIM Report
Stage 2 : CRIM
Stage 3 : Draft CRISP Report
Stage 4 : Final CRISP Report
26. Nathan Parish – UK Example
A406 CRISP Study
CRISP Process
Stage 1 : Pre-CRIM Report
Stage 2 : CRIM
Stage 3 : Draft CRISP Report
Stage 4 : Final CRISP Report
Review meeting
Issue Final CRISP Report
27. Nathan Parish – UK Example
A406 CRISP Study
CRISP Process
Stage 1 : Pre-CRIM Report
Stage 2 : CRIM
Stage 3 : Draft CRISP Report
Stage 4 : Final CRISP Report
Summary
30. Nigel Coates – AUS Example
Launceston Bike Plan 2004
To create safe commuting routes and improve
the safety of streets for cycling
31. Nigel Coates – AUS Example
Launceston Bike Plan 2004
Launceston Cycling Infrastructure Strategy 2009
32. Nigel Coates – AUS Example
Launceston Bike Plan 2004
Launceston Cycling Infrastructure Strategy 2009
Hierarchy of Solutions
33. Nigel Coates – AUS Example
Launceston Bike Plan 2004
Launceston Cycling Infrastructure Strategy 2009
Hierarchy of Solutions
Traffic reduction
34. Nigel Coates – AUS Example
Launceston Bike Plan 2004
Launceston Cycling Infrastructure Strategy 2009
Hierarchy of Solutions
Traffic reduction
Speed reduction
35. Nigel Coates – AUS Example
Launceston Bike Plan 2004
Launceston Cycling Infrastructure Strategy 2009
Hierarchy of Solutions
Traffic reduction
Speed reduction
Dealing with junctions
36. Nigel Coates – AUS Example
Launceston Bike Plan 2004
Launceston Cycling Infrastructure Strategy 2009
Hierarchy of Solutions
Traffic reduction
Speed reduction
Dealing with junctions
Road space redistribution
37. Nigel Coates – AUS Example
Launceston Bike Plan 2004
Launceston Cycling Infrastructure Strategy 2009
Hierarchy of Solutions
Traffic reduction
Speed reduction
Dealing with junctions
Road space redistribution
Off road provision
38. Nigel Coates – AUS Example
Launceston Bike Plan 2004
Launceston Cycling Infrastructure Strategy 2009
Launceston Arterial Bike Route Network (50 km)
39. Nigel Coates – AUS Example
Launceston Bike Plan 2004
Launceston Cycling Infrastructure Strategy 2009
Launceston Arterial Bike Route Network
40. Nigel Coates – AUS Example
Launceston Bike Plan 2004
Launceston Cycling Infrastructure Strategy 2009
Launceston Arterial Bike Route Network
$ State Bike Route Funding
41. Nigel Coates – AUS Example
Launceston Bike Plan 2004
Launceston Cycling Infrastructure Strategy 2009
Launceston Arterial Bike Route Network
$ State Bike Route Funding
$ Federal Bike Route Funding (Jobs Fund)
42. Nigel Coates – AUS Example
Launceston Bike Plan 2004
Launceston Cycling Infrastructure Strategy 2009
Launceston Arterial Bike Route Network
$ State Bike Route Funding
$ Federal Bike Route Funding (Jobs Fund)
$ 576,000
43. Nigel Coates – AUS Example
Launceston Bike Plan 2004
Launceston Cycling Infrastructure Strategy 2009
Launceston Arterial Bike Route Network
$ State Bike Route Funding
$ Federal Bike Route Funding (Jobs Fund)
$ 576,000
To spend by June 2010 (8 months!)
46. Nigel Coates – AUS Example
Location of Route
Constraints/Barriers
47. Nigel Coates – AUS Example
Location of Route
Constraints/Barriers
Route 1
48. Nigel Coates – AUS Example
Location of Route
Constraints/Barriers
Route 1
49. Nigel Coates – AUS Example
Location of Route
Constraints/Barriers
Route 1 – Bridge
50. Nigel Coates – AUS Example
Location of Route
Constraints/Barriers
Route 3
51. Nigel Coates – AUS Example
Location of Route
Constraints/Barriers
Route 3 – Separate Up & Down hill routes
52. Nigel Coates – AUS Example
Location of Route
Constraints/Barriers
Route 6
53. Nigel Coates – AUS Example
Location of Route
Constraints/Barriers
Route 6 – Waverley Street
54. Nigel Coates – AUS Example
Location of Route
Constraints / Barriers
Stakeholder Feedback
55. Nigel Coates – AUS Example
Location of Route
Constraints / Barriers
Stakeholder Feedback
Route 1 – Holbrook Street
56. Nigel Coates – AUS Example
Location of Route
Constraints / Barriers
Stakeholder Feedback
All routes – Gully Gratings
57. Nigel Coates – AUS Example
Location of Route
Constraints / Barriers
Stakeholder Feedback
Priority of Schemes
Costs and program
58. Nigel Coates – AUS Example
Location of Route
Constraints / Barriers
Stakeholder Feedback
Priority of Schemes
Costs and program
Black spot schemes
59. Nigel Coates – AUS Example
Location of Route
Constraints / Barriers
Stakeholder Feedback
Priority of Schemes
Costs and program
Black spot schemes
Asset upgrades
60. Nigel Coates – AUS Example
Location of Route
Constraints / Barriers
Stakeholder Feedback
Priority of Schemes
Costs and program
Black spot schemes
Asset upgrades
Jobs fund deadline
61. Nigel Coates – AUS Example
Location of Route
Constraints / Barriers
Stakeholder Feedback
Priority of Schemes
Costs and program
Lessons Learned
62. Nigel Coates – AUS Example
Location of Route
Constraints / Barriers
Stakeholder Feedback
Priority of Schemes
Costs and program
Lessons Learned
Not included
63. Nigel Coates – AUS Example
Location of Route
Constraints / Barriers
Stakeholder Feedback
Priority of Schemes
Costs and program
Lessons Learned
Not included
Pre CRIM report/meeting
64. Nigel Coates – AUS Example
Location of Route
Constraints / Barriers
Stakeholder Feedback
Priority of Schemes
Costs and program
Lessons Learned
Not included
Pre CRIM report/meeting
Other stakeholders
65. Nigel Coates – AUS Example
Location of Route
Constraints / Barriers
Stakeholder Feedback
Priority of Schemes
Costs and program
Lessons Learned
Not included
Pre CRIM report/meeting
Other stakeholders
Options costing
66. Nigel Coates – AUS Example
Location of Route
Constraints / Barriers
Stakeholder Feedback
Priority of Schemes
Costs and program
Lessons Learned
Not included
Pre CRIM report/meeting
Other stakeholders
Options costing
Large route maps
67. Nigel Coates – AUS Example
Location of Route
Constraints / Barriers
Stakeholder Feedback
Priority of Schemes
Costs and program
Lessons Learned
Added
68. Nigel Coates – AUS Example
Location of Route
Constraints / Barriers
Stakeholder Feedback
Priority of Schemes
Costs and program
Lessons Learned
Added
Hierarchy of solutions on data sheet
69. Nigel Coates – AUS Example
Location of Route
Constraints / Barriers
Stakeholder Feedback
Priority of Schemes
Costs and program
Lessons Learned
CRISP report presented to Council
70.
71. Architecture
Landscape
Engineering
Management COMPLETE Sydney
10 Regent Street
Chippendale
NSW 2008
P: +61 (02) 9282 9900
F: +61 (02) 9282 9277
COMPLETE Gold Coast
Suite 106 Lakeside
Bermuda Point
20 Lake Orr Drive Varsity Lakes
QLD 4227
P: +61 (07) 5553 5555
F: +61 (07) 5580 8088
Launceston City Council
www.completeurban.com.au
Thank youSee you next year?
Town Hall
St John Street
Launceston
Tasmania 7250
P: +61 (03) 6323 3442
F: +61 (03) 6323 3396