SlideShare a Scribd company logo
1 of 51
BOILER & CO-GENERATION
MAJOR CONTITUENTS
DM PLANT
COAL HANDLIING
PLANT
CO-GENERATION
PLANT
ASH ANDLING
PLANT
BOIILER
INTRODUCTION TO BOILER
 ENCLOSED
PRESSURE VESSEL
 HEAT GENERATED BY
COMBUSTION OF
FUEL IS
TRANSFERRED TO
WATER TO BECOME
STEAM
 PROCESS:
EVAPORATION
 STEAM VOLUME
INCREASES TO 1,600
TIMES FROM WATER AND
PRODUCES TREMENDOUS
FORCE
 BOILER TO BE EXTREMELY
3
What is a boiler?
COGENERATION PLANT VIEW
20ATA
11ATA
3.9ATA
11ATA
3.9ATA
CONDENSER
CONDENSER
5 BAR TO PROCESS
M
~
20ATA
~~
~
H.P.HTR
35 MW
6 MW
31.4 MW
5.6 MW
54 ATA COMMON HEADER
43ATAHEADER
54 ATA COMMON HEADER
To Economiser
From BFP
B#4
150
TPH
Reynolds
Digestion 1, 3 & 4
B#3
140
TPH
B#2
80
TPH
B#1
80
TPH
~
Auxiliary Steam
4 BAR STEAM
6 MW
600/250
12 Bar
steam to
Dig-2
7BarHdr
7 BAR TO PROCESS
250 PSI
from Hi-
Tech
COGENERATI
ON
PLANT•CO-GENERATION MEANS SIMULTANEOUSLY PRODUCTION OF POWER
& USEFUL THERMAL ENERGY FOR PROCESS FROM THE SAME
PRIMARY ENERGY SOURCE. AS PER MINISTRY OF POWER CO-
GENERATION IS DEFINED AS ONE WHICH SIMULTANEOUSLY
PRODUCES TWO OR MORE FORMS OF USEFUL ENERGY SUCH AS
ELECTRIC POWER AND STEAM, ELECTRIC POWER & SHAFT
(MECHANICAL) POWER ETC... IT ALSO DEFINES ANY FACILITY THAT
USES WASTE INDUSTRIAL HEAT FOR POWER GENERATION BY
SUPPLEMENTING HEAT, NOT MORE THAN 50%, FROM ANY FOSSIL
FUEL.
• AT HINDALCO WE ARE HAVING THE COGENERATION PLANT IN
WHICH WE USE THE STEAM FOR THE PROCESS REQUIREMENT AS
WELL AS POWER GENERATION
WHAT IS A BOILER
 ANY CLOSED VESSEL EXCEEDING 22.75
LITRES IN CAPACITY WHICH IS USED
EXCLUSIVELY FOR GENERATING STEAM
UNDER PRESSURE INCLUDES ANY
MOUNTING AND OTHER FITTING
ATTACHED TO SUCH VESSEL WHICH IS
FULLY OR PARTIALLY UNDER PRESSURE
WHEN SHUTOFF
AUXILIARIES OF BOILER
FANS
INDUCED
DRAFT
FAN
PRIMARY
AIR FAN
FORCED
DRAUGHT
FAN
ID FAN
• THE FUNCTION OF THIS FAN IS TO MAINTAIN THE DRAFT IN THE
FURNACE AND CARAY OUT FLUE GAS OF THE FURNACE AND MAINTAIN
THE NEGATIVE VALUE OF PRESSURE INSIDE THE FURNACE
PA FAN
• THE FUNCTION OF THIS FAN IS TO HEAT AND CARRY COAL FROM MILL
TO THE FURNACE ( PULVERISHED COAL).
FD FAN
• THE FAN IS USED FOR THE PURPOSE OF SUPPLYING EXCESS AIR IN
THE FURNACE FOR COMPLETE COMBUSTION OF COAL
AUXILIARIES OF BOILER
• The function of air preheater is to heat the incoming air
from the Primary air fan which is supplied to the mills,
Basically we are using this air as the medium for heating
and conveying the Pulverized coal. The air preheater is
located in the second pass of the Boiler and it gains its
heat by the flue gases and gives the heat to the incoming
air.
AIR
PREHEATER
• The Economizer is the located in the second pass of the
Boiler its function is to utilize the heat of flue gases
coming out of the first pass of the Boiler which have done
their work of producing steam from the Boiler. The
economizer utilizes this heat of Flue gases which would
otherwise be wasted to the atmosphere resulting in dry
flue gas loss and reducing the efficiency of the Boiler.
ECONOMISER
AUXILIARIES OF BOILER
• The function of the mill is to grind the coal in
the required size, like the size of coal required
in the Pulverized fuel fired Boilers is of 75
microns so to achieve that size the mills are
used. The mills used in the cogeneration plant
are of Ball mill and Bowl mill type.
MILL
• The function of super heater is to superheat
the Dry saturated steam coming from the drum
and convert it into the superheated from so
that chances of moisture is totally eliminated
and the Enthalpy of steam is increased.
SUPERHEATERS
AUXILIARIES OF BOILER
• The function of the Electrostatic
Precipitator is to collect the ash
coming out of the Boiler and
send it to the ash silo from
where it is further utilized as per
requirement. The ESP works on
the principle of Corona where
the Ash particles are charged
by Direct Current and further
collected at the collecting
electrodes and than removed
with the help of rappers and
collected in the ash silos.
ESP
DETAILS OF BOILERS
12
BOILERS TYPE CAPACITY
PR.
KG/CM2
TEMP.
0
C
YEAR OF
COMMISSI
ONING
MAKE
BOILER # 1
FRONT FIRING
(PF)
80 (TPH) 52.5 450 1986 WIL PUNE
BOILER # 2 AFBC 80 (TPH) 52.5 450 1989
BHEL,
TRICHI
BOILER # 3
TANGENTIAL
FIRING (PF)
140 (TPH) 111 535 1996
BHEL,
TRICHI
BOILER # 4
TANGENTIAL
FIRING (PF)
150 (TPH) 111 535 2004
BHEL,
TRICHI
STEAM GENERATION PER HOUR = 450 MT
STEAM RECEIVED FROM HI-TECH = 25-35 MT / HR
13
DM
water
Deaerat
or
BFP
Coal to
feeder
s by
Dozer
Coal
Convey
ors
Rotory
Coal
Feeder
s
Furnace
Coal
Transport
ing Line
Steam
Generati
on
Flue
Gas
to
ESP
PA
Fa
n
FD
Fa
n
Econo
miser
Water Circuit
Coal
Yard
Coal sizing circuit
for
-6mm size coal
Coal
Bunkers
ID Fan
Ash Recycling
feeder-2 No.
Steam to Power Plant /
Process
Exchange
of Heat
Energy
Feeder
Running
YES
Ash
Hopper
NOAsh
drain
Ash Recycling
feeder-2 No.
Process Flow of Boiler#2
FLUIDISED BED COMBUSTION BOILER
AFBC BOILER
15
•AFBC – ATMOSPHERIC FLUIDIZED BED
COMBUSTION
•DEFINITION
WHEN AIR OR GAS IS PASSED THROUGH AN
INERT BED OF SOLID PARTICLE SUCH AS SAND
OR CRUSHED REFRACTORY, THE AIR STARTS
BUBBLING THROUGH THE BED AND PARTICLE
ATTAIN A STATE OF HIGH TURBULENCE.
UNDER SUCH CONDITIONS, THE BED ASSUMES
THE APPEARANCE OF A FLUID AND EXHIBITS
THE PROPERTIES ASSOCIATED WITH A FLUID AND
FBC MECHANISM
16
IF THE BED MATERIAL IN FLUIDIZED
STATE IS HEATED TO THE IGNITION
TEMPERATURE OF THE FUEL AND
THE FUEL IS INJECTED CONTINUOUSLY
INTO THE BED, THE FUEL WILL BURN
RAPIDLY AND BED ATTAINS A
UNIFORM TEMPERATURE DUE TO
AFBC BOILER - ADVANTAGE
17
• FLEXIBLE IN THEIR ABILITY TO BURN A WIDE RANGE OF FUEL.
• DOES NOT REQUIRE OIL SUPPORT FOR START UP OR LOW LOAD
STABILIZATION.
• BY ADDING OF LIMESTONE IN THE BED STRINGENT SOX EMISSION
CONTROL IS POSSIBLE WITHOUT EXPENSING DOWN STREAM SCRUBBER
EQUIPMENT
• AUXILIARY POWER CONSUMPTION IS LOW.
• BETTER LOAD RESPONSE AND CAN BE VARIED FROM 20% TO 100% OF
NCR.
• LESS INITIAL COST.
• EASY IN OPERATION.
• C & I REQUIREMENT FOR FBC ARE MINIMAL. NO BMS REQUIRED
AFBC BOILER - DISADVANTAGE
18
• SUITABLE FOR LOW AND MEDIUM CAPACITY ONLY.
• MORE MAINTENANCE COST DUE TO HIGH
EROSION OF TUBES.
• LOWER EFFICIENCY.
• MORE EFFORTS REQUIRED WHEN IT IS INITIALLY
START UP WITH CHARCOAL.
FUEL FEEDING SYSTEM
19
•Fuel is evenly distributed by judicious location of feed points for burning
most of the volatiles and carbon within the bed and to avoid localized fuel
concentration
Comp-1Comp-2Comp-3Comp-4
Coal feed points
Recycle ash feed
points
Distributor plates
AIR DISTRIBUTION
20
•PROPER AIR DISTRIBUTOR IS REQUIRED TO ENSURE UNIFORM
DISTRIBUTION OF AIR ACROSS BED CROSS SECTION
Comp-1Comp-2Comp-3Comp-4
Nozzles are provided across the bed for proper air distribution
BED TEMPERATURE & HEIGHT
21
•BED TEMPERATURE: - FBC NORMALLY
OPERATES AT A TEMPERATURE RANGE
750-950º C FOR COAL
• BED HEIGHT: - DETERMINED BY THE NEED TO
SUBMERGE HEAT EXCHANGER TUBES AND IN CASE OF
HIGH SULPHUR COAL THE VOLUME REQUIREMENT FOR
EFFECTIVE SULPHUR CAPTURE
FOR MOST OF THE INDIAN FUELS A SHALLOW BED LESS
THAN 1000 MM IS ADEQUATE.
BED TEMPERATURE & HEIGHT
22
Water
Heade
r
Air from FD Fan
Coal Transporting
Line
Primar
y Air
Bed material
in Fluidization
state
BLOCK DIAGRAM OF AFBC BOILER
24
TECHNICAL DATA
25
SN PARAMETER UNIT CAPACITY
1 Heating Surface M² 3426.9
2 Steam Flow TPH 80
3 Steam Pressure
Kg/Cm
²
52.5
4 Steam Temperature Deg C 450±5
5 Feed Water Temp. Deg C 105
6 Fluidized Air Temp Deg C 130
7 Boiler Efficiency % 82±1.5
Coal Size: -(-) 6 mm to Furnace with maximum 20% fines
26
Boiler Flue gas
Steam Output
Efficiency = 100 – (1+2+3+4+5+6+7+8)
(by In Direct Method)
Air
Fuel Input, 100%
1. Dry Flue gas loss
2. H2 loss
3. Moisture in fuel
4. Moisture in air
5. CO loss
7. Fly ash loss
6. Surface loss
8. Bottom ash loss
WHAT ARE THE LOSSES THAT OCCUR
IN A BOILER?
27
INTERMITTENT
BLOWDOWN
• THE INTERMITTENT BLOWN DOWN IS GIVEN
BY MANUALLY OPERATING A VALVE FITTED
TO DISCHARGE PIPE AT THE LOWEST POINT
OF BOILER SHELL TO REDUCE PARAMETERS
(TDS OR CONDUCTIVITY, PH, SILICA ETC)
WITHIN PRESCRIBED LIMITS SO THAT
STEAM QUALITY IS NOT LIKELY TO BE
AFFECTED
• TDS LEVEL KEEPS VARYING
• FLUCTUATIONS OF THE WATER LEVEL IN
THE BOILER.
• SUBSTANTIAL AMOUNT OF HEAT ENERGY IS
28
•WHEN WATER EVAPORATES
•DISSOLVED SOLIDS GETS
CONCENTRATED
•SOLIDS PRECIPITATES
•COATING OF TUBES
•REDUCES THE HEAT TRANSFER
RATE
Why Boiler Blow Down ?
PULVERIZED FIRE BOILER SKETCH
PULVERIZED FUEL BOILER
30
Tangential firing
Coal is pulverised to a fine powder, so that less than 2% is +300
microns, and 70-75% is below 75 microns.
Coal is blown with part of the combustion air into the boiler plant
through a series of burner nozzles.
• Combustion takes place at
temperatures from 1300-1700°C
• Particle residence time in the
boiler is typically 2-5 seconds
• One of the most popular system
for firing pulverized coal is the
tangential firing using four
burners corner to corner to
create a fire ball at the center of
the furnace.
ADVANTAGES
 ITS ABILITY TO BURN ALL RANKS OF COAL FROM
ANTHRACITIC TO LIGNITE, AND IT PERMITS
COMBINATION FIRING (I.E., CAN USE COAL, OIL
AND GAS IN SAME BURNER). BECAUSE OF
THESE ADVANTAGES, THERE IS WIDESPREAD
USE OF PULVERIZED COAL FURNACES.
DISADVANTAGES
 HIGH POWER DEMAND FOR PULVERIZING
 REQUIRES MORE MAINTENANCE, FLY ASH
EROSION AND POLLUTION COMPLICATE UNIT
OPERATION.
31
Pulverized Fuel Boiler
32
PULVERIZED
FUEL
FIRING
FUELS SYSTEM IN PF BOILER#1
33
BALL MILL:-
• IT IS FRONT WALL FIRED PULVERIZED FUEL BOILER HAVING
FOUR BURNERS ON FRONT WALL.
• BOILER NO. 1 IS PULVERIZED FUEL BOILERS.
• OIL GUNS IS PROVIDED FOR START UP AND SUPPORT AT TWO
LEVELS.
• MINUS 20 MM SIZE COAL IS FED TO THE MILL THROUGH THE
TWO NUMBER VOLUMETRIC COAL FEEDERS.
AS THE MILL ROTATES, THE COAL IN THE MILL IS PULVERISED
BY THE CRUSHING AND GRINDING ACTION OF CASCADING
STEEL BALLS. PREHEATED AIR WHICH COMES FROM PRIMARY
AIR FAN, AND FUEL MIXTURE, AFTER PASSING THROUGH THE
CLASSIFIERS, ENTERS THE COAL CONDUITS AND PASSES ON
BALL MILL OF PF BOILER#1
34
FUELS SYSTEM IN PF BOILER#3 &
4
35
BOILER NO. 3 & 4 IS TANGENTIAL FIRED
PULVERIZED FUEL BOILER HAVING FOUR
ELEVATION BURNERS.
IN EACH ELEVATION FOUR COAL BURNER ARE
AVAILABLE.
FOUR NUMBER BOWL MILLS ARE THERE TO CRUSH
THE 20 MM SIZE COAL. OUT OF THESE FOUR MILLS,
THREE MILLS SHOULD BE IN SERVICE FOR FULL
STEAM LOAD.
BOWL AND ROLLERS ARRANGEMENTS ARE THERE
TO CRUSH THE 20-MM SIZE COAL INSIDE THE MILL.
HOT AIR FROM AIR PREHEATERS SUCKED BY THE
QUALITY OF COAL
36
Coal Feed Size
BOILER #1, 3 & 4: 100% (-) 20 MM TO MILL
70% (-) 200 MESH TO
FURNACE
BOILER#2 : (-) 6 MM WITH 20% FINES TO
MOISTURE
VOLATILE
MATTER
ASH
FIXED
CARBON
CALORIFIC
VALUE
10%-16% 21%-26% 35%-38% 25%-30%
2900-3500
KCAL/KG
Proximate Analysis
Values
37
. REDUCE STACK TEMPERATURE
22O C REDUCTION IN FLUE GAS TEMPERATURE INCREASES BOILER
EFFICIENCY BY 1%
. COMBUSTION AIR PREHEATING
. FEED WATER PREHEATING USING
ECONOMIZER6OC RAISE IN FEED WATER TEMPERATURE, BY ECONOMISER/CONDENSATE
RECOVERY, CORRESPONDS TO A 1% SAVING IN FUEL CONSUMPTION
IN ORDER TO IMPROVE THERMAL EFFICIENCY BY 1%, THE COMBUSTION AIR
TEMP. MUST BE RAISED BY 20 DEG C.
ENERGY CONSERVATION
OPPORTUNITIES IN BOILER
. INCOMPLETE COMBUSTION
38
Energy Conservation Opportunities in
Boiler
. CONTROL EXCESS AIR
For every 1% reduction in excess air ,0.6% rise in efficiency.
. RADIATION AND CONVECTION HEAT
LOSS
. AUTOMATIC BLOWDOWN CONTROL
. REDUCTION OF SCALING AND
SOOT LOSSES
. REDUCTION OF BOILER STEAM
PRESSURE
Performance of a Boiler
hg -the enthalpy of saturated steam in kcal/kg of steam
hf -the enthalpy of feed water in kcal/kg of water
Boiler Efficiency: Direct Method
Boiler efficiency () =
Heat output
Heat input
x 100 Q sx (hg – hf)
Q x GCV
x 100=
PARAMETERS TO BE MONITORED:
- QUANTITY OF STEAM GENERATED PER HOUR (QS) IN KG/HR
- QUANTITY OF FUEL USED PER HOUR (Q) IN KG/HR
- THE WORKING PRESSURE (IN KG/CM2(G)) AND SUPERHEAT
TEMPERATURE (OC), IF ANY
- THE TEMPERATURE OF FEED WATER (OC)
- TYPE OF FUEL AND GROSS CALORIFIC VALUE OF THE FUEL
(GCV) IN KCAL/KG OF FUEL
DM PLANT
 THE WATER TO BE FEED IN BOILER FOR STEAM
GENERATION MUST BE DEMINERALISED AS PER
SHOULD NOT CONTAIN ANY DISSOLVED SOLID
SUCH AS SILICA OR CHLORIDES AND CARBONATES
WHICH RESULTS IN SLUDEFE FORMATION AND
SCALE FORMATION IN THE BOILER RESULTING IN
LOW EFFICIENCY OF BOILER ,LOW RATE OF STEAM
GENERATION AND WASTAGE AND MORE
CONSUMPTION OF FUEL ACCOMPANING WITH
CORROSION OF INER BODY SURFACE OR CAN SAY
METAL OF BOILER BODY .
 SO FOR THIS PURPOSE WATER HAS TO BE
TREATED FIRST AND SHOULD MAINTAIN TDS(TOTAL
DISSOLVED SAOLID)AS LOW AS POSSIBLE BY
PROPER TREATMENT .
DM PLANT
PUMP
PUMP
AIR BLOWER
PUMP FLOW CHART OF D. M. PLANT
CW
TANK
DYNA-
-SAND
FILTE
R
M G F A C F S A C
DEGASSED
WATER
TANK
S B A
COLD DM
TANK
F W
TANK
DEMINERALIZATION OF WATER
• THE PROCESS OF DEMINERALIZATION RESULTS IN REMOVAL
OF MINERALS FROM WATER,.
CLEAR WATER IS RECEIVED FROM CLEAR WATER TANK AND THE
MONITORING OF PH (9.7-10.2) AND CONDUCTIVITY (BELOW 150
MICRO SIEMENS/CM) ON DAILY BASIS IS MADE.
DYNA SAND
FILTER
• SINGLE FILTER OF SAND SIZE 0.9 MM .ITS BASIC FUNCTION IS
TURBIDITY REMOVAL, INLET TURBIDITY TO THE FILTER IS 200PPM
AND OUTLET TURBIDITY IS LESS THAN 5 PPM ,ALUM DOSING IS
ALSO
DONE IN THIS FILTER.
MULTI GRATE FILTER
•THIS IS USED FOR THE REMOVAL OF TURBIDITY THE INLET
TURBIDITY
IS 40 PPM AND OUTLET TURBIDITY LESS THAN 5 PPM AT
PRESENT
WE ARE GETTING (0-1) NTU.
ACTIVATED
CARBON
FILTER•THIS IS USED TO ABSORB EXCESS CHLORINE, REMOVAL OF
ORGANIC MATTER AND OIL & GREASE IF ANY. AND CHARCOAL
IS
USED AS ACTIVATED CARBON IN THE ACTIVATED CARBON
FILTER.
STRONG ACID CATION
•THE STRONG ACID CATION RESIN EXCHANGES ALL CATION IN
WATER, THE CATION ASSOCIATED WITH ALKALINITY OR THOSE
COMBINED AS NEUTRAL SALTS ALL ARE REMOVED BY SAC RESIN.
I T HAS A GREATER AFFINITY FOR DIVALENT ION THAN THE
MONOVALENT ION AS A RESULT SELECTIVITY OF CA AND MG IS
MORE THAN FOR NA CONSEQUENTLY THE FRONT PORTIONS OF THE
RESIN BED ARE PREDOMINANT WITH CA & MG, WHILE NA GOES
TO THE TAIL SECTION OF THE RESIN BED AND SO THE NA ION SLIP
OUT OF CATION EXCHANGER DUE TO REGENERATIVE EFFECT OF
FREE
MINERAL ACID
DEGASSER
•IT IS USED FOR CARBON DIOXIDE REMOVAL . CARBONIC ACID
GENERATED IN SAC UNIT IS DECOMPOSED IN WATER+ CARBON
DIOXIDE AND IT ESCAPES OUT FROM THE TOP OF DEGASSER BY
DEGASSER BLOWER , MAXIMUM 6 PPM OF CO2 IS ALLOWED
AFTER DEGASSER UNIT.
STRONG BASE
ANION•SBA RESIN HAS GREATER AFFINITY FOR
IONIC SPECIES, SULFATE AND CHLORIDE THAN FOR THE MOLECULAR
CARBON DIOXIDE AND SILICA AND HIGHER SELECTIVITY FOR
SULFATE ION THAN CHLORIDE ION. AGAIN THERE IS DISTRIBUTION
OF CONTAMINANTS OVER THE RESIN BED WITH FRONT LAYER HIGH
IN SULFATE FOLLOWED BY CHLORIDE AND CARBON DIOXIDE AND
THE SILICA AT TAIL END OF THE BED.
MIXED BED
•THE MIXED BED DEMINERALIZATION PROCESS
CONSISTS OF SAC AND SBA RESIN INTIMATELY MIXED TO
BRING ABOUT THE DEMINERALIZATION OF WATER, IN EFFECT IT IS
MULTIPLE AND RANDOM TWO BED DEMINERALIZATION PAIRS
RESULTING IN VERY HIGH QUALITY OF DM WATER . HERE THE
LEAKAGE OF IONS CAUSED BY THE REGENERATING EFFECT OF
FMA OR OF NAOH FORMED IN THE EXCHANGING PROCESS IS
ABSENT ,THIS IS BECAUSE FMA GENERATED BY SAC RESIN IS
EXCHANGED BY NEIGHBORING SBA RESIN LIKE WISE NAOH
GENERATED BY SBA RESIN IS EXCHANGED BY ADJACENT SAC
RESIN .CATION RESIN IS HEAVIER THAN THE SBA RESIN SO
CATION FORMS THE DOWN LAYER . THE PARAMETERS AT THE
OUTPUT ARE PH-6 TO7,CONDUCTIVITY 2 MICRO SIEMENS/CM,
SILICA 0.02MG/LTR.
COAL
HANDLING
PLANT
coal yard
_
2
0
m
m
_
_
2
o
_
2
o
BOILER # 1 & 2 BUNKER FLOOR
Bunker
Boiler # 1
Bunker
Boiler # 2
Bunker
Boiler # 3
Tripper
Tripper Conveyor
BOILER # 3 BUNKER FLOOR
Tripper
Trolley
Tripper Conveyor
Conveyor No. 64
Reciprocating Feeder 1or 2
Reclain Conveyor
BC - 11831
To Old Circuit #1,#3 To Old Circuit # 2
Vibro Feeder Vibro Feeder
Impactor '+ / -' 6
mm'
Vibrating Screen
Impactor
-20mm Vibro Feeder
Vibrating Screen
'- 6 mm'
Coal
'+6 mm' Coal
'+20 mm' Coal
'BucketElevator
Daybin Conveyor
BC - 33830
Conveyor - 70
Conveyor - 69
Conveyor - 65
Cross Conveyor
NEW COAL CIRCUIT - FLOW CHART (COAL PLANT)
'- 20 mm' Coal
COAL PLANT OPERATION
•COAL IS UNLOADING FROM WAGON TIPPLER IN TWO SIZES I E: -
01. +25 MM AND –75 MM (ABOVE 25MM AND BELOW 75 MM)
02. –25 MM AND + 75MM (BELOW 25MM AND ABOVE 75MM)
• AFTER UNLOADING OF COAL WE FED THE DIFFERENT SIZE COAL
IN DIFFERENT BOILERS. WE HAVE FOUR BOILERS. THREE ARE PF
AND ONE IS FBC. IN PF BOILER WE HAVE USE THE COAL BELOW
THE 20MM. IN FBC BOILER WE HAVE USE THE COAL BELOW THE
6MM.FOR, WHICH VARIOUS EQUIPMENTS HAVE BEEN INSTALLED
IN COAL PLANT AREA.
•TO FEED THE COAL IN PF BOILERS (B#1,3 &4) PUSH THE COAL BY
DOZERS IN ROTORY FEEDERS GRIZZLY SITUATED IN COAL YARDS.
COAL IS COMING FROM RECLAIM CONVEYER TO CONVEYER#64,
THEN VIBRATING SCREEN HAVING SIZE OF 20MM THROUGH VIBRO
FEEDER. LESS THAT 20 MM COAL HAVE FALLEN THROUGH SCREEN
DIRECTLY TO CONVEYER#70 AND OVERSIZE COAL GOING TO
CONVEYER#70 THROUGH COAL IMPACTOR HAVING CAPACITY 120
TPH. FINALLY COAL IS GOING TO THE BUNKERS OF BOILER#1,3&4
THROUGH COMVEYER#70, DAYBIN CONVEYER AND TRIPPER
•TO FEED THE COAL IN FBC BOILER (B#2) PUSH THE COAL BY
DOZERS IN ROTARY FEEDERS GRIZZLY SITUATED IN COAL
YARDS. COAL IS COMING FROM RECLAIM CONVEYER TO
CONVEYER#64, VIBRO FEEDER THEN COAL IMPACTOR
(240TPH) TO TWO NUMBERS VIBRATING SCREENS HAVING
CAPACITY OF 120 TPH EACH THROUGH TWO VIBRO FEEDERS.
COAL HAS FALLEN THROUGH SCREEN DIRECTLY TO
CONVEYER#69(SIZE LESS THAT 6MM) AND OVERSIZE COAL
(ABOVE 6MM) GOING TO CONVEYER#64 THROUGH BUCKET
ELEVATOR HAVING CAPACITY 65 TPH FOR RECRUSHING IN
COAL IMPACTOR WITH FRESH COAL. CLOSE COAL CIRCUIT IS
RUNNING DURING COAL FEEDING IN B#2. FINALLY COAL IS
GOING TO THE BUNKERS THROUGH COMVEYER#70, DAYBIN
CONVEYER AND TRIPPER CONVEYER.
CHP
FLOW CHART
FLOW DIAGRAM FOR COAL HANDLING PLANT
Through Feeder Through Feeder
YES
Wagon Tippler (Crushed to less than 100 mm
size)
Newton In Motion Weighbridge for Weigment of wagons
C
a
o
o
m
C
o
e
e
s
S
z
e
L
e
s
s
h
a
n
5
0
0
m
m
100mm to 75mm and
less than 25mm size coal
collected in & out side the
coal shed for Boiler#1 &
3
75mm to 25mm size
coal collected in
side the coal shed
for Boiler#2
Reclaim Conveyor
Conveyor#64
Vibro Feeder (W)
For Boiler#1 & 3(51)
Vibro Feeder (E)
For Boiler#2(48)
Boiler#1 & 3 Coal
2
0
m
m
s
z
e
Boiler#2 Coal Impactor
(240 MT/HR)
8
m
m
s
z
e
B
U
C
K
E
T
E
L
E
V
A
B
u
n
k
e
r
s
o
Conv#
65
Vibro fdr#49 Vibro fdr#50
51

More Related Content

What's hot

Question & answers on boiler, MED 06209
Question & answers on boiler, MED 06209Question & answers on boiler, MED 06209
Question & answers on boiler, MED 06209Godiva-marwa
 
Introduction of Boiler
Introduction of BoilerIntroduction of Boiler
Introduction of BoilerMarine Study
 
Combustion in a CFBC Boiler
Combustion in a CFBC BoilerCombustion in a CFBC Boiler
Combustion in a CFBC BoilerTapash Nag
 
Boilers and-its-mountings and Boiler accessories
Boilers and-its-mountings and Boiler accessoriesBoilers and-its-mountings and Boiler accessories
Boilers and-its-mountings and Boiler accessoriesRipuranjan Singh
 
Boiler classification and application
Boiler classification and applicationBoiler classification and application
Boiler classification and applicationHaseeb Butt
 
THERMAL POWER ENGINEERING
THERMAL POWER ENGINEERINGTHERMAL POWER ENGINEERING
THERMAL POWER ENGINEERINGSajal Tiwari
 
Steam generation presentatiton
Steam generation presentatitonSteam generation presentatiton
Steam generation presentatitonMat Mett
 
Steam Boilers OR Steam Generators
Steam Boilers OR Steam GeneratorsSteam Boilers OR Steam Generators
Steam Boilers OR Steam GeneratorsHrishikesh Devan
 
A complete presentation on Boiler.
A complete presentation on Boiler.A complete presentation on Boiler.
A complete presentation on Boiler.Anuj Maurya
 
Circulating fluidizing bed combustion Boiler presentation
Circulating fluidizing bed combustion Boiler presentation Circulating fluidizing bed combustion Boiler presentation
Circulating fluidizing bed combustion Boiler presentation Sawan Vaja
 

What's hot (20)

Boiler classification by, Engr REHAN Khan salarzai
Boiler classification by, Engr REHAN Khan salarzaiBoiler classification by, Engr REHAN Khan salarzai
Boiler classification by, Engr REHAN Khan salarzai
 
Question & answers on boiler, MED 06209
Question & answers on boiler, MED 06209Question & answers on boiler, MED 06209
Question & answers on boiler, MED 06209
 
Presentation on CFBC Boilers
Presentation on CFBC BoilersPresentation on CFBC Boilers
Presentation on CFBC Boilers
 
BOILERS
BOILERSBOILERS
BOILERS
 
Introduction of Boiler
Introduction of BoilerIntroduction of Boiler
Introduction of Boiler
 
Combustion in a CFBC Boiler
Combustion in a CFBC BoilerCombustion in a CFBC Boiler
Combustion in a CFBC Boiler
 
Boilers and-its-mountings and Boiler accessories
Boilers and-its-mountings and Boiler accessoriesBoilers and-its-mountings and Boiler accessories
Boilers and-its-mountings and Boiler accessories
 
Boilers
BoilersBoilers
Boilers
 
Boiler classification and application
Boiler classification and applicationBoiler classification and application
Boiler classification and application
 
Boiler Designs
Boiler Designs Boiler Designs
Boiler Designs
 
CFBC Boiler vs Pulverized Fired Boiler
CFBC Boiler vs Pulverized Fired BoilerCFBC Boiler vs Pulverized Fired Boiler
CFBC Boiler vs Pulverized Fired Boiler
 
THERMAL POWER ENGINEERING
THERMAL POWER ENGINEERINGTHERMAL POWER ENGINEERING
THERMAL POWER ENGINEERING
 
fbc boilers
 fbc boilers fbc boilers
fbc boilers
 
Steam generation presentatiton
Steam generation presentatitonSteam generation presentatiton
Steam generation presentatiton
 
Steam Boilers OR Steam Generators
Steam Boilers OR Steam GeneratorsSteam Boilers OR Steam Generators
Steam Boilers OR Steam Generators
 
A complete presentation on Boiler.
A complete presentation on Boiler.A complete presentation on Boiler.
A complete presentation on Boiler.
 
ppt. clg
ppt. clgppt. clg
ppt. clg
 
Circulating fluidizing bed combustion Boiler presentation
Circulating fluidizing bed combustion Boiler presentation Circulating fluidizing bed combustion Boiler presentation
Circulating fluidizing bed combustion Boiler presentation
 
Steam generator part 1
Steam generator part 1Steam generator part 1
Steam generator part 1
 
Boiler and its types
Boiler and its types Boiler and its types
Boiler and its types
 

Viewers also liked

Oscar Jamuar Design Report in McNally sayaji Engineering Limited
Oscar Jamuar Design Report in McNally sayaji Engineering LimitedOscar Jamuar Design Report in McNally sayaji Engineering Limited
Oscar Jamuar Design Report in McNally sayaji Engineering LimitedOscar Jamuar
 
copper mould tube-LMM GROUP CO., LTD.
copper mould tube-LMM GROUP CO., LTD.copper mould tube-LMM GROUP CO., LTD.
copper mould tube-LMM GROUP CO., LTD.LMM GROUP CO., LTD.
 
wagon tippler with side arm charger - LMM GROUP
wagon tippler with side arm charger - LMM GROUPwagon tippler with side arm charger - LMM GROUP
wagon tippler with side arm charger - LMM GROUPLMM GROUP CO., LTD.
 
Chpppt 100617141038-phpapp01
Chpppt 100617141038-phpapp01Chpppt 100617141038-phpapp01
Chpppt 100617141038-phpapp01Aashutosh Rathore
 
Ppt of tursuperbocharger
Ppt of tursuperbochargerPpt of tursuperbocharger
Ppt of tursuperbochargerArvind Yadav
 
A Brief Introduction to Boilers
A Brief Introduction to BoilersA Brief Introduction to Boilers
A Brief Introduction to BoilersSATYAKAM MOHAPATRA
 
Coal Handling Plants....
Coal Handling Plants....Coal Handling Plants....
Coal Handling Plants....Vipul Sinha
 
Diesel Locomotive Works (DLW)
 Diesel Locomotive Works (DLW) Diesel Locomotive Works (DLW)
Diesel Locomotive Works (DLW)Neha Gethe
 
Overhead Crane Safety and Inspection Requirements by NPCA
Overhead Crane Safety and Inspection Requirements by NPCAOverhead Crane Safety and Inspection Requirements by NPCA
Overhead Crane Safety and Inspection Requirements by NPCAAtlantic Training, LLC.
 

Viewers also liked (19)

Oscar Jamuar Design Report in McNally sayaji Engineering Limited
Oscar Jamuar Design Report in McNally sayaji Engineering LimitedOscar Jamuar Design Report in McNally sayaji Engineering Limited
Oscar Jamuar Design Report in McNally sayaji Engineering Limited
 
RMHS Manual 2.1
RMHS Manual 2.1RMHS Manual 2.1
RMHS Manual 2.1
 
copper mould tube-LMM GROUP CO., LTD.
copper mould tube-LMM GROUP CO., LTD.copper mould tube-LMM GROUP CO., LTD.
copper mould tube-LMM GROUP CO., LTD.
 
wagon tippler with side arm charger - LMM GROUP
wagon tippler with side arm charger - LMM GROUPwagon tippler with side arm charger - LMM GROUP
wagon tippler with side arm charger - LMM GROUP
 
Chpppt 100617141038-phpapp01
Chpppt 100617141038-phpapp01Chpppt 100617141038-phpapp01
Chpppt 100617141038-phpapp01
 
Ppt of tursuperbocharger
Ppt of tursuperbochargerPpt of tursuperbocharger
Ppt of tursuperbocharger
 
Locomotive
Locomotive Locomotive
Locomotive
 
A Brief Introduction to Boilers
A Brief Introduction to BoilersA Brief Introduction to Boilers
A Brief Introduction to Boilers
 
Belt conveyor _2_
Belt conveyor _2_Belt conveyor _2_
Belt conveyor _2_
 
High Pressure Boilers
High Pressure BoilersHigh Pressure Boilers
High Pressure Boilers
 
Coal Handling Plants....
Coal Handling Plants....Coal Handling Plants....
Coal Handling Plants....
 
Diesel Locomotive Works (DLW)
 Diesel Locomotive Works (DLW) Diesel Locomotive Works (DLW)
Diesel Locomotive Works (DLW)
 
Overhead Crane
Overhead CraneOverhead Crane
Overhead Crane
 
Norma cmaa 70
Norma cmaa 70Norma cmaa 70
Norma cmaa 70
 
Overhead Crane Safety by FHM
Overhead Crane Safety by FHMOverhead Crane Safety by FHM
Overhead Crane Safety by FHM
 
Crane Operations by EHS Compliance
Crane Operations by EHS ComplianceCrane Operations by EHS Compliance
Crane Operations by EHS Compliance
 
Overhead Crane Safety and Inspection Requirements by NPCA
Overhead Crane Safety and Inspection Requirements by NPCAOverhead Crane Safety and Inspection Requirements by NPCA
Overhead Crane Safety and Inspection Requirements by NPCA
 
Overhead Crane Operators by
Overhead  Crane Operators byOverhead  Crane Operators by
Overhead Crane Operators by
 
Safe Operation and Explosions in Boilers
Safe Operation and Explosions in BoilersSafe Operation and Explosions in Boilers
Safe Operation and Explosions in Boilers
 

Similar to Boiler & Co-Generation Plant Overview

Thermal power plant
Thermal power plantThermal power plant
Thermal power plantRabi Kumar
 
Thermal Power plant
Thermal Power plantThermal Power plant
Thermal Power plantAvnish Anshu
 
SUMMER TRANNING REPORT PPT
SUMMER TRANNING REPORT PPTSUMMER TRANNING REPORT PPT
SUMMER TRANNING REPORT PPTAmanPandey0208
 
Thermal Power plant familarisation & its Auxillaries
Thermal Power plant familarisation & its AuxillariesThermal Power plant familarisation & its Auxillaries
Thermal Power plant familarisation & its AuxillariesVaibhav Paydelwar
 
Competitive clean coal power utilizing pressurized fluidized bed combined cyc...
Competitive clean coal power utilizing pressurized fluidized bed combined cyc...Competitive clean coal power utilizing pressurized fluidized bed combined cyc...
Competitive clean coal power utilizing pressurized fluidized bed combined cyc...aoopee
 
boiler and cogeneration training material
boiler and cogeneration training materialboiler and cogeneration training material
boiler and cogeneration training materialHarshit Kumar Mishra
 
Boiler thermalpowerplants 12898051220529-phpapp02
Boiler thermalpowerplants 12898051220529-phpapp02Boiler thermalpowerplants 12898051220529-phpapp02
Boiler thermalpowerplants 12898051220529-phpapp02akjshare
 
BOILER PRESENTATION ON 21.10.14 1.pdf
BOILER PRESENTATION ON 21.10.14 1.pdfBOILER PRESENTATION ON 21.10.14 1.pdf
BOILER PRESENTATION ON 21.10.14 1.pdfPrasadKandukuri4
 
Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...
Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...
Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...Shubham Thakur
 
Energy conservation boiler
Energy conservation boilerEnergy conservation boiler
Energy conservation boilerMANJUNATH N
 
Thermal Power Plants
Thermal Power PlantsThermal Power Plants
Thermal Power Plantspeeyush95
 
SIP Presentation
SIP PresentationSIP Presentation
SIP PresentationAmay Jain
 
Power plant engineering micro project
Power plant engineering micro projectPower plant engineering micro project
Power plant engineering micro projectSumitSutar6
 
1727092 634985076667011250
1727092 6349850766670112501727092 634985076667011250
1727092 634985076667011250akshar56
 
Soot Blowing Optimization- Field Experience
Soot Blowing Optimization- Field ExperienceSoot Blowing Optimization- Field Experience
Soot Blowing Optimization- Field ExperiencePooja Agarwal
 

Similar to Boiler & Co-Generation Plant Overview (20)

Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
Thermal Power plant
Thermal Power plantThermal Power plant
Thermal Power plant
 
SUMMER TRANNING REPORT PPT
SUMMER TRANNING REPORT PPTSUMMER TRANNING REPORT PPT
SUMMER TRANNING REPORT PPT
 
Thermal Power plant familarisation & its Auxillaries
Thermal Power plant familarisation & its AuxillariesThermal Power plant familarisation & its Auxillaries
Thermal Power plant familarisation & its Auxillaries
 
Competitive clean coal power utilizing pressurized fluidized bed combined cyc...
Competitive clean coal power utilizing pressurized fluidized bed combined cyc...Competitive clean coal power utilizing pressurized fluidized bed combined cyc...
Competitive clean coal power utilizing pressurized fluidized bed combined cyc...
 
boiler and cogeneration training material
boiler and cogeneration training materialboiler and cogeneration training material
boiler and cogeneration training material
 
Boiler thermalpowerplants 12898051220529-phpapp02
Boiler thermalpowerplants 12898051220529-phpapp02Boiler thermalpowerplants 12898051220529-phpapp02
Boiler thermalpowerplants 12898051220529-phpapp02
 
BOILER PRESENTATION ON 21.10.14 1.pdf
BOILER PRESENTATION ON 21.10.14 1.pdfBOILER PRESENTATION ON 21.10.14 1.pdf
BOILER PRESENTATION ON 21.10.14 1.pdf
 
Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...
Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...
Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...
 
Boiler and cogeneration
Boiler and cogenerationBoiler and cogeneration
Boiler and cogeneration
 
hindalco power
hindalco powerhindalco power
hindalco power
 
Thermal power plants
Thermal power plantsThermal power plants
Thermal power plants
 
Kstps ppt
Kstps pptKstps ppt
Kstps ppt
 
steam pow rplant
steam pow  rplantsteam pow  rplant
steam pow rplant
 
Energy conservation boiler
Energy conservation boilerEnergy conservation boiler
Energy conservation boiler
 
Thermal Power Plants
Thermal Power PlantsThermal Power Plants
Thermal Power Plants
 
SIP Presentation
SIP PresentationSIP Presentation
SIP Presentation
 
Power plant engineering micro project
Power plant engineering micro projectPower plant engineering micro project
Power plant engineering micro project
 
1727092 634985076667011250
1727092 6349850766670112501727092 634985076667011250
1727092 634985076667011250
 
Soot Blowing Optimization- Field Experience
Soot Blowing Optimization- Field ExperienceSoot Blowing Optimization- Field Experience
Soot Blowing Optimization- Field Experience
 

Boiler & Co-Generation Plant Overview

  • 2. MAJOR CONTITUENTS DM PLANT COAL HANDLIING PLANT CO-GENERATION PLANT ASH ANDLING PLANT BOIILER
  • 3. INTRODUCTION TO BOILER  ENCLOSED PRESSURE VESSEL  HEAT GENERATED BY COMBUSTION OF FUEL IS TRANSFERRED TO WATER TO BECOME STEAM  PROCESS: EVAPORATION  STEAM VOLUME INCREASES TO 1,600 TIMES FROM WATER AND PRODUCES TREMENDOUS FORCE  BOILER TO BE EXTREMELY 3 What is a boiler?
  • 4. COGENERATION PLANT VIEW 20ATA 11ATA 3.9ATA 11ATA 3.9ATA CONDENSER CONDENSER 5 BAR TO PROCESS M ~ 20ATA ~~ ~ H.P.HTR 35 MW 6 MW 31.4 MW 5.6 MW 54 ATA COMMON HEADER 43ATAHEADER 54 ATA COMMON HEADER To Economiser From BFP B#4 150 TPH Reynolds Digestion 1, 3 & 4 B#3 140 TPH B#2 80 TPH B#1 80 TPH ~ Auxiliary Steam 4 BAR STEAM 6 MW 600/250 12 Bar steam to Dig-2 7BarHdr 7 BAR TO PROCESS 250 PSI from Hi- Tech
  • 5. COGENERATI ON PLANT•CO-GENERATION MEANS SIMULTANEOUSLY PRODUCTION OF POWER & USEFUL THERMAL ENERGY FOR PROCESS FROM THE SAME PRIMARY ENERGY SOURCE. AS PER MINISTRY OF POWER CO- GENERATION IS DEFINED AS ONE WHICH SIMULTANEOUSLY PRODUCES TWO OR MORE FORMS OF USEFUL ENERGY SUCH AS ELECTRIC POWER AND STEAM, ELECTRIC POWER & SHAFT (MECHANICAL) POWER ETC... IT ALSO DEFINES ANY FACILITY THAT USES WASTE INDUSTRIAL HEAT FOR POWER GENERATION BY SUPPLEMENTING HEAT, NOT MORE THAN 50%, FROM ANY FOSSIL FUEL. • AT HINDALCO WE ARE HAVING THE COGENERATION PLANT IN WHICH WE USE THE STEAM FOR THE PROCESS REQUIREMENT AS WELL AS POWER GENERATION
  • 6. WHAT IS A BOILER  ANY CLOSED VESSEL EXCEEDING 22.75 LITRES IN CAPACITY WHICH IS USED EXCLUSIVELY FOR GENERATING STEAM UNDER PRESSURE INCLUDES ANY MOUNTING AND OTHER FITTING ATTACHED TO SUCH VESSEL WHICH IS FULLY OR PARTIALLY UNDER PRESSURE WHEN SHUTOFF
  • 8. ID FAN • THE FUNCTION OF THIS FAN IS TO MAINTAIN THE DRAFT IN THE FURNACE AND CARAY OUT FLUE GAS OF THE FURNACE AND MAINTAIN THE NEGATIVE VALUE OF PRESSURE INSIDE THE FURNACE PA FAN • THE FUNCTION OF THIS FAN IS TO HEAT AND CARRY COAL FROM MILL TO THE FURNACE ( PULVERISHED COAL). FD FAN • THE FAN IS USED FOR THE PURPOSE OF SUPPLYING EXCESS AIR IN THE FURNACE FOR COMPLETE COMBUSTION OF COAL
  • 9. AUXILIARIES OF BOILER • The function of air preheater is to heat the incoming air from the Primary air fan which is supplied to the mills, Basically we are using this air as the medium for heating and conveying the Pulverized coal. The air preheater is located in the second pass of the Boiler and it gains its heat by the flue gases and gives the heat to the incoming air. AIR PREHEATER • The Economizer is the located in the second pass of the Boiler its function is to utilize the heat of flue gases coming out of the first pass of the Boiler which have done their work of producing steam from the Boiler. The economizer utilizes this heat of Flue gases which would otherwise be wasted to the atmosphere resulting in dry flue gas loss and reducing the efficiency of the Boiler. ECONOMISER
  • 10. AUXILIARIES OF BOILER • The function of the mill is to grind the coal in the required size, like the size of coal required in the Pulverized fuel fired Boilers is of 75 microns so to achieve that size the mills are used. The mills used in the cogeneration plant are of Ball mill and Bowl mill type. MILL • The function of super heater is to superheat the Dry saturated steam coming from the drum and convert it into the superheated from so that chances of moisture is totally eliminated and the Enthalpy of steam is increased. SUPERHEATERS
  • 11. AUXILIARIES OF BOILER • The function of the Electrostatic Precipitator is to collect the ash coming out of the Boiler and send it to the ash silo from where it is further utilized as per requirement. The ESP works on the principle of Corona where the Ash particles are charged by Direct Current and further collected at the collecting electrodes and than removed with the help of rappers and collected in the ash silos. ESP
  • 12. DETAILS OF BOILERS 12 BOILERS TYPE CAPACITY PR. KG/CM2 TEMP. 0 C YEAR OF COMMISSI ONING MAKE BOILER # 1 FRONT FIRING (PF) 80 (TPH) 52.5 450 1986 WIL PUNE BOILER # 2 AFBC 80 (TPH) 52.5 450 1989 BHEL, TRICHI BOILER # 3 TANGENTIAL FIRING (PF) 140 (TPH) 111 535 1996 BHEL, TRICHI BOILER # 4 TANGENTIAL FIRING (PF) 150 (TPH) 111 535 2004 BHEL, TRICHI STEAM GENERATION PER HOUR = 450 MT STEAM RECEIVED FROM HI-TECH = 25-35 MT / HR
  • 13. 13 DM water Deaerat or BFP Coal to feeder s by Dozer Coal Convey ors Rotory Coal Feeder s Furnace Coal Transport ing Line Steam Generati on Flue Gas to ESP PA Fa n FD Fa n Econo miser Water Circuit Coal Yard Coal sizing circuit for -6mm size coal Coal Bunkers ID Fan Ash Recycling feeder-2 No. Steam to Power Plant / Process Exchange of Heat Energy Feeder Running YES Ash Hopper NOAsh drain Ash Recycling feeder-2 No. Process Flow of Boiler#2
  • 15. AFBC BOILER 15 •AFBC – ATMOSPHERIC FLUIDIZED BED COMBUSTION •DEFINITION WHEN AIR OR GAS IS PASSED THROUGH AN INERT BED OF SOLID PARTICLE SUCH AS SAND OR CRUSHED REFRACTORY, THE AIR STARTS BUBBLING THROUGH THE BED AND PARTICLE ATTAIN A STATE OF HIGH TURBULENCE. UNDER SUCH CONDITIONS, THE BED ASSUMES THE APPEARANCE OF A FLUID AND EXHIBITS THE PROPERTIES ASSOCIATED WITH A FLUID AND
  • 16. FBC MECHANISM 16 IF THE BED MATERIAL IN FLUIDIZED STATE IS HEATED TO THE IGNITION TEMPERATURE OF THE FUEL AND THE FUEL IS INJECTED CONTINUOUSLY INTO THE BED, THE FUEL WILL BURN RAPIDLY AND BED ATTAINS A UNIFORM TEMPERATURE DUE TO
  • 17. AFBC BOILER - ADVANTAGE 17 • FLEXIBLE IN THEIR ABILITY TO BURN A WIDE RANGE OF FUEL. • DOES NOT REQUIRE OIL SUPPORT FOR START UP OR LOW LOAD STABILIZATION. • BY ADDING OF LIMESTONE IN THE BED STRINGENT SOX EMISSION CONTROL IS POSSIBLE WITHOUT EXPENSING DOWN STREAM SCRUBBER EQUIPMENT • AUXILIARY POWER CONSUMPTION IS LOW. • BETTER LOAD RESPONSE AND CAN BE VARIED FROM 20% TO 100% OF NCR. • LESS INITIAL COST. • EASY IN OPERATION. • C & I REQUIREMENT FOR FBC ARE MINIMAL. NO BMS REQUIRED
  • 18. AFBC BOILER - DISADVANTAGE 18 • SUITABLE FOR LOW AND MEDIUM CAPACITY ONLY. • MORE MAINTENANCE COST DUE TO HIGH EROSION OF TUBES. • LOWER EFFICIENCY. • MORE EFFORTS REQUIRED WHEN IT IS INITIALLY START UP WITH CHARCOAL.
  • 19. FUEL FEEDING SYSTEM 19 •Fuel is evenly distributed by judicious location of feed points for burning most of the volatiles and carbon within the bed and to avoid localized fuel concentration Comp-1Comp-2Comp-3Comp-4 Coal feed points Recycle ash feed points Distributor plates
  • 20. AIR DISTRIBUTION 20 •PROPER AIR DISTRIBUTOR IS REQUIRED TO ENSURE UNIFORM DISTRIBUTION OF AIR ACROSS BED CROSS SECTION Comp-1Comp-2Comp-3Comp-4 Nozzles are provided across the bed for proper air distribution
  • 21. BED TEMPERATURE & HEIGHT 21 •BED TEMPERATURE: - FBC NORMALLY OPERATES AT A TEMPERATURE RANGE 750-950º C FOR COAL • BED HEIGHT: - DETERMINED BY THE NEED TO SUBMERGE HEAT EXCHANGER TUBES AND IN CASE OF HIGH SULPHUR COAL THE VOLUME REQUIREMENT FOR EFFECTIVE SULPHUR CAPTURE FOR MOST OF THE INDIAN FUELS A SHALLOW BED LESS THAN 1000 MM IS ADEQUATE.
  • 22. BED TEMPERATURE & HEIGHT 22 Water Heade r Air from FD Fan Coal Transporting Line Primar y Air Bed material in Fluidization state
  • 23.
  • 24. BLOCK DIAGRAM OF AFBC BOILER 24
  • 25. TECHNICAL DATA 25 SN PARAMETER UNIT CAPACITY 1 Heating Surface M² 3426.9 2 Steam Flow TPH 80 3 Steam Pressure Kg/Cm ² 52.5 4 Steam Temperature Deg C 450±5 5 Feed Water Temp. Deg C 105 6 Fluidized Air Temp Deg C 130 7 Boiler Efficiency % 82±1.5 Coal Size: -(-) 6 mm to Furnace with maximum 20% fines
  • 26. 26 Boiler Flue gas Steam Output Efficiency = 100 – (1+2+3+4+5+6+7+8) (by In Direct Method) Air Fuel Input, 100% 1. Dry Flue gas loss 2. H2 loss 3. Moisture in fuel 4. Moisture in air 5. CO loss 7. Fly ash loss 6. Surface loss 8. Bottom ash loss WHAT ARE THE LOSSES THAT OCCUR IN A BOILER?
  • 27. 27 INTERMITTENT BLOWDOWN • THE INTERMITTENT BLOWN DOWN IS GIVEN BY MANUALLY OPERATING A VALVE FITTED TO DISCHARGE PIPE AT THE LOWEST POINT OF BOILER SHELL TO REDUCE PARAMETERS (TDS OR CONDUCTIVITY, PH, SILICA ETC) WITHIN PRESCRIBED LIMITS SO THAT STEAM QUALITY IS NOT LIKELY TO BE AFFECTED • TDS LEVEL KEEPS VARYING • FLUCTUATIONS OF THE WATER LEVEL IN THE BOILER. • SUBSTANTIAL AMOUNT OF HEAT ENERGY IS
  • 28. 28 •WHEN WATER EVAPORATES •DISSOLVED SOLIDS GETS CONCENTRATED •SOLIDS PRECIPITATES •COATING OF TUBES •REDUCES THE HEAT TRANSFER RATE Why Boiler Blow Down ?
  • 30. PULVERIZED FUEL BOILER 30 Tangential firing Coal is pulverised to a fine powder, so that less than 2% is +300 microns, and 70-75% is below 75 microns. Coal is blown with part of the combustion air into the boiler plant through a series of burner nozzles. • Combustion takes place at temperatures from 1300-1700°C • Particle residence time in the boiler is typically 2-5 seconds • One of the most popular system for firing pulverized coal is the tangential firing using four burners corner to corner to create a fire ball at the center of the furnace.
  • 31. ADVANTAGES  ITS ABILITY TO BURN ALL RANKS OF COAL FROM ANTHRACITIC TO LIGNITE, AND IT PERMITS COMBINATION FIRING (I.E., CAN USE COAL, OIL AND GAS IN SAME BURNER). BECAUSE OF THESE ADVANTAGES, THERE IS WIDESPREAD USE OF PULVERIZED COAL FURNACES. DISADVANTAGES  HIGH POWER DEMAND FOR PULVERIZING  REQUIRES MORE MAINTENANCE, FLY ASH EROSION AND POLLUTION COMPLICATE UNIT OPERATION. 31 Pulverized Fuel Boiler
  • 33. FUELS SYSTEM IN PF BOILER#1 33 BALL MILL:- • IT IS FRONT WALL FIRED PULVERIZED FUEL BOILER HAVING FOUR BURNERS ON FRONT WALL. • BOILER NO. 1 IS PULVERIZED FUEL BOILERS. • OIL GUNS IS PROVIDED FOR START UP AND SUPPORT AT TWO LEVELS. • MINUS 20 MM SIZE COAL IS FED TO THE MILL THROUGH THE TWO NUMBER VOLUMETRIC COAL FEEDERS. AS THE MILL ROTATES, THE COAL IN THE MILL IS PULVERISED BY THE CRUSHING AND GRINDING ACTION OF CASCADING STEEL BALLS. PREHEATED AIR WHICH COMES FROM PRIMARY AIR FAN, AND FUEL MIXTURE, AFTER PASSING THROUGH THE CLASSIFIERS, ENTERS THE COAL CONDUITS AND PASSES ON
  • 34. BALL MILL OF PF BOILER#1 34
  • 35. FUELS SYSTEM IN PF BOILER#3 & 4 35 BOILER NO. 3 & 4 IS TANGENTIAL FIRED PULVERIZED FUEL BOILER HAVING FOUR ELEVATION BURNERS. IN EACH ELEVATION FOUR COAL BURNER ARE AVAILABLE. FOUR NUMBER BOWL MILLS ARE THERE TO CRUSH THE 20 MM SIZE COAL. OUT OF THESE FOUR MILLS, THREE MILLS SHOULD BE IN SERVICE FOR FULL STEAM LOAD. BOWL AND ROLLERS ARRANGEMENTS ARE THERE TO CRUSH THE 20-MM SIZE COAL INSIDE THE MILL. HOT AIR FROM AIR PREHEATERS SUCKED BY THE
  • 36. QUALITY OF COAL 36 Coal Feed Size BOILER #1, 3 & 4: 100% (-) 20 MM TO MILL 70% (-) 200 MESH TO FURNACE BOILER#2 : (-) 6 MM WITH 20% FINES TO MOISTURE VOLATILE MATTER ASH FIXED CARBON CALORIFIC VALUE 10%-16% 21%-26% 35%-38% 25%-30% 2900-3500 KCAL/KG Proximate Analysis Values
  • 37. 37 . REDUCE STACK TEMPERATURE 22O C REDUCTION IN FLUE GAS TEMPERATURE INCREASES BOILER EFFICIENCY BY 1% . COMBUSTION AIR PREHEATING . FEED WATER PREHEATING USING ECONOMIZER6OC RAISE IN FEED WATER TEMPERATURE, BY ECONOMISER/CONDENSATE RECOVERY, CORRESPONDS TO A 1% SAVING IN FUEL CONSUMPTION IN ORDER TO IMPROVE THERMAL EFFICIENCY BY 1%, THE COMBUSTION AIR TEMP. MUST BE RAISED BY 20 DEG C. ENERGY CONSERVATION OPPORTUNITIES IN BOILER . INCOMPLETE COMBUSTION
  • 38. 38 Energy Conservation Opportunities in Boiler . CONTROL EXCESS AIR For every 1% reduction in excess air ,0.6% rise in efficiency. . RADIATION AND CONVECTION HEAT LOSS . AUTOMATIC BLOWDOWN CONTROL . REDUCTION OF SCALING AND SOOT LOSSES . REDUCTION OF BOILER STEAM PRESSURE
  • 39. Performance of a Boiler hg -the enthalpy of saturated steam in kcal/kg of steam hf -the enthalpy of feed water in kcal/kg of water Boiler Efficiency: Direct Method Boiler efficiency () = Heat output Heat input x 100 Q sx (hg – hf) Q x GCV x 100= PARAMETERS TO BE MONITORED: - QUANTITY OF STEAM GENERATED PER HOUR (QS) IN KG/HR - QUANTITY OF FUEL USED PER HOUR (Q) IN KG/HR - THE WORKING PRESSURE (IN KG/CM2(G)) AND SUPERHEAT TEMPERATURE (OC), IF ANY - THE TEMPERATURE OF FEED WATER (OC) - TYPE OF FUEL AND GROSS CALORIFIC VALUE OF THE FUEL (GCV) IN KCAL/KG OF FUEL
  • 40. DM PLANT  THE WATER TO BE FEED IN BOILER FOR STEAM GENERATION MUST BE DEMINERALISED AS PER SHOULD NOT CONTAIN ANY DISSOLVED SOLID SUCH AS SILICA OR CHLORIDES AND CARBONATES WHICH RESULTS IN SLUDEFE FORMATION AND SCALE FORMATION IN THE BOILER RESULTING IN LOW EFFICIENCY OF BOILER ,LOW RATE OF STEAM GENERATION AND WASTAGE AND MORE CONSUMPTION OF FUEL ACCOMPANING WITH CORROSION OF INER BODY SURFACE OR CAN SAY METAL OF BOILER BODY .  SO FOR THIS PURPOSE WATER HAS TO BE TREATED FIRST AND SHOULD MAINTAIN TDS(TOTAL DISSOLVED SAOLID)AS LOW AS POSSIBLE BY PROPER TREATMENT .
  • 41. DM PLANT PUMP PUMP AIR BLOWER PUMP FLOW CHART OF D. M. PLANT CW TANK DYNA- -SAND FILTE R M G F A C F S A C DEGASSED WATER TANK S B A COLD DM TANK F W TANK
  • 42. DEMINERALIZATION OF WATER • THE PROCESS OF DEMINERALIZATION RESULTS IN REMOVAL OF MINERALS FROM WATER,. CLEAR WATER IS RECEIVED FROM CLEAR WATER TANK AND THE MONITORING OF PH (9.7-10.2) AND CONDUCTIVITY (BELOW 150 MICRO SIEMENS/CM) ON DAILY BASIS IS MADE. DYNA SAND FILTER • SINGLE FILTER OF SAND SIZE 0.9 MM .ITS BASIC FUNCTION IS TURBIDITY REMOVAL, INLET TURBIDITY TO THE FILTER IS 200PPM AND OUTLET TURBIDITY IS LESS THAN 5 PPM ,ALUM DOSING IS ALSO DONE IN THIS FILTER.
  • 43. MULTI GRATE FILTER •THIS IS USED FOR THE REMOVAL OF TURBIDITY THE INLET TURBIDITY IS 40 PPM AND OUTLET TURBIDITY LESS THAN 5 PPM AT PRESENT WE ARE GETTING (0-1) NTU. ACTIVATED CARBON FILTER•THIS IS USED TO ABSORB EXCESS CHLORINE, REMOVAL OF ORGANIC MATTER AND OIL & GREASE IF ANY. AND CHARCOAL IS USED AS ACTIVATED CARBON IN THE ACTIVATED CARBON FILTER.
  • 44. STRONG ACID CATION •THE STRONG ACID CATION RESIN EXCHANGES ALL CATION IN WATER, THE CATION ASSOCIATED WITH ALKALINITY OR THOSE COMBINED AS NEUTRAL SALTS ALL ARE REMOVED BY SAC RESIN. I T HAS A GREATER AFFINITY FOR DIVALENT ION THAN THE MONOVALENT ION AS A RESULT SELECTIVITY OF CA AND MG IS MORE THAN FOR NA CONSEQUENTLY THE FRONT PORTIONS OF THE RESIN BED ARE PREDOMINANT WITH CA & MG, WHILE NA GOES TO THE TAIL SECTION OF THE RESIN BED AND SO THE NA ION SLIP OUT OF CATION EXCHANGER DUE TO REGENERATIVE EFFECT OF FREE MINERAL ACID
  • 45. DEGASSER •IT IS USED FOR CARBON DIOXIDE REMOVAL . CARBONIC ACID GENERATED IN SAC UNIT IS DECOMPOSED IN WATER+ CARBON DIOXIDE AND IT ESCAPES OUT FROM THE TOP OF DEGASSER BY DEGASSER BLOWER , MAXIMUM 6 PPM OF CO2 IS ALLOWED AFTER DEGASSER UNIT. STRONG BASE ANION•SBA RESIN HAS GREATER AFFINITY FOR IONIC SPECIES, SULFATE AND CHLORIDE THAN FOR THE MOLECULAR CARBON DIOXIDE AND SILICA AND HIGHER SELECTIVITY FOR SULFATE ION THAN CHLORIDE ION. AGAIN THERE IS DISTRIBUTION OF CONTAMINANTS OVER THE RESIN BED WITH FRONT LAYER HIGH IN SULFATE FOLLOWED BY CHLORIDE AND CARBON DIOXIDE AND THE SILICA AT TAIL END OF THE BED.
  • 46. MIXED BED •THE MIXED BED DEMINERALIZATION PROCESS CONSISTS OF SAC AND SBA RESIN INTIMATELY MIXED TO BRING ABOUT THE DEMINERALIZATION OF WATER, IN EFFECT IT IS MULTIPLE AND RANDOM TWO BED DEMINERALIZATION PAIRS RESULTING IN VERY HIGH QUALITY OF DM WATER . HERE THE LEAKAGE OF IONS CAUSED BY THE REGENERATING EFFECT OF FMA OR OF NAOH FORMED IN THE EXCHANGING PROCESS IS ABSENT ,THIS IS BECAUSE FMA GENERATED BY SAC RESIN IS EXCHANGED BY NEIGHBORING SBA RESIN LIKE WISE NAOH GENERATED BY SBA RESIN IS EXCHANGED BY ADJACENT SAC RESIN .CATION RESIN IS HEAVIER THAN THE SBA RESIN SO CATION FORMS THE DOWN LAYER . THE PARAMETERS AT THE OUTPUT ARE PH-6 TO7,CONDUCTIVITY 2 MICRO SIEMENS/CM, SILICA 0.02MG/LTR.
  • 47. COAL HANDLING PLANT coal yard _ 2 0 m m _ _ 2 o _ 2 o BOILER # 1 & 2 BUNKER FLOOR Bunker Boiler # 1 Bunker Boiler # 2 Bunker Boiler # 3 Tripper Tripper Conveyor BOILER # 3 BUNKER FLOOR Tripper Trolley Tripper Conveyor Conveyor No. 64 Reciprocating Feeder 1or 2 Reclain Conveyor BC - 11831 To Old Circuit #1,#3 To Old Circuit # 2 Vibro Feeder Vibro Feeder Impactor '+ / -' 6 mm' Vibrating Screen Impactor -20mm Vibro Feeder Vibrating Screen '- 6 mm' Coal '+6 mm' Coal '+20 mm' Coal 'BucketElevator Daybin Conveyor BC - 33830 Conveyor - 70 Conveyor - 69 Conveyor - 65 Cross Conveyor NEW COAL CIRCUIT - FLOW CHART (COAL PLANT) '- 20 mm' Coal
  • 48. COAL PLANT OPERATION •COAL IS UNLOADING FROM WAGON TIPPLER IN TWO SIZES I E: - 01. +25 MM AND –75 MM (ABOVE 25MM AND BELOW 75 MM) 02. –25 MM AND + 75MM (BELOW 25MM AND ABOVE 75MM) • AFTER UNLOADING OF COAL WE FED THE DIFFERENT SIZE COAL IN DIFFERENT BOILERS. WE HAVE FOUR BOILERS. THREE ARE PF AND ONE IS FBC. IN PF BOILER WE HAVE USE THE COAL BELOW THE 20MM. IN FBC BOILER WE HAVE USE THE COAL BELOW THE 6MM.FOR, WHICH VARIOUS EQUIPMENTS HAVE BEEN INSTALLED IN COAL PLANT AREA. •TO FEED THE COAL IN PF BOILERS (B#1,3 &4) PUSH THE COAL BY DOZERS IN ROTORY FEEDERS GRIZZLY SITUATED IN COAL YARDS. COAL IS COMING FROM RECLAIM CONVEYER TO CONVEYER#64, THEN VIBRATING SCREEN HAVING SIZE OF 20MM THROUGH VIBRO FEEDER. LESS THAT 20 MM COAL HAVE FALLEN THROUGH SCREEN DIRECTLY TO CONVEYER#70 AND OVERSIZE COAL GOING TO CONVEYER#70 THROUGH COAL IMPACTOR HAVING CAPACITY 120 TPH. FINALLY COAL IS GOING TO THE BUNKERS OF BOILER#1,3&4 THROUGH COMVEYER#70, DAYBIN CONVEYER AND TRIPPER
  • 49. •TO FEED THE COAL IN FBC BOILER (B#2) PUSH THE COAL BY DOZERS IN ROTARY FEEDERS GRIZZLY SITUATED IN COAL YARDS. COAL IS COMING FROM RECLAIM CONVEYER TO CONVEYER#64, VIBRO FEEDER THEN COAL IMPACTOR (240TPH) TO TWO NUMBERS VIBRATING SCREENS HAVING CAPACITY OF 120 TPH EACH THROUGH TWO VIBRO FEEDERS. COAL HAS FALLEN THROUGH SCREEN DIRECTLY TO CONVEYER#69(SIZE LESS THAT 6MM) AND OVERSIZE COAL (ABOVE 6MM) GOING TO CONVEYER#64 THROUGH BUCKET ELEVATOR HAVING CAPACITY 65 TPH FOR RECRUSHING IN COAL IMPACTOR WITH FRESH COAL. CLOSE COAL CIRCUIT IS RUNNING DURING COAL FEEDING IN B#2. FINALLY COAL IS GOING TO THE BUNKERS THROUGH COMVEYER#70, DAYBIN CONVEYER AND TRIPPER CONVEYER.
  • 50. CHP FLOW CHART FLOW DIAGRAM FOR COAL HANDLING PLANT Through Feeder Through Feeder YES Wagon Tippler (Crushed to less than 100 mm size) Newton In Motion Weighbridge for Weigment of wagons C a o o m C o e e s S z e L e s s h a n 5 0 0 m m 100mm to 75mm and less than 25mm size coal collected in & out side the coal shed for Boiler#1 & 3 75mm to 25mm size coal collected in side the coal shed for Boiler#2 Reclaim Conveyor Conveyor#64 Vibro Feeder (W) For Boiler#1 & 3(51) Vibro Feeder (E) For Boiler#2(48) Boiler#1 & 3 Coal 2 0 m m s z e Boiler#2 Coal Impactor (240 MT/HR) 8 m m s z e B U C K E T E L E V A B u n k e r s o Conv# 65 Vibro fdr#49 Vibro fdr#50
  • 51. 51