SlideShare a Scribd company logo
1 of 10
Download to read offline
Enabling High Efficiency and Reliable Wind Power Projects
2


    Policy and Regulatory
                                                                                                            WinDForce Achievements
    1. MERC: Determination of Transmission Tariff for Intra-State Transmission
                                                                                                               Wind Resource Assessment for 3000+
    System (InSTS) for FY 2012-13
                                                                                                              MW
                                                                                                             Owner’s Engineer for 250+ MW
                  Item Description                         FY 2011-12              FY 2012-13
                                                                                                             Technical Due Diligence for 900+ MW
     Transmission Tariff
     (long term/ medium term)
                                                       5414 Rs/ MW/ day         7113 Rs/ MW/ day             Own Project Development for 100
                                                                                                              MW
     Transmission Tariff
     (short term/collective/ renewable energy)
                                                                                  0.29 Rs/ kWh               Detailed Project Report for more than
                                                                                                              300+ MW
                                                                                                             Total Wind Advisory 3500+ MW
    From the above table, we can evaluate that the Long/ Medium term Transmission
    Tariff for FY13 at 20, 00,000 kWh generation per MW comes out to be Rs 1.28 per
    kWh which has increased from Rs 0.988 per kWh for FY12. However, for short term/
    collective/ renewable power, it is Rs 0.29 per kWh.

    In case an RE generator opts for availing REC benefit then long/ medium term tariff
    shall be applicable and w/o REC benefit, Renewable Energy tariff @ Rs. 0.29/ Kwh
    shall be applicable.

    2. GERC: Retail Tariff for FY 2012-13

                                          HT Tariff - Base Energy charges

                                 Applicable for UGVCL, DGVCL, MGVCL and PGVCL

                                                             Existing Tariff        New Tariff

                                                            Paise per Unit        Paise per Unit

    Upto 500 kVA of billing demand                                390                  400

    For next 2000 kVA of billing demand                           410                  420

    For billing demand in excess of 2500 kVA                      420                  430


    As the tariff has increased by 10 paisa per unit, this has further firmed up the
    viability of captive wind power projects in the state of Gujarat, as invester can
    freeze the cost of power for next 20 years. With respect to the Draft GERC Policy
    discussion paper dated July 2012, an RE generator shall be eligible for availing REC
    benefit if it goes for captive arrangement without availing any preferential benefit.
    However, it is not clear that if any captive consumer wishes to go for REC benefit
    then what type (TOD etc) of banking facility shall be available to him (if any).




                                                                                                                www.windforce-management.com
Enabling High Efficiency and Reliable Wind Power Projects
3



    3. GERC: Determination of tariff for procurement of power from Wind Power
    Projects in Gujarat
    GERC has issued Draft discussion paper on determination of tariff for procurement
    of power by distribution licensees and others from Wind Power Projects in Gujarat.
    The important aspects of the same are :
                                                      Proposal for new control period starting from 11th
                                                                        August 2012

                                                               Option I                   Option II
                           As per Wind Tariff Order
          Parameters                                  (Interconnection point at   (Interconnection point at
                            dated 30 January 2010
                                                        wind farm pooling S/S)           GETCO S/S)

            Tariff            Rs. 3.56 per kWh            Rs. 3.97 per kWh            Rs. 4.21 per kWh

    From the two tier tariff, Investor have to invest more for project to get higher tariff
    PPA as it will require to build extra electrical lines from the windfarm pooling sub-
    station to the GETCO sub-station

    Transmission and Wheeling Charges
     Wind power projects wheeling power for own use/ third party sale and opting
        for RECs, will have to pay normal open access charges and losses.
       Wind power projects not opting for REC benefits can avail transmission and
        wheeling charges/ losses as per the GERC Order dated 30 January 2010.

    Cross Subsidy Surcharge
     Exempted for captive use and for third party sale of wind energy.

    Energy Metering
     Wind projects shall have to provide ABT compliant meters at the interface
        points and shall conform to the Central Electricity Authority (Installation and
        Operation of Meters) Regulations, 2006.
       Metering shall be done at interconnection point of the generator bus-bar with
        the transmission or distribution system concerned.

    Banking of Surplus Wind Energy
     One month banking allowed for captive wind energy projects. They are eligible
        to utilise the same during the month in proportion to the energy generated
        during peak and normal hour period.
       No banking facility offered to third party sale of wind energy.

    Purchase of Surplus Power from Wind Power Projects opting for Captive use and
    Third Party Sale under Open Access
     For captive wind energy projects, the surplus energy after one month's banking
        is considered for purchase by distribution licensee at 85% of the wind tariff.
       For third party wind energy sale, the surplus energy after 15 minutes time block
        is considered for purchase by distribution licensee at the rate of 85% of the
        tariff declared by the Commission.

    Renewable Energy Certificates for Third party sale and Captive Use of Wind
    Energy
     Third party sale and captive use of wind energy will be eligible for availing
        Renewable Energy Certificates as per CERC REC Regulations.
                                                                                                                    www.windforce-management.com
Enabling High Efficiency and Reliable Wind Power Projects
4



    4. TNERC: Stakeholder’s hearing on determination of tariff and allied issues
    related to power generation from NCES                                                      WinDForce Services
    TANGEDCO made a plea before the TNERC for abolishing the system of 'banking' of             Wind Resource Assessment (WRA)
    electricity by wind power producers.                                                        Structuring of PPA/ Sale of power and
    The 'banking' system allows wind power producers to put power into the grid and              management
    draw the power back for consumption within a year. This is particularly useful for          O w n e r ’s E n g i n e e r d u r i n g t h e
    wind power producers who also own other industries that may need electricity to                complete project implementation &
    run.                                                                                           post commissioning
    TANGEDCO's plea was that banking was hurting the organisation because wind                    Detailed Project feasibility Study
    power producers put electricity into the grid when there is enough power but                  Detailed Project Report
    exercise their option to draw power when there is a scarcity of power. As                     Contract Advisory
    TANGEDCO is bound to supply them the power, it has to purchase power at high                  Technical Due Diligence of proposed
    rates from the market for that purpose. In the bargain, TANGEDCO makes a loss.               as well as existing wind farms
    Furthermore, it has to supply power to the wind producers (who had 'banked' the             Technical Due Diligence of New

    power) in preference to other consumers.                                                     Manufacturing Facility
    Wind power producers, on the other hand, said that the facility of 'banking' was a          Environment Impact Assessment
                                                                                                Development/ Co-development of
    promise made by TANGEDCO on the basis of which heavy investments have been
    made & withdrawing the promised facility would tantamount to breach of                         Wind Power Projects at Identified
    agreement, wind power producers demanded higher rates in the range of Rs 5.32 a                sites by WinDForce
    unit to Rs 6.40 under preferential tariff, while TANGEDCO opposed for raising the
    'feed-in' tariff beyond the current Rs 3.39.

    5. TNERC: Extension of validity of the Commission's Tariff Order for Wind Projects
    The Commission issued a comprehensive Tariff Order on wind energy in Order No 1
    of 2009 on 20.03.2009. As the validity of the Order expired on 31.03.2011, the
    validity was extended by the Commission upto 31.12.2011 vide Tariff Order No 1 of
    2011 dated 08.04.2011.

    The validity of the said Order was further extended till 30.06.2012 by Order No 4 of
    2011 dated 15.12.2011.

    A stakeholders hearing was held on 08.06.2012 to elicit their views on the tariff
    determination. Various issues were raised in the hearing which needs to be
    examined in detail before finalising the tariff order for the wind energy generators.
    Therefore, the Commission has extending the validity of Order No 1 of 2009 upto
    31.07.2012 or the date of issue of tariff order, whichever is earlier.




                                                                                                   www.windforce-management.com
Enabling High Efficiency and Reliable Wind Power Projects
5



    6. RERC: Draft Tariff Order for Wind Power Plants for FY13

                                                                       New Tariff (Rs/kWh)
                                                                                             New Tariff (Rs/kWh)
                                                                            if higher
                                                Existing Tariff FY12                              if Higher
     Sr. No.              Particulars                                     depreciation
                                                     (Rs/kWh)                                   depreciation
                                                                         benefit is not
                                                                                              benefit is availed
                                                                             availed


                      Wind Power Plants
                     located in Jaisalmer,
            1                                          4.46                   5.18                  4.90
                      Jodhpur & Barmer
                           districts


                      Wind Power Plants
                   located in districts other
            2                                          4.69                   5.44                  5.14
                    than Jaisalmer, Jodhpur
                      & Barmer districts.




    The above tariff is levelised for 25 years.

    In the Order, following were introduced:

    (i)         As all reasonable costs and returns are being allowed to be recovered through
    the tariff, therefore, any policy support by way of capital subsidy/Capital Finance
    Assistance (CFA), higher depreciation benefit or Generation Based Incentive (GBI),
    which becomes available to the developer/generator, needs to be passed on to the
    utilities.
    -         This is been introduced first time and mostly not introduced by any SERC's
    (only CDM benefit is being shared with state utilities)

    (ii) In case, any wind power plant getting commissioned during FY 12-13 avails the
    benefit of GBI/Tariff subsidy under any Government Scheme, the applicable tariff
    worked out as above, would get reduced to the extent of GBI/Tariff subsidy so
    availed. In case such a benefit has not been availed, an undertaking to that effect
    would have to be given while signing PPA
    -      This means if any developer has availed GBI benefit to the tune of INR 50
    paise/kWhr then the same has to be reduced from the applicable tariff

    (iii)       Tariff if Higher Depreciation is availed and Tariff if Higher Depreciation is not
    availed
    -      Not clear whether Higher Depreciation is 15% + 25% or its 15% alone. Also in
    the tariff calculation depreciation benefit is considered as 17.50% ((50%
    (15%+20%))




                                                                                                                          www.windforce-management.com
Enabling High Efficiency and Reliable Wind Power Projects
6



    (iv)   Considering that considerable capacity of the wind projects already stands
    commissioned in the State, the Distribution licensees, in the interest of the                              WinDForce Esteemed Clients
    consumers, must strive to procure wind energy at a generic tariff being lower of the                       Hindustan Zinc Limited, NSL Renewable,
    two streams namely, with or without higher depreciation benefit by giving                                  Techno Electric, Bhilwara Energy Limited,
    preference, while finalising/signing PPA, to developers/generators offering the                            KSK Wind, Green Infra, Avigo Capital,
    lower rate among the said two tariff streams. However, if capacity in excess of RPO                        Olympus Capital, PTC India, Auro Mira,
    is to be contracted, the licensee must obtain prior approval of the Commission                             MSPL, TVS Energy, Indian Energy,
    based on reasons and full justification before contracting for capacity in excess of                       Reliance Power, CRISIL, IFCI Limited,
    RPO requirement.                                                                                           Oswal Woolen Mills Limited, Ushdev
    -     This clearly means if DISCOM has fulfilled their RPO obligation by procuring                         Power Holdings, Bharat Light and
    power under FIT mode, then it is in the hands of commission to give clearance for                          Power,RSPL Ltd. (Ghari Detergent),
    signing of any new PPA for any excess power beyond the DISCOM's RPO. Due care                              Modelama Exports Ltd, Tata Power, L & T
    should be taken by investors before finalization of their projects.                                        Infra, Kiran Gems, Dharmanandan
                                                                                                               Diamonds, Shah Promoters, Fena (P) Ltd.,
    7. KERC: Second Amendment to Procurement of Energy from Renewable Sources
                                                                                                               Bhabani Pigments, Panama Group,
    Regulations, 2012
                                                                                                               Kandla Port Trust etc.
    KERC has issued second amendment to REC/ RPO Regulations for Procurement of
    Energy from Renewable Sources Regulations, 2012.


                  Existing Regulation                              Amendment proposed


     Captive Power Producers (CPP) based on             Grid Connected Captive Power Producers (CPP)
     renewable sources of energy shall be eligible to   based on renewable sources of energy shall be
     get accredited for obtaining RE certificates for   eligible to get accredited for obtaining RE
     the entire energy generated from their plants      certificates for the energy generated and used
     including the energy used for captive              for captive consumption and for surplus energy,
     consumption.                                       if any, sold to the distribution licensee/s of the
                                                        State at the average pooled power purchase
                                                        cost notified by the Commission from time to
                                                        time




    This amendment provides more clarity on Captive format.




                                                                                                                   www.windforce-management.com
Enabling High Efficiency and Reliable Wind Power Projects
7


    What’s New

    1. Government rating of DISCOMs to include RPO fulfilment as a criteria
    Ministry of Power has developed an integrated rating methodology covering the
    DISCOMs. The system is an attempt to harmonize the rating of DISCOMs by banks
    and financial institutions. One of the criteria for ranking of the DISCOMs will also be
    the level of their Renewable Purchase Obligation (RPO) fulfilment.

    Renewable Energy Purchase Obligation shall account 25% weightage of total
    rating.
    A system of negative marks has also been introduced in the rating methodology.
    The parameters assigned negative marks include non-auditing of accounts (upto
    minus 12%), SEB unbundling (upto minus 5%), non-filing of tariff petition (upto
    minus 5%), untreated revenue gap (upto minus 5%), deterioration in AT&C Loss
    (upto minus 5%), increase in payables (upto minus 3%), presence of Regulatory
    Asset (upto minus 3%), negative net-worth (minus 3%) and extent of cross subsidy
    (upto minus 2%).

    The first ranking is expected to release in March 2013.

    As all the distribution companies require huge amount of funds for their planned
    capital expenditure as well as working capital, all need good rating. With above
    criteria, very high weightage is given to RPO compliance as well as negative ratings
    for other management issues, DISCOMS are likely to follow the best practices to
    maintain high ratings and this should in return should give much needed push to
    offtake to RECs.

    2. MNRE: Guidelines for installation of prototype wind turbine models in India
    The Ministry has decided to permit the installation of a limited number of
    prototype wind turbines to facilitate indigenization and encourage national
    industry. The guideline document is applicable for all the wind turbine
    manufacturers in India, who wish to install prototype wind turbine model(s) in the
    country and synchronize with the Indian grid system. The installation of a prototype
    wind turbine model will be allowed only to carry out type testing for obtaining type
    certificate from Internationally Accredited Certifying Agencies.

     http://mnre.gov.in/file-manager/UserFiles/guidelines_prototype_wind_turbine.pdf
     http://mnre.gov.in/file-manager/UserFiles/land_wind.pdf
     http://www.cwet.tn.nic.in/Docu/Requirements%20for%20installation%20of%20prototype%20wind%20turbine%20model%20in%20India.pdf




                                                                                                                                        www.windforce-management.com
Enabling High Efficiency and Reliable Wind Power Projects
8


    Upcoming Events




     Wind Power Project Development: Planning, Contracting, EPC organized by
                                                    th
      Renewable Market India to be held on 24 August 2012          at The Lalit
      Intercontinental, Mumbai
     Wind Power Development Forum India, organized by Wind Energy Update to be
      held on 6th - 7th September 2012 at Le Meridien, New Delhi




                                                                                          www.windforce-management.com
Enabling High Efficiency and Reliable Wind Power Projects
9




    REC Update (till 30.06.12)

    Total Accredited                                             = 1811.31 MW – Wind Specific
    Total Registered                                             = 1426.08 MW – Wind Specific

    Total Issued                                                 = 16,69,827 RECs
    Total Redeemed                                               = 14,92,437 RECs
    Total Inventory                                              = 1,77,391 RECs




    REC Trading

                                                                             Equilibrium Price
                                                                                                                                                                                      250000
                                       3,000

                                                                                                                                                                                      200000

                                       2,500
                            (Rs/REC)




                                                                                                                                                                                      150000


                                       2,000
                                                                                                                                                                                      100000


                                       2,500
                                                                                                                                                                                      50000


                                       1,000
                                                                                                                                                                                      0
                                               Apr’11   May’11   Jun’11   Jul’11   Aug’11   Sep’11   Oct’11   Nov’11   Dec’11   Jan’12   Feb’12   Mar’12   Apr’12   May’12   Jun’12



       IEX Traded Volume (REC)                  260     14,002   15,902   14,668   22,095   41,385   92,303   96,154 1,05,942 1,65,460 1,90,482 1,92,354 62,277 1,53,125 2,23,164



      IEX Equilibrium Price (Rs / REC)         1,500    1,500    1,505    1,555    1,800    2,300    2,700    2,900    2,950    3,051    3,066    2,900    2,201    2,402    2,402




    In June'12 trading session total around 2,50,000 RECs were traded at an average rate @
    Rs 2402/ MWh. Last year in Q1 at IEX total 30,164 RECs were traded at an avg. rate of Rs
    1502 per REC where as this year in Q1 at IEX total 4,38,566 RECs have been traded at an
    avg. rate of Rs 2373 per REC.

    This year, in Q1 it was expected that Trading Volumes will be on lower side and the
    clearing price shall also be low as last year. But the market has shown some maturity
    and confidence amongst the stake holders. For the continuous growth of REC Market, it
    is very necessary that the entities which have not matched their RPO in FY12 must be
    penalized ASAP otherwise other entities which are following the RPO shall start
    deviating.

    At various public forums, the investors have expressed their concern on the
    bankability of REC based Wind Projects primarily because of short (5 years) control
    period (currently upto 2017 only) & the enforceability of RPO. The Government
    representatives have indirectly indicated that these issues are being taken care of
    and soon new order to address these issues shall come.




                                                                                                                                                                                                         www.windforce-management.com
Contact Us                                                                                Corporate Office
Kindly write to us if you have any comments on this Newsletter. Your valuable             WinDForce Management Services Pvt. Ltd.
feedback on this would motivate and help us in improving the quality and enriching        5th Floor, Universal Trade Tower
the content. We are eagerly waiting for your kind response to the articles presented in   Gurgaon - Sohna Road
this Newsletter.                                                                          Gurgaon - 122001, Haryana
                                                                                          Tel: +91 124 6653100
Parish Gupta                                                                              Fax: +91 124 6653200
Mob: +91 98717 11445                                                                      Web: www.windforce-management.com
E-mail: parish@windforce-management.com

Rupesh Singh
Mob: +91 96507 58884
E-mail: rupesh@windforce-management.com



A WinDForce Publication
Disclaimer - This Newsletter has been compiled by WinDForce Management Services Private Limited
for circulation among the stakeholders in the energy market. Though the contents of this bulletin are
correct to the best of our knowledge, WinDForce does not vouch for their accuracy.



                                                        www.windforce-management.com

More Related Content

What's hot

Tariff Setting In the Indian Power Sector-An Overview
Tariff Setting In the Indian Power Sector-An OverviewTariff Setting In the Indian Power Sector-An Overview
Tariff Setting In the Indian Power Sector-An OverviewIOSR Journals
 
NOCA CLEAN ENERGY_PPP_Website_With_Housing
NOCA CLEAN ENERGY_PPP_Website_With_HousingNOCA CLEAN ENERGY_PPP_Website_With_Housing
NOCA CLEAN ENERGY_PPP_Website_With_HousingSir Collin H.Haughton
 
Solar net metering policy
Solar net metering policySolar net metering policy
Solar net metering policyJay Ranvir
 
India's National Solar Mission Phase 2 Batch 2 Tranche 1 Guidelines - Draft
India's National Solar Mission Phase 2 Batch 2 Tranche 1 Guidelines - DraftIndia's National Solar Mission Phase 2 Batch 2 Tranche 1 Guidelines - Draft
India's National Solar Mission Phase 2 Batch 2 Tranche 1 Guidelines - DraftHeadway Solar
 
Introduction to the Renewable Energy Certificate (REC) Mechanism
Introduction to the Renewable Energy Certificate (REC) MechanismIntroduction to the Renewable Energy Certificate (REC) Mechanism
Introduction to the Renewable Energy Certificate (REC) MechanismSpark Network
 
Renewable Energy Certificate
Renewable Energy CertificateRenewable Energy Certificate
Renewable Energy CertificateJaspal Bhatia
 
Bhatia small wind[1]
Bhatia small wind[1]Bhatia small wind[1]
Bhatia small wind[1]satishmnair
 
Feasibility of Solar Project with Open Access in Maharashtra
Feasibility of Solar Project with Open Access in Maharashtra Feasibility of Solar Project with Open Access in Maharashtra
Feasibility of Solar Project with Open Access in Maharashtra Gensol Engineering Limited
 
Final draft 3000 MW Phase 2 Batch 2 Tranche 1 Draft Guidelines
Final draft 3000 MW Phase 2 Batch 2 Tranche 1 Draft GuidelinesFinal draft 3000 MW Phase 2 Batch 2 Tranche 1 Draft Guidelines
Final draft 3000 MW Phase 2 Batch 2 Tranche 1 Draft GuidelinesHeadway Solar
 
Sgcp12 smith-nationalgrid
Sgcp12 smith-nationalgridSgcp12 smith-nationalgrid
Sgcp12 smith-nationalgridJustin Hayward
 
Improving Energy Efficiency in Optical Networks
Improving Energy Efficiency in Optical NetworksImproving Energy Efficiency in Optical Networks
Improving Energy Efficiency in Optical NetworksIJEEE
 
Renewable Energy Certificate Mechanism in India
Renewable Energy Certificate Mechanism in India Renewable Energy Certificate Mechanism in India
Renewable Energy Certificate Mechanism in India sanjeev jain
 
IRJET- Optimization with PSO and FPO based Control for Energy Efficient of Se...
IRJET- Optimization with PSO and FPO based Control for Energy Efficient of Se...IRJET- Optimization with PSO and FPO based Control for Energy Efficient of Se...
IRJET- Optimization with PSO and FPO based Control for Energy Efficient of Se...IRJET Journal
 
Jordan
JordanJordan
JordanRCREEE
 
Tender summary for SECI 2500 MW Wind-Solar Hybrid Tender
Tender summary for SECI 2500 MW Wind-Solar Hybrid TenderTender summary for SECI 2500 MW Wind-Solar Hybrid Tender
Tender summary for SECI 2500 MW Wind-Solar Hybrid TenderGensol Engineering Limited
 
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019Gensol Engineering Limited
 
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19Gensol Engineering Limited
 

What's hot (19)

Tariff Setting In the Indian Power Sector-An Overview
Tariff Setting In the Indian Power Sector-An OverviewTariff Setting In the Indian Power Sector-An Overview
Tariff Setting In the Indian Power Sector-An Overview
 
NOCA CLEAN ENERGY_PPP_Website_With_Housing
NOCA CLEAN ENERGY_PPP_Website_With_HousingNOCA CLEAN ENERGY_PPP_Website_With_Housing
NOCA CLEAN ENERGY_PPP_Website_With_Housing
 
Sudan
SudanSudan
Sudan
 
Solar net metering policy
Solar net metering policySolar net metering policy
Solar net metering policy
 
Levellised generic tariff
Levellised generic tariffLevellised generic tariff
Levellised generic tariff
 
India's National Solar Mission Phase 2 Batch 2 Tranche 1 Guidelines - Draft
India's National Solar Mission Phase 2 Batch 2 Tranche 1 Guidelines - DraftIndia's National Solar Mission Phase 2 Batch 2 Tranche 1 Guidelines - Draft
India's National Solar Mission Phase 2 Batch 2 Tranche 1 Guidelines - Draft
 
Introduction to the Renewable Energy Certificate (REC) Mechanism
Introduction to the Renewable Energy Certificate (REC) MechanismIntroduction to the Renewable Energy Certificate (REC) Mechanism
Introduction to the Renewable Energy Certificate (REC) Mechanism
 
Renewable Energy Certificate
Renewable Energy CertificateRenewable Energy Certificate
Renewable Energy Certificate
 
Bhatia small wind[1]
Bhatia small wind[1]Bhatia small wind[1]
Bhatia small wind[1]
 
Feasibility of Solar Project with Open Access in Maharashtra
Feasibility of Solar Project with Open Access in Maharashtra Feasibility of Solar Project with Open Access in Maharashtra
Feasibility of Solar Project with Open Access in Maharashtra
 
Final draft 3000 MW Phase 2 Batch 2 Tranche 1 Draft Guidelines
Final draft 3000 MW Phase 2 Batch 2 Tranche 1 Draft GuidelinesFinal draft 3000 MW Phase 2 Batch 2 Tranche 1 Draft Guidelines
Final draft 3000 MW Phase 2 Batch 2 Tranche 1 Draft Guidelines
 
Sgcp12 smith-nationalgrid
Sgcp12 smith-nationalgridSgcp12 smith-nationalgrid
Sgcp12 smith-nationalgrid
 
Improving Energy Efficiency in Optical Networks
Improving Energy Efficiency in Optical NetworksImproving Energy Efficiency in Optical Networks
Improving Energy Efficiency in Optical Networks
 
Renewable Energy Certificate Mechanism in India
Renewable Energy Certificate Mechanism in India Renewable Energy Certificate Mechanism in India
Renewable Energy Certificate Mechanism in India
 
IRJET- Optimization with PSO and FPO based Control for Energy Efficient of Se...
IRJET- Optimization with PSO and FPO based Control for Energy Efficient of Se...IRJET- Optimization with PSO and FPO based Control for Energy Efficient of Se...
IRJET- Optimization with PSO and FPO based Control for Energy Efficient of Se...
 
Jordan
JordanJordan
Jordan
 
Tender summary for SECI 2500 MW Wind-Solar Hybrid Tender
Tender summary for SECI 2500 MW Wind-Solar Hybrid TenderTender summary for SECI 2500 MW Wind-Solar Hybrid Tender
Tender summary for SECI 2500 MW Wind-Solar Hybrid Tender
 
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019
 
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
 

Viewers also liked

Wind Force Newsletter May, Edition, 2012
Wind Force Newsletter   May, Edition, 2012Wind Force Newsletter   May, Edition, 2012
Wind Force Newsletter May, Edition, 2012rupeshsingh_1
 
Wind Force Newsletter January, Edition, 2012
Wind Force Newsletter   January, Edition, 2012Wind Force Newsletter   January, Edition, 2012
Wind Force Newsletter January, Edition, 2012rupeshsingh_1
 
Wind Force Newsletter Feb, Edition, 2012
Wind Force Newsletter   Feb, Edition, 2012Wind Force Newsletter   Feb, Edition, 2012
Wind Force Newsletter Feb, Edition, 2012rupeshsingh_1
 
WinD Force Newsletter October Edition
WinD Force Newsletter   October EditionWinD Force Newsletter   October Edition
WinD Force Newsletter October Editionrupeshsingh_1
 
Wind Force Newsletter Nov, Edition, 2011
Wind Force Newsletter   Nov, Edition, 2011Wind Force Newsletter   Nov, Edition, 2011
Wind Force Newsletter Nov, Edition, 2011rupeshsingh_1
 
You are very lucky03
You are very lucky03You are very lucky03
You are very lucky03deepakstanley
 
Sourcing Beyond Boundries
Sourcing Beyond BoundriesSourcing Beyond Boundries
Sourcing Beyond Boundriesrd1596knl
 
About music
About musicAbout music
About musicRqzhik
 
Telecomunicacions
TelecomunicacionsTelecomunicacions
TelecomunicacionsNickvdgraaf
 
You are very lucky03
You are very lucky03You are very lucky03
You are very lucky03deepakstanley
 
Blueprint for success_-_copy
Blueprint for success_-_copyBlueprint for success_-_copy
Blueprint for success_-_copydeepakstanley
 
About music
About musicAbout music
About musicRqzhik
 
Third Party Inspection Services
Third Party Inspection ServicesThird Party Inspection Services
Third Party Inspection Servicesrd1596knl
 

Viewers also liked (14)

Wind Force Newsletter May, Edition, 2012
Wind Force Newsletter   May, Edition, 2012Wind Force Newsletter   May, Edition, 2012
Wind Force Newsletter May, Edition, 2012
 
Wind Force Newsletter January, Edition, 2012
Wind Force Newsletter   January, Edition, 2012Wind Force Newsletter   January, Edition, 2012
Wind Force Newsletter January, Edition, 2012
 
Wind Force Newsletter Feb, Edition, 2012
Wind Force Newsletter   Feb, Edition, 2012Wind Force Newsletter   Feb, Edition, 2012
Wind Force Newsletter Feb, Edition, 2012
 
WinD Force Newsletter October Edition
WinD Force Newsletter   October EditionWinD Force Newsletter   October Edition
WinD Force Newsletter October Edition
 
Wind Force Newsletter Nov, Edition, 2011
Wind Force Newsletter   Nov, Edition, 2011Wind Force Newsletter   Nov, Edition, 2011
Wind Force Newsletter Nov, Edition, 2011
 
You are very lucky03
You are very lucky03You are very lucky03
You are very lucky03
 
Sourcing Beyond Boundries
Sourcing Beyond BoundriesSourcing Beyond Boundries
Sourcing Beyond Boundries
 
About music
About musicAbout music
About music
 
Telecomunicacions
TelecomunicacionsTelecomunicacions
Telecomunicacions
 
You are very lucky03
You are very lucky03You are very lucky03
You are very lucky03
 
Blueprint for success_-_copy
Blueprint for success_-_copyBlueprint for success_-_copy
Blueprint for success_-_copy
 
About music
About musicAbout music
About music
 
Epid k3sesi2
Epid k3sesi2Epid k3sesi2
Epid k3sesi2
 
Third Party Inspection Services
Third Party Inspection ServicesThird Party Inspection Services
Third Party Inspection Services
 

Similar to Wind Force Newsletter July, Edition, 2012

Net Metering-NEPRA & DISCOS Rules/Regulations and Procedure
Net Metering-NEPRA & DISCOS Rules/Regulations and ProcedureNet Metering-NEPRA & DISCOS Rules/Regulations and Procedure
Net Metering-NEPRA & DISCOS Rules/Regulations and ProcedureSALMAN SAEED
 
IRJET- Improvement of Wind Turbine DFIG using Fault Ride Through Capability T...
IRJET- Improvement of Wind Turbine DFIG using Fault Ride Through Capability T...IRJET- Improvement of Wind Turbine DFIG using Fault Ride Through Capability T...
IRJET- Improvement of Wind Turbine DFIG using Fault Ride Through Capability T...IRJET Journal
 
Wind Vs Conventional Electricity Economics
Wind Vs Conventional Electricity EconomicsWind Vs Conventional Electricity Economics
Wind Vs Conventional Electricity Economicsvijcons
 
energy dispatch using virtual power plant
energy dispatch using virtual power plantenergy dispatch using virtual power plant
energy dispatch using virtual power plantGAUTAMKUMAR868
 
Review of different Fault Ride through (FRT) Control Strategies for a DFIG Wi...
Review of different Fault Ride through (FRT) Control Strategies for a DFIG Wi...Review of different Fault Ride through (FRT) Control Strategies for a DFIG Wi...
Review of different Fault Ride through (FRT) Control Strategies for a DFIG Wi...IRJET Journal
 
MNRE Clarification on the capacity with respect to inverter and eligibility o...
MNRE Clarification on the capacity with respect to inverter and eligibility o...MNRE Clarification on the capacity with respect to inverter and eligibility o...
MNRE Clarification on the capacity with respect to inverter and eligibility o...Harish Sharma
 
Mitigation of Voltage Dip and Swell Faults in Wind Energy Conversion Systems
Mitigation of Voltage Dip and Swell Faults in Wind Energy Conversion SystemsMitigation of Voltage Dip and Swell Faults in Wind Energy Conversion Systems
Mitigation of Voltage Dip and Swell Faults in Wind Energy Conversion SystemsIRJET Journal
 
Manipur solar policy 2014
Manipur solar policy 2014Manipur solar policy 2014
Manipur solar policy 2014Headway Solar
 
Distributed generation & power quality unit 5
Distributed generation & power quality unit 5Distributed generation & power quality unit 5
Distributed generation & power quality unit 5hariyenireddy1
 
Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...
Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...
Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...Headway Solar
 
Deepening Regional Power Collaboration to Enable a Successful Energy Transiti...
Deepening Regional Power Collaboration to Enable a Successful Energy Transiti...Deepening Regional Power Collaboration to Enable a Successful Energy Transiti...
Deepening Regional Power Collaboration to Enable a Successful Energy Transiti...Celestial Light
 
ABT a complete report and a case study
ABT a complete report and a case studyABT a complete report and a case study
ABT a complete report and a case studyWaseem Hashmat
 
IRJET- Active and Reactive Power Control of DFIG Wind Turbine with Energy Sto...
IRJET- Active and Reactive Power Control of DFIG Wind Turbine with Energy Sto...IRJET- Active and Reactive Power Control of DFIG Wind Turbine with Energy Sto...
IRJET- Active and Reactive Power Control of DFIG Wind Turbine with Energy Sto...IRJET Journal
 
Mixed Energy(NEPRA- State of industry Report 2020-2021)- Presentation
Mixed Energy(NEPRA- State of industry Report 2020-2021)- PresentationMixed Energy(NEPRA- State of industry Report 2020-2021)- Presentation
Mixed Energy(NEPRA- State of industry Report 2020-2021)- PresentationNAUMAN NAEEM
 
Enhancement of reactive power capability of doubly fed induction generator 2-3
Enhancement of reactive power capability of doubly fed induction generator 2-3Enhancement of reactive power capability of doubly fed induction generator 2-3
Enhancement of reactive power capability of doubly fed induction generator 2-3IAEME Publication
 

Similar to Wind Force Newsletter July, Edition, 2012 (20)

Net Metering-NEPRA & DISCOS Rules/Regulations and Procedure
Net Metering-NEPRA & DISCOS Rules/Regulations and ProcedureNet Metering-NEPRA & DISCOS Rules/Regulations and Procedure
Net Metering-NEPRA & DISCOS Rules/Regulations and Procedure
 
IRJET- Improvement of Wind Turbine DFIG using Fault Ride Through Capability T...
IRJET- Improvement of Wind Turbine DFIG using Fault Ride Through Capability T...IRJET- Improvement of Wind Turbine DFIG using Fault Ride Through Capability T...
IRJET- Improvement of Wind Turbine DFIG using Fault Ride Through Capability T...
 
Wind Vs Conventional Electricity Economics
Wind Vs Conventional Electricity EconomicsWind Vs Conventional Electricity Economics
Wind Vs Conventional Electricity Economics
 
energy dispatch using virtual power plant
energy dispatch using virtual power plantenergy dispatch using virtual power plant
energy dispatch using virtual power plant
 
REC status
REC statusREC status
REC status
 
Ds31803810
Ds31803810Ds31803810
Ds31803810
 
Review of different Fault Ride through (FRT) Control Strategies for a DFIG Wi...
Review of different Fault Ride through (FRT) Control Strategies for a DFIG Wi...Review of different Fault Ride through (FRT) Control Strategies for a DFIG Wi...
Review of different Fault Ride through (FRT) Control Strategies for a DFIG Wi...
 
MNRE Clarification on the capacity with respect to inverter and eligibility o...
MNRE Clarification on the capacity with respect to inverter and eligibility o...MNRE Clarification on the capacity with respect to inverter and eligibility o...
MNRE Clarification on the capacity with respect to inverter and eligibility o...
 
Mitigation of Voltage Dip and Swell Faults in Wind Energy Conversion Systems
Mitigation of Voltage Dip and Swell Faults in Wind Energy Conversion SystemsMitigation of Voltage Dip and Swell Faults in Wind Energy Conversion Systems
Mitigation of Voltage Dip and Swell Faults in Wind Energy Conversion Systems
 
Nit wardha-river
Nit wardha-riverNit wardha-river
Nit wardha-river
 
Manipur solar policy 2014
Manipur solar policy 2014Manipur solar policy 2014
Manipur solar policy 2014
 
Distributed generation & power quality unit 5
Distributed generation & power quality unit 5Distributed generation & power quality unit 5
Distributed generation & power quality unit 5
 
Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...
Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...
Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...
 
Deepening Regional Power Collaboration to Enable a Successful Energy Transiti...
Deepening Regional Power Collaboration to Enable a Successful Energy Transiti...Deepening Regional Power Collaboration to Enable a Successful Energy Transiti...
Deepening Regional Power Collaboration to Enable a Successful Energy Transiti...
 
Renewable energy
Renewable energyRenewable energy
Renewable energy
 
ABT a complete report and a case study
ABT a complete report and a case studyABT a complete report and a case study
ABT a complete report and a case study
 
IRJET- Active and Reactive Power Control of DFIG Wind Turbine with Energy Sto...
IRJET- Active and Reactive Power Control of DFIG Wind Turbine with Energy Sto...IRJET- Active and Reactive Power Control of DFIG Wind Turbine with Energy Sto...
IRJET- Active and Reactive Power Control of DFIG Wind Turbine with Energy Sto...
 
Mixed Energy(NEPRA- State of industry Report 2020-2021)- Presentation
Mixed Energy(NEPRA- State of industry Report 2020-2021)- PresentationMixed Energy(NEPRA- State of industry Report 2020-2021)- Presentation
Mixed Energy(NEPRA- State of industry Report 2020-2021)- Presentation
 
Dgvcl rerport
Dgvcl rerportDgvcl rerport
Dgvcl rerport
 
Enhancement of reactive power capability of doubly fed induction generator 2-3
Enhancement of reactive power capability of doubly fed induction generator 2-3Enhancement of reactive power capability of doubly fed induction generator 2-3
Enhancement of reactive power capability of doubly fed induction generator 2-3
 

Recently uploaded

Moving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdfMoving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdfLoriGlavin3
 
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdfHyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdfPrecisely
 
How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.Curtis Poe
 
Digital Identity is Under Attack: FIDO Paris Seminar.pptx
Digital Identity is Under Attack: FIDO Paris Seminar.pptxDigital Identity is Under Attack: FIDO Paris Seminar.pptx
Digital Identity is Under Attack: FIDO Paris Seminar.pptxLoriGlavin3
 
Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Mattias Andersson
 
DSPy a system for AI to Write Prompts and Do Fine Tuning
DSPy a system for AI to Write Prompts and Do Fine TuningDSPy a system for AI to Write Prompts and Do Fine Tuning
DSPy a system for AI to Write Prompts and Do Fine TuningLars Bell
 
TrustArc Webinar - How to Build Consumer Trust Through Data Privacy
TrustArc Webinar - How to Build Consumer Trust Through Data PrivacyTrustArc Webinar - How to Build Consumer Trust Through Data Privacy
TrustArc Webinar - How to Build Consumer Trust Through Data PrivacyTrustArc
 
TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024Lonnie McRorey
 
A Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptxA Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptxLoriGlavin3
 
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Mark Simos
 
What's New in Teams Calling, Meetings and Devices March 2024
What's New in Teams Calling, Meetings and Devices March 2024What's New in Teams Calling, Meetings and Devices March 2024
What's New in Teams Calling, Meetings and Devices March 2024Stephanie Beckett
 
Scanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL CertsScanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL CertsRizwan Syed
 
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptxThe Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptxLoriGlavin3
 
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptx
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptxPasskey Providers and Enabling Portability: FIDO Paris Seminar.pptx
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptxLoriGlavin3
 
WordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your BrandWordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your Brandgvaughan
 
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024BookNet Canada
 
"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii SoldatenkoFwdays
 
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024BookNet Canada
 
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024BookNet Canada
 

Recently uploaded (20)

DMCC Future of Trade Web3 - Special Edition
DMCC Future of Trade Web3 - Special EditionDMCC Future of Trade Web3 - Special Edition
DMCC Future of Trade Web3 - Special Edition
 
Moving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdfMoving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdf
 
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdfHyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
Hyperautomation and AI/ML: A Strategy for Digital Transformation Success.pdf
 
How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.
 
Digital Identity is Under Attack: FIDO Paris Seminar.pptx
Digital Identity is Under Attack: FIDO Paris Seminar.pptxDigital Identity is Under Attack: FIDO Paris Seminar.pptx
Digital Identity is Under Attack: FIDO Paris Seminar.pptx
 
Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?
 
DSPy a system for AI to Write Prompts and Do Fine Tuning
DSPy a system for AI to Write Prompts and Do Fine TuningDSPy a system for AI to Write Prompts and Do Fine Tuning
DSPy a system for AI to Write Prompts and Do Fine Tuning
 
TrustArc Webinar - How to Build Consumer Trust Through Data Privacy
TrustArc Webinar - How to Build Consumer Trust Through Data PrivacyTrustArc Webinar - How to Build Consumer Trust Through Data Privacy
TrustArc Webinar - How to Build Consumer Trust Through Data Privacy
 
TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024
 
A Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptxA Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptx
 
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
 
What's New in Teams Calling, Meetings and Devices March 2024
What's New in Teams Calling, Meetings and Devices March 2024What's New in Teams Calling, Meetings and Devices March 2024
What's New in Teams Calling, Meetings and Devices March 2024
 
Scanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL CertsScanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL Certs
 
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptxThe Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
 
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptx
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptxPasskey Providers and Enabling Portability: FIDO Paris Seminar.pptx
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptx
 
WordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your BrandWordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your Brand
 
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
 
"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko
 
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
 
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
 

Wind Force Newsletter July, Edition, 2012

  • 1.
  • 2. Enabling High Efficiency and Reliable Wind Power Projects 2 Policy and Regulatory WinDForce Achievements 1. MERC: Determination of Transmission Tariff for Intra-State Transmission  Wind Resource Assessment for 3000+ System (InSTS) for FY 2012-13 MW  Owner’s Engineer for 250+ MW Item Description FY 2011-12 FY 2012-13  Technical Due Diligence for 900+ MW Transmission Tariff (long term/ medium term) 5414 Rs/ MW/ day 7113 Rs/ MW/ day  Own Project Development for 100 MW Transmission Tariff (short term/collective/ renewable energy) 0.29 Rs/ kWh  Detailed Project Report for more than 300+ MW  Total Wind Advisory 3500+ MW From the above table, we can evaluate that the Long/ Medium term Transmission Tariff for FY13 at 20, 00,000 kWh generation per MW comes out to be Rs 1.28 per kWh which has increased from Rs 0.988 per kWh for FY12. However, for short term/ collective/ renewable power, it is Rs 0.29 per kWh. In case an RE generator opts for availing REC benefit then long/ medium term tariff shall be applicable and w/o REC benefit, Renewable Energy tariff @ Rs. 0.29/ Kwh shall be applicable. 2. GERC: Retail Tariff for FY 2012-13 HT Tariff - Base Energy charges Applicable for UGVCL, DGVCL, MGVCL and PGVCL Existing Tariff New Tariff Paise per Unit Paise per Unit Upto 500 kVA of billing demand 390 400 For next 2000 kVA of billing demand 410 420 For billing demand in excess of 2500 kVA 420 430 As the tariff has increased by 10 paisa per unit, this has further firmed up the viability of captive wind power projects in the state of Gujarat, as invester can freeze the cost of power for next 20 years. With respect to the Draft GERC Policy discussion paper dated July 2012, an RE generator shall be eligible for availing REC benefit if it goes for captive arrangement without availing any preferential benefit. However, it is not clear that if any captive consumer wishes to go for REC benefit then what type (TOD etc) of banking facility shall be available to him (if any). www.windforce-management.com
  • 3. Enabling High Efficiency and Reliable Wind Power Projects 3 3. GERC: Determination of tariff for procurement of power from Wind Power Projects in Gujarat GERC has issued Draft discussion paper on determination of tariff for procurement of power by distribution licensees and others from Wind Power Projects in Gujarat. The important aspects of the same are : Proposal for new control period starting from 11th August 2012 Option I Option II As per Wind Tariff Order Parameters (Interconnection point at (Interconnection point at dated 30 January 2010 wind farm pooling S/S) GETCO S/S) Tariff Rs. 3.56 per kWh Rs. 3.97 per kWh Rs. 4.21 per kWh From the two tier tariff, Investor have to invest more for project to get higher tariff PPA as it will require to build extra electrical lines from the windfarm pooling sub- station to the GETCO sub-station Transmission and Wheeling Charges  Wind power projects wheeling power for own use/ third party sale and opting for RECs, will have to pay normal open access charges and losses.  Wind power projects not opting for REC benefits can avail transmission and wheeling charges/ losses as per the GERC Order dated 30 January 2010. Cross Subsidy Surcharge  Exempted for captive use and for third party sale of wind energy. Energy Metering  Wind projects shall have to provide ABT compliant meters at the interface points and shall conform to the Central Electricity Authority (Installation and Operation of Meters) Regulations, 2006.  Metering shall be done at interconnection point of the generator bus-bar with the transmission or distribution system concerned. Banking of Surplus Wind Energy  One month banking allowed for captive wind energy projects. They are eligible to utilise the same during the month in proportion to the energy generated during peak and normal hour period.  No banking facility offered to third party sale of wind energy. Purchase of Surplus Power from Wind Power Projects opting for Captive use and Third Party Sale under Open Access  For captive wind energy projects, the surplus energy after one month's banking is considered for purchase by distribution licensee at 85% of the wind tariff.  For third party wind energy sale, the surplus energy after 15 minutes time block is considered for purchase by distribution licensee at the rate of 85% of the tariff declared by the Commission. Renewable Energy Certificates for Third party sale and Captive Use of Wind Energy  Third party sale and captive use of wind energy will be eligible for availing Renewable Energy Certificates as per CERC REC Regulations. www.windforce-management.com
  • 4. Enabling High Efficiency and Reliable Wind Power Projects 4 4. TNERC: Stakeholder’s hearing on determination of tariff and allied issues related to power generation from NCES WinDForce Services TANGEDCO made a plea before the TNERC for abolishing the system of 'banking' of  Wind Resource Assessment (WRA) electricity by wind power producers.  Structuring of PPA/ Sale of power and The 'banking' system allows wind power producers to put power into the grid and management draw the power back for consumption within a year. This is particularly useful for  O w n e r ’s E n g i n e e r d u r i n g t h e wind power producers who also own other industries that may need electricity to complete project implementation & run. post commissioning TANGEDCO's plea was that banking was hurting the organisation because wind  Detailed Project feasibility Study power producers put electricity into the grid when there is enough power but  Detailed Project Report exercise their option to draw power when there is a scarcity of power. As  Contract Advisory TANGEDCO is bound to supply them the power, it has to purchase power at high  Technical Due Diligence of proposed rates from the market for that purpose. In the bargain, TANGEDCO makes a loss. as well as existing wind farms Furthermore, it has to supply power to the wind producers (who had 'banked' the  Technical Due Diligence of New power) in preference to other consumers. Manufacturing Facility Wind power producers, on the other hand, said that the facility of 'banking' was a  Environment Impact Assessment  Development/ Co-development of promise made by TANGEDCO on the basis of which heavy investments have been made & withdrawing the promised facility would tantamount to breach of Wind Power Projects at Identified agreement, wind power producers demanded higher rates in the range of Rs 5.32 a sites by WinDForce unit to Rs 6.40 under preferential tariff, while TANGEDCO opposed for raising the 'feed-in' tariff beyond the current Rs 3.39. 5. TNERC: Extension of validity of the Commission's Tariff Order for Wind Projects The Commission issued a comprehensive Tariff Order on wind energy in Order No 1 of 2009 on 20.03.2009. As the validity of the Order expired on 31.03.2011, the validity was extended by the Commission upto 31.12.2011 vide Tariff Order No 1 of 2011 dated 08.04.2011. The validity of the said Order was further extended till 30.06.2012 by Order No 4 of 2011 dated 15.12.2011. A stakeholders hearing was held on 08.06.2012 to elicit their views on the tariff determination. Various issues were raised in the hearing which needs to be examined in detail before finalising the tariff order for the wind energy generators. Therefore, the Commission has extending the validity of Order No 1 of 2009 upto 31.07.2012 or the date of issue of tariff order, whichever is earlier. www.windforce-management.com
  • 5. Enabling High Efficiency and Reliable Wind Power Projects 5 6. RERC: Draft Tariff Order for Wind Power Plants for FY13 New Tariff (Rs/kWh) New Tariff (Rs/kWh) if higher Existing Tariff FY12 if Higher Sr. No. Particulars depreciation (Rs/kWh) depreciation benefit is not benefit is availed availed Wind Power Plants located in Jaisalmer, 1 4.46 5.18 4.90 Jodhpur & Barmer districts Wind Power Plants located in districts other 2 4.69 5.44 5.14 than Jaisalmer, Jodhpur & Barmer districts. The above tariff is levelised for 25 years. In the Order, following were introduced: (i) As all reasonable costs and returns are being allowed to be recovered through the tariff, therefore, any policy support by way of capital subsidy/Capital Finance Assistance (CFA), higher depreciation benefit or Generation Based Incentive (GBI), which becomes available to the developer/generator, needs to be passed on to the utilities. - This is been introduced first time and mostly not introduced by any SERC's (only CDM benefit is being shared with state utilities) (ii) In case, any wind power plant getting commissioned during FY 12-13 avails the benefit of GBI/Tariff subsidy under any Government Scheme, the applicable tariff worked out as above, would get reduced to the extent of GBI/Tariff subsidy so availed. In case such a benefit has not been availed, an undertaking to that effect would have to be given while signing PPA - This means if any developer has availed GBI benefit to the tune of INR 50 paise/kWhr then the same has to be reduced from the applicable tariff (iii) Tariff if Higher Depreciation is availed and Tariff if Higher Depreciation is not availed - Not clear whether Higher Depreciation is 15% + 25% or its 15% alone. Also in the tariff calculation depreciation benefit is considered as 17.50% ((50% (15%+20%)) www.windforce-management.com
  • 6. Enabling High Efficiency and Reliable Wind Power Projects 6 (iv) Considering that considerable capacity of the wind projects already stands commissioned in the State, the Distribution licensees, in the interest of the WinDForce Esteemed Clients consumers, must strive to procure wind energy at a generic tariff being lower of the Hindustan Zinc Limited, NSL Renewable, two streams namely, with or without higher depreciation benefit by giving Techno Electric, Bhilwara Energy Limited, preference, while finalising/signing PPA, to developers/generators offering the KSK Wind, Green Infra, Avigo Capital, lower rate among the said two tariff streams. However, if capacity in excess of RPO Olympus Capital, PTC India, Auro Mira, is to be contracted, the licensee must obtain prior approval of the Commission MSPL, TVS Energy, Indian Energy, based on reasons and full justification before contracting for capacity in excess of Reliance Power, CRISIL, IFCI Limited, RPO requirement. Oswal Woolen Mills Limited, Ushdev - This clearly means if DISCOM has fulfilled their RPO obligation by procuring Power Holdings, Bharat Light and power under FIT mode, then it is in the hands of commission to give clearance for Power,RSPL Ltd. (Ghari Detergent), signing of any new PPA for any excess power beyond the DISCOM's RPO. Due care Modelama Exports Ltd, Tata Power, L & T should be taken by investors before finalization of their projects. Infra, Kiran Gems, Dharmanandan Diamonds, Shah Promoters, Fena (P) Ltd., 7. KERC: Second Amendment to Procurement of Energy from Renewable Sources Bhabani Pigments, Panama Group, Regulations, 2012 Kandla Port Trust etc. KERC has issued second amendment to REC/ RPO Regulations for Procurement of Energy from Renewable Sources Regulations, 2012. Existing Regulation Amendment proposed Captive Power Producers (CPP) based on Grid Connected Captive Power Producers (CPP) renewable sources of energy shall be eligible to based on renewable sources of energy shall be get accredited for obtaining RE certificates for eligible to get accredited for obtaining RE the entire energy generated from their plants certificates for the energy generated and used including the energy used for captive for captive consumption and for surplus energy, consumption. if any, sold to the distribution licensee/s of the State at the average pooled power purchase cost notified by the Commission from time to time This amendment provides more clarity on Captive format. www.windforce-management.com
  • 7. Enabling High Efficiency and Reliable Wind Power Projects 7 What’s New 1. Government rating of DISCOMs to include RPO fulfilment as a criteria Ministry of Power has developed an integrated rating methodology covering the DISCOMs. The system is an attempt to harmonize the rating of DISCOMs by banks and financial institutions. One of the criteria for ranking of the DISCOMs will also be the level of their Renewable Purchase Obligation (RPO) fulfilment. Renewable Energy Purchase Obligation shall account 25% weightage of total rating. A system of negative marks has also been introduced in the rating methodology. The parameters assigned negative marks include non-auditing of accounts (upto minus 12%), SEB unbundling (upto minus 5%), non-filing of tariff petition (upto minus 5%), untreated revenue gap (upto minus 5%), deterioration in AT&C Loss (upto minus 5%), increase in payables (upto minus 3%), presence of Regulatory Asset (upto minus 3%), negative net-worth (minus 3%) and extent of cross subsidy (upto minus 2%). The first ranking is expected to release in March 2013. As all the distribution companies require huge amount of funds for their planned capital expenditure as well as working capital, all need good rating. With above criteria, very high weightage is given to RPO compliance as well as negative ratings for other management issues, DISCOMS are likely to follow the best practices to maintain high ratings and this should in return should give much needed push to offtake to RECs. 2. MNRE: Guidelines for installation of prototype wind turbine models in India The Ministry has decided to permit the installation of a limited number of prototype wind turbines to facilitate indigenization and encourage national industry. The guideline document is applicable for all the wind turbine manufacturers in India, who wish to install prototype wind turbine model(s) in the country and synchronize with the Indian grid system. The installation of a prototype wind turbine model will be allowed only to carry out type testing for obtaining type certificate from Internationally Accredited Certifying Agencies.  http://mnre.gov.in/file-manager/UserFiles/guidelines_prototype_wind_turbine.pdf  http://mnre.gov.in/file-manager/UserFiles/land_wind.pdf  http://www.cwet.tn.nic.in/Docu/Requirements%20for%20installation%20of%20prototype%20wind%20turbine%20model%20in%20India.pdf www.windforce-management.com
  • 8. Enabling High Efficiency and Reliable Wind Power Projects 8 Upcoming Events  Wind Power Project Development: Planning, Contracting, EPC organized by th Renewable Market India to be held on 24 August 2012 at The Lalit Intercontinental, Mumbai  Wind Power Development Forum India, organized by Wind Energy Update to be held on 6th - 7th September 2012 at Le Meridien, New Delhi www.windforce-management.com
  • 9. Enabling High Efficiency and Reliable Wind Power Projects 9 REC Update (till 30.06.12) Total Accredited = 1811.31 MW – Wind Specific Total Registered = 1426.08 MW – Wind Specific Total Issued = 16,69,827 RECs Total Redeemed = 14,92,437 RECs Total Inventory = 1,77,391 RECs REC Trading Equilibrium Price 250000 3,000 200000 2,500 (Rs/REC) 150000 2,000 100000 2,500 50000 1,000 0 Apr’11 May’11 Jun’11 Jul’11 Aug’11 Sep’11 Oct’11 Nov’11 Dec’11 Jan’12 Feb’12 Mar’12 Apr’12 May’12 Jun’12 IEX Traded Volume (REC) 260 14,002 15,902 14,668 22,095 41,385 92,303 96,154 1,05,942 1,65,460 1,90,482 1,92,354 62,277 1,53,125 2,23,164 IEX Equilibrium Price (Rs / REC) 1,500 1,500 1,505 1,555 1,800 2,300 2,700 2,900 2,950 3,051 3,066 2,900 2,201 2,402 2,402 In June'12 trading session total around 2,50,000 RECs were traded at an average rate @ Rs 2402/ MWh. Last year in Q1 at IEX total 30,164 RECs were traded at an avg. rate of Rs 1502 per REC where as this year in Q1 at IEX total 4,38,566 RECs have been traded at an avg. rate of Rs 2373 per REC. This year, in Q1 it was expected that Trading Volumes will be on lower side and the clearing price shall also be low as last year. But the market has shown some maturity and confidence amongst the stake holders. For the continuous growth of REC Market, it is very necessary that the entities which have not matched their RPO in FY12 must be penalized ASAP otherwise other entities which are following the RPO shall start deviating. At various public forums, the investors have expressed their concern on the bankability of REC based Wind Projects primarily because of short (5 years) control period (currently upto 2017 only) & the enforceability of RPO. The Government representatives have indirectly indicated that these issues are being taken care of and soon new order to address these issues shall come. www.windforce-management.com
  • 10. Contact Us Corporate Office Kindly write to us if you have any comments on this Newsletter. Your valuable WinDForce Management Services Pvt. Ltd. feedback on this would motivate and help us in improving the quality and enriching 5th Floor, Universal Trade Tower the content. We are eagerly waiting for your kind response to the articles presented in Gurgaon - Sohna Road this Newsletter. Gurgaon - 122001, Haryana Tel: +91 124 6653100 Parish Gupta Fax: +91 124 6653200 Mob: +91 98717 11445 Web: www.windforce-management.com E-mail: parish@windforce-management.com Rupesh Singh Mob: +91 96507 58884 E-mail: rupesh@windforce-management.com A WinDForce Publication Disclaimer - This Newsletter has been compiled by WinDForce Management Services Private Limited for circulation among the stakeholders in the energy market. Though the contents of this bulletin are correct to the best of our knowledge, WinDForce does not vouch for their accuracy. www.windforce-management.com