Rising building material costs and energy efficient construction
requirements make cost estimating and managing your project’s scope of
work and required inspections more important than ever. This session will
provide guidance in estimating project costs, managing the construction
process, and coordinating your project scope with important scheduling
activities.
2. Land Acquisition
Engineer to develop a preliminary plat
Land Dev. Committee and Board of Directors
Preliminary Pro Forma based on previous projects costs
Develop a Project Time Line
ID potential financial sources for Pre-Dev. cost as well
infrastructure Dev. Cost
3. FIRST PLAN
SHORT TERM GOALS
Develop Infrastructure Sell lots;
169 lots pay back Loans -
Rollow’s land
(April 2011- March 2012)
ID Financial acquisition and
infrastructure
Resources
Dec-Feb 2011
5. ROLLOW’S
FEASIBILITY ANALYSIS
Land
Land Rollow’s
Rollow’s
Acquisiti
Acquisiti Total
Total
on
on 39.6 acres
39.6 acres
TEDC
TEDC
($1,670,707)
($1,670,707)
RCAC Loan @
$ 5,176,485
5.5% $3,505,77
$920,707 8
HAC RHLF Loan
@ 5%
$750,000
6. Housing Assistance Council – Submitted an
application on December 2010
Wells Fargo Line of Credit (on hand)
RCAC (potential source)
SHOP Revolving Loan (on hand)
Housing America’s Land Development (on
hand)
7. USDA Rural Development Section 502 and 523 -- in jeopardy!!
Uncertainty on the Self Help programs
Census 2010 Results
MSA Designation /Rural Designation
HAC ‘s FINANCIAL APPLICATION WAS PUT ON HOLD!!!
8. P&Z reviewed the Plans and specifications for the Subdivision
The project was placed on hold with the City
Major conversations with HAC regarding other
Potential projects:
Phase I & II (High Construction Cost)
Reducing the number of lots from169
Add another potential project to the site
9. PROJECT GOALS (Rev)
Land Dev. Committee recommended to the
Board:
Reduce Subdivision to 149 lots
Dedicate 4.33 acres for a Multi Family Project
24 units 514/516 Farm Labor Housing
10 units 515 Rural Rental Housing
10. ISSUES AND NEGOTIATIONS WITH
MUNICIPALITY
Developed (4) separated plats to satisfy
the municipality (back and forth)
Final Approval!!!
Development Agreement
Shared Use Pathway System
A Six Feet (6’) block wall
Storm Water Retention
3 Improvement Districts
Bonds and Assurances
11. Change Primary Engineer
Timeline changes
Negotiations with the City
Dealing with NIMBY Neighbors (MF’s)
Spend more than $800K for Dev. Lots
SAGA Continuation on the Rural Designation
and the National Budget Continue Resolutions
12. Be persistent, believe in your
project
Sale your project
Hold more Land Dev. Meetings
Project Timeline Review with your
Eng.
Keep your Board informed
Avoid conflict with your city….