BPL




Bilt Power House
POWER HOUSE


 46 Kg/ cm2 pressure and 35 TPH Babcock and wilcox spreader stoker Boiler
X 1 NO

85 Kg/ cm2 pressure and 35 TPH x 03 nos (IJT)

TG Turbine 1 x 18 mw

 46 Kg/ cm2 pressure and 25 TPH Heat recovery Boiler X 1 NO (JMW)

 BTH TURBINE 6.25 MW X 1 NO (BRITISH THOMSON HOUSTEN)

 46 Kg/ cm2 pressure and 25 TPH Heat recovery Boiler X 1 NO (ABL)

Ash handling plant

Coal handling plant
BOILER SPECIFICATIONS                                BOILER PARAMETERS


Boiler No.   Unit     7       1       2       3     Boiler No.      Units     7
              s
                                                                                    1     2     3
Type of             Water   Water   Water   Water
boiler              Tube    Tube    Tube    tube

Make                B&W     IJT     IJT     IJT     Steam          kg/cm2    46    85    85    85
                                                    pressure

Designed     t/hr   35      35      35      35
Capacity
                                                    Steam            ºC      404   490   490   490
Designed      %     78      81      81      81
                                                    temperature
efficiency

Operating    t/hr   10 to   30 to   30 to   30 to
Capacity            35      40      40      40
                                                    Blow down        %       4-5   5-6   5-6   5-6
Operating     %     75-77   77 to   77to    77 to
efficiency                  80      80      80      %
                                                    Pollution     (ESP,      ESP   ESP   ESP   ESP
Fuel used           coal    coal    coal    Coal    control       cyclone)
                                                    device used
COAL HANDLING LAY OUT

                                  TRF/GB
       Make
                        :
       Capacity, tons /hr           80/40
               1.FEEDING SCREEN
                   2.VIBRATOR
  3.COAL CRUSHER OR GRANULATOR (HAMMER TYPE)
               4.CONVEYER BELTS
                   5.ROLLERS
                 6.COAL BUNKER
           Details of belt conveyor:
 Belt conveyer 1                [ 800 x 34, 263 long ]
 Belt conveyer 2                [ 600 x 14, 362 long ]
 Belt conveyer 3                [ 600 x 126,267 long]
 Belt conveyer 4                [ 600 x 21, 168 long ]
  Belt conveyer 5a & 5b        [ 800 x 32, 500 long ]
 Vibrating feeder            [ 915 wide x 1500 long ]
Coal size                     ¾ inches ( 15 – 20 mm )
            Grade of coal                 B
   Calorific value of coal      4500- 5000 kcal/kg
1 Type: V1000
              TRF                                                 COAL HANDLING LAY OUT
                    m
                                              coal
Coal charge                                   crusher
                                                             2
Type: 7 sfm




                        800x800x450




                                      3

  5A                4

                        me
                                          1- gear ratio : 30:1
5B                                        2-            : 30:1                      ELECON
                                          3-             :20 :1
                                          4-             :20:1      crusher          crusher
                                          5a :           :30:1
                                          5b :           :30:1
                                                                              OPP
FLUE GAS PATH HP BOILER
                               SECONDARY AIR


BOILER      1 ST CYCLON         2 ND CYCLON     3RD CYCLON


         TO GRATE
                                  HOT AIR OUT

                    AIR PRE
 ESP                                   ECONOMISER
                    HEATER

                      FD AIR




           SCREW CONVEYERS

         TO SUBMURGED ASH BELT
FLUE GAS PATH MP BOILER
                            econ


                                       GRN
       ESP




ID 90 KW

                         ID 200 KW
WORKING OF ESP

The flue gas laden with fly ash is sent through pipes having negatively
charged plates which give the particles a negative charge. The particles
are then routed past positively charged plates, or grounded plates,
which attract the now negatively-charged ash particles. The particles
stick to the positive plates until they are collected. The air that leaves
the plates is then clean from harmful pollutants. Just as the spoon
picked the salt and pepper up from the surface they were on, the
electrostatic precipitator extracts the pollutants out of the air.
ASH HANDLING LAY OUT

               ASH HANDLING PLANT                                         Impact rollers
               MAIN EQUIPMENTS:                                           plain rollers
               1.ASH BELT CONVEYER                                        Scrapper
               2.SUBMERGE BELTS
                                                                          Skirting
               3.SCREW CONVEYERS (SMALL AND LONG)
               4.ASH HOPPERS
               5.RIDDLING HOPPERS
               6. ROLLERS
                                                    To main ash Hooper
                SB1     SB3   SB3




                                                              ABC 3

                ABC 1
Plain return




                                            ABC 3 BYPASS
                 Carrying idler
                 Impact
                                                                         Carrying idler
                                                        Return
                                                                         Trough
ASH HANDLING LAY OUT




                                 BL 7 ESP



                                     HB




                            SB
                                     RAH



                                     FAH



      ECO   APH   ESP ESP



APH
ASH HANDLING PRE CAUTIONS


If inclined belt trips, Horizontal and submerged belt will automatically stops
OPP Submerged belt bypass : Trolley is used to transfer ash when it is bypassed
.Inclined belt : Bypass ABC 3 with in 3-5 minutes


Horizontal belt : ESP Hooper bypass

NPP Submerged belt has two bypass.

ABC 3 bypass                                                        PCS
Pull cord switch
                                                                     ZSS

                                                                     BSS



 ( Belt 1,Belt 2, Belt 3 (ABC 3by pass) ,horizontal belt, Inclined belt, submerged belts
  (3 in NPP and 1 in OPP). Only horizontal belt in OPP is having chain drive.
PDM


                               DEAERATOR

         OT                                 Suction

                                                      TO
                                                      HP
                                                      BOILERS


                                                      TO
                                                      ABL
                                                      BOILERS
 DARE.
  ABL




                                                      Suction




                      ABL          EFP1    85 KG      ABL
                      FP    EFP2           STEAM      STEAM
                                           FP         FP
ABL
deae. pump          LAY OUT FEED WATER (HP) SYSTEM
FEED PUMP SPECIFICATIONS

        ABL       85 KG     ELECT    ELECT    ABL FP
        STEAM     SFP       FP 1     FP 2
        FP
MAKE    KSB       MATH & MATH & MATH & KSB




                                                        NEW POWER PLANT
                  PLATT  PLATT  PLATT
TYPE    HAD       4/6 BFO 4/6 BFO 4/6 BFO HAD 50/15
        50/15     9 CHR   9 CHR   9 CHR
FLOW    25.3      145       145      145      25.3


HEAD    747MLC 1068 M       1068 M   1068 M   747 MLC


RPM     2960      2980      2980     2980     2950


KW/HP   -------   -------   700/938 700/938 100/134
Cond. From plant


                     Over head




                                                                                                           Prv outlet
                       tank




                                                                                    Prv outlet
                                                                   Prv outlet
                                             Deaerator




                                                           Vent




                                                                                                  Vent
   Cond
   tank




                                                         ST
                             3 KG                                 Exh           M                ST




                                                                                                         Exh
                                           suction


                                    MAIN
                                              DIRECT

                   46 KG
                                                         BL 7 FEED PUMP LINES
BL 7 FEED PUMP AREA PRE CAUTIONS

Condensate pump running indication by bulbs.

ABL feed pumps running indication by bulbs.

Inside feed pump attendants room electric feed pump running indication bulb

OT Level 10.5 feet indication bulb

OCT and NCT Level gauges (OCT-0-50-100 %=0-0.25-0.50 LEVEL),
 (NCT-0-50-100 % = 0-0.20-0.4 LEVEL)
 Inform DM plant if OCT level falls below 20 %)

OT level graphical indication also

Alarm will ring when any of the above condition is not satisfied.

Electric feed pump Amps above 370 Amps (OL on 380), Immediately steam
feed pump to be taken in service. Or if demand is more, inform NPP to start
supply from their end for ABL boiler in case BL 7 is running.

If any pump stops or trips immediately standby pump to be started.
BL 7 FEED PUMP AREA PRE CAUTIONS

Deaerator bypass system always in line
Balancing pressure should be within operating range to maintain the thrust
clearance
There are 2 supplies for ABL/Condensate / Deaerator pump viz. BTH / TG

Incase 2nd extraction pressure is more in BTH , Steam pump extraction line valve
required to be operate if instructed from BTH

Gland cooling line is to be continuously observed, There are two valves which are
of 55 & 150 hp , and if this is not available third one which comes from emergency
tank , valve to be opened

When JMW & BL 7 are in operation, ABL boiler feed water supply to be stopped
and ABL condensate pump to be started. (Valve near ABL boiler stairs entry). If only
JMW boiler is running feed water supply is from BL 7 feed pump.

JMW boiler feed water heater out temperature 130 deg. Cel. Maximum and steam
outlet temperature 405 deg. Cel. Maximum (Runs max 450 deg. Cel. )

No steam / water valve should be opened till the written memo is received and
physical check for drain, or isolation is confirmed
BL 7 FEED PUMP LINES
  TI                 TO STEAM DRUM



         ECO OUT

                         RTD




ECO IN

                                     MAIN

                                            Direct
JMW FEED WATER LINES

                                             To Boiler Drum




Eco in


         3 kg steam                                  Direct
                      Feed water heater




                                             Main
                  Condensate to NCT
Sr no   Parameter                      OV           Alarm   Trip
  FEED PUMP




                         FEED PUMP OPERATING PARAMETERS
Make:          M&P                                        1       Condensate pump load           30-32 A


                                                          2       Deaerator water temperature    105
Type: V.G PLUROVANE

                                                          3       Deaerator pump load            15-17 A
Head :        1980 ft.
             (600 m)                                      4       Deaerator discharge pressure   2-2.5


Size : 6” x 4”                                            5       Electric feed pump load        350          370     380
Discharge : 349 GPM
                                                          6       Suction pressure               1.5-2
             92 M3/HR
                                                          7       Discharge pressure             58-60
Motor :      322 HP
             430 KW                                       8       Balancing pressure             3                    6



RPM :                                                     9       Oil level

SP 1 :          3850
                                                          10      Overhead tank level            ABOVE        10.5
SP 2 :          3740                                                                             10.5 FT

EFP :           2960                                      11      OCT LEVEL                      Above 30 %   30 %    Below
                                                                                                                      20%

                                                          12      NCT Level                      Above 50 %   50 %    Below
                                                                                                                      40 %
CONDENSATE TANKS AND PDM

 TG condensate goes to PDM tank and from PDM tank to HP deaerator

BTH turbine,PM4, SPL machine condensate to NCT, then it is pumped to DM
plant for polishing, back to PDM tank

Remaining condensate from clo2,PM1,PM2,Pulp mill, S/R plant, chemical house
comes in OCT

From OCT it is pumped to Overhead feed tank of Boiler no 7 and other pump for
ABL overhead tank

OCT & NCT are inter connected ,OCT being on height than NCT.
 Level is maintained by DM plant, still if OCT level drops to 25 – 20 % verbally to
be inform to DM plant SE.
Hydrazine + Ammonia –LP Dosing & Nalcol 2518 + Caustic – HP Dosing
POLISHING: NCT            Charcoal filter               Iron filter      DM tank
PDM PUMP
Total head:45 m
                                    PDM Tank                       Secondary mixed bed
Flow : 416.7 lps
                                     BEFORE START UP OF BL 7, DM PLANT TO BE IMFORMED
85/46 STEAM HEADER

                                                                             Attempt. Line




                                            Range v/v BL2
                                                            Range v/v BL 3
    85 kg st pump




                            Range v/v BL1
                    TO TG




                                                                                       pg


                                                                             85/46


Condensate tank pump ( 1 and 3) and 2




                                                                                                                                    46 KG HEADER
                                                                                                              46 kg to TG Ejector
Raw water pump 1 and 3




                                                                                             To ABL st pump
Type: 4 U P3 (Double extraction)
Size : 150 x 100
Capacity : 40 lps (144 m3 / hr)
Head : 40 m
HP : 50
RPM : 1450
46/3 STEAM HEADER



                                                                    BTH TURBINE
  ABL 46




                                  JMW 46



                                           OLD 46




                                                                       Steam feed pump
46 KG/CM2 FROM           46/3 PRV
85/46 PRV

                        Location: JMW                     46/17/7




                                                                       BTH
   When condensate flow to TG condenser is less ,46/3 PRV is
   required to be charged. Control of opening of this valve is in
   TG Control room.

   It is assumed that steam flow from this line is 5 Tons Per
   Hour.
SOOTING JMW
   46 HEADER            650/250/100
                                                  Blade
                                                  coating   Pulp mill
46/17/7                                              17




                                                             7



 From 10/7 TG


                                     Chem house               7/3 PRV

                        Not in use




                BTH 7
PM1 , PM2 LINES



Supplim. For PM1
From BTH



  7 / 3 PRV
                                            PM 1 Supplim

                                     PM 2 Supplim



   3 kg                                             PM1


                                                    PM2
OPP office
10KG STEAM HEADER               rail     clo2
                     SM                           PULP MILL


      ABL




                            PRV 10/7                     10 KG
                                                         TG
             LIME KLIN




                                                                     From 46/17/7 prv
        Dorr plant    JMW APH          7 KG BTH
PMC4                     3 KG NETWORK
                                                         85 KG SFP   ABL




                                                                                                PULP MILL
                                                                                    DEAERATOR
                                                                          PM 4
                                           DORR

                        JMW FW HEATER



CH
                DEAERATOR
                FP EXH LINE
     BTH 7 KG




                                                           SM
                                                                     10 KG
                                                                                 CLO2



                                                                SR EVAP




                                                  CLO2




                                        SPL M/C
MP STEAM VALVE LOCATIONS

Sr. Customer               Pr.      Location
No                         Kg/cm2
.
1   PM 5                   10       Back side of CT
2   STARCH MILL            10       Railway gate
3   ABL                    10       Railway gate

4   PULP MILL              10       Behind TG room platform
5   CLO2                   10       Behind OPP Office
6   PULP MILL              7        Wooden bridge Boiler & BTH
7   CHEMICAL HOUSE         7        BTH header chain valve
8   BLADE COATING          17       Wooden bridge Boiler & BTH

9   FEED PUMP              46       ASH plant
LP STEAM VALVE LOCATIONS
Sr.   Customer                 Pr.    Location
No.                            Kg/cm2
1     CHEMICAL HOUSE           3      Above MW section TR 18 (Toilet)
2     PM 1                     3      Platform in front of PM 1
3     PM2                      3      Platform in front of PM 2


4     PM1 SUPPLM.VALVE         3      BTH house
5     PM2 SUPPLM.VALVE         3      In front of BTH between 2 tanks
6     S/R EVAPORATOR           3      Near 46/3 PRV STAIRS
7     PM 5 / 6 / 7             3      Above BL 7 Control room
8     PM4                      3      Near BL 1 FD fan area
9     DORR PLANT               3      Near JMW ESP Stairs
10    HP DEAERATOR             3      Hp deaerator
11    ABL DEAERATOR            3      ABL deaerator
12    BL 7 DEAERATOR           3      BL 7 feed pump area
13    PULP MILL                3      Rail gate + 46/10 PRV
14    MC NO 4                  3      From BTH also
15    CLO2                     3      Above BL 7 Control room
BOILER NO 7

       FRONT AND REAR TUBES GOES TO STEAM DRUM

       RIGHT & LEFT END TUBES FORM HEADER ,THEN
       GOES TO STEAM DRUM
               RIGHT




                                        COAL FEEDER SIDE
                                FRONT
REAR




           LEFT
BL NO 7 WATER WALLS




REAR END
LEFT END
 RIGHT END
FRONT END
BOILER NO 7,8 MOUNTINGS AND FITTINGS
Drum safety valves
SH stop valve
SH safety valve
Drum gauge glass
Range valve
Blow down valve (04 + 02)   RGG
Economizer safety valve
Steam flow meter
Water flow meter
Hi and LO Whistle




                                                         DOSING
COOLING TOWERS

MAKE : PAHARPUR COOLING TOWERS (Induced draft )

BTH                                             TG
Total fans :9 nos                         Fans : 02 nos
Current : 36 amps                         Current : Fan 1 VFD 45 amps
Circulation rate: 2900 m3/hr                        Fan 2 65 amps
Evaporation lass : 16 m3/hr               Circulation rate : 3200 m3/hr
                                          Evaporation loss: 32 m3/hr

.
TUBE WELL SUPPLY:              3,4,8,16,20,22. 10,12,14,15,17   18,19   1,21

CHEMICALS USED:

H2SO4 - PH CONTROL                         7002
2718:                                      7500
7000:                                      CHLORINE
150 HP PUMP HOUSE

                           NOT IN USE
Pump 1 current: 25 A           OLD PH           PULP MILL
VFD 40 HZ




                                                                   PM 4 & OLD
                                                                   PH


     5              4           3           2            1


                                                         TANK LEVEL 12 FEET
                                                         SCALE
                                                         READING -------FEET
                                                         EMPTY

      TO HYDRANT

 TUBE WELL LINES:       3,4,8,16,20,22. 10,12,14,15,17   18,19   1,21
150 HP PUMP HOUSE ELECTRICAL SUPPLY




 PUMP NO 1 IS HAVING VFD.

PUMP NO 2 IS HAVING COS FROM DB2 (BTH AND TG).

PUMP NO 3 IS HAVING BTH SUPPLY

PUMP NO 4 AND 5 HAS COS FROM DB2.

FROM 150 HP PUMP HOUSE COS DB2 AND COS DB1 SUPPLY IS GIVEN.

PUMP NO 1 RUNS NORMALLY IN 150 HP PUMP HOUSE

PUMP NO 4 – HYDRANT
55 HP PUMP HOUSE
                                            NOT IN USE
MC 1,4 NOT IN USE                           COATING PLANT               NOT IN USE



           Pump 5 current: 82-84 A




    1              2                         4           5


                                                                TANK LEVEL 5 FEET
                                                                SCALE
                                                                READING -------FEET
                                                                FULL
                                    MC 1,4 / DM/ DORR/ SR/ PH/ CH/ NPP


TUBE WELL LINES:       3,4,8,16,20,22. 10,12,14,15,17   18,19    1,21
FROM SPL PUMP
                                                               55 HP PUMP HOUSE
                             DM PLANT
                                                        TUBE WELL NO 6 / 9 CONNECTION
                                                                                                     55




                                                                                                          PMC 1 , 2
                                               EMERGENCY
FROM SPLITY PUMP HOUSE




                                               GLAND
                                               FILLING TANK
                                                                   BTH SUMP
                           BFW PUMPS
                           GLAND


                         DORR / SR/NPP
                          BFW PUMPS
                          GLAND

                                                                              BTH OIL / AIR COOLER
                          SR/NPP


                                   BTH DRINKING/WASHING


                                                              CH
55 HP PUMP HOUSE ELECTRICAL SUPPLY




 PUMP NO 5 IS HAVING VFD.

SUPPLY FROM PANEL NO 2

DB1 SUPPLY TO TUBE WELL NO 1 AND 2 ,AND TO SERVICE PUMP NO 4.

COS IS FOR ABOVE. (Main supply from 150 HP pump house)

SUPPLY FOR PUMP NO 1 FROM PANEL NO 1.

COS FOR DB2 IS FOR SERVICE PUMP NO 1 , 2 , AND 5.

PUMP NO 5 RUNS NORMALLY.
FIRE PUMP DETAILS

At four location Fire pump stations are available

 Main fire pump house at S/R area (4 Pumps)

At ETP (2 Pumps, One electric driven and other Diesel 12 cyl driven )

At Yard sump Electric pump

At 150 HP pump house , pump no 4.

From main fire pump house, pump no 4 runs normally

Yard fire pump some times used when sump level to be make up

All three supply available
FIRE PUMP DETAILS

Fire hydrant circuit 1 (cooling pond)    Pump 2
Pump 1 (Pump no 3)                       Make Mather and greeves
Make : Mather and Platt                  Type: 8/8 MHL
Type : 7.2 ST MEDI                       Capacity: 1500 gpm
Capacity: 1000 gpm                       Head : 290 ft
Head : 290 ft
                                         HP : 200 RPM: 1450
HP : 190 RPM : 1450

 Pump 2B (ETP)                           Diesel engine driven pump :
 Make : Kirloskar                        8/8 MHL Mather and platt
 Type: SVA 8                             Capacity : 1500 gpm
 Size: 8 x 8                             Head : 290 ft
 Capacity : 1400 gpm                     RPM : 1450
 Head : 225 ft                           Diesel engine make: MWM
 HP : 200 RPM : 1450                     Type: TD – 237 – VIZ
Fire hydrant circuit 3 ( Chipper yard)   BHP : 200
Pump no 3:                               RPM : 1500
Make : Mather and Platt
Capacity : 1500 gpm
Head : 290 ft
HP : 200 RPM : 1440
Reservoir capacity : 2 lacs gallon
FIRE PUMP HOUSE



Sometimes pump no 2 is started for CH increased consumption




         1               2                   4                3




                                      66 A / 2.5 K/c2
SPECIALITY PUMP HOUSE DETAILS
                                                                              250 M3/HR
                                                                              4 K/C2
                                                  TW NO 9 / 6                 85 A




                                                                                            COATING PLANT
                     NEW POWER HOUSE




                                                                           AIR COMPRESSOR
                              M3/HR




                                                 55/ 150 LINE
                              2-2.5 K/C2
                              65-70 A




                                                                                                            PULP MILL
           SHUT               1 RUNNING                           1 RUNNING

TUBE WELL LINES:    3,4,8,16,20,22. 10,12,14,15,17              18,19   1,21
AIR COMPRESSORS

 Air compressors in power house are situated as follows Motor load: 230-250 A

1) 2 nos at old power plant

2) 2 nos at new power plant

3) 4 nos at specialty machine area

                                               cooler   2.5 kg/cm2

 Air comp no 2,6,4,5                                                           PROCESS
                                               cooler



                                                                 Coating plant
                                                    5 kg/cm2
AD        AD

                                      cooler
                                                   5 kg/cm2    Pulp mill , spl machines ,
                       RECIEVER                                Clo2 plant, power house
                         TANK
                                      cooler
AIR COMPRESSORS


NPP :   KG KHOSLA MAKE                  SPL :    KG KHOSLA MAKE
        Double stage                             Double stage
        3H Y2TCER                                Air comp no 4,5,6
        RPM : 650                                RPM : 800
        Pr. : 7 kg/cm2                           Pr. : 7 kg/cm2
        Cap : 5.89 m3/min                        Cap : 51.41 m3/min
        Pr 1 st stage : 2 kg/cm2                 Pr 1 st stage : 2 kg/cm2
        pr 2 nd stage : 5.5 kg/cm2               pr 2 nd stage : 5.5 kg/cm2
        oil pr. : 2.5 kg/cm2                     oil pr. : 2.5 kg/cm2


                      SPL :   KG KHOSLA MAKE
                              Single stage
                              Air comp no 2
                              RPM : 560
                              Pr. : 7 kg/cm2
                              Cap : 11.01 m3/min
                              oil pr. : 2.5 kg/cm2
AIR COMPRESSORS PRE CAUTIONS




 Air is distributed from new power plant air compressors to POWER HOUSE

 Air compressors in Old Power House are standby.

In case of air pressure drop or compressor trip, SPL pump house air compressor
valve can be opened which is at NPP electrical panel room.

Also one line from S/R plant air compressors is available for the same purpose
but it is rarely used.

Air compressors in Old Power Plant can be started in emergencies, can be put in
Auto mode .One will be Auto and other will be stand by.
TUBE WELL NETWORK
INSIDE 1,2,6,7,9,10,12,14,15,17,21




                                                                                                                             OUT SIDE 3,4,8,16,20,22
                                     TUBE WELL   LOCATION                                  SUPPLY        CHANGE OVER
                                     NO
                                     1           CHAIR REPAIR WORK SHOP                                  55 HP PUMP HOUSE
                                     2           COATING PLANT (BEHIND 55 HP PUMP HOUSE)                 55 HP PUMP HOUSE
                                     3           TI CLUB                                                 NEAR TUBE WELL 8
                                     4           RAMLEELA STAGE                                          NEAR TUBE WELL 8
                                     5           DOES NOT EXSISTS                                        -------
                                     6           BEHIND DM PLANT                                         SAME LOCATION
                                     7           DISPENSARY NO 5                                         NEAR TUBE WELL 8
                                     8           TR BUILDING NEAR TEMPLE                                 NEAR TUBE WELL 8
                                     9           GHEE PLANT                                FROM BOILER
                                                                                           HOUSE DB
                                     10          GATE NO 9                                               NEAR TUBE WELL 10




                                                                                                                             PUNJAB 18,19
                                     11          DOES NOT EXSISTS                                        -------
                                     12          ETP                                                     MACHINE NO 5 / 7
                                     13          DOES NOT EXSISTS                                        -------
                                     14          200 QTR NEW GATE                                        SAME LOCATION
                                     15          GATE NO 8                                               NEAR TUBE WELL 10
                                     16          CHUNA BHATTI                                            NEAR DR BUILDING
                                     17          NANGAL POWER HOUSE
                                     18          PUNJAB MILL                               NANGAL        NO CCHANGE OVER
                                     19          PUNJAB MILL                               NANGAL        NO CHANGE OVER
                                     20          TR BUILDING GROUND                                      NEAR TUBE WELL 8
                                     21          NEAR TRAFFIC DEPT.                                      Location
                                     22          DR BUILDING OLD                                         NEAR DR BUILDING
Power house specifications & operations

Contenu connexe

Tendances

Biofuels In France - From 1st To 2nd Generation Within A Biorefinery Strateg...
Biofuels In France -  From 1st To 2nd Generation Within A Biorefinery Strateg...Biofuels In France -  From 1st To 2nd Generation Within A Biorefinery Strateg...
Biofuels In France - From 1st To 2nd Generation Within A Biorefinery Strateg...BioMotion Tour
 
Propulsion - Ultra Steam Turbine - 5 pp
Propulsion - Ultra Steam Turbine - 5 ppPropulsion - Ultra Steam Turbine - 5 pp
Propulsion - Ultra Steam Turbine - 5 ppIngeniería Marina
 
2008 04 15 Hydraulic Range
2008 04 15 Hydraulic Range2008 04 15 Hydraulic Range
2008 04 15 Hydraulic Rangejlvaz
 
Filtration equipment
Filtration equipmentFiltration equipment
Filtration equipmentFluidra India
 

Tendances (8)

Biofuels In France - From 1st To 2nd Generation Within A Biorefinery Strateg...
Biofuels In France -  From 1st To 2nd Generation Within A Biorefinery Strateg...Biofuels In France -  From 1st To 2nd Generation Within A Biorefinery Strateg...
Biofuels In France - From 1st To 2nd Generation Within A Biorefinery Strateg...
 
Propulsion - Ultra Steam Turbine - 5 pp
Propulsion - Ultra Steam Turbine - 5 ppPropulsion - Ultra Steam Turbine - 5 pp
Propulsion - Ultra Steam Turbine - 5 pp
 
Lavavajillas
LavavajillasLavavajillas
Lavavajillas
 
2008 04 15 Hydraulic Range
2008 04 15 Hydraulic Range2008 04 15 Hydraulic Range
2008 04 15 Hydraulic Range
 
Le tourneau l2350
Le tourneau l2350Le tourneau l2350
Le tourneau l2350
 
Schaaf pumps flyer
Schaaf pumps   flyerSchaaf pumps   flyer
Schaaf pumps flyer
 
Filtration equipment
Filtration equipmentFiltration equipment
Filtration equipment
 
Stamford pi144 f
Stamford pi144 fStamford pi144 f
Stamford pi144 f
 

En vedette

Presentation on Dehar power house(DPH), slapper
Presentation on Dehar power house(DPH), slapperPresentation on Dehar power house(DPH), slapper
Presentation on Dehar power house(DPH), slapperJyoti Rawat
 
Powerhouse Presentation
Powerhouse PresentationPowerhouse Presentation
Powerhouse Presentationwacotao
 
Hydropower - power house
Hydropower - power houseHydropower - power house
Hydropower - power housearullawrance90
 
Penstocks, powerhouse and tailrace
Penstocks, powerhouse and tailracePenstocks, powerhouse and tailrace
Penstocks, powerhouse and tailraceRakesh Sunari Magar
 

En vedette (6)

Presentation on Dehar power house(DPH), slapper
Presentation on Dehar power house(DPH), slapperPresentation on Dehar power house(DPH), slapper
Presentation on Dehar power house(DPH), slapper
 
Powerhouse Presentation
Powerhouse PresentationPowerhouse Presentation
Powerhouse Presentation
 
Hydropower - power house
Hydropower - power houseHydropower - power house
Hydropower - power house
 
Water treatment of steam boilers
Water treatment of steam boilersWater treatment of steam boilers
Water treatment of steam boilers
 
Hydro power plant
Hydro power plantHydro power plant
Hydro power plant
 
Penstocks, powerhouse and tailrace
Penstocks, powerhouse and tailracePenstocks, powerhouse and tailrace
Penstocks, powerhouse and tailrace
 

Similaire à Power house specifications & operations

2011 co coman coconut coir machine catalogue a
2011 co coman coconut coir machine catalogue a2011 co coman coconut coir machine catalogue a
2011 co coman coconut coir machine catalogue arodrigolaraalmaraz
 
BRITISH THOMSON HOUSTON TURBINE
BRITISH THOMSON HOUSTON TURBINE BRITISH THOMSON HOUSTON TURBINE
BRITISH THOMSON HOUSTON TURBINE Sakshi Vashist
 
ppt on summer training Vardhman's Mahavir Spinning Mills Baddi (weaving devis...
ppt on summer training Vardhman's Mahavir Spinning Mills Baddi (weaving devis...ppt on summer training Vardhman's Mahavir Spinning Mills Baddi (weaving devis...
ppt on summer training Vardhman's Mahavir Spinning Mills Baddi (weaving devis...Bharat Rana
 
Coal Handling Plant
Coal Handling PlantCoal Handling Plant
Coal Handling PlantAshrant Dass
 
kstps summer training 36 slides
 kstps summer training 36 slides kstps summer training 36 slides
kstps summer training 36 slidesDanveer Singh
 
Presentation on THERMAL POWER PLANT
Presentation on THERMAL POWER PLANT Presentation on THERMAL POWER PLANT
Presentation on THERMAL POWER PLANT Abhijeet Thakur
 
PPT 31-05-2023 CHP ET TRAINING.pptx
PPT 31-05-2023 CHP ET TRAINING.pptxPPT 31-05-2023 CHP ET TRAINING.pptx
PPT 31-05-2023 CHP ET TRAINING.pptxGholamRabbaniGhause
 
Pumps and counter current pdf document Aqua Middle East FZC
Pumps and counter current pdf document Aqua Middle East FZCPumps and counter current pdf document Aqua Middle East FZC
Pumps and counter current pdf document Aqua Middle East FZCAdolfsmith69
 
Coal to Electricity
Coal to Electricity Coal to Electricity
Coal to Electricity Study Hub
 
Ntpc (national thermal power corporation) sipat boiler haxxo24 i~i
Ntpc (national thermal power corporation) sipat boiler haxxo24 i~iNtpc (national thermal power corporation) sipat boiler haxxo24 i~i
Ntpc (national thermal power corporation) sipat boiler haxxo24 i~ihaxxo24
 

Similaire à Power house specifications & operations (20)

High Pressure Boilers
High Pressure BoilersHigh Pressure Boilers
High Pressure Boilers
 
Thermal power plants
Thermal power plantsThermal power plants
Thermal power plants
 
2011 co coman coconut coir machine catalogue a
2011 co coman coconut coir machine catalogue a2011 co coman coconut coir machine catalogue a
2011 co coman coconut coir machine catalogue a
 
BRITISH THOMSON HOUSTON TURBINE
BRITISH THOMSON HOUSTON TURBINE BRITISH THOMSON HOUSTON TURBINE
BRITISH THOMSON HOUSTON TURBINE
 
ppt on summer training Vardhman's Mahavir Spinning Mills Baddi (weaving devis...
ppt on summer training Vardhman's Mahavir Spinning Mills Baddi (weaving devis...ppt on summer training Vardhman's Mahavir Spinning Mills Baddi (weaving devis...
ppt on summer training Vardhman's Mahavir Spinning Mills Baddi (weaving devis...
 
coal pulveriser
coal pulveriser coal pulveriser
coal pulveriser
 
Gas producer plant
Gas producer plantGas producer plant
Gas producer plant
 
Coal Handling Plant
Coal Handling PlantCoal Handling Plant
Coal Handling Plant
 
kstps summer training 36 slides
 kstps summer training 36 slides kstps summer training 36 slides
kstps summer training 36 slides
 
Power generation
Power generationPower generation
Power generation
 
Ecopro am-918
Ecopro am-918Ecopro am-918
Ecopro am-918
 
Maesod boiler training
Maesod boiler trainingMaesod boiler training
Maesod boiler training
 
Lhb ac buffet car
Lhb ac buffet carLhb ac buffet car
Lhb ac buffet car
 
Presentation on THERMAL POWER PLANT
Presentation on THERMAL POWER PLANT Presentation on THERMAL POWER PLANT
Presentation on THERMAL POWER PLANT
 
PPT 31-05-2023 CHP ET TRAINING.pptx
PPT 31-05-2023 CHP ET TRAINING.pptxPPT 31-05-2023 CHP ET TRAINING.pptx
PPT 31-05-2023 CHP ET TRAINING.pptx
 
Pumps and counter current pdf document Aqua Middle East FZC
Pumps and counter current pdf document Aqua Middle East FZCPumps and counter current pdf document Aqua Middle East FZC
Pumps and counter current pdf document Aqua Middle East FZC
 
Coal to Electricity
Coal to Electricity Coal to Electricity
Coal to Electricity
 
Ntpc (national thermal power corporation) sipat boiler haxxo24 i~i
Ntpc (national thermal power corporation) sipat boiler haxxo24 i~iNtpc (national thermal power corporation) sipat boiler haxxo24 i~i
Ntpc (national thermal power corporation) sipat boiler haxxo24 i~i
 
Brayton cycle
Brayton cycleBrayton cycle
Brayton cycle
 
Pppp
PpppPppp
Pppp
 

Plus de Sakshi Vashist

400 challenging puzzles
400 challenging puzzles400 challenging puzzles
400 challenging puzzlesSakshi Vashist
 
Aptitude testing puzzles for freshers
Aptitude testing puzzles for freshersAptitude testing puzzles for freshers
Aptitude testing puzzles for freshersSakshi Vashist
 
MCC Motor Control Center 4
MCC Motor Control Center 4MCC Motor Control Center 4
MCC Motor Control Center 4Sakshi Vashist
 
MCC Motor Control Center 3
MCC Motor Control Center 3MCC Motor Control Center 3
MCC Motor Control Center 3Sakshi Vashist
 
MCC Motor Control Center 2
MCC Motor Control Center 2MCC Motor Control Center 2
MCC Motor Control Center 2Sakshi Vashist
 
MCC Motor Control Center 1
MCC Motor Control Center 1MCC Motor Control Center 1
MCC Motor Control Center 1Sakshi Vashist
 
Residential Surge Protection 3
Residential Surge Protection 3Residential Surge Protection 3
Residential Surge Protection 3Sakshi Vashist
 
Residential Surge Protection 2
Residential Surge Protection 2Residential Surge Protection 2
Residential Surge Protection 2Sakshi Vashist
 
Residential Surge Protection 1
Residential Surge Protection 1Residential Surge Protection 1
Residential Surge Protection 1Sakshi Vashist
 
variable frequency drive (VFD) installation
variable frequency drive (VFD) installationvariable frequency drive (VFD) installation
variable frequency drive (VFD) installationSakshi Vashist
 
Power plant instrumentation
Power plant instrumentationPower plant instrumentation
Power plant instrumentationSakshi Vashist
 
All about paper making process
All about paper making processAll about paper making process
All about paper making processSakshi Vashist
 

Plus de Sakshi Vashist (20)

Puzzles to puzzle you
Puzzles to puzzle youPuzzles to puzzle you
Puzzles to puzzle you
 
Mind blowing puzzles
Mind blowing puzzlesMind blowing puzzles
Mind blowing puzzles
 
400 challenging puzzles
400 challenging puzzles400 challenging puzzles
400 challenging puzzles
 
400 infy puzzles
400 infy puzzles400 infy puzzles
400 infy puzzles
 
Aptitude testing puzzles for freshers
Aptitude testing puzzles for freshersAptitude testing puzzles for freshers
Aptitude testing puzzles for freshers
 
MCC Motor Control Center 4
MCC Motor Control Center 4MCC Motor Control Center 4
MCC Motor Control Center 4
 
MCC Motor Control Center 3
MCC Motor Control Center 3MCC Motor Control Center 3
MCC Motor Control Center 3
 
MCC Motor Control Center 2
MCC Motor Control Center 2MCC Motor Control Center 2
MCC Motor Control Center 2
 
MCC Motor Control Center 1
MCC Motor Control Center 1MCC Motor Control Center 1
MCC Motor Control Center 1
 
Residential Surge Protection 3
Residential Surge Protection 3Residential Surge Protection 3
Residential Surge Protection 3
 
Residential Surge Protection 2
Residential Surge Protection 2Residential Surge Protection 2
Residential Surge Protection 2
 
Residential Surge Protection 1
Residential Surge Protection 1Residential Surge Protection 1
Residential Surge Protection 1
 
Plc operation part 4
Plc operation part 4Plc operation part 4
Plc operation part 4
 
Plc operation part 3
Plc operation part 3Plc operation part 3
Plc operation part 3
 
Plc operation part 2
Plc operation part 2Plc operation part 2
Plc operation part 2
 
PLC operation part 1
PLC operation part 1PLC operation part 1
PLC operation part 1
 
Tg turbine
Tg turbineTg turbine
Tg turbine
 
variable frequency drive (VFD) installation
variable frequency drive (VFD) installationvariable frequency drive (VFD) installation
variable frequency drive (VFD) installation
 
Power plant instrumentation
Power plant instrumentationPower plant instrumentation
Power plant instrumentation
 
All about paper making process
All about paper making processAll about paper making process
All about paper making process
 

Dernier

Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptxUse of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptxLoriGlavin3
 
A Framework for Development in the AI Age
A Framework for Development in the AI AgeA Framework for Development in the AI Age
A Framework for Development in the AI AgeCprime
 
TrustArc Webinar - How to Build Consumer Trust Through Data Privacy
TrustArc Webinar - How to Build Consumer Trust Through Data PrivacyTrustArc Webinar - How to Build Consumer Trust Through Data Privacy
TrustArc Webinar - How to Build Consumer Trust Through Data PrivacyTrustArc
 
So einfach geht modernes Roaming fuer Notes und Nomad.pdf
So einfach geht modernes Roaming fuer Notes und Nomad.pdfSo einfach geht modernes Roaming fuer Notes und Nomad.pdf
So einfach geht modernes Roaming fuer Notes und Nomad.pdfpanagenda
 
Potential of AI (Generative AI) in Business: Learnings and Insights
Potential of AI (Generative AI) in Business: Learnings and InsightsPotential of AI (Generative AI) in Business: Learnings and Insights
Potential of AI (Generative AI) in Business: Learnings and InsightsRavi Sanghani
 
[Webinar] SpiraTest - Setting New Standards in Quality Assurance
[Webinar] SpiraTest - Setting New Standards in Quality Assurance[Webinar] SpiraTest - Setting New Standards in Quality Assurance
[Webinar] SpiraTest - Setting New Standards in Quality AssuranceInflectra
 
Genislab builds better products and faster go-to-market with Lean project man...
Genislab builds better products and faster go-to-market with Lean project man...Genislab builds better products and faster go-to-market with Lean project man...
Genislab builds better products and faster go-to-market with Lean project man...Farhan Tariq
 
Long journey of Ruby standard library at RubyConf AU 2024
Long journey of Ruby standard library at RubyConf AU 2024Long journey of Ruby standard library at RubyConf AU 2024
Long journey of Ruby standard library at RubyConf AU 2024Hiroshi SHIBATA
 
Connecting the Dots for Information Discovery.pdf
Connecting the Dots for Information Discovery.pdfConnecting the Dots for Information Discovery.pdf
Connecting the Dots for Information Discovery.pdfNeo4j
 
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptxThe Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptxLoriGlavin3
 
UiPath Community: Communication Mining from Zero to Hero
UiPath Community: Communication Mining from Zero to HeroUiPath Community: Communication Mining from Zero to Hero
UiPath Community: Communication Mining from Zero to HeroUiPathCommunity
 
Digital Identity is Under Attack: FIDO Paris Seminar.pptx
Digital Identity is Under Attack: FIDO Paris Seminar.pptxDigital Identity is Under Attack: FIDO Paris Seminar.pptx
Digital Identity is Under Attack: FIDO Paris Seminar.pptxLoriGlavin3
 
Emixa Mendix Meetup 11 April 2024 about Mendix Native development
Emixa Mendix Meetup 11 April 2024 about Mendix Native developmentEmixa Mendix Meetup 11 April 2024 about Mendix Native development
Emixa Mendix Meetup 11 April 2024 about Mendix Native developmentPim van der Noll
 
Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...
Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...
Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...Alkin Tezuysal
 
Manual 508 Accessibility Compliance Audit
Manual 508 Accessibility Compliance AuditManual 508 Accessibility Compliance Audit
Manual 508 Accessibility Compliance AuditSkynet Technologies
 
Sample pptx for embedding into website for demo
Sample pptx for embedding into website for demoSample pptx for embedding into website for demo
Sample pptx for embedding into website for demoHarshalMandlekar2
 
Scale your database traffic with Read & Write split using MySQL Router
Scale your database traffic with Read & Write split using MySQL RouterScale your database traffic with Read & Write split using MySQL Router
Scale your database traffic with Read & Write split using MySQL RouterMydbops
 
Generative Artificial Intelligence: How generative AI works.pdf
Generative Artificial Intelligence: How generative AI works.pdfGenerative Artificial Intelligence: How generative AI works.pdf
Generative Artificial Intelligence: How generative AI works.pdfIngrid Airi González
 
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...Wes McKinney
 
How to write a Business Continuity Plan
How to write a Business Continuity PlanHow to write a Business Continuity Plan
How to write a Business Continuity PlanDatabarracks
 

Dernier (20)

Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptxUse of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
 
A Framework for Development in the AI Age
A Framework for Development in the AI AgeA Framework for Development in the AI Age
A Framework for Development in the AI Age
 
TrustArc Webinar - How to Build Consumer Trust Through Data Privacy
TrustArc Webinar - How to Build Consumer Trust Through Data PrivacyTrustArc Webinar - How to Build Consumer Trust Through Data Privacy
TrustArc Webinar - How to Build Consumer Trust Through Data Privacy
 
So einfach geht modernes Roaming fuer Notes und Nomad.pdf
So einfach geht modernes Roaming fuer Notes und Nomad.pdfSo einfach geht modernes Roaming fuer Notes und Nomad.pdf
So einfach geht modernes Roaming fuer Notes und Nomad.pdf
 
Potential of AI (Generative AI) in Business: Learnings and Insights
Potential of AI (Generative AI) in Business: Learnings and InsightsPotential of AI (Generative AI) in Business: Learnings and Insights
Potential of AI (Generative AI) in Business: Learnings and Insights
 
[Webinar] SpiraTest - Setting New Standards in Quality Assurance
[Webinar] SpiraTest - Setting New Standards in Quality Assurance[Webinar] SpiraTest - Setting New Standards in Quality Assurance
[Webinar] SpiraTest - Setting New Standards in Quality Assurance
 
Genislab builds better products and faster go-to-market with Lean project man...
Genislab builds better products and faster go-to-market with Lean project man...Genislab builds better products and faster go-to-market with Lean project man...
Genislab builds better products and faster go-to-market with Lean project man...
 
Long journey of Ruby standard library at RubyConf AU 2024
Long journey of Ruby standard library at RubyConf AU 2024Long journey of Ruby standard library at RubyConf AU 2024
Long journey of Ruby standard library at RubyConf AU 2024
 
Connecting the Dots for Information Discovery.pdf
Connecting the Dots for Information Discovery.pdfConnecting the Dots for Information Discovery.pdf
Connecting the Dots for Information Discovery.pdf
 
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptxThe Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
 
UiPath Community: Communication Mining from Zero to Hero
UiPath Community: Communication Mining from Zero to HeroUiPath Community: Communication Mining from Zero to Hero
UiPath Community: Communication Mining from Zero to Hero
 
Digital Identity is Under Attack: FIDO Paris Seminar.pptx
Digital Identity is Under Attack: FIDO Paris Seminar.pptxDigital Identity is Under Attack: FIDO Paris Seminar.pptx
Digital Identity is Under Attack: FIDO Paris Seminar.pptx
 
Emixa Mendix Meetup 11 April 2024 about Mendix Native development
Emixa Mendix Meetup 11 April 2024 about Mendix Native developmentEmixa Mendix Meetup 11 April 2024 about Mendix Native development
Emixa Mendix Meetup 11 April 2024 about Mendix Native development
 
Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...
Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...
Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...
 
Manual 508 Accessibility Compliance Audit
Manual 508 Accessibility Compliance AuditManual 508 Accessibility Compliance Audit
Manual 508 Accessibility Compliance Audit
 
Sample pptx for embedding into website for demo
Sample pptx for embedding into website for demoSample pptx for embedding into website for demo
Sample pptx for embedding into website for demo
 
Scale your database traffic with Read & Write split using MySQL Router
Scale your database traffic with Read & Write split using MySQL RouterScale your database traffic with Read & Write split using MySQL Router
Scale your database traffic with Read & Write split using MySQL Router
 
Generative Artificial Intelligence: How generative AI works.pdf
Generative Artificial Intelligence: How generative AI works.pdfGenerative Artificial Intelligence: How generative AI works.pdf
Generative Artificial Intelligence: How generative AI works.pdf
 
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...
 
How to write a Business Continuity Plan
How to write a Business Continuity PlanHow to write a Business Continuity Plan
How to write a Business Continuity Plan
 

Power house specifications & operations

  • 2. POWER HOUSE  46 Kg/ cm2 pressure and 35 TPH Babcock and wilcox spreader stoker Boiler X 1 NO 85 Kg/ cm2 pressure and 35 TPH x 03 nos (IJT) TG Turbine 1 x 18 mw  46 Kg/ cm2 pressure and 25 TPH Heat recovery Boiler X 1 NO (JMW)  BTH TURBINE 6.25 MW X 1 NO (BRITISH THOMSON HOUSTEN)  46 Kg/ cm2 pressure and 25 TPH Heat recovery Boiler X 1 NO (ABL) Ash handling plant Coal handling plant
  • 3. BOILER SPECIFICATIONS BOILER PARAMETERS Boiler No. Unit 7 1 2 3 Boiler No. Units 7 s 1 2 3 Type of Water Water Water Water boiler Tube Tube Tube tube Make B&W IJT IJT IJT Steam kg/cm2 46 85 85 85 pressure Designed t/hr 35 35 35 35 Capacity Steam ºC 404 490 490 490 Designed % 78 81 81 81 temperature efficiency Operating t/hr 10 to 30 to 30 to 30 to Capacity 35 40 40 40 Blow down % 4-5 5-6 5-6 5-6 Operating % 75-77 77 to 77to 77 to efficiency 80 80 80 % Pollution (ESP, ESP ESP ESP ESP Fuel used coal coal coal Coal control cyclone) device used
  • 4. COAL HANDLING LAY OUT TRF/GB Make : Capacity, tons /hr 80/40 1.FEEDING SCREEN 2.VIBRATOR 3.COAL CRUSHER OR GRANULATOR (HAMMER TYPE) 4.CONVEYER BELTS 5.ROLLERS 6.COAL BUNKER Details of belt conveyor: Belt conveyer 1 [ 800 x 34, 263 long ] Belt conveyer 2 [ 600 x 14, 362 long ] Belt conveyer 3 [ 600 x 126,267 long] Belt conveyer 4 [ 600 x 21, 168 long ] Belt conveyer 5a & 5b [ 800 x 32, 500 long ] Vibrating feeder [ 915 wide x 1500 long ] Coal size ¾ inches ( 15 – 20 mm ) Grade of coal B Calorific value of coal 4500- 5000 kcal/kg
  • 5. 1 Type: V1000 TRF COAL HANDLING LAY OUT m coal Coal charge crusher 2 Type: 7 sfm 800x800x450 3 5A 4 me 1- gear ratio : 30:1 5B 2- : 30:1 ELECON 3- :20 :1 4- :20:1 crusher crusher 5a : :30:1 5b : :30:1 OPP
  • 6. FLUE GAS PATH HP BOILER SECONDARY AIR BOILER 1 ST CYCLON 2 ND CYCLON 3RD CYCLON TO GRATE HOT AIR OUT AIR PRE ESP ECONOMISER HEATER FD AIR SCREW CONVEYERS TO SUBMURGED ASH BELT
  • 7. FLUE GAS PATH MP BOILER econ GRN ESP ID 90 KW ID 200 KW
  • 8. WORKING OF ESP The flue gas laden with fly ash is sent through pipes having negatively charged plates which give the particles a negative charge. The particles are then routed past positively charged plates, or grounded plates, which attract the now negatively-charged ash particles. The particles stick to the positive plates until they are collected. The air that leaves the plates is then clean from harmful pollutants. Just as the spoon picked the salt and pepper up from the surface they were on, the electrostatic precipitator extracts the pollutants out of the air.
  • 9. ASH HANDLING LAY OUT ASH HANDLING PLANT Impact rollers MAIN EQUIPMENTS: plain rollers 1.ASH BELT CONVEYER Scrapper 2.SUBMERGE BELTS Skirting 3.SCREW CONVEYERS (SMALL AND LONG) 4.ASH HOPPERS 5.RIDDLING HOPPERS 6. ROLLERS To main ash Hooper SB1 SB3 SB3 ABC 3 ABC 1 Plain return ABC 3 BYPASS Carrying idler Impact Carrying idler Return Trough
  • 10. ASH HANDLING LAY OUT BL 7 ESP HB SB RAH FAH ECO APH ESP ESP APH
  • 11. ASH HANDLING PRE CAUTIONS If inclined belt trips, Horizontal and submerged belt will automatically stops OPP Submerged belt bypass : Trolley is used to transfer ash when it is bypassed .Inclined belt : Bypass ABC 3 with in 3-5 minutes Horizontal belt : ESP Hooper bypass  NPP Submerged belt has two bypass. ABC 3 bypass PCS Pull cord switch ZSS BSS  ( Belt 1,Belt 2, Belt 3 (ABC 3by pass) ,horizontal belt, Inclined belt, submerged belts (3 in NPP and 1 in OPP). Only horizontal belt in OPP is having chain drive.
  • 12. PDM DEAERATOR OT Suction TO HP BOILERS TO ABL BOILERS DARE. ABL Suction ABL EFP1 85 KG ABL FP EFP2 STEAM STEAM FP FP ABL deae. pump LAY OUT FEED WATER (HP) SYSTEM
  • 13. FEED PUMP SPECIFICATIONS ABL 85 KG ELECT ELECT ABL FP STEAM SFP FP 1 FP 2 FP MAKE KSB MATH & MATH & MATH & KSB NEW POWER PLANT PLATT PLATT PLATT TYPE HAD 4/6 BFO 4/6 BFO 4/6 BFO HAD 50/15 50/15 9 CHR 9 CHR 9 CHR FLOW 25.3 145 145 145 25.3 HEAD 747MLC 1068 M 1068 M 1068 M 747 MLC RPM 2960 2980 2980 2980 2950 KW/HP ------- ------- 700/938 700/938 100/134
  • 14. Cond. From plant Over head Prv outlet tank Prv outlet Prv outlet Deaerator Vent Vent Cond tank ST 3 KG Exh M ST Exh suction MAIN DIRECT 46 KG BL 7 FEED PUMP LINES
  • 15. BL 7 FEED PUMP AREA PRE CAUTIONS Condensate pump running indication by bulbs. ABL feed pumps running indication by bulbs. Inside feed pump attendants room electric feed pump running indication bulb OT Level 10.5 feet indication bulb OCT and NCT Level gauges (OCT-0-50-100 %=0-0.25-0.50 LEVEL), (NCT-0-50-100 % = 0-0.20-0.4 LEVEL) Inform DM plant if OCT level falls below 20 %) OT level graphical indication also Alarm will ring when any of the above condition is not satisfied. Electric feed pump Amps above 370 Amps (OL on 380), Immediately steam feed pump to be taken in service. Or if demand is more, inform NPP to start supply from their end for ABL boiler in case BL 7 is running. If any pump stops or trips immediately standby pump to be started.
  • 16. BL 7 FEED PUMP AREA PRE CAUTIONS Deaerator bypass system always in line Balancing pressure should be within operating range to maintain the thrust clearance There are 2 supplies for ABL/Condensate / Deaerator pump viz. BTH / TG Incase 2nd extraction pressure is more in BTH , Steam pump extraction line valve required to be operate if instructed from BTH Gland cooling line is to be continuously observed, There are two valves which are of 55 & 150 hp , and if this is not available third one which comes from emergency tank , valve to be opened When JMW & BL 7 are in operation, ABL boiler feed water supply to be stopped and ABL condensate pump to be started. (Valve near ABL boiler stairs entry). If only JMW boiler is running feed water supply is from BL 7 feed pump. JMW boiler feed water heater out temperature 130 deg. Cel. Maximum and steam outlet temperature 405 deg. Cel. Maximum (Runs max 450 deg. Cel. ) No steam / water valve should be opened till the written memo is received and physical check for drain, or isolation is confirmed
  • 17. BL 7 FEED PUMP LINES TI TO STEAM DRUM ECO OUT RTD ECO IN MAIN Direct
  • 18. JMW FEED WATER LINES To Boiler Drum Eco in 3 kg steam Direct Feed water heater Main Condensate to NCT
  • 19. Sr no Parameter OV Alarm Trip FEED PUMP FEED PUMP OPERATING PARAMETERS Make: M&P 1 Condensate pump load 30-32 A 2 Deaerator water temperature 105 Type: V.G PLUROVANE 3 Deaerator pump load 15-17 A Head : 1980 ft. (600 m) 4 Deaerator discharge pressure 2-2.5 Size : 6” x 4” 5 Electric feed pump load 350 370 380 Discharge : 349 GPM 6 Suction pressure 1.5-2 92 M3/HR 7 Discharge pressure 58-60 Motor : 322 HP 430 KW 8 Balancing pressure 3 6 RPM : 9 Oil level SP 1 : 3850 10 Overhead tank level ABOVE 10.5 SP 2 : 3740 10.5 FT EFP : 2960 11 OCT LEVEL Above 30 % 30 % Below 20% 12 NCT Level Above 50 % 50 % Below 40 %
  • 20. CONDENSATE TANKS AND PDM  TG condensate goes to PDM tank and from PDM tank to HP deaerator BTH turbine,PM4, SPL machine condensate to NCT, then it is pumped to DM plant for polishing, back to PDM tank Remaining condensate from clo2,PM1,PM2,Pulp mill, S/R plant, chemical house comes in OCT From OCT it is pumped to Overhead feed tank of Boiler no 7 and other pump for ABL overhead tank OCT & NCT are inter connected ,OCT being on height than NCT. Level is maintained by DM plant, still if OCT level drops to 25 – 20 % verbally to be inform to DM plant SE. Hydrazine + Ammonia –LP Dosing & Nalcol 2518 + Caustic – HP Dosing POLISHING: NCT Charcoal filter Iron filter DM tank PDM PUMP Total head:45 m PDM Tank Secondary mixed bed Flow : 416.7 lps BEFORE START UP OF BL 7, DM PLANT TO BE IMFORMED
  • 21. 85/46 STEAM HEADER Attempt. Line Range v/v BL2 Range v/v BL 3 85 kg st pump Range v/v BL1 TO TG pg 85/46 Condensate tank pump ( 1 and 3) and 2 46 KG HEADER 46 kg to TG Ejector Raw water pump 1 and 3 To ABL st pump Type: 4 U P3 (Double extraction) Size : 150 x 100 Capacity : 40 lps (144 m3 / hr) Head : 40 m HP : 50 RPM : 1450
  • 22. 46/3 STEAM HEADER BTH TURBINE ABL 46 JMW 46 OLD 46 Steam feed pump 46 KG/CM2 FROM 46/3 PRV 85/46 PRV Location: JMW 46/17/7 BTH When condensate flow to TG condenser is less ,46/3 PRV is required to be charged. Control of opening of this valve is in TG Control room. It is assumed that steam flow from this line is 5 Tons Per Hour.
  • 23. SOOTING JMW 46 HEADER 650/250/100 Blade coating Pulp mill 46/17/7 17 7 From 10/7 TG Chem house 7/3 PRV Not in use BTH 7
  • 24. PM1 , PM2 LINES Supplim. For PM1 From BTH 7 / 3 PRV PM 1 Supplim PM 2 Supplim 3 kg PM1 PM2
  • 25. OPP office 10KG STEAM HEADER rail clo2 SM PULP MILL ABL PRV 10/7 10 KG TG LIME KLIN From 46/17/7 prv Dorr plant JMW APH 7 KG BTH
  • 26. PMC4 3 KG NETWORK 85 KG SFP ABL PULP MILL DEAERATOR PM 4 DORR JMW FW HEATER CH DEAERATOR FP EXH LINE BTH 7 KG SM 10 KG CLO2 SR EVAP CLO2 SPL M/C
  • 27. MP STEAM VALVE LOCATIONS Sr. Customer Pr. Location No Kg/cm2 . 1 PM 5 10 Back side of CT 2 STARCH MILL 10 Railway gate 3 ABL 10 Railway gate 4 PULP MILL 10 Behind TG room platform 5 CLO2 10 Behind OPP Office 6 PULP MILL 7 Wooden bridge Boiler & BTH 7 CHEMICAL HOUSE 7 BTH header chain valve 8 BLADE COATING 17 Wooden bridge Boiler & BTH 9 FEED PUMP 46 ASH plant
  • 28. LP STEAM VALVE LOCATIONS Sr. Customer Pr. Location No. Kg/cm2 1 CHEMICAL HOUSE 3 Above MW section TR 18 (Toilet) 2 PM 1 3 Platform in front of PM 1 3 PM2 3 Platform in front of PM 2 4 PM1 SUPPLM.VALVE 3 BTH house 5 PM2 SUPPLM.VALVE 3 In front of BTH between 2 tanks 6 S/R EVAPORATOR 3 Near 46/3 PRV STAIRS 7 PM 5 / 6 / 7 3 Above BL 7 Control room 8 PM4 3 Near BL 1 FD fan area 9 DORR PLANT 3 Near JMW ESP Stairs 10 HP DEAERATOR 3 Hp deaerator 11 ABL DEAERATOR 3 ABL deaerator 12 BL 7 DEAERATOR 3 BL 7 feed pump area 13 PULP MILL 3 Rail gate + 46/10 PRV 14 MC NO 4 3 From BTH also 15 CLO2 3 Above BL 7 Control room
  • 29. BOILER NO 7 FRONT AND REAR TUBES GOES TO STEAM DRUM RIGHT & LEFT END TUBES FORM HEADER ,THEN GOES TO STEAM DRUM RIGHT COAL FEEDER SIDE FRONT REAR LEFT
  • 30. BL NO 7 WATER WALLS REAR END LEFT END RIGHT END FRONT END
  • 31. BOILER NO 7,8 MOUNTINGS AND FITTINGS Drum safety valves SH stop valve SH safety valve Drum gauge glass Range valve Blow down valve (04 + 02) RGG Economizer safety valve Steam flow meter Water flow meter Hi and LO Whistle DOSING
  • 32. COOLING TOWERS MAKE : PAHARPUR COOLING TOWERS (Induced draft ) BTH TG Total fans :9 nos Fans : 02 nos Current : 36 amps Current : Fan 1 VFD 45 amps Circulation rate: 2900 m3/hr Fan 2 65 amps Evaporation lass : 16 m3/hr Circulation rate : 3200 m3/hr Evaporation loss: 32 m3/hr . TUBE WELL SUPPLY: 3,4,8,16,20,22. 10,12,14,15,17 18,19 1,21 CHEMICALS USED: H2SO4 - PH CONTROL 7002 2718: 7500 7000: CHLORINE
  • 33. 150 HP PUMP HOUSE NOT IN USE Pump 1 current: 25 A OLD PH PULP MILL VFD 40 HZ PM 4 & OLD PH 5 4 3 2 1 TANK LEVEL 12 FEET SCALE READING -------FEET EMPTY TO HYDRANT TUBE WELL LINES: 3,4,8,16,20,22. 10,12,14,15,17 18,19 1,21
  • 34. 150 HP PUMP HOUSE ELECTRICAL SUPPLY  PUMP NO 1 IS HAVING VFD. PUMP NO 2 IS HAVING COS FROM DB2 (BTH AND TG). PUMP NO 3 IS HAVING BTH SUPPLY PUMP NO 4 AND 5 HAS COS FROM DB2. FROM 150 HP PUMP HOUSE COS DB2 AND COS DB1 SUPPLY IS GIVEN. PUMP NO 1 RUNS NORMALLY IN 150 HP PUMP HOUSE PUMP NO 4 – HYDRANT
  • 35. 55 HP PUMP HOUSE NOT IN USE MC 1,4 NOT IN USE COATING PLANT NOT IN USE Pump 5 current: 82-84 A 1 2 4 5 TANK LEVEL 5 FEET SCALE READING -------FEET FULL MC 1,4 / DM/ DORR/ SR/ PH/ CH/ NPP TUBE WELL LINES: 3,4,8,16,20,22. 10,12,14,15,17 18,19 1,21
  • 36. FROM SPL PUMP 55 HP PUMP HOUSE DM PLANT TUBE WELL NO 6 / 9 CONNECTION 55 PMC 1 , 2 EMERGENCY FROM SPLITY PUMP HOUSE GLAND FILLING TANK BTH SUMP BFW PUMPS GLAND DORR / SR/NPP BFW PUMPS GLAND BTH OIL / AIR COOLER SR/NPP BTH DRINKING/WASHING CH
  • 37. 55 HP PUMP HOUSE ELECTRICAL SUPPLY  PUMP NO 5 IS HAVING VFD. SUPPLY FROM PANEL NO 2 DB1 SUPPLY TO TUBE WELL NO 1 AND 2 ,AND TO SERVICE PUMP NO 4. COS IS FOR ABOVE. (Main supply from 150 HP pump house) SUPPLY FOR PUMP NO 1 FROM PANEL NO 1. COS FOR DB2 IS FOR SERVICE PUMP NO 1 , 2 , AND 5. PUMP NO 5 RUNS NORMALLY.
  • 38. FIRE PUMP DETAILS At four location Fire pump stations are available  Main fire pump house at S/R area (4 Pumps) At ETP (2 Pumps, One electric driven and other Diesel 12 cyl driven ) At Yard sump Electric pump At 150 HP pump house , pump no 4. From main fire pump house, pump no 4 runs normally Yard fire pump some times used when sump level to be make up All three supply available
  • 39. FIRE PUMP DETAILS Fire hydrant circuit 1 (cooling pond) Pump 2 Pump 1 (Pump no 3) Make Mather and greeves Make : Mather and Platt Type: 8/8 MHL Type : 7.2 ST MEDI Capacity: 1500 gpm Capacity: 1000 gpm Head : 290 ft Head : 290 ft HP : 200 RPM: 1450 HP : 190 RPM : 1450 Pump 2B (ETP) Diesel engine driven pump : Make : Kirloskar 8/8 MHL Mather and platt Type: SVA 8 Capacity : 1500 gpm Size: 8 x 8 Head : 290 ft Capacity : 1400 gpm RPM : 1450 Head : 225 ft Diesel engine make: MWM HP : 200 RPM : 1450 Type: TD – 237 – VIZ Fire hydrant circuit 3 ( Chipper yard) BHP : 200 Pump no 3: RPM : 1500 Make : Mather and Platt Capacity : 1500 gpm Head : 290 ft HP : 200 RPM : 1440 Reservoir capacity : 2 lacs gallon
  • 40. FIRE PUMP HOUSE Sometimes pump no 2 is started for CH increased consumption 1 2 4 3 66 A / 2.5 K/c2
  • 41. SPECIALITY PUMP HOUSE DETAILS 250 M3/HR 4 K/C2 TW NO 9 / 6 85 A COATING PLANT NEW POWER HOUSE AIR COMPRESSOR M3/HR 55/ 150 LINE 2-2.5 K/C2 65-70 A PULP MILL SHUT 1 RUNNING 1 RUNNING TUBE WELL LINES: 3,4,8,16,20,22. 10,12,14,15,17 18,19 1,21
  • 42. AIR COMPRESSORS  Air compressors in power house are situated as follows Motor load: 230-250 A 1) 2 nos at old power plant 2) 2 nos at new power plant 3) 4 nos at specialty machine area cooler 2.5 kg/cm2 Air comp no 2,6,4,5 PROCESS cooler Coating plant 5 kg/cm2 AD AD cooler 5 kg/cm2 Pulp mill , spl machines , RECIEVER Clo2 plant, power house TANK cooler
  • 43. AIR COMPRESSORS NPP : KG KHOSLA MAKE SPL : KG KHOSLA MAKE Double stage Double stage 3H Y2TCER Air comp no 4,5,6 RPM : 650 RPM : 800 Pr. : 7 kg/cm2 Pr. : 7 kg/cm2 Cap : 5.89 m3/min Cap : 51.41 m3/min Pr 1 st stage : 2 kg/cm2 Pr 1 st stage : 2 kg/cm2 pr 2 nd stage : 5.5 kg/cm2 pr 2 nd stage : 5.5 kg/cm2 oil pr. : 2.5 kg/cm2 oil pr. : 2.5 kg/cm2 SPL : KG KHOSLA MAKE Single stage Air comp no 2 RPM : 560 Pr. : 7 kg/cm2 Cap : 11.01 m3/min oil pr. : 2.5 kg/cm2
  • 44. AIR COMPRESSORS PRE CAUTIONS  Air is distributed from new power plant air compressors to POWER HOUSE  Air compressors in Old Power House are standby. In case of air pressure drop or compressor trip, SPL pump house air compressor valve can be opened which is at NPP electrical panel room. Also one line from S/R plant air compressors is available for the same purpose but it is rarely used. Air compressors in Old Power Plant can be started in emergencies, can be put in Auto mode .One will be Auto and other will be stand by.
  • 45. TUBE WELL NETWORK INSIDE 1,2,6,7,9,10,12,14,15,17,21 OUT SIDE 3,4,8,16,20,22 TUBE WELL LOCATION SUPPLY CHANGE OVER NO 1 CHAIR REPAIR WORK SHOP 55 HP PUMP HOUSE 2 COATING PLANT (BEHIND 55 HP PUMP HOUSE) 55 HP PUMP HOUSE 3 TI CLUB NEAR TUBE WELL 8 4 RAMLEELA STAGE NEAR TUBE WELL 8 5 DOES NOT EXSISTS ------- 6 BEHIND DM PLANT SAME LOCATION 7 DISPENSARY NO 5 NEAR TUBE WELL 8 8 TR BUILDING NEAR TEMPLE NEAR TUBE WELL 8 9 GHEE PLANT FROM BOILER HOUSE DB 10 GATE NO 9 NEAR TUBE WELL 10 PUNJAB 18,19 11 DOES NOT EXSISTS ------- 12 ETP MACHINE NO 5 / 7 13 DOES NOT EXSISTS ------- 14 200 QTR NEW GATE SAME LOCATION 15 GATE NO 8 NEAR TUBE WELL 10 16 CHUNA BHATTI NEAR DR BUILDING 17 NANGAL POWER HOUSE 18 PUNJAB MILL NANGAL NO CCHANGE OVER 19 PUNJAB MILL NANGAL NO CHANGE OVER 20 TR BUILDING GROUND NEAR TUBE WELL 8 21 NEAR TRAFFIC DEPT. Location 22 DR BUILDING OLD NEAR DR BUILDING