SlideShare a Scribd company logo
1 of 23
Earned Value Management
(EVM)
Shenin Hassan
2015
Outline
• Introduction
• Basic Elements of EVM
• Performance Analysis
and Forecasting
• Guidance for the use of
Key EVM Practices
Introduction
• Feedback of the Project
is critical
– Identify problems
– Early decision making
• EVM is one of the most
effective “performance
measurements and
feedback tools”
EVM
• “Management with
Lights On”
– Illumine where a project
is and where it is going
compared to where it
was supposed to be
• Patterns and Trends in
the past can be good
predictors of the future
EVM
• Part of Monitoring and
Controlling
– Scope
– Schedule &
– Cost
• Includes
– Measuring
– Analysing
– Forecasting
– Reporting
EVM
Scope
Time
Cost
Quality
& Risk
What’s the Project Status? Are we on Schedule?
Late by 2 Weeks
Mmm…so?...what’s the new finish date?
Couple of Changes…not
only schedule…cost…
EVMS Answers to
When is the project likely to be completed?
Are we currently under or over our budget?
How efficiently are we using our resources?
Critical Data Elements of EVM
Planned Value - PV
Earned Value - EV
Actual Cost - AC
Planned Value
• Amount of resources (expressed in budget-
numbers) that are EXPECTED (PLANNED) to
accomplish a specific piece of work
– Budgeted Cost of Work Scheduled (BCWS)
– Spend Plan
– Cost Estimate Amount of resources ($) that are
expected to be consumed to
accomplish a specific piece of
work scope.
Example: Planned Value (PV)
Task Budget Jan Feb Mar Apr
1 12 6 6
2 20 8 12
3 28 7 21
PV 60 6 14 19 21
CUM 6 20 39 60
Total PV = 60
Total PV is called Budget at Completion (BAC)
Earned Value (EV)
• Amount of work accomplished at a given
point in time.
• Budgeted Cost of Work Performed (BCWP)
Snapshot of work
progress at a given point
in time
Example: Earned Value (EV) as of March
Task Budget Jan Feb Mar Apr
1 12 6 6
2 20 8 12
3 28 7 21
PV 60 6 14 19 21
CUM 6 20 39 60
EV 20 6 14 0
CUM 6 20 20
NO Work Performed (as per PLAN)
in March
For instance, in construction projects –
no physical work might happen as per
the plan, however money is spent on
certain equipments and tools (rented
crane, idle laborers for e.g.)
Actual Cost
• Amount of resources expended in a specific
time period to accomplish a task(s).
• Actual Cost of Work Performed (ACWP)
• Resource Expenditure against Planned Work
Amount of money spent
in a specific period of
time
Example: Actual Cost (AC) as of March
Task Budget Jan Feb Mar Apr
1 12 6 6
2 20 8 12
3 28 7 21
PV 60 6 14 19 21
CUM 6 20 39 60
EV 20 6 14 0
CUM 6 20 20
AC 25 6 14 5
6 20 25
Summary
Task Budget Jan Feb Mar Apr
1 12 6 6
2 20 8 12
3 28 7 21
PV 60 6 14 19 21
CUM 6 20 39 60
EV 20 6 14 0
CUM 6 20 20
AC 25 6 14 5
6 20 25
• PV(As of Mar) = 39
• EV (As of Mar) = 20
• AC (As of Mar) = 25
• Total PV = 60
• Total PV is called
Budget at Completion
(BAC)
Answering Project Management
Questions
Are we ahead or behind schedule? (VARIATION)
How efficiently are we using time? (PERFORMANCE INDEX)
When are we likely to finish work? (ESTIMATION/ FORECASTS)
Are we under or over our budget? (VARIATION)
What is the project likely to cost? (ESTIMATION/ FORECASTS)
What will the remaining work cost? (ESTIMATION/ FORECASTS)
How efficiently we must use our remaining resources ? (PERFORMANCE)
Analyzing Performance based on
VARIANCE
INDICES
(EFFICIENCY)
FORECASTS
Variance
Variance
During the Project –
at a point in time
At Completion
• Variance
– Schedule Variance
– Cost Variance
• Both “during the course” of
the project and at the “end”
of the project
Variance Types
Schedule Variance
Cost Variance
Variance at Completion
Variance
Are we ahead or behind schedule? – Schedule Variance (SV)
SV = EV – PV
Are we under or over budget? – Cost Variance ( CV)
CV = EV- AC
Will we be under or Over Budget (at the end)? –
Variance at Completion (VAC)
Project Management Question EVM Performance Measures Formula
Time-wise Schedule Analysis & Forecasting
Are we ahead or behind schedule? Schedule Variance SV= EV- PV
How efficiently are using time? Schedule Performance Index (SPI) SPI = EV/ PV
When are we likely to finish work? Time Estimate at Completion (EACt) EACt = BAC/ SPI
Cost-wise Cost Analysis & Forecasting
Are we under or over budget? Cost Variance (CV) CV = EV - AC
How efficiently are we using our
resources?
Cost Performance Index (CPI) CPI = EV/AC
How efficiently must we use our
remaining resources?
To-complete Performance Index (TCPI) TCPI = (BAC-EV)/ (BAC- AC)
What is the Project likely to cost? Estimate at Completion (EAC) EAC = BAC/CPI
Will we be under of over budget? Variance at Completion (VAC) VAC = BAC-EAC
What will the remaining work cost? Estimate to Complete (ETC) ETC = (BAC-EV)/ CPI
PMI Global Standard © 2005 PMI Page - 16
Elements Budget May June July August
Professional
Development
1500 300
(Buy 2
Books –
150 Each)
500
Enroll for
a short
course
worth 500
300
(Buy 2
Books– 150
Each)
400
(Buy 2
Books– 200
Each)
Home 12,000 3000 3000 3000 3000
Entertainment 1500 500 200 300 500
PV 15,000 (BAC) 3800 3700 3600 3900
CUM 3800 7500 11,100 15,000
EV 20 Bought 2
books
Enrolled
for a short
course
Short
course
continued
to July – so
did not
touch what
was
planned in

More Related Content

What's hot

Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value AnalysisSaqib Raza
 
Earned value analysis
Earned value analysisEarned value analysis
Earned value analysisNikhil Raj
 
project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 waleed hamdy
 
Chap 7.3 Determine budget
Chap 7.3   Determine budgetChap 7.3   Determine budget
Chap 7.3 Determine budgetAnand Bobade
 
Earned value
Earned valueEarned value
Earned valueOliver
 
Introduction to Earned Value Management
Introduction to Earned Value ManagementIntroduction to Earned Value Management
Introduction to Earned Value ManagementUnanet
 
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project schedulingSoe Naing Win
 
What is a Work Breakdown Structure?
What is a Work Breakdown Structure?What is a Work Breakdown Structure?
What is a Work Breakdown Structure?Kenny Hirschmann
 
PROJECT CONTROL PROCESS
PROJECT CONTROL PROCESS PROJECT CONTROL PROCESS
PROJECT CONTROL PROCESS Akash Prasanna
 
Project control & Monitoring
Project control & MonitoringProject control & Monitoring
Project control & MonitoringJawad Ahmad
 
Project Cost Management - PMBOK6
Project Cost Management - PMBOK6Project Cost Management - PMBOK6
Project Cost Management - PMBOK6Agus Suhanto
 
Work breakdown structure
Work breakdown structureWork breakdown structure
Work breakdown structureCOEPD HR
 
Work breakdown structure ppt
Work breakdown structure pptWork breakdown structure ppt
Work breakdown structure pptnazi2020
 
Project Monitoring and Control
Project Monitoring and ControlProject Monitoring and Control
Project Monitoring and Controlguy_davis
 

What's hot (20)

Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
Earned value analysis
Earned value analysisEarned value analysis
Earned value analysis
 
Project cost management
Project cost managementProject cost management
Project cost management
 
project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 project control using earned value analysis - Part 01
project control using earned value analysis - Part 01
 
Chap 7.3 Determine budget
Chap 7.3   Determine budgetChap 7.3   Determine budget
Chap 7.3 Determine budget
 
Earned value
Earned valueEarned value
Earned value
 
Introduction to Earned Value Management
Introduction to Earned Value ManagementIntroduction to Earned Value Management
Introduction to Earned Value Management
 
Project Monitoring and Control
Project Monitoring and ControlProject Monitoring and Control
Project Monitoring and Control
 
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project scheduling
 
What is a Work Breakdown Structure?
What is a Work Breakdown Structure?What is a Work Breakdown Structure?
What is a Work Breakdown Structure?
 
PROJECT CONTROL PROCESS
PROJECT CONTROL PROCESS PROJECT CONTROL PROCESS
PROJECT CONTROL PROCESS
 
Project Management
Project ManagementProject Management
Project Management
 
Project cost control
Project cost controlProject cost control
Project cost control
 
Work breakdown structure
Work breakdown structureWork breakdown structure
Work breakdown structure
 
Project control & Monitoring
Project control & MonitoringProject control & Monitoring
Project control & Monitoring
 
Project Cost Management - PMBOK6
Project Cost Management - PMBOK6Project Cost Management - PMBOK6
Project Cost Management - PMBOK6
 
Work breakdown structure
Work breakdown structureWork breakdown structure
Work breakdown structure
 
Work breakdown structure ppt
Work breakdown structure pptWork breakdown structure ppt
Work breakdown structure ppt
 
Project Monitoring and Control
Project Monitoring and ControlProject Monitoring and Control
Project Monitoring and Control
 

Viewers also liked

DonnaCluneResume
DonnaCluneResumeDonnaCluneResume
DonnaCluneResumeDonna Clune
 
Sales Development QBR Template
Sales Development QBR TemplateSales Development QBR Template
Sales Development QBR TemplateRalph Barsi
 
How to Develop a Quarterly Business Review
How to Develop a Quarterly Business ReviewHow to Develop a Quarterly Business Review
How to Develop a Quarterly Business ReviewGainsight
 
Quarterly Business Review Template - QBR Template - Customer Success Management
Quarterly Business Review Template - QBR Template - Customer Success ManagementQuarterly Business Review Template - QBR Template - Customer Success Management
Quarterly Business Review Template - QBR Template - Customer Success ManagementGainsight
 
QBR Presentation Template
QBR Presentation TemplateQBR Presentation Template
QBR Presentation TemplateSwayne Hill
 
Quarterly Business Review Template
Quarterly Business Review TemplateQuarterly Business Review Template
Quarterly Business Review TemplateOpsPanda
 
3 Things Every Sales Team Needs to Be Thinking About in 2017
3 Things Every Sales Team Needs to Be Thinking About in 20173 Things Every Sales Team Needs to Be Thinking About in 2017
3 Things Every Sales Team Needs to Be Thinking About in 2017Drift
 

Viewers also liked (10)

DonnaCluneResume
DonnaCluneResumeDonnaCluneResume
DonnaCluneResume
 
Arbetsmarknad stockholm
Arbetsmarknad stockholmArbetsmarknad stockholm
Arbetsmarknad stockholm
 
Sales Development QBR Template
Sales Development QBR TemplateSales Development QBR Template
Sales Development QBR Template
 
Sample QBR Slides
Sample QBR SlidesSample QBR Slides
Sample QBR Slides
 
How to Develop a Quarterly Business Review
How to Develop a Quarterly Business ReviewHow to Develop a Quarterly Business Review
How to Develop a Quarterly Business Review
 
Quarterly Business Review Template - QBR Template - Customer Success Management
Quarterly Business Review Template - QBR Template - Customer Success ManagementQuarterly Business Review Template - QBR Template - Customer Success Management
Quarterly Business Review Template - QBR Template - Customer Success Management
 
QBR Presentation Template
QBR Presentation TemplateQBR Presentation Template
QBR Presentation Template
 
Quarterly Business Review Template
Quarterly Business Review TemplateQuarterly Business Review Template
Quarterly Business Review Template
 
3 Things Every Sales Team Needs to Be Thinking About in 2017
3 Things Every Sales Team Needs to Be Thinking About in 20173 Things Every Sales Team Needs to Be Thinking About in 2017
3 Things Every Sales Team Needs to Be Thinking About in 2017
 
Build Features, Not Apps
Build Features, Not AppsBuild Features, Not Apps
Build Features, Not Apps
 

Similar to Earned value management for Beginners

Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisBECM, RUET, Bangladesh
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost ManagementSerdar Temiz
 
PM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdfPM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdfNajm Naqvi
 
07 projectcostmanagement
07 projectcostmanagement07 projectcostmanagement
07 projectcostmanagementDhamo daran
 
Projects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part OneProjects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part OneWaleed Hamdy Albana
 
Topic 10 - Project Performance Management.pdf
Topic 10 - Project Performance Management.pdfTopic 10 - Project Performance Management.pdf
Topic 10 - Project Performance Management.pdfHuyNguyen657394
 
Pppl evms training_02
Pppl evms training_02Pppl evms training_02
Pppl evms training_02apocalypto1
 
cost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.pptcost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.pptRedhaElhuni
 
EVMmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmm.pdf
EVMmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmm.pdfEVMmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmm.pdf
EVMmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmm.pdfRedhaElhuni
 
Symposium 2016 : CONF. 401 Jonathan Shriqui EVM: Go Beyond the Numbers
Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the NumbersSymposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers
Symposium 2016 : CONF. 401 Jonathan Shriqui EVM: Go Beyond the NumbersPMI-Montréal
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxsagarlesley
 
project monitoring_and_control in project mgt
project monitoring_and_control in project mgtproject monitoring_and_control in project mgt
project monitoring_and_control in project mgtdebmahuya
 

Similar to Earned value management for Beginners (20)

Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting Projects Performance Analysis & Forecasting
Projects Performance Analysis & Forecasting
 
IT Park - Earned Value ppt.ppt
IT Park - Earned Value ppt.pptIT Park - Earned Value ppt.ppt
IT Park - Earned Value ppt.ppt
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value Analysis
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
PM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdfPM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdf
 
07 projectcostmanagement
07 projectcostmanagement07 projectcostmanagement
07 projectcostmanagement
 
Projects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part OneProjects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part One
 
Topic 10 - Project Performance Management.pdf
Topic 10 - Project Performance Management.pdfTopic 10 - Project Performance Management.pdf
Topic 10 - Project Performance Management.pdf
 
Back to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinarBack to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinar
 
Pppl evms training_02
Pppl evms training_02Pppl evms training_02
Pppl evms training_02
 
cost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.pptcost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.ppt
 
Project monitoring lecture 1
Project monitoring lecture 1Project monitoring lecture 1
Project monitoring lecture 1
 
EVMmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmm.pdf
EVMmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmm.pdfEVMmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmm.pdf
EVMmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmm.pdf
 
Symposium 2016 : CONF. 401 Jonathan Shriqui EVM: Go Beyond the Numbers
Symposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the NumbersSymposium 2016 : CONF. 401  Jonathan Shriqui EVM: Go Beyond the Numbers
Symposium 2016 : CONF. 401 Jonathan Shriqui EVM: Go Beyond the Numbers
 
Delivering nothing efficiently
Delivering nothing efficientlyDelivering nothing efficiently
Delivering nothing efficiently
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docx
 
Earned value 01
Earned value 01Earned value 01
Earned value 01
 
project monitoring_and_control in project mgt
project monitoring_and_control in project mgtproject monitoring_and_control in project mgt
project monitoring_and_control in project mgt
 
Performing against the wall - SPI after completion
Performing against the wall - SPI after completionPerforming against the wall - SPI after completion
Performing against the wall - SPI after completion
 
PMP COST FORMULAE
PMP COST FORMULAEPMP COST FORMULAE
PMP COST FORMULAE
 

Recently uploaded

Event mailer assignment progress report .pdf
Event mailer assignment progress report .pdfEvent mailer assignment progress report .pdf
Event mailer assignment progress report .pdftbatkhuu1
 
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxB.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxpriyanshujha201
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...anilsa9823
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communicationskarancommunications
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒anilsa9823
 
Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Roland Driesen
 
VIP Call Girls Gandi Maisamma ( Hyderabad ) Phone 8250192130 | ₹5k To 25k Wit...
VIP Call Girls Gandi Maisamma ( Hyderabad ) Phone 8250192130 | ₹5k To 25k Wit...VIP Call Girls Gandi Maisamma ( Hyderabad ) Phone 8250192130 | ₹5k To 25k Wit...
VIP Call Girls Gandi Maisamma ( Hyderabad ) Phone 8250192130 | ₹5k To 25k Wit...Suhani Kapoor
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Neil Kimberley
 
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetCreating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetDenis Gagné
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear RegressionRavindra Nath Shukla
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...Aggregage
 
A305_A2_file_Batkhuu progress report.pdf
A305_A2_file_Batkhuu progress report.pdfA305_A2_file_Batkhuu progress report.pdf
A305_A2_file_Batkhuu progress report.pdftbatkhuu1
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfPaul Menig
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Serviceritikaroy0888
 
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...Any kyc Account
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Delhi Call girls
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageMatteo Carbone
 
Call Girls In Holiday Inn Express Gurugram➥99902@11544 ( Best price)100% Genu...
Call Girls In Holiday Inn Express Gurugram➥99902@11544 ( Best price)100% Genu...Call Girls In Holiday Inn Express Gurugram➥99902@11544 ( Best price)100% Genu...
Call Girls In Holiday Inn Express Gurugram➥99902@11544 ( Best price)100% Genu...lizamodels9
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesDipal Arora
 

Recently uploaded (20)

Event mailer assignment progress report .pdf
Event mailer assignment progress report .pdfEvent mailer assignment progress report .pdf
Event mailer assignment progress report .pdf
 
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxB.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communications
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
 
Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...
 
VIP Call Girls Gandi Maisamma ( Hyderabad ) Phone 8250192130 | ₹5k To 25k Wit...
VIP Call Girls Gandi Maisamma ( Hyderabad ) Phone 8250192130 | ₹5k To 25k Wit...VIP Call Girls Gandi Maisamma ( Hyderabad ) Phone 8250192130 | ₹5k To 25k Wit...
VIP Call Girls Gandi Maisamma ( Hyderabad ) Phone 8250192130 | ₹5k To 25k Wit...
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetCreating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
 
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabiunwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear Regression
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
 
A305_A2_file_Batkhuu progress report.pdf
A305_A2_file_Batkhuu progress report.pdfA305_A2_file_Batkhuu progress report.pdf
A305_A2_file_Batkhuu progress report.pdf
 
Grateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdfGrateful 7 speech thanking everyone that has helped.pdf
Grateful 7 speech thanking everyone that has helped.pdf
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Service
 
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
KYC-Verified Accounts: Helping Companies Handle Challenging Regulatory Enviro...
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
 
Call Girls In Holiday Inn Express Gurugram➥99902@11544 ( Best price)100% Genu...
Call Girls In Holiday Inn Express Gurugram➥99902@11544 ( Best price)100% Genu...Call Girls In Holiday Inn Express Gurugram➥99902@11544 ( Best price)100% Genu...
Call Girls In Holiday Inn Express Gurugram➥99902@11544 ( Best price)100% Genu...
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
 

Earned value management for Beginners

  • 2. Outline • Introduction • Basic Elements of EVM • Performance Analysis and Forecasting • Guidance for the use of Key EVM Practices
  • 3. Introduction • Feedback of the Project is critical – Identify problems – Early decision making • EVM is one of the most effective “performance measurements and feedback tools”
  • 4. EVM • “Management with Lights On” – Illumine where a project is and where it is going compared to where it was supposed to be • Patterns and Trends in the past can be good predictors of the future
  • 5. EVM • Part of Monitoring and Controlling – Scope – Schedule & – Cost • Includes – Measuring – Analysing – Forecasting – Reporting EVM Scope Time Cost Quality & Risk
  • 6. What’s the Project Status? Are we on Schedule? Late by 2 Weeks Mmm…so?...what’s the new finish date? Couple of Changes…not only schedule…cost…
  • 7. EVMS Answers to When is the project likely to be completed? Are we currently under or over our budget? How efficiently are we using our resources?
  • 8. Critical Data Elements of EVM Planned Value - PV Earned Value - EV Actual Cost - AC
  • 9. Planned Value • Amount of resources (expressed in budget- numbers) that are EXPECTED (PLANNED) to accomplish a specific piece of work – Budgeted Cost of Work Scheduled (BCWS) – Spend Plan – Cost Estimate Amount of resources ($) that are expected to be consumed to accomplish a specific piece of work scope.
  • 10. Example: Planned Value (PV) Task Budget Jan Feb Mar Apr 1 12 6 6 2 20 8 12 3 28 7 21 PV 60 6 14 19 21 CUM 6 20 39 60 Total PV = 60 Total PV is called Budget at Completion (BAC)
  • 11. Earned Value (EV) • Amount of work accomplished at a given point in time. • Budgeted Cost of Work Performed (BCWP) Snapshot of work progress at a given point in time
  • 12. Example: Earned Value (EV) as of March Task Budget Jan Feb Mar Apr 1 12 6 6 2 20 8 12 3 28 7 21 PV 60 6 14 19 21 CUM 6 20 39 60 EV 20 6 14 0 CUM 6 20 20 NO Work Performed (as per PLAN) in March For instance, in construction projects – no physical work might happen as per the plan, however money is spent on certain equipments and tools (rented crane, idle laborers for e.g.)
  • 13. Actual Cost • Amount of resources expended in a specific time period to accomplish a task(s). • Actual Cost of Work Performed (ACWP) • Resource Expenditure against Planned Work Amount of money spent in a specific period of time
  • 14. Example: Actual Cost (AC) as of March Task Budget Jan Feb Mar Apr 1 12 6 6 2 20 8 12 3 28 7 21 PV 60 6 14 19 21 CUM 6 20 39 60 EV 20 6 14 0 CUM 6 20 20 AC 25 6 14 5 6 20 25
  • 15. Summary Task Budget Jan Feb Mar Apr 1 12 6 6 2 20 8 12 3 28 7 21 PV 60 6 14 19 21 CUM 6 20 39 60 EV 20 6 14 0 CUM 6 20 20 AC 25 6 14 5 6 20 25 • PV(As of Mar) = 39 • EV (As of Mar) = 20 • AC (As of Mar) = 25 • Total PV = 60 • Total PV is called Budget at Completion (BAC)
  • 16. Answering Project Management Questions Are we ahead or behind schedule? (VARIATION) How efficiently are we using time? (PERFORMANCE INDEX) When are we likely to finish work? (ESTIMATION/ FORECASTS) Are we under or over our budget? (VARIATION) What is the project likely to cost? (ESTIMATION/ FORECASTS) What will the remaining work cost? (ESTIMATION/ FORECASTS) How efficiently we must use our remaining resources ? (PERFORMANCE)
  • 17. Analyzing Performance based on VARIANCE INDICES (EFFICIENCY) FORECASTS
  • 18. Variance Variance During the Project – at a point in time At Completion • Variance – Schedule Variance – Cost Variance • Both “during the course” of the project and at the “end” of the project
  • 19. Variance Types Schedule Variance Cost Variance Variance at Completion
  • 20. Variance Are we ahead or behind schedule? – Schedule Variance (SV) SV = EV – PV Are we under or over budget? – Cost Variance ( CV) CV = EV- AC Will we be under or Over Budget (at the end)? – Variance at Completion (VAC)
  • 21. Project Management Question EVM Performance Measures Formula Time-wise Schedule Analysis & Forecasting Are we ahead or behind schedule? Schedule Variance SV= EV- PV How efficiently are using time? Schedule Performance Index (SPI) SPI = EV/ PV When are we likely to finish work? Time Estimate at Completion (EACt) EACt = BAC/ SPI Cost-wise Cost Analysis & Forecasting Are we under or over budget? Cost Variance (CV) CV = EV - AC How efficiently are we using our resources? Cost Performance Index (CPI) CPI = EV/AC How efficiently must we use our remaining resources? To-complete Performance Index (TCPI) TCPI = (BAC-EV)/ (BAC- AC) What is the Project likely to cost? Estimate at Completion (EAC) EAC = BAC/CPI Will we be under of over budget? Variance at Completion (VAC) VAC = BAC-EAC What will the remaining work cost? Estimate to Complete (ETC) ETC = (BAC-EV)/ CPI
  • 22. PMI Global Standard © 2005 PMI Page - 16
  • 23. Elements Budget May June July August Professional Development 1500 300 (Buy 2 Books – 150 Each) 500 Enroll for a short course worth 500 300 (Buy 2 Books– 150 Each) 400 (Buy 2 Books– 200 Each) Home 12,000 3000 3000 3000 3000 Entertainment 1500 500 200 300 500 PV 15,000 (BAC) 3800 3700 3600 3900 CUM 3800 7500 11,100 15,000 EV 20 Bought 2 books Enrolled for a short course Short course continued to July – so did not touch what was planned in

Editor's Notes

  1. Budgeted Cost of Work Scheduled (BCWS)