SlideShare une entreprise Scribd logo
1  sur  15
Hoover dam bypass bridge
Table of contents
❖ introduction
❖ Pre-feasibility
❖ Project conception
❖ Project need & objective
❖ Project preparation
❖ Environmental impact assessment
❖ Technical assessment
❖ Financial information
❖ Construction
❖ Operation & maintenance
❖ Transfer of the project
Introduction
❖ Hoover dam bypass is a part of 4 miles long
highway connecting Arizona and Nevada
interstates.
❖ The new 1900 ft. (571 m) Hoover dam bypass
bridge spans the black canyon at about 1500 ft.
(457.2m) south of the Hoover Dam, connecting
the Arizona and Nevada approach highways
nearly 900 ft.
❖ The bridge carries four lanes of traffic and
sidewalk.
❖ It is a composite steel concrete deck arch bridge
with main span of 1060 ft. (323m). The arch rib is
made of reinforce concrete.
❖ It is the second largest concrete arch bridge span
in the world. The bride is owned by Arizona DOT
and Nevada DOT.
Pre-feasibility stage
❖ Project conception
❖ “Colorado river bridge project management team” came into place by joint decision of
Navida and Arizona state department of transportation.
Project Need and objective
Potential problems identified
❖ Accidents
❖ Sharp turns
❖ Limited sight distances
❖ No adequate room for
disabled cars
❖ Speed was as low as 15MPH
against initial speed of 50MPH
❖ inadequate road capacity
❖ Less travel times
Objective of the project
• To minimise the potential for traffic accidents
• To remove the bottlenecks to interstate and international commerce to reduce traffic
congested
• To reduce travel time
• To protect Hoover dam employees, visitors, equipment, power generations capabilities
• To provide safe and improved conditions for the maintenance and operation of Hoover
dam
Project Preparation activities
After initial surveys at this point it was decided to carryout two important studies in detail
❖ Engineering & technical aspect
❖ Environmental impact assessment
Environmental impact assessment
studies
• Air quality analysis
• Noise analysis
• Visual resources analysis
• Biological assessments
• Archaeological resources survey
Project Design
The requirement for the design of the bridge was both
technical and aesthetics of the bridge, the most important
requirement in the design would be design load which in
this case was 180 metric tons. Various designs were
studied some of them were as follows.
After considering the design criteria for the bridge the
team selected composite steel and concrete type of
bridge that met all the design criteria.
Financial information
Contract contractor value
Arizona Approach
Mont/VASTCO $22M
Navida Approach
Edward Kraemer & sons $30M
River bridge
Obayashi/Mitsubishi $114M
Paving
Freshener & Las Vegas paving $15M
Total $181M
Construction
❖ Phase 1. Building connection between
Colorado Bridge and U.S 93 this included 4
lanes of roadway
❖ Phase2. This was from Navida side, The
Roadway from the project start to the
Colorado Bridge, started in 2003 and finished
in 2005 ahead of time by 2 months.
❖ Phase3. The contractor constructed 2.11 miles of new four-lane highway
alignment including six new bridges, a new traffic interchange at US 93 near the
Hacienda Casino, retaining walls, wildlife crossing.
❖ Phase4. Asphalt paving of the entire 4 miles from Arizona to Nevada side to the
project. This was complete in 2010.
Operation & maintenance
The operation and maintenance is either side of
the bypass bridge done by Arizona state DOT
and Nevada State DOT. The aim of the
maintenance is to insure safety, carryout visual
and technical inspection of the bridge, to
maintain smooth traffic flow, repairs to the
bridges, road pavements. The funding for the
same comes from the Nevada and Arizona
state departments of transportations.
Achievement
❖ The project completion on budget was a great success story although it went slightly
away from the schedule. The project primary purpose and objective of reduction in
traffic congestion was achieved and this facilitated smooth traffic.
❖ The travel time of the existing road was 16.5minutes while this newly construction
facility reduced it to 6 minutes, a total of 10 minutes were saved. This also increased
speed. The environmental impact assessment helped reduce and mitigate the problems
of environment and also wild life crossing between different points.
Project Schedule
Project Transfer
The twin-rib arch of the Colorado River
Bridge was completed in August 2009 and
the bridge columns were constructed in
November 2009. Construction of the entire
bypass was completed in September 2010. It
was celebrated by making grand ceremony.
The bypass opened to traffic a month later in
October 2010.
Learning
This project helped me a lot in understanding the complexity of the infrastructural project
development, in this exercise I learned various surveys required in each stage of the project,
the project coordination, construction and impact analysis on the environment. Every project
before comes into existence must go through a logical process, I learned practically what
process were involved in this project.
Conclusion
The Hoover Dam, Bypass Colorado River Bridge was an extreme challenge, due to the
structure itself, advanced construction schemes, and the surrounding environment. The
effort of all personnel involved made the incredible graceful bridge into reality. The Hoover
dam bypass Colorado River Bridge was completed in 2010, The Bridge was opened to
traffic on October 2010. The Project resulted iconic landmark structure set in the Colorado
River’s black canyon with a view to historic Hoover Dam. Ten minutes reduction time was
another achievement followed by reduction in traffic congestion and accidents.
References
1. http://energy.gov/sites/prod/files/nepapub/nepa_documents/RedDont/EA-1478-FEA-2003.pdf
2. http://www.roadtraffic-technology.com/projects/hoover-bypass/
3. https://books.google.co.in/books?id=jJ3MBQAAQBAJ&pg=PA1282&dq=hoover+dam+bridge&hl=en&sa=X&ved=0CCIQ6AEwAmoVChMI4
4. http://www.roadtraffic-technology.com/projects/hoover-bypass/hoover-bypass6.html
5. http://www.jpci.or.jp/NR/pdf/40.pdf
6. http://design.transportation.org/Documents/SCOD,Hammontree,FHWA,HooverDamBypass.pdf
7. http://www.klbconstruction.com/pdf/making_history_near_hoover_dam.pdf
8. http://www.crma.ac.th/histdept/journal/jour-49/49-jour-12.pdf
9. http://transportation.ky.gov/SASHTO/The%20Mike%20OCallaghan%20Pat%20Tillman%20Memorial%20Bridge.pdf
10. http://mcedc.colorado.edu/sites/default/files/FinalHooverDamBypass.pdf
11. http://www.hpcbridgeviews.com/i63/Printable.pdf
12. http://www.atkinsglobal.com/en-gb/projects/hoover-dam-bypass
13. http://nepis.epa.gov/Exe/ZyNET.exe/20005FMQ.TXT?ZyActionD=ZyDocument&Client=EPA&Index=2000+Thru+2005&Docs=&Query=&T

Contenu connexe

Tendances (20)

Burj khalifa
Burj khalifaBurj khalifa
Burj khalifa
 
Burj khalifa
Burj khalifaBurj khalifa
Burj khalifa
 
3. palm jumeirah final
3. palm jumeirah final3. palm jumeirah final
3. palm jumeirah final
 
Burj Khalifa Tower Project
Burj Khalifa Tower ProjectBurj Khalifa Tower Project
Burj Khalifa Tower Project
 
Burj khalifa
Burj khalifaBurj khalifa
Burj khalifa
 
Presentation on burj khalifa
Presentation on burj khalifaPresentation on burj khalifa
Presentation on burj khalifa
 
burjjjj new
burjjjj newburjjjj new
burjjjj new
 
Burj khalifa
Burj khalifaBurj khalifa
Burj khalifa
 
Burj Al Arab
Burj Al ArabBurj Al Arab
Burj Al Arab
 
Burj Al Arab, Tower Of The Arabs
Burj Al Arab, Tower Of The ArabsBurj Al Arab, Tower Of The Arabs
Burj Al Arab, Tower Of The Arabs
 
Palm island Construction with Management 5 Ms
Palm island Construction with Management 5 MsPalm island Construction with Management 5 Ms
Palm island Construction with Management 5 Ms
 
Palm jumeirah
Palm jumeirah Palm jumeirah
Palm jumeirah
 
Burj al arab-uae
Burj al arab-uaeBurj al arab-uae
Burj al arab-uae
 
Burj khalifa
Burj khalifaBurj khalifa
Burj khalifa
 
Burj kalifa
Burj kalifaBurj kalifa
Burj kalifa
 
high rise building
high rise buildinghigh rise building
high rise building
 
Burj al Arab Constuction
Burj al Arab ConstuctionBurj al Arab Constuction
Burj al Arab Constuction
 
Burj khalifa
Burj  khalifaBurj  khalifa
Burj khalifa
 
Burj al arab
Burj al arabBurj al arab
Burj al arab
 
Burj Khalifa
Burj KhalifaBurj Khalifa
Burj Khalifa
 

En vedette

Hoover dam bypass_bridge2
Hoover dam bypass_bridge2Hoover dam bypass_bridge2
Hoover dam bypass_bridge2George Martin
 
Note for Hoover Dam
Note for Hoover DamNote for Hoover Dam
Note for Hoover DamLengkengs
 
The hoover dam 3
The hoover dam 3The hoover dam 3
The hoover dam 3l yingling
 
What can we learn from the hoover dam
What can we learn from the hoover damWhat can we learn from the hoover dam
What can we learn from the hoover damJasmine Tung
 
Hoover dam and the negative effects on environment
Hoover dam and the negative effects on environmentHoover dam and the negative effects on environment
Hoover dam and the negative effects on environmentLengkengs
 
The hoover dam elena's homework
The hoover dam elena's homeworkThe hoover dam elena's homework
The hoover dam elena's homeworkmrzislion
 
Herbert Hoover Presidential Library-Museum
Herbert Hoover Presidential Library-MuseumHerbert Hoover Presidential Library-Museum
Herbert Hoover Presidential Library-MuseumAidan Brady
 
Student Presentation: The Hoover Dam by Sid and Vic
Student Presentation: The Hoover Dam by Sid and VicStudent Presentation: The Hoover Dam by Sid and Vic
Student Presentation: The Hoover Dam by Sid and Vicmrs_murphy_ncssm
 
Grace Cathedral - San Francisco California
Grace Cathedral  - San Francisco CaliforniaGrace Cathedral  - San Francisco California
Grace Cathedral - San Francisco CaliforniaSteven Cantler
 
Hoover Dam - Arizona & Nevada
Hoover Dam - Arizona & NevadaHoover Dam - Arizona & Nevada
Hoover Dam - Arizona & NevadaSteven Cantler
 
Student Presentation: The Hoover Dam by Sid and Vic
Student Presentation: The Hoover Dam by Sid and VicStudent Presentation: The Hoover Dam by Sid and Vic
Student Presentation: The Hoover Dam by Sid and Vicmrs_murphy_ncssm
 
4M Presentation - E-learning platform
4M Presentation - E-learning platform4M Presentation - E-learning platform
4M Presentation - E-learning platformProxicon Ltd
 

En vedette (20)

Hoover dam bypass_bridge2
Hoover dam bypass_bridge2Hoover dam bypass_bridge2
Hoover dam bypass_bridge2
 
Note for Hoover Dam
Note for Hoover DamNote for Hoover Dam
Note for Hoover Dam
 
The hoover dam 3
The hoover dam 3The hoover dam 3
The hoover dam 3
 
What can we learn from the hoover dam
What can we learn from the hoover damWhat can we learn from the hoover dam
What can we learn from the hoover dam
 
Hoover dam
Hoover damHoover dam
Hoover dam
 
Hoover dam and the negative effects on environment
Hoover dam and the negative effects on environmentHoover dam and the negative effects on environment
Hoover dam and the negative effects on environment
 
Hoover
HooverHoover
Hoover
 
Hoover Dam by John Howard
Hoover Dam by John HowardHoover Dam by John Howard
Hoover Dam by John Howard
 
Women
WomenWomen
Women
 
The hoover dam elena's homework
The hoover dam elena's homeworkThe hoover dam elena's homework
The hoover dam elena's homework
 
Herbert Hoover Presidential Library-Museum
Herbert Hoover Presidential Library-MuseumHerbert Hoover Presidential Library-Museum
Herbert Hoover Presidential Library-Museum
 
Student Presentation: The Hoover Dam by Sid and Vic
Student Presentation: The Hoover Dam by Sid and VicStudent Presentation: The Hoover Dam by Sid and Vic
Student Presentation: The Hoover Dam by Sid and Vic
 
HOOVER DAM DOC
HOOVER DAM DOCHOOVER DAM DOC
HOOVER DAM DOC
 
Grace Cathedral - San Francisco California
Grace Cathedral  - San Francisco CaliforniaGrace Cathedral  - San Francisco California
Grace Cathedral - San Francisco California
 
Hoover Dam - Arizona & Nevada
Hoover Dam - Arizona & NevadaHoover Dam - Arizona & Nevada
Hoover Dam - Arizona & Nevada
 
Hoover Dam
Hoover DamHoover Dam
Hoover Dam
 
Student Presentation: The Hoover Dam by Sid and Vic
Student Presentation: The Hoover Dam by Sid and VicStudent Presentation: The Hoover Dam by Sid and Vic
Student Presentation: The Hoover Dam by Sid and Vic
 
4M Presentation - E-learning platform
4M Presentation - E-learning platform4M Presentation - E-learning platform
4M Presentation - E-learning platform
 
Herbert Hoover
Herbert HooverHerbert Hoover
Herbert Hoover
 
Hoover Dam
Hoover DamHoover Dam
Hoover Dam
 

Similaire à Hoover dam bypass bridge

Hooverdambypassbridge 151003030959-lva1-app6891
Hooverdambypassbridge 151003030959-lva1-app6891Hooverdambypassbridge 151003030959-lva1-app6891
Hooverdambypassbridge 151003030959-lva1-app6891Soumalya Bag
 
APWA Award Winning Roundabout in Ann Arbor
APWA Award Winning Roundabout in Ann ArborAPWA Award Winning Roundabout in Ann Arbor
APWA Award Winning Roundabout in Ann ArborOHM Advisors
 
Walton Boulevard Reconstruction, APWA Project of the Year
Walton Boulevard Reconstruction, APWA Project of the YearWalton Boulevard Reconstruction, APWA Project of the Year
Walton Boulevard Reconstruction, APWA Project of the YearOHM Advisors
 
Scottish_Forth_Crossing_2011
Scottish_Forth_Crossing_2011Scottish_Forth_Crossing_2011
Scottish_Forth_Crossing_2011Mike Bisland
 
Devore vvcc feb 13 2013 final
Devore vvcc feb 13 2013 finalDevore vvcc feb 13 2013 final
Devore vvcc feb 13 2013 finalvvchamber123
 
William Faoro - 4pResumeM1
William Faoro - 4pResumeM1William Faoro - 4pResumeM1
William Faoro - 4pResumeM1William Faoro PE
 
Austroads Bridge Conference 2017
Austroads Bridge Conference 2017Austroads Bridge Conference 2017
Austroads Bridge Conference 2017Eric Boothman
 
2014 IRF GRAA Winners
2014 IRF GRAA Winners2014 IRF GRAA Winners
2014 IRF GRAA WinnersLars Forslöf
 
Public Information Meeting: Realignment of Old Courthouse Road at Besley Road
Public Information Meeting: Realignment of Old Courthouse Road at Besley RoadPublic Information Meeting: Realignment of Old Courthouse Road at Besley Road
Public Information Meeting: Realignment of Old Courthouse Road at Besley RoadFairfax County
 
India's preparedness for IWT
India's preparedness for IWTIndia's preparedness for IWT
India's preparedness for IWTcmmindia2017
 
Quander Road Outfall and Stream Restoration
Quander Road Outfall and Stream RestorationQuander Road Outfall and Stream Restoration
Quander Road Outfall and Stream RestorationFairfax County
 
101024 Mafraq_Presentation_Javad_Akhtar
101024 Mafraq_Presentation_Javad_Akhtar101024 Mafraq_Presentation_Javad_Akhtar
101024 Mafraq_Presentation_Javad_AkhtarJavad Akhtar
 
Cinder Bed Road Realignment
Cinder Bed Road RealignmentCinder Bed Road Realignment
Cinder Bed Road RealignmentFairfax County
 
Nikolai Tim (01-24-11) (3)
Nikolai Tim (01-24-11) (3)Nikolai Tim (01-24-11) (3)
Nikolai Tim (01-24-11) (3)Timothy Nikolai
 
Indian Run Restoration Project
Indian Run Restoration ProjectIndian Run Restoration Project
Indian Run Restoration ProjectFairfax County
 
Public Information Meeting: Realignment of Old Courthouse Road at Besley Road
Public Information Meeting: Realignment of Old Courthouse Road at Besley RoadPublic Information Meeting: Realignment of Old Courthouse Road at Besley Road
Public Information Meeting: Realignment of Old Courthouse Road at Besley RoadFairfax County
 
ACEC/SD 2009 Engineering Excellence Awards
ACEC/SD 2009 Engineering Excellence AwardsACEC/SD 2009 Engineering Excellence Awards
ACEC/SD 2009 Engineering Excellence AwardsACECSDES
 

Similaire à Hoover dam bypass bridge (20)

Hooverdambypassbridge 151003030959-lva1-app6891
Hooverdambypassbridge 151003030959-lva1-app6891Hooverdambypassbridge 151003030959-lva1-app6891
Hooverdambypassbridge 151003030959-lva1-app6891
 
APWA Award Winning Roundabout in Ann Arbor
APWA Award Winning Roundabout in Ann ArborAPWA Award Winning Roundabout in Ann Arbor
APWA Award Winning Roundabout in Ann Arbor
 
Walton Boulevard Reconstruction, APWA Project of the Year
Walton Boulevard Reconstruction, APWA Project of the YearWalton Boulevard Reconstruction, APWA Project of the Year
Walton Boulevard Reconstruction, APWA Project of the Year
 
Scottish_Forth_Crossing_2011
Scottish_Forth_Crossing_2011Scottish_Forth_Crossing_2011
Scottish_Forth_Crossing_2011
 
Devore vvcc feb 13 2013 final
Devore vvcc feb 13 2013 finalDevore vvcc feb 13 2013 final
Devore vvcc feb 13 2013 final
 
William Faoro - 4pResumeM1
William Faoro - 4pResumeM1William Faoro - 4pResumeM1
William Faoro - 4pResumeM1
 
Austroads Bridge Conference 2017
Austroads Bridge Conference 2017Austroads Bridge Conference 2017
Austroads Bridge Conference 2017
 
2014 IRF GRAA Winners
2014 IRF GRAA Winners2014 IRF GRAA Winners
2014 IRF GRAA Winners
 
Public Information Meeting: Realignment of Old Courthouse Road at Besley Road
Public Information Meeting: Realignment of Old Courthouse Road at Besley RoadPublic Information Meeting: Realignment of Old Courthouse Road at Besley Road
Public Information Meeting: Realignment of Old Courthouse Road at Besley Road
 
Canal City - Poster-
Canal City - Poster-Canal City - Poster-
Canal City - Poster-
 
Virginia
VirginiaVirginia
Virginia
 
India's preparedness for IWT
India's preparedness for IWTIndia's preparedness for IWT
India's preparedness for IWT
 
Quander Road Outfall and Stream Restoration
Quander Road Outfall and Stream RestorationQuander Road Outfall and Stream Restoration
Quander Road Outfall and Stream Restoration
 
Theodor Nicolas Master
Theodor Nicolas MasterTheodor Nicolas Master
Theodor Nicolas Master
 
101024 Mafraq_Presentation_Javad_Akhtar
101024 Mafraq_Presentation_Javad_Akhtar101024 Mafraq_Presentation_Javad_Akhtar
101024 Mafraq_Presentation_Javad_Akhtar
 
Cinder Bed Road Realignment
Cinder Bed Road RealignmentCinder Bed Road Realignment
Cinder Bed Road Realignment
 
Nikolai Tim (01-24-11) (3)
Nikolai Tim (01-24-11) (3)Nikolai Tim (01-24-11) (3)
Nikolai Tim (01-24-11) (3)
 
Indian Run Restoration Project
Indian Run Restoration ProjectIndian Run Restoration Project
Indian Run Restoration Project
 
Public Information Meeting: Realignment of Old Courthouse Road at Besley Road
Public Information Meeting: Realignment of Old Courthouse Road at Besley RoadPublic Information Meeting: Realignment of Old Courthouse Road at Besley Road
Public Information Meeting: Realignment of Old Courthouse Road at Besley Road
 
ACEC/SD 2009 Engineering Excellence Awards
ACEC/SD 2009 Engineering Excellence AwardsACEC/SD 2009 Engineering Excellence Awards
ACEC/SD 2009 Engineering Excellence Awards
 

Dernier

ROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.ppt
ROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.pptROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.ppt
ROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.pptJohnWilliam111370
 
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...Sumanth A
 
"Exploring the Essential Functions and Design Considerations of Spillways in ...
"Exploring the Essential Functions and Design Considerations of Spillways in ..."Exploring the Essential Functions and Design Considerations of Spillways in ...
"Exploring the Essential Functions and Design Considerations of Spillways in ...Erbil Polytechnic University
 
DEVICE DRIVERS AND INTERRUPTS SERVICE MECHANISM.pdf
DEVICE DRIVERS AND INTERRUPTS  SERVICE MECHANISM.pdfDEVICE DRIVERS AND INTERRUPTS  SERVICE MECHANISM.pdf
DEVICE DRIVERS AND INTERRUPTS SERVICE MECHANISM.pdfAkritiPradhan2
 
Cost estimation approach: FP to COCOMO scenario based question
Cost estimation approach: FP to COCOMO scenario based questionCost estimation approach: FP to COCOMO scenario based question
Cost estimation approach: FP to COCOMO scenario based questionSneha Padhiar
 
OOP concepts -in-Python programming language
OOP concepts -in-Python programming languageOOP concepts -in-Python programming language
OOP concepts -in-Python programming languageSmritiSharma901052
 
Module-1-(Building Acoustics) Noise Control (Unit-3). pdf
Module-1-(Building Acoustics) Noise Control (Unit-3). pdfModule-1-(Building Acoustics) Noise Control (Unit-3). pdf
Module-1-(Building Acoustics) Noise Control (Unit-3). pdfManish Kumar
 
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENT
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENTFUNCTIONAL AND NON FUNCTIONAL REQUIREMENT
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENTSneha Padhiar
 
Levelling - Rise and fall - Height of instrument method
Levelling - Rise and fall - Height of instrument methodLevelling - Rise and fall - Height of instrument method
Levelling - Rise and fall - Height of instrument methodManicka Mamallan Andavar
 
System Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingSystem Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingBootNeck1
 
Prach: A Feature-Rich Platform Empowering the Autism Community
Prach: A Feature-Rich Platform Empowering the Autism CommunityPrach: A Feature-Rich Platform Empowering the Autism Community
Prach: A Feature-Rich Platform Empowering the Autism Communityprachaibot
 
Main Memory Management in Operating System
Main Memory Management in Operating SystemMain Memory Management in Operating System
Main Memory Management in Operating SystemRashmi Bhat
 
Engineering Drawing section of solid
Engineering Drawing     section of solidEngineering Drawing     section of solid
Engineering Drawing section of solidnamansinghjarodiya
 
Mine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxMine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxRomil Mishra
 
Input Output Management in Operating System
Input Output Management in Operating SystemInput Output Management in Operating System
Input Output Management in Operating SystemRashmi Bhat
 
Comprehensive energy systems.pdf Comprehensive energy systems.pdf
Comprehensive energy systems.pdf Comprehensive energy systems.pdfComprehensive energy systems.pdf Comprehensive energy systems.pdf
Comprehensive energy systems.pdf Comprehensive energy systems.pdfalene1
 
SOFTWARE ESTIMATION COCOMO AND FP CALCULATION
SOFTWARE ESTIMATION COCOMO AND FP CALCULATIONSOFTWARE ESTIMATION COCOMO AND FP CALCULATION
SOFTWARE ESTIMATION COCOMO AND FP CALCULATIONSneha Padhiar
 
Virtual memory management in Operating System
Virtual memory management in Operating SystemVirtual memory management in Operating System
Virtual memory management in Operating SystemRashmi Bhat
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionMebane Rash
 

Dernier (20)

ROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.ppt
ROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.pptROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.ppt
ROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.ppt
 
Designing pile caps according to ACI 318-19.pptx
Designing pile caps according to ACI 318-19.pptxDesigning pile caps according to ACI 318-19.pptx
Designing pile caps according to ACI 318-19.pptx
 
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...
 
"Exploring the Essential Functions and Design Considerations of Spillways in ...
"Exploring the Essential Functions and Design Considerations of Spillways in ..."Exploring the Essential Functions and Design Considerations of Spillways in ...
"Exploring the Essential Functions and Design Considerations of Spillways in ...
 
DEVICE DRIVERS AND INTERRUPTS SERVICE MECHANISM.pdf
DEVICE DRIVERS AND INTERRUPTS  SERVICE MECHANISM.pdfDEVICE DRIVERS AND INTERRUPTS  SERVICE MECHANISM.pdf
DEVICE DRIVERS AND INTERRUPTS SERVICE MECHANISM.pdf
 
Cost estimation approach: FP to COCOMO scenario based question
Cost estimation approach: FP to COCOMO scenario based questionCost estimation approach: FP to COCOMO scenario based question
Cost estimation approach: FP to COCOMO scenario based question
 
OOP concepts -in-Python programming language
OOP concepts -in-Python programming languageOOP concepts -in-Python programming language
OOP concepts -in-Python programming language
 
Module-1-(Building Acoustics) Noise Control (Unit-3). pdf
Module-1-(Building Acoustics) Noise Control (Unit-3). pdfModule-1-(Building Acoustics) Noise Control (Unit-3). pdf
Module-1-(Building Acoustics) Noise Control (Unit-3). pdf
 
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENT
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENTFUNCTIONAL AND NON FUNCTIONAL REQUIREMENT
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENT
 
Levelling - Rise and fall - Height of instrument method
Levelling - Rise and fall - Height of instrument methodLevelling - Rise and fall - Height of instrument method
Levelling - Rise and fall - Height of instrument method
 
System Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingSystem Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event Scheduling
 
Prach: A Feature-Rich Platform Empowering the Autism Community
Prach: A Feature-Rich Platform Empowering the Autism CommunityPrach: A Feature-Rich Platform Empowering the Autism Community
Prach: A Feature-Rich Platform Empowering the Autism Community
 
Main Memory Management in Operating System
Main Memory Management in Operating SystemMain Memory Management in Operating System
Main Memory Management in Operating System
 
Engineering Drawing section of solid
Engineering Drawing     section of solidEngineering Drawing     section of solid
Engineering Drawing section of solid
 
Mine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxMine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptx
 
Input Output Management in Operating System
Input Output Management in Operating SystemInput Output Management in Operating System
Input Output Management in Operating System
 
Comprehensive energy systems.pdf Comprehensive energy systems.pdf
Comprehensive energy systems.pdf Comprehensive energy systems.pdfComprehensive energy systems.pdf Comprehensive energy systems.pdf
Comprehensive energy systems.pdf Comprehensive energy systems.pdf
 
SOFTWARE ESTIMATION COCOMO AND FP CALCULATION
SOFTWARE ESTIMATION COCOMO AND FP CALCULATIONSOFTWARE ESTIMATION COCOMO AND FP CALCULATION
SOFTWARE ESTIMATION COCOMO AND FP CALCULATION
 
Virtual memory management in Operating System
Virtual memory management in Operating SystemVirtual memory management in Operating System
Virtual memory management in Operating System
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of Action
 

Hoover dam bypass bridge

  • 2. Table of contents ❖ introduction ❖ Pre-feasibility ❖ Project conception ❖ Project need & objective ❖ Project preparation ❖ Environmental impact assessment ❖ Technical assessment ❖ Financial information ❖ Construction ❖ Operation & maintenance ❖ Transfer of the project
  • 3. Introduction ❖ Hoover dam bypass is a part of 4 miles long highway connecting Arizona and Nevada interstates. ❖ The new 1900 ft. (571 m) Hoover dam bypass bridge spans the black canyon at about 1500 ft. (457.2m) south of the Hoover Dam, connecting the Arizona and Nevada approach highways nearly 900 ft. ❖ The bridge carries four lanes of traffic and sidewalk. ❖ It is a composite steel concrete deck arch bridge with main span of 1060 ft. (323m). The arch rib is made of reinforce concrete. ❖ It is the second largest concrete arch bridge span in the world. The bride is owned by Arizona DOT and Nevada DOT.
  • 4. Pre-feasibility stage ❖ Project conception ❖ “Colorado river bridge project management team” came into place by joint decision of Navida and Arizona state department of transportation.
  • 5. Project Need and objective Potential problems identified ❖ Accidents ❖ Sharp turns ❖ Limited sight distances ❖ No adequate room for disabled cars ❖ Speed was as low as 15MPH against initial speed of 50MPH ❖ inadequate road capacity ❖ Less travel times
  • 6. Objective of the project • To minimise the potential for traffic accidents • To remove the bottlenecks to interstate and international commerce to reduce traffic congested • To reduce travel time • To protect Hoover dam employees, visitors, equipment, power generations capabilities • To provide safe and improved conditions for the maintenance and operation of Hoover dam Project Preparation activities After initial surveys at this point it was decided to carryout two important studies in detail ❖ Engineering & technical aspect ❖ Environmental impact assessment
  • 7. Environmental impact assessment studies • Air quality analysis • Noise analysis • Visual resources analysis • Biological assessments • Archaeological resources survey Project Design The requirement for the design of the bridge was both technical and aesthetics of the bridge, the most important requirement in the design would be design load which in this case was 180 metric tons. Various designs were studied some of them were as follows. After considering the design criteria for the bridge the team selected composite steel and concrete type of bridge that met all the design criteria.
  • 8. Financial information Contract contractor value Arizona Approach Mont/VASTCO $22M Navida Approach Edward Kraemer & sons $30M River bridge Obayashi/Mitsubishi $114M Paving Freshener & Las Vegas paving $15M Total $181M
  • 9. Construction ❖ Phase 1. Building connection between Colorado Bridge and U.S 93 this included 4 lanes of roadway ❖ Phase2. This was from Navida side, The Roadway from the project start to the Colorado Bridge, started in 2003 and finished in 2005 ahead of time by 2 months. ❖ Phase3. The contractor constructed 2.11 miles of new four-lane highway alignment including six new bridges, a new traffic interchange at US 93 near the Hacienda Casino, retaining walls, wildlife crossing. ❖ Phase4. Asphalt paving of the entire 4 miles from Arizona to Nevada side to the project. This was complete in 2010.
  • 10. Operation & maintenance The operation and maintenance is either side of the bypass bridge done by Arizona state DOT and Nevada State DOT. The aim of the maintenance is to insure safety, carryout visual and technical inspection of the bridge, to maintain smooth traffic flow, repairs to the bridges, road pavements. The funding for the same comes from the Nevada and Arizona state departments of transportations.
  • 11. Achievement ❖ The project completion on budget was a great success story although it went slightly away from the schedule. The project primary purpose and objective of reduction in traffic congestion was achieved and this facilitated smooth traffic. ❖ The travel time of the existing road was 16.5minutes while this newly construction facility reduced it to 6 minutes, a total of 10 minutes were saved. This also increased speed. The environmental impact assessment helped reduce and mitigate the problems of environment and also wild life crossing between different points.
  • 13. Project Transfer The twin-rib arch of the Colorado River Bridge was completed in August 2009 and the bridge columns were constructed in November 2009. Construction of the entire bypass was completed in September 2010. It was celebrated by making grand ceremony. The bypass opened to traffic a month later in October 2010.
  • 14. Learning This project helped me a lot in understanding the complexity of the infrastructural project development, in this exercise I learned various surveys required in each stage of the project, the project coordination, construction and impact analysis on the environment. Every project before comes into existence must go through a logical process, I learned practically what process were involved in this project. Conclusion The Hoover Dam, Bypass Colorado River Bridge was an extreme challenge, due to the structure itself, advanced construction schemes, and the surrounding environment. The effort of all personnel involved made the incredible graceful bridge into reality. The Hoover dam bypass Colorado River Bridge was completed in 2010, The Bridge was opened to traffic on October 2010. The Project resulted iconic landmark structure set in the Colorado River’s black canyon with a view to historic Hoover Dam. Ten minutes reduction time was another achievement followed by reduction in traffic congestion and accidents.
  • 15. References 1. http://energy.gov/sites/prod/files/nepapub/nepa_documents/RedDont/EA-1478-FEA-2003.pdf 2. http://www.roadtraffic-technology.com/projects/hoover-bypass/ 3. https://books.google.co.in/books?id=jJ3MBQAAQBAJ&pg=PA1282&dq=hoover+dam+bridge&hl=en&sa=X&ved=0CCIQ6AEwAmoVChMI4 4. http://www.roadtraffic-technology.com/projects/hoover-bypass/hoover-bypass6.html 5. http://www.jpci.or.jp/NR/pdf/40.pdf 6. http://design.transportation.org/Documents/SCOD,Hammontree,FHWA,HooverDamBypass.pdf 7. http://www.klbconstruction.com/pdf/making_history_near_hoover_dam.pdf 8. http://www.crma.ac.th/histdept/journal/jour-49/49-jour-12.pdf 9. http://transportation.ky.gov/SASHTO/The%20Mike%20OCallaghan%20Pat%20Tillman%20Memorial%20Bridge.pdf 10. http://mcedc.colorado.edu/sites/default/files/FinalHooverDamBypass.pdf 11. http://www.hpcbridgeviews.com/i63/Printable.pdf 12. http://www.atkinsglobal.com/en-gb/projects/hoover-dam-bypass 13. http://nepis.epa.gov/Exe/ZyNET.exe/20005FMQ.TXT?ZyActionD=ZyDocument&Client=EPA&Index=2000+Thru+2005&Docs=&Query=&T