Chapter 26
These slides are designed to accompany Software Engineering: A Practitioner’s Approach, 7/e
(McGraw-Hill 2009). Slides copyright 2009 by Roger Pressman. 1
 Estimation for Software Projects
Slide Set to accompany
Software Engineering: A Practitioner’s Approach, 7/e
by Roger S. Pressman
Slides copyright © 1996, 2001, 2005, 2009 by Roger S. Pressman
For non-profit educational use only
May be reproduced ONLY for student use at the university level when used in conjunction
with Software Engineering: A Practitioner's Approach, 7/e. Any other reproduction or use is
prohibited without the express written permission of the author.
All copyright information MUST appear if these slides are posted on a website for student
use.
Software Project Planning
The overall goal of project planning is to
establish a pragmatic strategy for controlling,
tracking, and monitoring a complex technical
project.
Why?
So the end result gets done on time, with
quality!
These slides are designed to accompany Software Engineering: A Practitioner’s Approach, 7/e
(McGraw-Hill 2009). Slides copyright 2009 by Roger Pressman. 2
Project Planning Task Set-I
These slides are designed to accompany Software Engineering: A Practitioner’s Approach, 7/e
(McGraw-Hill 2009). Slides copyright 2009 by Roger Pressman. 3
 Establish project scope
 Determine feasibility
 Analyze risks
 Risk analysis is considered in detail in Chapter 25.
 Define required resources
 Determine require human resources
 Define reusable software resources
 Identify environmental resources
Project Planning Task Set-II
These slides are designed to accompany Software Engineering: A Practitioner’s Approach, 7/e
(McGraw-Hill 2009). Slides copyright 2009 by Roger Pressman. 4
 Estimate cost and effort
 Decompose the problem
 Develop two or more estimates using size, function
points, process tasks or use-cases
 Reconcile the estimates
 Develop a project schedule
 Scheduling is considered in detail in Chapter 27.
• Establish a meaningful task set
• Define a task network
• Use scheduling tools to develop a timeline chart
• Define schedule tracking mechanisms
Estimation
These slides are designed to accompany Software Engineering: A Practitioner’s Approach, 7/e
(McGraw-Hill 2009). Slides copyright 2009 by Roger Pressman. 5
 Estimation of resources, cost, and schedule for
a software engineering effort requires
 experience
 access to good historical information (metrics)
 the courage to commit to quantitative predictions
when qualitative information is all that exists
 Estimation carries inherent risk and this risk
leads to uncertainty
Write it Down!
Software
Project
Plan
Project Scope
Estimates
Risks
Schedule
Control strategy
These slides are designed to accompany Software Engineering: A Practitioner’s Approach, 7/e
(McGraw-Hill 2009). Slides copyright 2009 by Roger Pressman. 6
To Understand Scope ...
 Understand the customers needs
 understand the business context
 understand the project boundaries
 understand the customer’s motivation
 understand the likely paths for change
 understand that ...
Even when you understand,
nothing is guaranteed!
These slides are designed to accompany Software Engineering: A Practitioner’s Approach, 7/e
(McGraw-Hill 2009). Slides copyright 2009 by Roger Pressman. 7
What is Scope?
These slides are designed to accompany Software Engineering: A Practitioner’s Approach, 7/e
(McGraw-Hill 2009). Slides copyright 2009 by Roger Pressman. 8
 Software scope describes
 the functions and features that are to be delivered to
end-users
 the data that are input and output
 the “content” that is presented to users as a
consequence of using the software
 the performance, constraints, interfaces, and
reliability that bound the system.
 Scope is defined using one of two techniques:
• A narrative description of software scope is developed
after communication with all stakeholders.
• A set of use-cases is developed by end-users.
Resources
project
These slides are designed to accompany Software Engineering: A Practitioner’s Approach, 7/e
(McGraw-Hill 2009). Slides copyright 2009 by Roger Pressman. 9
people
skills
number
location
reusable
softw are
OTS
components
f ull-experience
components
new
components
part.-experience
components
environment
hardware
sof tware
tools
network
resources
Project Estimation
 Project scope must be
understood
 Elaboration (decomposition) is
necessary
 Historical metrics are very helpful
 At least two different techniques
should be used
 Uncertainty is inherent in the
process
These slides are designed to accompany Software Engineering: A Practitioner’s Approach, 7/e
(McGraw-Hill 2009). Slides copyright 2009 by Roger Pressman. 10
Estimation Techniques
 Past (similar) project experience
 Conventional estimation techniques
 task breakdown and effort estimates
 size (e.g., FP) estimates
 Empirical models
 Automated tools
These slides are designed to accompany Software Engineering: A Practitioner’s Approach, 7/e
(McGraw-Hill 2009). Slides copyright 2009 by Roger Pressman. 11
Estimation Accuracy
These slides are designed to accompany Software Engineering: A Practitioner’s Approach, 7/e
(McGraw-Hill 2009). Slides copyright 2009 by Roger Pressman. 12
 Predicated on …
 the degree to which the planner has properly
estimated the size of the product to be built
 the ability to translate the size estimate into human
effort, calendar time, and dollars (a function of the
availability of reliable software metrics from past
projects)
 the degree to which the project plan reflects the
abilities of the software team
 the stability of product requirements and the
environment that supports the software engineering
effort.
Functional Decomposition
functional
decomposition
Statement
of
Scope
Perform a
Grammatical “parse”
These slides are designed to accompany Software Engineering: A Practitioner’s Approach, 7/e
(McGraw-Hill 2009). Slides copyright 2009 by Roger Pressman. 13
Conventional Methods:
LOC/FP Approach
These slides are designed to accompany Software Engineering: A Practitioner’s Approach, 7/e
(McGraw-Hill 2009). Slides copyright 2009 by Roger Pressman. 14
 compute LOC/FP using estimates of
information domain values
 use historical data to build estimates for
the project
Example: LOC Approach
Average productivity for systems of this type = 620 LOC/pm.
Burdened labor rate =$8000 per month, the cost per line of
code is approximately $13.
Based on the LOC estimate and the historical productivity
data, the total estimated project cost is $431,000 and the
estimated effort is 54 person-months.
These slides are designed to accompany Software Engineering: A Practitioner’s Approach, 7/e
(McGraw-Hill 2009). Slides copyright 2009 by Roger Pressman. 15
Example: FP Approach
The estimated number of FP is derived:
FPestimated = count-total 3 [0.65 + 0.01 3 S (Fi)]
FPestimated = 375
organizational average productivity = 6.5 FP/pm.
burdened labor rate = $8000 per month, approximately $1230/FP.
Based on the FP estimate and the historical productivity data, total estimated
project cost is $461,000 and estimated effort is 58 person-months.
These slides are designed to accompany Software Engineering: A Practitioner’s Approach, 7/e
(McGraw-Hill 2009). Slides copyright 2009 by Roger Pressman. 16
Process-Based Estimation
Obtained from “process framework”
application
functions
framework activities
Effort required to
accomplish
each framework
activity for each
application function
These slides are designed to accompany Software Engineering: A Practitioner’s Approach, 7/e
(McGraw-Hill 2009). Slides copyright 2009 by Roger Pressman. 17
Process-Based Estimation Example
Activity
CC Planning
Risk
Engineering
Construction
CE
Analysis Release Totals
Task analysis design code test
Functio
n
UICF 0.50 2.50 0.40 5.00 n/a 8.40
2DGA 0.75 4.00 0.60 2.00 n/a 7.35
3DGA 0.50 4.00 1.00 3.00 n/a 8.50
CGDF 0.50 3.00 1.00 1.50 n/a 6.00
DSM 0.50 3.00 0.75 1.50 n/a 5.75
PCF 0.25 2.00 0.50 1.50 n/a 4.25
DAM 0.50 2.00 0.50 2.00 n/a 5.00
Totals 0.25 0.25 0.25 3.50 20.50 4.50 16.50 46.00
% effort 1% 1% 1% 8% 45% 10% 36%
CC = customer communication CE= customer evaluation
Based on an average burdened labor rate of $8,000 per
month, the total estimated project cost is $368,000 and
the estimated effort is 46 person-months.
These slides are designed to accompany Software Engineering: A Practitioner’s Approach, 7/e
(McGraw-Hill 2009). Slides copyright 2009 by Roger Pressman. 18
Tool-Based Estimation
project characteristics
calibration factors
LOC/FP data
These slides are designed to accompany Software Engineering: A Practitioner’s Approach, 7/e
(McGraw-Hill 2009). Slides copyright 2009 by Roger Pressman. 19
Estimation with Use-Cases
use cases scenariospages Źscenarios pages
6 10 6 Ź 12 5
LOC LOCestimate
560 3,366
esubsystem
subsystemgroup
e subsystemgroup
stimate
10 20 8 Ź 16 8 3100 31,233
5 6 5 Ź 10 6 1650 7,970
Ź Ź Ź Ź
Ź Ź Ź Ź 42,568
Userinterface subsystem
Engineering subsystemgroup
Infrastructure subsystem group
Total LOCestimate
Using 620 LOC/pm as the average productivity for systems of
this type and a burdened labor rate of $8000 per month, the
cost per line of code is approximately $13. Based on the use-
case estimate and the historical productivity data, the total
estimated project cost is $552,000 and the estimated
effort is 68 person-months.
These slides are designed to accompany Software Engineering: A Practitioner’s Approach, 7/e
(McGraw-Hill 2009). Slides copyright 2009 by Roger Pressman. 20
Empirical Estimation Models
General form:
exponent
effort = tuning coefficient * size
usually derived
as person-months
of effort required
either a constant or
a number derived based
on complexity of project
usually LOC but
may also be
function point
empirically
derived
These slides are designed to accompany Software Engineering: A Practitioner’s Approach, 7/e
(McGraw-Hill 2009). Slides copyright 2009 by Roger Pressman. 21
COCOMO-II
These slides are designed to accompany Software Engineering: A Practitioner’s Approach, 7/e
(McGraw-Hill 2009). Slides copyright 2009 by Roger Pressman. 22
 COCOMO II is actually a hierarchy of
estimation models that address the following
areas:
• Application composition model. Used during the early
stages of software engineering, when prototyping of
user interfaces, consideration of software and system
interaction, assessment of performance, and
evaluation of technology maturity are paramount.
• Early design stage model. Used once requirements
have been stabilized and basic software architecture
has been established.
• Post-architecture-stage model. Used during the
construction of the software.
The Software Equation
A dynamic multivariable model
E = [LOC x B0.333/P]3 x (1/t4)
where
E = effort in person-months or person-years
t = project duration in months or years
B = “special skills factor”
P = “productivity parameter”
These slides are designed to accompany Software Engineering: A Practitioner’s Approach, 7/e
(McGraw-Hill 2009). Slides copyright 2009 by Roger Pressman. 23
Estimation for OO Projects-I
These slides are designed to accompany Software Engineering: A Practitioner’s Approach, 7/e
(McGraw-Hill 2009). Slides copyright 2009 by Roger Pressman. 24
 Develop estimates using effort decomposition, FP analysis,
and any other method that is applicable for conventional
applications.
 Using object-oriented requirements modeling (Chapter 6),
develop use-cases and determine a count.
 From the analysis model, determine the number of key classes
(called analysis classes in Chapter 6).
 Categorize the type of interface for the application and develop
a multiplier for support classes:
 Interface type
 No GUI
 Text-based user interface
 GUI
 Complex GUI
Multiplier
2.0
2.25
2.5
3.0
Estimation for OO Projects-II
These slides are designed to accompany Software Engineering: A Practitioner’s Approach, 7/e
(McGraw-Hill 2009). Slides copyright 2009 by Roger Pressman. 25
 Multiply the number of key classes (step 3) by the
multiplier to obtain an estimate for the number of support
classes.
 Multiply the total number of classes (key + support) by
the average number of work-units per class. Lorenz and
Kidd suggest 15 to 20 person-days per class.
 Cross check the class-based estimate by multiplying the
average number of work-units per use-case
Estimation for Agile Projects
These slides are designed to accompany Software Engineering: A Practitioner’s Approach, 7/e
(McGraw-Hill 2009). Slides copyright 2009 by Roger Pressman. 26
 Each user scenario (a mini-use-case) is considered separately
for estimation purposes.
 The scenario is decomposed into the set of software
engineering tasks that will be required to develop it.
 Each task is estimated separately. Note: estimation can be
based on historical data, an empirical model, or “experience.”
 Alternatively, the ‘volume’ of the scenario can be estimated in LOC,
FP or some other volume-oriented measure (e.g., use-case count).
 Estimates for each task are summed to create an estimate for
the scenario.
 Alternatively, the volume estimate for the scenario is translated into
effort using historical data.
 The effort estimates for all scenarios that are to be implemented
for a given software increment are summed to develop the effort
estimate for the increment.
The Make-Buy Decision
These slides are designed to accompany Software Engineering: A Practitioner’s Approach, 7/e
(McGraw-Hill 2009). Slides copyright 2009 by Roger Pressman. 27

More Related Content

What's hot

software project management Waterfall model
software project management Waterfall modelsoftware project management Waterfall model
software project management Waterfall modelREHMAT ULLAH
 
Software Engineering (Metrics for Process and Projects)
Software Engineering (Metrics for Process and Projects)Software Engineering (Metrics for Process and Projects)
Software Engineering (Metrics for Process and Projects)ShudipPal
 
Pressman ch-21-project-management-concepts
Pressman ch-21-project-management-conceptsPressman ch-21-project-management-concepts
Pressman ch-21-project-management-conceptsseethaveera
 
Chapter 13 software testing strategies
Chapter 13 software testing strategiesChapter 13 software testing strategies
Chapter 13 software testing strategiesSHREEHARI WADAWADAGI
 
Software engineering lecture notes
Software engineering lecture notesSoftware engineering lecture notes
Software engineering lecture notesSiva Ayyakutti
 
Introduction to software testing
Introduction to software testingIntroduction to software testing
Introduction to software testingHadi Fadlallah
 
Programming team structure
Programming team structureProgramming team structure
Programming team structureNancyBeaulah_R
 
Types of software testing
Types of software testingTypes of software testing
Types of software testingPrachi Sasankar
 
Software Process Models
Software Process ModelsSoftware Process Models
Software Process ModelsAtul Karmyal
 
Defining the Problem - Goals and requirements
Defining the Problem - Goals and requirementsDefining the Problem - Goals and requirements
Defining the Problem - Goals and requirementsStephennancy
 
Software Testing Fundamentals
Software Testing FundamentalsSoftware Testing Fundamentals
Software Testing FundamentalsChankey Pathak
 
Design concept -Software Engineering
Design concept -Software EngineeringDesign concept -Software Engineering
Design concept -Software EngineeringVarsha Ajith
 

What's hot (20)

software project management Waterfall model
software project management Waterfall modelsoftware project management Waterfall model
software project management Waterfall model
 
Software Engineering (Metrics for Process and Projects)
Software Engineering (Metrics for Process and Projects)Software Engineering (Metrics for Process and Projects)
Software Engineering (Metrics for Process and Projects)
 
Pressman ch-21-project-management-concepts
Pressman ch-21-project-management-conceptsPressman ch-21-project-management-concepts
Pressman ch-21-project-management-concepts
 
Chapter 13 software testing strategies
Chapter 13 software testing strategiesChapter 13 software testing strategies
Chapter 13 software testing strategies
 
Software quality assurance
Software quality assuranceSoftware quality assurance
Software quality assurance
 
Software engineering lecture notes
Software engineering lecture notesSoftware engineering lecture notes
Software engineering lecture notes
 
The Software Development Process
The Software Development ProcessThe Software Development Process
The Software Development Process
 
Introduction to software testing
Introduction to software testingIntroduction to software testing
Introduction to software testing
 
Programming team structure
Programming team structureProgramming team structure
Programming team structure
 
Software quality
Software qualitySoftware quality
Software quality
 
Types of software testing
Types of software testingTypes of software testing
Types of software testing
 
RMMM Plan
RMMM PlanRMMM Plan
RMMM Plan
 
Software Process Models
Software Process ModelsSoftware Process Models
Software Process Models
 
Defining the Problem - Goals and requirements
Defining the Problem - Goals and requirementsDefining the Problem - Goals and requirements
Defining the Problem - Goals and requirements
 
Software Testing Fundamentals
Software Testing FundamentalsSoftware Testing Fundamentals
Software Testing Fundamentals
 
Slides chapters 26-27
Slides chapters 26-27Slides chapters 26-27
Slides chapters 26-27
 
Test Levels & Techniques
Test Levels & TechniquesTest Levels & Techniques
Test Levels & Techniques
 
Software design
Software designSoftware design
Software design
 
Design concept -Software Engineering
Design concept -Software EngineeringDesign concept -Software Engineering
Design concept -Software Engineering
 
Slides chapter 2
Slides chapter 2Slides chapter 2
Slides chapter 2
 

Similar to estimation-for-software-projects-chapter-26-ppt.pptx

005614116.pdf
005614116.pdf005614116.pdf
005614116.pdfEidTahir
 
SE CHAPTER 2 PROCESS MODELS
SE CHAPTER 2 PROCESS MODELSSE CHAPTER 2 PROCESS MODELS
SE CHAPTER 2 PROCESS MODELSAbrar ali
 
Process models
Process modelsProcess models
Process modelsStudent
 
SE CHAPTER 1 SOFTWARE ENGINEERING
SE CHAPTER 1 SOFTWARE ENGINEERINGSE CHAPTER 1 SOFTWARE ENGINEERING
SE CHAPTER 1 SOFTWARE ENGINEERINGAbrar ali
 
Chapter 01 software engineering pressman
Chapter 01  software engineering pressmanChapter 01  software engineering pressman
Chapter 01 software engineering pressmanRohitGoyal183
 
Chapter 03
Chapter 03Chapter 03
Chapter 03ppp mmm
 
Agile Development software engineering process model
Agile Development software engineering process modelAgile Development software engineering process model
Agile Development software engineering process modelGovadaDhana
 
Chapter_03.ppt
Chapter_03.pptChapter_03.ppt
Chapter_03.pptoluobes
 
Chapter 2_Process Models sunorgamisedASE_finalised.ppt
Chapter 2_Process Models sunorgamisedASE_finalised.pptChapter 2_Process Models sunorgamisedASE_finalised.ppt
Chapter 2_Process Models sunorgamisedASE_finalised.pptBule Hora University
 
Project Management Concepts
Project Management ConceptsProject Management Concepts
Project Management ConceptsSaqib Raza
 
Software project planning in software engineering by ram k paliwal unit 2
Software project planning in software engineering by ram k paliwal unit 2Software project planning in software engineering by ram k paliwal unit 2
Software project planning in software engineering by ram k paliwal unit 2Ram Paliwal
 
Unit iii(part d - component level design)
Unit   iii(part d - component level design)Unit   iii(part d - component level design)
Unit iii(part d - component level design)BALAJI A
 
TESTING STRATEGY.ppt
TESTING STRATEGY.pptTESTING STRATEGY.ppt
TESTING STRATEGY.pptFawazHussain4
 
Chapter 22- Software Configuration Management.ppt
Chapter 22- Software Configuration Management.pptChapter 22- Software Configuration Management.ppt
Chapter 22- Software Configuration Management.pptTanzinAhammad
 
Chapter 08
Chapter 08Chapter 08
Chapter 08guru3188
 
5- Requirement.ppt
5- Requirement.ppt5- Requirement.ppt
5- Requirement.pptssusera1c25a
 

Similar to estimation-for-software-projects-chapter-26-ppt.pptx (20)

005614116.pdf
005614116.pdf005614116.pdf
005614116.pdf
 
Chapter_25.ppt
Chapter_25.pptChapter_25.ppt
Chapter_25.ppt
 
SE CHAPTER 2 PROCESS MODELS
SE CHAPTER 2 PROCESS MODELSSE CHAPTER 2 PROCESS MODELS
SE CHAPTER 2 PROCESS MODELS
 
Process models
Process modelsProcess models
Process models
 
ch3.pptx
ch3.pptxch3.pptx
ch3.pptx
 
SE CHAPTER 1 SOFTWARE ENGINEERING
SE CHAPTER 1 SOFTWARE ENGINEERINGSE CHAPTER 1 SOFTWARE ENGINEERING
SE CHAPTER 1 SOFTWARE ENGINEERING
 
Software Engineering
Software Engineering Software Engineering
Software Engineering
 
Chapter 01 software engineering pressman
Chapter 01  software engineering pressmanChapter 01  software engineering pressman
Chapter 01 software engineering pressman
 
Chapter 03
Chapter 03Chapter 03
Chapter 03
 
Agile Development software engineering process model
Agile Development software engineering process modelAgile Development software engineering process model
Agile Development software engineering process model
 
Chapter_03.ppt
Chapter_03.pptChapter_03.ppt
Chapter_03.ppt
 
Chapter 2_Process Models sunorgamisedASE_finalised.ppt
Chapter 2_Process Models sunorgamisedASE_finalised.pptChapter 2_Process Models sunorgamisedASE_finalised.ppt
Chapter 2_Process Models sunorgamisedASE_finalised.ppt
 
Project Management Concepts
Project Management ConceptsProject Management Concepts
Project Management Concepts
 
Software project planning in software engineering by ram k paliwal unit 2
Software project planning in software engineering by ram k paliwal unit 2Software project planning in software engineering by ram k paliwal unit 2
Software project planning in software engineering by ram k paliwal unit 2
 
Unit iii(part d - component level design)
Unit   iii(part d - component level design)Unit   iii(part d - component level design)
Unit iii(part d - component level design)
 
TESTING STRATEGY.ppt
TESTING STRATEGY.pptTESTING STRATEGY.ppt
TESTING STRATEGY.ppt
 
Chapter 22- Software Configuration Management.ppt
Chapter 22- Software Configuration Management.pptChapter 22- Software Configuration Management.ppt
Chapter 22- Software Configuration Management.ppt
 
Chapter 08
Chapter 08Chapter 08
Chapter 08
 
Chapter_07.pptx
Chapter_07.pptxChapter_07.pptx
Chapter_07.pptx
 
5- Requirement.ppt
5- Requirement.ppt5- Requirement.ppt
5- Requirement.ppt
 

More from ubaidullah75790

vu-re-lecture-33 requirement engineering.ppt
vu-re-lecture-33 requirement engineering.pptvu-re-lecture-33 requirement engineering.ppt
vu-re-lecture-33 requirement engineering.pptubaidullah75790
 
Requirement management traceability.ppt
Requirement management  traceability.pptRequirement management  traceability.ppt
Requirement management traceability.pptubaidullah75790
 
SRS for banking system requirement engineer.ppt
SRS for banking system requirement engineer.pptSRS for banking system requirement engineer.ppt
SRS for banking system requirement engineer.pptubaidullah75790
 
Agile Method requirement engineering.ppt
Agile Method requirement engineering.pptAgile Method requirement engineering.ppt
Agile Method requirement engineering.pptubaidullah75790
 
traceabilty transport layer is liye .ppt
traceabilty transport layer is liye .ppttraceabilty transport layer is liye .ppt
traceabilty transport layer is liye .pptubaidullah75790
 
vu-re-lecture-45 requirement engineering.ppt
vu-re-lecture-45 requirement engineering.pptvu-re-lecture-45 requirement engineering.ppt
vu-re-lecture-45 requirement engineering.pptubaidullah75790
 
SRS for banking system requirement s.ppt
SRS for banking system requirement s.pptSRS for banking system requirement s.ppt
SRS for banking system requirement s.pptubaidullah75790
 
SRS 2 requiremenr engineering in computer.ppt
SRS 2 requiremenr engineering in computer.pptSRS 2 requiremenr engineering in computer.ppt
SRS 2 requiremenr engineering in computer.pptubaidullah75790
 
Requirments management traceability.ppt
Requirments  management traceability.pptRequirments  management traceability.ppt
Requirments management traceability.pptubaidullah75790
 
SRS 1 software requirement specificatio.ppt
SRS 1 software requirement specificatio.pptSRS 1 software requirement specificatio.ppt
SRS 1 software requirement specificatio.pptubaidullah75790
 
vu-re-lecture-10 requirement engineering.ppt
vu-re-lecture-10 requirement engineering.pptvu-re-lecture-10 requirement engineering.ppt
vu-re-lecture-10 requirement engineering.pptubaidullah75790
 
vu-re-lecture-09 engineering requiremen.ppt
vu-re-lecture-09 engineering requiremen.pptvu-re-lecture-09 engineering requiremen.ppt
vu-re-lecture-09 engineering requiremen.pptubaidullah75790
 
vu-re-lecture-08 requirement engineer.ppt
vu-re-lecture-08 requirement engineer.pptvu-re-lecture-08 requirement engineer.ppt
vu-re-lecture-08 requirement engineer.pptubaidullah75790
 
vu-re-lecture-06 requirement engineer.ppt
vu-re-lecture-06 requirement engineer.pptvu-re-lecture-06 requirement engineer.ppt
vu-re-lecture-06 requirement engineer.pptubaidullah75790
 
vu-re-lecture-05 requirement engineering.ppt
vu-re-lecture-05 requirement engineering.pptvu-re-lecture-05 requirement engineering.ppt
vu-re-lecture-05 requirement engineering.pptubaidullah75790
 
vu-re-lecture-04 software engineering.ppt
vu-re-lecture-04 software engineering.pptvu-re-lecture-04 software engineering.ppt
vu-re-lecture-04 software engineering.pptubaidullah75790
 
vu-re-lecture-03 requirement engineering.ppt
vu-re-lecture-03 requirement engineering.pptvu-re-lecture-03 requirement engineering.ppt
vu-re-lecture-03 requirement engineering.pptubaidullah75790
 
vu-re-lecture-02 requirements engineering.ppt
vu-re-lecture-02 requirements engineering.pptvu-re-lecture-02 requirements engineering.ppt
vu-re-lecture-02 requirements engineering.pptubaidullah75790
 
vu-re-lecture-01 software engineering.ppt
vu-re-lecture-01 software engineering.pptvu-re-lecture-01 software engineering.ppt
vu-re-lecture-01 software engineering.pptubaidullah75790
 
vu-re-lecture software requirement-25.ppt
vu-re-lecture software requirement-25.pptvu-re-lecture software requirement-25.ppt
vu-re-lecture software requirement-25.pptubaidullah75790
 

More from ubaidullah75790 (20)

vu-re-lecture-33 requirement engineering.ppt
vu-re-lecture-33 requirement engineering.pptvu-re-lecture-33 requirement engineering.ppt
vu-re-lecture-33 requirement engineering.ppt
 
Requirement management traceability.ppt
Requirement management  traceability.pptRequirement management  traceability.ppt
Requirement management traceability.ppt
 
SRS for banking system requirement engineer.ppt
SRS for banking system requirement engineer.pptSRS for banking system requirement engineer.ppt
SRS for banking system requirement engineer.ppt
 
Agile Method requirement engineering.ppt
Agile Method requirement engineering.pptAgile Method requirement engineering.ppt
Agile Method requirement engineering.ppt
 
traceabilty transport layer is liye .ppt
traceabilty transport layer is liye .ppttraceabilty transport layer is liye .ppt
traceabilty transport layer is liye .ppt
 
vu-re-lecture-45 requirement engineering.ppt
vu-re-lecture-45 requirement engineering.pptvu-re-lecture-45 requirement engineering.ppt
vu-re-lecture-45 requirement engineering.ppt
 
SRS for banking system requirement s.ppt
SRS for banking system requirement s.pptSRS for banking system requirement s.ppt
SRS for banking system requirement s.ppt
 
SRS 2 requiremenr engineering in computer.ppt
SRS 2 requiremenr engineering in computer.pptSRS 2 requiremenr engineering in computer.ppt
SRS 2 requiremenr engineering in computer.ppt
 
Requirments management traceability.ppt
Requirments  management traceability.pptRequirments  management traceability.ppt
Requirments management traceability.ppt
 
SRS 1 software requirement specificatio.ppt
SRS 1 software requirement specificatio.pptSRS 1 software requirement specificatio.ppt
SRS 1 software requirement specificatio.ppt
 
vu-re-lecture-10 requirement engineering.ppt
vu-re-lecture-10 requirement engineering.pptvu-re-lecture-10 requirement engineering.ppt
vu-re-lecture-10 requirement engineering.ppt
 
vu-re-lecture-09 engineering requiremen.ppt
vu-re-lecture-09 engineering requiremen.pptvu-re-lecture-09 engineering requiremen.ppt
vu-re-lecture-09 engineering requiremen.ppt
 
vu-re-lecture-08 requirement engineer.ppt
vu-re-lecture-08 requirement engineer.pptvu-re-lecture-08 requirement engineer.ppt
vu-re-lecture-08 requirement engineer.ppt
 
vu-re-lecture-06 requirement engineer.ppt
vu-re-lecture-06 requirement engineer.pptvu-re-lecture-06 requirement engineer.ppt
vu-re-lecture-06 requirement engineer.ppt
 
vu-re-lecture-05 requirement engineering.ppt
vu-re-lecture-05 requirement engineering.pptvu-re-lecture-05 requirement engineering.ppt
vu-re-lecture-05 requirement engineering.ppt
 
vu-re-lecture-04 software engineering.ppt
vu-re-lecture-04 software engineering.pptvu-re-lecture-04 software engineering.ppt
vu-re-lecture-04 software engineering.ppt
 
vu-re-lecture-03 requirement engineering.ppt
vu-re-lecture-03 requirement engineering.pptvu-re-lecture-03 requirement engineering.ppt
vu-re-lecture-03 requirement engineering.ppt
 
vu-re-lecture-02 requirements engineering.ppt
vu-re-lecture-02 requirements engineering.pptvu-re-lecture-02 requirements engineering.ppt
vu-re-lecture-02 requirements engineering.ppt
 
vu-re-lecture-01 software engineering.ppt
vu-re-lecture-01 software engineering.pptvu-re-lecture-01 software engineering.ppt
vu-re-lecture-01 software engineering.ppt
 
vu-re-lecture software requirement-25.ppt
vu-re-lecture software requirement-25.pptvu-re-lecture software requirement-25.ppt
vu-re-lecture software requirement-25.ppt
 

Recently uploaded

Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startQuintin Balsdon
 
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...HenryBriggs2
 
2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projectssmsksolar
 
kiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal loadkiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal loadhamedmustafa094
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VDineshKumar4165
 
Bridge Jacking Design Sample Calculation.pptx
Bridge Jacking Design Sample Calculation.pptxBridge Jacking Design Sample Calculation.pptx
Bridge Jacking Design Sample Calculation.pptxnuruddin69
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network DevicesChandrakantDivate1
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdfKamal Acharya
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaOmar Fathy
 
Learn the concepts of Thermodynamics on Magic Marks
Learn the concepts of Thermodynamics on Magic MarksLearn the concepts of Thermodynamics on Magic Marks
Learn the concepts of Thermodynamics on Magic MarksMagic Marks
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptxJIT KUMAR GUPTA
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdfKamal Acharya
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . pptDineshKumar4165
 
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxA CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxmaisarahman1
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptNANDHAKUMARA10
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwaitjaanualu31
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapRishantSharmaFr
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityMorshed Ahmed Rahath
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.Kamal Acharya
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsvanyagupta248
 

Recently uploaded (20)

Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
 
2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects
 
kiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal loadkiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal load
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
Bridge Jacking Design Sample Calculation.pptx
Bridge Jacking Design Sample Calculation.pptxBridge Jacking Design Sample Calculation.pptx
Bridge Jacking Design Sample Calculation.pptx
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network Devices
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
Learn the concepts of Thermodynamics on Magic Marks
Learn the concepts of Thermodynamics on Magic MarksLearn the concepts of Thermodynamics on Magic Marks
Learn the concepts of Thermodynamics on Magic Marks
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxA CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech students
 

estimation-for-software-projects-chapter-26-ppt.pptx

  • 1. Chapter 26 These slides are designed to accompany Software Engineering: A Practitioner’s Approach, 7/e (McGraw-Hill 2009). Slides copyright 2009 by Roger Pressman. 1  Estimation for Software Projects Slide Set to accompany Software Engineering: A Practitioner’s Approach, 7/e by Roger S. Pressman Slides copyright © 1996, 2001, 2005, 2009 by Roger S. Pressman For non-profit educational use only May be reproduced ONLY for student use at the university level when used in conjunction with Software Engineering: A Practitioner's Approach, 7/e. Any other reproduction or use is prohibited without the express written permission of the author. All copyright information MUST appear if these slides are posted on a website for student use.
  • 2. Software Project Planning The overall goal of project planning is to establish a pragmatic strategy for controlling, tracking, and monitoring a complex technical project. Why? So the end result gets done on time, with quality! These slides are designed to accompany Software Engineering: A Practitioner’s Approach, 7/e (McGraw-Hill 2009). Slides copyright 2009 by Roger Pressman. 2
  • 3. Project Planning Task Set-I These slides are designed to accompany Software Engineering: A Practitioner’s Approach, 7/e (McGraw-Hill 2009). Slides copyright 2009 by Roger Pressman. 3  Establish project scope  Determine feasibility  Analyze risks  Risk analysis is considered in detail in Chapter 25.  Define required resources  Determine require human resources  Define reusable software resources  Identify environmental resources
  • 4. Project Planning Task Set-II These slides are designed to accompany Software Engineering: A Practitioner’s Approach, 7/e (McGraw-Hill 2009). Slides copyright 2009 by Roger Pressman. 4  Estimate cost and effort  Decompose the problem  Develop two or more estimates using size, function points, process tasks or use-cases  Reconcile the estimates  Develop a project schedule  Scheduling is considered in detail in Chapter 27. • Establish a meaningful task set • Define a task network • Use scheduling tools to develop a timeline chart • Define schedule tracking mechanisms
  • 5. Estimation These slides are designed to accompany Software Engineering: A Practitioner’s Approach, 7/e (McGraw-Hill 2009). Slides copyright 2009 by Roger Pressman. 5  Estimation of resources, cost, and schedule for a software engineering effort requires  experience  access to good historical information (metrics)  the courage to commit to quantitative predictions when qualitative information is all that exists  Estimation carries inherent risk and this risk leads to uncertainty
  • 6. Write it Down! Software Project Plan Project Scope Estimates Risks Schedule Control strategy These slides are designed to accompany Software Engineering: A Practitioner’s Approach, 7/e (McGraw-Hill 2009). Slides copyright 2009 by Roger Pressman. 6
  • 7. To Understand Scope ...  Understand the customers needs  understand the business context  understand the project boundaries  understand the customer’s motivation  understand the likely paths for change  understand that ... Even when you understand, nothing is guaranteed! These slides are designed to accompany Software Engineering: A Practitioner’s Approach, 7/e (McGraw-Hill 2009). Slides copyright 2009 by Roger Pressman. 7
  • 8. What is Scope? These slides are designed to accompany Software Engineering: A Practitioner’s Approach, 7/e (McGraw-Hill 2009). Slides copyright 2009 by Roger Pressman. 8  Software scope describes  the functions and features that are to be delivered to end-users  the data that are input and output  the “content” that is presented to users as a consequence of using the software  the performance, constraints, interfaces, and reliability that bound the system.  Scope is defined using one of two techniques: • A narrative description of software scope is developed after communication with all stakeholders. • A set of use-cases is developed by end-users.
  • 9. Resources project These slides are designed to accompany Software Engineering: A Practitioner’s Approach, 7/e (McGraw-Hill 2009). Slides copyright 2009 by Roger Pressman. 9 people skills number location reusable softw are OTS components f ull-experience components new components part.-experience components environment hardware sof tware tools network resources
  • 10. Project Estimation  Project scope must be understood  Elaboration (decomposition) is necessary  Historical metrics are very helpful  At least two different techniques should be used  Uncertainty is inherent in the process These slides are designed to accompany Software Engineering: A Practitioner’s Approach, 7/e (McGraw-Hill 2009). Slides copyright 2009 by Roger Pressman. 10
  • 11. Estimation Techniques  Past (similar) project experience  Conventional estimation techniques  task breakdown and effort estimates  size (e.g., FP) estimates  Empirical models  Automated tools These slides are designed to accompany Software Engineering: A Practitioner’s Approach, 7/e (McGraw-Hill 2009). Slides copyright 2009 by Roger Pressman. 11
  • 12. Estimation Accuracy These slides are designed to accompany Software Engineering: A Practitioner’s Approach, 7/e (McGraw-Hill 2009). Slides copyright 2009 by Roger Pressman. 12  Predicated on …  the degree to which the planner has properly estimated the size of the product to be built  the ability to translate the size estimate into human effort, calendar time, and dollars (a function of the availability of reliable software metrics from past projects)  the degree to which the project plan reflects the abilities of the software team  the stability of product requirements and the environment that supports the software engineering effort.
  • 13. Functional Decomposition functional decomposition Statement of Scope Perform a Grammatical “parse” These slides are designed to accompany Software Engineering: A Practitioner’s Approach, 7/e (McGraw-Hill 2009). Slides copyright 2009 by Roger Pressman. 13
  • 14. Conventional Methods: LOC/FP Approach These slides are designed to accompany Software Engineering: A Practitioner’s Approach, 7/e (McGraw-Hill 2009). Slides copyright 2009 by Roger Pressman. 14  compute LOC/FP using estimates of information domain values  use historical data to build estimates for the project
  • 15. Example: LOC Approach Average productivity for systems of this type = 620 LOC/pm. Burdened labor rate =$8000 per month, the cost per line of code is approximately $13. Based on the LOC estimate and the historical productivity data, the total estimated project cost is $431,000 and the estimated effort is 54 person-months. These slides are designed to accompany Software Engineering: A Practitioner’s Approach, 7/e (McGraw-Hill 2009). Slides copyright 2009 by Roger Pressman. 15
  • 16. Example: FP Approach The estimated number of FP is derived: FPestimated = count-total 3 [0.65 + 0.01 3 S (Fi)] FPestimated = 375 organizational average productivity = 6.5 FP/pm. burdened labor rate = $8000 per month, approximately $1230/FP. Based on the FP estimate and the historical productivity data, total estimated project cost is $461,000 and estimated effort is 58 person-months. These slides are designed to accompany Software Engineering: A Practitioner’s Approach, 7/e (McGraw-Hill 2009). Slides copyright 2009 by Roger Pressman. 16
  • 17. Process-Based Estimation Obtained from “process framework” application functions framework activities Effort required to accomplish each framework activity for each application function These slides are designed to accompany Software Engineering: A Practitioner’s Approach, 7/e (McGraw-Hill 2009). Slides copyright 2009 by Roger Pressman. 17
  • 18. Process-Based Estimation Example Activity CC Planning Risk Engineering Construction CE Analysis Release Totals Task analysis design code test Functio n UICF 0.50 2.50 0.40 5.00 n/a 8.40 2DGA 0.75 4.00 0.60 2.00 n/a 7.35 3DGA 0.50 4.00 1.00 3.00 n/a 8.50 CGDF 0.50 3.00 1.00 1.50 n/a 6.00 DSM 0.50 3.00 0.75 1.50 n/a 5.75 PCF 0.25 2.00 0.50 1.50 n/a 4.25 DAM 0.50 2.00 0.50 2.00 n/a 5.00 Totals 0.25 0.25 0.25 3.50 20.50 4.50 16.50 46.00 % effort 1% 1% 1% 8% 45% 10% 36% CC = customer communication CE= customer evaluation Based on an average burdened labor rate of $8,000 per month, the total estimated project cost is $368,000 and the estimated effort is 46 person-months. These slides are designed to accompany Software Engineering: A Practitioner’s Approach, 7/e (McGraw-Hill 2009). Slides copyright 2009 by Roger Pressman. 18
  • 19. Tool-Based Estimation project characteristics calibration factors LOC/FP data These slides are designed to accompany Software Engineering: A Practitioner’s Approach, 7/e (McGraw-Hill 2009). Slides copyright 2009 by Roger Pressman. 19
  • 20. Estimation with Use-Cases use cases scenariospages Źscenarios pages 6 10 6 Ź 12 5 LOC LOCestimate 560 3,366 esubsystem subsystemgroup e subsystemgroup stimate 10 20 8 Ź 16 8 3100 31,233 5 6 5 Ź 10 6 1650 7,970 Ź Ź Ź Ź Ź Ź Ź Ź 42,568 Userinterface subsystem Engineering subsystemgroup Infrastructure subsystem group Total LOCestimate Using 620 LOC/pm as the average productivity for systems of this type and a burdened labor rate of $8000 per month, the cost per line of code is approximately $13. Based on the use- case estimate and the historical productivity data, the total estimated project cost is $552,000 and the estimated effort is 68 person-months. These slides are designed to accompany Software Engineering: A Practitioner’s Approach, 7/e (McGraw-Hill 2009). Slides copyright 2009 by Roger Pressman. 20
  • 21. Empirical Estimation Models General form: exponent effort = tuning coefficient * size usually derived as person-months of effort required either a constant or a number derived based on complexity of project usually LOC but may also be function point empirically derived These slides are designed to accompany Software Engineering: A Practitioner’s Approach, 7/e (McGraw-Hill 2009). Slides copyright 2009 by Roger Pressman. 21
  • 22. COCOMO-II These slides are designed to accompany Software Engineering: A Practitioner’s Approach, 7/e (McGraw-Hill 2009). Slides copyright 2009 by Roger Pressman. 22  COCOMO II is actually a hierarchy of estimation models that address the following areas: • Application composition model. Used during the early stages of software engineering, when prototyping of user interfaces, consideration of software and system interaction, assessment of performance, and evaluation of technology maturity are paramount. • Early design stage model. Used once requirements have been stabilized and basic software architecture has been established. • Post-architecture-stage model. Used during the construction of the software.
  • 23. The Software Equation A dynamic multivariable model E = [LOC x B0.333/P]3 x (1/t4) where E = effort in person-months or person-years t = project duration in months or years B = “special skills factor” P = “productivity parameter” These slides are designed to accompany Software Engineering: A Practitioner’s Approach, 7/e (McGraw-Hill 2009). Slides copyright 2009 by Roger Pressman. 23
  • 24. Estimation for OO Projects-I These slides are designed to accompany Software Engineering: A Practitioner’s Approach, 7/e (McGraw-Hill 2009). Slides copyright 2009 by Roger Pressman. 24  Develop estimates using effort decomposition, FP analysis, and any other method that is applicable for conventional applications.  Using object-oriented requirements modeling (Chapter 6), develop use-cases and determine a count.  From the analysis model, determine the number of key classes (called analysis classes in Chapter 6).  Categorize the type of interface for the application and develop a multiplier for support classes:  Interface type  No GUI  Text-based user interface  GUI  Complex GUI Multiplier 2.0 2.25 2.5 3.0
  • 25. Estimation for OO Projects-II These slides are designed to accompany Software Engineering: A Practitioner’s Approach, 7/e (McGraw-Hill 2009). Slides copyright 2009 by Roger Pressman. 25  Multiply the number of key classes (step 3) by the multiplier to obtain an estimate for the number of support classes.  Multiply the total number of classes (key + support) by the average number of work-units per class. Lorenz and Kidd suggest 15 to 20 person-days per class.  Cross check the class-based estimate by multiplying the average number of work-units per use-case
  • 26. Estimation for Agile Projects These slides are designed to accompany Software Engineering: A Practitioner’s Approach, 7/e (McGraw-Hill 2009). Slides copyright 2009 by Roger Pressman. 26  Each user scenario (a mini-use-case) is considered separately for estimation purposes.  The scenario is decomposed into the set of software engineering tasks that will be required to develop it.  Each task is estimated separately. Note: estimation can be based on historical data, an empirical model, or “experience.”  Alternatively, the ‘volume’ of the scenario can be estimated in LOC, FP or some other volume-oriented measure (e.g., use-case count).  Estimates for each task are summed to create an estimate for the scenario.  Alternatively, the volume estimate for the scenario is translated into effort using historical data.  The effort estimates for all scenarios that are to be implemented for a given software increment are summed to develop the effort estimate for the increment.
  • 27. The Make-Buy Decision These slides are designed to accompany Software Engineering: A Practitioner’s Approach, 7/e (McGraw-Hill 2009). Slides copyright 2009 by Roger Pressman. 27