SlideShare a Scribd company logo
1 of 12
PresenterPresenter
IntroductionIntroduction
ToTo
Project Life CycleProject Life Cycle
&&
PMSPMS
Vaibhav Sharma PMPVaibhav Sharma PMP
– Preferred global engineering Practices of excellence
Project Life CycleProject Life Cycle
Initiate
Plan
Execute
Monitor &
Control
Close Out
Formal
Initiation of
the project
Deliverable
List, Milestone
Identification.
Project
Execution as
per plan
Monitoring
Project
Progress as
per plan
Plan & Actual
records,
Lessons
Learnt
Timely Control
the Project
Measure / Monitor : Expenditures ? Or Work ?Measure / Monitor : Expenditures ? Or Work ?
Actual Cost / ` is not an indication of work progress, only anActual Cost / ` is not an indication of work progress, only an
indication of hours/money spent.indication of hours/money spent.
Well, I’ve spent 400 hrs ,
Does that mean I’ve
accomplished 400 hrs
of Work?
OutcomeOutcome
 Uniformity:
– Monitoring & Reporting Mechanism for all projects.
 Performance gauge:
– Project performance track & records Real Time:
– Instantaneous Progress Update as and when required.
 Optimized project execution:
– Progress monitoring against approved baseline plan, including
resources.
 Track Changes:
– Timely monitoring & alarming for upcoming changes in schedule
& resource requirements.
 Forecast:
– Lessons learnt utilization for future project estimates & execution.
PROJECT EXECUTION STRATEGYPROJECT EXECUTION STRATEGY
Q: Project Execution & Monitoring
Mechanism
A: PMS (Progress Measurement
System)
Key questions that PMS answersKey questions that PMS answers
Are we on schedule?
Are we on cost?
What are the significant variances?
Why do we have variances?
Who is responsible?
What is the trend to date?
Are we on schedule?
Are we on cost?
What are the significant variances?
Why do we have variances?
Who is responsible?
What is the trend to date?
When will we finish?
What will it cost at the end?
How can we control the trend?
When will we finish?
What will it cost at the end?
How can we control the trend?
We analyze past performance………to help us control the future
PAST PRESENT FUTURE
1. Did we get what we wanted for what we spent?
2. At the end of the project, is it likely that the cost will be
less than or equal to the original estimate?
The Two Key
Questions
Road to growthRoad to growth
• Can identify slipping project schedule
or cost deviation
• We can track near real-time delivery
against the plan (Schedule)
• Senior management can view
performance of a live project at any
instant without wait.
• We can have more control over early
detection of schedule & cost deviation
because you can accurately see
when & where deviation is trending
against your baseline
Step 1
Step 3
Step 5
Step 4
Step 2
5 steps for PMS5 steps for PMS
BAC-Budget at completion
PV-Planned value
AC-Actual cost
EV-Earn value
EVM-Earn value
management
Estimate / Budget (BAC)
PV
AC
EV
EVM
Key Focus areasKey Focus areas
Plan the Work
Work the Plan
Lessons
Learnt
Collect Results
Define the Work
Analyze
Deviations
Take
Corrective Action
Take
Corrective Action
Measure
Performance
Close Project
PMS Tool OptionsPMS Tool Options
Tools Advantages Disadvantages
Excel • Low cost • Time consuming
• Suitable for small projects
MS Project • Familiar business
product.
• Built-in EVM
system.
• Detailed plans above 200 lines can be complex to
manage.
• Can be unreliable & time consuming
• No collaboration & automation
MS Project &
MS
Sharepoint
• Familiarity + EVM
• Collaboration
• Low up front cost
• Automation Avail:
• Requires an integrator to set-up a MOSS site to the
right level
• Partial Integration
PPM Tools
•Clarity
•Planview
• Rich feature set
• Fully automated
• High purchase price + excluding year on year running
costs.
• ROI can be hard to justify
BenefitsBenefits
 Provides advanced warning of cost and schedule overruns
 Enables preventative measures and/or corrective actions to be
undertaken at the earliest signs of project deviation.
 Provides a mechanism to monitor the performance of suppliers and
their staff in near real time.
 Provides a direct link between budgets, plans, resources and delivery.
 Provides statistics to stakeholders and steering groups showing past,
current and predicted performance
 Enhances management visibility, allowing you to drill down into a
portfolio of projects & tasks to retrieve statistics, that can be measured
against a baseline
 Provides a management reporting methodology that encourages
delegation and an exception based management style. Reduces Micro
Management.
Thank you !Thank you !

More Related Content

What's hot

Iso 9001 internal audit tips
Iso 9001 internal audit tipsIso 9001 internal audit tips
Iso 9001 internal audit tipsBaptist Molai
 
ISO 9001 2015 | Management Reviews | The Five Rules To Business Excellence
ISO 9001 2015 | Management Reviews | The Five Rules To Business ExcellenceISO 9001 2015 | Management Reviews | The Five Rules To Business Excellence
ISO 9001 2015 | Management Reviews | The Five Rules To Business ExcellenceAndre Barnarde
 
Iso 9001 2015 audit checklist
Iso 9001 2015 audit checklistIso 9001 2015 audit checklist
Iso 9001 2015 audit checklistHamid Ali
 
Management review format
Management review formatManagement review format
Management review formatcrazy_hornet
 
Iso 9001:2015 internal auditor Course
Iso 9001:2015  internal auditor Course Iso 9001:2015  internal auditor Course
Iso 9001:2015 internal auditor Course Atif Alhaj
 
Internal Process Audit
Internal Process AuditInternal Process Audit
Internal Process Auditintellisenseit
 
Internal Audit 03-03-16
Internal Audit 03-03-16Internal Audit 03-03-16
Internal Audit 03-03-16Lisa Barnes
 
ISO 9001:2008 Internal Auditing of Quality Management Systems - Introduction
ISO 9001:2008 Internal Auditing of Quality Management Systems - IntroductionISO 9001:2008 Internal Auditing of Quality Management Systems - Introduction
ISO 9001:2008 Internal Auditing of Quality Management Systems - IntroductionKanriConsulting
 
Qms auditing powerpoint
Qms auditing powerpointQms auditing powerpoint
Qms auditing powerpointPat Kilbane
 
Iso 9001:2015 Documented Information Guidance
Iso 9001:2015 Documented Information GuidanceIso 9001:2015 Documented Information Guidance
Iso 9001:2015 Documented Information GuidanceMohammad Elshahat
 
Iso Process Audit Training
Iso Process Audit TrainingIso Process Audit Training
Iso Process Audit Trainingsrmortensen
 
Conducting management review1
Conducting management review1Conducting management review1
Conducting management review1mdt77777
 
Risk elimination and safety committee
Risk elimination and safety committeeRisk elimination and safety committee
Risk elimination and safety committeeHpm India
 
Audit iso 9001-2015-checklist-
Audit iso 9001-2015-checklist-Audit iso 9001-2015-checklist-
Audit iso 9001-2015-checklist-Anand Vedpathak
 
ISO 9001 Training | QMS Training | ISO 9001 Internal Auditor Training
ISO 9001 Training | QMS Training | ISO 9001 Internal Auditor TrainingISO 9001 Training | QMS Training | ISO 9001 Internal Auditor Training
ISO 9001 Training | QMS Training | ISO 9001 Internal Auditor Traininghimalya sharma
 
7 Questions to Ask When Auditing Your Customer Success Processes
7 Questions to Ask When Auditing Your Customer Success Processes 7 Questions to Ask When Auditing Your Customer Success Processes
7 Questions to Ask When Auditing Your Customer Success Processes LizzyManz
 

What's hot (20)

Iso 9001 internal audit tips
Iso 9001 internal audit tipsIso 9001 internal audit tips
Iso 9001 internal audit tips
 
ISO 9001 2015 | Management Reviews | The Five Rules To Business Excellence
ISO 9001 2015 | Management Reviews | The Five Rules To Business ExcellenceISO 9001 2015 | Management Reviews | The Five Rules To Business Excellence
ISO 9001 2015 | Management Reviews | The Five Rules To Business Excellence
 
Iso 9001 2015 audit checklist
Iso 9001 2015 audit checklistIso 9001 2015 audit checklist
Iso 9001 2015 audit checklist
 
Audit General
Audit GeneralAudit General
Audit General
 
QMS Audit Process June 2015
QMS Audit Process June 2015QMS Audit Process June 2015
QMS Audit Process June 2015
 
Management review format
Management review formatManagement review format
Management review format
 
Iso 9001:2015 internal auditor Course
Iso 9001:2015  internal auditor Course Iso 9001:2015  internal auditor Course
Iso 9001:2015 internal auditor Course
 
Internal Process Audit
Internal Process AuditInternal Process Audit
Internal Process Audit
 
Internal Audit 03-03-16
Internal Audit 03-03-16Internal Audit 03-03-16
Internal Audit 03-03-16
 
ISO 9001:2008 Internal Auditing of Quality Management Systems - Introduction
ISO 9001:2008 Internal Auditing of Quality Management Systems - IntroductionISO 9001:2008 Internal Auditing of Quality Management Systems - Introduction
ISO 9001:2008 Internal Auditing of Quality Management Systems - Introduction
 
Practical auditing
Practical auditingPractical auditing
Practical auditing
 
Introduction to Internal Auditing FSMS
Introduction to Internal Auditing FSMSIntroduction to Internal Auditing FSMS
Introduction to Internal Auditing FSMS
 
Qms auditing powerpoint
Qms auditing powerpointQms auditing powerpoint
Qms auditing powerpoint
 
Iso 9001:2015 Documented Information Guidance
Iso 9001:2015 Documented Information GuidanceIso 9001:2015 Documented Information Guidance
Iso 9001:2015 Documented Information Guidance
 
Iso Process Audit Training
Iso Process Audit TrainingIso Process Audit Training
Iso Process Audit Training
 
Conducting management review1
Conducting management review1Conducting management review1
Conducting management review1
 
Risk elimination and safety committee
Risk elimination and safety committeeRisk elimination and safety committee
Risk elimination and safety committee
 
Audit iso 9001-2015-checklist-
Audit iso 9001-2015-checklist-Audit iso 9001-2015-checklist-
Audit iso 9001-2015-checklist-
 
ISO 9001 Training | QMS Training | ISO 9001 Internal Auditor Training
ISO 9001 Training | QMS Training | ISO 9001 Internal Auditor TrainingISO 9001 Training | QMS Training | ISO 9001 Internal Auditor Training
ISO 9001 Training | QMS Training | ISO 9001 Internal Auditor Training
 
7 Questions to Ask When Auditing Your Customer Success Processes
7 Questions to Ask When Auditing Your Customer Success Processes 7 Questions to Ask When Auditing Your Customer Success Processes
7 Questions to Ask When Auditing Your Customer Success Processes
 

Similar to Webinar on PMS

Chap05_Project Monitoring and Control.pdf
Chap05_Project Monitoring and Control.pdfChap05_Project Monitoring and Control.pdf
Chap05_Project Monitoring and Control.pdfVarunSubramanyam
 
The Business of Projects
The Business of ProjectsThe Business of Projects
The Business of ProjectsUnanet
 
Monitoring and information systems
Monitoring and information systemsMonitoring and information systems
Monitoring and information systemsLibra chudry
 
07 projectcostmanagement
07 projectcostmanagement07 projectcostmanagement
07 projectcostmanagementDhamo daran
 
2.11 Milestone Review - Phase 1.ppt
2.11 Milestone Review - Phase 1.ppt2.11 Milestone Review - Phase 1.ppt
2.11 Milestone Review - Phase 1.pptAlfredoArturoGranado
 
Chapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptxChapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptxssusercf695b
 
Project Management.pptx
Project Management.pptxProject Management.pptx
Project Management.pptxYogesh Singh
 
Mitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueMitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueChris Carson
 
Schedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueSchedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueChris Carson
 
Mba ii pmom_unit-4.1 project management a
Mba ii pmom_unit-4.1 project management aMba ii pmom_unit-4.1 project management a
Mba ii pmom_unit-4.1 project management aRai University
 
The Project Management Process - Week 9 Performance Management
The Project Management Process - Week 9   Performance ManagementThe Project Management Process - Week 9   Performance Management
The Project Management Process - Week 9 Performance ManagementCraig Brown
 
iEVM (Integrated Earned Value Management) An approach for integrating quality...
iEVM (Integrated Earned Value Management) An approach for integrating quality...iEVM (Integrated Earned Value Management) An approach for integrating quality...
iEVM (Integrated Earned Value Management) An approach for integrating quality...IRJET Journal
 
Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement ignitetribes
 
Introduction to Earned Value Management
Introduction to Earned Value ManagementIntroduction to Earned Value Management
Introduction to Earned Value ManagementUnanet
 
271710575-Lecture-14-Project-Monitoring.ppt
271710575-Lecture-14-Project-Monitoring.ppt271710575-Lecture-14-Project-Monitoring.ppt
271710575-Lecture-14-Project-Monitoring.pptMohd Zulhairi Mohd Noor
 
Monitor and control process group part two
Monitor and control process group part twoMonitor and control process group part two
Monitor and control process group part twoHossam Maghrabi
 
Promaxpmc Presentation 1
Promaxpmc Presentation 1Promaxpmc Presentation 1
Promaxpmc Presentation 1sbalagem
 
Using Earned Value Management Concepts to Improve Commercial Project Performance
Using Earned Value Management Concepts to Improve Commercial Project PerformanceUsing Earned Value Management Concepts to Improve Commercial Project Performance
Using Earned Value Management Concepts to Improve Commercial Project PerformanceLewisFowlerLLC
 

Similar to Webinar on PMS (20)

Chap05_Project Monitoring and Control.pdf
Chap05_Project Monitoring and Control.pdfChap05_Project Monitoring and Control.pdf
Chap05_Project Monitoring and Control.pdf
 
The Business of Projects
The Business of ProjectsThe Business of Projects
The Business of Projects
 
T24 Temenos Earned Value Management & Project Planning Presentation
T24 Temenos Earned Value Management & Project Planning PresentationT24 Temenos Earned Value Management & Project Planning Presentation
T24 Temenos Earned Value Management & Project Planning Presentation
 
Monitoring and information systems
Monitoring and information systemsMonitoring and information systems
Monitoring and information systems
 
07 projectcostmanagement
07 projectcostmanagement07 projectcostmanagement
07 projectcostmanagement
 
2.11 Milestone Review - Phase 1.ppt
2.11 Milestone Review - Phase 1.ppt2.11 Milestone Review - Phase 1.ppt
2.11 Milestone Review - Phase 1.ppt
 
Chapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptxChapter 3 Project Cost Control and Monitoring.pptx
Chapter 3 Project Cost Control and Monitoring.pptx
 
Project Management.pptx
Project Management.pptxProject Management.pptx
Project Management.pptx
 
Mitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueMitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned Value
 
Schedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueSchedule Recovery Using Earned Value
Schedule Recovery Using Earned Value
 
Mba ii pmom_unit-4.1 project management a
Mba ii pmom_unit-4.1 project management aMba ii pmom_unit-4.1 project management a
Mba ii pmom_unit-4.1 project management a
 
The Project Management Process - Week 9 Performance Management
The Project Management Process - Week 9   Performance ManagementThe Project Management Process - Week 9   Performance Management
The Project Management Process - Week 9 Performance Management
 
iEVM (Integrated Earned Value Management) An approach for integrating quality...
iEVM (Integrated Earned Value Management) An approach for integrating quality...iEVM (Integrated Earned Value Management) An approach for integrating quality...
iEVM (Integrated Earned Value Management) An approach for integrating quality...
 
Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement
 
Introduction to Earned Value Management
Introduction to Earned Value ManagementIntroduction to Earned Value Management
Introduction to Earned Value Management
 
formation.docx
formation.docxformation.docx
formation.docx
 
271710575-Lecture-14-Project-Monitoring.ppt
271710575-Lecture-14-Project-Monitoring.ppt271710575-Lecture-14-Project-Monitoring.ppt
271710575-Lecture-14-Project-Monitoring.ppt
 
Monitor and control process group part two
Monitor and control process group part twoMonitor and control process group part two
Monitor and control process group part two
 
Promaxpmc Presentation 1
Promaxpmc Presentation 1Promaxpmc Presentation 1
Promaxpmc Presentation 1
 
Using Earned Value Management Concepts to Improve Commercial Project Performance
Using Earned Value Management Concepts to Improve Commercial Project PerformanceUsing Earned Value Management Concepts to Improve Commercial Project Performance
Using Earned Value Management Concepts to Improve Commercial Project Performance
 

Recently uploaded

The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyEthan lee
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Roland Driesen
 
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxB.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxpriyanshujha201
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxAndy Lambert
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒anilsa9823
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...Paul Menig
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Lviv Startup Club
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Servicediscovermytutordmt
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Neil Kimberley
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...Aggregage
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfAdmir Softic
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with CultureSeta Wicaksana
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMRavindra Nath Shukla
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Dipal Arora
 
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...amitlee9823
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableDipal Arora
 
RSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataRSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataExhibitors Data
 
Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Roland Driesen
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxWorkforce Group
 

Recently uploaded (20)

The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...
 
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxB.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
 
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptx
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Service
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with Culture
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSM
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
 
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
 
RSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataRSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors Data
 
Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptx
 

Webinar on PMS

  • 1. PresenterPresenter IntroductionIntroduction ToTo Project Life CycleProject Life Cycle && PMSPMS Vaibhav Sharma PMPVaibhav Sharma PMP
  • 2. – Preferred global engineering Practices of excellence Project Life CycleProject Life Cycle Initiate Plan Execute Monitor & Control Close Out Formal Initiation of the project Deliverable List, Milestone Identification. Project Execution as per plan Monitoring Project Progress as per plan Plan & Actual records, Lessons Learnt Timely Control the Project
  • 3. Measure / Monitor : Expenditures ? Or Work ?Measure / Monitor : Expenditures ? Or Work ? Actual Cost / ` is not an indication of work progress, only anActual Cost / ` is not an indication of work progress, only an indication of hours/money spent.indication of hours/money spent. Well, I’ve spent 400 hrs , Does that mean I’ve accomplished 400 hrs of Work?
  • 4. OutcomeOutcome  Uniformity: – Monitoring & Reporting Mechanism for all projects.  Performance gauge: – Project performance track & records Real Time: – Instantaneous Progress Update as and when required.  Optimized project execution: – Progress monitoring against approved baseline plan, including resources.  Track Changes: – Timely monitoring & alarming for upcoming changes in schedule & resource requirements.  Forecast: – Lessons learnt utilization for future project estimates & execution.
  • 5. PROJECT EXECUTION STRATEGYPROJECT EXECUTION STRATEGY Q: Project Execution & Monitoring Mechanism A: PMS (Progress Measurement System)
  • 6. Key questions that PMS answersKey questions that PMS answers Are we on schedule? Are we on cost? What are the significant variances? Why do we have variances? Who is responsible? What is the trend to date? Are we on schedule? Are we on cost? What are the significant variances? Why do we have variances? Who is responsible? What is the trend to date? When will we finish? What will it cost at the end? How can we control the trend? When will we finish? What will it cost at the end? How can we control the trend? We analyze past performance………to help us control the future PAST PRESENT FUTURE 1. Did we get what we wanted for what we spent? 2. At the end of the project, is it likely that the cost will be less than or equal to the original estimate? The Two Key Questions
  • 7. Road to growthRoad to growth • Can identify slipping project schedule or cost deviation • We can track near real-time delivery against the plan (Schedule) • Senior management can view performance of a live project at any instant without wait. • We can have more control over early detection of schedule & cost deviation because you can accurately see when & where deviation is trending against your baseline
  • 8. Step 1 Step 3 Step 5 Step 4 Step 2 5 steps for PMS5 steps for PMS BAC-Budget at completion PV-Planned value AC-Actual cost EV-Earn value EVM-Earn value management Estimate / Budget (BAC) PV AC EV EVM
  • 9. Key Focus areasKey Focus areas Plan the Work Work the Plan Lessons Learnt Collect Results Define the Work Analyze Deviations Take Corrective Action Take Corrective Action Measure Performance Close Project
  • 10. PMS Tool OptionsPMS Tool Options Tools Advantages Disadvantages Excel • Low cost • Time consuming • Suitable for small projects MS Project • Familiar business product. • Built-in EVM system. • Detailed plans above 200 lines can be complex to manage. • Can be unreliable & time consuming • No collaboration & automation MS Project & MS Sharepoint • Familiarity + EVM • Collaboration • Low up front cost • Automation Avail: • Requires an integrator to set-up a MOSS site to the right level • Partial Integration PPM Tools •Clarity •Planview • Rich feature set • Fully automated • High purchase price + excluding year on year running costs. • ROI can be hard to justify
  • 11. BenefitsBenefits  Provides advanced warning of cost and schedule overruns  Enables preventative measures and/or corrective actions to be undertaken at the earliest signs of project deviation.  Provides a mechanism to monitor the performance of suppliers and their staff in near real time.  Provides a direct link between budgets, plans, resources and delivery.  Provides statistics to stakeholders and steering groups showing past, current and predicted performance  Enhances management visibility, allowing you to drill down into a portfolio of projects & tasks to retrieve statistics, that can be measured against a baseline  Provides a management reporting methodology that encourages delegation and an exception based management style. Reduces Micro Management.

Editor's Notes

  1. Keywords: Steps, Goal, achievement, process