SlideShare une entreprise Scribd logo
1  sur  53
Secondary Selective Substation
Transfer Scheme
April 2013
Industrial Power System Design
Presentation Outline
• Definition – Secondary Selective Substation
• Equipment Arrangement
• Discussion Topics – How do you design a
transfer scheme?
• Existing System Description
 Normal System Loading
 Abnormal System Loading
• Final System Configuration
• Transfer Scheme Definitions
• Implementation
Definition
Secondary Selective Substation
• Substations having two busses, each supplied by a
normally-closed incoming line circuit breaker and
connected together by a normally-open bus tie
circuit breaker.
Single Tie Arrangement
Double Tie Arrangement
Discussion Topics
How do you design a transfer scheme?
• What conditions are required for transfer?
 Breaker positions?
 Breaker status?
 Voltage conditions?
 Make before break or break before make?
 Do we need to know about one side or both sides of
switchgear to initiate transfer?
 Flow Chart, Logic Chart or if then statements?
• What is the equipment arrangement?
 Where are current transformers going to be placed? Why?
 Where are potential transformers going to be placed? Why?
Discussion Topics
How do you design a transfer scheme?
• Safety concerns?
 Electrical protection requirements?
 Re-energizing bus with fault present?
 What do I do with downstream power sources (i.e.
generators or synchronous motors)?
 Sources synchronized? How do you know?
• Motor spin down complete
• How will the system be implemented?
 Mechanical relays/hardwired
 Electronic relays/hardwired
 Electronic relays/communication
Discussion Topics
How do you design a transfer scheme?
• How do you recover from automatic transfer?
 Automatic or Manual?
• If electronic relays, which ones?
 Pros and Cons for each
 Do you want to program the scheme or do you want to
work within an existing framework?
 Typical: SEL or MULTILIN
 Does one give you an advantage in terms of end of
project paperwork?
 Will final implementation be “black box” approach or will
there be certain outputs that can be checked to tell you
where you are in the transfer initiation by technician?
Discussion Topics
How do you design a transfer scheme?
• Communication between team members?
 No two engineers will design the system the same way.
 What are common assumptions?
• Single mode of failure or multiple?
• Will additional failure modes be handled with internal
programming or procedural changes to the operation
of the equipment.
• What ranges or setpoints will be utilized? Why?
• What requires an alarm to be sent?
• What requires the automatic system to be disabled?
Discussion Topics
How do you design a transfer scheme?
• How do you test the system?
 What equipment is needed?
 If doors are stand alone
• Where do you test the system?
 Factory
 Office/Lab
 In the field
• Who should be involved in final testing?
• Who decides on final testing methodology?
Discussion Topics
How do you design a transfer scheme?
• How do you know if your system is working properly?
• Maintenance
 What needs to be done on a periodic basis?
• Software updates, how do they effect the current system?
• Who maintains programming files?
• Standard breaker maintenance and time testing?
• Relay testing to validate accuracy?
• Training
 Who gets trained?
 What material is provided to make that individual
successful?
52-A 52-B
52-T
50P/N,
51P/N,
25, 27
51P/N,
25, 27
PT-1
PT-2 PT-4
PT-3
50P/N,
51P/N,
25, 27
Single Tie Arrangement
52-A 52-B
52-T
50P/N,
51P/N,
25, 27
PT-1 PT-350P/N,
51P/N,
25, 27
Single Tie Arrangement
Flow Chart
Flow Chart
Flow Chart
One-Line
Depiction
• 27I-1, 27I-2 Instantantaneous under voltage relay
• 27R-1, 27R-2 Residual voltage relay, 3 phase
• 50/51-1, 2 Instantaneous and time overcrurrent relay
• 50N/51N-1, 2 Residually connected instantaneous and time overcurrent relay
• 51G-1, 2 Transformer X0 connection overcurrent relay
One-Line
Depiction
• 63 - Transformer fault pressure relay, rate-of-rise type or Buchholz relay
• 63X - Auxiliary seal in relay
• 86T- Hand reset transformer lockout relay
• 25- Synchronism check relay
One-Line
Depiction
• 27I Relays 27I prevent an automatic transfer from occurring upon simultaneous
loss of both sources, or loss of one source and low voltage on the other.
Relays 27I operate through auxiliary relay 96. Because relays 96 are time
delay type, an automatic transfer is also prevented upon simultaneous
restoration of both sources after a double outage. Relays 27I also seal in
relays 97 to prevent transfer if the supply breaker should trip first on
overcurrent faults in the secondary selective substation.
Main Breaker Schematic
27I Relays 27I prevent an automatic transfer from occurring upon simultaneous
loss of both sources, or loss of one source and low voltage on the other.
Relays 27I operate through auxiliary relay 96. Because relays 96 are time
delay type, an automatic transfer is also prevented upon simultaneous
restoration of both sources after a double outage. Relays 27I also seal in
relays 97 to prevent transfer if the supply breaker should trip first on
overcurrent faults in the secondary selective substation.
Main Breaker Schematic
50/50N Relays 50 and 50N operate through the 97 relay, and are used to
block transfer during overcurrent faults until the fault is cleared by
the feeder breaker or incoming line breaker. When the settings are
properly set they permit relay 27 to time out faster under fault
conditions. The backup to this scheme includes time
current/voltage coordination between the 51 overcurrent relay and
the 27 undervoltage relay. The 51 relay should trip before the 27
sends the tripping signal.
Main Breaker Schematic
•83- Auxiliary relay used in the transfer initiation from the main breaker to
the tie breaker via the following functions:
Trips the main breaker
Closes the tie once the main breaker opens, and the bus voltage is
25% of it nominal value to prevent out of phase re-closer
Main Breaker Schematic
• Auxiliary relay, instantaneous pickup, adjustable time delay drop out
TDDO- time delay dropout,
TDC- time delay closing,
TDO-time delay opening
Main Breaker Schematic
• 52LS-1 contact closes when incomer No. 1 is in the racked in position.
• 52LS-2 contact closes when incomer No. 2 is in the racked in position.
• 24LS contact closes when the tie breaker is in the racked in position.
• 52-2/a contact closes when incomer No. 2 breaker is closed.
• 10 trip selector switch used in manual transfers.
Main Breaker Schematic
• 24/a contact closes when the tie breaker is closed.
• 52-1/a contact closes when incomer No. 1 breaker is closed.
• 96-1/TDC blocks the automatic transfer if the incomer No. 2 bus voltage is not
healthy.
• 97-1/TDC blocks the automatic transfer if the 50 instantaneous current relay
detects flow of fault current. The block doesn't clear until the 50 relay
clears and there is no longer a depressed undervoltage condition
caused by the fault condition.
Main Breaker Schematic
• 24/b breaks the transfer system seal in rung when the tie breaker closes.
• 83-1 auxiliary relay that initiates the automatic transfer.
Tie Breaker Schematic
24LS
D-C BUS NO.3
(+)
8-T
27R-1 27R-2
24CS
C 83-1 83-2
52-1
b
52-2
b
24
b
(1)
52LS-1 (4)
52LS-2 (4)
10
T
52-1
a
52-2
a
(4)
(4)
24CS
TRLGL
(8)
(8)
(8) 24
a
24
TC
(1)
24
CC
(-)
8-T D-C BUS NO.3
25Y (2)
27R Relays protect the motors which carry through automatic transfer, against
overvoltage and instantaneous tripping of their circuit breakers due to
closing in out of phase with residual voltage. Protection is achieved by
delaying transfer until residual voltage drops to a safe level. Motors will
generate a decaying residual voltage if source power is interrupted under
load with no fault to dissipate magnetic energy stored in the motors.
Tie Breaker Schematic
24LS
D-C BUS NO.3
(+)
8-T
27R-1 27R-2
24CS
C 83-1 83-2
52-1
b
52-2
b
24
b
(1)
52LS-1 (4)
52LS-2 (4)
10
T
52-1
a
52-2
a
(4)
(4)
24CS
TRLGL
(8)
(8)
(8) 24
a
24
TC
(1)
24
CC
(-)
8-T D-C BUS NO.3
25Y (2)
27R-1 contact closes when the residual bus voltage decays to 25% of
the rated bus voltage in order to prevent an out of phase
reclosure between the motor back emf and the new source
voltage when the tie breaker is closed.
Normal Operating Condition
SCE Owned/
Operated
XOM Owned/
Operated
Cable Capacity
Transformer Capacity
Switchgear Capacity
18
Air Cooled
Fan Cooled
15
22.4
Power
MVA
21.6
Normal Load 12.5 MVA Normal Load 15.5 MVA
Cable Capacity
Transformer Capacity
Air Cooled
Fan Cooled
Switchgear Capacity
18
Power
MVA
15
22.4
21.6
Normal
Flow
Normal
Flow
12.5 MVA 15.5 MVA
Percent Capacity
Utilized
86
103
69
72
Total Load 28 MVA
Breaker Open
Breaker Closed Breaker Closed
69
83
56
58
Percent Capacity
Utilized
Bus 1 Bus 2
Abnormal Operating Condition
SCE Owned/
Operated
XOM Owned/
Operated
Cable Capacity
Transformer Capacity
Switchgear Capacity
18
Air Cooled
Fan Cooled
15
22.4
Power
MVA
21.6
Normal Load 12.5 MVA Normal Load 15.5 MVA
Cable Out of Service
Transformer Out of Service
Switchgear Breaker Out of Service
Abnormal
Flow
Abnormal
Flow
0 MVA 28 MVA
Percent Capacity
Utilized
156
187
123
130
Total Load 28 MVA
Breaker Closed
Breaker Closed
Breaker Open
Bus 1 Bus 2
Final System Logic Diagrams
Final System Logic Diagrams
Final System Logic Diagrams
Final System Logic Diagrams
Final System Logic Diagrams
Final System Logic Diagrams
Final System Logic Diagrams
Final System Logic Diagrams
Final System Logic Diagrams
Final System Logic Diagrams
Final System Logic Diagrams
Final System Logic Diagrams
Final System Logic Diagrams
Final System Logic Diagrams
Final Discussion
End Transfer Schemes

Contenu connexe

Tendances

presentation on substation layout and BUS bar arrangement.
presentation on substation layout and BUS bar arrangement.presentation on substation layout and BUS bar arrangement.
presentation on substation layout and BUS bar arrangement.Hemendra Kumar Rajput
 
“STUDY OF THE PROTECTIVE EQUIPMENTS OF A SUBSTATION AND POWER FACTOR IMPROVEM...
“STUDY OF THE PROTECTIVE EQUIPMENTS OF A SUBSTATION AND POWER FACTOR IMPROVEM...“STUDY OF THE PROTECTIVE EQUIPMENTS OF A SUBSTATION AND POWER FACTOR IMPROVEM...
“STUDY OF THE PROTECTIVE EQUIPMENTS OF A SUBSTATION AND POWER FACTOR IMPROVEM...rohit nadella
 
Distribution boards and Protection devices ppt
Distribution boards and Protection devices  pptDistribution boards and Protection devices  ppt
Distribution boards and Protection devices pptZuhairQadri
 
Practical handbook-for-relay-protection-engineers
Practical handbook-for-relay-protection-engineersPractical handbook-for-relay-protection-engineers
Practical handbook-for-relay-protection-engineersSARAVANAN A
 
Tutorial on Distance and Over Current Protection
Tutorial on Distance and Over  Current ProtectionTutorial on Distance and Over  Current Protection
Tutorial on Distance and Over Current ProtectionSARAVANAN A
 
protection of transmission lines[distance relay protection scheme]
protection of transmission lines[distance relay protection scheme]protection of transmission lines[distance relay protection scheme]
protection of transmission lines[distance relay protection scheme]moiz89
 
Protection schemes and zones
Protection schemes and zonesProtection schemes and zones
Protection schemes and zonesSlides Hub
 
Protection Of Generator
Protection Of GeneratorProtection Of Generator
Protection Of GeneratorRahuldey1991
 
Power system protection
Power system protectionPower system protection
Power system protectionAnu Priya
 
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)ABB - TRANSFORMERS-PROTECTION-COURSE (2001)
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)J. FR
 
transformer protection
transformer protection transformer protection
transformer protection jason adidela
 
132 33kv substation documentation
132 33kv substation documentation132 33kv substation documentation
132 33kv substation documentationRajashekar Gurrala
 
Equipments of power transmission
Equipments of power transmissionEquipments of power transmission
Equipments of power transmissionRasika Ghongade
 
Power system-protection-presentation-dated-03-10-2013-integrated-protection-c...
Power system-protection-presentation-dated-03-10-2013-integrated-protection-c...Power system-protection-presentation-dated-03-10-2013-integrated-protection-c...
Power system-protection-presentation-dated-03-10-2013-integrated-protection-c...jbpatel7290
 
Generator protection LEC 2
Generator protection  LEC 2Generator protection  LEC 2
Generator protection LEC 2Rahaf Waheep
 
Power Transformer Differential protection
Power Transformer Differential protectionPower Transformer Differential protection
Power Transformer Differential protectionRishi Tandon
 

Tendances (20)

presentation on substation layout and BUS bar arrangement.
presentation on substation layout and BUS bar arrangement.presentation on substation layout and BUS bar arrangement.
presentation on substation layout and BUS bar arrangement.
 
BUS BAR PROTECTION PPT BY:-R.K.PANDIT
BUS BAR  PROTECTION PPT BY:-R.K.PANDITBUS BAR  PROTECTION PPT BY:-R.K.PANDIT
BUS BAR PROTECTION PPT BY:-R.K.PANDIT
 
“STUDY OF THE PROTECTIVE EQUIPMENTS OF A SUBSTATION AND POWER FACTOR IMPROVEM...
“STUDY OF THE PROTECTIVE EQUIPMENTS OF A SUBSTATION AND POWER FACTOR IMPROVEM...“STUDY OF THE PROTECTIVE EQUIPMENTS OF A SUBSTATION AND POWER FACTOR IMPROVEM...
“STUDY OF THE PROTECTIVE EQUIPMENTS OF A SUBSTATION AND POWER FACTOR IMPROVEM...
 
Distribution boards and Protection devices ppt
Distribution boards and Protection devices  pptDistribution boards and Protection devices  ppt
Distribution boards and Protection devices ppt
 
Practical handbook-for-relay-protection-engineers
Practical handbook-for-relay-protection-engineersPractical handbook-for-relay-protection-engineers
Practical handbook-for-relay-protection-engineers
 
Tutorial on Distance and Over Current Protection
Tutorial on Distance and Over  Current ProtectionTutorial on Distance and Over  Current Protection
Tutorial on Distance and Over Current Protection
 
MV Switchgear from IEEE
MV Switchgear from IEEEMV Switchgear from IEEE
MV Switchgear from IEEE
 
protection of transmission lines[distance relay protection scheme]
protection of transmission lines[distance relay protection scheme]protection of transmission lines[distance relay protection scheme]
protection of transmission lines[distance relay protection scheme]
 
Protection schemes and zones
Protection schemes and zonesProtection schemes and zones
Protection schemes and zones
 
Protection Of Generator
Protection Of GeneratorProtection Of Generator
Protection Of Generator
 
Power system protection
Power system protectionPower system protection
Power system protection
 
Earthing system
Earthing system   Earthing system
Earthing system
 
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)ABB - TRANSFORMERS-PROTECTION-COURSE (2001)
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)
 
transformer protection
transformer protection transformer protection
transformer protection
 
Switch yard & Protection
Switch yard & ProtectionSwitch yard & Protection
Switch yard & Protection
 
132 33kv substation documentation
132 33kv substation documentation132 33kv substation documentation
132 33kv substation documentation
 
Equipments of power transmission
Equipments of power transmissionEquipments of power transmission
Equipments of power transmission
 
Power system-protection-presentation-dated-03-10-2013-integrated-protection-c...
Power system-protection-presentation-dated-03-10-2013-integrated-protection-c...Power system-protection-presentation-dated-03-10-2013-integrated-protection-c...
Power system-protection-presentation-dated-03-10-2013-integrated-protection-c...
 
Generator protection LEC 2
Generator protection  LEC 2Generator protection  LEC 2
Generator protection LEC 2
 
Power Transformer Differential protection
Power Transformer Differential protectionPower Transformer Differential protection
Power Transformer Differential protection
 

En vedette

Motor bus transfer
Motor bus transferMotor bus transfer
Motor bus transfermichaeljmack
 
Tracking firm presentation (vincent wedelich) mmm
Tracking firm presentation (vincent wedelich) mmmTracking firm presentation (vincent wedelich) mmm
Tracking firm presentation (vincent wedelich) mmmVincent Wedelich, PE MBA
 
PERCEPTIONS OF GENDER EQUALITY IN CORPORATE AMERICA
PERCEPTIONS OF GENDER EQUALITY IN CORPORATE AMERICAPERCEPTIONS OF GENDER EQUALITY IN CORPORATE AMERICA
PERCEPTIONS OF GENDER EQUALITY IN CORPORATE AMERICAVincent Wedelich, PE MBA
 
Zero Policy = maximize profits; Clients (Refineries and petrochemical Facilit...
Zero Policy = maximize profits; Clients (Refineries and petrochemical Facilit...Zero Policy = maximize profits; Clients (Refineries and petrochemical Facilit...
Zero Policy = maximize profits; Clients (Refineries and petrochemical Facilit...Vincent Wedelich, PE MBA
 
Electrical master plan for chemical engineers and managers
Electrical master plan for chemical engineers and managersElectrical master plan for chemical engineers and managers
Electrical master plan for chemical engineers and managersVincent Wedelich, PE MBA
 
Affordable automobile for low income families
Affordable automobile for low income families Affordable automobile for low income families
Affordable automobile for low income families Vincent Wedelich, PE MBA
 

En vedette (20)

Motor bus transfer
Motor bus transferMotor bus transfer
Motor bus transfer
 
Tracking firm presentation (vincent wedelich) mmm
Tracking firm presentation (vincent wedelich) mmmTracking firm presentation (vincent wedelich) mmm
Tracking firm presentation (vincent wedelich) mmm
 
FUTURES TRADING
FUTURES TRADINGFUTURES TRADING
FUTURES TRADING
 
Understanding power concepts rev 0
Understanding power concepts rev 0Understanding power concepts rev 0
Understanding power concepts rev 0
 
MANAGEMENT ACCOUNTING STUDY PPT
MANAGEMENT ACCOUNTING STUDY PPTMANAGEMENT ACCOUNTING STUDY PPT
MANAGEMENT ACCOUNTING STUDY PPT
 
PERCEPTIONS OF GENDER EQUALITY IN CORPORATE AMERICA
PERCEPTIONS OF GENDER EQUALITY IN CORPORATE AMERICAPERCEPTIONS OF GENDER EQUALITY IN CORPORATE AMERICA
PERCEPTIONS OF GENDER EQUALITY IN CORPORATE AMERICA
 
American barrick vww
American barrick vwwAmerican barrick vww
American barrick vww
 
Area classification
Area classification Area classification
Area classification
 
2012 ieee pes lunch ethics 020112
2012 ieee pes lunch ethics 0201122012 ieee pes lunch ethics 020112
2012 ieee pes lunch ethics 020112
 
Electrical Condition monitoring part 1
Electrical Condition monitoring part 1Electrical Condition monitoring part 1
Electrical Condition monitoring part 1
 
Ieee power quality distribution systems
Ieee power quality distribution systemsIeee power quality distribution systems
Ieee power quality distribution systems
 
Zero Policy = maximize profits; Clients (Refineries and petrochemical Facilit...
Zero Policy = maximize profits; Clients (Refineries and petrochemical Facilit...Zero Policy = maximize profits; Clients (Refineries and petrochemical Facilit...
Zero Policy = maximize profits; Clients (Refineries and petrochemical Facilit...
 
Good to great ppt (vww)
Good to great ppt (vww)Good to great ppt (vww)
Good to great ppt (vww)
 
Area classification
Area classification Area classification
Area classification
 
MANAGEMENT ACCOUNTING STUDY PPT
MANAGEMENT ACCOUNTING STUDY PPTMANAGEMENT ACCOUNTING STUDY PPT
MANAGEMENT ACCOUNTING STUDY PPT
 
Electrical master plan for chemical engineers and managers
Electrical master plan for chemical engineers and managersElectrical master plan for chemical engineers and managers
Electrical master plan for chemical engineers and managers
 
Solar skin
Solar skinSolar skin
Solar skin
 
Affordable automobile for low income families
Affordable automobile for low income families Affordable automobile for low income families
Affordable automobile for low income families
 
IEEE Motor Presentation
IEEE Motor PresentationIEEE Motor Presentation
IEEE Motor Presentation
 
Executive compensation main ppt
Executive compensation main pptExecutive compensation main ppt
Executive compensation main ppt
 

Similaire à Ieee transfer schemes for M-T-M distribution systems

TSE SCADA Design presentation new
TSE SCADA Design presentation newTSE SCADA Design presentation new
TSE SCADA Design presentation newMohamed ElSirsy
 
Fundamentals of Microprocessor Based Relays
Fundamentals of Microprocessor Based RelaysFundamentals of Microprocessor Based Relays
Fundamentals of Microprocessor Based Relaysmichaeljmack
 
Selective Coordination "The Rest of the Story"
Selective Coordination "The Rest of the Story"Selective Coordination "The Rest of the Story"
Selective Coordination "The Rest of the Story"michaeljmack
 
DISTRIBUTION SYSTEM OPERATION AND CONTROL
DISTRIBUTION SYSTEM OPERATION AND CONTROLDISTRIBUTION SYSTEM OPERATION AND CONTROL
DISTRIBUTION SYSTEM OPERATION AND CONTROLyohannes feleke
 
ABB Controlled Switching with Switchsync
ABB Controlled Switching with SwitchsyncABB Controlled Switching with Switchsync
ABB Controlled Switching with SwitchsyncPower System Operation
 
Protection and local control of HVDC grids
Protection and local control of HVDC gridsProtection and local control of HVDC grids
Protection and local control of HVDC gridsPower System Operation
 
Ohiri-Principles-and-Philosophy-of-Protective-Relaying.pptx
Ohiri-Principles-and-Philosophy-of-Protective-Relaying.pptxOhiri-Principles-and-Philosophy-of-Protective-Relaying.pptx
Ohiri-Principles-and-Philosophy-of-Protective-Relaying.pptxGodwin308555
 
Substation monitoring system for maintaining a data log.ppt
Substation monitoring system for maintaining a data log.pptSubstation monitoring system for maintaining a data log.ppt
Substation monitoring system for maintaining a data log.pptSAI SREE
 
vacuum circuit breakers in flexible ac transmission system
vacuum circuit breakers in flexible ac transmission systemvacuum circuit breakers in flexible ac transmission system
vacuum circuit breakers in flexible ac transmission systemKMEA ENGINEERING COLLEGE
 
Introduction of LVAC Auto Change Over Scheme in DEWA Transmission System
Introduction of LVAC Auto Change Over Scheme in DEWA Transmission SystemIntroduction of LVAC Auto Change Over Scheme in DEWA Transmission System
Introduction of LVAC Auto Change Over Scheme in DEWA Transmission SystemIRJET Journal
 

Similaire à Ieee transfer schemes for M-T-M distribution systems (20)

Stability of power
Stability of powerStability of power
Stability of power
 
TSE SCADA Design presentation new
TSE SCADA Design presentation newTSE SCADA Design presentation new
TSE SCADA Design presentation new
 
Fundamentals of Microprocessor-based Relaying
Fundamentals of Microprocessor-based RelayingFundamentals of Microprocessor-based Relaying
Fundamentals of Microprocessor-based Relaying
 
Fundamentals of Microprocessor Based Relays
Fundamentals of Microprocessor Based RelaysFundamentals of Microprocessor Based Relays
Fundamentals of Microprocessor Based Relays
 
EIT_Presentation
EIT_PresentationEIT_Presentation
EIT_Presentation
 
auto-reclosure
auto-reclosureauto-reclosure
auto-reclosure
 
Selective Coordination "The Rest of the Story"
Selective Coordination "The Rest of the Story"Selective Coordination "The Rest of the Story"
Selective Coordination "The Rest of the Story"
 
DISTRIBUTION SYSTEM OPERATION AND CONTROL
DISTRIBUTION SYSTEM OPERATION AND CONTROLDISTRIBUTION SYSTEM OPERATION AND CONTROL
DISTRIBUTION SYSTEM OPERATION AND CONTROL
 
IIA module 6
IIA module 6IIA module 6
IIA module 6
 
Abb b.g. controlled switching ed4
Abb b.g. controlled switching ed4Abb b.g. controlled switching ed4
Abb b.g. controlled switching ed4
 
ABB Controlled Switching with Switchsync
ABB Controlled Switching with SwitchsyncABB Controlled Switching with Switchsync
ABB Controlled Switching with Switchsync
 
EIT_Presentation
EIT_PresentationEIT_Presentation
EIT_Presentation
 
Protection and local control of HVDC grids
Protection and local control of HVDC gridsProtection and local control of HVDC grids
Protection and local control of HVDC grids
 
Ohiri-Principles-and-Philosophy-of-Protective-Relaying.pptx
Ohiri-Principles-and-Philosophy-of-Protective-Relaying.pptxOhiri-Principles-and-Philosophy-of-Protective-Relaying.pptx
Ohiri-Principles-and-Philosophy-of-Protective-Relaying.pptx
 
Carrier_Protn_08_01_16 - Copy.pdf
Carrier_Protn_08_01_16 - Copy.pdfCarrier_Protn_08_01_16 - Copy.pdf
Carrier_Protn_08_01_16 - Copy.pdf
 
Carrier_Protn_08_01_16.pdf
Carrier_Protn_08_01_16.pdfCarrier_Protn_08_01_16.pdf
Carrier_Protn_08_01_16.pdf
 
Substation monitoring system for maintaining a data log.ppt
Substation monitoring system for maintaining a data log.pptSubstation monitoring system for maintaining a data log.ppt
Substation monitoring system for maintaining a data log.ppt
 
vacuum circuit breakers in flexible ac transmission system
vacuum circuit breakers in flexible ac transmission systemvacuum circuit breakers in flexible ac transmission system
vacuum circuit breakers in flexible ac transmission system
 
Introduction of LVAC Auto Change Over Scheme in DEWA Transmission System
Introduction of LVAC Auto Change Over Scheme in DEWA Transmission SystemIntroduction of LVAC Auto Change Over Scheme in DEWA Transmission System
Introduction of LVAC Auto Change Over Scheme in DEWA Transmission System
 
MTDC SYSTEMS
MTDC SYSTEMSMTDC SYSTEMS
MTDC SYSTEMS
 

Plus de Vincent Wedelich, PE MBA (14)

Part 3 motor application considerations understanding power concepts rev 5 vi...
Part 3 motor application considerations understanding power concepts rev 5 vi...Part 3 motor application considerations understanding power concepts rev 5 vi...
Part 3 motor application considerations understanding power concepts rev 5 vi...
 
Amerada hess final presentation
Amerada hess final presentationAmerada hess final presentation
Amerada hess final presentation
 
Balanced scorecard presentation rev 0
Balanced scorecard presentation rev 0Balanced scorecard presentation rev 0
Balanced scorecard presentation rev 0
 
THE PROFIT CHAIN
THE PROFIT CHAINTHE PROFIT CHAIN
THE PROFIT CHAIN
 
Frontier corporation
Frontier corporationFrontier corporation
Frontier corporation
 
Financial Derivatives and Options
Financial Derivatives and OptionsFinancial Derivatives and Options
Financial Derivatives and Options
 
Iceland krona vincent wedelich
Iceland krona vincent wedelichIceland krona vincent wedelich
Iceland krona vincent wedelich
 
Tracking firm presentation (vincent wedelich) mmm 3M
Tracking firm presentation (vincent wedelich) mmm 3MTracking firm presentation (vincent wedelich) mmm 3M
Tracking firm presentation (vincent wedelich) mmm 3M
 
capacitors
capacitorscapacitors
capacitors
 
Electrical condition monitoring part 2
Electrical condition monitoring part 2Electrical condition monitoring part 2
Electrical condition monitoring part 2
 
Overcurrent coordination
Overcurrent coordinationOvercurrent coordination
Overcurrent coordination
 
Overcurrent protection
Overcurrent protectionOvercurrent protection
Overcurrent protection
 
Improving substation reliability & availability
Improving substation reliability & availability Improving substation reliability & availability
Improving substation reliability & availability
 
Lightning protection
Lightning protectionLightning protection
Lightning protection
 

Dernier

Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
welding defects observed during the welding
welding defects observed during the weldingwelding defects observed during the welding
welding defects observed during the weldingMuhammadUzairLiaqat
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 
Indian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptIndian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptMadan Karki
 
computer application and construction management
computer application and construction managementcomputer application and construction management
computer application and construction managementMariconPadriquez1
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - GuideGOPINATHS437943
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionMebane Rash
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleAlluxio, Inc.
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 

Dernier (20)

Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
welding defects observed during the welding
welding defects observed during the weldingwelding defects observed during the welding
welding defects observed during the welding
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Indian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptIndian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.ppt
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
computer application and construction management
computer application and construction managementcomputer application and construction management
computer application and construction management
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - Guide
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of Action
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at Scale
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 

Ieee transfer schemes for M-T-M distribution systems

  • 1. Secondary Selective Substation Transfer Scheme April 2013 Industrial Power System Design
  • 2. Presentation Outline • Definition – Secondary Selective Substation • Equipment Arrangement • Discussion Topics – How do you design a transfer scheme? • Existing System Description  Normal System Loading  Abnormal System Loading • Final System Configuration • Transfer Scheme Definitions • Implementation
  • 3. Definition Secondary Selective Substation • Substations having two busses, each supplied by a normally-closed incoming line circuit breaker and connected together by a normally-open bus tie circuit breaker.
  • 6. Discussion Topics How do you design a transfer scheme? • What conditions are required for transfer?  Breaker positions?  Breaker status?  Voltage conditions?  Make before break or break before make?  Do we need to know about one side or both sides of switchgear to initiate transfer?  Flow Chart, Logic Chart or if then statements? • What is the equipment arrangement?  Where are current transformers going to be placed? Why?  Where are potential transformers going to be placed? Why?
  • 7. Discussion Topics How do you design a transfer scheme? • Safety concerns?  Electrical protection requirements?  Re-energizing bus with fault present?  What do I do with downstream power sources (i.e. generators or synchronous motors)?  Sources synchronized? How do you know? • Motor spin down complete • How will the system be implemented?  Mechanical relays/hardwired  Electronic relays/hardwired  Electronic relays/communication
  • 8. Discussion Topics How do you design a transfer scheme? • How do you recover from automatic transfer?  Automatic or Manual? • If electronic relays, which ones?  Pros and Cons for each  Do you want to program the scheme or do you want to work within an existing framework?  Typical: SEL or MULTILIN  Does one give you an advantage in terms of end of project paperwork?  Will final implementation be “black box” approach or will there be certain outputs that can be checked to tell you where you are in the transfer initiation by technician?
  • 9. Discussion Topics How do you design a transfer scheme? • Communication between team members?  No two engineers will design the system the same way.  What are common assumptions? • Single mode of failure or multiple? • Will additional failure modes be handled with internal programming or procedural changes to the operation of the equipment. • What ranges or setpoints will be utilized? Why? • What requires an alarm to be sent? • What requires the automatic system to be disabled?
  • 10. Discussion Topics How do you design a transfer scheme? • How do you test the system?  What equipment is needed?  If doors are stand alone • Where do you test the system?  Factory  Office/Lab  In the field • Who should be involved in final testing? • Who decides on final testing methodology?
  • 11. Discussion Topics How do you design a transfer scheme? • How do you know if your system is working properly? • Maintenance  What needs to be done on a periodic basis? • Software updates, how do they effect the current system? • Who maintains programming files? • Standard breaker maintenance and time testing? • Relay testing to validate accuracy? • Training  Who gets trained?  What material is provided to make that individual successful?
  • 12. 52-A 52-B 52-T 50P/N, 51P/N, 25, 27 51P/N, 25, 27 PT-1 PT-2 PT-4 PT-3 50P/N, 51P/N, 25, 27 Single Tie Arrangement
  • 13. 52-A 52-B 52-T 50P/N, 51P/N, 25, 27 PT-1 PT-350P/N, 51P/N, 25, 27 Single Tie Arrangement
  • 17. One-Line Depiction • 27I-1, 27I-2 Instantantaneous under voltage relay • 27R-1, 27R-2 Residual voltage relay, 3 phase • 50/51-1, 2 Instantaneous and time overcrurrent relay • 50N/51N-1, 2 Residually connected instantaneous and time overcurrent relay • 51G-1, 2 Transformer X0 connection overcurrent relay
  • 18. One-Line Depiction • 63 - Transformer fault pressure relay, rate-of-rise type or Buchholz relay • 63X - Auxiliary seal in relay • 86T- Hand reset transformer lockout relay • 25- Synchronism check relay
  • 19. One-Line Depiction • 27I Relays 27I prevent an automatic transfer from occurring upon simultaneous loss of both sources, or loss of one source and low voltage on the other. Relays 27I operate through auxiliary relay 96. Because relays 96 are time delay type, an automatic transfer is also prevented upon simultaneous restoration of both sources after a double outage. Relays 27I also seal in relays 97 to prevent transfer if the supply breaker should trip first on overcurrent faults in the secondary selective substation.
  • 20. Main Breaker Schematic 27I Relays 27I prevent an automatic transfer from occurring upon simultaneous loss of both sources, or loss of one source and low voltage on the other. Relays 27I operate through auxiliary relay 96. Because relays 96 are time delay type, an automatic transfer is also prevented upon simultaneous restoration of both sources after a double outage. Relays 27I also seal in relays 97 to prevent transfer if the supply breaker should trip first on overcurrent faults in the secondary selective substation.
  • 21. Main Breaker Schematic 50/50N Relays 50 and 50N operate through the 97 relay, and are used to block transfer during overcurrent faults until the fault is cleared by the feeder breaker or incoming line breaker. When the settings are properly set they permit relay 27 to time out faster under fault conditions. The backup to this scheme includes time current/voltage coordination between the 51 overcurrent relay and the 27 undervoltage relay. The 51 relay should trip before the 27 sends the tripping signal.
  • 22. Main Breaker Schematic •83- Auxiliary relay used in the transfer initiation from the main breaker to the tie breaker via the following functions: Trips the main breaker Closes the tie once the main breaker opens, and the bus voltage is 25% of it nominal value to prevent out of phase re-closer
  • 23. Main Breaker Schematic • Auxiliary relay, instantaneous pickup, adjustable time delay drop out TDDO- time delay dropout, TDC- time delay closing, TDO-time delay opening
  • 24. Main Breaker Schematic • 52LS-1 contact closes when incomer No. 1 is in the racked in position. • 52LS-2 contact closes when incomer No. 2 is in the racked in position. • 24LS contact closes when the tie breaker is in the racked in position. • 52-2/a contact closes when incomer No. 2 breaker is closed. • 10 trip selector switch used in manual transfers.
  • 25. Main Breaker Schematic • 24/a contact closes when the tie breaker is closed. • 52-1/a contact closes when incomer No. 1 breaker is closed. • 96-1/TDC blocks the automatic transfer if the incomer No. 2 bus voltage is not healthy. • 97-1/TDC blocks the automatic transfer if the 50 instantaneous current relay detects flow of fault current. The block doesn't clear until the 50 relay clears and there is no longer a depressed undervoltage condition caused by the fault condition.
  • 26. Main Breaker Schematic • 24/b breaks the transfer system seal in rung when the tie breaker closes. • 83-1 auxiliary relay that initiates the automatic transfer.
  • 27. Tie Breaker Schematic 24LS D-C BUS NO.3 (+) 8-T 27R-1 27R-2 24CS C 83-1 83-2 52-1 b 52-2 b 24 b (1) 52LS-1 (4) 52LS-2 (4) 10 T 52-1 a 52-2 a (4) (4) 24CS TRLGL (8) (8) (8) 24 a 24 TC (1) 24 CC (-) 8-T D-C BUS NO.3 25Y (2) 27R Relays protect the motors which carry through automatic transfer, against overvoltage and instantaneous tripping of their circuit breakers due to closing in out of phase with residual voltage. Protection is achieved by delaying transfer until residual voltage drops to a safe level. Motors will generate a decaying residual voltage if source power is interrupted under load with no fault to dissipate magnetic energy stored in the motors.
  • 28. Tie Breaker Schematic 24LS D-C BUS NO.3 (+) 8-T 27R-1 27R-2 24CS C 83-1 83-2 52-1 b 52-2 b 24 b (1) 52LS-1 (4) 52LS-2 (4) 10 T 52-1 a 52-2 a (4) (4) 24CS TRLGL (8) (8) (8) 24 a 24 TC (1) 24 CC (-) 8-T D-C BUS NO.3 25Y (2) 27R-1 contact closes when the residual bus voltage decays to 25% of the rated bus voltage in order to prevent an out of phase reclosure between the motor back emf and the new source voltage when the tie breaker is closed.
  • 29. Normal Operating Condition SCE Owned/ Operated XOM Owned/ Operated Cable Capacity Transformer Capacity Switchgear Capacity 18 Air Cooled Fan Cooled 15 22.4 Power MVA 21.6 Normal Load 12.5 MVA Normal Load 15.5 MVA Cable Capacity Transformer Capacity Air Cooled Fan Cooled Switchgear Capacity 18 Power MVA 15 22.4 21.6 Normal Flow Normal Flow 12.5 MVA 15.5 MVA Percent Capacity Utilized 86 103 69 72 Total Load 28 MVA Breaker Open Breaker Closed Breaker Closed 69 83 56 58 Percent Capacity Utilized Bus 1 Bus 2
  • 30. Abnormal Operating Condition SCE Owned/ Operated XOM Owned/ Operated Cable Capacity Transformer Capacity Switchgear Capacity 18 Air Cooled Fan Cooled 15 22.4 Power MVA 21.6 Normal Load 12.5 MVA Normal Load 15.5 MVA Cable Out of Service Transformer Out of Service Switchgear Breaker Out of Service Abnormal Flow Abnormal Flow 0 MVA 28 MVA Percent Capacity Utilized 156 187 123 130 Total Load 28 MVA Breaker Closed Breaker Closed Breaker Open Bus 1 Bus 2
  • 31.
  • 32.
  • 33.
  • 34.
  • 35.
  • 36.
  • 37.
  • 38. Final System Logic Diagrams
  • 39. Final System Logic Diagrams
  • 40. Final System Logic Diagrams
  • 41. Final System Logic Diagrams
  • 42. Final System Logic Diagrams
  • 43. Final System Logic Diagrams
  • 44. Final System Logic Diagrams
  • 45. Final System Logic Diagrams
  • 46. Final System Logic Diagrams
  • 47. Final System Logic Diagrams
  • 48. Final System Logic Diagrams
  • 49. Final System Logic Diagrams
  • 50. Final System Logic Diagrams
  • 51. Final System Logic Diagrams

Notes de l'éditeur

  1. Permissives: MOC (Both Mains Closed and Tie Open/Dummy Tie Closed) TOC (Both Mains and Tie/Dummy Tie Racked In) No 86 Lockouts (M, L, T, or B) Good Voltage on alternate incomer for a minimum of X seconds. On fault block transfer and allow for downstream coordinated fault clearing