SlideShare une entreprise Scribd logo
1  sur  6
Télécharger pour lire hors ligne
Journal of Energy Technologies and Policy
www.iiste.org
ISSN 2224-3232 (Paper) ISSN 2225-0573 (Online)
Vol.3, No.11, 2013 – Special Issue for International Conference on Energy, Environment and Sustainable Economy (EESE 2013)

Prospects of Building Information Modeling (BIM) in Malaysian
Construction Industry as Conflict Resolution Tool
Syed Shujaa Safdar Gardezi1* Nasir Shafiq1 M. Faris B. Khamidi1
1. University Teknologi Petronas, Bander Seri Iskandar, 31750 Tronoh Perak, Malaysia;
*Email address of corresponding author: engineershujaa@gmail.com
Abstract
The construction industry of today’s world is becoming more challenging and the projects, on the other hand, are
becoming more complex than before. The projects in construction industry consume huge proportions of
resources especially in-terms of financial resources. Malaysian construction industry is also no exception to this
challenging environment. Different concepts and technology innovations have been developed to mitigate and
rule out factors affecting the performance of the construction industry. Building Information Modeling is one of
them (BIM). The BIM technology helps building in a virtual environment prior to physical construction. This
objective of this study is to propose a model / frame work based on BIM technology which will allow reducing
the potential adverse affects of delays, cost overrun, productivity, quality and other errors in the light of the
available literature and past construction practices. The paper highlights the challenging issues like construction
delays, claims, design changes, delayed approvals etc.
Keywords: Building Information Modelling (BIM), Construction Industry, Construction delays, Claims,
Malaysian Construction Industry
1. Introduction
Construction is one of the major industry contributing significantly in the economy, in terms of GDP, for the
most of the countries especially developing countries. Despite of the fact stated above, the construction industry
is not performing to its fullest potential in almost all countries due to certain barriers caused due to its volatile
nature. The nature of construction industry is such that there is an inherit conflicting issues between the major
construction project stakeholders, participants, owners, design professionals, consultants, contractors. The
history of such issues is well known to the players that have been in the industry for quite some time. The one
important fact that remains to be accepted that the nature of human beings is such that it is not possible get entire
satisfaction in any aspect of any works. Same is the case with the construction industry. No matter how
advanced and sophisticated the technology becomes, the scheduling methods improve, manufacturing and
computer modeling methods innovate and construction methods become hi-tech, the never ending war of
interests between the major roles of a construction project are likely affect the potential performance of the
industry forever. Given the inevitability of conflicting interests of human nature, one must be wondering whether
there is a hope for the industry for reducing the severity and extent of such interests. But there is always room for
improvement and fortunately, the affects of such conflicting interest can be minimized up-to a great extent by
using proper knowledge, professional skills and technology advancements and innovations.
The Malaysian economy is a fast growing economy in South-East Asia (Sambasivan & Soon,2007). The
Malaysian construction industry is one of the main pillars of the country’s economy. In addition, it also provides
a large no. of employment opportunities for the skilled, semi-skilled and unskilled labor force. However, the
Malaysian construction is no exception to conflicting issues and the projects in Malaysia also continue to suffer
from such environment. The issues like construction claims, design errors, poorly defined scope of work, poor
communications, unrealistic expectations , project delivery methods , sustainability issue, ineffective and
inefficient methods and practices, difficulty in securing timely and adequate financing at various stages of
construction and difficulty in repatriating profits / dividends, inability to provide total integrated solutions in
foreign projects and inadequately trained workforce also impairs the industry’s ability to adopt new technologies
and to cope with new challenges.
The construction industry of today is at the cross roads of change. Looking to the future is an important aspect in
its improvement. Different advancement in technology and specific knowledge areas along with proper skills can
help and lead to offset maximum effects of such confliction environment. Building Information Modeling (BIM)
is one of such technology innovations. Building Information Modeling (BIM) represents the process of
development and use of a computer generated model to simulate the planning, design, construction and operation
of a facility in a virtual environment as shown in Figure 1.

346
EESE-2013 is organised by International Society for Commerce, Industry & Engineering.
Journal of Energy Technologies and Policy
www.iiste.org
ISSN 2224-3232 (Paper) ISSN 2225-0573 (Online)
Vol.3, No.11, 2013 – Special Issue for International Conference on Energy, Environment and Sustainable Economy (EESE 2013)

Figure 1: BIM Generated Model (Salman et al , 2012)
The resulting model, a Building Information Model, is a data-rich, object-oriented, intelligent and parametric
digital representation of the facility, from which views and data appropriate to various users’ needs can be
extracted and analyzed to generate information that can be used to make decisions and to improve the process of
delivering the facility (AGC, 2005).
This study is aimed to propose a model based on Building Information Modelling (BIM) technology innovations
which will act as conflict resolution tool for major current issues which occur between the different stake holders
of Malaysian Construction Industry.
2. Literature Review
The construction industry is subject to more risk and uncertainty than other industries. Construction projects
involve complex and time-consuming design. The processes of construction are also characterized by unforeseen
circumstances (Acharya et al ,2006). As a result, risk management has become a major problem that confronts
the construction industry (Ogulana, Promkuntong & Kearkjirm).Mainly there are three main stake holders of a
construction project i.e. the Client/Owner, Consultant and the Contractor. The conflicting issues in the
construction industry are being categories according to these three (Sambasivan & Soon,2007):
Client/Owner Related Factors:
Proper arrangement of funds, timely payments, and owner’s interference, slow process of decision making and
approvals, unrealistic time durations, frequent design changes.
Consultant Related Factors:
Delay in approval of variation statements, discrepancies between contract documents, delayed preparation and
approval of drawings, quality assurance and waiting time for approval of test and inspection.
Contractor Related Factors:
Poor site management, improper construction methods, improper planning, errors during construction,
inadequate experience of the contractor, level of labour and staff hired, lack of procurement schedule,
organizational structure.
Two major common issues of conflicts i.e. construction delays and claims are being focused in this study.
2.1 Construction Delays
The delays in the construction industry are a global phenomenon (Sambasivan & Soon,2007) and are considered
as one of the most persistent problems throughout the world (Tumi SAH & Omran,2009). Delay may be defined
as an event that causes prolongation or extension of time to complete all or part of a project (Sambasivan &
Soon,2007). It may also be defined as the time overrun, either beyond the date for completion specified by the
contract or beyond the extended contract period where an extension of time has been granted (Fugar &
Agyak ,2010). The six most attributed affects of delays are: time overrun, cost overrun, dispute, arbitration, total
abandonment and litigation (Aibinu & Jagboro ,2002).
347
EESE-2013 is organised by International Society for Commerce, Industry & Engineering.
Journal of Energy Technologies and Policy
www.iiste.org
ISSN 2224-3232 (Paper) ISSN 2225-0573 (Online)
Vol.3, No.11, 2013 – Special Issue for International Conference on Energy, Environment and Sustainable Economy (EESE 2013)

The key controlling features of time, cost, quality and safety for a project are adversely affected by the impacts
of such delays. The delays in construction industry have many after effects among which the main are time
extension, cost overrun, disputes, arbitrations and litigations etc (Bryan, shapiro & Knutson ,2005).A project
may be facing delays in all phases of project life cycle. However, the construction phase is the one with the
occurrence of most delays (Acharya et al ,2006). Delays give rise to disruption of work and loss of productivity,
late completion of project increased time related costs, and third party claims and abandonment or termination of
contract (Tumi SAH & Omran,2009). The main causes of the delays in construction projects may be delayed
payments, lack of instructions, delayed decisions, changes in the design etc. So it is essential to define the actual
causes of delays in order to minimize and avoid them in any construction project.
2.2 Claims
The construction claims are one of the most occurring events in the construction projects (Bryan, shapiro &
Knutson ,2005). There may be two main types of such claims: time extension claims and financial claims. These
claims probably cause more disputes than any other contractual or technical issue. The major causes of the
claims may be delayed payments, delayed approval, disruption of works, cost overruns, change in scope of work,
additional works etc (Sambasivan & Soon,2007). Almost 95% of all the claims arise out of the state of
contractual relationship between the parties involved in the project (Bryan, shapiro & Knutson ,2005). Provided
that principal stakeholders spare a little time and emphasis on this issue, most of such conflicts can be easily
avoided or settled without any delay.
2.3 Building Information Modeling (BIM)
Building Information Modeling (BIM) is also known as n-D Modeling or Virtual Prototyping Technology. This
revolutionary development in technology is quickly reshaping the Architecture-Engineering-Construction (AEC)
industry (Salman & Tayyab ,2006). It is a technology as well as a process. The main edge of BIM is that it
enables project stakeholders to visualize in a simulated environment what is actually going to be built and helps
them to identify any potential conflicting issues pertinent to design phase, construction or operational phase
(Salman et al, 2013).
The model characterizes the geometry, spatial relationships, geographic information, quantities and properties of
building elements, cost estimates, material inventories, and project schedule (Salman et al, 2013). It can be used
to display the entire life cycle of a building project.
2.4 Construction Industry of Malaysia
The Construction industry of Malaysia is making its vital contribution in the followings economic sectors:
energy, water resources development, communication, building, architecture and planning, public health
engineering, oil and gas, petrochemicals and industries etc. A revived construction industry striving for
excellence shall lead Malaysia to world class country by improving its overall performance in terms of quality,
efficiency, productivity, site safety, environmental sustainability and customer satisfaction.
3. Research Methodology
A comprehensive literature review has been carried out for the issues resulting into delays at the project site in
Malaysian construction industry. Significant factors resulting in delays have been identified from these studies
and are streamlined with the innovations provided in the BIM technology. Different features of BIM technology
are being applied on these identified factors and a model has been proposed accordingly.
4. Proposed Conflict Resolution Model based on BIM
Considering the conflicting issue related to the three prime stakeholders (Client, Consultant and Contractor) for
the most of the projects, a conflict resolution model is being proposed, in Figure 2, which is based on BIM
innovations.

348
EESE-2013 is organised by International Society for Commerce, Industry & Engineering.
Journal of Energy Technologies and Policy
www.iiste.org
ISSN 2224-3232 (Paper) ISSN 2225-0573 (Online)
Vol.3, No.11, 2013 – Special Issue for International Conference on Energy, Environment and Sustainable Economy (EESE 2013)

CLIENT
Frequent design
changes

C
O
N
S
U
L
T
A
N
T

Proper
arrangement of
funds

Timely
payments

Owner’s
interference

Slow decision
making and
Approvals

Un-realistic
time
durations

Delay in approval of
variation statements

Poor site management

Discrepancies between
contract documents

Improper planning

Delayed preparation and
approval of drawings

Improper construction
methods

Quality assurance

Organizational structure

Waiting time for
approval of test and
inspection

Lack o f Procurement
schedule

INTEGRATED PROJECT DELIVERY
Figure 2: Proposed Model for Conflict Resolution through BIM
4.1 Client Related Factors
The conflicting issues pertinent to the clients are mostly related to financial management, timely decisions and
realistic construction schedules. Clients can benefit significantly from BIM processes and tools to streamlines the
conflicting issues mentioned above. The ability of BIM to generate automatic quantity surveying from the
project model under consideration shall help Clients to manage their financial arrangements at an early stage and
effectively monitor the same when the actual execution takes place. A working environment between different
stake holders under BIM umbrella shall enable the Clients to reduce errors, avoid changes during execution and
enable the clients to achieve a more efficient, well coordinated and reliable delivery process which ultimately
shall result in reduction of project expenses and time.
4.2 Consultant Related Factors
The issues of conflicts pertinent to the consulting firms are mostly related to the documentations. The ability of
BIM to provide for a proper documentation directory is key to resolution of these issues. The ability of BIM to
generate conceptual design, integrated engineering services, construction level modelling and designconstruction integration are key features that shall ensure the timely generation and approvals of VOs,
integration between different project documents, prompt delivery of drawings, perform routine inspection and
ensure quality assurance and quality control for the consulting organizations.
4.3 Contractor Related Factors
The conflicting issues of the Contractor firms are mostly related to construction and site management e.g. poor
site management, improper planning, improper construction methods, lack of organizational structure and lack of
procurement schedules. The conflicts arise when the contracting firms lose a lot of time and finances for their
349
EESE-2013 is organised by International Society for Commerce, Industry & Engineering.

C
O
N
R
A
C
T
O
R
Journal of Energy Technologies and Policy
www.iiste.org
ISSN 2224-3232 (Paper) ISSN 2225-0573 (Online)
Vol.3, No.11, 2013 – Special Issue for International Conference on Energy, Environment and Sustainable Economy (EESE 2013)

improper management and they do not get compensated for that even if they are themselves on the fault. The
BIM technology provides a very efficient solution for that also. The 3D attribute of BIM helps the Contractors to
observe the construction of building in a virtual environment which helps them to improve their site management,
construction methods and strengthen their organizational structure as per project requirement. The 4D (time)
attribute shall enable the contractor to explore project phasing and construction sequencing of the activities and
ensure proper utilization of time frame allotted for completion. The 5D (cost) innovation of BIM can generate
automated quantity take-offs and cost estimates at the design stage. If the contractors properly implement this
innovation of BIM, it shall enable them to achieve a very comprehensive procurement schedule for them. They
will be able to plan their procurements according to the construction phase of the project well before when its
actual stage of execution is reached.
Conclusions
An integrated construction industry capable of continuous improvement towards excellence in a market-driven
environment is our vision. By implementation of BIM, all conflicts or clashes between building systems can be
worked out prior to physical construction beginning. Some of the long terms gains expected in Malaysian
construction industry, by implementation of proposed model based on BIM technology innovations, are
•

Avoidance of Delays

•

Integrated Building Structures

•

Timely Completion

•

Innovative Project Award And Delivery Mechanisms

•

Procurement, Engineering And Construction Process

•

Constructability Analysis

•

Cost And Schedule Controls

•

Dispute Resolution Provisions

•

Research and development Opportunities

References
Sambasivan M. and Soon.Causes and effects of delays in Malaysian construction industry. International Journal
of Project Management, 25 (2007), 517-526
Tumi SAH, Omran A, Pakir AHK . Causes of delays in construction industry in Libya. ICEA-FAA 2009
Fugar, F D K and Agyak wah-Baah, A B. Delays in building construction projects in Ghana. Australasian
Journal of Construction Economics and Building,(2010) 10 (1/2) 103-116
Aibinu, A.A. and Jagboro G.O. (2002). The effects of construction delays on project delivery in Nigerian
construction industry. International Journal of Project Management, (Elsevier), 20, 593-599.
Bryan Shapiro and Shapiro Hankinson & Knutson. Inherent conflicts in the construction industry and the
structure of contracts. Understanding the Issues conference Vancouver BC, February 2005, GEN/03273676/26021.1
Abdul-Rahman, H., Berawi, M.A., Berawi, A.R., Mohamed, Othman, M. and Yahya, I.A. (2006). Delay
mitigation in the Malaysian construction industry. Journal of Construction Engineering and Management
(ASCE), 132.2, 125-133.
Acharya NK , Lee Y D , Kim SY, Lee JC, Kim CS. Analysis of construction delay factor : A Korean Prospective.
APIEMS Conference 2006, Bankok Thialand .
Ogunlana, S.O., Promkuntong, K., and Jearkjirm. V. (1996). Construction delays in a fast growing economy:
comparing Thailand with other economies. Int. Journal of Project Management, (Elsevier), 14.1, 37-45.
Salman Azhar malik Khalfan and Tayyab Maqsood . Building Information Modeling (BIM) : Now and Beyond.
Australasian Journal of Construction Economics and Building
Salman Azhar, Alex Behringer B.S. A BIM-based Approach for Communicating and Implementing a
Construction Site Safety Plan. 49th ASC Annual International Conference Proceedings, Associated Schools
of Construction
Salman Azhar. Building Information Modeling (BIM): Trends, Benefits, Risks, and Challenges for the AEC
Industry. A.M.ASCE, July 2011, Leadership Manage. Eng. 2011.11:241-252.

350
EESE-2013 is organised by International Society for Commerce, Industry & Engineering.
This academic article was published by The International Institute for Science,
Technology and Education (IISTE). The IISTE is a pioneer in the Open Access
Publishing service based in the U.S. and Europe. The aim of the institute is
Accelerating Global Knowledge Sharing.
More information about the publisher can be found in the IISTE’s homepage:
http://www.iiste.org
CALL FOR JOURNAL PAPERS
The IISTE is currently hosting more than 30 peer-reviewed academic journals and
collaborating with academic institutions around the world. There’s no deadline for
submission. Prospective authors of IISTE journals can find the submission
instruction on the following page: http://www.iiste.org/journals/
The IISTE
editorial team promises to the review and publish all the qualified submissions in a
fast manner. All the journals articles are available online to the readers all over the
world without financial, legal, or technical barriers other than those inseparable from
gaining access to the internet itself. Printed version of the journals is also available
upon request of readers and authors.
MORE RESOURCES
Book publication information: http://www.iiste.org/book/
Recent conferences: http://www.iiste.org/conference/
IISTE Knowledge Sharing Partners
EBSCO, Index Copernicus, Ulrich's Periodicals Directory, JournalTOCS, PKP Open
Archives Harvester, Bielefeld Academic Search Engine, Elektronische
Zeitschriftenbibliothek EZB, Open J-Gate, OCLC WorldCat, Universe Digtial
Library , NewJour, Google Scholar

Contenu connexe

Tendances

Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...
IJERA Editor
 
11.the adequacy of contractual provisions in managing construction failure in...
11.the adequacy of contractual provisions in managing construction failure in...11.the adequacy of contractual provisions in managing construction failure in...
11.the adequacy of contractual provisions in managing construction failure in...
Alexander Decker
 
The adequacy of contractual provisions in managing construction failure in ma...
The adequacy of contractual provisions in managing construction failure in ma...The adequacy of contractual provisions in managing construction failure in ma...
The adequacy of contractual provisions in managing construction failure in ma...
Alexander Decker
 
Construction economic
Construction economicConstruction economic
Construction economic
fauziani
 

Tendances (20)

Rate of Occurrence of Fatal Accidents in Malaysian Construction Industry afte...
Rate of Occurrence of Fatal Accidents in Malaysian Construction Industry afte...Rate of Occurrence of Fatal Accidents in Malaysian Construction Industry afte...
Rate of Occurrence of Fatal Accidents in Malaysian Construction Industry afte...
 
20320140503023
2032014050302320320140503023
20320140503023
 
Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...
 
Green Building Effect in Commercial Building
Green Building Effect in Commercial Building Green Building Effect in Commercial Building
Green Building Effect in Commercial Building
 
Causes and Effects of Change Orders on Construction Projects in Kuwait
Causes and Effects of Change Orders on Construction Projects in KuwaitCauses and Effects of Change Orders on Construction Projects in Kuwait
Causes and Effects of Change Orders on Construction Projects in Kuwait
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction Project
 
Causes of Variation Orders 1268
Causes of Variation Orders 1268Causes of Variation Orders 1268
Causes of Variation Orders 1268
 
Time delay and cost escalation in construction works
Time delay and cost escalation in construction worksTime delay and cost escalation in construction works
Time delay and cost escalation in construction works
 
IRJET - Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET -  	  Causes, Effects and Minimizing Methods of Construction Projects D...IRJET -  	  Causes, Effects and Minimizing Methods of Construction Projects D...
IRJET - Causes, Effects and Minimizing Methods of Construction Projects D...
 
11.the adequacy of contractual provisions in managing construction failure in...
11.the adequacy of contractual provisions in managing construction failure in...11.the adequacy of contractual provisions in managing construction failure in...
11.the adequacy of contractual provisions in managing construction failure in...
 
The adequacy of contractual provisions in managing construction failure in ma...
The adequacy of contractual provisions in managing construction failure in ma...The adequacy of contractual provisions in managing construction failure in ma...
The adequacy of contractual provisions in managing construction failure in ma...
 
Construction economic
Construction economicConstruction economic
Construction economic
 
IRJET- Risk Management in the Construction Project: Review
IRJET-  	  Risk Management in the Construction Project: ReviewIRJET-  	  Risk Management in the Construction Project: Review
IRJET- Risk Management in the Construction Project: Review
 
IRJET- Quantifay the Different Constraints for Delays in Infrastructure C...
IRJET-  	  Quantifay the Different Constraints for Delays in Infrastructure C...IRJET-  	  Quantifay the Different Constraints for Delays in Infrastructure C...
IRJET- Quantifay the Different Constraints for Delays in Infrastructure C...
 
IRJET- Study & Analysis of Subcontracting Practices in Infrastructure Project
IRJET- Study & Analysis of Subcontracting Practices in Infrastructure ProjectIRJET- Study & Analysis of Subcontracting Practices in Infrastructure Project
IRJET- Study & Analysis of Subcontracting Practices in Infrastructure Project
 
IRJET- Recognition of Factor Impacting Labor Productivity for Reinforcement I...
IRJET- Recognition of Factor Impacting Labor Productivity for Reinforcement I...IRJET- Recognition of Factor Impacting Labor Productivity for Reinforcement I...
IRJET- Recognition of Factor Impacting Labor Productivity for Reinforcement I...
 
IRJET- A Study on Low Cost Housing Construction with Delay Management
IRJET- A Study on Low Cost Housing Construction with Delay ManagementIRJET- A Study on Low Cost Housing Construction with Delay Management
IRJET- A Study on Low Cost Housing Construction with Delay Management
 
(Essay) HRO & Lean 6 Sigma
(Essay) HRO & Lean 6 Sigma(Essay) HRO & Lean 6 Sigma
(Essay) HRO & Lean 6 Sigma
 
IRJET-A Review of Impact on Labour Management in Construction Industry
IRJET-A Review of Impact on Labour Management in Construction IndustryIRJET-A Review of Impact on Labour Management in Construction Industry
IRJET-A Review of Impact on Labour Management in Construction Industry
 
Building construction
Building constructionBuilding construction
Building construction
 

Similaire à Prospects of building information modeling (bim) in malaysian construction industry as conflict resolution tool

To Identify the Various Constraints for Delays in Construction Work and Sugge...
To Identify the Various Constraints for Delays in Construction Work and Sugge...To Identify the Various Constraints for Delays in Construction Work and Sugge...
To Identify the Various Constraints for Delays in Construction Work and Sugge...
Harish Rajmane
 
Quality &Amp; Risk Management In Construction Industry
Quality &Amp; Risk Management In Construction IndustryQuality &Amp; Risk Management In Construction Industry
Quality &Amp; Risk Management In Construction Industry
Michelle Madero
 
BIM based organizational learning
BIM based organizational learningBIM based organizational learning
BIM based organizational learning
IJRES Journal
 
Effect of construction delays on project time overrun
Effect of construction delays on project time overrunEffect of construction delays on project time overrun
Effect of construction delays on project time overrun
eSAT Journals
 
Factors Affecting Cost Escalation in Construction Projects in Gaza Strip
Factors Affecting Cost Escalation in Construction Projects in Gaza StripFactors Affecting Cost Escalation in Construction Projects in Gaza Strip
Factors Affecting Cost Escalation in Construction Projects in Gaza Strip
Dr. Amarjeet Singh
 
Examining the Effect of Project Delays in Construction Field, A Case Study of...
Examining the Effect of Project Delays in Construction Field, A Case Study of...Examining the Effect of Project Delays in Construction Field, A Case Study of...
Examining the Effect of Project Delays in Construction Field, A Case Study of...
Associate Professor in VSB Coimbatore
 
Dual Engineering And Integrated Product Development
Dual Engineering And Integrated Product DevelopmentDual Engineering And Integrated Product Development
Dual Engineering And Integrated Product Development
Tracy Berry
 

Similaire à Prospects of building information modeling (bim) in malaysian construction industry as conflict resolution tool (19)

To Identify the Various Constraints for Delays in Construction Work and Sugge...
To Identify the Various Constraints for Delays in Construction Work and Sugge...To Identify the Various Constraints for Delays in Construction Work and Sugge...
To Identify the Various Constraints for Delays in Construction Work and Sugge...
 
Quality &Amp; Risk Management In Construction Industry
Quality &Amp; Risk Management In Construction IndustryQuality &Amp; Risk Management In Construction Industry
Quality &Amp; Risk Management In Construction Industry
 
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTSFACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
FACTORS AFFECTING DELAYS ON PRIVATE CONSTRUCTION PROJECTS
 
BIM based organizational learning
BIM based organizational learningBIM based organizational learning
BIM based organizational learning
 
A Critical Review of the Causes of Cost Overrun in Construction Industries in...
A Critical Review of the Causes of Cost Overrun in Construction Industries in...A Critical Review of the Causes of Cost Overrun in Construction Industries in...
A Critical Review of the Causes of Cost Overrun in Construction Industries in...
 
Effect of construction delays on project time overrun
Effect of construction delays on project time overrunEffect of construction delays on project time overrun
Effect of construction delays on project time overrun
 
Effect of construction delays on project time overrun
Effect of construction delays on project time overrunEffect of construction delays on project time overrun
Effect of construction delays on project time overrun
 
Element of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A ReviewElement of Cost overrun and Delay in Construction: A Review
Element of Cost overrun and Delay in Construction: A Review
 
IMPORTANCE OF MANAGEMENT IN IMPROVING THE CONSTRUCTION PRODUCTIVITY
IMPORTANCE OF MANAGEMENT IN IMPROVING THE CONSTRUCTION PRODUCTIVITYIMPORTANCE OF MANAGEMENT IN IMPROVING THE CONSTRUCTION PRODUCTIVITY
IMPORTANCE OF MANAGEMENT IN IMPROVING THE CONSTRUCTION PRODUCTIVITY
 
Essay Construction
Essay ConstructionEssay Construction
Essay Construction
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...
 
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
IRJET- Case Study on Budget and Schedule Overrun During the Construction Phas...
 
Factors Affecting Cost Escalation in Construction Projects in Gaza Strip
Factors Affecting Cost Escalation in Construction Projects in Gaza StripFactors Affecting Cost Escalation in Construction Projects in Gaza Strip
Factors Affecting Cost Escalation in Construction Projects in Gaza Strip
 
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECTINVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
INVESTIGATION ON CAUSES OF DELAYS IN RESIDENTIAL BUILDING CONSTRUCTION PROJECT
 
Examining the Effect of Project Delays in Construction Field, A Case Study of...
Examining the Effect of Project Delays in Construction Field, A Case Study of...Examining the Effect of Project Delays in Construction Field, A Case Study of...
Examining the Effect of Project Delays in Construction Field, A Case Study of...
 
Dual Engineering And Integrated Product Development
Dual Engineering And Integrated Product DevelopmentDual Engineering And Integrated Product Development
Dual Engineering And Integrated Product Development
 
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
Practical Investigation of Factors Affecting Selection of Dispute Resolution ...
 
Construction Project Essay
Construction Project EssayConstruction Project Essay
Construction Project Essay
 
L012238891
L012238891L012238891
L012238891
 

Plus de Alexander Decker

Abnormalities of hormones and inflammatory cytokines in women affected with p...
Abnormalities of hormones and inflammatory cytokines in women affected with p...Abnormalities of hormones and inflammatory cytokines in women affected with p...
Abnormalities of hormones and inflammatory cytokines in women affected with p...
Alexander Decker
 
A usability evaluation framework for b2 c e commerce websites
A usability evaluation framework for b2 c e commerce websitesA usability evaluation framework for b2 c e commerce websites
A usability evaluation framework for b2 c e commerce websites
Alexander Decker
 
A universal model for managing the marketing executives in nigerian banks
A universal model for managing the marketing executives in nigerian banksA universal model for managing the marketing executives in nigerian banks
A universal model for managing the marketing executives in nigerian banks
Alexander Decker
 
A unique common fixed point theorems in generalized d
A unique common fixed point theorems in generalized dA unique common fixed point theorems in generalized d
A unique common fixed point theorems in generalized d
Alexander Decker
 
A trends of salmonella and antibiotic resistance
A trends of salmonella and antibiotic resistanceA trends of salmonella and antibiotic resistance
A trends of salmonella and antibiotic resistance
Alexander Decker
 
A transformational generative approach towards understanding al-istifham
A transformational  generative approach towards understanding al-istifhamA transformational  generative approach towards understanding al-istifham
A transformational generative approach towards understanding al-istifham
Alexander Decker
 
A time series analysis of the determinants of savings in namibia
A time series analysis of the determinants of savings in namibiaA time series analysis of the determinants of savings in namibia
A time series analysis of the determinants of savings in namibia
Alexander Decker
 
A therapy for physical and mental fitness of school children
A therapy for physical and mental fitness of school childrenA therapy for physical and mental fitness of school children
A therapy for physical and mental fitness of school children
Alexander Decker
 
A theory of efficiency for managing the marketing executives in nigerian banks
A theory of efficiency for managing the marketing executives in nigerian banksA theory of efficiency for managing the marketing executives in nigerian banks
A theory of efficiency for managing the marketing executives in nigerian banks
Alexander Decker
 
A systematic evaluation of link budget for
A systematic evaluation of link budget forA systematic evaluation of link budget for
A systematic evaluation of link budget for
Alexander Decker
 
A synthetic review of contraceptive supplies in punjab
A synthetic review of contraceptive supplies in punjabA synthetic review of contraceptive supplies in punjab
A synthetic review of contraceptive supplies in punjab
Alexander Decker
 
A synthesis of taylor’s and fayol’s management approaches for managing market...
A synthesis of taylor’s and fayol’s management approaches for managing market...A synthesis of taylor’s and fayol’s management approaches for managing market...
A synthesis of taylor’s and fayol’s management approaches for managing market...
Alexander Decker
 
A survey paper on sequence pattern mining with incremental
A survey paper on sequence pattern mining with incrementalA survey paper on sequence pattern mining with incremental
A survey paper on sequence pattern mining with incremental
Alexander Decker
 
A survey on live virtual machine migrations and its techniques
A survey on live virtual machine migrations and its techniquesA survey on live virtual machine migrations and its techniques
A survey on live virtual machine migrations and its techniques
Alexander Decker
 
A survey on data mining and analysis in hadoop and mongo db
A survey on data mining and analysis in hadoop and mongo dbA survey on data mining and analysis in hadoop and mongo db
A survey on data mining and analysis in hadoop and mongo db
Alexander Decker
 
A survey on challenges to the media cloud
A survey on challenges to the media cloudA survey on challenges to the media cloud
A survey on challenges to the media cloud
Alexander Decker
 
A survey of provenance leveraged
A survey of provenance leveragedA survey of provenance leveraged
A survey of provenance leveraged
Alexander Decker
 
A survey of private equity investments in kenya
A survey of private equity investments in kenyaA survey of private equity investments in kenya
A survey of private equity investments in kenya
Alexander Decker
 
A study to measures the financial health of
A study to measures the financial health ofA study to measures the financial health of
A study to measures the financial health of
Alexander Decker
 

Plus de Alexander Decker (20)

Abnormalities of hormones and inflammatory cytokines in women affected with p...
Abnormalities of hormones and inflammatory cytokines in women affected with p...Abnormalities of hormones and inflammatory cytokines in women affected with p...
Abnormalities of hormones and inflammatory cytokines in women affected with p...
 
A validation of the adverse childhood experiences scale in
A validation of the adverse childhood experiences scale inA validation of the adverse childhood experiences scale in
A validation of the adverse childhood experiences scale in
 
A usability evaluation framework for b2 c e commerce websites
A usability evaluation framework for b2 c e commerce websitesA usability evaluation framework for b2 c e commerce websites
A usability evaluation framework for b2 c e commerce websites
 
A universal model for managing the marketing executives in nigerian banks
A universal model for managing the marketing executives in nigerian banksA universal model for managing the marketing executives in nigerian banks
A universal model for managing the marketing executives in nigerian banks
 
A unique common fixed point theorems in generalized d
A unique common fixed point theorems in generalized dA unique common fixed point theorems in generalized d
A unique common fixed point theorems in generalized d
 
A trends of salmonella and antibiotic resistance
A trends of salmonella and antibiotic resistanceA trends of salmonella and antibiotic resistance
A trends of salmonella and antibiotic resistance
 
A transformational generative approach towards understanding al-istifham
A transformational  generative approach towards understanding al-istifhamA transformational  generative approach towards understanding al-istifham
A transformational generative approach towards understanding al-istifham
 
A time series analysis of the determinants of savings in namibia
A time series analysis of the determinants of savings in namibiaA time series analysis of the determinants of savings in namibia
A time series analysis of the determinants of savings in namibia
 
A therapy for physical and mental fitness of school children
A therapy for physical and mental fitness of school childrenA therapy for physical and mental fitness of school children
A therapy for physical and mental fitness of school children
 
A theory of efficiency for managing the marketing executives in nigerian banks
A theory of efficiency for managing the marketing executives in nigerian banksA theory of efficiency for managing the marketing executives in nigerian banks
A theory of efficiency for managing the marketing executives in nigerian banks
 
A systematic evaluation of link budget for
A systematic evaluation of link budget forA systematic evaluation of link budget for
A systematic evaluation of link budget for
 
A synthetic review of contraceptive supplies in punjab
A synthetic review of contraceptive supplies in punjabA synthetic review of contraceptive supplies in punjab
A synthetic review of contraceptive supplies in punjab
 
A synthesis of taylor’s and fayol’s management approaches for managing market...
A synthesis of taylor’s and fayol’s management approaches for managing market...A synthesis of taylor’s and fayol’s management approaches for managing market...
A synthesis of taylor’s and fayol’s management approaches for managing market...
 
A survey paper on sequence pattern mining with incremental
A survey paper on sequence pattern mining with incrementalA survey paper on sequence pattern mining with incremental
A survey paper on sequence pattern mining with incremental
 
A survey on live virtual machine migrations and its techniques
A survey on live virtual machine migrations and its techniquesA survey on live virtual machine migrations and its techniques
A survey on live virtual machine migrations and its techniques
 
A survey on data mining and analysis in hadoop and mongo db
A survey on data mining and analysis in hadoop and mongo dbA survey on data mining and analysis in hadoop and mongo db
A survey on data mining and analysis in hadoop and mongo db
 
A survey on challenges to the media cloud
A survey on challenges to the media cloudA survey on challenges to the media cloud
A survey on challenges to the media cloud
 
A survey of provenance leveraged
A survey of provenance leveragedA survey of provenance leveraged
A survey of provenance leveraged
 
A survey of private equity investments in kenya
A survey of private equity investments in kenyaA survey of private equity investments in kenya
A survey of private equity investments in kenya
 
A study to measures the financial health of
A study to measures the financial health ofA study to measures the financial health of
A study to measures the financial health of
 

Dernier

Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
amitlee9823
 
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
amitlee9823
 
Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...
Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...
Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...
lizamodels9
 
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Sheetaleventcompany
 
Call Girls From Raj Nagar Extension Ghaziabad❤️8448577510 ⊹Best Escorts Servi...
Call Girls From Raj Nagar Extension Ghaziabad❤️8448577510 ⊹Best Escorts Servi...Call Girls From Raj Nagar Extension Ghaziabad❤️8448577510 ⊹Best Escorts Servi...
Call Girls From Raj Nagar Extension Ghaziabad❤️8448577510 ⊹Best Escorts Servi...
lizamodels9
 
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai KuwaitThe Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
daisycvs
 
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
dollysharma2066
 
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
lizamodels9
 

Dernier (20)

Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
 
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
 
Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...
Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...
Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...
 
Cheap Rate Call Girls In Noida Sector 62 Metro 959961乂3876
Cheap Rate Call Girls In Noida Sector 62 Metro 959961乂3876Cheap Rate Call Girls In Noida Sector 62 Metro 959961乂3876
Cheap Rate Call Girls In Noida Sector 62 Metro 959961乂3876
 
Falcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business GrowthFalcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business Growth
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and pains
 
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
 
Falcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to ProsperityFalcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to Prosperity
 
Marel Q1 2024 Investor Presentation from May 8, 2024
Marel Q1 2024 Investor Presentation from May 8, 2024Marel Q1 2024 Investor Presentation from May 8, 2024
Marel Q1 2024 Investor Presentation from May 8, 2024
 
Falcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business PotentialFalcon Invoice Discounting: Unlock Your Business Potential
Falcon Invoice Discounting: Unlock Your Business Potential
 
Call Girls From Raj Nagar Extension Ghaziabad❤️8448577510 ⊹Best Escorts Servi...
Call Girls From Raj Nagar Extension Ghaziabad❤️8448577510 ⊹Best Escorts Servi...Call Girls From Raj Nagar Extension Ghaziabad❤️8448577510 ⊹Best Escorts Servi...
Call Girls From Raj Nagar Extension Ghaziabad❤️8448577510 ⊹Best Escorts Servi...
 
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
Unveiling Falcon Invoice Discounting: Leading the Way as India's Premier Bill...
 
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai KuwaitThe Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
 
Malegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
Malegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort ServiceMalegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
Malegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
 
Phases of Negotiation .pptx
 Phases of Negotiation .pptx Phases of Negotiation .pptx
Phases of Negotiation .pptx
 
Falcon Invoice Discounting platform in india
Falcon Invoice Discounting platform in indiaFalcon Invoice Discounting platform in india
Falcon Invoice Discounting platform in india
 
Business Model Canvas (BMC)- A new venture concept
Business Model Canvas (BMC)-  A new venture conceptBusiness Model Canvas (BMC)-  A new venture concept
Business Model Canvas (BMC)- A new venture concept
 
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort ServiceEluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
 
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
 
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
 

Prospects of building information modeling (bim) in malaysian construction industry as conflict resolution tool

  • 1. Journal of Energy Technologies and Policy www.iiste.org ISSN 2224-3232 (Paper) ISSN 2225-0573 (Online) Vol.3, No.11, 2013 – Special Issue for International Conference on Energy, Environment and Sustainable Economy (EESE 2013) Prospects of Building Information Modeling (BIM) in Malaysian Construction Industry as Conflict Resolution Tool Syed Shujaa Safdar Gardezi1* Nasir Shafiq1 M. Faris B. Khamidi1 1. University Teknologi Petronas, Bander Seri Iskandar, 31750 Tronoh Perak, Malaysia; *Email address of corresponding author: engineershujaa@gmail.com Abstract The construction industry of today’s world is becoming more challenging and the projects, on the other hand, are becoming more complex than before. The projects in construction industry consume huge proportions of resources especially in-terms of financial resources. Malaysian construction industry is also no exception to this challenging environment. Different concepts and technology innovations have been developed to mitigate and rule out factors affecting the performance of the construction industry. Building Information Modeling is one of them (BIM). The BIM technology helps building in a virtual environment prior to physical construction. This objective of this study is to propose a model / frame work based on BIM technology which will allow reducing the potential adverse affects of delays, cost overrun, productivity, quality and other errors in the light of the available literature and past construction practices. The paper highlights the challenging issues like construction delays, claims, design changes, delayed approvals etc. Keywords: Building Information Modelling (BIM), Construction Industry, Construction delays, Claims, Malaysian Construction Industry 1. Introduction Construction is one of the major industry contributing significantly in the economy, in terms of GDP, for the most of the countries especially developing countries. Despite of the fact stated above, the construction industry is not performing to its fullest potential in almost all countries due to certain barriers caused due to its volatile nature. The nature of construction industry is such that there is an inherit conflicting issues between the major construction project stakeholders, participants, owners, design professionals, consultants, contractors. The history of such issues is well known to the players that have been in the industry for quite some time. The one important fact that remains to be accepted that the nature of human beings is such that it is not possible get entire satisfaction in any aspect of any works. Same is the case with the construction industry. No matter how advanced and sophisticated the technology becomes, the scheduling methods improve, manufacturing and computer modeling methods innovate and construction methods become hi-tech, the never ending war of interests between the major roles of a construction project are likely affect the potential performance of the industry forever. Given the inevitability of conflicting interests of human nature, one must be wondering whether there is a hope for the industry for reducing the severity and extent of such interests. But there is always room for improvement and fortunately, the affects of such conflicting interest can be minimized up-to a great extent by using proper knowledge, professional skills and technology advancements and innovations. The Malaysian economy is a fast growing economy in South-East Asia (Sambasivan & Soon,2007). The Malaysian construction industry is one of the main pillars of the country’s economy. In addition, it also provides a large no. of employment opportunities for the skilled, semi-skilled and unskilled labor force. However, the Malaysian construction is no exception to conflicting issues and the projects in Malaysia also continue to suffer from such environment. The issues like construction claims, design errors, poorly defined scope of work, poor communications, unrealistic expectations , project delivery methods , sustainability issue, ineffective and inefficient methods and practices, difficulty in securing timely and adequate financing at various stages of construction and difficulty in repatriating profits / dividends, inability to provide total integrated solutions in foreign projects and inadequately trained workforce also impairs the industry’s ability to adopt new technologies and to cope with new challenges. The construction industry of today is at the cross roads of change. Looking to the future is an important aspect in its improvement. Different advancement in technology and specific knowledge areas along with proper skills can help and lead to offset maximum effects of such confliction environment. Building Information Modeling (BIM) is one of such technology innovations. Building Information Modeling (BIM) represents the process of development and use of a computer generated model to simulate the planning, design, construction and operation of a facility in a virtual environment as shown in Figure 1. 346 EESE-2013 is organised by International Society for Commerce, Industry & Engineering.
  • 2. Journal of Energy Technologies and Policy www.iiste.org ISSN 2224-3232 (Paper) ISSN 2225-0573 (Online) Vol.3, No.11, 2013 – Special Issue for International Conference on Energy, Environment and Sustainable Economy (EESE 2013) Figure 1: BIM Generated Model (Salman et al , 2012) The resulting model, a Building Information Model, is a data-rich, object-oriented, intelligent and parametric digital representation of the facility, from which views and data appropriate to various users’ needs can be extracted and analyzed to generate information that can be used to make decisions and to improve the process of delivering the facility (AGC, 2005). This study is aimed to propose a model based on Building Information Modelling (BIM) technology innovations which will act as conflict resolution tool for major current issues which occur between the different stake holders of Malaysian Construction Industry. 2. Literature Review The construction industry is subject to more risk and uncertainty than other industries. Construction projects involve complex and time-consuming design. The processes of construction are also characterized by unforeseen circumstances (Acharya et al ,2006). As a result, risk management has become a major problem that confronts the construction industry (Ogulana, Promkuntong & Kearkjirm).Mainly there are three main stake holders of a construction project i.e. the Client/Owner, Consultant and the Contractor. The conflicting issues in the construction industry are being categories according to these three (Sambasivan & Soon,2007): Client/Owner Related Factors: Proper arrangement of funds, timely payments, and owner’s interference, slow process of decision making and approvals, unrealistic time durations, frequent design changes. Consultant Related Factors: Delay in approval of variation statements, discrepancies between contract documents, delayed preparation and approval of drawings, quality assurance and waiting time for approval of test and inspection. Contractor Related Factors: Poor site management, improper construction methods, improper planning, errors during construction, inadequate experience of the contractor, level of labour and staff hired, lack of procurement schedule, organizational structure. Two major common issues of conflicts i.e. construction delays and claims are being focused in this study. 2.1 Construction Delays The delays in the construction industry are a global phenomenon (Sambasivan & Soon,2007) and are considered as one of the most persistent problems throughout the world (Tumi SAH & Omran,2009). Delay may be defined as an event that causes prolongation or extension of time to complete all or part of a project (Sambasivan & Soon,2007). It may also be defined as the time overrun, either beyond the date for completion specified by the contract or beyond the extended contract period where an extension of time has been granted (Fugar & Agyak ,2010). The six most attributed affects of delays are: time overrun, cost overrun, dispute, arbitration, total abandonment and litigation (Aibinu & Jagboro ,2002). 347 EESE-2013 is organised by International Society for Commerce, Industry & Engineering.
  • 3. Journal of Energy Technologies and Policy www.iiste.org ISSN 2224-3232 (Paper) ISSN 2225-0573 (Online) Vol.3, No.11, 2013 – Special Issue for International Conference on Energy, Environment and Sustainable Economy (EESE 2013) The key controlling features of time, cost, quality and safety for a project are adversely affected by the impacts of such delays. The delays in construction industry have many after effects among which the main are time extension, cost overrun, disputes, arbitrations and litigations etc (Bryan, shapiro & Knutson ,2005).A project may be facing delays in all phases of project life cycle. However, the construction phase is the one with the occurrence of most delays (Acharya et al ,2006). Delays give rise to disruption of work and loss of productivity, late completion of project increased time related costs, and third party claims and abandonment or termination of contract (Tumi SAH & Omran,2009). The main causes of the delays in construction projects may be delayed payments, lack of instructions, delayed decisions, changes in the design etc. So it is essential to define the actual causes of delays in order to minimize and avoid them in any construction project. 2.2 Claims The construction claims are one of the most occurring events in the construction projects (Bryan, shapiro & Knutson ,2005). There may be two main types of such claims: time extension claims and financial claims. These claims probably cause more disputes than any other contractual or technical issue. The major causes of the claims may be delayed payments, delayed approval, disruption of works, cost overruns, change in scope of work, additional works etc (Sambasivan & Soon,2007). Almost 95% of all the claims arise out of the state of contractual relationship between the parties involved in the project (Bryan, shapiro & Knutson ,2005). Provided that principal stakeholders spare a little time and emphasis on this issue, most of such conflicts can be easily avoided or settled without any delay. 2.3 Building Information Modeling (BIM) Building Information Modeling (BIM) is also known as n-D Modeling or Virtual Prototyping Technology. This revolutionary development in technology is quickly reshaping the Architecture-Engineering-Construction (AEC) industry (Salman & Tayyab ,2006). It is a technology as well as a process. The main edge of BIM is that it enables project stakeholders to visualize in a simulated environment what is actually going to be built and helps them to identify any potential conflicting issues pertinent to design phase, construction or operational phase (Salman et al, 2013). The model characterizes the geometry, spatial relationships, geographic information, quantities and properties of building elements, cost estimates, material inventories, and project schedule (Salman et al, 2013). It can be used to display the entire life cycle of a building project. 2.4 Construction Industry of Malaysia The Construction industry of Malaysia is making its vital contribution in the followings economic sectors: energy, water resources development, communication, building, architecture and planning, public health engineering, oil and gas, petrochemicals and industries etc. A revived construction industry striving for excellence shall lead Malaysia to world class country by improving its overall performance in terms of quality, efficiency, productivity, site safety, environmental sustainability and customer satisfaction. 3. Research Methodology A comprehensive literature review has been carried out for the issues resulting into delays at the project site in Malaysian construction industry. Significant factors resulting in delays have been identified from these studies and are streamlined with the innovations provided in the BIM technology. Different features of BIM technology are being applied on these identified factors and a model has been proposed accordingly. 4. Proposed Conflict Resolution Model based on BIM Considering the conflicting issue related to the three prime stakeholders (Client, Consultant and Contractor) for the most of the projects, a conflict resolution model is being proposed, in Figure 2, which is based on BIM innovations. 348 EESE-2013 is organised by International Society for Commerce, Industry & Engineering.
  • 4. Journal of Energy Technologies and Policy www.iiste.org ISSN 2224-3232 (Paper) ISSN 2225-0573 (Online) Vol.3, No.11, 2013 – Special Issue for International Conference on Energy, Environment and Sustainable Economy (EESE 2013) CLIENT Frequent design changes C O N S U L T A N T Proper arrangement of funds Timely payments Owner’s interference Slow decision making and Approvals Un-realistic time durations Delay in approval of variation statements Poor site management Discrepancies between contract documents Improper planning Delayed preparation and approval of drawings Improper construction methods Quality assurance Organizational structure Waiting time for approval of test and inspection Lack o f Procurement schedule INTEGRATED PROJECT DELIVERY Figure 2: Proposed Model for Conflict Resolution through BIM 4.1 Client Related Factors The conflicting issues pertinent to the clients are mostly related to financial management, timely decisions and realistic construction schedules. Clients can benefit significantly from BIM processes and tools to streamlines the conflicting issues mentioned above. The ability of BIM to generate automatic quantity surveying from the project model under consideration shall help Clients to manage their financial arrangements at an early stage and effectively monitor the same when the actual execution takes place. A working environment between different stake holders under BIM umbrella shall enable the Clients to reduce errors, avoid changes during execution and enable the clients to achieve a more efficient, well coordinated and reliable delivery process which ultimately shall result in reduction of project expenses and time. 4.2 Consultant Related Factors The issues of conflicts pertinent to the consulting firms are mostly related to the documentations. The ability of BIM to provide for a proper documentation directory is key to resolution of these issues. The ability of BIM to generate conceptual design, integrated engineering services, construction level modelling and designconstruction integration are key features that shall ensure the timely generation and approvals of VOs, integration between different project documents, prompt delivery of drawings, perform routine inspection and ensure quality assurance and quality control for the consulting organizations. 4.3 Contractor Related Factors The conflicting issues of the Contractor firms are mostly related to construction and site management e.g. poor site management, improper planning, improper construction methods, lack of organizational structure and lack of procurement schedules. The conflicts arise when the contracting firms lose a lot of time and finances for their 349 EESE-2013 is organised by International Society for Commerce, Industry & Engineering. C O N R A C T O R
  • 5. Journal of Energy Technologies and Policy www.iiste.org ISSN 2224-3232 (Paper) ISSN 2225-0573 (Online) Vol.3, No.11, 2013 – Special Issue for International Conference on Energy, Environment and Sustainable Economy (EESE 2013) improper management and they do not get compensated for that even if they are themselves on the fault. The BIM technology provides a very efficient solution for that also. The 3D attribute of BIM helps the Contractors to observe the construction of building in a virtual environment which helps them to improve their site management, construction methods and strengthen their organizational structure as per project requirement. The 4D (time) attribute shall enable the contractor to explore project phasing and construction sequencing of the activities and ensure proper utilization of time frame allotted for completion. The 5D (cost) innovation of BIM can generate automated quantity take-offs and cost estimates at the design stage. If the contractors properly implement this innovation of BIM, it shall enable them to achieve a very comprehensive procurement schedule for them. They will be able to plan their procurements according to the construction phase of the project well before when its actual stage of execution is reached. Conclusions An integrated construction industry capable of continuous improvement towards excellence in a market-driven environment is our vision. By implementation of BIM, all conflicts or clashes between building systems can be worked out prior to physical construction beginning. Some of the long terms gains expected in Malaysian construction industry, by implementation of proposed model based on BIM technology innovations, are • Avoidance of Delays • Integrated Building Structures • Timely Completion • Innovative Project Award And Delivery Mechanisms • Procurement, Engineering And Construction Process • Constructability Analysis • Cost And Schedule Controls • Dispute Resolution Provisions • Research and development Opportunities References Sambasivan M. and Soon.Causes and effects of delays in Malaysian construction industry. International Journal of Project Management, 25 (2007), 517-526 Tumi SAH, Omran A, Pakir AHK . Causes of delays in construction industry in Libya. ICEA-FAA 2009 Fugar, F D K and Agyak wah-Baah, A B. Delays in building construction projects in Ghana. Australasian Journal of Construction Economics and Building,(2010) 10 (1/2) 103-116 Aibinu, A.A. and Jagboro G.O. (2002). The effects of construction delays on project delivery in Nigerian construction industry. International Journal of Project Management, (Elsevier), 20, 593-599. Bryan Shapiro and Shapiro Hankinson & Knutson. Inherent conflicts in the construction industry and the structure of contracts. Understanding the Issues conference Vancouver BC, February 2005, GEN/03273676/26021.1 Abdul-Rahman, H., Berawi, M.A., Berawi, A.R., Mohamed, Othman, M. and Yahya, I.A. (2006). Delay mitigation in the Malaysian construction industry. Journal of Construction Engineering and Management (ASCE), 132.2, 125-133. Acharya NK , Lee Y D , Kim SY, Lee JC, Kim CS. Analysis of construction delay factor : A Korean Prospective. APIEMS Conference 2006, Bankok Thialand . Ogunlana, S.O., Promkuntong, K., and Jearkjirm. V. (1996). Construction delays in a fast growing economy: comparing Thailand with other economies. Int. Journal of Project Management, (Elsevier), 14.1, 37-45. Salman Azhar malik Khalfan and Tayyab Maqsood . Building Information Modeling (BIM) : Now and Beyond. Australasian Journal of Construction Economics and Building Salman Azhar, Alex Behringer B.S. A BIM-based Approach for Communicating and Implementing a Construction Site Safety Plan. 49th ASC Annual International Conference Proceedings, Associated Schools of Construction Salman Azhar. Building Information Modeling (BIM): Trends, Benefits, Risks, and Challenges for the AEC Industry. A.M.ASCE, July 2011, Leadership Manage. Eng. 2011.11:241-252. 350 EESE-2013 is organised by International Society for Commerce, Industry & Engineering.
  • 6. This academic article was published by The International Institute for Science, Technology and Education (IISTE). The IISTE is a pioneer in the Open Access Publishing service based in the U.S. and Europe. The aim of the institute is Accelerating Global Knowledge Sharing. More information about the publisher can be found in the IISTE’s homepage: http://www.iiste.org CALL FOR JOURNAL PAPERS The IISTE is currently hosting more than 30 peer-reviewed academic journals and collaborating with academic institutions around the world. There’s no deadline for submission. Prospective authors of IISTE journals can find the submission instruction on the following page: http://www.iiste.org/journals/ The IISTE editorial team promises to the review and publish all the qualified submissions in a fast manner. All the journals articles are available online to the readers all over the world without financial, legal, or technical barriers other than those inseparable from gaining access to the internet itself. Printed version of the journals is also available upon request of readers and authors. MORE RESOURCES Book publication information: http://www.iiste.org/book/ Recent conferences: http://www.iiste.org/conference/ IISTE Knowledge Sharing Partners EBSCO, Index Copernicus, Ulrich's Periodicals Directory, JournalTOCS, PKP Open Archives Harvester, Bielefeld Academic Search Engine, Elektronische Zeitschriftenbibliothek EZB, Open J-Gate, OCLC WorldCat, Universe Digtial Library , NewJour, Google Scholar