IOSR Journal of Mechanical and Civil Engineering (IOSR-JMCE)
e-ISSN: 2278-1684,p-ISSN: 2320-334X, Volume 12, Issue 1 Ver. IV (Jan- Feb. 2015), PP 08-12
www.iosrjournals.org
DOI: 10.9790/1684-12140812 www.iosrjournals.org 8 | Page
Causes of Delay in Construction of Bridge Girders
Keval J. Shah1
, Prof. M. R. Apte2
1
Post graduate student, Department of Civil Engineering, Maharashtra Institute of Technology,
Pune (Maharashtra, India)
2
Professor Emeritus, Department of Civil Engineering, Maharashtra Institute of Technology, Pune
(Maharashtra, India)
Abstract: The construction industry is the tool through which a society achieves its goal of urban and rural
development. Delays inconstruction are the most serious problems which even slow down the national
development. It is one of the sectors that provides important ingredient for the development of an economy.It is
widely accepted that a project is successful when it is finished on time. Unfortunately, due to many reasons,
largenumber of construction projects fails to follow the planned schedule and hence delayed. Construction
delay is considered to be one of the recurring problems in the construction industry and it has an adverse effect
on project success in terms of time, cost and quality. So, careful study and planning of each and every activity of
a construction project becomes important in order to minimise delays. This paper presents the causes of
delayoccurring on anongoing bridge construction project with respect to constructionof bridge girders of three
spansof a Major bridge across river Sabarmati, Gandhinagar, Gujaratas a case study.
Keywords:Project delay, Types of delay, Time overrun, Cost overrun
I. Introduction
Issue of delay in the construction sector is a worldwideproblem. Delays occur in most construction
projects, either simple or complex. In construction, delay can be defined as the extension of time in the
completion of project. In short delay means failure to complete project in targeted time and budgeted cost as
agreed in contract. Construction site activities are only the second part of the whole construction process. The
first part comprises of all kinds of office work like planning, designing, estimating, negotiating, purchasing,
scheduling, controlling, accounting, etc. are required to be done carefully in the office before the work starts on
the site to accomplish the objective of a project within budget and on schedule. Construction delays are
widespread in most projects around the world. Some delays may happen in the preconstruction phase which is
defined as the period beginning from the initial conception of the project to the signing of the contract between
the owner and the contractor; however some of them may happen in the construction phase that is the period
when actual construction is underway. Project schedules are dynamic and uncertain. Several factors,
controllable and uncontrollable, affect the project schedule and cause delays. These delays definitely create
negative impacts on project performance. Delay in schedule in the completion of a construction project is a
majorproblem for contractors leading to disputes and spoiled relationships between project participants.
The challenge is to measure the net impact of construction delays accurately. In absence of which delay
claims between all parties involved in the construction process would become serious and lead to litigation.Time
for performance of a project is particularly an important consideration for the owner and the contractor. Often,
the most troublesome construction disputes involve delays and failure to complete the work in a timely manner.
In fact, delays can be caused by several parties therefore the effects and remedies vary from case to case.
Concurrent delays are two or more delays occurring at the same time and are always difficult to resolve.
So, in this paper delay occurrences on a bridge project is given with respect to the construction
ofgirders as a case study.
II. Objective Of Study
The objectives of this study are:
1. Determine the major construction delays of the project.
2. To analyse different causes of delay of the project
3. To measure the net impact of construction delays accurately.
III. Construction Delays
There are a number of definitions for delay. In the construction management context, the simplest
definition of a delay is “an event or a condition that results in finishing the project later than stipulated in the
contract.”
There are four main groups of construction delays:
Causes of Delay in Construction of Bridge Girders
DOI: 10.9790/1684-12140812 www.iosrjournals.org 9 | Page
1. Critical or noncritical
2. Excusable or non-excusable
3. Compensable or non-compensable
4. Concurrent or non-concurrent
The diagram displayedin figure presents a general overview of how the construction delays can be
categorized and some of the frequently occurring delays on any infrastructure project and the responsible stack
holder are as follows.
Chart 1: Delay classification
SR. REASONS FOR DELAY RESPONSIBILITY
1. Delay in handing over of site Client
2. Unforeseen ground conditions Consultant
3. Conflicts between owner and other parties Other
4. Improper planning of contractor during bidding stage Contractor
5. Poor means of contracting Contractor
6. Inaccurate specification of site condition Client
7. Unrealistic time schedule given in contract Consultant
8. Faulty soil investigation report Client
9. Slow decision from owner Client
10. Bureaucracy in client's organisation. Client
11. Ambiguity in specifications and conflicting interpretation by parties. Client
12. Unrealistic inspection and testing methods proposed in contract. Client
13. Delay in approval of completed work (i.e. stage passing) Client
14. Delay in approval of shop drawings and samples Client
15. Non availability of drawing/ design on time Client
16. Consultant or Architect's reluctance for change Consultant
17. Obtaining permissions from local authorities Client
18. Poor organizational structure for client or consultant Client/Consultant
19. Financial Constraints of contractor Contactor
20. Delay in running bill payments to the contractor Client
21. Inadequate experience of contractor Contractor
22. Poor labour productivity Contractor
23. Lack of control over subcontractor Contractor
24. Frequent change of subcontractor Contractor
25. Poor site management and supervision Contractor
26. Use of improper or obsolete construction methods Contractor
27. Increase in scope of work Client
28. Rework due to errors in execution Contractor
29. Rework due to change of design or deviation order Client
30. Delay in finalization of rates for extra items Client
31. Poor coordination among parties Client
32. Delay in material delivery by vendors Other
33. Delay in material to be supplied by the owner client
34. Delay in material procurement (action by the contractor) Contractor
35. Change in material prices/ price escalation Other
36. Improper storage of materials leading to damaged material when necessary Contractor
37. Inefficient use of equipment Contractor
38. Lack of skilled operators for specialized equipment Contractor
39. Extreme weather conditions Other
40. Local political conditions Other
41. Restricted access at site Client
42. Site accidents due to lack of safety measures Contractor
43. Site accidents due to Negligence Contractor
44. Lack of motivation for contractor(viz. Incentive for early finish etc.) Client
Causes of Delay in Construction of Bridge Girders
DOI: 10.9790/1684-12140812 www.iosrjournals.org 10 | Page
IV. Research Methodology
Research methodology is designed after assessing the extent of the objectives to be fulfilled. For data
collection a cable stayed Major Bridge across river Sabarmati, Gandhinagar, Gujaratis taken as a case study.
There was a huge difference in rate of progress and time required in completion between planned schedule and
actual execution in girders of three spans constructed on site. Frequent site visits were carried out to find the key
factors that control time performance as well as the factors which govern the rate of progress in order to find out
major as well as general causes of delay in construction of girders.
V. Data Collection
The data collected from site regarding the progress of construction of bridge girders is given in
Appendix-A (planned vs execution period in days).
End cross section of girder
VI. Data Analysis
For data analysis each activity of construction of bridge girders has been compared with its planned
duration andactual duration. Delays occurred in each activity and the cumulative delay are calculated in days as
shown in Appendix B (delay and cumulative delay in days). Also graphs for planned schedule vs as executed
and cumulative delay occurred on each girder are plotted for better understanding of the delay phenomenon.
Total delay caused on the project in completion of girders for 3 spans is 75 days (Appendix B (Delay and
Cumulative delay in days)). Activity wise total delay is shown in following table.
Sr. Activity Delay on Span 1
(Days)
Delay on Span 2
(Days)
Delay on Span 3
(Days)
TotalDelay
(Days)
1 Staging work 3 3 2 8
2 Shuttering Work 7 7 2 16
3 Reinforcement fixing 22 6 6 39
4 Cable arrangement 8 4 0 12
5 Concreting 0 0 0 0
Total 75
There upon reasons of delay and interpretation are discussed in next section.
Chart 1: Cumulative delay
Chart 2: Planned vs Execution.
Causes of Delay in Construction of Bridge Girders
DOI: 10.9790/1684-12140812 www.iosrjournals.org 11 | Page
After careful study of delay occurred on each activity and the reason of delay are worked out and the
stake holders responsible for the delay are as follows.
SR. REASONS FOR DELAY RESPONSIBE PARTY
1 Insufficient crane capacity Contractor
2 Non availability of bar binder Contractor
3 Non availability of skilled labour Contractor
4 Delay in design Client /Consultant
5 Labour issues Contractor
6 Conventional method of bar cutting and bending Contractor
7 Over labour employment on a single work other than important one. Contractor
8 Poor site layout resulting in poor labour productivity Contractor
9 Shortage of Concrete due to insufficient capacity of RMC Contractor
10 Delay in procurement of bearing plate Contractor
Table: Summary of Delay reasons
Above mentioned causes of delay have direct effecton time overrun and cost overrun for the whole
project. Careful identification and mitigation of causes of delay is required to save time and cost. The
comparisonof cumulative delay is shown in Chart 1. It is observed from Chart 1 thatthe construction of girder of
span 1 delayed more than the other two girders. Major cause of delay of construction offirst girder on span 1 is
delay in getting working drawings.Other two girders will not be affected by this reason because all girders are
symmetrical on the bridge. There are also some reasons which affect performance of girder on span 1 such as
labour issues, more number of labours employed on an unimportant work and lack of skilled labours etc.
Another important reason is poor site layout planning. Because of poor site layout planning workers have to
walk more and this resulted in wastage of time and poor labour productivity. Same girder on span 2 gets delayed
by less number of days compared tothat on span 1. Major reason is labour issues. Contractor is responsible for
this delay. Third girder is delayed by 15 days only and major reason for delay is again labour issues.
VII. Conclusion
This study aims to investigate the important causes of delay in construction of bridge girder. Activities
on site with respect to construction of girder are thoroughly observed and comparison done between planned
and as executed schedule. The results revealed that the problem ofdelays in construction of bridge girder is
frequent and notable. Contractor plays vital role in completion of project as scheduled. Most of reasons for
delays are related with contractor performance such as site management, labour productivity, and lack of expert
proficiency in supervision etc. Same as delay in drawing and delay in design come under client responsibility.It
is evident that consultant has a less responsibility. Some of the causes are to be addressed are beyond the control
of all the project parties such as differing site conditions, unforeseen weather etc. Talking about the overall
responsibility of delay, contractor possesses near about more responsibility.
Total time required as per planned scheduleon Span 1 + Span 2 + Span 3 = 150 days but actual time of
execution taken for the same 225 days. Therefore total delay is 75 days.
Causes of Delay in Construction of Bridge Girders
DOI: 10.9790/1684-12140812 www.iosrjournals.org 12 | Page
References
[1] Assaf, S. A., And Al-Hejji S. (2006). “Causes of Delay in Large Construction Projects”. International J. Project Mgmt.,Science Direct,
24, 349-357. 4
[2] Enasfathitaher, R.K.Pandey “Study Of Delay In Project Planning And Design Stage Of Civil Engineering Projects” (2013)
[3] S.K.Patil, A.K.Gupta, D.B.Desai, A.S.Sajane “Causes Of Delay In Indian Transportation Infrastructure Project” (2013)
[4] Jyh-Bin Yang And Chih-Kuei Kao “Review Of Delay Analysis Methods: A Process-Based Comparison” (2008)
[5] Tarek Hegazy And Wail Menesi “Delay Analysis Under Multiple Baseline Updates” (2007)
[6] Muralisambasivan , Yau Wen Soon “Causes And Effects Of Delays In Malaysian Construction Industry”
[7] Ashwiniarunsalunkhe, Rahul S. Patil“Effect Of Construction Delays On Project Time Overrun Indian Scenario (2014)
[8] Ram Singh, “Delays And Cost Overruns In Infrastructure Projects: Extent, Causes And Remedies”, Economic And Political Weekly,
Vol.21. May 22, 2010, Pp 43-54.

Contenu connexe

Tendances

Delay analysis of raw water reservoir and pumping Station
Delay analysis of raw water reservoir and pumping StationDelay analysis of raw water reservoir and pumping Station
Delay analysis of raw water reservoir and pumping Stationchetlapally balakrishna
 
The significant Causes and effects of delays in Ghadir 2206 residential project
The significant Causes and effects of delays in Ghadir 2206 residential projectThe significant Causes and effects of delays in Ghadir 2206 residential project
The significant Causes and effects of delays in Ghadir 2206 residential projectIOSR Journals
 
"Types and Causes of Construction Claims"
"Types and Causes of Construction Claims""Types and Causes of Construction Claims"
"Types and Causes of Construction Claims"Abhishek Shah
 
Project Management
Project ManagementProject Management
Project ManagementAnton Orlov
 
Project Controls Expo - 31st Oct 2012 - Forensic Delay Analysis The Ultimate ...
Project Controls Expo - 31st Oct 2012 - Forensic Delay Analysis The Ultimate ...Project Controls Expo - 31st Oct 2012 - Forensic Delay Analysis The Ultimate ...
Project Controls Expo - 31st Oct 2012 - Forensic Delay Analysis The Ultimate ...Project Controls Expo
 
Extension of time Analysis
Extension of time AnalysisExtension of time Analysis
Extension of time AnalysisFarhan Moosa
 
Construction Project Management Class Project Presentation
Construction Project Management Class Project PresentationConstruction Project Management Class Project Presentation
Construction Project Management Class Project PresentationWayne Holley
 
Claims & disputes management
Claims & disputes managementClaims & disputes management
Claims & disputes managementMohammed Tanbouz
 
FIDIC Lecture - Joint operation of multiple Fidic Forms - A Case Study
FIDIC Lecture - Joint operation of multiple Fidic Forms - A Case StudyFIDIC Lecture - Joint operation of multiple Fidic Forms - A Case Study
FIDIC Lecture - Joint operation of multiple Fidic Forms - A Case StudyKhalil Hasan
 
J.S. Daniel paper for practical checklist of schedule
J.S. Daniel paper for practical checklist of scheduleJ.S. Daniel paper for practical checklist of schedule
J.S. Daniel paper for practical checklist of scheduleJ.S. Daniel
 
J.S. Daniel paper of fast tracking design in megaproject construction
J.S. Daniel paper of fast tracking design in megaproject constructionJ.S. Daniel paper of fast tracking design in megaproject construction
J.S. Daniel paper of fast tracking design in megaproject constructionJ.S. Daniel
 
An Investigation into the Delays in Road Projects in Bahrain
An Investigation into the Delays in Road Projects in BahrainAn Investigation into the Delays in Road Projects in Bahrain
An Investigation into the Delays in Road Projects in BahrainIJRES Journal
 
Variations under the FIDIC form, subject to EU Procurement law
Variations under the FIDIC form, subject to EU Procurement lawVariations under the FIDIC form, subject to EU Procurement law
Variations under the FIDIC form, subject to EU Procurement law39 Essex Chambers
 
Fidic conditions of subcontract agreement
Fidic conditions of subcontract agreementFidic conditions of subcontract agreement
Fidic conditions of subcontract agreementabdmuhaiminyunus
 
J.S. Daniel presentation on planning
J.S. Daniel presentation on planningJ.S. Daniel presentation on planning
J.S. Daniel presentation on planningJ.S. Daniel
 

Tendances (19)

Delay analysis of raw water reservoir and pumping Station
Delay analysis of raw water reservoir and pumping StationDelay analysis of raw water reservoir and pumping Station
Delay analysis of raw water reservoir and pumping Station
 
Kandil_Sameh_AR50123
Kandil_Sameh_AR50123Kandil_Sameh_AR50123
Kandil_Sameh_AR50123
 
The significant Causes and effects of delays in Ghadir 2206 residential project
The significant Causes and effects of delays in Ghadir 2206 residential projectThe significant Causes and effects of delays in Ghadir 2206 residential project
The significant Causes and effects of delays in Ghadir 2206 residential project
 
"Types and Causes of Construction Claims"
"Types and Causes of Construction Claims""Types and Causes of Construction Claims"
"Types and Causes of Construction Claims"
 
Claims
ClaimsClaims
Claims
 
Project Management
Project ManagementProject Management
Project Management
 
Kandil_Sameh_CPMPart 4 _b
Kandil_Sameh_CPMPart 4 _bKandil_Sameh_CPMPart 4 _b
Kandil_Sameh_CPMPart 4 _b
 
Project Controls Expo - 31st Oct 2012 - Forensic Delay Analysis The Ultimate ...
Project Controls Expo - 31st Oct 2012 - Forensic Delay Analysis The Ultimate ...Project Controls Expo - 31st Oct 2012 - Forensic Delay Analysis The Ultimate ...
Project Controls Expo - 31st Oct 2012 - Forensic Delay Analysis The Ultimate ...
 
Extension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed IbarhimExtension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed Ibarhim
 
Extension of time Analysis
Extension of time AnalysisExtension of time Analysis
Extension of time Analysis
 
Construction Project Management Class Project Presentation
Construction Project Management Class Project PresentationConstruction Project Management Class Project Presentation
Construction Project Management Class Project Presentation
 
Claims & disputes management
Claims & disputes managementClaims & disputes management
Claims & disputes management
 
FIDIC Lecture - Joint operation of multiple Fidic Forms - A Case Study
FIDIC Lecture - Joint operation of multiple Fidic Forms - A Case StudyFIDIC Lecture - Joint operation of multiple Fidic Forms - A Case Study
FIDIC Lecture - Joint operation of multiple Fidic Forms - A Case Study
 
J.S. Daniel paper for practical checklist of schedule
J.S. Daniel paper for practical checklist of scheduleJ.S. Daniel paper for practical checklist of schedule
J.S. Daniel paper for practical checklist of schedule
 
J.S. Daniel paper of fast tracking design in megaproject construction
J.S. Daniel paper of fast tracking design in megaproject constructionJ.S. Daniel paper of fast tracking design in megaproject construction
J.S. Daniel paper of fast tracking design in megaproject construction
 
An Investigation into the Delays in Road Projects in Bahrain
An Investigation into the Delays in Road Projects in BahrainAn Investigation into the Delays in Road Projects in Bahrain
An Investigation into the Delays in Road Projects in Bahrain
 
Variations under the FIDIC form, subject to EU Procurement law
Variations under the FIDIC form, subject to EU Procurement lawVariations under the FIDIC form, subject to EU Procurement law
Variations under the FIDIC form, subject to EU Procurement law
 
Fidic conditions of subcontract agreement
Fidic conditions of subcontract agreementFidic conditions of subcontract agreement
Fidic conditions of subcontract agreement
 
J.S. Daniel presentation on planning
J.S. Daniel presentation on planningJ.S. Daniel presentation on planning
J.S. Daniel presentation on planning
 

En vedette

Design and Analysis of Single Microstrip Patch Antenna with Proximity Coupler...
Design and Analysis of Single Microstrip Patch Antenna with Proximity Coupler...Design and Analysis of Single Microstrip Patch Antenna with Proximity Coupler...
Design and Analysis of Single Microstrip Patch Antenna with Proximity Coupler...IOSR Journals
 
Spectrophotometric Determination of Drugs and Pharmaceuticals by Cerium (IV) ...
Spectrophotometric Determination of Drugs and Pharmaceuticals by Cerium (IV) ...Spectrophotometric Determination of Drugs and Pharmaceuticals by Cerium (IV) ...
Spectrophotometric Determination of Drugs and Pharmaceuticals by Cerium (IV) ...IOSR Journals
 
Impact of Biomedical Waste on City Environment :Case Study of Pune India.
Impact of Biomedical Waste on City Environment :Case Study of Pune India.Impact of Biomedical Waste on City Environment :Case Study of Pune India.
Impact of Biomedical Waste on City Environment :Case Study of Pune India.IOSR Journals
 
Phytochemical, cytotoxic, in-vitro antioxidant and anti-microbial investigati...
Phytochemical, cytotoxic, in-vitro antioxidant and anti-microbial investigati...Phytochemical, cytotoxic, in-vitro antioxidant and anti-microbial investigati...
Phytochemical, cytotoxic, in-vitro antioxidant and anti-microbial investigati...IOSR Journals
 
(𝛕𝐢, 𝛕𝐣)− RGB Closed Sets in Bitopological Spaces
(𝛕𝐢, 𝛕𝐣)− RGB Closed Sets in Bitopological Spaces(𝛕𝐢, 𝛕𝐣)− RGB Closed Sets in Bitopological Spaces
(𝛕𝐢, 𝛕𝐣)− RGB Closed Sets in Bitopological SpacesIOSR Journals
 
Traditional use of Monocotyledon Plants of Arakuvalley Mandalam, Visakhapatna...
Traditional use of Monocotyledon Plants of Arakuvalley Mandalam, Visakhapatna...Traditional use of Monocotyledon Plants of Arakuvalley Mandalam, Visakhapatna...
Traditional use of Monocotyledon Plants of Arakuvalley Mandalam, Visakhapatna...IOSR Journals
 
Application of Data Mining Technique in Invasion Recognition
Application of Data Mining Technique in Invasion RecognitionApplication of Data Mining Technique in Invasion Recognition
Application of Data Mining Technique in Invasion RecognitionIOSR Journals
 
Combination of Cubic and Quartic Plane Curve
Combination of Cubic and Quartic Plane CurveCombination of Cubic and Quartic Plane Curve
Combination of Cubic and Quartic Plane CurveIOSR Journals
 
Air Conditioning System with Ground Source Heat Exchanger
Air Conditioning System with Ground Source Heat ExchangerAir Conditioning System with Ground Source Heat Exchanger
Air Conditioning System with Ground Source Heat ExchangerIOSR Journals
 
DC Motor Position Control Using Fuzzy Proportional-Derivative Controllers Wit...
DC Motor Position Control Using Fuzzy Proportional-Derivative Controllers Wit...DC Motor Position Control Using Fuzzy Proportional-Derivative Controllers Wit...
DC Motor Position Control Using Fuzzy Proportional-Derivative Controllers Wit...IOSR Journals
 
50 Hz Frequency Magnetic Field Effects On Pseudomonas Aeruginosa And Bacillus...
50 Hz Frequency Magnetic Field Effects On Pseudomonas Aeruginosa And Bacillus...50 Hz Frequency Magnetic Field Effects On Pseudomonas Aeruginosa And Bacillus...
50 Hz Frequency Magnetic Field Effects On Pseudomonas Aeruginosa And Bacillus...IOSR Journals
 
Modeling Object Oriented Applications by Using Dynamic Information for the I...
Modeling Object Oriented Applications by Using Dynamic  Information for the I...Modeling Object Oriented Applications by Using Dynamic  Information for the I...
Modeling Object Oriented Applications by Using Dynamic Information for the I...IOSR Journals
 
Research Paper Selection Based On an Ontology and Text Mining Technique Using...
Research Paper Selection Based On an Ontology and Text Mining Technique Using...Research Paper Selection Based On an Ontology and Text Mining Technique Using...
Research Paper Selection Based On an Ontology and Text Mining Technique Using...IOSR Journals
 
Spectral studies of 5-({4-amino-2-[(Z)-(2-hydroxybenzylidene) amino] pyrimidi...
Spectral studies of 5-({4-amino-2-[(Z)-(2-hydroxybenzylidene) amino] pyrimidi...Spectral studies of 5-({4-amino-2-[(Z)-(2-hydroxybenzylidene) amino] pyrimidi...
Spectral studies of 5-({4-amino-2-[(Z)-(2-hydroxybenzylidene) amino] pyrimidi...IOSR Journals
 
Membrane Stabilizing And Antimicrobial Activities Of Caladium Bicolor And Che...
Membrane Stabilizing And Antimicrobial Activities Of Caladium Bicolor And Che...Membrane Stabilizing And Antimicrobial Activities Of Caladium Bicolor And Che...
Membrane Stabilizing And Antimicrobial Activities Of Caladium Bicolor And Che...IOSR Journals
 

En vedette (20)

Design and Analysis of Single Microstrip Patch Antenna with Proximity Coupler...
Design and Analysis of Single Microstrip Patch Antenna with Proximity Coupler...Design and Analysis of Single Microstrip Patch Antenna with Proximity Coupler...
Design and Analysis of Single Microstrip Patch Antenna with Proximity Coupler...
 
I012657382
I012657382I012657382
I012657382
 
Spectrophotometric Determination of Drugs and Pharmaceuticals by Cerium (IV) ...
Spectrophotometric Determination of Drugs and Pharmaceuticals by Cerium (IV) ...Spectrophotometric Determination of Drugs and Pharmaceuticals by Cerium (IV) ...
Spectrophotometric Determination of Drugs and Pharmaceuticals by Cerium (IV) ...
 
Impact of Biomedical Waste on City Environment :Case Study of Pune India.
Impact of Biomedical Waste on City Environment :Case Study of Pune India.Impact of Biomedical Waste on City Environment :Case Study of Pune India.
Impact of Biomedical Waste on City Environment :Case Study of Pune India.
 
Phytochemical, cytotoxic, in-vitro antioxidant and anti-microbial investigati...
Phytochemical, cytotoxic, in-vitro antioxidant and anti-microbial investigati...Phytochemical, cytotoxic, in-vitro antioxidant and anti-microbial investigati...
Phytochemical, cytotoxic, in-vitro antioxidant and anti-microbial investigati...
 
(𝛕𝐢, 𝛕𝐣)− RGB Closed Sets in Bitopological Spaces
(𝛕𝐢, 𝛕𝐣)− RGB Closed Sets in Bitopological Spaces(𝛕𝐢, 𝛕𝐣)− RGB Closed Sets in Bitopological Spaces
(𝛕𝐢, 𝛕𝐣)− RGB Closed Sets in Bitopological Spaces
 
Traditional use of Monocotyledon Plants of Arakuvalley Mandalam, Visakhapatna...
Traditional use of Monocotyledon Plants of Arakuvalley Mandalam, Visakhapatna...Traditional use of Monocotyledon Plants of Arakuvalley Mandalam, Visakhapatna...
Traditional use of Monocotyledon Plants of Arakuvalley Mandalam, Visakhapatna...
 
Application of Data Mining Technique in Invasion Recognition
Application of Data Mining Technique in Invasion RecognitionApplication of Data Mining Technique in Invasion Recognition
Application of Data Mining Technique in Invasion Recognition
 
N010637794
N010637794N010637794
N010637794
 
Combination of Cubic and Quartic Plane Curve
Combination of Cubic and Quartic Plane CurveCombination of Cubic and Quartic Plane Curve
Combination of Cubic and Quartic Plane Curve
 
K1303016770
K1303016770K1303016770
K1303016770
 
Air Conditioning System with Ground Source Heat Exchanger
Air Conditioning System with Ground Source Heat ExchangerAir Conditioning System with Ground Source Heat Exchanger
Air Conditioning System with Ground Source Heat Exchanger
 
C1302031319
C1302031319C1302031319
C1302031319
 
DC Motor Position Control Using Fuzzy Proportional-Derivative Controllers Wit...
DC Motor Position Control Using Fuzzy Proportional-Derivative Controllers Wit...DC Motor Position Control Using Fuzzy Proportional-Derivative Controllers Wit...
DC Motor Position Control Using Fuzzy Proportional-Derivative Controllers Wit...
 
J1302024854
J1302024854J1302024854
J1302024854
 
50 Hz Frequency Magnetic Field Effects On Pseudomonas Aeruginosa And Bacillus...
50 Hz Frequency Magnetic Field Effects On Pseudomonas Aeruginosa And Bacillus...50 Hz Frequency Magnetic Field Effects On Pseudomonas Aeruginosa And Bacillus...
50 Hz Frequency Magnetic Field Effects On Pseudomonas Aeruginosa And Bacillus...
 
Modeling Object Oriented Applications by Using Dynamic Information for the I...
Modeling Object Oriented Applications by Using Dynamic  Information for the I...Modeling Object Oriented Applications by Using Dynamic  Information for the I...
Modeling Object Oriented Applications by Using Dynamic Information for the I...
 
Research Paper Selection Based On an Ontology and Text Mining Technique Using...
Research Paper Selection Based On an Ontology and Text Mining Technique Using...Research Paper Selection Based On an Ontology and Text Mining Technique Using...
Research Paper Selection Based On an Ontology and Text Mining Technique Using...
 
Spectral studies of 5-({4-amino-2-[(Z)-(2-hydroxybenzylidene) amino] pyrimidi...
Spectral studies of 5-({4-amino-2-[(Z)-(2-hydroxybenzylidene) amino] pyrimidi...Spectral studies of 5-({4-amino-2-[(Z)-(2-hydroxybenzylidene) amino] pyrimidi...
Spectral studies of 5-({4-amino-2-[(Z)-(2-hydroxybenzylidene) amino] pyrimidi...
 
Membrane Stabilizing And Antimicrobial Activities Of Caladium Bicolor And Che...
Membrane Stabilizing And Antimicrobial Activities Of Caladium Bicolor And Che...Membrane Stabilizing And Antimicrobial Activities Of Caladium Bicolor And Che...
Membrane Stabilizing And Antimicrobial Activities Of Caladium Bicolor And Che...
 

Similaire à Causes of Delay in Construction of Bridge Girders

A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...IRJET Journal
 
IRJET- Delay in Construction its Causes and Mitigation: A Review
IRJET-  	  Delay in Construction its Causes and Mitigation: A ReviewIRJET-  	  Delay in Construction its Causes and Mitigation: A Review
IRJET- Delay in Construction its Causes and Mitigation: A ReviewIRJET Journal
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...IRJET Journal
 
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...IJMER
 
A Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction ProjectsA Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction ProjectsRick Vogel
 
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...IRJET Journal
 
Literature review on_ extension of time
Literature review on_ extension of timeLiterature review on_ extension of time
Literature review on_ extension of timeJoseph Sangpang
 
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...IRJET Journal
 
A Study in Construction Delays of Residential Structures
A Study in Construction Delays of Residential StructuresA Study in Construction Delays of Residential Structures
A Study in Construction Delays of Residential StructuresIRJESJOURNAL
 
Investigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsInvestigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsDr. Amarjeet Singh
 
C. Site managment chapter 5.pptx
C. Site managment chapter 5.pptxC. Site managment chapter 5.pptx
C. Site managment chapter 5.pptxEdenBekele5
 
1616-5398-2-PB.pdf
1616-5398-2-PB.pdf1616-5398-2-PB.pdf
1616-5398-2-PB.pdfEyobMiteku
 
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...IRJET Journal
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction ProjectIRJET Journal
 
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECTHOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECTIRJET Journal
 
Analysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projectsAnalysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projectseSAT Journals
 
Analysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projectsAnalysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projectseSAT Journals
 
Analysis of factors contributing delays and claims in
Analysis of factors contributing delays and claims inAnalysis of factors contributing delays and claims in
Analysis of factors contributing delays and claims ineSAT Publishing House
 
Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...IJERA Editor
 

Similaire à Causes of Delay in Construction of Bridge Girders (20)

A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...
 
IRJET- Delay in Construction its Causes and Mitigation: A Review
IRJET-  	  Delay in Construction its Causes and Mitigation: A ReviewIRJET-  	  Delay in Construction its Causes and Mitigation: A Review
IRJET- Delay in Construction its Causes and Mitigation: A Review
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...
 
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
 
A Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction ProjectsA Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction Projects
 
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
 
Literature review on_ extension of time
Literature review on_ extension of timeLiterature review on_ extension of time
Literature review on_ extension of time
 
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
A Project On Comparative Analysis Of Cost Overrun And Time Delay In Road Cons...
 
A Study in Construction Delays of Residential Structures
A Study in Construction Delays of Residential StructuresA Study in Construction Delays of Residential Structures
A Study in Construction Delays of Residential Structures
 
Investigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure ProjectsInvestigating the Factors Affecting Delays in Infrastructure Projects
Investigating the Factors Affecting Delays in Infrastructure Projects
 
C. Site managment chapter 5.pptx
C. Site managment chapter 5.pptxC. Site managment chapter 5.pptx
C. Site managment chapter 5.pptx
 
1616-5398-2-PB.pdf
1616-5398-2-PB.pdf1616-5398-2-PB.pdf
1616-5398-2-PB.pdf
 
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
 
IRJET- To Study the Causes and Effects of Delays in Construction Project
IRJET-  	  To Study the Causes and Effects of Delays in Construction ProjectIRJET-  	  To Study the Causes and Effects of Delays in Construction Project
IRJET- To Study the Causes and Effects of Delays in Construction Project
 
D012522433
D012522433D012522433
D012522433
 
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECTHOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
 
Analysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projectsAnalysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projects
 
Analysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projectsAnalysis of factors contributing delays and claims in construction projects
Analysis of factors contributing delays and claims in construction projects
 
Analysis of factors contributing delays and claims in
Analysis of factors contributing delays and claims inAnalysis of factors contributing delays and claims in
Analysis of factors contributing delays and claims in
 
Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...
 

Plus de IOSR Journals (20)

A011140104
A011140104A011140104
A011140104
 
M0111397100
M0111397100M0111397100
M0111397100
 
L011138596
L011138596L011138596
L011138596
 
K011138084
K011138084K011138084
K011138084
 
J011137479
J011137479J011137479
J011137479
 
I011136673
I011136673I011136673
I011136673
 
G011134454
G011134454G011134454
G011134454
 
H011135565
H011135565H011135565
H011135565
 
F011134043
F011134043F011134043
F011134043
 
E011133639
E011133639E011133639
E011133639
 
D011132635
D011132635D011132635
D011132635
 
C011131925
C011131925C011131925
C011131925
 
B011130918
B011130918B011130918
B011130918
 
A011130108
A011130108A011130108
A011130108
 
I011125160
I011125160I011125160
I011125160
 
H011124050
H011124050H011124050
H011124050
 
G011123539
G011123539G011123539
G011123539
 
F011123134
F011123134F011123134
F011123134
 
E011122530
E011122530E011122530
E011122530
 
D011121524
D011121524D011121524
D011121524
 

Dernier

VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 

Dernier (20)

VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 

Causes of Delay in Construction of Bridge Girders

  • 1. IOSR Journal of Mechanical and Civil Engineering (IOSR-JMCE) e-ISSN: 2278-1684,p-ISSN: 2320-334X, Volume 12, Issue 1 Ver. IV (Jan- Feb. 2015), PP 08-12 www.iosrjournals.org DOI: 10.9790/1684-12140812 www.iosrjournals.org 8 | Page Causes of Delay in Construction of Bridge Girders Keval J. Shah1 , Prof. M. R. Apte2 1 Post graduate student, Department of Civil Engineering, Maharashtra Institute of Technology, Pune (Maharashtra, India) 2 Professor Emeritus, Department of Civil Engineering, Maharashtra Institute of Technology, Pune (Maharashtra, India) Abstract: The construction industry is the tool through which a society achieves its goal of urban and rural development. Delays inconstruction are the most serious problems which even slow down the national development. It is one of the sectors that provides important ingredient for the development of an economy.It is widely accepted that a project is successful when it is finished on time. Unfortunately, due to many reasons, largenumber of construction projects fails to follow the planned schedule and hence delayed. Construction delay is considered to be one of the recurring problems in the construction industry and it has an adverse effect on project success in terms of time, cost and quality. So, careful study and planning of each and every activity of a construction project becomes important in order to minimise delays. This paper presents the causes of delayoccurring on anongoing bridge construction project with respect to constructionof bridge girders of three spansof a Major bridge across river Sabarmati, Gandhinagar, Gujaratas a case study. Keywords:Project delay, Types of delay, Time overrun, Cost overrun I. Introduction Issue of delay in the construction sector is a worldwideproblem. Delays occur in most construction projects, either simple or complex. In construction, delay can be defined as the extension of time in the completion of project. In short delay means failure to complete project in targeted time and budgeted cost as agreed in contract. Construction site activities are only the second part of the whole construction process. The first part comprises of all kinds of office work like planning, designing, estimating, negotiating, purchasing, scheduling, controlling, accounting, etc. are required to be done carefully in the office before the work starts on the site to accomplish the objective of a project within budget and on schedule. Construction delays are widespread in most projects around the world. Some delays may happen in the preconstruction phase which is defined as the period beginning from the initial conception of the project to the signing of the contract between the owner and the contractor; however some of them may happen in the construction phase that is the period when actual construction is underway. Project schedules are dynamic and uncertain. Several factors, controllable and uncontrollable, affect the project schedule and cause delays. These delays definitely create negative impacts on project performance. Delay in schedule in the completion of a construction project is a majorproblem for contractors leading to disputes and spoiled relationships between project participants. The challenge is to measure the net impact of construction delays accurately. In absence of which delay claims between all parties involved in the construction process would become serious and lead to litigation.Time for performance of a project is particularly an important consideration for the owner and the contractor. Often, the most troublesome construction disputes involve delays and failure to complete the work in a timely manner. In fact, delays can be caused by several parties therefore the effects and remedies vary from case to case. Concurrent delays are two or more delays occurring at the same time and are always difficult to resolve. So, in this paper delay occurrences on a bridge project is given with respect to the construction ofgirders as a case study. II. Objective Of Study The objectives of this study are: 1. Determine the major construction delays of the project. 2. To analyse different causes of delay of the project 3. To measure the net impact of construction delays accurately. III. Construction Delays There are a number of definitions for delay. In the construction management context, the simplest definition of a delay is “an event or a condition that results in finishing the project later than stipulated in the contract.” There are four main groups of construction delays:
  • 2. Causes of Delay in Construction of Bridge Girders DOI: 10.9790/1684-12140812 www.iosrjournals.org 9 | Page 1. Critical or noncritical 2. Excusable or non-excusable 3. Compensable or non-compensable 4. Concurrent or non-concurrent The diagram displayedin figure presents a general overview of how the construction delays can be categorized and some of the frequently occurring delays on any infrastructure project and the responsible stack holder are as follows. Chart 1: Delay classification SR. REASONS FOR DELAY RESPONSIBILITY 1. Delay in handing over of site Client 2. Unforeseen ground conditions Consultant 3. Conflicts between owner and other parties Other 4. Improper planning of contractor during bidding stage Contractor 5. Poor means of contracting Contractor 6. Inaccurate specification of site condition Client 7. Unrealistic time schedule given in contract Consultant 8. Faulty soil investigation report Client 9. Slow decision from owner Client 10. Bureaucracy in client's organisation. Client 11. Ambiguity in specifications and conflicting interpretation by parties. Client 12. Unrealistic inspection and testing methods proposed in contract. Client 13. Delay in approval of completed work (i.e. stage passing) Client 14. Delay in approval of shop drawings and samples Client 15. Non availability of drawing/ design on time Client 16. Consultant or Architect's reluctance for change Consultant 17. Obtaining permissions from local authorities Client 18. Poor organizational structure for client or consultant Client/Consultant 19. Financial Constraints of contractor Contactor 20. Delay in running bill payments to the contractor Client 21. Inadequate experience of contractor Contractor 22. Poor labour productivity Contractor 23. Lack of control over subcontractor Contractor 24. Frequent change of subcontractor Contractor 25. Poor site management and supervision Contractor 26. Use of improper or obsolete construction methods Contractor 27. Increase in scope of work Client 28. Rework due to errors in execution Contractor 29. Rework due to change of design or deviation order Client 30. Delay in finalization of rates for extra items Client 31. Poor coordination among parties Client 32. Delay in material delivery by vendors Other 33. Delay in material to be supplied by the owner client 34. Delay in material procurement (action by the contractor) Contractor 35. Change in material prices/ price escalation Other 36. Improper storage of materials leading to damaged material when necessary Contractor 37. Inefficient use of equipment Contractor 38. Lack of skilled operators for specialized equipment Contractor 39. Extreme weather conditions Other 40. Local political conditions Other 41. Restricted access at site Client 42. Site accidents due to lack of safety measures Contractor 43. Site accidents due to Negligence Contractor 44. Lack of motivation for contractor(viz. Incentive for early finish etc.) Client
  • 3. Causes of Delay in Construction of Bridge Girders DOI: 10.9790/1684-12140812 www.iosrjournals.org 10 | Page IV. Research Methodology Research methodology is designed after assessing the extent of the objectives to be fulfilled. For data collection a cable stayed Major Bridge across river Sabarmati, Gandhinagar, Gujaratis taken as a case study. There was a huge difference in rate of progress and time required in completion between planned schedule and actual execution in girders of three spans constructed on site. Frequent site visits were carried out to find the key factors that control time performance as well as the factors which govern the rate of progress in order to find out major as well as general causes of delay in construction of girders. V. Data Collection The data collected from site regarding the progress of construction of bridge girders is given in Appendix-A (planned vs execution period in days). End cross section of girder VI. Data Analysis For data analysis each activity of construction of bridge girders has been compared with its planned duration andactual duration. Delays occurred in each activity and the cumulative delay are calculated in days as shown in Appendix B (delay and cumulative delay in days). Also graphs for planned schedule vs as executed and cumulative delay occurred on each girder are plotted for better understanding of the delay phenomenon. Total delay caused on the project in completion of girders for 3 spans is 75 days (Appendix B (Delay and Cumulative delay in days)). Activity wise total delay is shown in following table. Sr. Activity Delay on Span 1 (Days) Delay on Span 2 (Days) Delay on Span 3 (Days) TotalDelay (Days) 1 Staging work 3 3 2 8 2 Shuttering Work 7 7 2 16 3 Reinforcement fixing 22 6 6 39 4 Cable arrangement 8 4 0 12 5 Concreting 0 0 0 0 Total 75 There upon reasons of delay and interpretation are discussed in next section. Chart 1: Cumulative delay Chart 2: Planned vs Execution.
  • 4. Causes of Delay in Construction of Bridge Girders DOI: 10.9790/1684-12140812 www.iosrjournals.org 11 | Page After careful study of delay occurred on each activity and the reason of delay are worked out and the stake holders responsible for the delay are as follows. SR. REASONS FOR DELAY RESPONSIBE PARTY 1 Insufficient crane capacity Contractor 2 Non availability of bar binder Contractor 3 Non availability of skilled labour Contractor 4 Delay in design Client /Consultant 5 Labour issues Contractor 6 Conventional method of bar cutting and bending Contractor 7 Over labour employment on a single work other than important one. Contractor 8 Poor site layout resulting in poor labour productivity Contractor 9 Shortage of Concrete due to insufficient capacity of RMC Contractor 10 Delay in procurement of bearing plate Contractor Table: Summary of Delay reasons Above mentioned causes of delay have direct effecton time overrun and cost overrun for the whole project. Careful identification and mitigation of causes of delay is required to save time and cost. The comparisonof cumulative delay is shown in Chart 1. It is observed from Chart 1 thatthe construction of girder of span 1 delayed more than the other two girders. Major cause of delay of construction offirst girder on span 1 is delay in getting working drawings.Other two girders will not be affected by this reason because all girders are symmetrical on the bridge. There are also some reasons which affect performance of girder on span 1 such as labour issues, more number of labours employed on an unimportant work and lack of skilled labours etc. Another important reason is poor site layout planning. Because of poor site layout planning workers have to walk more and this resulted in wastage of time and poor labour productivity. Same girder on span 2 gets delayed by less number of days compared tothat on span 1. Major reason is labour issues. Contractor is responsible for this delay. Third girder is delayed by 15 days only and major reason for delay is again labour issues. VII. Conclusion This study aims to investigate the important causes of delay in construction of bridge girder. Activities on site with respect to construction of girder are thoroughly observed and comparison done between planned and as executed schedule. The results revealed that the problem ofdelays in construction of bridge girder is frequent and notable. Contractor plays vital role in completion of project as scheduled. Most of reasons for delays are related with contractor performance such as site management, labour productivity, and lack of expert proficiency in supervision etc. Same as delay in drawing and delay in design come under client responsibility.It is evident that consultant has a less responsibility. Some of the causes are to be addressed are beyond the control of all the project parties such as differing site conditions, unforeseen weather etc. Talking about the overall responsibility of delay, contractor possesses near about more responsibility. Total time required as per planned scheduleon Span 1 + Span 2 + Span 3 = 150 days but actual time of execution taken for the same 225 days. Therefore total delay is 75 days.
  • 5. Causes of Delay in Construction of Bridge Girders DOI: 10.9790/1684-12140812 www.iosrjournals.org 12 | Page References [1] Assaf, S. A., And Al-Hejji S. (2006). “Causes of Delay in Large Construction Projects”. International J. Project Mgmt.,Science Direct, 24, 349-357. 4 [2] Enasfathitaher, R.K.Pandey “Study Of Delay In Project Planning And Design Stage Of Civil Engineering Projects” (2013) [3] S.K.Patil, A.K.Gupta, D.B.Desai, A.S.Sajane “Causes Of Delay In Indian Transportation Infrastructure Project” (2013) [4] Jyh-Bin Yang And Chih-Kuei Kao “Review Of Delay Analysis Methods: A Process-Based Comparison” (2008) [5] Tarek Hegazy And Wail Menesi “Delay Analysis Under Multiple Baseline Updates” (2007) [6] Muralisambasivan , Yau Wen Soon “Causes And Effects Of Delays In Malaysian Construction Industry” [7] Ashwiniarunsalunkhe, Rahul S. Patil“Effect Of Construction Delays On Project Time Overrun Indian Scenario (2014) [8] Ram Singh, “Delays And Cost Overruns In Infrastructure Projects: Extent, Causes And Remedies”, Economic And Political Weekly, Vol.21. May 22, 2010, Pp 43-54.