SlideShare une entreprise Scribd logo
1  sur  18
Télécharger pour lire hors ligne
Progress Update (Nr. 1)
Week ending 25th September
Programme Update - ITS
Scheme Start on Site : 14th September
Throughout the course of the two weeks we have successfully completed the below:
- Isolated and disconnected the existing mechanical and electrical building services
- Commenced internal strip out and demolitions of the existing building fabric
- Carried out the asbestos removal within the lower ground plant room
- Demolished the existing outbuilding and garage/office areas
- Commenced scaffold to the rear of the building to enable efficient waste removal
Progress Photos – External
Site Compound and external hoardings set up
Progress Photos – External
External outbuilding and
garage/office demolished
Progress Photos – External
Tree protection area set up
around Horse Chestnut Tree
Progress Photos – Internal
Internal soft strip and
demolition works
commenced
Progress Photos – Internal
Progress Photos – Internal
Existing Plant Room now
fully stripped of asbestos
Next Few Weeks………..
A look ahead to works commencing within the next 2 weeks :
- Complete strip out of existing mechanical and electrical building services
- Complete internal soft strip and demolition works
- Remove scaffold & associated rubbish chute at the rear of the building
- Commence external drainage works (including forming new manholes)
- Commence excavation to proposed basement area
- Install temporary propping to basement to assist with excavations
Progress Update (Nr. 2)
Week ending 9th October
Programme Update - ITS
For Period : Mon 28th September – Friday 9th October
- Fully completed strip out of existing mechanical and electrical building services
- Fully completed internal soft strip, demolition and non-structural works
- Removed scaffold & associated rubbish chute at the rear of the building
- Fully completed cut and carve demolition of structures around rear of building
- Commenced external drainage works (including forming new manhole)
- Numerous trial pits excavated and waste samples collected for review off site; in
preparation for groundworks commencing
Progress Photos – Internal
Building now completely
stripped at all floor levels
Progress Photos – Internal
Building now completely
stripped at all floor levels
Progress Photos – Internal
All internal non-structural
walls now removed on each
floor level
Progress Photos – External
Trial pits now complete and
backfilled on site to
establish extent of existing
foundations
Progress Photos – External
All external demolition
works now complete
Next Few Weeks………..
A look ahead to works commencing within the next 2 weeks :
- Commence excavations to the new basement area of the extension and muck away
- Begin excavations of new perimeter retaining walls
- Fully set out new building footprint and excavate necessary pad foundations
- Installation of associated insulation, reinforcement and temporary formwork in
preparation for concrete pours
- Commence new internal flooring infills where redundant staircases removed
- Commence first fix mechanical and electrical works within existing building

Contenu connexe

Similaire à ITS building project progress update 1+2

SCTE Solar Story
SCTE Solar StorySCTE Solar Story
SCTE Solar Story
SCTE
 
PROJECT-Details_Attach_B_Jim Benge 6-14
PROJECT-Details_Attach_B_Jim Benge 6-14PROJECT-Details_Attach_B_Jim Benge 6-14
PROJECT-Details_Attach_B_Jim Benge 6-14
Jim Benge
 
Christian AKL CV-typ.DOC
Christian AKL CV-typ.DOCChristian AKL CV-typ.DOC
Christian AKL CV-typ.DOC
Christian Akl
 

Similaire à ITS building project progress update 1+2 (13)

ITS Building Project - progress update 6
ITS Building Project - progress update 6ITS Building Project - progress update 6
ITS Building Project - progress update 6
 
ITS Building Project - progress update 4
ITS Building Project - progress update 4ITS Building Project - progress update 4
ITS Building Project - progress update 4
 
ITS Building Project - progress update 7
ITS Building Project - progress update 7ITS Building Project - progress update 7
ITS Building Project - progress update 7
 
ITS Building Project - progress update 8
ITS Building Project - progress update 8ITS Building Project - progress update 8
ITS Building Project - progress update 8
 
SCTE Solar Story
SCTE Solar StorySCTE Solar Story
SCTE Solar Story
 
Office Building Constructed in Nine Weeks !
Office Building Constructed in Nine Weeks !Office Building Constructed in Nine Weeks !
Office Building Constructed in Nine Weeks !
 
advanced constructiion technologies
advanced constructiion technologiesadvanced constructiion technologies
advanced constructiion technologies
 
Angeline Kon_Kee Hooi_0302068_BTech1-P1-Alternative Construction Solution and...
Angeline Kon_Kee Hooi_0302068_BTech1-P1-Alternative Construction Solution and...Angeline Kon_Kee Hooi_0302068_BTech1-P1-Alternative Construction Solution and...
Angeline Kon_Kee Hooi_0302068_BTech1-P1-Alternative Construction Solution and...
 
superstructure ppt.ppt
superstructure ppt.pptsuperstructure ppt.ppt
superstructure ppt.ppt
 
PROJECT-Details_Attach_B_Jim Benge 6-14
PROJECT-Details_Attach_B_Jim Benge 6-14PROJECT-Details_Attach_B_Jim Benge 6-14
PROJECT-Details_Attach_B_Jim Benge 6-14
 
Christian akl cv typ
Christian akl cv typChristian akl cv typ
Christian akl cv typ
 
Christian akl cv typ
Christian akl cv typChristian akl cv typ
Christian akl cv typ
 
Christian AKL CV-typ.DOC
Christian AKL CV-typ.DOCChristian AKL CV-typ.DOC
Christian AKL CV-typ.DOC
 

Plus de Institute for Transport Studies (ITS)

Social networks, activities, and travel - building links to understand behaviour
Social networks, activities, and travel - building links to understand behaviourSocial networks, activities, and travel - building links to understand behaviour
Social networks, activities, and travel - building links to understand behaviour
Institute for Transport Studies (ITS)
 
Rail freight in Japan - track access
Rail freight in Japan - track accessRail freight in Japan - track access
Rail freight in Japan - track access
Institute for Transport Studies (ITS)
 

Plus de Institute for Transport Studies (ITS) (20)

Transport Projects Aimed at Fostering Economic Growth – experience in the UK ...
Transport Projects Aimed at Fostering Economic Growth – experience in the UK ...Transport Projects Aimed at Fostering Economic Growth – experience in the UK ...
Transport Projects Aimed at Fostering Economic Growth – experience in the UK ...
 
BA Geography with Transport Studies at the University of Leeds
BA Geography with Transport Studies at the University of LeedsBA Geography with Transport Studies at the University of Leeds
BA Geography with Transport Studies at the University of Leeds
 
Highways Benchmarking - Accelerating Impact
Highways Benchmarking - Accelerating ImpactHighways Benchmarking - Accelerating Impact
Highways Benchmarking - Accelerating Impact
 
Using telematics data to research traffic related air pollution
Using telematics data to research traffic related air pollutionUsing telematics data to research traffic related air pollution
Using telematics data to research traffic related air pollution
 
Masters Dissertation Posters 2017
Masters Dissertation Posters 2017Masters Dissertation Posters 2017
Masters Dissertation Posters 2017
 
Institute for Transport Studies - Masters Open Day 2017
Institute for Transport Studies - Masters Open Day 2017Institute for Transport Studies - Masters Open Day 2017
Institute for Transport Studies - Masters Open Day 2017
 
London's Crossrail Scheme - its evolution, governance, financing and challenges
London's Crossrail Scheme  - its evolution, governance, financing and challengesLondon's Crossrail Scheme  - its evolution, governance, financing and challenges
London's Crossrail Scheme - its evolution, governance, financing and challenges
 
Secretary of State Visit
Secretary of State VisitSecretary of State Visit
Secretary of State Visit
 
Business model innovation for electrical vehicle futures
Business model innovation for electrical vehicle futuresBusiness model innovation for electrical vehicle futures
Business model innovation for electrical vehicle futures
 
A clustering method based on repeated trip behaviour to identify road user cl...
A clustering method based on repeated trip behaviour to identify road user cl...A clustering method based on repeated trip behaviour to identify road user cl...
A clustering method based on repeated trip behaviour to identify road user cl...
 
Cars cars everywhere
Cars cars everywhereCars cars everywhere
Cars cars everywhere
 
Annual Review 2015-16 - University of leeds
Annual Review 2015-16 - University of leedsAnnual Review 2015-16 - University of leeds
Annual Review 2015-16 - University of leeds
 
Social networks, activities, and travel - building links to understand behaviour
Social networks, activities, and travel - building links to understand behaviourSocial networks, activities, and travel - building links to understand behaviour
Social networks, activities, and travel - building links to understand behaviour
 
Rail freight in Japan - track access
Rail freight in Japan - track accessRail freight in Japan - track access
Rail freight in Japan - track access
 
Real time traffic management - challenges and solutions
Real time traffic management - challenges and solutionsReal time traffic management - challenges and solutions
Real time traffic management - challenges and solutions
 
Proportionally fair scheduling for traffic light networks
Proportionally fair scheduling for traffic light networksProportionally fair scheduling for traffic light networks
Proportionally fair scheduling for traffic light networks
 
Capacity maximising traffic signal control policies
Capacity maximising traffic signal control policiesCapacity maximising traffic signal control policies
Capacity maximising traffic signal control policies
 
Bayesian risk assessment of autonomous vehicles
Bayesian risk assessment of autonomous vehiclesBayesian risk assessment of autonomous vehicles
Bayesian risk assessment of autonomous vehicles
 
Agent based car following model for heterogeneities of platoon driving with v...
Agent based car following model for heterogeneities of platoon driving with v...Agent based car following model for heterogeneities of platoon driving with v...
Agent based car following model for heterogeneities of platoon driving with v...
 
A new theory of lane selection on highways
A new theory of lane selection on highwaysA new theory of lane selection on highways
A new theory of lane selection on highways
 

Dernier

1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
QucHHunhnh
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
kauryashika82
 

Dernier (20)

9548086042 for call girls in Indira Nagar with room service
9548086042  for call girls in Indira Nagar  with room service9548086042  for call girls in Indira Nagar  with room service
9548086042 for call girls in Indira Nagar with room service
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptx
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
 
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in DelhiRussian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
Russian Escort Service in Delhi 11k Hotel Foreigner Russian Call Girls in Delhi
 
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
 
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104
 
Class 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfClass 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdf
 
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
IGNOU MSCCFT and PGDCFT Exam Question Pattern: MCFT003 Counselling and Family...
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The Basics
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SD
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..Sports & Fitness Value Added Course FY..
Sports & Fitness Value Added Course FY..
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17
 
fourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingfourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writing
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across Sectors
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy Consulting
 
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
BAG TECHNIQUE Bag technique-a tool making use of public health bag through wh...
 

ITS building project progress update 1+2

  • 1.
  • 2. Progress Update (Nr. 1) Week ending 25th September
  • 3. Programme Update - ITS Scheme Start on Site : 14th September Throughout the course of the two weeks we have successfully completed the below: - Isolated and disconnected the existing mechanical and electrical building services - Commenced internal strip out and demolitions of the existing building fabric - Carried out the asbestos removal within the lower ground plant room - Demolished the existing outbuilding and garage/office areas - Commenced scaffold to the rear of the building to enable efficient waste removal
  • 4. Progress Photos – External Site Compound and external hoardings set up
  • 5. Progress Photos – External External outbuilding and garage/office demolished
  • 6. Progress Photos – External Tree protection area set up around Horse Chestnut Tree
  • 7. Progress Photos – Internal Internal soft strip and demolition works commenced
  • 9. Progress Photos – Internal Existing Plant Room now fully stripped of asbestos
  • 10. Next Few Weeks……….. A look ahead to works commencing within the next 2 weeks : - Complete strip out of existing mechanical and electrical building services - Complete internal soft strip and demolition works - Remove scaffold & associated rubbish chute at the rear of the building - Commence external drainage works (including forming new manholes) - Commence excavation to proposed basement area - Install temporary propping to basement to assist with excavations
  • 11. Progress Update (Nr. 2) Week ending 9th October
  • 12. Programme Update - ITS For Period : Mon 28th September – Friday 9th October - Fully completed strip out of existing mechanical and electrical building services - Fully completed internal soft strip, demolition and non-structural works - Removed scaffold & associated rubbish chute at the rear of the building - Fully completed cut and carve demolition of structures around rear of building - Commenced external drainage works (including forming new manhole) - Numerous trial pits excavated and waste samples collected for review off site; in preparation for groundworks commencing
  • 13. Progress Photos – Internal Building now completely stripped at all floor levels
  • 14. Progress Photos – Internal Building now completely stripped at all floor levels
  • 15. Progress Photos – Internal All internal non-structural walls now removed on each floor level
  • 16. Progress Photos – External Trial pits now complete and backfilled on site to establish extent of existing foundations
  • 17. Progress Photos – External All external demolition works now complete
  • 18. Next Few Weeks……….. A look ahead to works commencing within the next 2 weeks : - Commence excavations to the new basement area of the extension and muck away - Begin excavations of new perimeter retaining walls - Fully set out new building footprint and excavate necessary pad foundations - Installation of associated insulation, reinforcement and temporary formwork in preparation for concrete pours - Commence new internal flooring infills where redundant staircases removed - Commence first fix mechanical and electrical works within existing building