SlideShare une entreprise Scribd logo
1  sur  12
7Aum gam ganapataye namya.




Transition Management:
 Transition Management:
Strategy & Process for High Risk
 Strategy & Process for High
Risk Project for Taking
 Project for Taking Transition in
Transition in the Project Manager
 the Middle as a Middle as a
Project Manager




  Sunil Kumar Sharma, PMP
  Infosys Technologies
Sunil Kumar Sharma, PMP
   Deepali Goyal
Infosys Technologies
  Infosys Technologies
Deepali Goyal
   Ranjan Sopan Kolte
Infosys Technologies
   Infosys Technologies

Ranjan Sopan Kolte
Infosys Technologies
Contents 
   1.1    Abstract .............................................................................................................. 3 
   1.2    Introduction ......................................................................................................... 3 
   1.3    Case under Discussion ....................................................................................... 4 
   1.4    Project Challenges uncovered during transition ................................................. 5 
   1.5    Methodology Adopted for Turn Around .............................................................. 6 
   1.6    Outcome ............................................................................................................. 7 
   1.7    Recommendations .............................................................................................. 8 
   1.8    References ....................................................................................................... 11 
   1.9    Author(s) Profile ................................................................................................ 11 




2|Page
1.1 Abstract
         Does a project manager’s role in a project start with project initiation? Not always! A
         project manager may be required to take over in a project already in execution. How
         does midway transition to a new project manager in a high risk complex project with
         distributed team and stakeholders from across organizations and geographies impact
         the project and new project manager? How do we apply best project management
         practices in transition phase to ensure a smooth takeover and successful
         delivery? Can we assume that outgoing project manager would be a PMP and would
         have followed all the processes and all reports and collaterals can be taken at face
         value? Can we assume that all stakeholders have the correct view of the project and
         roles and responsibilities the way currently defined are signed off? This paper
         attempts to examine taking over a new partially executed project as a separate project
         phase within the project life cycle, a separate process and it relationship with all other
         processes and knowledge areas via a case study of a mid way takeover of a high risk
         project by a PMO certified project manager. Transition process steps, inputs, output
         and collaterals are discussed in light of challenges, risks and learning’s faced during
         the project transition and post transition execution by application of standard project
         management processes. This paper outlines the transition methodology, based on the
         learning from midway transition of a high risk project and issues found and processes
         deployed for transition.
         .


         1.2 Introduction
         First thought when we talk about transition  is  addition of risk to the project. There 
         are  comprehensive  methodologies  for  transition  of  projects  to  new  team  and 
         guidelines for due diligence to ensure minimal addition of risk. It is often found that 
         same  rigor  is  not  applied  for  transition  of  key  roles  to  new  person.  Elaborate 
         mechanisms and guidelines which can be used as a standard are not available. This 
         becomes very crucial for the success of the project when the key role in question is 
         the Project Manager as it adds significant risk to an already high risk projects. In this 
         paper we examine this issue and propose a process for project manager transition. 
                                     
          Project is just not a set of process and documents but has a very big human factor 
         and is influenced by personal management style of the project managers. Initiatives 
         like PMI have helped a lot to being about a standard project management practices 
         but environmental factors, personal leadership style of project manager are still great 
         influencers. Hence a transition is always a risk and could be significant in a high risk 
         complex project. 
          
         Project  manager,  one  taking  over  transition  of  a  project  with  significant  complexity 
         and in advanced stage has  a lot of worry about. Shouldn’t a transition of signed off 
         documents  baselines,  project  plan,  charter  etc  should  enable  the  new  project 
         manager to take over the project and start managing. Answer could be  ’yes’ in some 
         cases and ‘no’ is lot many cases. ‘No’ not because outgoing project manager will play 
         deliberate  mischief  and  may  not  be  trained  in  project  management,  but  more 
         because nature of project management since it is based on progressive elaborations 
         and is in constant state of potential changes. Due to break in continuity lot of things 
         can fall through the gap.  So what could go wrong in a real scenario 

3|Page
 
             •   WBS may not be updated as team may be too busy. One may be surprised to find 
                 out  that  lot  changes  which  team  is  working  on  may  actually  qualify  for  change 
                 requests which no one is taking care of. 
             •   A  close  look  at  updated  WBS  may  reveal  the  budget  left  is  inadequate  and 
                 schedule unachievable 
             •   There may be many undocumented commitments which may not be known till a 
                 deep discussion happens with stakeholders 
             •   Scope  and  estimation  may  not  have  been  done  using  the  standard  techniques 
                 and may be well off the mark. 
             •   Team may not have right skills to do the job and as a new project manager it may 
                 take some time before team members become open about issues unless there is 
                 a conscious attempt during transition 
             •   There  may  be  issues  with  resource  availability  and  issues  which  may  need 
                 immediate escalation but may not be documented. 
             •   There may be changes which should have been initiated by now but are deferred 
                 because of adverse environment.  
             •   Dependencies  may  have  forced  project  manager  to  deviate  from  original  plan 
                 and risks may not be registered. 
             •   Due  to  potential  transition  there  is  a  chance  that  some  processes  may  be 
                 adhered to as diligently 

             When the same project manager continues he may be able to handle many of these 
             things but as a new project manager it is responsibility of new project manager to 
             start with correct baseline and not end up being a person who is bringing new issues 
             though project was sailing smoothly before. With this responsibility on shoulders 
             project manager’s transition becomes a lot more intensive exercise which needs buy 
             in from all stakeholders. A structured and process driven approach can help reduce 
             the uncertainly and risks associated with transition.  
          

             1.3 Case under Discussion
             A global bank GBANK initiated a strategic IT project to develop a core application for 
             its  investment  bank  division.  The  project  was  to  address  regulatory  compliance 
             related  to  assess  the  risk  exposure  of  organization’s  investment  over  several  time 
             steps for multiple investment products. As part of the scope, project had to interface 
             with  multiple  upstream  and  downstream  systems  on  variety  of  technologies.  Any 
             error in final reports to regulatory compliance bodies would result into financial and 
             legal  implications.  GBANK  had  decided  to  execute  this  project  by  outsourcing  it  to 
             vendor  partner  INNVO.  Project  was  structured  to  be  executed  from  multiple 
             locations across US, India and other APAC regions. Because of the regulatory nature 
             of  project  there  was  push  from  business  to  implement  the  application  as  soon  as 
             possible  so  that  business  gets  sufficient  time  to  test  the  outputs.  Owing  to  the 


4|Page
pressures, the stakeholders agreed to start the project. A Project Manager who had 
         managed  small  projects  successfully  in  the  past  was  assigned  the  responsibility  of 
         managing the project. The project in question was being executed on‐schedule with 
         green status till the build phases. During integration, it was realized that some of the 
         components did not tie together well. The reasons for the same can be attributed to 
         multiple  factors  such  as  lack  of  integration  planning,  technological  limitations  and 
         product incompatibility. The problems compounded by the delayed discovery of the 
         issues.  The  team  on  the  ground  had  decided  to  go  for  break‐fix  rather  than  going 
         back to the drawing board as a solution to this problem. This went for a month and 
         then a week before the delivery the Project Manager highlighted the inability to do 
         delivery on time. Extension of 8 weeks was sought. In the second week of extension 
         period  the  Project  Manager  had  to  leave  the  project  because  of  unavoidable 
         circumstances  on  personal  front.  A  PMI  certified  PMP  professional  was  brought  as 
         replacement  and  a  worst  case  transition  of  a  week  was  planned.  The  incoming 
         project  manager  had  planned  for  transition  based  on  the  tenets  of  project 
         management as recommended by PMI.  



         1.4 Project Challenges uncovered during
         transition
         One  of  the  biggest  challenges  faced  by  new  project  manager  was  the 
         misleading/incorrect status reporting. Though prima facie schedule appeared to have 
         been  monitored  and  tracked,  yet  there  was  not  much  evidence  of  monitoring  of 
         other key parameters like cost, quality and scope changes. Project manager listed the 
         potential challenges before putting action plan in place – 
         1. Gap in status reporting from the perspective of completeness and correctness 
         2. Gap in tracking the earned value 
         3. Gap in quality processes institutionalization 
         4. Gap in key  stakeholders communication as huge mismatch in expectation vis‐à‐
            vis the plan and the appraisal of actual progress 
         5. Risk  and  issues  tracking  started  but  was  stopped  sometime  while  the  work 
            pressure started mounting 
         6. Gap in implanting change control process  

         Delving  deep  into  the  issues,  after  initial  few  meetings  as  part  of  transition  it  was 
         quite clear that taking a transition without validation of baseline was like getting into 
         a  minefield.  Following  issues  were  identified  as  potential  isues  in  brainstorming 
         session with Project Manager and key stakeholders ‐ 

         •    Issues in scope definition: It was evident that scope documented and
              WBS don’t look in sync and scope definition was not correct. This will
              depend on project context but scope revalidation is a key activity without
              which a project transition is at serious risk. Hence, a review with all key



5|Page
stakeholders and project sponsor is mandatory in this process. Mere
                 document transfer will not be sufficient.
             •   Issue in estimation: Re-estimation for all the scope changes was not
                 done. Though for an in-flight project there are expected deviations from
                 initial estimations but a sanity check is required to uncover any major risks.
                 A clear understanding of how estimation was done using what
                 methodology and whether enough expert judgment was used are some of
                 key sanity checks.
             •   Issues with Project Plan: Project plan was not updated for major
                 changes during the fire fighting mode. This is the biggest minefield which
                 can reveal a lot about current state of the project. There are a lot of sub
                 plans which hold the key for the project manager
                      o Scope Management and WBS: Need to be closely reviewed to
                          ensure WBS covers all the tasks
                      o Schedule Management
                      o Cost Management
                      o Risk Management
                      o Issues Management
             •   Issues in task allocation: Task allocation was being done on adhoc basis
                 based on the availability of the resources. Skillet and task allocation should
                 be reviewed and rationale understood. Any serious gaps should be
                 presented for stakeholder review .
             •   Issue in Change control: Change control process was not triggered at
                 appropriate time. There could be many changes which were accepted
                 without change control process. Change control process should be
                 triggered for any serious issues having impact on schedule, cost and/or
                 quality.
             •   Issues in Stakeholder communication: Stakeholders may not held a
                 uniform view and correct view of the project. Any such issues should be
                 recorded and remediated.
             •   Contract management: This may look simple but can lead to serious
                 complications. With help of finance department this should also be
                 reviewed.
          
             After the initial analysis it was assessed that a transition and continuation of project 
             AS‐IS will take 7 months for completion.


             1.5 Methodology Adopted for Turn Around
             For transition it was decided this will be done by adopting a process driven approach 
             rather than treat it like a person transition. Approach adopted is described below ‐ 




6|Page
Initiation – This phase involves kick‐off of the transition, stakeholder communication 
         about  the  change,  gathering  all  the  relevant  artifacts  for  transition  and 
         understanding the health of the project. Ground work for the validation and analysis 
         phase is done during this phase 
          
         Validation – This is a crucial phase as it involves re‐assessment of the project health 
         by a new eye. 
          
         Analysis and Recommendation – This phase is equally crucial as the Validation phase 
         because  it  involves  identification  of  gaps,  re‐assessment  of  risk  and  the  more 
         important of all alignment of all the stakeholders about the project health 
    
         Closure  –  Transition  closure  can  be  looked  upon  as  a  course  correction  and 
         continuation  of  the  journey  towards  successful  completion  of  the  project.  All  the 
         modified artifacts are baselined and form the basis for driving the future course.


         1.6 Outcome
         The  project  was  completed  successfully  and  handed  over  to  business  within  the 
         revised budget and two months ahead of the schedule revised during the transition




7|Page
1.7
         1 Reco
              ommend
                   dations
         We would like to recommend a process for project m
         W                                                        manager transsition to be in
                                                                                             ncluded 
         inn PMBOK as a a separate pro  ocess so thatt it can be ensured that Pr
                                                                               roject Manag  gers are 
         abble to take ov
                        ver in‐flight project and ma anage it in ac
                                                                  ccordance witth principles l
                                                                                             laid out 
         by PMI  to  enh
            y           hance  the  pr roject  success rate.  Propo
                                                      s           osed  Project  Manager  traansition 
         pr rocess‐  
          
          




                                                                                                       


          
          
          
         Trransition Initi
                         iation Phase
         During  transit tion  initiation  phase  pro oject  manag gets  to  know  about basic 
                                                                  ger                         t 
         obbjectives of the project , b brief history o
                                                      of the project
                                                                   t , get to know basic struccture of 
         prroject  docummentation  and  a  brief  int troduction  with  key  stake
                                                                                 eholder.  Belo is  a 
                                                                                              ow 
         suummary  list  of  document ,reports  and  factors  w
                                        ts                        which  should  be  covered  in  this 


8|Page
phase.  An  updated  transition  planning  checklist  will  be  key  output  for  successful 
         transition. 
          
         Plans                        Reports and Records             Environment and Other 
                                                                      factors 

           •      Project Charter      •    Record of change            •   Lead time taken for 
           •      Project                   requests (scope                 closure of issues  
                  Management Plan           changes)                    •   Involvement of 
                  and sub‐plans        •    Risk Review Reports             appropriate 
           •      Schedule             •    Record of plan                  stakeholders  
           •      Risk Records              changes and re‐             •   Confirmation on 
           •      Issue Logs                baselines                       stakeholders 
           •      Scope and scope      •    Record of estimation            understanding of 
                  change requests           changes and schedule            their roles and 
           •      Baseline                  re‐baselines                    responsibilities 
                  acceptance           •    Review of cost and          •   SME co‐operation and 
                  criteria                  schedule adherence              availability 
                                       •    Review of latest issue      •   Team motivation and 
                                            logs and status                 people issues (if any) 
                                       •    Stakeholder                 •   Changes in team and 
                                            communication                   attrition 
                                            records                     •   Understanding of 
                                       •    Milestone review                business drivers for 
                                            reports                         the project, any 
                                                                            critical dependencies, 
                                                                            legal and regulatory 
                                                                            implications for client 
                                                                        •   Elicitation of specific 
                                                                            undocumented 
                                                                            requirements or 
                                                                            expectations from the 
                                                                            stakeholders 
    
         Transition Planning Phase  
     
         After transition initiation phase based on  information received a detailed transition 
         plan is prepared using the checklist. Some of the best practices are  
         • Project manager should get buy in from all stakeholders about their availability 
             as required. 
         • Transition plan should reflect the resource and SME availability, factor lead 
             time for any access, approval, legal and security aspects . 
         • Transition plan should cover all areas of transition checklist. 
         • A  reasonable  time  should  be  assumed  for  validation  phase  and  expert  s 
             availability for the same should be factored. 


9|Page
Baseline Validation Phase 
                
               Base line validation is the most important step in project manager transition process. 
               In this phase focus should be retained on issues finding if any and documenting the 
               same. Some of the best practices for the phase are  
               •    Analysis of the gaps is separated as a process steps as that steps may need 
                    a more complete picture and ad‐hoc analysis should be avoided.  
               •    Issue  log  should  be  shared  with  stakeholders  only  on  need  to  know  basis 
                    during the process to avoid unnecessary alarm. 
               •    Final issue log should be shared with all relevant stakeholders 

       
               Gap Analysis and Stakeholder Communication Process 
       
               Once  the  issues  in  base  line  validation  phase  are  available  next  steps  is  analysis  of 
               gaps  with  relevant  stakeholders  to  understand  the  impact  .  Following  actions  may 
               result from this phase  
       
               •    Some  part  of  impact  may  introduce  a  reasonable  risk  which  in  which  case  risk 
                    register needs to be updated.  
               •    Some  issues,  like  gaps  in  documentation,  small  missing  portions  in  WBS  and 
                    communication  and  perception  gap,  may  be  possible  to  remediate  and  same 
                    should be done. 
               •    For  some  of  larger  impact  issues  change  control  process  may  need  to  be 
                    triggered 

       
               Change Control Process 
       
               Once  stakeholders  have  reviewed  the  gaps  and  there  is  agreement  on  triggering 
               change  control  process  then  change  requests  should  be  raised  and  process  assets 
               modified accordingly. 
               •    Impact on cost, schedule and impact should be documented  
               •    Risk register should be updated 
               •    Project plan and WBS should be updated  
               •    Communication management plan should be updated 

               Once  change  are  approved  then  a  new  baseline  should  be  created  for  the  project 
               which  should  reflect  current  status  ,  understanding  of  scope,  roles  and 
               responsibilities, risks , budget and schedule.  
       
       
       
       


10 | P a g e
Stakeholder’s Review and Project takeover  
                                       
               New baseline should be reviewed by all stakeholders. Stakeholder should be briefed 
               about  
               • How gaps have been addressed 
               • Impact of changes  
               • Review of risk register  

               Upon stakeholder  approval project manager  should take over the project and 
               start Managing. 


               1.8 References
               1. PMBOK Version  

               © 2009 Infosys Technologies Limited.

               ALL RIGHTS RESERVED

               Copyright in whole and in part of this document “Infosys Virtual Concierge Solution” belongs
               to Infosys Technologies Limited. This work may not be used, sold, transferred, adapted,
               abridged, copied or reproduced in whole or in part in any manner or form or in any media
               without the prior written consent of Infosys Technologies Limited.


               1.9 Author(s) Profile




                                         
       
               Sunil Kumar Sharma, is a Sr Project Manager with Infosys. He has diverse
               experience in project and program management of IT services delivery, solution
               design, outsourcing and client relationship management

               E-mail: sunil_sharma@infosys.com




11 | P a g e
Deepali is a Senior Project Manager with Infosys Technologies Limited. She has over
               16 years of experience in project and program management of IT consulting, solutions
               and services.

               E-mail: deepali_goyal@infosys.com




               Ranjan is a Senior Project Manager with Infosys Technologies Limited. He 
               has over 10 years of experience in Project and Program Management. He 
               has managed complex programs which required transition from clients 
               and multi‐vendor from multiple locations across the globe.  

               E-mail: ranjankolte@infosys.com;  
                       ranjan_kolte@yahoo.com  




12 | P a g e

Contenu connexe

Tendances

Old definition of project management
Old definition of project managementOld definition of project management
Old definition of project management
Arlen Mark
 
Project mangement chp 1 12
Project mangement chp 1 12Project mangement chp 1 12
Project mangement chp 1 12
Dreams Design
 
Duncan.william
Duncan.williamDuncan.william
Duncan.william
NASAPMC
 
Cassidy.jim
Cassidy.jimCassidy.jim
Cassidy.jim
NASAPMC
 
Definition Of Project Management
Definition Of Project ManagementDefinition Of Project Management
Definition Of Project Management
Mostafa Ewees
 
SDPM - Lecture 2 -The STEP WISE Approach to Project Planning
SDPM - Lecture 2 -The STEP WISE Approach to Project PlanningSDPM - Lecture 2 -The STEP WISE Approach to Project Planning
SDPM - Lecture 2 -The STEP WISE Approach to Project Planning
OpenLearningLab
 

Tendances (20)

Trn 05
Trn 05Trn 05
Trn 05
 
Rapid assessment and recovery of troubled projects
Rapid assessment and recovery of troubled projectsRapid assessment and recovery of troubled projects
Rapid assessment and recovery of troubled projects
 
Top Ten Obstacles To Project Success
Top Ten Obstacles To Project SuccessTop Ten Obstacles To Project Success
Top Ten Obstacles To Project Success
 
Old definition of project management
Old definition of project managementOld definition of project management
Old definition of project management
 
5 Key Chart Project Management (TM) Methodology
5 Key Chart Project Management (TM) Methodology5 Key Chart Project Management (TM) Methodology
5 Key Chart Project Management (TM) Methodology
 
Project Recovery
Project RecoveryProject Recovery
Project Recovery
 
Project mangement chp 1 12
Project mangement chp 1 12Project mangement chp 1 12
Project mangement chp 1 12
 
Demo project planning and control training with lego
Demo project planning and control training with legoDemo project planning and control training with lego
Demo project planning and control training with lego
 
Duncan.william
Duncan.williamDuncan.william
Duncan.william
 
Immutable principles of project management (fw pmi)(v4)
Immutable principles of project management (fw pmi)(v4)Immutable principles of project management (fw pmi)(v4)
Immutable principles of project management (fw pmi)(v4)
 
10 tips to rescue a problem project
10 tips to rescue a problem project10 tips to rescue a problem project
10 tips to rescue a problem project
 
Project Management Best Practices: Brock Boddie/General Assembly
Project Management Best Practices: Brock Boddie/General AssemblyProject Management Best Practices: Brock Boddie/General Assembly
Project Management Best Practices: Brock Boddie/General Assembly
 
Cassidy.jim
Cassidy.jimCassidy.jim
Cassidy.jim
 
Definition Of Project Management
Definition Of Project ManagementDefinition Of Project Management
Definition Of Project Management
 
Iss 03
Iss 03Iss 03
Iss 03
 
SDPM - Lecture 2 -The STEP WISE Approach to Project Planning
SDPM - Lecture 2 -The STEP WISE Approach to Project PlanningSDPM - Lecture 2 -The STEP WISE Approach to Project Planning
SDPM - Lecture 2 -The STEP WISE Approach to Project Planning
 
12 Step Program and 12 Reasons why PRojects Fail
12 Step Program and 12 Reasons why PRojects Fail12 Step Program and 12 Reasons why PRojects Fail
12 Step Program and 12 Reasons why PRojects Fail
 
English Vocabulary for Project Management (Part 1)
English Vocabulary for Project Management (Part 1)English Vocabulary for Project Management (Part 1)
English Vocabulary for Project Management (Part 1)
 
P070 a simple_view_of_complexity
P070 a simple_view_of_complexityP070 a simple_view_of_complexity
P070 a simple_view_of_complexity
 
Lecture 2. project management – Description (1)
Lecture 2. project management – Description (1)Lecture 2. project management – Description (1)
Lecture 2. project management – Description (1)
 

En vedette (9)

Upp7
Upp7Upp7
Upp7
 
PMI - Portfolio Management
PMI - Portfolio ManagementPMI - Portfolio Management
PMI - Portfolio Management
 
Upp
UppUpp
Upp
 
Gaurav hazra pmi india 2010
Gaurav hazra   pmi india 2010Gaurav hazra   pmi india 2010
Gaurav hazra pmi india 2010
 
PMIufa_2014-03-25
PMIufa_2014-03-25PMIufa_2014-03-25
PMIufa_2014-03-25
 
анализ денежного потока
анализ денежного потокаанализ денежного потока
анализ денежного потока
 
PfMP - A Practical Guide to Project Portfolio Management
PfMP - A Practical Guide to  Project Portfolio ManagementPfMP - A Practical Guide to  Project Portfolio Management
PfMP - A Practical Guide to Project Portfolio Management
 
Portfolio Management Processes Flow
Portfolio Management Processes FlowPortfolio Management Processes Flow
Portfolio Management Processes Flow
 
From Balanced Scorecard to Project Portfolio Management
From Balanced Scorecard to Project Portfolio ManagementFrom Balanced Scorecard to Project Portfolio Management
From Balanced Scorecard to Project Portfolio Management
 

Similaire à Iss 06

Presentation by beebejan valiyakath
Presentation by beebejan valiyakathPresentation by beebejan valiyakath
Presentation by beebejan valiyakath
PMI_IREP_TP
 
Project Management Msc. 7Pjmn009W Project Management Project.
Project Management Msc. 7Pjmn009W Project Management Project.Project Management Msc. 7Pjmn009W Project Management Project.
Project Management Msc. 7Pjmn009W Project Management Project.
Renee Jones
 
Project Plan For A Project Management Project
Project Plan For A Project Management ProjectProject Plan For A Project Management Project
Project Plan For A Project Management Project
Mary Stevenson
 
How to Avoid Project Train Wrecks
How to Avoid Project Train WrecksHow to Avoid Project Train Wrecks
How to Avoid Project Train Wrecks
Pete Luan
 
Project management unit 5(1)
Project management unit 5(1)Project management unit 5(1)
Project management unit 5(1)
Rintu Das
 
Project Manager Primer
Project Manager PrimerProject Manager Primer
Project Manager Primer
Tom Cremins
 
2 Project Management Life CycleKemaltaneriStockThinkstoc.docx
2 Project Management Life CycleKemaltaneriStockThinkstoc.docx2 Project Management Life CycleKemaltaneriStockThinkstoc.docx
2 Project Management Life CycleKemaltaneriStockThinkstoc.docx
eugeniadean34240
 
Critical thinking Project Management.docx
Critical thinking Project Management.docxCritical thinking Project Management.docx
Critical thinking Project Management.docx
write31
 
Critical thinking Project Management.docx
Critical thinking Project Management.docxCritical thinking Project Management.docx
Critical thinking Project Management.docx
write22
 

Similaire à Iss 06 (20)

Presentation by beebejan valiyakath
Presentation by beebejan valiyakathPresentation by beebejan valiyakath
Presentation by beebejan valiyakath
 
Project Management Msc. 7Pjmn009W Project Management Project.
Project Management Msc. 7Pjmn009W Project Management Project.Project Management Msc. 7Pjmn009W Project Management Project.
Project Management Msc. 7Pjmn009W Project Management Project.
 
Project Plan For A Project Management Project
Project Plan For A Project Management ProjectProject Plan For A Project Management Project
Project Plan For A Project Management Project
 
How to Avoid Project Train Wrecks
How to Avoid Project Train WrecksHow to Avoid Project Train Wrecks
How to Avoid Project Train Wrecks
 
10 Project Management Mistakes
10 Project Management Mistakes10 Project Management Mistakes
10 Project Management Mistakes
 
BPP Training on Project Management - Day 1
BPP Training on Project Management - Day 1BPP Training on Project Management - Day 1
BPP Training on Project Management - Day 1
 
Project Life Cycle final.pptx
Project Life Cycle final.pptxProject Life Cycle final.pptx
Project Life Cycle final.pptx
 
Project management unit 5(1)
Project management unit 5(1)Project management unit 5(1)
Project management unit 5(1)
 
Project Manager Primer
Project Manager PrimerProject Manager Primer
Project Manager Primer
 
Mega project not mega problems session 1
Mega project not mega problems session 1Mega project not mega problems session 1
Mega project not mega problems session 1
 
An introduction to project management
An introduction to project management An introduction to project management
An introduction to project management
 
Project management
Project managementProject management
Project management
 
Communication 1
Communication 1Communication 1
Communication 1
 
2 Project Management Life CycleKemaltaneriStockThinkstoc.docx
2 Project Management Life CycleKemaltaneriStockThinkstoc.docx2 Project Management Life CycleKemaltaneriStockThinkstoc.docx
2 Project Management Life CycleKemaltaneriStockThinkstoc.docx
 
Project management [module 1]
Project management [module 1]Project management [module 1]
Project management [module 1]
 
UNIT-1.pptx
UNIT-1.pptxUNIT-1.pptx
UNIT-1.pptx
 
Project management for technologies MGT410
Project management for technologies   MGT410Project management for technologies   MGT410
Project management for technologies MGT410
 
Critical thinking Project Management.docx
Critical thinking Project Management.docxCritical thinking Project Management.docx
Critical thinking Project Management.docx
 
Critical thinking Project Management.docx
Critical thinking Project Management.docxCritical thinking Project Management.docx
Critical thinking Project Management.docx
 
Project Management
Project ManagementProject Management
Project Management
 

Plus de PMInstituteIndia (20)

Piyush govil archana_sharma
Piyush govil  archana_sharmaPiyush govil  archana_sharma
Piyush govil archana_sharma
 
D john peter
D john peterD john peter
D john peter
 
Trn 10
Trn 10Trn 10
Trn 10
 
Trn 11
Trn 11Trn 11
Trn 11
 
Trn 09
Trn 09Trn 09
Trn 09
 
Trn 08
Trn 08Trn 08
Trn 08
 
Trn 07
Trn 07Trn 07
Trn 07
 
Trn 06
Trn 06Trn 06
Trn 06
 
Trn 04
Trn 04Trn 04
Trn 04
 
Trn 03
Trn 03Trn 03
Trn 03
 
Trn 02
Trn 02Trn 02
Trn 02
 
Trn 01
Trn 01Trn 01
Trn 01
 
Trn 12
Trn 12Trn 12
Trn 12
 
Sps 01
Sps 01Sps 01
Sps 01
 
Sft 03
Sft 03Sft 03
Sft 03
 
Sft 02
Sft 02Sft 02
Sft 02
 
Sft 01
Sft 01Sft 01
Sft 01
 
Sft 04
Sft 04Sft 04
Sft 04
 
Rsc 06
Rsc 06Rsc 06
Rsc 06
 
Rsc 05
Rsc 05Rsc 05
Rsc 05
 

Dernier

0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
Renandantas16
 
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
lizamodels9
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Dipal Arora
 
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
amitlee9823
 
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
amitlee9823
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
lizamodels9
 
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
dollysharma2066
 

Dernier (20)

Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
 
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Service
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear Regression
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and pains
 
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxB.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptx
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
 
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with Culture
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
 
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
 
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
 

Iss 06

  • 1. 7Aum gam ganapataye namya. Transition Management: Transition Management: Strategy & Process for High Risk Strategy & Process for High Risk Project for Taking Project for Taking Transition in Transition in the Project Manager the Middle as a Middle as a Project Manager Sunil Kumar Sharma, PMP Infosys Technologies Sunil Kumar Sharma, PMP Deepali Goyal Infosys Technologies Infosys Technologies Deepali Goyal Ranjan Sopan Kolte Infosys Technologies Infosys Technologies Ranjan Sopan Kolte Infosys Technologies
  • 2. Contents  1.1  Abstract .............................................................................................................. 3  1.2  Introduction ......................................................................................................... 3  1.3  Case under Discussion ....................................................................................... 4  1.4  Project Challenges uncovered during transition ................................................. 5  1.5  Methodology Adopted for Turn Around .............................................................. 6  1.6  Outcome ............................................................................................................. 7  1.7  Recommendations .............................................................................................. 8  1.8  References ....................................................................................................... 11  1.9  Author(s) Profile ................................................................................................ 11  2|Page
  • 3. 1.1 Abstract Does a project manager’s role in a project start with project initiation? Not always! A project manager may be required to take over in a project already in execution. How does midway transition to a new project manager in a high risk complex project with distributed team and stakeholders from across organizations and geographies impact the project and new project manager? How do we apply best project management practices in transition phase to ensure a smooth takeover and successful delivery? Can we assume that outgoing project manager would be a PMP and would have followed all the processes and all reports and collaterals can be taken at face value? Can we assume that all stakeholders have the correct view of the project and roles and responsibilities the way currently defined are signed off? This paper attempts to examine taking over a new partially executed project as a separate project phase within the project life cycle, a separate process and it relationship with all other processes and knowledge areas via a case study of a mid way takeover of a high risk project by a PMO certified project manager. Transition process steps, inputs, output and collaterals are discussed in light of challenges, risks and learning’s faced during the project transition and post transition execution by application of standard project management processes. This paper outlines the transition methodology, based on the learning from midway transition of a high risk project and issues found and processes deployed for transition. . 1.2 Introduction First thought when we talk about transition  is  addition of risk to the project. There  are  comprehensive  methodologies  for  transition  of  projects  to  new  team  and  guidelines for due diligence to ensure minimal addition of risk. It is often found that  same  rigor  is  not  applied  for  transition  of  key  roles  to  new  person.  Elaborate  mechanisms and guidelines which can be used as a standard are not available. This  becomes very crucial for the success of the project when the key role in question is  the Project Manager as it adds significant risk to an already high risk projects. In this  paper we examine this issue and propose a process for project manager transition.     Project is just not a set of process and documents but has a very big human factor  and is influenced by personal management style of the project managers. Initiatives  like PMI have helped a lot to being about a standard project management practices  but environmental factors, personal leadership style of project manager are still great  influencers. Hence a transition is always a risk and could be significant in a high risk  complex project.    Project  manager,  one  taking  over  transition  of  a  project  with  significant  complexity  and in advanced stage has  a lot of worry about. Shouldn’t a transition of signed off  documents  baselines,  project  plan,  charter  etc  should  enable  the  new  project  manager to take over the project and start managing. Answer could be  ’yes’ in some  cases and ‘no’ is lot many cases. ‘No’ not because outgoing project manager will play  deliberate  mischief  and  may  not  be  trained  in  project  management,  but  more  because nature of project management since it is based on progressive elaborations  and is in constant state of potential changes. Due to break in continuity lot of things  can fall through the gap.  So what could go wrong in a real scenario  3|Page
  • 4.   • WBS may not be updated as team may be too busy. One may be surprised to find  out  that  lot  changes  which  team  is  working  on  may  actually  qualify  for  change  requests which no one is taking care of.  • A  close  look  at  updated  WBS  may  reveal  the  budget  left  is  inadequate  and  schedule unachievable  • There may be many undocumented commitments which may not be known till a  deep discussion happens with stakeholders  • Scope  and  estimation  may  not  have  been  done  using  the  standard  techniques  and may be well off the mark.  • Team may not have right skills to do the job and as a new project manager it may  take some time before team members become open about issues unless there is  a conscious attempt during transition  • There  may  be  issues  with  resource  availability  and  issues  which  may  need  immediate escalation but may not be documented.  • There may be changes which should have been initiated by now but are deferred  because of adverse environment.   • Dependencies  may  have  forced  project  manager  to  deviate  from  original  plan  and risks may not be registered.  • Due  to  potential  transition  there  is  a  chance  that  some  processes  may  be  adhered to as diligently  When the same project manager continues he may be able to handle many of these  things but as a new project manager it is responsibility of new project manager to  start with correct baseline and not end up being a person who is bringing new issues  though project was sailing smoothly before. With this responsibility on shoulders  project manager’s transition becomes a lot more intensive exercise which needs buy  in from all stakeholders. A structured and process driven approach can help reduce  the uncertainly and risks associated with transition.     1.3 Case under Discussion A global bank GBANK initiated a strategic IT project to develop a core application for  its  investment  bank  division.  The  project  was  to  address  regulatory  compliance  related  to  assess  the  risk  exposure  of  organization’s  investment  over  several  time  steps for multiple investment products. As part of the scope, project had to interface  with  multiple  upstream  and  downstream  systems  on  variety  of  technologies.  Any  error in final reports to regulatory compliance bodies would result into financial and  legal  implications.  GBANK  had  decided  to  execute  this  project  by  outsourcing  it  to  vendor  partner  INNVO.  Project  was  structured  to  be  executed  from  multiple  locations across US, India and other APAC regions. Because of the regulatory nature  of  project  there  was  push  from  business  to  implement  the  application  as  soon  as  possible  so  that  business  gets  sufficient  time  to  test  the  outputs.  Owing  to  the  4|Page
  • 5. pressures, the stakeholders agreed to start the project. A Project Manager who had  managed  small  projects  successfully  in  the  past  was  assigned  the  responsibility  of  managing the project. The project in question was being executed on‐schedule with  green status till the build phases. During integration, it was realized that some of the  components did not tie together well. The reasons for the same can be attributed to  multiple  factors  such  as  lack  of  integration  planning,  technological  limitations  and  product incompatibility. The problems compounded by the delayed discovery of the  issues.  The  team  on  the  ground  had  decided  to  go  for  break‐fix  rather  than  going  back to the drawing board as a solution to this problem. This went for a month and  then a week before the delivery the Project Manager highlighted the inability to do  delivery on time. Extension of 8 weeks was sought. In the second week of extension  period  the  Project  Manager  had  to  leave  the  project  because  of  unavoidable  circumstances  on  personal  front.  A  PMI  certified  PMP  professional  was  brought  as  replacement  and  a  worst  case  transition  of  a  week  was  planned.  The  incoming  project  manager  had  planned  for  transition  based  on  the  tenets  of  project  management as recommended by PMI.   1.4 Project Challenges uncovered during transition One  of  the  biggest  challenges  faced  by  new  project  manager  was  the  misleading/incorrect status reporting. Though prima facie schedule appeared to have  been  monitored  and  tracked,  yet  there  was  not  much  evidence  of  monitoring  of  other key parameters like cost, quality and scope changes. Project manager listed the  potential challenges before putting action plan in place –  1. Gap in status reporting from the perspective of completeness and correctness  2. Gap in tracking the earned value  3. Gap in quality processes institutionalization  4. Gap in key  stakeholders communication as huge mismatch in expectation vis‐à‐ vis the plan and the appraisal of actual progress  5. Risk  and  issues  tracking  started  but  was  stopped  sometime  while  the  work  pressure started mounting  6. Gap in implanting change control process   Delving  deep  into  the  issues,  after  initial  few  meetings  as  part  of  transition  it  was  quite clear that taking a transition without validation of baseline was like getting into  a  minefield.  Following  issues  were  identified  as  potential  isues  in  brainstorming  session with Project Manager and key stakeholders ‐  • Issues in scope definition: It was evident that scope documented and WBS don’t look in sync and scope definition was not correct. This will depend on project context but scope revalidation is a key activity without which a project transition is at serious risk. Hence, a review with all key 5|Page
  • 6. stakeholders and project sponsor is mandatory in this process. Mere document transfer will not be sufficient. • Issue in estimation: Re-estimation for all the scope changes was not done. Though for an in-flight project there are expected deviations from initial estimations but a sanity check is required to uncover any major risks. A clear understanding of how estimation was done using what methodology and whether enough expert judgment was used are some of key sanity checks. • Issues with Project Plan: Project plan was not updated for major changes during the fire fighting mode. This is the biggest minefield which can reveal a lot about current state of the project. There are a lot of sub plans which hold the key for the project manager o Scope Management and WBS: Need to be closely reviewed to ensure WBS covers all the tasks o Schedule Management o Cost Management o Risk Management o Issues Management • Issues in task allocation: Task allocation was being done on adhoc basis based on the availability of the resources. Skillet and task allocation should be reviewed and rationale understood. Any serious gaps should be presented for stakeholder review . • Issue in Change control: Change control process was not triggered at appropriate time. There could be many changes which were accepted without change control process. Change control process should be triggered for any serious issues having impact on schedule, cost and/or quality. • Issues in Stakeholder communication: Stakeholders may not held a uniform view and correct view of the project. Any such issues should be recorded and remediated. • Contract management: This may look simple but can lead to serious complications. With help of finance department this should also be reviewed.   After the initial analysis it was assessed that a transition and continuation of project  AS‐IS will take 7 months for completion. 1.5 Methodology Adopted for Turn Around For transition it was decided this will be done by adopting a process driven approach  rather than treat it like a person transition. Approach adopted is described below ‐  6|Page
  • 7. Initiation – This phase involves kick‐off of the transition, stakeholder communication  about  the  change,  gathering  all  the  relevant  artifacts  for  transition  and  understanding the health of the project. Ground work for the validation and analysis  phase is done during this phase    Validation – This is a crucial phase as it involves re‐assessment of the project health  by a new eye.    Analysis and Recommendation – This phase is equally crucial as the Validation phase  because  it  involves  identification  of  gaps,  re‐assessment  of  risk  and  the  more  important of all alignment of all the stakeholders about the project health    Closure  –  Transition  closure  can  be  looked  upon  as  a  course  correction  and  continuation  of  the  journey  towards  successful  completion  of  the  project.  All  the  modified artifacts are baselined and form the basis for driving the future course. 1.6 Outcome The  project  was  completed  successfully  and  handed  over  to  business  within  the  revised budget and two months ahead of the schedule revised during the transition 7|Page
  • 8. 1.7 1 Reco ommend dations We would like to recommend a process for project m W manager transsition to be in ncluded  inn PMBOK as a a separate pro ocess so thatt it can be ensured that Pr roject Manag gers are  abble to take ov ver in‐flight project and ma anage it in ac ccordance witth principles l laid out  by PMI  to  enh y  hance  the  pr roject  success rate.  Propo s  osed  Project  Manager  traansition  pr rocess‐               Trransition Initi iation Phase During  transit tion  initiation  phase  pro oject  manag gets  to  know  about basic  ger  t  obbjectives of the project , b brief history o of the project t , get to know basic struccture of  prroject  docummentation  and  a  brief  int troduction  with  key  stake eholder.  Belo is  a  ow  suummary  list  of  document ,reports  and  factors  w ts  which  should  be  covered  in  this  8|Page
  • 9. phase.  An  updated  transition  planning  checklist  will  be  key  output  for  successful  transition.    Plans  Reports and Records Environment and Other  factors  • Project Charter  • Record of change  • Lead time taken for  • Project  requests (scope  closure of issues   Management Plan  changes)  • Involvement of  and sub‐plans  • Risk Review Reports  appropriate  • Schedule  • Record of plan  stakeholders   • Risk Records  changes and re‐ • Confirmation on  • Issue Logs  baselines  stakeholders  • Scope and scope   • Record of estimation  understanding of  change requests  changes and schedule  their roles and  • Baseline  re‐baselines  responsibilities  acceptance      • Review of cost and  • SME co‐operation and  criteria  schedule adherence  availability  • Review of latest issue  • Team motivation and  logs and status  people issues (if any)  • Stakeholder  • Changes in team and  communication  attrition  records  • Understanding of  • Milestone review  business drivers for  reports  the project, any  critical dependencies,  legal and regulatory  implications for client  • Elicitation of specific  undocumented  requirements or  expectations from the  stakeholders    Transition Planning Phase      After transition initiation phase based on  information received a detailed transition  plan is prepared using the checklist. Some of the best practices are   • Project manager should get buy in from all stakeholders about their availability  as required.  • Transition plan should reflect the resource and SME availability, factor lead  time for any access, approval, legal and security aspects .  • Transition plan should cover all areas of transition checklist.  • A  reasonable  time  should  be  assumed  for  validation  phase  and  expert  s  availability for the same should be factored.  9|Page
  • 10. Baseline Validation Phase    Base line validation is the most important step in project manager transition process.  In this phase focus should be retained on issues finding if any and documenting the  same. Some of the best practices for the phase are   • Analysis of the gaps is separated as a process steps as that steps may need  a more complete picture and ad‐hoc analysis should be avoided.   • Issue  log  should  be  shared  with  stakeholders  only  on  need  to  know  basis  during the process to avoid unnecessary alarm.  • Final issue log should be shared with all relevant stakeholders    Gap Analysis and Stakeholder Communication Process    Once  the  issues  in  base  line  validation  phase  are  available  next  steps  is  analysis  of  gaps  with  relevant  stakeholders  to  understand  the  impact  .  Following  actions  may  result from this phase     • Some  part  of  impact  may  introduce  a  reasonable  risk  which  in  which  case  risk  register needs to be updated.   • Some  issues,  like  gaps  in  documentation,  small  missing  portions  in  WBS  and  communication  and  perception  gap,  may  be  possible  to  remediate  and  same  should be done.  • For  some  of  larger  impact  issues  change  control  process  may  need  to  be  triggered    Change Control Process    Once  stakeholders  have  reviewed  the  gaps  and  there  is  agreement  on  triggering  change  control  process  then  change  requests  should  be  raised  and  process  assets  modified accordingly.  • Impact on cost, schedule and impact should be documented   • Risk register should be updated  • Project plan and WBS should be updated   • Communication management plan should be updated  Once  change  are  approved  then  a  new  baseline  should  be  created  for  the  project  which  should  reflect  current  status  ,  understanding  of  scope,  roles  and  responsibilities, risks , budget and schedule.           10 | P a g e
  • 11. Stakeholder’s Review and Project takeover     New baseline should be reviewed by all stakeholders. Stakeholder should be briefed  about   • How gaps have been addressed  • Impact of changes   • Review of risk register   Upon stakeholder  approval project manager  should take over the project and  start Managing.  1.8 References 1. PMBOK Version   © 2009 Infosys Technologies Limited. ALL RIGHTS RESERVED Copyright in whole and in part of this document “Infosys Virtual Concierge Solution” belongs to Infosys Technologies Limited. This work may not be used, sold, transferred, adapted, abridged, copied or reproduced in whole or in part in any manner or form or in any media without the prior written consent of Infosys Technologies Limited. 1.9 Author(s) Profile     Sunil Kumar Sharma, is a Sr Project Manager with Infosys. He has diverse experience in project and program management of IT services delivery, solution design, outsourcing and client relationship management E-mail: sunil_sharma@infosys.com 11 | P a g e
  • 12. Deepali is a Senior Project Manager with Infosys Technologies Limited. She has over 16 years of experience in project and program management of IT consulting, solutions and services. E-mail: deepali_goyal@infosys.com Ranjan is a Senior Project Manager with Infosys Technologies Limited. He  has over 10 years of experience in Project and Program Management. He  has managed complex programs which required transition from clients  and multi‐vendor from multiple locations across the globe.   E-mail: ranjankolte@infosys.com;   ranjan_kolte@yahoo.com   12 | P a g e