This presentation was presented in Indian Railway's IPWE Seminar in January 2013 at Chennai. It depicts the innovations and new Technologies (in the context of Indian Railways) adopted on the project, and the various technical issues, and how they were dealt with.
4. PROJECT SUMMARY
4
COMMENCEMENT DATE 18th January 2008
ORIGINAL CONTRACT PERIOD
Seremban to Sg. Gadut 30 months i.e., 17th July 2010
Sg Gadut to Gemas 48 months i.e., 17th January 2012
REVISED CONTRACT COMPLETION
Seremban to Sg. Gadut 30th April 2011 (Completed & Handedover)
Sg Gadut to Gemas 31st July 2013
CONTRACT SUM RM 3,450 million
PROJECTED CONTRACT SUM RM 3,367 million
OVERALL PHYSICAL PROGRESS 94.00%
SCHEDULE PHYSICAL PROGRESS 93.89%
AHEAD (+) / DELAY (-) +0.11% ahead
5. PROJECT FEATURES
• Curve Radius min. 1268 mts. Design
Speed of 160 kmph (M.G.)
– MX Rail
– 29 Criss Crosses
• Hydrology Review through HACRAS
Modelling Software
• Total Grade Separation
– 13 ROBs, 8 VBCs, 8 MPOBs
• Integrated Pier / PSC Girders
– 15% Cost Savings
– Bearing Less, Maintenance Free
• Detention Pond up stream of
Bridges to Buffer Flash Floods
• Project FBW to weld 25 mts. Rail to
150 mts. Panel
• Old Hoppers Modifications For
Central Discharge.
5
• Maximum Design Speed:160
km/hr
• Maximum Operating Speed:140
km/hr
• Maximum Operating Speed for
freight train:90 km/hr
• Maximum Vertical Gradient:1%
• Minimum track spacing:4.2m
• Maximum Axel Load:20 tonnes
• Weldable CMS X-ings
• Through CWR
• Through FBW (AT @ T/Outs,
Destressing)
• Bidirectional Automatic Signalling,
ATP, SSI with Hot Stand by, CTC.
7. SCHEMATIC LINE DIAGRAM OF TRACK WORK PROGRESS
DN LINE
UP LINE
Legend:
Completed (184 KM)
In progress (32 KM)
TDC: 30.12.12 TDC: 15.02.13
Length:8.04 Km Length:14.9 Km Length:24.8 Km
Length:21.9 Km Length:27.3 Km
Ch.461.234
Ch.564.000
10. GEO-TECH CONDITIONS AND SOLUTIONS
• Malaysia:
– Very Poor Soil Conditions.
• Peat, Marine Clay, Organic Soils or Lime Stone Cavities
• Geo-tech solutions aim at ZERO Formation settlement despite poor
Soil Conditions
• Ground Improvement Cost May be as much as 20% of the Infra
Project Cost
– Stone Columns
– RE walls used in Rly. Bridge Approaches!
– Soli Nails and Crib Walls are very common in Cutting
– Geotextile sandwitched between sand layers is a standard,
even for Existing Track Rehabilitation
• PVD
• Geo-wrapping on Temporary Railway Banks
• Geo Cells
13. 13
HIGH FORMATION / CUTTINGS
• HIGH EMBANKMENT IN
COUNTRY SIDE
• HIGH CUTTING
• 3mt BERM EVERY 6mt HEIGHT
• BERM DRAIN, CASCADING DRAIN,
TOE SIDE DRAIN
14. • RAIL HANDLING CRANE
EQUPIED DMT
• STEEL CHEQURED PLATE
TROLLEY PATH WAY
14
NEW SOLUTIONS
16. BALLAST BOX FOR BOTTOM BALLST
SPREADING
• EVEN 150mm BOTTOM
BALLASTING
• LESS MANUAL LABOUR
• BETTER INITIAL TRACK
GEOMETRY ON LAYING
SLEEPERS WITH
SLEEPER LAYING BEAM
16
17. STONE COLUMNS FOR WEAK SOILS
• FASTER CONSOLIDATION AND STRENGTH
MOBILIZATION:
– PROVIDES A DRAINAGE PATH THROUGH ORGANIC PEAT /
MARINE CLAY
– PROVIDES A SUPPORT COLUMN
17
18. Existing track
23.1 m
ROB 09 ABUTMENT B
MATIER’S ARCH
Longitudinal profile
of proposed road
• LENGTH OF MATIER’S ARCH CONSTRUCTED IS 62.5m AT A TOAT COST
OF RM 1.24 MILLION. RATE PER METER OF MATIER’S ARCH IS RM19,840.
• MATIER’S ARCH AT ROB 09 WAS COMPLETED WITHIN THREE MONTHS.
MATIER’S ARCH AT ROB 09
21. SOIL NAIL SUPPORTED CUTTING
• WHEN FLAT SLOPES ARE NOT POSSIBLE
– CONTINUOUS HILL SLOPES AT 1 FOS, MINIMAL
MUCK GENERATION
– BUILT UP AREA AT TOP, MACHINE ACCESS AT TOP
MAY NOT BE POSSIBLE
– TOP DOWN EXCAVATION AS YOU PROTECT 21