SlideShare une entreprise Scribd logo
1  sur  30
Télécharger pour lire hors ligne
INNOVATIVE CONSTRUCTION
SOLUTIONS IN RAILWAY DOUBLING
PROJECT
SHARING MALAYSIAN EXPERIENCE
-Hitesh Khanna
ME’s VISIT TO SGEDT / MLY.
HON’BLE ME DESIRED TO SHARE THE EXPERIENCE ON
A MUCH WIDER FORUM.
2
Gemas
Tampin
Rembau
Senawang
Sg. Gadut
Seremban
Batang Melaka
Legend :
Existing Alignment
New Major Realignment
Proposed station
CH : 461.234
CH : 469.275
CH : 483.750
CH : 509.675
CH : 535.150
CH : 562.270
CH : 465.300
3
STATION
PROJECT SUMMARY
4
COMMENCEMENT DATE 18th January 2008
ORIGINAL CONTRACT PERIOD
Seremban to Sg. Gadut 30 months i.e., 17th July 2010
Sg Gadut to Gemas 48 months i.e., 17th January 2012
REVISED CONTRACT COMPLETION
Seremban to Sg. Gadut 30th April 2011 (Completed & Handedover)
Sg Gadut to Gemas 31st July 2013
CONTRACT SUM RM 3,450 million
PROJECTED CONTRACT SUM RM 3,367 million
OVERALL PHYSICAL PROGRESS 94.00%
SCHEDULE PHYSICAL PROGRESS 93.89%
AHEAD (+) / DELAY (-) +0.11% ahead
PROJECT FEATURES
• Curve Radius min. 1268 mts. Design
Speed of 160 kmph (M.G.)
– MX Rail
– 29 Criss Crosses
• Hydrology Review through HACRAS
Modelling Software
• Total Grade Separation
– 13 ROBs, 8 VBCs, 8 MPOBs
• Integrated Pier / PSC Girders
– 15% Cost Savings
– Bearing Less, Maintenance Free
• Detention Pond up stream of
Bridges to Buffer Flash Floods
• Project FBW to weld 25 mts. Rail to
150 mts. Panel
• Old Hoppers Modifications For
Central Discharge.
5
• Maximum Design Speed:160
km/hr
• Maximum Operating Speed:140
km/hr
• Maximum Operating Speed for
freight train:90 km/hr
• Maximum Vertical Gradient:1%
• Minimum track spacing:4.2m
• Maximum Axel Load:20 tonnes
• Weldable CMS X-ings
• Through CWR
• Through FBW (AT @ T/Outs,
Destressing)
• Bidirectional Automatic Signalling,
ATP, SSI with Hot Stand by, CTC.
PHASE-2PHASE-1
COMMISSIONED
PROPOSED ALIGNMENT
Structure Total
Viaduct 03 number ( 2.2km)
ROB 14 nos
RUB 08 nos
BRV 35 nos
Culvert 124 nos
Linear Waterway 2000 m
SCHEMATIC LINE DIAGRAM OF TRACK WORK PROGRESS
DN LINE
UP LINE
Legend:
Completed (184 KM)
In progress (32 KM)
TDC: 30.12.12 TDC: 15.02.13
Length:8.04 Km Length:14.9 Km Length:24.8 Km
Length:21.9 Km Length:27.3 Km
Ch.461.234
Ch.564.000
TRADE WISE PROGRESS
MONITORING
8
TRADES OF WORKS
TOTAL WORK PROGRESS
AS ON 02.11.2012
CONSTRUCTION (INFRA WORKS) 98.54%
PACKAGE INF 1A (Sec. 1A : CH. 461.234 - CH. 472.500) 100.00%
PACKAGE INF 1B (Sec. 1B : CH. 472.500 - CH. 500.600) 99.90%
PACKAGE INF 2 (Sec. 2A : CH. 500.600 - CH. 506.558) 97.30%
PACKAGE INF 3 (Sec. 2B : CH. 502.400 - CH. 535.500) 99.88%
PACKAGE INF 4 (Sec. 3 : CH. 535.500 - CH. 563.496) 99.83%
PACKAGE INF 5 (Station Buildings & Platforms) 96.82%
PACKAGE INF 6 (TRACK WORK) 97.45%
PACKAGE INF 7 (MISC. WORKS-FENCING & GEMAS
FACILITIES)
78.11%
INSTALLATION OF SYSTEM WORKS 59.70%
PACKAGE SYS 1 (ELECTRICAL WORKS) 52.42%
PACKAGE SYS 2 (SIGNALLING) 61.81%
PACKAGE SYS 2 (COMMUNICATION) 78.97%
TESTING 57.18%
TOTAL 94.00%
9
GEO-TECH CONDITIONS AND SOLUTIONS
• Malaysia:
– Very Poor Soil Conditions.
• Peat, Marine Clay, Organic Soils or Lime Stone Cavities
• Geo-tech solutions aim at ZERO Formation settlement despite poor
Soil Conditions
• Ground Improvement Cost May be as much as 20% of the Infra
Project Cost
– Stone Columns
– RE walls used in Rly. Bridge Approaches!
– Soli Nails and Crib Walls are very common in Cutting
– Geotextile sandwitched between sand layers is a standard,
even for Existing Track Rehabilitation
• PVD
• Geo-wrapping on Temporary Railway Banks
• Geo Cells
Typical Track Structure
Sub-Ballast
Sub-Grade
Ballast
Psc Sleeper
Fittings (Pandrol fastclip)
Rails (UIC 54)
SandandGeotextile
300 mm
300 mm
100 mm
600 mm
TYPICAL CROSS SECTION
DN LINE UP LINE
DN LINE UP LINE
13
HIGH FORMATION / CUTTINGS
• HIGH EMBANKMENT IN
COUNTRY SIDE
• HIGH CUTTING
• 3mt BERM EVERY 6mt HEIGHT
• BERM DRAIN, CASCADING DRAIN,
TOE SIDE DRAIN
• RAIL HANDLING CRANE
EQUPIED DMT
• STEEL CHEQURED PLATE
TROLLEY PATH WAY
14
NEW SOLUTIONS
15
MPOB (MOTOR CYCLE/
PEDESTRAIN BRIDGE)
BALLAST BOX FOR BOTTOM BALLST
SPREADING
• EVEN 150mm BOTTOM
BALLASTING
• LESS MANUAL LABOUR
• BETTER INITIAL TRACK
GEOMETRY ON LAYING
SLEEPERS WITH
SLEEPER LAYING BEAM
16
STONE COLUMNS FOR WEAK SOILS
• FASTER CONSOLIDATION AND STRENGTH
MOBILIZATION:
– PROVIDES A DRAINAGE PATH THROUGH ORGANIC PEAT /
MARINE CLAY
– PROVIDES A SUPPORT COLUMN
17
Existing track
23.1 m
ROB 09 ABUTMENT B
MATIER’S ARCH
Longitudinal profile
of proposed road
• LENGTH OF MATIER’S ARCH CONSTRUCTED IS 62.5m AT A TOAT COST
OF RM 1.24 MILLION. RATE PER METER OF MATIER’S ARCH IS RM19,840.
• MATIER’S ARCH AT ROB 09 WAS COMPLETED WITHIN THREE MONTHS.
MATIER’S ARCH AT ROB 09
MATIER’S ARCH AT ROB 09
MATIER’S ARCH AT ROB 09
SOIL NAIL SUPPORTED CUTTING
• WHEN FLAT SLOPES ARE NOT POSSIBLE
– CONTINUOUS HILL SLOPES AT 1 FOS, MINIMAL
MUCK GENERATION
– BUILT UP AREA AT TOP, MACHINE ACCESS AT TOP
MAY NOT BE POSSIBLE
– TOP DOWN EXCAVATION AS YOU PROTECT 21
Pedestrian Bridge
ML
Main Building
Secondary
Building
SENAWANG HALT
Viaduct
Main Building
DN UP
SUNGAI GADUT STATION
Pedestrian Bridge
DN Loop UP LoopML
Main BuildingSecondary
Building
REMBAU STATION
30
FIRST TRIAL TRAIN ACROSS PIR PANJAL

Contenu connexe

Tendances

Nidec asi tunnel ventilation ala
Nidec asi tunnel ventilation alaNidec asi tunnel ventilation ala
Nidec asi tunnel ventilation alaNidec Corporation
 
Tunnel boring machine
Tunnel boring machineTunnel boring machine
Tunnel boring machinerutuldave
 
Segmental Lining Design Presentation
Segmental Lining Design PresentationSegmental Lining Design Presentation
Segmental Lining Design PresentationKeith Kong
 
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAMNhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAMIshant Gautam.
 
Why Pressurized Exits for Transportation Tunnels May Not Make Sense
Why Pressurized Exits for Transportation Tunnels May Not Make SenseWhy Pressurized Exits for Transportation Tunnels May Not Make Sense
Why Pressurized Exits for Transportation Tunnels May Not Make SenseWSP
 
Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Rajesh Prasad
 
DELHI METRO UNDERGROUND TUNNELING : SHAHBAZ KHAN DMRC
DELHI METRO UNDERGROUND TUNNELING : SHAHBAZ KHAN DMRCDELHI METRO UNDERGROUND TUNNELING : SHAHBAZ KHAN DMRC
DELHI METRO UNDERGROUND TUNNELING : SHAHBAZ KHAN DMRCAl Hakam Khan
 
tunnel boring machine
tunnel boring machine tunnel boring machine
tunnel boring machine Milan Sheta
 
Mihalis presentation final 10092011
Mihalis presentation final 10092011Mihalis presentation final 10092011
Mihalis presentation final 10092011ILIAS MICHALIS
 
Procedure and construction of road under bridge by box pushing method
Procedure and construction of road under bridge by box pushing methodProcedure and construction of road under bridge by box pushing method
Procedure and construction of road under bridge by box pushing methodeSAT Journals
 
analysis and design of telecommunication tower
analysis and design of telecommunication toweranalysis and design of telecommunication tower
analysis and design of telecommunication towerRohithasangaraju
 
HS2 Tunnel Ventilation - lessons learned from Crossrail 2018_12_12
HS2 Tunnel Ventilation - lessons learned from Crossrail 2018_12_12HS2 Tunnel Ventilation - lessons learned from Crossrail 2018_12_12
HS2 Tunnel Ventilation - lessons learned from Crossrail 2018_12_12Quintus Murphy
 
Railway Industry Fire Association RIFA talk about Crossrail Tunnel Ventilation
Railway Industry Fire Association RIFA talk about Crossrail Tunnel VentilationRailway Industry Fire Association RIFA talk about Crossrail Tunnel Ventilation
Railway Industry Fire Association RIFA talk about Crossrail Tunnel VentilationQuintus Murphy
 
Microtunneling presentation 2014
Microtunneling presentation 2014Microtunneling presentation 2014
Microtunneling presentation 2014Jamal A'Bed
 
Innovations and trend in metal mining & tunnellng
Innovations and trend in metal mining & tunnellngInnovations and trend in metal mining & tunnellng
Innovations and trend in metal mining & tunnellngSafdar Ali
 
coal mining training report
coal mining training report coal mining training report
coal mining training report VIKRAMSINGH1231
 
Computational Fluid Dynamics Simulations for Risk Analysis of Fires in Road T...
Computational Fluid Dynamics Simulations for Risk Analysis of Fires in Road T...Computational Fluid Dynamics Simulations for Risk Analysis of Fires in Road T...
Computational Fluid Dynamics Simulations for Risk Analysis of Fires in Road T...Franco Bontempi
 
Presentation 6th mining congress MGMI, by S.K.Bag
Presentation 6th mining congress MGMI, by S.K.BagPresentation 6th mining congress MGMI, by S.K.Bag
Presentation 6th mining congress MGMI, by S.K.BagShyamal Bag
 

Tendances (20)

Nidec asi tunnel ventilation ala
Nidec asi tunnel ventilation alaNidec asi tunnel ventilation ala
Nidec asi tunnel ventilation ala
 
Tunnel boring machine
Tunnel boring machineTunnel boring machine
Tunnel boring machine
 
Pipe Jacking
Pipe JackingPipe Jacking
Pipe Jacking
 
Segmental Lining Design Presentation
Segmental Lining Design PresentationSegmental Lining Design Presentation
Segmental Lining Design Presentation
 
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAMNhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
 
Why Pressurized Exits for Transportation Tunnels May Not Make Sense
Why Pressurized Exits for Transportation Tunnels May Not Make SenseWhy Pressurized Exits for Transportation Tunnels May Not Make Sense
Why Pressurized Exits for Transportation Tunnels May Not Make Sense
 
Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...
 
DELHI METRO UNDERGROUND TUNNELING : SHAHBAZ KHAN DMRC
DELHI METRO UNDERGROUND TUNNELING : SHAHBAZ KHAN DMRCDELHI METRO UNDERGROUND TUNNELING : SHAHBAZ KHAN DMRC
DELHI METRO UNDERGROUND TUNNELING : SHAHBAZ KHAN DMRC
 
tunnel boring machine
tunnel boring machine tunnel boring machine
tunnel boring machine
 
Mihalis presentation final 10092011
Mihalis presentation final 10092011Mihalis presentation final 10092011
Mihalis presentation final 10092011
 
Procedure and construction of road under bridge by box pushing method
Procedure and construction of road under bridge by box pushing methodProcedure and construction of road under bridge by box pushing method
Procedure and construction of road under bridge by box pushing method
 
analysis and design of telecommunication tower
analysis and design of telecommunication toweranalysis and design of telecommunication tower
analysis and design of telecommunication tower
 
Trenchless Technologies for New Pipe Installations
Trenchless Technologies for New Pipe InstallationsTrenchless Technologies for New Pipe Installations
Trenchless Technologies for New Pipe Installations
 
HS2 Tunnel Ventilation - lessons learned from Crossrail 2018_12_12
HS2 Tunnel Ventilation - lessons learned from Crossrail 2018_12_12HS2 Tunnel Ventilation - lessons learned from Crossrail 2018_12_12
HS2 Tunnel Ventilation - lessons learned from Crossrail 2018_12_12
 
Railway Industry Fire Association RIFA talk about Crossrail Tunnel Ventilation
Railway Industry Fire Association RIFA talk about Crossrail Tunnel VentilationRailway Industry Fire Association RIFA talk about Crossrail Tunnel Ventilation
Railway Industry Fire Association RIFA talk about Crossrail Tunnel Ventilation
 
Microtunneling presentation 2014
Microtunneling presentation 2014Microtunneling presentation 2014
Microtunneling presentation 2014
 
Innovations and trend in metal mining & tunnellng
Innovations and trend in metal mining & tunnellngInnovations and trend in metal mining & tunnellng
Innovations and trend in metal mining & tunnellng
 
coal mining training report
coal mining training report coal mining training report
coal mining training report
 
Computational Fluid Dynamics Simulations for Risk Analysis of Fires in Road T...
Computational Fluid Dynamics Simulations for Risk Analysis of Fires in Road T...Computational Fluid Dynamics Simulations for Risk Analysis of Fires in Road T...
Computational Fluid Dynamics Simulations for Risk Analysis of Fires in Road T...
 
Presentation 6th mining congress MGMI, by S.K.Bag
Presentation 6th mining congress MGMI, by S.K.BagPresentation 6th mining congress MGMI, by S.K.Bag
Presentation 6th mining congress MGMI, by S.K.Bag
 

Similaire à Presentation about Ircon's SGEDT project in Malaysia.

IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18Rajesh Prasad
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18Rajesh Prasad
 
. Narmada Canal ExPresentation for Extradose Bridge for Gandhi Nagar Metro....
.   Narmada Canal ExPresentation for Extradose Bridge for Gandhi Nagar Metro.....   Narmada Canal ExPresentation for Extradose Bridge for Gandhi Nagar Metro....
. Narmada Canal ExPresentation for Extradose Bridge for Gandhi Nagar Metro....IndraNathMishra2
 
Uses of Larsa 4 d and Lusas 4 D models for Implementation of Cable Stayed ...
Uses of Larsa   4 d and Lusas  4 D models for Implementation of Cable Stayed ...Uses of Larsa   4 d and Lusas  4 D models for Implementation of Cable Stayed ...
Uses of Larsa 4 d and Lusas 4 D models for Implementation of Cable Stayed ...Rajesh Prasad
 
Cable stay bridge 05.01.16-IPWE seminar NewDelhi
Cable stay bridge  05.01.16-IPWE seminar NewDelhiCable stay bridge  05.01.16-IPWE seminar NewDelhi
Cable stay bridge 05.01.16-IPWE seminar NewDelhiRajesh Prasad
 
internship report on NJHPP
internship report on NJHPPinternship report on NJHPP
internship report on NJHPPSaad Raja
 
Pkg-1&2-Project Status on 31.01.2022 (To HO) (1).pptx
Pkg-1&2-Project Status on 31.01.2022 (To HO) (1).pptxPkg-1&2-Project Status on 31.01.2022 (To HO) (1).pptx
Pkg-1&2-Project Status on 31.01.2022 (To HO) (1).pptxVenkatesh Dontha
 
Ppt u girder casting by l.k.prasad
Ppt u girder casting by l.k.prasadPpt u girder casting by l.k.prasad
Ppt u girder casting by l.k.prasadLachhmikant. Prasad
 
CE Confr Presentation 08 Oct 2022.pptx
CE Confr Presentation 08 Oct 2022.pptxCE Confr Presentation 08 Oct 2022.pptx
CE Confr Presentation 08 Oct 2022.pptxSaketChandra4
 
Presentation on Flyover at Aziz Cross on GT Road Gujranwala
Presentation on Flyover at Aziz Cross on GT Road GujranwalaPresentation on Flyover at Aziz Cross on GT Road Gujranwala
Presentation on Flyover at Aziz Cross on GT Road GujranwalaRubnawaz Bhatti
 
428836159-Presentation-on-Mumbai-Ahmadabad-High-Speed-Rail-Project.pptx
428836159-Presentation-on-Mumbai-Ahmadabad-High-Speed-Rail-Project.pptx428836159-Presentation-on-Mumbai-Ahmadabad-High-Speed-Rail-Project.pptx
428836159-Presentation-on-Mumbai-Ahmadabad-High-Speed-Rail-Project.pptxRAKESHPANDEY754083
 
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...Egyptian Engineers Association
 
101024 Mafraq_Presentation_Javad_Akhtar
101024 Mafraq_Presentation_Javad_Akhtar101024 Mafraq_Presentation_Javad_Akhtar
101024 Mafraq_Presentation_Javad_AkhtarJavad Akhtar
 
Ppt of pre casting yard
Ppt of pre casting yardPpt of pre casting yard
Ppt of pre casting yardRavinder Singh
 
Construction of Box Girders, Piers, Piles and Roads by Engineer Muhammad K...
 Construction of Box Girders, Piers, Piles and Roads   by Engineer Muhammad K... Construction of Box Girders, Piers, Piles and Roads   by Engineer Muhammad K...
Construction of Box Girders, Piers, Piles and Roads by Engineer Muhammad K...Kamal787
 
Doubling presentation
Doubling  presentationDoubling  presentation
Doubling presentationNeha Singh
 

Similaire à Presentation about Ircon's SGEDT project in Malaysia. (20)

IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18
 
New mandovi bridge
New mandovi bridgeNew mandovi bridge
New mandovi bridge
 
SMHB
SMHBSMHB
SMHB
 
. Narmada Canal ExPresentation for Extradose Bridge for Gandhi Nagar Metro....
.   Narmada Canal ExPresentation for Extradose Bridge for Gandhi Nagar Metro.....   Narmada Canal ExPresentation for Extradose Bridge for Gandhi Nagar Metro....
. Narmada Canal ExPresentation for Extradose Bridge for Gandhi Nagar Metro....
 
The poster
The posterThe poster
The poster
 
Uses of Larsa 4 d and Lusas 4 D models for Implementation of Cable Stayed ...
Uses of Larsa   4 d and Lusas  4 D models for Implementation of Cable Stayed ...Uses of Larsa   4 d and Lusas  4 D models for Implementation of Cable Stayed ...
Uses of Larsa 4 d and Lusas 4 D models for Implementation of Cable Stayed ...
 
Cable stay bridge 05.01.16-IPWE seminar NewDelhi
Cable stay bridge  05.01.16-IPWE seminar NewDelhiCable stay bridge  05.01.16-IPWE seminar NewDelhi
Cable stay bridge 05.01.16-IPWE seminar NewDelhi
 
internship report on NJHPP
internship report on NJHPPinternship report on NJHPP
internship report on NJHPP
 
Pkg-1&2-Project Status on 31.01.2022 (To HO) (1).pptx
Pkg-1&2-Project Status on 31.01.2022 (To HO) (1).pptxPkg-1&2-Project Status on 31.01.2022 (To HO) (1).pptx
Pkg-1&2-Project Status on 31.01.2022 (To HO) (1).pptx
 
Ppt u girder casting by l.k.prasad
Ppt u girder casting by l.k.prasadPpt u girder casting by l.k.prasad
Ppt u girder casting by l.k.prasad
 
CE Confr Presentation 08 Oct 2022.pptx
CE Confr Presentation 08 Oct 2022.pptxCE Confr Presentation 08 Oct 2022.pptx
CE Confr Presentation 08 Oct 2022.pptx
 
Presentation on Flyover at Aziz Cross on GT Road Gujranwala
Presentation on Flyover at Aziz Cross on GT Road GujranwalaPresentation on Flyover at Aziz Cross on GT Road Gujranwala
Presentation on Flyover at Aziz Cross on GT Road Gujranwala
 
Paper
PaperPaper
Paper
 
428836159-Presentation-on-Mumbai-Ahmadabad-High-Speed-Rail-Project.pptx
428836159-Presentation-on-Mumbai-Ahmadabad-High-Speed-Rail-Project.pptx428836159-Presentation-on-Mumbai-Ahmadabad-High-Speed-Rail-Project.pptx
428836159-Presentation-on-Mumbai-Ahmadabad-High-Speed-Rail-Project.pptx
 
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
 
101024 Mafraq_Presentation_Javad_Akhtar
101024 Mafraq_Presentation_Javad_Akhtar101024 Mafraq_Presentation_Javad_Akhtar
101024 Mafraq_Presentation_Javad_Akhtar
 
Ppt of pre casting yard
Ppt of pre casting yardPpt of pre casting yard
Ppt of pre casting yard
 
Construction of Box Girders, Piers, Piles and Roads by Engineer Muhammad K...
 Construction of Box Girders, Piers, Piles and Roads   by Engineer Muhammad K... Construction of Box Girders, Piers, Piles and Roads   by Engineer Muhammad K...
Construction of Box Girders, Piers, Piles and Roads by Engineer Muhammad K...
 
Doubling presentation
Doubling  presentationDoubling  presentation
Doubling presentation
 

Dernier

WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure serviceWhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure servicePooja Nehwal
 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonAnna Loughnan Colquhoun
 
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfThe Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfEnterprise Knowledge
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...apidays
 
🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘RTylerCroy
 
Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processorsdebabhi2
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)Gabriella Davis
 
Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Allon Mureinik
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking MenDelhi Call girls
 
A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024Results
 
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Igalia
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsEnterprise Knowledge
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024The Digital Insurer
 
Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024The Digital Insurer
 
Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Enterprise Knowledge
 
Boost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityBoost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityPrincipled Technologies
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdfhans926745
 
The Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxThe Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxMalak Abu Hammad
 
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Miguel Araújo
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationRadu Cotescu
 

Dernier (20)

WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure serviceWhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt Robison
 
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfThe Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
 
🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘
 
Exploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone ProcessorsExploring the Future Potential of AI-Enabled Smartphone Processors
Exploring the Future Potential of AI-Enabled Smartphone Processors
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)
 
Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
 
A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024
 
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024
 
Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024
 
Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...
 
Boost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivityBoost PC performance: How more available memory can improve productivity
Boost PC performance: How more available memory can improve productivity
 
[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf[2024]Digital Global Overview Report 2024 Meltwater.pdf
[2024]Digital Global Overview Report 2024 Meltwater.pdf
 
The Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxThe Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptx
 
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organization
 

Presentation about Ircon's SGEDT project in Malaysia.

  • 1. INNOVATIVE CONSTRUCTION SOLUTIONS IN RAILWAY DOUBLING PROJECT SHARING MALAYSIAN EXPERIENCE -Hitesh Khanna
  • 2. ME’s VISIT TO SGEDT / MLY. HON’BLE ME DESIRED TO SHARE THE EXPERIENCE ON A MUCH WIDER FORUM. 2
  • 3. Gemas Tampin Rembau Senawang Sg. Gadut Seremban Batang Melaka Legend : Existing Alignment New Major Realignment Proposed station CH : 461.234 CH : 469.275 CH : 483.750 CH : 509.675 CH : 535.150 CH : 562.270 CH : 465.300 3 STATION
  • 4. PROJECT SUMMARY 4 COMMENCEMENT DATE 18th January 2008 ORIGINAL CONTRACT PERIOD Seremban to Sg. Gadut 30 months i.e., 17th July 2010 Sg Gadut to Gemas 48 months i.e., 17th January 2012 REVISED CONTRACT COMPLETION Seremban to Sg. Gadut 30th April 2011 (Completed & Handedover) Sg Gadut to Gemas 31st July 2013 CONTRACT SUM RM 3,450 million PROJECTED CONTRACT SUM RM 3,367 million OVERALL PHYSICAL PROGRESS 94.00% SCHEDULE PHYSICAL PROGRESS 93.89% AHEAD (+) / DELAY (-) +0.11% ahead
  • 5. PROJECT FEATURES • Curve Radius min. 1268 mts. Design Speed of 160 kmph (M.G.) – MX Rail – 29 Criss Crosses • Hydrology Review through HACRAS Modelling Software • Total Grade Separation – 13 ROBs, 8 VBCs, 8 MPOBs • Integrated Pier / PSC Girders – 15% Cost Savings – Bearing Less, Maintenance Free • Detention Pond up stream of Bridges to Buffer Flash Floods • Project FBW to weld 25 mts. Rail to 150 mts. Panel • Old Hoppers Modifications For Central Discharge. 5 • Maximum Design Speed:160 km/hr • Maximum Operating Speed:140 km/hr • Maximum Operating Speed for freight train:90 km/hr • Maximum Vertical Gradient:1% • Minimum track spacing:4.2m • Maximum Axel Load:20 tonnes • Weldable CMS X-ings • Through CWR • Through FBW (AT @ T/Outs, Destressing) • Bidirectional Automatic Signalling, ATP, SSI with Hot Stand by, CTC.
  • 6. PHASE-2PHASE-1 COMMISSIONED PROPOSED ALIGNMENT Structure Total Viaduct 03 number ( 2.2km) ROB 14 nos RUB 08 nos BRV 35 nos Culvert 124 nos Linear Waterway 2000 m
  • 7. SCHEMATIC LINE DIAGRAM OF TRACK WORK PROGRESS DN LINE UP LINE Legend: Completed (184 KM) In progress (32 KM) TDC: 30.12.12 TDC: 15.02.13 Length:8.04 Km Length:14.9 Km Length:24.8 Km Length:21.9 Km Length:27.3 Km Ch.461.234 Ch.564.000
  • 8. TRADE WISE PROGRESS MONITORING 8 TRADES OF WORKS TOTAL WORK PROGRESS AS ON 02.11.2012 CONSTRUCTION (INFRA WORKS) 98.54% PACKAGE INF 1A (Sec. 1A : CH. 461.234 - CH. 472.500) 100.00% PACKAGE INF 1B (Sec. 1B : CH. 472.500 - CH. 500.600) 99.90% PACKAGE INF 2 (Sec. 2A : CH. 500.600 - CH. 506.558) 97.30% PACKAGE INF 3 (Sec. 2B : CH. 502.400 - CH. 535.500) 99.88% PACKAGE INF 4 (Sec. 3 : CH. 535.500 - CH. 563.496) 99.83% PACKAGE INF 5 (Station Buildings & Platforms) 96.82% PACKAGE INF 6 (TRACK WORK) 97.45% PACKAGE INF 7 (MISC. WORKS-FENCING & GEMAS FACILITIES) 78.11% INSTALLATION OF SYSTEM WORKS 59.70% PACKAGE SYS 1 (ELECTRICAL WORKS) 52.42% PACKAGE SYS 2 (SIGNALLING) 61.81% PACKAGE SYS 2 (COMMUNICATION) 78.97% TESTING 57.18% TOTAL 94.00%
  • 9. 9
  • 10. GEO-TECH CONDITIONS AND SOLUTIONS • Malaysia: – Very Poor Soil Conditions. • Peat, Marine Clay, Organic Soils or Lime Stone Cavities • Geo-tech solutions aim at ZERO Formation settlement despite poor Soil Conditions • Ground Improvement Cost May be as much as 20% of the Infra Project Cost – Stone Columns – RE walls used in Rly. Bridge Approaches! – Soli Nails and Crib Walls are very common in Cutting – Geotextile sandwitched between sand layers is a standard, even for Existing Track Rehabilitation • PVD • Geo-wrapping on Temporary Railway Banks • Geo Cells
  • 11. Typical Track Structure Sub-Ballast Sub-Grade Ballast Psc Sleeper Fittings (Pandrol fastclip) Rails (UIC 54) SandandGeotextile 300 mm 300 mm 100 mm 600 mm
  • 12. TYPICAL CROSS SECTION DN LINE UP LINE DN LINE UP LINE
  • 13. 13 HIGH FORMATION / CUTTINGS • HIGH EMBANKMENT IN COUNTRY SIDE • HIGH CUTTING • 3mt BERM EVERY 6mt HEIGHT • BERM DRAIN, CASCADING DRAIN, TOE SIDE DRAIN
  • 14. • RAIL HANDLING CRANE EQUPIED DMT • STEEL CHEQURED PLATE TROLLEY PATH WAY 14 NEW SOLUTIONS
  • 16. BALLAST BOX FOR BOTTOM BALLST SPREADING • EVEN 150mm BOTTOM BALLASTING • LESS MANUAL LABOUR • BETTER INITIAL TRACK GEOMETRY ON LAYING SLEEPERS WITH SLEEPER LAYING BEAM 16
  • 17. STONE COLUMNS FOR WEAK SOILS • FASTER CONSOLIDATION AND STRENGTH MOBILIZATION: – PROVIDES A DRAINAGE PATH THROUGH ORGANIC PEAT / MARINE CLAY – PROVIDES A SUPPORT COLUMN 17
  • 18. Existing track 23.1 m ROB 09 ABUTMENT B MATIER’S ARCH Longitudinal profile of proposed road • LENGTH OF MATIER’S ARCH CONSTRUCTED IS 62.5m AT A TOAT COST OF RM 1.24 MILLION. RATE PER METER OF MATIER’S ARCH IS RM19,840. • MATIER’S ARCH AT ROB 09 WAS COMPLETED WITHIN THREE MONTHS. MATIER’S ARCH AT ROB 09
  • 21. SOIL NAIL SUPPORTED CUTTING • WHEN FLAT SLOPES ARE NOT POSSIBLE – CONTINUOUS HILL SLOPES AT 1 FOS, MINIMAL MUCK GENERATION – BUILT UP AREA AT TOP, MACHINE ACCESS AT TOP MAY NOT BE POSSIBLE – TOP DOWN EXCAVATION AS YOU PROTECT 21
  • 23.
  • 25.
  • 26. Pedestrian Bridge DN Loop UP LoopML Main BuildingSecondary Building REMBAU STATION
  • 27.
  • 28.
  • 29.
  • 30. 30 FIRST TRIAL TRAIN ACROSS PIR PANJAL