International Journal of Engineering Research and Development 
e-ISSN: 2278-067X, p-ISSN: 2278-800X, www.ijerd.com 
Volume 10, Issue 9 (September 2014), PP.33-41 
Comparative Study of Analysis and Design of Pre-Engineered 
Buildings and Conventional Frames 
G. Durga Rama Naidu1, K. Srinivasa Vengala Rao2, V. Divya Sri3, 
M. Navakanth4, G.V. Rama Rao5 
1, 2, 3, 4 M.E. Students, Department of Civil Engineering,Andhra University College of Engineering, Visakhapatnam, India. 
5Professor, Department of Civil Engineering, Andhra University College of Engineering, Visakhapatnam, India. 
Abstract:- Long Span, Column free structures are the most essential in any type of industrial structures and Pre 
Engineered Buildings (PEB) fulfills this requirement along with reduced time and cost as compared to 
conventional structures. The present work involves the comparative study and design of Pre Engineered 
Buildings (PEB) and Conventional steel frames. Design of the structure is being done in Staad Pro software and 
the same is then compared with conventional type, in terms of weight which in turn reduces the cost. Three 
examples have been taken for the study. Comparison of Pre Engineered Buildings (PEB) and Conventional steel 
frames is done in two examples and in the third example, Pre Engineered Building structure with increased bay 
space is taken for the study. In the present work, Pre Engineered Buildings (PEB) and Conventional steel frames 
structure is designed for wind forces. Wind analysis has been done manually as per IS 875 (Part III) – 1987. 
Keywords:- Pre-Engineered-Buildings; Conventional Buildings; Staad Pro; Steel Take-off; Tapered Sections. 
I. INTRODUCTION 
Steel industry is growing rapidly in almost all the parts of the world. The use of steel structures is not 
only economical but also ecofriendly at the time when there is a threat of global warming. Here, “economical” 
word is stated considering time and cost. Time being the most important aspect, steel structures (Pre-fabricated) 
is built in very short period and one such example is Pre Engineered Buildings (PEB). Pre-engineered buildings 
are nothing but steel buildings in which excess steel is avoided by tapering the sections as per the bending 
moment’s requirement. One may think about its possibility, but it’s a fact many people are not aware about Pre 
Engineered Buildings. If we go for regular steel structures, time frame will be more, and also cost will be more, 
and both together i.e. time and cost, makes it uneconomical. Thus in pre-engineered buildings, the total design is 
done in the factory, and as per the design, members are pre-fabricated and then transported to the site where they 
are erected in a time less than 6 to 8 weeks. 
The structural performance of these buildings is well understood and, for the most part, adequate code 
provisions are currently in place to ensure satisfactory behavior in high winds. Steel structures also have much 
better strength-to-weight ratios than RCC and they also can be easily dismantled. Pre Engineered Buildings have 
bolted connections and hence can also be reused after dismantling. Thus, pre-engineered buildings can be 
shifted and/or expanded as per the requirements in future. In this paper we will discuss the various advantages of 
pre-engineered buildings and also, with the help of three examples, a comparison will be made between pre-engineered 
33 
buildings and conventional steel structures. 
1.1 Pre Engineered Buildings 
Presently, large column free area is the utmost requirement for any type of industry and with the advent 
of computer software’s it is now easily possible. With the improvement in technology, computer software’s 
have contributed immensely to the enhancement of quality of life through new researches. Pre-engineered 
building (PEB) is one of such revolution. "Pre-engineered buildings" are fully fabricated in the factory after 
designing, then transported to the site in completely knocked down (CKD) condition and all components are 
assembled and erected with nut-bolts, thereby reducing the time of completion. 
1.1.1 Advantages of PEB 
Following are some of the advantages Pre-engineered building structures 
a) Construction Time: Buildings are generally constructed in just 6 to 8 weeks after approval 
ofdrawings. PEB will thus reduce total construction time of the project by at least 40%. This allows 
faster occupancy and earlier realization of revenue.
Comparative Study of Analysis and Design of Pre-Engineered Buildings and Conventional Frames 
This is one of the main advantages of using Pre-engineered building. 
b) Lower Cost: Because of systems approach, considerable saving is achieved in design, manufacturing 
and erection cost. 
c) Flexibility of Expansion: As discussed earlier, these can be easily expanded in length by adding 
additional bays. Also expansion in width and height is possible by pre designing for future expansion. 
d) Large Clear Spans: Buildings can be supplied to around 90m clear spans. This is one of the most 
important advantages of PEB giving column free space. 
e) Quality Control: Buildings are manufactured completely in the factory under controlled conditions, 
and hence the quality can be assured. 
f) Low Maintenance: PEB Buildings have high quality paint systems for cladding and steel to suit 
ambient conditions at the site, which in turn gives long durability and low maintenance coats. 
g) Energy Efficient Roofing: Buildings are supplied with polyurethane insulated panels or fiberglass 
blankets insulation to achieve required “U” values (overall heat transfer coefficient). 
h) Erection: Steel members are brought to site in CKD conditions, thereby avoiding cutting and welding 
at site. As PEB sections are lighter in weight, the small members can be very easily assembled, bolted and raised 
with the help of cranes. This allows very fast construction and reduces wastage and labor requirement. 
From the numerous advantages of Pre-engineered building, in the present study, the point b is 
considered for the study, i.e. to save the steel and reducing cost, while all the other points are self-explanatory. 
II. ANALYSIS AND DESIGN OF PEB 
In this present work, Staad Pro software has been used in order to analyze and design Pre-engineered 
building structures and conventional structures. In the first example, a 2D plane frame of length 60 m, width 
25m and bay spacing 6 m for both PEB and Conventional has been designed and comparison has been made in 
terms of weight of steel. In the second example, a 2D plane frame of length 60 m, width 25m and bay spacing 8 
m has been designed with tapered sections for PEB, this example is not solved with conventional sections as it is 
neither possible by using only conventional steel sections nor it is economical. This frame has been designed for 
different bay spacing to choose the most economical. 
34 
2.1 Structural Analysis and Design 
STAAD Pro software can be used for analyzing and designing of the pre-engineered buildings. It gives 
the Bending Moment, Axial Forces, Shear Forces, Torsion, Beam Stresses of a steel structure so that the design 
can be done using tapered sections and check for the safety. 
2.1.1Static Analysis 
In the present work, using the Staad Pro software, 2D analysis has been done using Stiffness Matrix 
Method. All the components of Pre-engineered building are tapered using the in-built option of the Software. 
The software provides options for hinged, fixed, and spring supports with releases so as to analyze as per our 
requirement. Herein this work, fixed supports are assigned to the structures. It also facilitates Linear, P-Delta 
Analysis, and Non-Linear Analysis with automatic load and stiffness correction. Multiple Analyses can also be 
done simultaneously which reduces the time. It also has an option of assigning members as tension-onlymembers 
and compression-only members for truss structures. 
2.1.2 Dynamic Analysis 
Dynamic analysis has been done in the present work taking wind loads into consideration. The software 
provides automatic load generation for wind forces, however, the wind loads are calculated manually for the 
present work as per IS codes. The software also provides Loading for Joints, Members/Elements including 
concentrated, Uniform, Linear, Trapezoidal, Temperature, Strain, Support Displacement, Prestressed and Fixed-end 
Loads. It also provides the facility of Combination of Dynamic forceswith Static loading for subsequent 
design. 
III. EXAMPLE 1- INDUSTRIAL SHED 
3.1 Statement of the Problem 
In this Example a comparison of 2D Plane Frame is made for both pre-engineered building and 
conventional type. The plane frame is having width 25 m and bay spacing 6 m and eave height 6 m, subjected to 
wind load. A 5-Ton Crane System is considered. A typical 2D PEB frame is shown in Fig 1 and the 
conventional frame as shown in Fig 2.
Comparative Study of Analysis and Design of Pre-Engineered Buildings and Conventional Frames 
Figure 1: Elevation of Pre-Engineered Frame 
Figure 2: Elevation of Conventional Frame 
35 
Design Data- 
Main Frame- 
Frame Type - Clear Span, Rigid Frame. 
Support- Pinned 
Building Width (W) – 25 m (O/O Steel Columns) 
Building Length (L) – 60 m (O/O Steel Columns) 
Bay Spacing- 11 @ 6 m 
Eaves height- 6 m 
Roof Slope- 1 in10 
Grits Type- 
Sidewall grits- Continuous 
End wall grits- Continuous 
Purlin Type- 
Roof Purlin- Continuous 
Spacing- 1.5m c/c 
Panel Type- 
Roof- Galvanized sheet.
Comparative Study of Analysis and Design of Pre-Engineered Buildings and Conventional Frames 
36 
3.2 LOAD CALCULATIONS 
3.2.1 Calculation of static loads: 
Dead loads are considered as per Table-2 of IS 875 (Part-1) – 1987 
Weight of the G.I sheeting = 0.05 kN/m2 (class 1 G.I sheeting, thickness 0.5 mm) 
Self-weight of section = 0.05 kN/m2 
Total weight = 0.10 kN/m2 
Spacing of purlin = 1.5 m 
Bay spacing = 6 m 
Total weight on frame = 0.10 x 6 = 0.6 kN/m 
Live load are considered as per Table-2 of IS 875 (Part-2) – 1987 
Live load on the sloping roof = 0.75 kN/m2 
Live load on rafter = 0.75 x 6 = 4.5 kN/m 
3.2.2 Calculation of Wind Loads: 
Wind loads are calculated as per IS 875 Part III (1987), in this example. For the Present work, the basic wind 
speed (Vb) is assumed as 44 m/s and the building is considered to be open terrain with well scattered 
obstructions having height less than 10m with maximum dimension more than 50m and accordingly factors K1, 
K2, K3 have been calculated as per IS 875 Part III (1987). 
Terrain Category- 2, Class- C 
K1- Probability factor- 1.0 
K2- Terrain, height and size factor- 0.93 
K3- Topography factor- 1 
Design wind speed, Vz= Vb (K1 x K2 x K3) 
Vz= 40.92 m/s 
Design pressure, P= 0.6 Vz² 
= 1.005 kN/m² 
Ratio- H/W=0.24, L/W= 2.4 
Wind Pressure Coefficients- 
External and Internal wind coefficients are calculated for all the surfaces for both pressure and suction. 
Openingin the building has been considered less than 5% and accordingly internal coefficients are taken as +0.2 
and -0.2. 
The external coefficients and internal coefficients calculated as per IS 875 Part III (1987). 
Wind load on individual members are then calculated as below. 
F= (Cpe – Cpi) A Pz 
Where, Cpe, Cpi are external coefficients and internal coefficients respectively and A and P are Surface Area 
inm² and Design Wind Pressure in kN/m² respectively. 
Table 1: Wind load Left (Cpi = +0.2) 
Description Roof W.W Roof L.W Wall A Wall B 
Coefficients (Cpe) -0.94 -0.4 +0.7 -0.25 
(Cpe – Cpi) -1.14 -0.6 0.5 -0.45 
Wind load(F) kN/m -6.874 -3.618 3.015 -2.714 
Table 2 Wind load Left (Cpi = -0.2) 
Description Roof W.W Roof L.W Wall A Wall B 
Coefficients (Cpe) -0.94 -0.4 +0.7 -0.25 
(Cpe – Cpi) -0.74 -0.2 0.9 -0.05 
Wind load(F) kN/m -4.462 -1.206 5.427 -0.302 
Table 3 Wind load Right (Cpi = +0.2) 
Description Roof W.W Roof L.W Wall A Wall B 
Coefficients (Cpe) -0.94 -0.4 +0.7 -0.25 
(Cpe – Cpi) -1.14 -0.6 0.5 -0.45 
Wind load(F) kN/m -6.874 -3.618 3.015 -2.714
Comparative Study of Analysis and Design of Pre-Engineered Buildings and Conventional Frames 
Table 4 Wind load Right (Cpi = -0.2) 
Description Roof W.W Roof L.W Wall A Wall B 
Coefficients (Cpe) -0.94 -0.4 +0.7 -0.25 
(Cpe – Cpi) -0.74 -0.2 0.9 -0.05 
Wind load(F) kN/m -4.462 -1.206 5.427 -0.302 
Table 5 Wind load Parallel (Cpi = +0.2) 
Description Roof W.W Roof L.W Wall A Wall B Wall C Wall D 
Coefficients (Cpe) -0.94 -0.4 +0.7 -0.25 -0.6 -0.6 
(Cpe – Cpi) -1.14 -0.6 0.5 -0.45 -0.8 -0.8 
Wind load(F) kN/m -3.437 -1.809 1.508 -1.357 -4.02 -4.02 
Table 6 Wind load Parallel (Cpi = -0.2) 
Description Roof W.W Roof L.W Wall A Wall B Wall C Wall D 
Coefficients (Cpe) -0.94 -0.4 +0.7 -0.25 -0.6 -0.6 
(Cpe – Cpi) -0.74 -0.2 0.9 -0.05 -0.4 -0.4 
Wind load(F) kN/m -2.231 -0.603 2.714 -0.151 -2.01 -2.01 
3.3 Weight of Steel (Steel Take Off) 
3.3.1 Weight of the steel for the conventional steel building 
In order to calculate the steel weight of conventional steel building the following member properties 
are used (Table 7). Hot rolled “I” sections are assigned for beams and columns. For purlins, girts and eave strut 
Z sections are used. Now using the above parameters the length and weights are calculated accordingly. 
Table 7: Steel take-off for conventional steel building 
Profile Length (m) Weight (t) 
ST ISMB250 12.56 4.584 
ST ISMB300 2.50 1.081 
ST ISMB450 6.00 4.254 
ST ISMB550 18.56 18.837 
ISA 75X75X6 170.95 11.372 
ISA 50X50X6 171.93 7.52 
ST 200Z60X2 1560 8.547 
37 
Total = 56.17 
Figure 3 Primary Frame Showing the Section
Comparative Study of Analysis and Design of Pre-Engineered Buildings and Conventional Frames 
3.4.2 Weight of the steel for the PEB with primary frame spacing 6 m 
In order to calculate steel weight of PEB of primary frame spacing 6 m the following member 
properties are used (Table 8). For columns and rafters Tapered “I” sections are assigned. For the purlins and 
girts cold formed “Z” sections are used. For bracings Indian standard angle sections are used. Now using the 
above parameters the lengths and weights are calculated accordingly. 
Table 8 Steel take-off for the PEB with primary frame spacing 6 m 
Profile Length (m) Weight (t) 
Tapered MembNo: 1 6.00 2.503 
Tapered MembNo: 2 12.56 8.975 
Tapered MembNo: 3 12.56 7.921 
Tapered MembNo: 4 6.00 3.308 
ST ISMB300 2.50 1.081 
ISA 75X75X6 170.95 11.372 
ISA 50X50X6 171.93 7.502 
ST 200Z60X2 1560 8.547 
38 
Total = 42.66 
Figure 4 Primary Frame showing Sections 
56.17 
Graph 1 Weight Comparison between CSB and PEB 6 m span. 
60 
50 
40 
30 
20 
10 
0 
1 
42.66 
Weight (Tons) 
WEIGHT COMPARISON BETWEEN CSB AND PEB 
6 M SPAN 
CSB 6 M SPAN PEB 6 M SPAN
Comparative Study of Analysis and Design of Pre-Engineered Buildings and Conventional Frames 
IV. EXAMPLE-2 INDUSTRIAL SHED 
In this Example a 2D Plane Frame Pre-engineered building Frame is analyzed and designed. The plane 
frame is having width 25 m and bay spacing 8 m and eave height 6 m, subjected to wind load. A 5-Ton Crane 
System is considered. A 3-D PEB is shown in fig 5. 
Figure 53-D structure of PEB of Primary Frame spacing of 8 m. 
39 
4.1 Loadings: 
All loads are calculated as given in Section 3.1. 
4.2 Weight of Steel (Steel Take-Off). 
4.2.1 Weight of the steel for the PEB with primary frame spacing 8 m 
In order to calculate steel weight of PEB of primary frame spacing 8 m the following member 
properties are used. For columns and rafters tapered “I” sections are used. For the purlins and cold formed “Z” 
sections are used. For bracings Indian standard angle sections are used. Now using the above parameter the 
lengths and weights are calculated accordingly. 
Table 9 Steel take-off for the PEB with primary frame spacing 8 m 
Profile Length (m) Weight (t) 
Tapered MembNo: 1 6.00 2.641 
Tapered MembNo: 2 18.56 12.320 
Tapered MembNo: 3 12.56 6.794 
ST ISMB300 2.50 1.081 
ISA 75X75X6 170.95 11.372 
ISA 50X50X6 171.93 7.502 
ST 200Z60X2 1560 8.547 
Total = 41.71
Comparative Study of Analysis and Design of Pre-Engineered Buildings and Conventional Frames 
1 
42.66 
41.71 
Graph 2 Weight Comparison between PEB 6 m span and PEB 8 m span. 
V. CONCLUSION 
43 
42.8 
42.6 
42.4 
42.2 
42 
41.8 
41.6 
41.4 
41.2 
41 
Pre-engineered steel structures building offers low cost, strength, durability, design flexibility, 
adaptability andrecyclability. Steel is the basic material that is used in the materials that are used for Pre-engineered 
steelbuilding. It negates from regional sources. Infinitely recyclable, steel is the material that reflects 
the imperativesof sustainable development.Based on the analytical and design results thereon of conventional 
and pre-engineered steel buildings, the following conclusions are drawn. 
1. The total steel take-off for PEB with primary frame spacing of 6 m is 76% of the conventional steel 
40 
building. 
2. The total steel take-off for PEB with primary frame spacing of 8 m is 74.4% of the conventional steel 
building. 
3. Steel take-off is more for PEB with primary frame spacing of 6 m than PEB with primary frame 
spacing of 8 m. 
It is also seen that the weight of PEB depends on the Bay Spacing, with the increase in Bay Spacing up 
to certain spacing, the weight reduces and further increase makes the weight heavier. 
To Conclude “Pre-Engineered Building Construction gives the end users a much more economical and 
better solution for long span structures where large column free areas are needed”. 
REFERENCES 
[1] IS 875 (part-1) “Code of practice for design loads (other than earthquake) for building and structures”, 
Dead loads, New Delhi, 1987. 
[2] IS 875 (part-2) “Code of practice for design loads (other than earthquake) for building and structures”, 
Imposed loads, New Delhi, 1987. 
[3] IS 875 (part-3) “Code of practice for design loads (other than earthquake) for building and structures”, 
Wind loads, New Delhi, 1987. 
[4] Jatin D.Thakar, P.G. Patel, “Comparative Study of Pre-Engineered Steel Structure by varying width of 
Structure”, International Journal of Advanced Engineering Technology, Volume IV, Issue III, sept 
2013, pp: 56-62. 
Weight (Tons) 
WEIGHT COMPARISON BETWEEN PEB 6 M 
SPAN AND PEB 8 M SPAN 
PEB 6 M SPAN PEB 8 M SPAN
Comparative Study of Analysis and Design of Pre-Engineered Buildings and Conventional Frames 
[5] Kanakambara Rao et al. “Design of Pre-Engineered steel structures building and to choose a material 
which offers low cost, strength, durability, design flexibility and recyclability”, International Journal of 
Engineering Research and Applications (IJERA), Vol. 2, Issue 2, April 2012, pp: 267-272. 
[6] Kulkarni A.V., “Comparative Study of Analysis and Design of Pre-Engineered Buildings and 
Conventional Frames and various advantages of PEB’s”, IOSR journal of mechanical and civil 
engineering, Volume 5, Issue 3, Jan. – Feb. 2013, pp: 47-53. 
41

Contenu connexe

Tendances

Micce 2010 Peb Presentation (2) By Habibie Razak Cm4 2
Micce 2010 Peb Presentation (2) By Habibie Razak Cm4 2Micce 2010 Peb Presentation (2) By Habibie Razak Cm4 2
Micce 2010 Peb Presentation (2) By Habibie Razak Cm4 2
Habibie Razak
 

Tendances (20)

IRJET-Pre-Engineered Building Design of an Industrial Warehouse
IRJET-Pre-Engineered Building Design of an Industrial WarehouseIRJET-Pre-Engineered Building Design of an Industrial Warehouse
IRJET-Pre-Engineered Building Design of an Industrial Warehouse
 
IRJET- Analysis of PEB Structures and Comparison Wit H Conventional Steel...
IRJET-  	  Analysis of PEB Structures and Comparison Wit H Conventional Steel...IRJET-  	  Analysis of PEB Structures and Comparison Wit H Conventional Steel...
IRJET- Analysis of PEB Structures and Comparison Wit H Conventional Steel...
 
Comparative Study on the Economy between Pre-Engineered and Conventional Stee...
Comparative Study on the Economy between Pre-Engineered and Conventional Stee...Comparative Study on the Economy between Pre-Engineered and Conventional Stee...
Comparative Study on the Economy between Pre-Engineered and Conventional Stee...
 
A Study of Performance of Pre-Engineered Building of an Industrial Warehouse ...
A Study of Performance of Pre-Engineered Building of an Industrial Warehouse ...A Study of Performance of Pre-Engineered Building of an Industrial Warehouse ...
A Study of Performance of Pre-Engineered Building of an Industrial Warehouse ...
 
IRJET- Flexural Strengthening of Pre-Cracked Corroded RC Beams using CFRP Sheets
IRJET- Flexural Strengthening of Pre-Cracked Corroded RC Beams using CFRP SheetsIRJET- Flexural Strengthening of Pre-Cracked Corroded RC Beams using CFRP Sheets
IRJET- Flexural Strengthening of Pre-Cracked Corroded RC Beams using CFRP Sheets
 
IRJET- Finite Element Analysis of Retrofitting of RC Beam with CFRP using Abaqus
IRJET- Finite Element Analysis of Retrofitting of RC Beam with CFRP using AbaqusIRJET- Finite Element Analysis of Retrofitting of RC Beam with CFRP using Abaqus
IRJET- Finite Element Analysis of Retrofitting of RC Beam with CFRP using Abaqus
 
Micce 2010 Peb Presentation (2) By Habibie Razak Cm4 2
Micce 2010 Peb Presentation (2) By Habibie Razak Cm4 2Micce 2010 Peb Presentation (2) By Habibie Razak Cm4 2
Micce 2010 Peb Presentation (2) By Habibie Razak Cm4 2
 
IRJET - Experimental Study on Performance of Buckling Restrained Bracings
IRJET - Experimental Study on Performance of Buckling Restrained BracingsIRJET - Experimental Study on Performance of Buckling Restrained Bracings
IRJET - Experimental Study on Performance of Buckling Restrained Bracings
 
Finite element analysis of jacketed reinforced concrete column subjected to u...
Finite element analysis of jacketed reinforced concrete column subjected to u...Finite element analysis of jacketed reinforced concrete column subjected to u...
Finite element analysis of jacketed reinforced concrete column subjected to u...
 
IRJET- Comparative Analysis on Seismic Behavior of R.C.C, Composite Encased a...
IRJET- Comparative Analysis on Seismic Behavior of R.C.C, Composite Encased a...IRJET- Comparative Analysis on Seismic Behavior of R.C.C, Composite Encased a...
IRJET- Comparative Analysis on Seismic Behavior of R.C.C, Composite Encased a...
 
IRJET- A Comparative Study on Pre Engineered Building by using STAAD PRO
IRJET- A Comparative Study on Pre Engineered Building by using STAAD PROIRJET- A Comparative Study on Pre Engineered Building by using STAAD PRO
IRJET- A Comparative Study on Pre Engineered Building by using STAAD PRO
 
Ac4502185188
Ac4502185188Ac4502185188
Ac4502185188
 
Dynamic Analysis of Multi Storey Steel Structures
Dynamic Analysis of Multi Storey Steel StructuresDynamic Analysis of Multi Storey Steel Structures
Dynamic Analysis of Multi Storey Steel Structures
 
Kt3419401945
Kt3419401945Kt3419401945
Kt3419401945
 
Retrofitting and Strengthening of Damaged Reinforced Concrete Columns Using S...
Retrofitting and Strengthening of Damaged Reinforced Concrete Columns Using S...Retrofitting and Strengthening of Damaged Reinforced Concrete Columns Using S...
Retrofitting and Strengthening of Damaged Reinforced Concrete Columns Using S...
 
IRJET- Comparative Study of Rc Structure with Different Infill Materials
IRJET-  	  Comparative Study of Rc Structure with Different Infill MaterialsIRJET-  	  Comparative Study of Rc Structure with Different Infill Materials
IRJET- Comparative Study of Rc Structure with Different Infill Materials
 
IRJET- Response Analysis of Cold-Formed Dimpled Column
IRJET- Response Analysis of Cold-Formed Dimpled ColumnIRJET- Response Analysis of Cold-Formed Dimpled Column
IRJET- Response Analysis of Cold-Formed Dimpled Column
 
Cyclic Load Test on Beam-Column Behavior of Portal Frame Strengthening by Mic...
Cyclic Load Test on Beam-Column Behavior of Portal Frame Strengthening by Mic...Cyclic Load Test on Beam-Column Behavior of Portal Frame Strengthening by Mic...
Cyclic Load Test on Beam-Column Behavior of Portal Frame Strengthening by Mic...
 
IRJET-Cost Comparison Between Frames with Solid Slab and Ribbed Slab using HC...
IRJET-Cost Comparison Between Frames with Solid Slab and Ribbed Slab using HC...IRJET-Cost Comparison Between Frames with Solid Slab and Ribbed Slab using HC...
IRJET-Cost Comparison Between Frames with Solid Slab and Ribbed Slab using HC...
 
IRJET- Finite Element Analysis of New Circular Lateral Bracing System: A Para...
IRJET- Finite Element Analysis of New Circular Lateral Bracing System: A Para...IRJET- Finite Element Analysis of New Circular Lateral Bracing System: A Para...
IRJET- Finite Element Analysis of New Circular Lateral Bracing System: A Para...
 

Similaire à International Journal of Engineering Research and Development

Paper id 212014131
Paper id 212014131Paper id 212014131
Paper id 212014131
IJRAT
 
Effect of configuration on lateral displacement and cost of the structure for...
Effect of configuration on lateral displacement and cost of the structure for...Effect of configuration on lateral displacement and cost of the structure for...
Effect of configuration on lateral displacement and cost of the structure for...
eSAT Journals
 

Similaire à International Journal of Engineering Research and Development (20)

IRJET- Alternative Designs for Gable Industrial Structure
IRJET-  	  Alternative Designs for Gable Industrial StructureIRJET-  	  Alternative Designs for Gable Industrial Structure
IRJET- Alternative Designs for Gable Industrial Structure
 
Analysis And Design of Pre-Engineered Building Using Indian And Equivalent Am...
Analysis And Design of Pre-Engineered Building Using Indian And Equivalent Am...Analysis And Design of Pre-Engineered Building Using Indian And Equivalent Am...
Analysis And Design of Pre-Engineered Building Using Indian And Equivalent Am...
 
Analysis And Design of Pre-Engineered Building Using Indian And Equivalent Am...
Analysis And Design of Pre-Engineered Building Using Indian And Equivalent Am...Analysis And Design of Pre-Engineered Building Using Indian And Equivalent Am...
Analysis And Design of Pre-Engineered Building Using Indian And Equivalent Am...
 
Research Paper on Analysis and Design of Steel Truss by using Angle and Tube ...
Research Paper on Analysis and Design of Steel Truss by using Angle and Tube ...Research Paper on Analysis and Design of Steel Truss by using Angle and Tube ...
Research Paper on Analysis and Design of Steel Truss by using Angle and Tube ...
 
Paper id 212014131
Paper id 212014131Paper id 212014131
Paper id 212014131
 
Comparison of Pre-Engineered Building and Conventional Steel Truss Building
Comparison of Pre-Engineered Building and Conventional Steel Truss BuildingComparison of Pre-Engineered Building and Conventional Steel Truss Building
Comparison of Pre-Engineered Building and Conventional Steel Truss Building
 
Review Paper on Analysis and Design of Steel Truss by using Angle and Tube Se...
Review Paper on Analysis and Design of Steel Truss by using Angle and Tube Se...Review Paper on Analysis and Design of Steel Truss by using Angle and Tube Se...
Review Paper on Analysis and Design of Steel Truss by using Angle and Tube Se...
 
Effect of Harp and Perimeter Bracing on PEB Subjected to Wind Loading
Effect of Harp and Perimeter Bracing on PEB Subjected to Wind LoadingEffect of Harp and Perimeter Bracing on PEB Subjected to Wind Loading
Effect of Harp and Perimeter Bracing on PEB Subjected to Wind Loading
 
Pre Engineered Structure study: A review
Pre Engineered Structure study: A reviewPre Engineered Structure study: A review
Pre Engineered Structure study: A review
 
A Review on PEB Regarding Cost and Time
A Review on PEB Regarding Cost and TimeA Review on PEB Regarding Cost and Time
A Review on PEB Regarding Cost and Time
 
IRJET- Comparative Study of Multi-Storey Multi-Span G+4 Building by PEB and C...
IRJET- Comparative Study of Multi-Storey Multi-Span G+4 Building by PEB and C...IRJET- Comparative Study of Multi-Storey Multi-Span G+4 Building by PEB and C...
IRJET- Comparative Study of Multi-Storey Multi-Span G+4 Building by PEB and C...
 
IRJET- Study of Pre-Engineered Building
IRJET-  	  Study of Pre-Engineered BuildingIRJET-  	  Study of Pre-Engineered Building
IRJET- Study of Pre-Engineered Building
 
Analysis of warehouse in staad pro.
Analysis of warehouse in staad pro. Analysis of warehouse in staad pro.
Analysis of warehouse in staad pro.
 
Comparative Study of Conventional Steel Structure and Tubular Steel Structure
Comparative Study of Conventional Steel Structure and Tubular Steel StructureComparative Study of Conventional Steel Structure and Tubular Steel Structure
Comparative Study of Conventional Steel Structure and Tubular Steel Structure
 
IRJET- Comparison of Structural Elements of a Pre-Engineered Building in Two ...
IRJET- Comparison of Structural Elements of a Pre-Engineered Building in Two ...IRJET- Comparison of Structural Elements of a Pre-Engineered Building in Two ...
IRJET- Comparison of Structural Elements of a Pre-Engineered Building in Two ...
 
Comparative Study of Codal Provisions for Pre-Engineered Buildings
Comparative Study of  Codal Provisions for Pre-Engineered BuildingsComparative Study of  Codal Provisions for Pre-Engineered Buildings
Comparative Study of Codal Provisions for Pre-Engineered Buildings
 
Irjet v4 i7530
Irjet v4 i7530Irjet v4 i7530
Irjet v4 i7530
 
An Investigation on Cost, Delay & Labor Problems in PEB Structure
An Investigation on Cost, Delay & Labor Problems in PEB StructureAn Investigation on Cost, Delay & Labor Problems in PEB Structure
An Investigation on Cost, Delay & Labor Problems in PEB Structure
 
IRJET- A Review on Comparative Study between Girder Bridge and Extradosed...
IRJET-  	  A Review on Comparative Study between Girder Bridge and Extradosed...IRJET-  	  A Review on Comparative Study between Girder Bridge and Extradosed...
IRJET- A Review on Comparative Study between Girder Bridge and Extradosed...
 
Effect of configuration on lateral displacement and cost of the structure for...
Effect of configuration on lateral displacement and cost of the structure for...Effect of configuration on lateral displacement and cost of the structure for...
Effect of configuration on lateral displacement and cost of the structure for...
 

Plus de IJERD Editor

A Novel Method for Prevention of Bandwidth Distributed Denial of Service Attacks
A Novel Method for Prevention of Bandwidth Distributed Denial of Service AttacksA Novel Method for Prevention of Bandwidth Distributed Denial of Service Attacks
A Novel Method for Prevention of Bandwidth Distributed Denial of Service Attacks
IJERD Editor
 
Gold prospecting using Remote Sensing ‘A case study of Sudan’
Gold prospecting using Remote Sensing ‘A case study of Sudan’Gold prospecting using Remote Sensing ‘A case study of Sudan’
Gold prospecting using Remote Sensing ‘A case study of Sudan’
IJERD Editor
 
Gesture Gaming on the World Wide Web Using an Ordinary Web Camera
Gesture Gaming on the World Wide Web Using an Ordinary Web CameraGesture Gaming on the World Wide Web Using an Ordinary Web Camera
Gesture Gaming on the World Wide Web Using an Ordinary Web Camera
IJERD Editor
 
Hardware Analysis of Resonant Frequency Converter Using Isolated Circuits And...
Hardware Analysis of Resonant Frequency Converter Using Isolated Circuits And...Hardware Analysis of Resonant Frequency Converter Using Isolated Circuits And...
Hardware Analysis of Resonant Frequency Converter Using Isolated Circuits And...
IJERD Editor
 
Simulated Analysis of Resonant Frequency Converter Using Different Tank Circu...
Simulated Analysis of Resonant Frequency Converter Using Different Tank Circu...Simulated Analysis of Resonant Frequency Converter Using Different Tank Circu...
Simulated Analysis of Resonant Frequency Converter Using Different Tank Circu...
IJERD Editor
 

Plus de IJERD Editor (20)

A Novel Method for Prevention of Bandwidth Distributed Denial of Service Attacks
A Novel Method for Prevention of Bandwidth Distributed Denial of Service AttacksA Novel Method for Prevention of Bandwidth Distributed Denial of Service Attacks
A Novel Method for Prevention of Bandwidth Distributed Denial of Service Attacks
 
MEMS MICROPHONE INTERFACE
MEMS MICROPHONE INTERFACEMEMS MICROPHONE INTERFACE
MEMS MICROPHONE INTERFACE
 
Influence of tensile behaviour of slab on the structural Behaviour of shear c...
Influence of tensile behaviour of slab on the structural Behaviour of shear c...Influence of tensile behaviour of slab on the structural Behaviour of shear c...
Influence of tensile behaviour of slab on the structural Behaviour of shear c...
 
Gold prospecting using Remote Sensing ‘A case study of Sudan’
Gold prospecting using Remote Sensing ‘A case study of Sudan’Gold prospecting using Remote Sensing ‘A case study of Sudan’
Gold prospecting using Remote Sensing ‘A case study of Sudan’
 
Reducing Corrosion Rate by Welding Design
Reducing Corrosion Rate by Welding DesignReducing Corrosion Rate by Welding Design
Reducing Corrosion Rate by Welding Design
 
Router 1X3 – RTL Design and Verification
Router 1X3 – RTL Design and VerificationRouter 1X3 – RTL Design and Verification
Router 1X3 – RTL Design and Verification
 
Active Power Exchange in Distributed Power-Flow Controller (DPFC) At Third Ha...
Active Power Exchange in Distributed Power-Flow Controller (DPFC) At Third Ha...Active Power Exchange in Distributed Power-Flow Controller (DPFC) At Third Ha...
Active Power Exchange in Distributed Power-Flow Controller (DPFC) At Third Ha...
 
Mitigation of Voltage Sag/Swell with Fuzzy Control Reduced Rating DVR
Mitigation of Voltage Sag/Swell with Fuzzy Control Reduced Rating DVRMitigation of Voltage Sag/Swell with Fuzzy Control Reduced Rating DVR
Mitigation of Voltage Sag/Swell with Fuzzy Control Reduced Rating DVR
 
Study on the Fused Deposition Modelling In Additive Manufacturing
Study on the Fused Deposition Modelling In Additive ManufacturingStudy on the Fused Deposition Modelling In Additive Manufacturing
Study on the Fused Deposition Modelling In Additive Manufacturing
 
Spyware triggering system by particular string value
Spyware triggering system by particular string valueSpyware triggering system by particular string value
Spyware triggering system by particular string value
 
A Blind Steganalysis on JPEG Gray Level Image Based on Statistical Features a...
A Blind Steganalysis on JPEG Gray Level Image Based on Statistical Features a...A Blind Steganalysis on JPEG Gray Level Image Based on Statistical Features a...
A Blind Steganalysis on JPEG Gray Level Image Based on Statistical Features a...
 
Secure Image Transmission for Cloud Storage System Using Hybrid Scheme
Secure Image Transmission for Cloud Storage System Using Hybrid SchemeSecure Image Transmission for Cloud Storage System Using Hybrid Scheme
Secure Image Transmission for Cloud Storage System Using Hybrid Scheme
 
Application of Buckley-Leverett Equation in Modeling the Radius of Invasion i...
Application of Buckley-Leverett Equation in Modeling the Radius of Invasion i...Application of Buckley-Leverett Equation in Modeling the Radius of Invasion i...
Application of Buckley-Leverett Equation in Modeling the Radius of Invasion i...
 
Gesture Gaming on the World Wide Web Using an Ordinary Web Camera
Gesture Gaming on the World Wide Web Using an Ordinary Web CameraGesture Gaming on the World Wide Web Using an Ordinary Web Camera
Gesture Gaming on the World Wide Web Using an Ordinary Web Camera
 
Hardware Analysis of Resonant Frequency Converter Using Isolated Circuits And...
Hardware Analysis of Resonant Frequency Converter Using Isolated Circuits And...Hardware Analysis of Resonant Frequency Converter Using Isolated Circuits And...
Hardware Analysis of Resonant Frequency Converter Using Isolated Circuits And...
 
Simulated Analysis of Resonant Frequency Converter Using Different Tank Circu...
Simulated Analysis of Resonant Frequency Converter Using Different Tank Circu...Simulated Analysis of Resonant Frequency Converter Using Different Tank Circu...
Simulated Analysis of Resonant Frequency Converter Using Different Tank Circu...
 
Moon-bounce: A Boon for VHF Dxing
Moon-bounce: A Boon for VHF DxingMoon-bounce: A Boon for VHF Dxing
Moon-bounce: A Boon for VHF Dxing
 
“MS-Extractor: An Innovative Approach to Extract Microsatellites on „Y‟ Chrom...
“MS-Extractor: An Innovative Approach to Extract Microsatellites on „Y‟ Chrom...“MS-Extractor: An Innovative Approach to Extract Microsatellites on „Y‟ Chrom...
“MS-Extractor: An Innovative Approach to Extract Microsatellites on „Y‟ Chrom...
 
Importance of Measurements in Smart Grid
Importance of Measurements in Smart GridImportance of Measurements in Smart Grid
Importance of Measurements in Smart Grid
 
Study of Macro level Properties of SCC using GGBS and Lime stone powder
Study of Macro level Properties of SCC using GGBS and Lime stone powderStudy of Macro level Properties of SCC using GGBS and Lime stone powder
Study of Macro level Properties of SCC using GGBS and Lime stone powder
 

Dernier

sample sample sample sample sample sample
sample sample sample sample sample samplesample sample sample sample sample sample
sample sample sample sample sample sample
Casey Keith
 
💕📲09602870969💓Girl Escort Services Udaipur Call Girls in Chittorgarh Haldighati
💕📲09602870969💓Girl Escort Services Udaipur Call Girls in Chittorgarh Haldighati💕📲09602870969💓Girl Escort Services Udaipur Call Girls in Chittorgarh Haldighati
💕📲09602870969💓Girl Escort Services Udaipur Call Girls in Chittorgarh Haldighati
Apsara Of India
 
CYTOTEC DUBAI ☎️ +966572737505 } Abortion pills in Abu dhabi,get misoprostal ...
CYTOTEC DUBAI ☎️ +966572737505 } Abortion pills in Abu dhabi,get misoprostal ...CYTOTEC DUBAI ☎️ +966572737505 } Abortion pills in Abu dhabi,get misoprostal ...
CYTOTEC DUBAI ☎️ +966572737505 } Abortion pills in Abu dhabi,get misoprostal ...
Abortion pills in Riyadh +966572737505 get cytotec
 
sample sample sample sample sample sample
sample sample sample sample sample samplesample sample sample sample sample sample
sample sample sample sample sample sample
Casey Keith
 
Ahmedabad Escort Service Ahmedabad Call Girl 0000000000
Ahmedabad Escort Service Ahmedabad Call Girl 0000000000Ahmedabad Escort Service Ahmedabad Call Girl 0000000000
Ahmedabad Escort Service Ahmedabad Call Girl 0000000000
mountabuangels4u
 

Dernier (20)

Genuine 8250077686 Hot and Beautiful 💕 Chennai Escorts call Girls
Genuine 8250077686 Hot and Beautiful 💕 Chennai Escorts call GirlsGenuine 8250077686 Hot and Beautiful 💕 Chennai Escorts call Girls
Genuine 8250077686 Hot and Beautiful 💕 Chennai Escorts call Girls
 
Sun World Bana Hills, Vienam Part 2 (越南 巴拿山太陽世界 下集).ppsx
Sun World Bana Hills, Vienam Part 2  (越南 巴拿山太陽世界 下集).ppsxSun World Bana Hills, Vienam Part 2  (越南 巴拿山太陽世界 下集).ppsx
Sun World Bana Hills, Vienam Part 2 (越南 巴拿山太陽世界 下集).ppsx
 
sample sample sample sample sample sample
sample sample sample sample sample samplesample sample sample sample sample sample
sample sample sample sample sample sample
 
💕📲09602870969💓Girl Escort Services Udaipur Call Girls in Chittorgarh Haldighati
💕📲09602870969💓Girl Escort Services Udaipur Call Girls in Chittorgarh Haldighati💕📲09602870969💓Girl Escort Services Udaipur Call Girls in Chittorgarh Haldighati
💕📲09602870969💓Girl Escort Services Udaipur Call Girls in Chittorgarh Haldighati
 
Darjeeling Call Girls 8250077686 Service Offer VIP Hot Model
Darjeeling Call Girls 8250077686 Service Offer VIP Hot ModelDarjeeling Call Girls 8250077686 Service Offer VIP Hot Model
Darjeeling Call Girls 8250077686 Service Offer VIP Hot Model
 
CYTOTEC DUBAI ☎️ +966572737505 } Abortion pills in Abu dhabi,get misoprostal ...
CYTOTEC DUBAI ☎️ +966572737505 } Abortion pills in Abu dhabi,get misoprostal ...CYTOTEC DUBAI ☎️ +966572737505 } Abortion pills in Abu dhabi,get misoprostal ...
CYTOTEC DUBAI ☎️ +966572737505 } Abortion pills in Abu dhabi,get misoprostal ...
 
WhatsApp Chat: 📞 8617697112 Independent Call Girls in Darjeeling
WhatsApp Chat: 📞 8617697112 Independent Call Girls in DarjeelingWhatsApp Chat: 📞 8617697112 Independent Call Girls in Darjeeling
WhatsApp Chat: 📞 8617697112 Independent Call Girls in Darjeeling
 
Andheri East Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Andheri East Call Girls 🥰 8617370543 Service Offer VIP Hot ModelAndheri East Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Andheri East Call Girls 🥰 8617370543 Service Offer VIP Hot Model
 
Top travel agency in panchkula - Best travel agents in panchkula
Top  travel agency in panchkula - Best travel agents in panchkulaTop  travel agency in panchkula - Best travel agents in panchkula
Top travel agency in panchkula - Best travel agents in panchkula
 
Hire 💕 8617697112 Chamba Call Girls Service Call Girls Agency
Hire 💕 8617697112 Chamba Call Girls Service Call Girls AgencyHire 💕 8617697112 Chamba Call Girls Service Call Girls Agency
Hire 💕 8617697112 Chamba Call Girls Service Call Girls Agency
 
Hire 💕 8617697112 Reckong Peo Call Girls Service Call Girls Agency
Hire 💕 8617697112 Reckong Peo Call Girls Service Call Girls AgencyHire 💕 8617697112 Reckong Peo Call Girls Service Call Girls Agency
Hire 💕 8617697112 Reckong Peo Call Girls Service Call Girls Agency
 
Alipore Call Girls - 📞 8617697112 🔝 Top Class Call Girls Service Available
Alipore Call Girls - 📞 8617697112 🔝 Top Class Call Girls Service AvailableAlipore Call Girls - 📞 8617697112 🔝 Top Class Call Girls Service Available
Alipore Call Girls - 📞 8617697112 🔝 Top Class Call Girls Service Available
 
sample sample sample sample sample sample
sample sample sample sample sample samplesample sample sample sample sample sample
sample sample sample sample sample sample
 
Tamluk ❤CALL GIRL 8617697112 ❤CALL GIRLS IN Tamluk ESCORT SERVICE❤CALL GIRL
Tamluk ❤CALL GIRL 8617697112 ❤CALL GIRLS IN Tamluk ESCORT SERVICE❤CALL GIRLTamluk ❤CALL GIRL 8617697112 ❤CALL GIRLS IN Tamluk ESCORT SERVICE❤CALL GIRL
Tamluk ❤CALL GIRL 8617697112 ❤CALL GIRLS IN Tamluk ESCORT SERVICE❤CALL GIRL
 
Genuine 8250077686 Hot and Beautiful 💕 Bhavnagar Escorts call Girls
Genuine 8250077686 Hot and Beautiful 💕 Bhavnagar Escorts call GirlsGenuine 8250077686 Hot and Beautiful 💕 Bhavnagar Escorts call Girls
Genuine 8250077686 Hot and Beautiful 💕 Bhavnagar Escorts call Girls
 
Kolkata Call Girls - 📞 8617697112 🔝 Top Class Call Girls Service Available
Kolkata Call Girls - 📞 8617697112 🔝 Top Class Call Girls Service AvailableKolkata Call Girls - 📞 8617697112 🔝 Top Class Call Girls Service Available
Kolkata Call Girls - 📞 8617697112 🔝 Top Class Call Girls Service Available
 
Papi kondalu Call Girls 8250077686 Service Offer VIP Hot Model
Papi kondalu Call Girls 8250077686 Service Offer VIP Hot ModelPapi kondalu Call Girls 8250077686 Service Offer VIP Hot Model
Papi kondalu Call Girls 8250077686 Service Offer VIP Hot Model
 
Genuine 8250077686 Hot and Beautiful 💕 Hosur Escorts call Girls
Genuine 8250077686 Hot and Beautiful 💕 Hosur Escorts call GirlsGenuine 8250077686 Hot and Beautiful 💕 Hosur Escorts call Girls
Genuine 8250077686 Hot and Beautiful 💕 Hosur Escorts call Girls
 
Genuine 8250077686 Hot and Beautiful 💕 Visakhapatnam Escorts call Girls
Genuine 8250077686 Hot and Beautiful 💕 Visakhapatnam Escorts call GirlsGenuine 8250077686 Hot and Beautiful 💕 Visakhapatnam Escorts call Girls
Genuine 8250077686 Hot and Beautiful 💕 Visakhapatnam Escorts call Girls
 
Ahmedabad Escort Service Ahmedabad Call Girl 0000000000
Ahmedabad Escort Service Ahmedabad Call Girl 0000000000Ahmedabad Escort Service Ahmedabad Call Girl 0000000000
Ahmedabad Escort Service Ahmedabad Call Girl 0000000000
 

International Journal of Engineering Research and Development

  • 1. International Journal of Engineering Research and Development e-ISSN: 2278-067X, p-ISSN: 2278-800X, www.ijerd.com Volume 10, Issue 9 (September 2014), PP.33-41 Comparative Study of Analysis and Design of Pre-Engineered Buildings and Conventional Frames G. Durga Rama Naidu1, K. Srinivasa Vengala Rao2, V. Divya Sri3, M. Navakanth4, G.V. Rama Rao5 1, 2, 3, 4 M.E. Students, Department of Civil Engineering,Andhra University College of Engineering, Visakhapatnam, India. 5Professor, Department of Civil Engineering, Andhra University College of Engineering, Visakhapatnam, India. Abstract:- Long Span, Column free structures are the most essential in any type of industrial structures and Pre Engineered Buildings (PEB) fulfills this requirement along with reduced time and cost as compared to conventional structures. The present work involves the comparative study and design of Pre Engineered Buildings (PEB) and Conventional steel frames. Design of the structure is being done in Staad Pro software and the same is then compared with conventional type, in terms of weight which in turn reduces the cost. Three examples have been taken for the study. Comparison of Pre Engineered Buildings (PEB) and Conventional steel frames is done in two examples and in the third example, Pre Engineered Building structure with increased bay space is taken for the study. In the present work, Pre Engineered Buildings (PEB) and Conventional steel frames structure is designed for wind forces. Wind analysis has been done manually as per IS 875 (Part III) – 1987. Keywords:- Pre-Engineered-Buildings; Conventional Buildings; Staad Pro; Steel Take-off; Tapered Sections. I. INTRODUCTION Steel industry is growing rapidly in almost all the parts of the world. The use of steel structures is not only economical but also ecofriendly at the time when there is a threat of global warming. Here, “economical” word is stated considering time and cost. Time being the most important aspect, steel structures (Pre-fabricated) is built in very short period and one such example is Pre Engineered Buildings (PEB). Pre-engineered buildings are nothing but steel buildings in which excess steel is avoided by tapering the sections as per the bending moment’s requirement. One may think about its possibility, but it’s a fact many people are not aware about Pre Engineered Buildings. If we go for regular steel structures, time frame will be more, and also cost will be more, and both together i.e. time and cost, makes it uneconomical. Thus in pre-engineered buildings, the total design is done in the factory, and as per the design, members are pre-fabricated and then transported to the site where they are erected in a time less than 6 to 8 weeks. The structural performance of these buildings is well understood and, for the most part, adequate code provisions are currently in place to ensure satisfactory behavior in high winds. Steel structures also have much better strength-to-weight ratios than RCC and they also can be easily dismantled. Pre Engineered Buildings have bolted connections and hence can also be reused after dismantling. Thus, pre-engineered buildings can be shifted and/or expanded as per the requirements in future. In this paper we will discuss the various advantages of pre-engineered buildings and also, with the help of three examples, a comparison will be made between pre-engineered 33 buildings and conventional steel structures. 1.1 Pre Engineered Buildings Presently, large column free area is the utmost requirement for any type of industry and with the advent of computer software’s it is now easily possible. With the improvement in technology, computer software’s have contributed immensely to the enhancement of quality of life through new researches. Pre-engineered building (PEB) is one of such revolution. "Pre-engineered buildings" are fully fabricated in the factory after designing, then transported to the site in completely knocked down (CKD) condition and all components are assembled and erected with nut-bolts, thereby reducing the time of completion. 1.1.1 Advantages of PEB Following are some of the advantages Pre-engineered building structures a) Construction Time: Buildings are generally constructed in just 6 to 8 weeks after approval ofdrawings. PEB will thus reduce total construction time of the project by at least 40%. This allows faster occupancy and earlier realization of revenue.
  • 2. Comparative Study of Analysis and Design of Pre-Engineered Buildings and Conventional Frames This is one of the main advantages of using Pre-engineered building. b) Lower Cost: Because of systems approach, considerable saving is achieved in design, manufacturing and erection cost. c) Flexibility of Expansion: As discussed earlier, these can be easily expanded in length by adding additional bays. Also expansion in width and height is possible by pre designing for future expansion. d) Large Clear Spans: Buildings can be supplied to around 90m clear spans. This is one of the most important advantages of PEB giving column free space. e) Quality Control: Buildings are manufactured completely in the factory under controlled conditions, and hence the quality can be assured. f) Low Maintenance: PEB Buildings have high quality paint systems for cladding and steel to suit ambient conditions at the site, which in turn gives long durability and low maintenance coats. g) Energy Efficient Roofing: Buildings are supplied with polyurethane insulated panels or fiberglass blankets insulation to achieve required “U” values (overall heat transfer coefficient). h) Erection: Steel members are brought to site in CKD conditions, thereby avoiding cutting and welding at site. As PEB sections are lighter in weight, the small members can be very easily assembled, bolted and raised with the help of cranes. This allows very fast construction and reduces wastage and labor requirement. From the numerous advantages of Pre-engineered building, in the present study, the point b is considered for the study, i.e. to save the steel and reducing cost, while all the other points are self-explanatory. II. ANALYSIS AND DESIGN OF PEB In this present work, Staad Pro software has been used in order to analyze and design Pre-engineered building structures and conventional structures. In the first example, a 2D plane frame of length 60 m, width 25m and bay spacing 6 m for both PEB and Conventional has been designed and comparison has been made in terms of weight of steel. In the second example, a 2D plane frame of length 60 m, width 25m and bay spacing 8 m has been designed with tapered sections for PEB, this example is not solved with conventional sections as it is neither possible by using only conventional steel sections nor it is economical. This frame has been designed for different bay spacing to choose the most economical. 34 2.1 Structural Analysis and Design STAAD Pro software can be used for analyzing and designing of the pre-engineered buildings. It gives the Bending Moment, Axial Forces, Shear Forces, Torsion, Beam Stresses of a steel structure so that the design can be done using tapered sections and check for the safety. 2.1.1Static Analysis In the present work, using the Staad Pro software, 2D analysis has been done using Stiffness Matrix Method. All the components of Pre-engineered building are tapered using the in-built option of the Software. The software provides options for hinged, fixed, and spring supports with releases so as to analyze as per our requirement. Herein this work, fixed supports are assigned to the structures. It also facilitates Linear, P-Delta Analysis, and Non-Linear Analysis with automatic load and stiffness correction. Multiple Analyses can also be done simultaneously which reduces the time. It also has an option of assigning members as tension-onlymembers and compression-only members for truss structures. 2.1.2 Dynamic Analysis Dynamic analysis has been done in the present work taking wind loads into consideration. The software provides automatic load generation for wind forces, however, the wind loads are calculated manually for the present work as per IS codes. The software also provides Loading for Joints, Members/Elements including concentrated, Uniform, Linear, Trapezoidal, Temperature, Strain, Support Displacement, Prestressed and Fixed-end Loads. It also provides the facility of Combination of Dynamic forceswith Static loading for subsequent design. III. EXAMPLE 1- INDUSTRIAL SHED 3.1 Statement of the Problem In this Example a comparison of 2D Plane Frame is made for both pre-engineered building and conventional type. The plane frame is having width 25 m and bay spacing 6 m and eave height 6 m, subjected to wind load. A 5-Ton Crane System is considered. A typical 2D PEB frame is shown in Fig 1 and the conventional frame as shown in Fig 2.
  • 3. Comparative Study of Analysis and Design of Pre-Engineered Buildings and Conventional Frames Figure 1: Elevation of Pre-Engineered Frame Figure 2: Elevation of Conventional Frame 35 Design Data- Main Frame- Frame Type - Clear Span, Rigid Frame. Support- Pinned Building Width (W) – 25 m (O/O Steel Columns) Building Length (L) – 60 m (O/O Steel Columns) Bay Spacing- 11 @ 6 m Eaves height- 6 m Roof Slope- 1 in10 Grits Type- Sidewall grits- Continuous End wall grits- Continuous Purlin Type- Roof Purlin- Continuous Spacing- 1.5m c/c Panel Type- Roof- Galvanized sheet.
  • 4. Comparative Study of Analysis and Design of Pre-Engineered Buildings and Conventional Frames 36 3.2 LOAD CALCULATIONS 3.2.1 Calculation of static loads: Dead loads are considered as per Table-2 of IS 875 (Part-1) – 1987 Weight of the G.I sheeting = 0.05 kN/m2 (class 1 G.I sheeting, thickness 0.5 mm) Self-weight of section = 0.05 kN/m2 Total weight = 0.10 kN/m2 Spacing of purlin = 1.5 m Bay spacing = 6 m Total weight on frame = 0.10 x 6 = 0.6 kN/m Live load are considered as per Table-2 of IS 875 (Part-2) – 1987 Live load on the sloping roof = 0.75 kN/m2 Live load on rafter = 0.75 x 6 = 4.5 kN/m 3.2.2 Calculation of Wind Loads: Wind loads are calculated as per IS 875 Part III (1987), in this example. For the Present work, the basic wind speed (Vb) is assumed as 44 m/s and the building is considered to be open terrain with well scattered obstructions having height less than 10m with maximum dimension more than 50m and accordingly factors K1, K2, K3 have been calculated as per IS 875 Part III (1987). Terrain Category- 2, Class- C K1- Probability factor- 1.0 K2- Terrain, height and size factor- 0.93 K3- Topography factor- 1 Design wind speed, Vz= Vb (K1 x K2 x K3) Vz= 40.92 m/s Design pressure, P= 0.6 Vz² = 1.005 kN/m² Ratio- H/W=0.24, L/W= 2.4 Wind Pressure Coefficients- External and Internal wind coefficients are calculated for all the surfaces for both pressure and suction. Openingin the building has been considered less than 5% and accordingly internal coefficients are taken as +0.2 and -0.2. The external coefficients and internal coefficients calculated as per IS 875 Part III (1987). Wind load on individual members are then calculated as below. F= (Cpe – Cpi) A Pz Where, Cpe, Cpi are external coefficients and internal coefficients respectively and A and P are Surface Area inm² and Design Wind Pressure in kN/m² respectively. Table 1: Wind load Left (Cpi = +0.2) Description Roof W.W Roof L.W Wall A Wall B Coefficients (Cpe) -0.94 -0.4 +0.7 -0.25 (Cpe – Cpi) -1.14 -0.6 0.5 -0.45 Wind load(F) kN/m -6.874 -3.618 3.015 -2.714 Table 2 Wind load Left (Cpi = -0.2) Description Roof W.W Roof L.W Wall A Wall B Coefficients (Cpe) -0.94 -0.4 +0.7 -0.25 (Cpe – Cpi) -0.74 -0.2 0.9 -0.05 Wind load(F) kN/m -4.462 -1.206 5.427 -0.302 Table 3 Wind load Right (Cpi = +0.2) Description Roof W.W Roof L.W Wall A Wall B Coefficients (Cpe) -0.94 -0.4 +0.7 -0.25 (Cpe – Cpi) -1.14 -0.6 0.5 -0.45 Wind load(F) kN/m -6.874 -3.618 3.015 -2.714
  • 5. Comparative Study of Analysis and Design of Pre-Engineered Buildings and Conventional Frames Table 4 Wind load Right (Cpi = -0.2) Description Roof W.W Roof L.W Wall A Wall B Coefficients (Cpe) -0.94 -0.4 +0.7 -0.25 (Cpe – Cpi) -0.74 -0.2 0.9 -0.05 Wind load(F) kN/m -4.462 -1.206 5.427 -0.302 Table 5 Wind load Parallel (Cpi = +0.2) Description Roof W.W Roof L.W Wall A Wall B Wall C Wall D Coefficients (Cpe) -0.94 -0.4 +0.7 -0.25 -0.6 -0.6 (Cpe – Cpi) -1.14 -0.6 0.5 -0.45 -0.8 -0.8 Wind load(F) kN/m -3.437 -1.809 1.508 -1.357 -4.02 -4.02 Table 6 Wind load Parallel (Cpi = -0.2) Description Roof W.W Roof L.W Wall A Wall B Wall C Wall D Coefficients (Cpe) -0.94 -0.4 +0.7 -0.25 -0.6 -0.6 (Cpe – Cpi) -0.74 -0.2 0.9 -0.05 -0.4 -0.4 Wind load(F) kN/m -2.231 -0.603 2.714 -0.151 -2.01 -2.01 3.3 Weight of Steel (Steel Take Off) 3.3.1 Weight of the steel for the conventional steel building In order to calculate the steel weight of conventional steel building the following member properties are used (Table 7). Hot rolled “I” sections are assigned for beams and columns. For purlins, girts and eave strut Z sections are used. Now using the above parameters the length and weights are calculated accordingly. Table 7: Steel take-off for conventional steel building Profile Length (m) Weight (t) ST ISMB250 12.56 4.584 ST ISMB300 2.50 1.081 ST ISMB450 6.00 4.254 ST ISMB550 18.56 18.837 ISA 75X75X6 170.95 11.372 ISA 50X50X6 171.93 7.52 ST 200Z60X2 1560 8.547 37 Total = 56.17 Figure 3 Primary Frame Showing the Section
  • 6. Comparative Study of Analysis and Design of Pre-Engineered Buildings and Conventional Frames 3.4.2 Weight of the steel for the PEB with primary frame spacing 6 m In order to calculate steel weight of PEB of primary frame spacing 6 m the following member properties are used (Table 8). For columns and rafters Tapered “I” sections are assigned. For the purlins and girts cold formed “Z” sections are used. For bracings Indian standard angle sections are used. Now using the above parameters the lengths and weights are calculated accordingly. Table 8 Steel take-off for the PEB with primary frame spacing 6 m Profile Length (m) Weight (t) Tapered MembNo: 1 6.00 2.503 Tapered MembNo: 2 12.56 8.975 Tapered MembNo: 3 12.56 7.921 Tapered MembNo: 4 6.00 3.308 ST ISMB300 2.50 1.081 ISA 75X75X6 170.95 11.372 ISA 50X50X6 171.93 7.502 ST 200Z60X2 1560 8.547 38 Total = 42.66 Figure 4 Primary Frame showing Sections 56.17 Graph 1 Weight Comparison between CSB and PEB 6 m span. 60 50 40 30 20 10 0 1 42.66 Weight (Tons) WEIGHT COMPARISON BETWEEN CSB AND PEB 6 M SPAN CSB 6 M SPAN PEB 6 M SPAN
  • 7. Comparative Study of Analysis and Design of Pre-Engineered Buildings and Conventional Frames IV. EXAMPLE-2 INDUSTRIAL SHED In this Example a 2D Plane Frame Pre-engineered building Frame is analyzed and designed. The plane frame is having width 25 m and bay spacing 8 m and eave height 6 m, subjected to wind load. A 5-Ton Crane System is considered. A 3-D PEB is shown in fig 5. Figure 53-D structure of PEB of Primary Frame spacing of 8 m. 39 4.1 Loadings: All loads are calculated as given in Section 3.1. 4.2 Weight of Steel (Steel Take-Off). 4.2.1 Weight of the steel for the PEB with primary frame spacing 8 m In order to calculate steel weight of PEB of primary frame spacing 8 m the following member properties are used. For columns and rafters tapered “I” sections are used. For the purlins and cold formed “Z” sections are used. For bracings Indian standard angle sections are used. Now using the above parameter the lengths and weights are calculated accordingly. Table 9 Steel take-off for the PEB with primary frame spacing 8 m Profile Length (m) Weight (t) Tapered MembNo: 1 6.00 2.641 Tapered MembNo: 2 18.56 12.320 Tapered MembNo: 3 12.56 6.794 ST ISMB300 2.50 1.081 ISA 75X75X6 170.95 11.372 ISA 50X50X6 171.93 7.502 ST 200Z60X2 1560 8.547 Total = 41.71
  • 8. Comparative Study of Analysis and Design of Pre-Engineered Buildings and Conventional Frames 1 42.66 41.71 Graph 2 Weight Comparison between PEB 6 m span and PEB 8 m span. V. CONCLUSION 43 42.8 42.6 42.4 42.2 42 41.8 41.6 41.4 41.2 41 Pre-engineered steel structures building offers low cost, strength, durability, design flexibility, adaptability andrecyclability. Steel is the basic material that is used in the materials that are used for Pre-engineered steelbuilding. It negates from regional sources. Infinitely recyclable, steel is the material that reflects the imperativesof sustainable development.Based on the analytical and design results thereon of conventional and pre-engineered steel buildings, the following conclusions are drawn. 1. The total steel take-off for PEB with primary frame spacing of 6 m is 76% of the conventional steel 40 building. 2. The total steel take-off for PEB with primary frame spacing of 8 m is 74.4% of the conventional steel building. 3. Steel take-off is more for PEB with primary frame spacing of 6 m than PEB with primary frame spacing of 8 m. It is also seen that the weight of PEB depends on the Bay Spacing, with the increase in Bay Spacing up to certain spacing, the weight reduces and further increase makes the weight heavier. To Conclude “Pre-Engineered Building Construction gives the end users a much more economical and better solution for long span structures where large column free areas are needed”. REFERENCES [1] IS 875 (part-1) “Code of practice for design loads (other than earthquake) for building and structures”, Dead loads, New Delhi, 1987. [2] IS 875 (part-2) “Code of practice for design loads (other than earthquake) for building and structures”, Imposed loads, New Delhi, 1987. [3] IS 875 (part-3) “Code of practice for design loads (other than earthquake) for building and structures”, Wind loads, New Delhi, 1987. [4] Jatin D.Thakar, P.G. Patel, “Comparative Study of Pre-Engineered Steel Structure by varying width of Structure”, International Journal of Advanced Engineering Technology, Volume IV, Issue III, sept 2013, pp: 56-62. Weight (Tons) WEIGHT COMPARISON BETWEEN PEB 6 M SPAN AND PEB 8 M SPAN PEB 6 M SPAN PEB 8 M SPAN
  • 9. Comparative Study of Analysis and Design of Pre-Engineered Buildings and Conventional Frames [5] Kanakambara Rao et al. “Design of Pre-Engineered steel structures building and to choose a material which offers low cost, strength, durability, design flexibility and recyclability”, International Journal of Engineering Research and Applications (IJERA), Vol. 2, Issue 2, April 2012, pp: 267-272. [6] Kulkarni A.V., “Comparative Study of Analysis and Design of Pre-Engineered Buildings and Conventional Frames and various advantages of PEB’s”, IOSR journal of mechanical and civil engineering, Volume 5, Issue 3, Jan. – Feb. 2013, pp: 47-53. 41