5. What is Risk?
5
Uncertain Event or Condition
Always in the Future
Effect on Project Objective
Has Causes, Impact and Probability
Negative or Positive Outcome
6. 6
Practice: What are the benefits of risks
management?
Define common ways to manage risks, analyze, response plans
Increase project success probability
Realistic estimates
Remove obstacles on project launch phases
Increase profitability
Less stress
Professionalism and reputation
7. Whenever a project
doesn’t meet to the
expectation of the
Stakeholders.
7
Project Failure
A Project is considered as Failure……
8. • Cost & Time Over-runs
• Quality Degradation
• Frustration & Stress: sometime resulting in
people quitting
• Low Job Satisfaction
• Low Corporate Market Value
• Low Public Opinion
• Negative Media Campaigns
• May even force the company into Closure
Impact of Project Failure
8
10. Problems:
The changes that were not initially planned for, are added to
project.
The Project takes longer and costs more than planned and there
is no record of WHY??
Causes:
Not having a method to handle or recognize changes.
1. Lack of Change Management
10
11. Problems:
Team Members do not have the information they need when they
need it.
Issues or changes do not get escalated.
Project reporting is sluggish
Causes:
The project’s communication plan
was not completed.
The project’s communication plan
doesn’t have enough details.
2. Poor Communication
11
12. You do not have enough people, the right skill-sets, or the team is not
committed to the projects.
Problems:
Tasks take longer than expected
to complete.
Deadlines and milestones get
missed.
Project completion date comes
into jeopardy.
You end up working double shifts to
complete all the works.
Causes:
There was no pre-commitment of resources to the projects.
The Project was not supported.
There was no analysis and documentation of all skill-set required
3. Inadequate Resources
12
13. “I would like a set of stairs that leads up to a bridge.”
Problems:
Customer will be unhappy.
Customer will complain and you will end up doing the what they
want- at your expense.
Causes:
What the customer wants, was not clearly documented.
What you believe the customer wants is different that what
the customer believes they have asked for?
4. Poorly Defined Requirement
13
14. How do you figure out how long the project will take?
Problems:
An unrealistic timeline or budget will be agreed to.
You will not be able to do all the work in the time allocated.
Causes:
No formal estimating method
Estimate confidence is law.
Volume of work not understood
5. Inaccurate Estimates
14
15. Sorry about the project, I left it in my car & there was a bit
of an incidents.
Problems:
Unexpected events cause delays.
Domino effect of thing going wrong.
Causes:
No Formal Risk Management.
Just try to predict the big things that can go wrong.
It’s the sum of the all little things that make a project late.
Nothing is more stressful than trying to keep on schedule when
unexpected things keep happening.
6. Poor Risk Management
15
16. “Emergency Phone installed, Deliverable completed”
Problems:
Difficult to get the agreement that the product is finished.
Customer Keep wanting more, saying you didn’t do it to their
Specification.
Causes:
The Milestones or deliverables were not measurable.
The customer never told us How many they wanted So we just
assumed 1,
7. Poorly Defined Deliverables
16
17. Of course we Can do that for you.
Problems:
There was little or no planning before deciding you can get the
job done.
The task you agree to turns out to be more work than expected.
It takes you longer and jeopardizes other deliverables.
Causes:
Not enough time spent planning.
You may have been pressured into giving an answer right then
and there.
Didn’t have a full understanding of the work involved before
committing.
8. Over Optimism
17
18. Hurry .... We have a tight deadline. No time to plan. Just start digging.
Problems:
The plan is flawed from the start.
The project gets out of control and can’t be recovered.
Causes:
You have to do the work and weren’t also given time for project
management.
Perhaps you only have 10% or 20%
allotment for the project management
duties.
9. No time for Project Management
18
19. You Don't Know What You Don't Know.
Problems:
Your project don’t finish on time.
Your project are always squeezed at the end.
Your project are stressful.
You have to deal with unrealistic expectation or customers.
You feel your projects are out of control.
Causes:
People often don’t know what they don’t know.
Their project are out of control but they
don’t know WHY??
They feel they are doing okay but could
benefit from formal PM education.
10. Improved PM Skill-set needed
19
20. Risk Management Process
20
Plan Risk
Management
Identify Risks
Perform Risk
Analysis
Plan Risk
Responses
Monitoring &
Control
21. Define how will we work with Risks:
resources, responsibilities, frequency, risk
tolerance…
Plan Risk Management
21
22. Risk Management Plan:
• Categorize risk sources
• Probability Matrix
• Roles, Responsibilities, Activity Plan
• Monitoring, Reporting, Communication
• Tolerance, Management/Contingency
reserves, reaction (before, after)
Plan Risk Management
22
26. Matrix of Probability and Impact
Scale: Planning Poker
Matrix of Probability and Impact
27. Matrix of Influence Definition
Should correlate with Matrix of Probability and
Impact and with Categorization of Sources and
Influence
Matrix of Influence Definition
Should correlate with Matrix of Probability and Impact and
with Categorization of Sources and Influence
29. Risk Register
30
ID Risk Impact Probability Impact Risk Value Notes
1
Application response will
be worse than expected
according to the
acceptance criteria
Architecture redesign –
3 weeks
2
Specifications aren’t
confirmed by client
Corresponding time
delay, budget increase
3 … …
30. ID Risk Impact Probability Impact Risk Value Notes
1
Application response will
be worse than expected
according to the
acceptance criteria
Architecture redesign –
3 weeks
3 5 15
2
Specifications aren’t
confirmed by client
Corresponding time
delay, budget increase
2 1 2
3 … …
Perform Qualitative Risk Analysis
Current Risks
Watchlist
Perform Qualitative Risk Analysis
31. Negative Risks: Avoid, Transfer, Mitigate
Positive Risks: Exploit, Share, Enhance
Acceptance of Positive and Negative
Risks
Plan Risk Responses
32
32. Risk Management Strategies
33
If your project requires
that you stand on the
edge of a cliff, then
there’s a risk that you
could fall.
If it’s very windy out or
the ground is slippery
and uneven, then
falling is more likely.
33. Risk Management Strategies - Avoid
34
The easiest way to
avoid this risk is to
walk away from the
cliff… but that may not
be an option on this
project
34. Risk Management Strategies - Mitigate
35
If you can’t avoid the risk,
you can mitigate it. This
means taking some sort of
action that will cause it do
as little damage to your
project as possible.
35. Risk Management Strategies - Transfer
36
One effective way of deal
with risk is to pay someone
else to accept it for you.
The most common way to
do this is to buy insurance.
36. Risk Management Strategies - Accept
37
If you can’t avoid the
risk and there’s nothing
you can do to reduce its
impact then accepting it
is you only choice
Looks like falling is
the best option
37. Monitor and Control Risks
38
Information Management Systems
▪ Expert Judgment
▪ Meetings
38. Monitor and Control Risks
Iteratively!
Monitor and Control Risks
Project Start
Project EndProject Plan Changes, Change
Requests, Change in Risk
Register and Project
Documents
39. Emergency Budget (direct, indirect)
strategy “Before”:
Most critical Risks in the project plan from very beginning
strategy “After”:
Contingency Reserve should be in the project plan
management Reserve:
5%-7% for unpredictable cases (in addition to known risks)
Risks and Client
40
Project Scope
Proactive
Reaction
Contingency
Reserve
Management
Reserve
43. 10 Golden Rules of Risk Management
1. Make Risk Management Part of Your Project
2. Identify Risks Early in Your Project
3. Communicate About Risks
4. Consider Both Threats and Opportunities
5. Clarify Ownership Issues
6. Prioritize Risks
7. Analyze Risks
8. Plan and Implement Risk Responses
9. Register Project Risks
10.Track Risks and Associated Tasks
10 Golden Rules of Risk Management
• Make Risk Management Part of Your Project
• Identify Risks Early in Your Project
• Communicate About Risks
• Consider Both Threats and Opportunities
• Clarify Ownership Issues
• Prioritize Risks
• Analyze Risks
• Plan and Implement Risk Responses
• Register Project Risks
• Track Risks and Associated Tasks
45. Thank you
USA TELEPHONE
Toll-Free: 866.687.3588
Office: 239.690.3111
EMAIL
info@softserveinc.com
WEBSITE:
www.softserveinc.com
EUROPE OFFICES
United Kingdom
Germany
Netherlands
Ukraine
Bulgaria
US OFFICES
Austin, TX
Fort Myers, FL
Boston, MA
Newport Beach, CA
Salt Lake City, UT
46. There is a web application – business analytics. Known technologies,
DB, 23 main modules, DB architecture is very complex, DB performance
is very critical with the strict acceptance criteria. Requirement are 50%
defined, very low chances for requirements to be changed, but they
should be very clear before the realization.
Now is August, release is on April 1. Client wants to have full
transparency on progress. There couldn’t be delay with the delivery of
the whole scope, it is more important than budget.
Test environment is on client’s side, very big load on the network
connection (more than the channel is now).
Client is very qualified in business area, will be doing UAT. Main expert
on the client’s side is Jar Jar Binks. Project team should be 15 people, 5
are missing, they will be not used after project completion. DB architect
works on another project 60-70%. Client’s expert Jar Jar Binks hardly
uses email and has strong non-English accent.
Practice
47