SlideShare une entreprise Scribd logo
1  sur  12
PMI, PMP, CAPM, PgMP, PMI-ACP, PMI-SP, PMI-RMP and PMBOK are trademarks of the Project Management Institute, Inc. PMI has
not endorsed and did not participate in the development of this publication. PMI does not sponsor this publication and makes no
warranty, guarantee or representation, expressed or implied as to the accuracy or content. Every attempt has been made by OSP
International LLC to ensure that the information presented in this publication is accurate and can serve as preparation for the PMP
certification exam. However, OSP International LLC accepts no legal responsibility for the content herein. This document should be
used only as a reference and not as a replacement for officially published material. Using the information from this document does not
guarantee that the reader will pass the PMP certification exam. No such guarantees or warranties are implied or expressed by OSP
International LLC.
PMPPMP®
SampleSample
QuestionsQuestions
This presentation will showcase free
sample PMP®
questions that will
help and guide you in studying for
your PMP®
exam
Find more free sample
questions when you visit
www.free-pm-exam-questions.com
and free.pm-exam-simulator.com
Which of the following elements constitute the scope baseline?
a.Scope Statement, WBS, and Project Schedule
b.Scope Statement, Project Schedule, and WBS Dictionary
c.WBS Dictionary, Resource Calendars, and Project Schedule
d.Scope Statement, WBS, and WBS Dictionary
Sample PMP®
Exam Question
HINT: The Scope Baseline should contain the scope and related work
information.
The correct answer is D
The Scope Baseline contains the Scope
Statement, the WBS, and the WBS Dictionary.
Answer and Explanation
Which of the following buffers are placed at the end of the critical chain to protect
the target finish date from slippage?
a.Feeding Buffer
b.Project Buffer
c.Free Buffer
d.Activity Buffer
Sample PMP®
Exam Question
HINT: This buffer protects the target finish date from moving and is
intended to protect the project end date.
The correct answer is B
A Project Buffer is placed at the end of the
critical chain to protect the target finish from
slippage along the critical chain. On the other
hand, Feeding Buffers are placed at those
points in the chain where tasks that are not on
the critical path feed into the critical path. Free
buffers and Activity buffers are not used in
critical chain.
Answer and Explanation
According to the PMBOK®
Guide, which of the following is not a valid activity
dependency?
a.Mandatory Dependency
b.Internal Dependency
c.External Dependency
d.Discretional Dependency
Sample PMP®
Exam Question
HINT: This question references the Sequence Activities process.
The correct answer is B
The PMBOK Guide recognizes three types of dependencies;
Mandatory, Discretionary and External. The PMBOK Guide
doesn't recognize "Internal Dependencies" as a type of
dependency. Did it confuse you that one of the answers used
the term "Discretional Dependencies" instead of
"Discretionary Dependencies"? Expect that even on the
actual PMP exam you will come across questions where
terminology does not exactly match the PMBOK Guide. Even
considering that "Discretional Dependencies" is not the exact
same term as “Discretionary Dependencies”, "Internal
Dependencies" is even less correct and therefore the correct
answer.
Answer and Explanation
According to the PMBOK Guide, a WBS is not directly involved in which of the
following processes?
a.Develop Project Management Plan
b.Define Activities
c.Create WBS
d.Define Scope
Sample PMP®
Exam Question
HINT: Develop Project Management Plan process creates the Scope
Management Plan.
The correct answer is D
The Develop Project Management Plan
process carries out scope planning, which
documents how the WBS will be created and
defined. Define Activities takes the WBS as an
input and decomposes it to define activities.
Create WBS creates the WBS itself. The
Define Scope process must be completed
before the Create WBS process can be
started.
Answer and Explanation
Information in the WBS dictionary does not include?
a.Contract Information
b.Quality Requirements
c.Responsible Organization
d.Project Activities
Sample PMP®
Exam Question
HINT: WBS dictionary contains a lot of items and explains each work
package in great detail.
The correct answer is D
The WBS Dictionary contains a lot of items and
explains each work package in great detail.
This information includes Contract Information
regarding the work packages, Quality
Requirements, and the Responsible
Organization. However, the WBS Dictionary
does not included the specific project activities.
Answer and Explanation

Contenu connexe

Tendances

Tendances (18)

Pmp sample questions
Pmp sample questionsPmp sample questions
Pmp sample questions
 
PMP Exam Sample Questions
PMP Exam Sample QuestionsPMP Exam Sample Questions
PMP Exam Sample Questions
 
PMP Sample Questions Set 5
PMP Sample Questions Set 5PMP Sample Questions Set 5
PMP Sample Questions Set 5
 
PMP Exam Sample Questions
PMP Exam Sample QuestionsPMP Exam Sample Questions
PMP Exam Sample Questions
 
PMP Exam Sample Questions
PMP Exam Sample QuestionsPMP Exam Sample Questions
PMP Exam Sample Questions
 
Free PMP Sample Q & A
Free PMP Sample Q & AFree PMP Sample Q & A
Free PMP Sample Q & A
 
PMP Exam Sample Questions
PMP Exam Sample QuestionsPMP Exam Sample Questions
PMP Exam Sample Questions
 
Free PMP® Exam Sample Question
Free PMP® Exam Sample QuestionFree PMP® Exam Sample Question
Free PMP® Exam Sample Question
 
Free PMP Sample Q & A
Free PMP Sample Q & AFree PMP Sample Q & A
Free PMP Sample Q & A
 
Free PMP Sample Q & A
Free PMP Sample Q & AFree PMP Sample Q & A
Free PMP Sample Q & A
 
Free PMP Sample Q & A
Free PMP Sample Q & AFree PMP Sample Q & A
Free PMP Sample Q & A
 
Free PMP Sample Q & A
Free PMP Sample Q & AFree PMP Sample Q & A
Free PMP Sample Q & A
 
Exam1
Exam1Exam1
Exam1
 
PMP® Sample Questions Set #2
PMP® Sample Questions Set #2PMP® Sample Questions Set #2
PMP® Sample Questions Set #2
 
PMP® Sample Questions 6
PMP® Sample Questions 6PMP® Sample Questions 6
PMP® Sample Questions 6
 
Pmp sample questions set2
Pmp sample questions set2Pmp sample questions set2
Pmp sample questions set2
 
PMP Five Sample Questions
PMP Five Sample QuestionsPMP Five Sample Questions
PMP Five Sample Questions
 
03 pmp project management processes exam
03 pmp project management processes exam03 pmp project management processes exam
03 pmp project management processes exam
 

En vedette

En vedette (11)

PMP® Sample Questions 3
PMP® Sample Questions 3PMP® Sample Questions 3
PMP® Sample Questions 3
 
PMP Exam Q&A
PMP Exam Q&APMP Exam Q&A
PMP Exam Q&A
 
PMP Sample Questions Set 2
PMP Sample Questions Set 2PMP Sample Questions Set 2
PMP Sample Questions Set 2
 
Sample PMP Exam Questions
Sample PMP Exam QuestionsSample PMP Exam Questions
Sample PMP Exam Questions
 
PMP® Sample Questions and Answers
PMP® Sample Questions and AnswersPMP® Sample Questions and Answers
PMP® Sample Questions and Answers
 
PMP® Sample Questions
PMP® Sample QuestionsPMP® Sample Questions
PMP® Sample Questions
 
PMP Exam Sample Questions 4
PMP Exam Sample Questions 4PMP Exam Sample Questions 4
PMP Exam Sample Questions 4
 
175 PMP Sample Questions
175 PMP Sample Questions175 PMP Sample Questions
175 PMP Sample Questions
 
PMP Exam Sample Questions 9
PMP Exam Sample Questions 9PMP Exam Sample Questions 9
PMP Exam Sample Questions 9
 
Pmp questions and explanations
Pmp questions and explanationsPmp questions and explanations
Pmp questions and explanations
 
1 project management framework - Fifth edition
1  project management framework - Fifth edition1  project management framework - Fifth edition
1 project management framework - Fifth edition
 

Similaire à PMP Exam Sample Questions Set 8

pmp-examination-content-outline.pdf
pmp-examination-content-outline.pdfpmp-examination-content-outline.pdf
pmp-examination-content-outline.pdf
ssuserffe62d
 
F5 PM_BPP_Workbook_2020-2021.pdf
F5 PM_BPP_Workbook_2020-2021.pdfF5 PM_BPP_Workbook_2020-2021.pdf
F5 PM_BPP_Workbook_2020-2021.pdf
NgcThu48
 
V 2.0Project Charter Project NamePro.docx
V 2.0Project Charter Project NamePro.docxV 2.0Project Charter Project NamePro.docx
V 2.0Project Charter Project NamePro.docx
dickonsondorris
 

Similaire à PMP Exam Sample Questions Set 8 (20)

Pmp Five Sample Questions
Pmp Five Sample QuestionsPmp Five Sample Questions
Pmp Five Sample Questions
 
PMP Exam Sample Questions
PMP Exam Sample QuestionsPMP Exam Sample Questions
PMP Exam Sample Questions
 
PMP Exam Sample Questions
PMP Exam Sample QuestionsPMP Exam Sample Questions
PMP Exam Sample Questions
 
Free CAPM® Exam Sample Question
Free CAPM® Exam Sample QuestionFree CAPM® Exam Sample Question
Free CAPM® Exam Sample Question
 
PMP® Sample Questions 5
PMP® Sample Questions 5PMP® Sample Questions 5
PMP® Sample Questions 5
 
Understanding 15 pmi question types by adekunle adeniyi taskmodes_march 2017
Understanding 15 pmi question types by adekunle adeniyi taskmodes_march 2017Understanding 15 pmi question types by adekunle adeniyi taskmodes_march 2017
Understanding 15 pmi question types by adekunle adeniyi taskmodes_march 2017
 
project management entrance exam content.pdf
project management entrance exam content.pdfproject management entrance exam content.pdf
project management entrance exam content.pdf
 
pmp-examination-content-outline.pdf
pmp-examination-content-outline.pdfpmp-examination-content-outline.pdf
pmp-examination-content-outline.pdf
 
Session 6 Everything You Should Know About PMP & CAPM Certifications
Session 6 Everything You Should Know About PMP & CAPM CertificationsSession 6 Everything You Should Know About PMP & CAPM Certifications
Session 6 Everything You Should Know About PMP & CAPM Certifications
 
Pmp1
Pmp1Pmp1
Pmp1
 
PMP certification
PMP certificationPMP certification
PMP certification
 
Free PMP® Exam Sample Question
Free PMP® Exam Sample QuestionFree PMP® Exam Sample Question
Free PMP® Exam Sample Question
 
How To Build A Credible Performance Measurement Baseline
How To Build A Credible Performance Measurement BaselineHow To Build A Credible Performance Measurement Baseline
How To Build A Credible Performance Measurement Baseline
 
How To Build A Credible Performance Measurement Baseline
How To Build A Credible Performance Measurement BaselineHow To Build A Credible Performance Measurement Baseline
How To Build A Credible Performance Measurement Baseline
 
F5 PM_BPP_Workbook_2020-2021.pdf
F5 PM_BPP_Workbook_2020-2021.pdfF5 PM_BPP_Workbook_2020-2021.pdf
F5 PM_BPP_Workbook_2020-2021.pdf
 
V 2.0Project Charter Project NamePro.docx
V 2.0Project Charter Project NamePro.docxV 2.0Project Charter Project NamePro.docx
V 2.0Project Charter Project NamePro.docx
 
Free PMP Exam Sample Question
Free PMP Exam Sample QuestionFree PMP Exam Sample Question
Free PMP Exam Sample Question
 
PMP Exam Q & A
PMP Exam Q & APMP Exam Q & A
PMP Exam Q & A
 
Session 5 Everything You Should Know About PMP & CAPM Certifications
Session 5 Everything You Should Know About PMP & CAPM CertificationsSession 5 Everything You Should Know About PMP & CAPM Certifications
Session 5 Everything You Should Know About PMP & CAPM Certifications
 
PMP Exam Q & A
PMP Exam Q & APMP Exam Q & A
PMP Exam Q & A
 

Plus de OSP International LLC

Plus de OSP International LLC (20)

Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free CAPM Exam Sample Question of the Week!
Free CAPM Exam Sample Question of the Week!Free CAPM Exam Sample Question of the Week!
Free CAPM Exam Sample Question of the Week!
 
Free PMP Exam Sample Question of the Week!
Free PMP Exam Sample Question of the Week!Free PMP Exam Sample Question of the Week!
Free PMP Exam Sample Question of the Week!
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 
Free PMP Exam Sample Question from the PM Exam Simulator
Free PMP Exam Sample Question from the PM Exam SimulatorFree PMP Exam Sample Question from the PM Exam Simulator
Free PMP Exam Sample Question from the PM Exam Simulator
 
Free CAPM Exam Sample Question from the PM Exam Simulator
Free CAPM Exam Sample Question from the PM Exam SimulatorFree CAPM Exam Sample Question from the PM Exam Simulator
Free CAPM Exam Sample Question from the PM Exam Simulator
 
Free PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the WeekFree PMP Exam Sample Question of the Week
Free PMP Exam Sample Question of the Week
 
Free CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the WeekFree CAPM Exam Sample Question of the Week
Free CAPM Exam Sample Question of the Week
 

Dernier

Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
PECB
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
QucHHunhnh
 

Dernier (20)

Sociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning ExhibitSociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning Exhibit
 
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptxINDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan Fellows
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot Graph
 
psychiatric nursing HISTORY COLLECTION .docx
psychiatric  nursing HISTORY  COLLECTION  .docxpsychiatric  nursing HISTORY  COLLECTION  .docx
psychiatric nursing HISTORY COLLECTION .docx
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
Role Of Transgenic Animal In Target Validation-1.pptx
Role Of Transgenic Animal In Target Validation-1.pptxRole Of Transgenic Animal In Target Validation-1.pptx
Role Of Transgenic Animal In Target Validation-1.pptx
 
General Principles of Intellectual Property: Concepts of Intellectual Proper...
General Principles of Intellectual Property: Concepts of Intellectual  Proper...General Principles of Intellectual Property: Concepts of Intellectual  Proper...
General Principles of Intellectual Property: Concepts of Intellectual Proper...
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptx
 
ComPTIA Overview | Comptia Security+ Book SY0-701
ComPTIA Overview | Comptia Security+ Book SY0-701ComPTIA Overview | Comptia Security+ Book SY0-701
ComPTIA Overview | Comptia Security+ Book SY0-701
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and Mode
 
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 

PMP Exam Sample Questions Set 8

  • 1. PMI, PMP, CAPM, PgMP, PMI-ACP, PMI-SP, PMI-RMP and PMBOK are trademarks of the Project Management Institute, Inc. PMI has not endorsed and did not participate in the development of this publication. PMI does not sponsor this publication and makes no warranty, guarantee or representation, expressed or implied as to the accuracy or content. Every attempt has been made by OSP International LLC to ensure that the information presented in this publication is accurate and can serve as preparation for the PMP certification exam. However, OSP International LLC accepts no legal responsibility for the content herein. This document should be used only as a reference and not as a replacement for officially published material. Using the information from this document does not guarantee that the reader will pass the PMP certification exam. No such guarantees or warranties are implied or expressed by OSP International LLC. PMPPMP® SampleSample QuestionsQuestions
  • 2. This presentation will showcase free sample PMP® questions that will help and guide you in studying for your PMP® exam Find more free sample questions when you visit www.free-pm-exam-questions.com and free.pm-exam-simulator.com
  • 3. Which of the following elements constitute the scope baseline? a.Scope Statement, WBS, and Project Schedule b.Scope Statement, Project Schedule, and WBS Dictionary c.WBS Dictionary, Resource Calendars, and Project Schedule d.Scope Statement, WBS, and WBS Dictionary Sample PMP® Exam Question HINT: The Scope Baseline should contain the scope and related work information.
  • 4. The correct answer is D The Scope Baseline contains the Scope Statement, the WBS, and the WBS Dictionary. Answer and Explanation
  • 5. Which of the following buffers are placed at the end of the critical chain to protect the target finish date from slippage? a.Feeding Buffer b.Project Buffer c.Free Buffer d.Activity Buffer Sample PMP® Exam Question HINT: This buffer protects the target finish date from moving and is intended to protect the project end date.
  • 6. The correct answer is B A Project Buffer is placed at the end of the critical chain to protect the target finish from slippage along the critical chain. On the other hand, Feeding Buffers are placed at those points in the chain where tasks that are not on the critical path feed into the critical path. Free buffers and Activity buffers are not used in critical chain. Answer and Explanation
  • 7. According to the PMBOK® Guide, which of the following is not a valid activity dependency? a.Mandatory Dependency b.Internal Dependency c.External Dependency d.Discretional Dependency Sample PMP® Exam Question HINT: This question references the Sequence Activities process.
  • 8. The correct answer is B The PMBOK Guide recognizes three types of dependencies; Mandatory, Discretionary and External. The PMBOK Guide doesn't recognize "Internal Dependencies" as a type of dependency. Did it confuse you that one of the answers used the term "Discretional Dependencies" instead of "Discretionary Dependencies"? Expect that even on the actual PMP exam you will come across questions where terminology does not exactly match the PMBOK Guide. Even considering that "Discretional Dependencies" is not the exact same term as “Discretionary Dependencies”, "Internal Dependencies" is even less correct and therefore the correct answer. Answer and Explanation
  • 9. According to the PMBOK Guide, a WBS is not directly involved in which of the following processes? a.Develop Project Management Plan b.Define Activities c.Create WBS d.Define Scope Sample PMP® Exam Question HINT: Develop Project Management Plan process creates the Scope Management Plan.
  • 10. The correct answer is D The Develop Project Management Plan process carries out scope planning, which documents how the WBS will be created and defined. Define Activities takes the WBS as an input and decomposes it to define activities. Create WBS creates the WBS itself. The Define Scope process must be completed before the Create WBS process can be started. Answer and Explanation
  • 11. Information in the WBS dictionary does not include? a.Contract Information b.Quality Requirements c.Responsible Organization d.Project Activities Sample PMP® Exam Question HINT: WBS dictionary contains a lot of items and explains each work package in great detail.
  • 12. The correct answer is D The WBS Dictionary contains a lot of items and explains each work package in great detail. This information includes Contract Information regarding the work packages, Quality Requirements, and the Responsible Organization. However, the WBS Dictionary does not included the specific project activities. Answer and Explanation