SlideShare une entreprise Scribd logo
1  sur  10
USE OF NETWORK SCHEDULING TECHNIQUE (CPM) TO
SET UP A TEAM AND TO FABRICATE A FSAE CAR BY THE
TEAM

A report submitted in partial fulfillment of the
requirements for the course

of

OPERATIONS RESEARCH
by
BOLISETTI SIVA PRADEEP
09BEM080

SCHOOL OF MECHANICAL AND BUILDING SCIENCES

Vellore – 632014, Tamil Nadu, India

www. vit.ac.in

APRIL 2012

0
CONTENTS

Chapter No.

CHAPTER

1

Title

INTRODUCTION

Page No.

3

1.1 Introduction to network scheduling
1.2 Introduction to the team, objectives and
whole content of the project

CHAPTER

2

LITERATURE REVIEW

4

CHAPTER

3

METHODOLOGY

6

3.1

Problem Statements

3.2

Solutions

4

RESULTS AND DISCUSSION

4.1

Results and its significance

CHAPTER

4.2
CHAPTER

9

Advantages - Applications
5

CONCLUSIONS

10

REFERENCES

10

1
1. INTRODUCTION
1.1 INTRODUCTION TO NETWORK SCHEDULING
The complexities of the present day management problems and the business competitions
have added to the pressure on the brains of decision makers. In a large and complex project
involving a number of interrelated activities, requiring a number of men, machines and materials,
it is not possible for the management to make and execute an optimum schedule just by intuition
based on the organizational capabilities and work experience. Management are thus always on
the lookout for some methods and techniques which may help in planning, scheduling and
controlling the project. The aim of planning is to develop a sequence of activities of the project,
so that project completion time and cost are properly balanced and that the excessive demand of
key resources is avoided. CPM is one of the many network techniques which have been widely
used for planning, scheduling and controlling the large and complex projects.
The network technique which emphasizes more on activities is called CPM. CPM does
not take into account the uncertainties while estimating its activity times. The main difference
between CPM and PERT is PERT emphasizes more on events while CPM on activities.The
estimates in PERT are probabilistic while the times in CPM are relatively less uncertain and are
thus of deterministic in nature.
1.2 INTRODUCTION TO THE TEAM, OBJECTIVES AND WHOLE CONTENT OF
THE PROJECT
In V.I.T university we have many teams which make a car of their discipline to compete
in their corresponding event, for example BAJA. Team Pravega is one among them. Team
Pravega is a team which designs a small formula type race car. Each student team designs, builds
and tests a prototype based on a series of rules. The success of any team depends on the
commitment of its docile members, planning, scheduling and controlling the activities
efficiently, on contrary if planning, scheduling and controlling of the activities is not done
efficiently the team is vulnerable to failure. Construction of a FSAE car is a complex project
which involves many activities. These activities have to be planned, scheduled and controlled
properly so that project completion time and cost are properly balanced. The aim of my project is
to find out all the activities involved in design and fabrication of FSAE car by Team Pravega and
to draw the network and to apply network scheduling techniques like CPM for planning,
scheduling and controlling of this project and to finally find out the critical activities and critical
path.

2
2. LITERATURE REVIEW
N.K.Kwak et al in the year 2002 studied on critical path method and CRTI, a computerized CPM
program, as a tool for reporting and developing management information system Microbiology
Department of Deaconess Hospital to synchronize and coordinate the various tasks for efficient
management.
Edward L. Hanna et al in the year 2002 demonstrated on how goal programming can be used to
incorporate considerations other than project completion time and total project cost into the
typical CPM problem.
Lawrence Jones et al in the year 2002 dealt with application of CPM scheduling for the National
center for Drug Analysis. The model was constructed based on empirical data obtained at the
center for a five year period. It assists the management of the center in developing a complex
work planning process and in controlling the project tasks.
J.F.Barlow et al in the year 2003 studied on plotting of activity on node by computer using
output obtained from critical path analysis program. Three types of connections was allowed
between activities which are shown as boxes.
Yu Cheng et al in the year 2004 studied on optimal train traffic rescheduling simulation by
knowledge based system combined with critical path method for getting a nearly optimum
rescheduling under time and resource constraints. Global information concerning final
completion times of trains is used as a feedback function to control the delay and resolve the
resource conflict concerning current processing trains.
Shin Pin Chen et al in the year 2006 proposed an approach to critical path analysis for a project
network with activity times being fuzzy numbers, in that the membership function of the fuzzy
total duration time is constructed. The basic idea was based on the extension principle and linear
programming formulation. The total duration time is completely expressed by a membership
function.
Tarun Gupta et al in the year 2006 proposed an idea of applying CPM to continuous production
systems, and to implement the CPM not just at the outset but throughout the process. The
algorithm calls for repeatedly calculating the critical path through the production process and
routing parts so as to remain off the path.
Glenn R Dundas et al in the year 2006 studied on application of CPM for introducing an
industrial product. The paper suggests use of critical path method to ensure success at the
announcement/ introduction phase of the new product development.
R.A.Web et al in the year 2007 studied on application of critical path analysis to strawberry fruit
production from runner propagation to first harvest in an experimental situation. The analysis
indicated three phases of development.
3
Yan Lie Chang et al in the year 2007 investigated on two types of time constraints commonly
encountered in project management. The first is the time window constraint and second is the
time schedule constraint. An efficient linear time algorithm for finding the critical path and for
analyzing the flow time of each arc was developed for activity networks with these time
constraints.

4
3.METHODOLOGY
3.1 PROBLEM STATMENTS
A list of all the activities involved and time taken for each activity has been found out by
interacting with the team members. A table showing list of all activities involved in fabricating a
FSAE car and the corresponding time take for each activity has been tabulated to draw the
network and to find out the critical activities and critical path by using CPM.

ACTIVITY
TASK INVOLVED
A
Setting up a productive team through rigorous selection
procedure involving written tests followed by interview
and presentation.
B
To get to know the first hand information about all the
departments in a car, for example suspension system etc.
C
Preparing a question paper for splitting the team into
corresponding departments.
D
Splitting the team into various departments based upon the
individual performance in the test and his field of interest.
E
Knowing the in-depth concepts by an individual
corresponding to his department and simultaneously
designing the components.
F
Selecting the event location.
G
Start of ordering the parts based on the calculations made
and receiving the parts.
H
Design of prototype by using software's.
I
Validating the final designs.
J
Fabricating the roll cage based on the designs made.
K
Machining the components which are to be custom made.
L
Assembly of all components.
M
Test run and troubleshooting.
Table 3.1 List of activities and their duration

5

No OF DAYS
7

10
3
5
40

7
60
25
5
30
50
20
10
3.2 SOLUTIONS
For the above list of activities the precedence relationship has been found out, a network
involving all the activities has been dawn and finally the total length of the project, critical
activities and critical path has been found out using CPM.
PRECEDENCE RELATIONSHIP
A < B, C
B, C < D
D < E, F
E, F < G, H
G, H < I
I < J, K
J, K < L
L<M
NETWORK

Fig 3.1 Network involving all the activities

6
REPRESENTATION IN TABULAR FORM
PREDESES
SOR
EVENT (i)

SUCCES
SOR
EVENT
(j)

ACTIVI
TY
DURATI
ON
tEij

1
2
2
3
4
5
5
6
7
7
8
9
10
10
11
12
13

2
3
4
4
5
6
7
7
8
9
9
10
11
12
12
13
14

7
3
10
0
5
7
40
0
60
25
0
5
30
50
0
20
10

EARLI
EST
START
TIME
Esi

EARLIES
T
COMPLE
TION
TIME
Ecij
0
7
7
10
7
17
10
10
17
22
22
29
22
62
29
29
62
122
62
87
122
122
122
127
127
150
127
177
157
157
177
197
197
207
Table 3.2

7

LATE
ST
STAR
T
TIME
Lsij
0
14
7
17
17
55
22
62
62
97
122
122
147
127
177
177
197

LATEST
COMPLE
TION
TIME
Lcj
7
17
17
17
22
62
62
62
122
122
122
127
177
177
177
197
207

FLO
AT

0
7
0
7
0
33
0
33
0
35
0
0
27
0
20
0
0
4.RESULTS AND DISCUSSIONS
4.1 RESULTS AND ITS SIGNIFICANCE
The total length of the project was found out to be two hundred and seven days.
The critical activities were 1-2, 2-4, 4-5, 5-7, 7-8, 8-9, 9-10, 10-12, 12-13, 13-14.
The critical path is 1-2-4-5-7-8-9-10-12-13-14.
By applying CPM the total length of the project was found out to be two hundred seven days but
according to the previous year's team database the length of the project was three hundred and
thirty days. This increased length of the project can be attributed to the delay of critical activities,
as we know that the delay of critical activities leads to the delay of the entire project. The delay
of critical activities can further be attributed to scheduling of the university exams during the
project and non availability of the team members due to some reasons like health problems etc.
An example of delay in critical activity may be delay in receiving the ordered parts.
4.2 ADVANTAGES - APPLICATION
Finding out the critical activities and critical path assists the team in developing a complex work
planning process and in controlling the project tasks.

8
5. CONCLUSIONS

Thus the total length of the project, critical activities and critical path has been found out
by applying CPM technique in network scheduling. It has been found that the previous year's
total length of the project is exceeding the calculated total length of the project which may be
due to the delay in critical activities.

REFERENCES
1. D.S.HIRA, PREM KUMAR GUPTA (2008) Operations Research, S.Chand
2. www.sciencedirect.com

9

Contenu connexe

Tendances

Comparative characteristics of pert and cpm
Comparative characteristics of pert and cpmComparative characteristics of pert and cpm
Comparative characteristics of pert and cpmKinshook Chaturvedi
 
Cpm network analysis and problems
Cpm network analysis and problemsCpm network analysis and problems
Cpm network analysis and problemsSHAHIDBASHIRMALIK
 
Finance management in construction site
Finance management in construction siteFinance management in construction site
Finance management in construction siteSHAHIDBASHIRMALIK
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTS.Vijaya Bhaskar
 
OR PERT CPM AND JOB SCHEDULING
OR PERT CPM AND JOB SCHEDULINGOR PERT CPM AND JOB SCHEDULING
OR PERT CPM AND JOB SCHEDULINGJignesh Kariya
 
IRJET- Achieving Total Quality Management in Construction Project using Six S...
IRJET- Achieving Total Quality Management in Construction Project using Six S...IRJET- Achieving Total Quality Management in Construction Project using Six S...
IRJET- Achieving Total Quality Management in Construction Project using Six S...IRJET Journal
 
IRJET- Application of Machine Learning in Predicting Key Performance Indicato...
IRJET- Application of Machine Learning in Predicting Key Performance Indicato...IRJET- Application of Machine Learning in Predicting Key Performance Indicato...
IRJET- Application of Machine Learning in Predicting Key Performance Indicato...IRJET Journal
 
Project management
Project managementProject management
Project managementShankaran Rd
 

Tendances (19)

Pert Analysis
Pert AnalysisPert Analysis
Pert Analysis
 
Comparative characteristics of pert and cpm
Comparative characteristics of pert and cpmComparative characteristics of pert and cpm
Comparative characteristics of pert and cpm
 
Project management cpm-pert
Project management   cpm-pertProject management   cpm-pert
Project management cpm-pert
 
Cpm network analysis and problems
Cpm network analysis and problemsCpm network analysis and problems
Cpm network analysis and problems
 
Finance management in construction site
Finance management in construction siteFinance management in construction site
Finance management in construction site
 
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERTProject Management: NETWORK ANALYSIS - CPM and PERT
Project Management: NETWORK ANALYSIS - CPM and PERT
 
OR PERT CPM AND JOB SCHEDULING
OR PERT CPM AND JOB SCHEDULINGOR PERT CPM AND JOB SCHEDULING
OR PERT CPM AND JOB SCHEDULING
 
cpmpertmy (1)
cpmpertmy (1)cpmpertmy (1)
cpmpertmy (1)
 
Cpm pert asgm. prashant
Cpm pert asgm. prashantCpm pert asgm. prashant
Cpm pert asgm. prashant
 
Cpm pert
Cpm pertCpm pert
Cpm pert
 
Pert & cpm
Pert & cpmPert & cpm
Pert & cpm
 
Time cost-trade-off
Time cost-trade-offTime cost-trade-off
Time cost-trade-off
 
IRJET- Achieving Total Quality Management in Construction Project using Six S...
IRJET- Achieving Total Quality Management in Construction Project using Six S...IRJET- Achieving Total Quality Management in Construction Project using Six S...
IRJET- Achieving Total Quality Management in Construction Project using Six S...
 
IRJET- Application of Machine Learning in Predicting Key Performance Indicato...
IRJET- Application of Machine Learning in Predicting Key Performance Indicato...IRJET- Application of Machine Learning in Predicting Key Performance Indicato...
IRJET- Application of Machine Learning in Predicting Key Performance Indicato...
 
Project management - CPM & PERT
Project management   - CPM & PERTProject management   - CPM & PERT
Project management - CPM & PERT
 
asdfds
asdfdsasdfds
asdfds
 
Project Management
Project Management Project Management
Project Management
 
Cpm and pert
Cpm and pertCpm and pert
Cpm and pert
 
Project management
Project managementProject management
Project management
 

Similaire à Use of network scheduling technique

IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...IRJET Journal
 
TOOLS OF EDUCATIONAL MANAGEMENT-8615
TOOLS OF EDUCATIONAL MANAGEMENT-8615TOOLS OF EDUCATIONAL MANAGEMENT-8615
TOOLS OF EDUCATIONAL MANAGEMENT-8615EqraBaig
 
Delay Analysis in EPC Projects using Ishikawa Diagram
Delay Analysis in EPC Projects using Ishikawa DiagramDelay Analysis in EPC Projects using Ishikawa Diagram
Delay Analysis in EPC Projects using Ishikawa DiagramIJAEMSJORNAL
 
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.pptTinotendaChivese
 
Scheduling coordination and control of projects
Scheduling coordination and control of projects Scheduling coordination and control of projects
Scheduling coordination and control of projects Somashekar S.M
 
A Study on Project Planning Using the Deterministic and Probabilistic Models ...
A Study on Project Planning Using the Deterministic and Probabilistic Models ...A Study on Project Planning Using the Deterministic and Probabilistic Models ...
A Study on Project Planning Using the Deterministic and Probabilistic Models ...IJERA Editor
 
Programme Evaluation and Review Technique
Programme Evaluation and Review TechniqueProgramme Evaluation and Review Technique
Programme Evaluation and Review TechniqueDrAsifMohammad
 
PERT Ghant chart and bench marking with application to nursing
PERT Ghant chart and bench marking with application to nursingPERT Ghant chart and bench marking with application to nursing
PERT Ghant chart and bench marking with application to nursingHariasha
 
The Automation of Critical Path Method using Machine Learning: A Conceptual S...
The Automation of Critical Path Method using Machine Learning: A Conceptual S...The Automation of Critical Path Method using Machine Learning: A Conceptual S...
The Automation of Critical Path Method using Machine Learning: A Conceptual S...Dr. Amarjeet Singh
 
IRJET- Comparative Analysis between Critical Path Method and Monte Carlo S...
IRJET- 	  Comparative Analysis between Critical Path Method and Monte Carlo S...IRJET- 	  Comparative Analysis between Critical Path Method and Monte Carlo S...
IRJET- Comparative Analysis between Critical Path Method and Monte Carlo S...IRJET Journal
 
Activity schedule and affective control of component based project
Activity schedule and affective control of component based projectActivity schedule and affective control of component based project
Activity schedule and affective control of component based projecteSAT Journals
 
AN ARTIFICIAL NEURAL NETWORK-BASED APPROACH COUPLED WITH TAGUCHI'S METHOD FOR...
AN ARTIFICIAL NEURAL NETWORK-BASED APPROACH COUPLED WITH TAGUCHI'S METHOD FOR...AN ARTIFICIAL NEURAL NETWORK-BASED APPROACH COUPLED WITH TAGUCHI'S METHOD FOR...
AN ARTIFICIAL NEURAL NETWORK-BASED APPROACH COUPLED WITH TAGUCHI'S METHOD FOR...IAEME Publication
 
Planning and Optimization of Resource Constrained Project Scheduling by using...
Planning and Optimization of Resource Constrained Project Scheduling by using...Planning and Optimization of Resource Constrained Project Scheduling by using...
Planning and Optimization of Resource Constrained Project Scheduling by using...IRJET Journal
 

Similaire à Use of network scheduling technique (20)

IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
 
TOOLS OF EDUCATIONAL MANAGEMENT-8615
TOOLS OF EDUCATIONAL MANAGEMENT-8615TOOLS OF EDUCATIONAL MANAGEMENT-8615
TOOLS OF EDUCATIONAL MANAGEMENT-8615
 
Delay Analysis in EPC Projects using Ishikawa Diagram
Delay Analysis in EPC Projects using Ishikawa DiagramDelay Analysis in EPC Projects using Ishikawa Diagram
Delay Analysis in EPC Projects using Ishikawa Diagram
 
Ijciet 10 01_075
Ijciet 10 01_075Ijciet 10 01_075
Ijciet 10 01_075
 
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
 
Scheduling coordination and control of projects
Scheduling coordination and control of projects Scheduling coordination and control of projects
Scheduling coordination and control of projects
 
A Study on Project Planning Using the Deterministic and Probabilistic Models ...
A Study on Project Planning Using the Deterministic and Probabilistic Models ...A Study on Project Planning Using the Deterministic and Probabilistic Models ...
A Study on Project Planning Using the Deterministic and Probabilistic Models ...
 
Programme Evaluation and Review Technique
Programme Evaluation and Review TechniqueProgramme Evaluation and Review Technique
Programme Evaluation and Review Technique
 
Ijmet 09 11_006
Ijmet 09 11_006Ijmet 09 11_006
Ijmet 09 11_006
 
Pert & Cpm
Pert & CpmPert & Cpm
Pert & Cpm
 
Pm chapter 5...
Pm chapter 5...Pm chapter 5...
Pm chapter 5...
 
B1303020508
B1303020508B1303020508
B1303020508
 
PERT Ghant chart and bench marking with application to nursing
PERT Ghant chart and bench marking with application to nursingPERT Ghant chart and bench marking with application to nursing
PERT Ghant chart and bench marking with application to nursing
 
The Automation of Critical Path Method using Machine Learning: A Conceptual S...
The Automation of Critical Path Method using Machine Learning: A Conceptual S...The Automation of Critical Path Method using Machine Learning: A Conceptual S...
The Automation of Critical Path Method using Machine Learning: A Conceptual S...
 
IRJET- Comparative Analysis between Critical Path Method and Monte Carlo S...
IRJET- 	  Comparative Analysis between Critical Path Method and Monte Carlo S...IRJET- 	  Comparative Analysis between Critical Path Method and Monte Carlo S...
IRJET- Comparative Analysis between Critical Path Method and Monte Carlo S...
 
Activity schedule and affective control of component based project
Activity schedule and affective control of component based projectActivity schedule and affective control of component based project
Activity schedule and affective control of component based project
 
AN ARTIFICIAL NEURAL NETWORK-BASED APPROACH COUPLED WITH TAGUCHI'S METHOD FOR...
AN ARTIFICIAL NEURAL NETWORK-BASED APPROACH COUPLED WITH TAGUCHI'S METHOD FOR...AN ARTIFICIAL NEURAL NETWORK-BASED APPROACH COUPLED WITH TAGUCHI'S METHOD FOR...
AN ARTIFICIAL NEURAL NETWORK-BASED APPROACH COUPLED WITH TAGUCHI'S METHOD FOR...
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
 
Planning and Optimization of Resource Constrained Project Scheduling by using...
Planning and Optimization of Resource Constrained Project Scheduling by using...Planning and Optimization of Resource Constrained Project Scheduling by using...
Planning and Optimization of Resource Constrained Project Scheduling by using...
 

Plus de Siva Pradeep Bolisetti

Plus de Siva Pradeep Bolisetti (13)

SAP Security interview questions
SAP Security interview questionsSAP Security interview questions
SAP Security interview questions
 
Cua setup procedure SAP security
Cua setup procedure SAP securityCua setup procedure SAP security
Cua setup procedure SAP security
 
SAP BI 7 security concepts
SAP BI 7 security conceptsSAP BI 7 security concepts
SAP BI 7 security concepts
 
Step by step exercise for bw 365
Step by step exercise for bw 365Step by step exercise for bw 365
Step by step exercise for bw 365
 
Solar refrigeration system
Solar refrigeration system Solar refrigeration system
Solar refrigeration system
 
Welding and types
Welding and types Welding and types
Welding and types
 
Calculation of optimum cost of transportation of goods from godowns to differ...
Calculation of optimum cost of transportation of goods from godowns to differ...Calculation of optimum cost of transportation of goods from godowns to differ...
Calculation of optimum cost of transportation of goods from godowns to differ...
 
Practical guide for sap security
Practical guide for sap security Practical guide for sap security
Practical guide for sap security
 
Sap security tasks
Sap security tasksSap security tasks
Sap security tasks
 
Sappress sap governance risk and compliance
Sappress sap governance risk and complianceSappress sap governance risk and compliance
Sappress sap governance risk and compliance
 
How to improve user experience via roles
How to improve user experience via rolesHow to improve user experience via roles
How to improve user experience via roles
 
Bluetooth Technology -- detailed explanation
Bluetooth Technology -- detailed explanation Bluetooth Technology -- detailed explanation
Bluetooth Technology -- detailed explanation
 
Bearing design for Turbo Generator- Internship at BHEL
Bearing design for Turbo Generator- Internship at BHELBearing design for Turbo Generator- Internship at BHEL
Bearing design for Turbo Generator- Internship at BHEL
 

Dernier

Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Mark Reed
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Celine George
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17Celine George
 
Keynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designKeynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designMIPLM
 
Choosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for ParentsChoosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for Parentsnavabharathschool99
 
Gas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptxGas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptxDr.Ibrahim Hassaan
 
Q4 English4 Week3 PPT Melcnmg-based.pptx
Q4 English4 Week3 PPT Melcnmg-based.pptxQ4 English4 Week3 PPT Melcnmg-based.pptx
Q4 English4 Week3 PPT Melcnmg-based.pptxnelietumpap1
 
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSGRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSJoshuaGantuangco2
 
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxMULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxAnupkumar Sharma
 
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxINTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxHumphrey A Beña
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxthorishapillay1
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTiammrhaywood
 
ENGLISH6-Q4-W3.pptxqurter our high choom
ENGLISH6-Q4-W3.pptxqurter our high choomENGLISH6-Q4-W3.pptxqurter our high choom
ENGLISH6-Q4-W3.pptxqurter our high choomnelietumpap1
 
ACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdfACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdfSpandanaRallapalli
 
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITYISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITYKayeClaireEstoconing
 

Dernier (20)

FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptxFINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
 
Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
OS-operating systems- ch04 (Threads) ...
OS-operating systems- ch04 (Threads) ...OS-operating systems- ch04 (Threads) ...
OS-operating systems- ch04 (Threads) ...
 
How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17How to Add Barcode on PDF Report in Odoo 17
How to Add Barcode on PDF Report in Odoo 17
 
Keynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designKeynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-design
 
Choosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for ParentsChoosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for Parents
 
YOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptx
YOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptxYOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptx
YOUVE_GOT_EMAIL_PRELIMS_EL_DORADO_2024.pptx
 
Gas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptxGas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptx
 
Q4 English4 Week3 PPT Melcnmg-based.pptx
Q4 English4 Week3 PPT Melcnmg-based.pptxQ4 English4 Week3 PPT Melcnmg-based.pptx
Q4 English4 Week3 PPT Melcnmg-based.pptx
 
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTSGRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
GRADE 4 - SUMMATIVE TEST QUARTER 4 ALL SUBJECTS
 
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxMULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
 
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxINTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
 
Raw materials used in Herbal Cosmetics.pptx
Raw materials used in Herbal Cosmetics.pptxRaw materials used in Herbal Cosmetics.pptx
Raw materials used in Herbal Cosmetics.pptx
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptx
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
 
ENGLISH6-Q4-W3.pptxqurter our high choom
ENGLISH6-Q4-W3.pptxqurter our high choomENGLISH6-Q4-W3.pptxqurter our high choom
ENGLISH6-Q4-W3.pptxqurter our high choom
 
ACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdfACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdf
 
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITYISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
ISYU TUNGKOL SA SEKSWLADIDA (ISSUE ABOUT SEXUALITY
 

Use of network scheduling technique

  • 1. USE OF NETWORK SCHEDULING TECHNIQUE (CPM) TO SET UP A TEAM AND TO FABRICATE A FSAE CAR BY THE TEAM A report submitted in partial fulfillment of the requirements for the course of OPERATIONS RESEARCH by BOLISETTI SIVA PRADEEP 09BEM080 SCHOOL OF MECHANICAL AND BUILDING SCIENCES Vellore – 632014, Tamil Nadu, India www. vit.ac.in APRIL 2012 0
  • 2. CONTENTS Chapter No. CHAPTER 1 Title INTRODUCTION Page No. 3 1.1 Introduction to network scheduling 1.2 Introduction to the team, objectives and whole content of the project CHAPTER 2 LITERATURE REVIEW 4 CHAPTER 3 METHODOLOGY 6 3.1 Problem Statements 3.2 Solutions 4 RESULTS AND DISCUSSION 4.1 Results and its significance CHAPTER 4.2 CHAPTER 9 Advantages - Applications 5 CONCLUSIONS 10 REFERENCES 10 1
  • 3. 1. INTRODUCTION 1.1 INTRODUCTION TO NETWORK SCHEDULING The complexities of the present day management problems and the business competitions have added to the pressure on the brains of decision makers. In a large and complex project involving a number of interrelated activities, requiring a number of men, machines and materials, it is not possible for the management to make and execute an optimum schedule just by intuition based on the organizational capabilities and work experience. Management are thus always on the lookout for some methods and techniques which may help in planning, scheduling and controlling the project. The aim of planning is to develop a sequence of activities of the project, so that project completion time and cost are properly balanced and that the excessive demand of key resources is avoided. CPM is one of the many network techniques which have been widely used for planning, scheduling and controlling the large and complex projects. The network technique which emphasizes more on activities is called CPM. CPM does not take into account the uncertainties while estimating its activity times. The main difference between CPM and PERT is PERT emphasizes more on events while CPM on activities.The estimates in PERT are probabilistic while the times in CPM are relatively less uncertain and are thus of deterministic in nature. 1.2 INTRODUCTION TO THE TEAM, OBJECTIVES AND WHOLE CONTENT OF THE PROJECT In V.I.T university we have many teams which make a car of their discipline to compete in their corresponding event, for example BAJA. Team Pravega is one among them. Team Pravega is a team which designs a small formula type race car. Each student team designs, builds and tests a prototype based on a series of rules. The success of any team depends on the commitment of its docile members, planning, scheduling and controlling the activities efficiently, on contrary if planning, scheduling and controlling of the activities is not done efficiently the team is vulnerable to failure. Construction of a FSAE car is a complex project which involves many activities. These activities have to be planned, scheduled and controlled properly so that project completion time and cost are properly balanced. The aim of my project is to find out all the activities involved in design and fabrication of FSAE car by Team Pravega and to draw the network and to apply network scheduling techniques like CPM for planning, scheduling and controlling of this project and to finally find out the critical activities and critical path. 2
  • 4. 2. LITERATURE REVIEW N.K.Kwak et al in the year 2002 studied on critical path method and CRTI, a computerized CPM program, as a tool for reporting and developing management information system Microbiology Department of Deaconess Hospital to synchronize and coordinate the various tasks for efficient management. Edward L. Hanna et al in the year 2002 demonstrated on how goal programming can be used to incorporate considerations other than project completion time and total project cost into the typical CPM problem. Lawrence Jones et al in the year 2002 dealt with application of CPM scheduling for the National center for Drug Analysis. The model was constructed based on empirical data obtained at the center for a five year period. It assists the management of the center in developing a complex work planning process and in controlling the project tasks. J.F.Barlow et al in the year 2003 studied on plotting of activity on node by computer using output obtained from critical path analysis program. Three types of connections was allowed between activities which are shown as boxes. Yu Cheng et al in the year 2004 studied on optimal train traffic rescheduling simulation by knowledge based system combined with critical path method for getting a nearly optimum rescheduling under time and resource constraints. Global information concerning final completion times of trains is used as a feedback function to control the delay and resolve the resource conflict concerning current processing trains. Shin Pin Chen et al in the year 2006 proposed an approach to critical path analysis for a project network with activity times being fuzzy numbers, in that the membership function of the fuzzy total duration time is constructed. The basic idea was based on the extension principle and linear programming formulation. The total duration time is completely expressed by a membership function. Tarun Gupta et al in the year 2006 proposed an idea of applying CPM to continuous production systems, and to implement the CPM not just at the outset but throughout the process. The algorithm calls for repeatedly calculating the critical path through the production process and routing parts so as to remain off the path. Glenn R Dundas et al in the year 2006 studied on application of CPM for introducing an industrial product. The paper suggests use of critical path method to ensure success at the announcement/ introduction phase of the new product development. R.A.Web et al in the year 2007 studied on application of critical path analysis to strawberry fruit production from runner propagation to first harvest in an experimental situation. The analysis indicated three phases of development. 3
  • 5. Yan Lie Chang et al in the year 2007 investigated on two types of time constraints commonly encountered in project management. The first is the time window constraint and second is the time schedule constraint. An efficient linear time algorithm for finding the critical path and for analyzing the flow time of each arc was developed for activity networks with these time constraints. 4
  • 6. 3.METHODOLOGY 3.1 PROBLEM STATMENTS A list of all the activities involved and time taken for each activity has been found out by interacting with the team members. A table showing list of all activities involved in fabricating a FSAE car and the corresponding time take for each activity has been tabulated to draw the network and to find out the critical activities and critical path by using CPM. ACTIVITY TASK INVOLVED A Setting up a productive team through rigorous selection procedure involving written tests followed by interview and presentation. B To get to know the first hand information about all the departments in a car, for example suspension system etc. C Preparing a question paper for splitting the team into corresponding departments. D Splitting the team into various departments based upon the individual performance in the test and his field of interest. E Knowing the in-depth concepts by an individual corresponding to his department and simultaneously designing the components. F Selecting the event location. G Start of ordering the parts based on the calculations made and receiving the parts. H Design of prototype by using software's. I Validating the final designs. J Fabricating the roll cage based on the designs made. K Machining the components which are to be custom made. L Assembly of all components. M Test run and troubleshooting. Table 3.1 List of activities and their duration 5 No OF DAYS 7 10 3 5 40 7 60 25 5 30 50 20 10
  • 7. 3.2 SOLUTIONS For the above list of activities the precedence relationship has been found out, a network involving all the activities has been dawn and finally the total length of the project, critical activities and critical path has been found out using CPM. PRECEDENCE RELATIONSHIP A < B, C B, C < D D < E, F E, F < G, H G, H < I I < J, K J, K < L L<M NETWORK Fig 3.1 Network involving all the activities 6
  • 8. REPRESENTATION IN TABULAR FORM PREDESES SOR EVENT (i) SUCCES SOR EVENT (j) ACTIVI TY DURATI ON tEij 1 2 2 3 4 5 5 6 7 7 8 9 10 10 11 12 13 2 3 4 4 5 6 7 7 8 9 9 10 11 12 12 13 14 7 3 10 0 5 7 40 0 60 25 0 5 30 50 0 20 10 EARLI EST START TIME Esi EARLIES T COMPLE TION TIME Ecij 0 7 7 10 7 17 10 10 17 22 22 29 22 62 29 29 62 122 62 87 122 122 122 127 127 150 127 177 157 157 177 197 197 207 Table 3.2 7 LATE ST STAR T TIME Lsij 0 14 7 17 17 55 22 62 62 97 122 122 147 127 177 177 197 LATEST COMPLE TION TIME Lcj 7 17 17 17 22 62 62 62 122 122 122 127 177 177 177 197 207 FLO AT 0 7 0 7 0 33 0 33 0 35 0 0 27 0 20 0 0
  • 9. 4.RESULTS AND DISCUSSIONS 4.1 RESULTS AND ITS SIGNIFICANCE The total length of the project was found out to be two hundred and seven days. The critical activities were 1-2, 2-4, 4-5, 5-7, 7-8, 8-9, 9-10, 10-12, 12-13, 13-14. The critical path is 1-2-4-5-7-8-9-10-12-13-14. By applying CPM the total length of the project was found out to be two hundred seven days but according to the previous year's team database the length of the project was three hundred and thirty days. This increased length of the project can be attributed to the delay of critical activities, as we know that the delay of critical activities leads to the delay of the entire project. The delay of critical activities can further be attributed to scheduling of the university exams during the project and non availability of the team members due to some reasons like health problems etc. An example of delay in critical activity may be delay in receiving the ordered parts. 4.2 ADVANTAGES - APPLICATION Finding out the critical activities and critical path assists the team in developing a complex work planning process and in controlling the project tasks. 8
  • 10. 5. CONCLUSIONS Thus the total length of the project, critical activities and critical path has been found out by applying CPM technique in network scheduling. It has been found that the previous year's total length of the project is exceeding the calculated total length of the project which may be due to the delay in critical activities. REFERENCES 1. D.S.HIRA, PREM KUMAR GUPTA (2008) Operations Research, S.Chand 2. www.sciencedirect.com 9