PROGRAM GOVERNANCE STRUCTURE 
SETUP & MANAGEMENT 
By Saurabh Sardesai 
www.starvaluemodel.com 
June 2014
Objectives 
 Establish a Program/Project governance structure within the 
organization and ensure stakeholder participation 
 Define the program roles, decision making hierarchy, 
program execution strategies and best practices 
 Describe the protocol for proper flow of relevant information 
to all stakeholders 
 Establish a project/program review, issue management & 
change mgmt mechanism 
 Mechanism to identify program compliance and 
communications to all stakeholders 
 Evaluate various models of program governance and 
investigate their suitability for adaption 
 Translate business strategy into actual program execution via 
a proper governance framework
Governance defined 
 Governance, for a program or a project, is a 
combination of individuals filling executive and 
management roles, program oversight functions 
organized into structures, and policies that define 
management principles and decision making. 
 This combination is focused upon providing direction 
and oversight, which guide the achievement of the 
needed business outcome from the execution of the 
program effort, and providing data and feedback, 
which measure the ongoing contribution by the 
program to needed results within the overall 
business strategy and direction.
Need/Background 
 The organization was facing a huge problem of 
managing diverse projects across geographies without 
having a formal program structure in place 
 Senior management was finding it increasingly difficult 
to have an oversight on project execution in absence of 
proper governance structure and formal feedback 
channels 
 There was a clear disconnect between project execution 
and business mission or strategy 
 There was no overarching body like a Steering 
committee to provide oversight to projects 
 A need was felt to aggregate all multiple projects data in 
a central place and use the information to better 
manage the defined outcomes
Stakeholders 
 Board of Directors and C level executives 
 Project sponsors and funding partners 
 Internal and external clients of the organization 
 Business units within the organization 
 Vendor partners of the organization 
 Project managers and delivery managers/heads 
 Development teams, architects and testers 
 Support staff, line managers and consultants 
 Product control and management teams 
 Other relevant project stakeholders
Plan of action 
 Initiate consultations with relevant stakeholders to get 
their opinion & feedback 
 Establish a Program Steering Committee as the 
overarching body for program/project execution 
 Establish a Program Management Office (PMO) 
 Establish a Program Organization model and Project 
Organization model 
 Define and set up roles for Program Director, Program 
Managers, PMO managers and PMO support staff 
 Implement mechanisms to provide guidance and direction 
regarding policies, governance principles, and decision or 
authority specifications. 
 Establish a communications network and protocol for 
effective program and project communication to internal 
and external stakeholders of the organization
Steering committee models 
 Consensus Model: Executive-level sponsors who must reach 
consensus on issues, changes, and adjustments in order to proceed 
 Consultative Model: Executives and senior managers who are 
stakeholders for some aspect of the defined outcomes. Their role is 
to understand issues and needed changes, provide advice and 
assessment of potential impact, and make needed adjustments 
within their own responsibility area 
 Advisory Model: Representatives for the major business segments 
who are responsible for outcomes, or portions of outcomes, within 
the business strategy and direction. Their role is to monitor program 
progress, understand issues raised and adjustments made, assess 
potential impact within their own business segments, and carry back 
information about committee decisions to their respective business 
segments 
 For our initiative we recommend the Advisory model as the 
organization is large and has many interdependent businesses that 
routinely interact with each other
Recommended model – Program 
Management Office (PMO) 
 The Program Management Office (PMO) 
provides support along administrative, financial, 
process, and staff dimensions associated with 
successful program execution. 
 The PMO also provides review and tracking of 
financial expenditures, generation of required 
reports and financial documents, and ensures 
compliance with policies and practices. 
 The PMO provides & administers policies, 
procedures, & practices that provide an 
operational framework for program members
Sample Program model
Sample PMO structure
Sample Project structure 
within a PMO
Benefits of recommended model 
 Increases the long term potential of the program 
and individual projects 
 Continuous linkage to enterprise business 
strategy and direction 
 Clear and well-understood decision-making 
authority 
 Effective oversight of & insight into program 
progress and direction 
 Executive control over program evolution and 
outcomes 
 Central storage and management of all project 
data
Measuring Program success 
 Delivering the program to the client on time and 
within the dates specified in the agreement, taking 
into account any amendments or approved change 
requests 
 Achieving the financial objectives set forth in the 
business case, taking into account any amendments 
or change controls 
 Meeting all expectations related to quality and 
fulfilment of program requirements 
 Adhering to an established program methodology 
measured by a joint governance board 
 Achieving overall client satisfaction and repeat 
business
PMO – Tools of engagement 
 Overview and statement of purpose 
 Communication plan 
 Integrated program schedule 
 Program quality plan 
 Program risk management plan 
 Program issue management plan 
 Program change management 
 Program monitoring and control 
management
Elements of good program 
governance 
 A compelling business case, stating the objects of the 
project and specifying the in-scope and out-of-scope 
aspects 
 A mechanism to assess the compliance of the completed 
project to its original objectives 
 Identifying all stakeholders with an interest in the project 
 A defined method of communication to each stakeholder 
 A set of business-level requirements as agreed by all 
stakeholders 
 An agreed specification for the project deliverables 
 The appointment of a project manager 
 Clear assignment of project roles and responsibilities
Elements of good program 
governance….contd. 
 A current, published project plan that spans all project 
stages from project initiation through development to the 
transition to operations. 
 A system of accurate upward status- and progress-reporting 
including time records. 
 A central document repository for the project 
 A centrally-held glossary of project terms 
 A process for the management and resolution of issues that 
arise during the project 
 A process for the recording and communication 
of risks identified during the project 
 A standard for quality review of the key governance 
documents and of the project deliverables
Program Communications Plan 
 Sets up approved methods of communication 
 Establishes standard communication procedure 
 Frequency and type of updates provided to the 
program/project stakeholders 
 Provides consistency in information flow 
 Removes misinterpretations and doubts 
 What information to be sent to whom & when 
 Ensures Executive program engagement 
 Helps keep everyone on the same page
Communication Plan elements 
 Documented communication paths for information sharing, 
including tools (VOIP, email, video/Web conferencing, etc.) 
will be used throughout the program & for projects 
 Program and project contact lists based 
 Roles and responsibilities matrix for all stakeholders 
 A program organization chart to identify high-level 
organization, reporting, escalation and accountability for the 
program. 
 Approval and escalation procedures for decision making 
 Recurring Communication Matrix to ensure timely and 
effective communication 
 Program event management plan that ensures the right 
event occurrence reporting about issues, risks, milestones etc
Integrated Program Schedule 
 Key program tasks 
 Key program and/or project milestones 
 Duration of the program and projects in it 
 Dependencies related to the program 
 Assigned responsibilities within the program 
 Key deliverables of the program & schedule 
 Program tracking and control mechanism 
 Actual v/s Expected program metrics 
 Measurement and analysis of any deviations
Program Quality Plan 
 The quality plan defines the expectations of 
quality that will be delivered by the program. 
 The plan addresses the overall approach that will 
be adopted by the program and associated 
projects to ensure that quality is delivered 
according to stakeholder expectations. 
 The quality plan also defines quantitative 
measures that are used to validate quality prior 
to moving through a quality gate and eventually 
prior to implementation.
Program Risk Management Plan 
 The risk management plan is used to define the tolerance 
for risk throughout the program life cycle as well as the 
methods for identifying, recording and addressing risk 
throughout the program. 
 The early and frequent identification of risk in a program is 
essential to meeting cost, schedule and quality 
expectations. 
 Steering committee and program manager to meet on a 
monthly basis, or as defined in the communication plan, to 
review the identified risks, examine each associated action 
plan and define updates that need to be initiated. 
 Additionally, the team communicates any newly identified 
risks that may impact the program as they surface.
Sample program risk 
distribution chart 
14% 
20% 
6% 
33% 
2% 
12% 
13% 
Dependencies 
Requirements 
Knowledge 
Availability 
Commitment 
Project size 
Complexity
Program Mgr v/s Project Mgr 
Program manager Project manager 
Integrates efforts, continuously assesses and refines approaches 
and plans, ensures good communication. 
Plans, organizes, directs, and 
controls the project effort. 
Directs managers to achieve defined outcomes aligned with 
business strategy. 
Manages for on-time delivery of 
specific products. 
Acts as the implementation arm of the program sponsor(s) and / 
or steering committee. 
Manages work within the project 
plan framework. 
Manages managers. Manages technical staff. 
As Table above shows, the program manager and project manager roles 
are quite different from one another. Whereas project managers 
typically focus on delivering a specific component, program managers 
typically focus on one or more outcomes that are business strategy 
components.
Links to Business Strategy 
 Throughout program planning and execution, 
managers must ensure that the program sustains a 
connection to the business strategy. 
 This strategy is dynamic, not static. Both internal 
and external events affect the enterprise's initiatives, 
 So programs need mechanisms that will maintain a 
link between the initiative and the business strategy, 
and provide for effective data exchange and 
necessary adjustments. 
 We can divide such mechanisms into two categories: 
those active during program mobilization and 
planning, and those active during execution.
Program Mobilization – 
Strategic Review 
 IT goals and strategy 
 Program capital and expenses budget 
 Program benefits definition 
 Program outline 
 Candidate projects identification 
 Program mobilization plan 
 Consulting and staffing agreements 
 A business strategy review 
 Program planning strategy
Program execution reviews 
 As the program proceeds, the program plan and 
schedule should provide for periodic strategy 
reviews by the program sponsor(s) and / or 
steering committee. 
 The schedule for these reviews can be aligned 
with the program's phase structure, which cuts 
across all of the constituent projects. 
 As a phase-end approaches, reviewers can 
compare the program's current state and results 
against the then-current business strategy, and 
propose needed adjustments.
Decisions and Authority 
 An important aspect of program governance 
is assigning specific decision-making 
authority to each executive and management 
role. 
 Program managers can hold special group 
work sessions for this purpose and then 
create and distribute a matrix for major 
decision areas and roles. 
 Decision hierarchy structure should be clearly 
communicated to all program stakeholders
Sample authority matrix
Program Issue Management 
Plan 
 Throughout any program, risks are bound to become 
issues needing resolution in accordance with the 
strategy defined in the risk management plan. 
 In the likely scenario that an issue arises that has not 
yet been identified as a risk, the issue management 
plan provides strategies and guiding principles for 
resolving the issue. 
 Recognizing that this theoretical situation is not the 
typical situation in the execution of programs and 
projects, the same escalation principles identified 
through the program organization chart apply in the 
escalation of issues.
Program Change Management 
 Whether due to missed requirements, project 
issues or increased scope, a program is bound to 
encounter change during the life cycle. 
 The program change management plan defines 
the authority that the program has to approve 
change from an associated project, how said 
project requests change the agreed-to plan 
 How the program should receive approval on 
change requests that are beyond its authority is 
also defined in this plan
Program monitoring & control 
 Event log (includes identified risks, issues, 
changes, decisions and action items) 
 Project performance information such as key 
metrics on realized rate, resource utilization, 
ROI, duration, deliverables etc 
 Weekly status reports to stakeholders 
 Recommendations for intervention and 
corrective actions from senior management 
 Lessons learnt activities from closed initiatives 
 Managing change control requests 
 Effectively manage deviations from baseline
Conclusion 
 Establishing a governance framework is a 
significant activity requiring participation 
from all the relevant stakeholders 
 The key to a program’s success is optimal 
utilization of the governance framework, 
policies and best practices 
 Continuous feedback and communication are 
the essential ingredients of a Program 
 Program Management is a ‘people’ thing’ and 
must be projected that way
Thank you

Contenu connexe

Tendances

Project, Program & Portfolio Management
Project, Program & Portfolio ManagementProject, Program & Portfolio Management
Project, Program & Portfolio ManagementAnand Subramaniam
 
Program management - Fundamentals
Program management   - FundamentalsProgram management   - Fundamentals
Program management - FundamentalsJulen Mohanty
 
Project Management
Project ManagementProject Management
Project Managementajithsrc
 
Introduction to Project Portfolio Management (PPM)
Introduction to Project Portfolio Management (PPM)Introduction to Project Portfolio Management (PPM)
Introduction to Project Portfolio Management (PPM)Kimmy Chen
 
Project management fundamentals
Project management fundamentalsProject management fundamentals
Project management fundamentalsshantdey
 
PgMP Course Training Material Slides PowerPoint Presentation
PgMP Course Training Material Slides PowerPoint PresentationPgMP Course Training Material Slides PowerPoint Presentation
PgMP Course Training Material Slides PowerPoint PresentationOsama Zarzour
 
PMO View Interactive Dashboard
PMO View Interactive DashboardPMO View Interactive Dashboard
PMO View Interactive DashboardMatt Angerer
 
PMO (Project Management Office)
PMO (Project Management Office)PMO (Project Management Office)
PMO (Project Management Office)Dilawar Abbas
 
Smart project management - Best Practices to Manage Project effectively
Smart project management - Best Practices to Manage Project effectivelySmart project management - Best Practices to Manage Project effectively
Smart project management - Best Practices to Manage Project effectivelyChetan Khanzode
 
Project Management vs. Program Management: Strategies for Transition Success
Project Management vs. Program Management: Strategies for Transition SuccessProject Management vs. Program Management: Strategies for Transition Success
Project Management vs. Program Management: Strategies for Transition SuccessRuffin Veal and Associates, Inc.
 
Establishing an Effective PMO
Establishing an Effective PMOEstablishing an Effective PMO
Establishing an Effective PMOBusiness Beam
 

Tendances (20)

Project, Program & Portfolio Management
Project, Program & Portfolio ManagementProject, Program & Portfolio Management
Project, Program & Portfolio Management
 
Program management - Fundamentals
Program management   - FundamentalsProgram management   - Fundamentals
Program management - Fundamentals
 
Project Management Concepts
Project Management ConceptsProject Management Concepts
Project Management Concepts
 
PMO Mandate
PMO MandatePMO Mandate
PMO Mandate
 
Program Management Deployment Concept Consulting
Program Management Deployment Concept ConsultingProgram Management Deployment Concept Consulting
Program Management Deployment Concept Consulting
 
Project Management
Project ManagementProject Management
Project Management
 
Introduction to Project Portfolio Management (PPM)
Introduction to Project Portfolio Management (PPM)Introduction to Project Portfolio Management (PPM)
Introduction to Project Portfolio Management (PPM)
 
PMP PMBOK 6th
PMP PMBOK 6thPMP PMBOK 6th
PMP PMBOK 6th
 
Project management fundamentals
Project management fundamentalsProject management fundamentals
Project management fundamentals
 
Creating a colaborative program governance
Creating a colaborative program governanceCreating a colaborative program governance
Creating a colaborative program governance
 
Project Management
Project ManagementProject Management
Project Management
 
Program Management
Program ManagementProgram Management
Program Management
 
PgMP Course Training Material Slides PowerPoint Presentation
PgMP Course Training Material Slides PowerPoint PresentationPgMP Course Training Material Slides PowerPoint Presentation
PgMP Course Training Material Slides PowerPoint Presentation
 
PMO View Interactive Dashboard
PMO View Interactive DashboardPMO View Interactive Dashboard
PMO View Interactive Dashboard
 
PMO (Project Management Office)
PMO (Project Management Office)PMO (Project Management Office)
PMO (Project Management Office)
 
PgMP - Introduction to Program Management
PgMP -  Introduction to Program ManagementPgMP -  Introduction to Program Management
PgMP - Introduction to Program Management
 
Smart project management - Best Practices to Manage Project effectively
Smart project management - Best Practices to Manage Project effectivelySmart project management - Best Practices to Manage Project effectively
Smart project management - Best Practices to Manage Project effectively
 
Project Management vs. Program Management: Strategies for Transition Success
Project Management vs. Program Management: Strategies for Transition SuccessProject Management vs. Program Management: Strategies for Transition Success
Project Management vs. Program Management: Strategies for Transition Success
 
Project Management Framework
Project Management FrameworkProject Management Framework
Project Management Framework
 
Establishing an Effective PMO
Establishing an Effective PMOEstablishing an Effective PMO
Establishing an Effective PMO
 

En vedette

Enterprise Agile Transformation Case Study
Enterprise Agile Transformation Case StudyEnterprise Agile Transformation Case Study
Enterprise Agile Transformation Case Studysystred
 
Saurabh Reengineering Your Business
Saurabh   Reengineering Your BusinessSaurabh   Reengineering Your Business
Saurabh Reengineering Your BusinessSaurabh Sardesai
 
Value in entireness saurabh sardesai
Value in entireness saurabh sardesaiValue in entireness saurabh sardesai
Value in entireness saurabh sardesaiSaurabh Sardesai
 
Decision Making in an Organization
Decision Making in an OrganizationDecision Making in an Organization
Decision Making in an Organizationed gbargaye
 
Saurabh Harmony Business Analysis
Saurabh Harmony Business AnalysisSaurabh Harmony Business Analysis
Saurabh Harmony Business AnalysisSaurabh Sardesai
 
IT Project Governance Overview
IT Project Governance OverviewIT Project Governance Overview
IT Project Governance OverviewSteve Gerick
 
Principles of program governance
Principles of program governancePrinciples of program governance
Principles of program governanceGlen Alleman
 
Effective GOVERNANCE in Project Portfolio Management
Effective GOVERNANCE in Project Portfolio ManagementEffective GOVERNANCE in Project Portfolio Management
Effective GOVERNANCE in Project Portfolio ManagementMichal Augustini
 
Difference between management & administration
Difference between management & administrationDifference between management & administration
Difference between management & administrationProf. Chhaya Sachin Patel
 
Administration Vs. Management
Administration Vs. ManagementAdministration Vs. Management
Administration Vs. ManagementIrene Deona
 
6. Andy Murray - embedding governance (lessons from maturity models) GOV011015
6. Andy Murray - embedding governance (lessons from maturity models) GOV0110156. Andy Murray - embedding governance (lessons from maturity models) GOV011015
6. Andy Murray - embedding governance (lessons from maturity models) GOV011015Association for Project Management
 
London's Crossrail Scheme - its evolution, governance, financing and challenges
London's Crossrail Scheme  - its evolution, governance, financing and challengesLondon's Crossrail Scheme  - its evolution, governance, financing and challenges
London's Crossrail Scheme - its evolution, governance, financing and challengesInstitute for Transport Studies (ITS)
 
Project Governance and Failure
Project Governance and FailureProject Governance and Failure
Project Governance and FailureMichael Krigsman
 
3. Ross Garland - building governance capability - challenges facing good gov...
3. Ross Garland - building governance capability - challenges facing good gov...3. Ross Garland - building governance capability - challenges facing good gov...
3. Ross Garland - building governance capability - challenges facing good gov...Association for Project Management
 

En vedette (20)

Enterprise Agile Transformation Case Study
Enterprise Agile Transformation Case StudyEnterprise Agile Transformation Case Study
Enterprise Agile Transformation Case Study
 
Saurabh Reengineering Your Business
Saurabh   Reengineering Your BusinessSaurabh   Reengineering Your Business
Saurabh Reengineering Your Business
 
Value in entireness saurabh sardesai
Value in entireness saurabh sardesaiValue in entireness saurabh sardesai
Value in entireness saurabh sardesai
 
Decision Making in an Organization
Decision Making in an OrganizationDecision Making in an Organization
Decision Making in an Organization
 
Saurabh Harmony Business Analysis
Saurabh Harmony Business AnalysisSaurabh Harmony Business Analysis
Saurabh Harmony Business Analysis
 
IT Project Governance Overview
IT Project Governance OverviewIT Project Governance Overview
IT Project Governance Overview
 
Principles of program governance
Principles of program governancePrinciples of program governance
Principles of program governance
 
Effective GOVERNANCE in Project Portfolio Management
Effective GOVERNANCE in Project Portfolio ManagementEffective GOVERNANCE in Project Portfolio Management
Effective GOVERNANCE in Project Portfolio Management
 
Difference between management & administration
Difference between management & administrationDifference between management & administration
Difference between management & administration
 
Administration Vs. Management
Administration Vs. ManagementAdministration Vs. Management
Administration Vs. Management
 
6. Andy Murray - embedding governance (lessons from maturity models) GOV011015
6. Andy Murray - embedding governance (lessons from maturity models) GOV0110156. Andy Murray - embedding governance (lessons from maturity models) GOV011015
6. Andy Murray - embedding governance (lessons from maturity models) GOV011015
 
Integrated Assurance and Audit at Crossrail, 17 may 2016
Integrated Assurance and Audit at Crossrail, 17 may 2016Integrated Assurance and Audit at Crossrail, 17 may 2016
Integrated Assurance and Audit at Crossrail, 17 may 2016
 
1. Roger Garrini - good governance guidance GOV011015
1. Roger Garrini - good governance guidance GOV0110151. Roger Garrini - good governance guidance GOV011015
1. Roger Garrini - good governance guidance GOV011015
 
London's Crossrail Scheme - its evolution, governance, financing and challenges
London's Crossrail Scheme  - its evolution, governance, financing and challengesLondon's Crossrail Scheme  - its evolution, governance, financing and challenges
London's Crossrail Scheme - its evolution, governance, financing and challenges
 
Crossrail: lessons in governance
Crossrail: lessons in governanceCrossrail: lessons in governance
Crossrail: lessons in governance
 
Project Governance and Failure
Project Governance and FailureProject Governance and Failure
Project Governance and Failure
 
4. Stuart Collins BBC - strategic governance of p3m GOV011015
4. Stuart Collins BBC - strategic governance of p3m GOV0110154. Stuart Collins BBC - strategic governance of p3m GOV011015
4. Stuart Collins BBC - strategic governance of p3m GOV011015
 
3. Ross Garland - building governance capability - challenges facing good gov...
3. Ross Garland - building governance capability - challenges facing good gov...3. Ross Garland - building governance capability - challenges facing good gov...
3. Ross Garland - building governance capability - challenges facing good gov...
 
4. Ian Triplow - developing good governance... GOV011015
4. Ian Triplow - developing good governance... GOV0110154. Ian Triplow - developing good governance... GOV011015
4. Ian Triplow - developing good governance... GOV011015
 
1. Martin Samphire - introduction GOV011015
1. Martin Samphire - introduction GOV0110151. Martin Samphire - introduction GOV011015
1. Martin Samphire - introduction GOV011015
 

Similaire à Program governance Structure

Advanced program management constituency management
Advanced program management   constituency managementAdvanced program management   constituency management
Advanced program management constituency managementMarcus Vannini
 
DAS PM RESPONSIBILITIES
DAS PM RESPONSIBILITIESDAS PM RESPONSIBILITIES
DAS PM RESPONSIBILITIESJoseph Hoffman
 
PMO Proposal For Global Sales Operations
PMO Proposal For Global Sales OperationsPMO Proposal For Global Sales Operations
PMO Proposal For Global Sales Operationstonyhinojosa
 
Change Management for Technology Projects 4
Change Management for Technology Projects 4Change Management for Technology Projects 4
Change Management for Technology Projects 4dmdk12
 
It Project Management
It Project ManagementIt Project Management
It Project ManagementTJ Rains
 
Program management scope management
Program management   scope managementProgram management   scope management
Program management scope managementJulen Mohanty
 
Almm monitoring and evaluation tools draft[1]acm
Almm monitoring and evaluation tools draft[1]acmAlmm monitoring and evaluation tools draft[1]acm
Almm monitoring and evaluation tools draft[1]acmAlberto Mico
 
PMO 3.0 - Next Gen Lean Model - Doug Floyd
PMO 3.0 - Next Gen Lean Model - Doug FloydPMO 3.0 - Next Gen Lean Model - Doug Floyd
PMO 3.0 - Next Gen Lean Model - Doug Floyddvfloyd
 
Project monitoring and control & planning for monitoring
Project monitoring and control & planning for monitoringProject monitoring and control & planning for monitoring
Project monitoring and control & planning for monitoringSandeep Kumar
 
P3O - The Value Adding PMO - from Strategy to Projects
P3O - The Value Adding PMO - from Strategy to ProjectsP3O - The Value Adding PMO - from Strategy to Projects
P3O - The Value Adding PMO - from Strategy to ProjectsTony Vynckier
 
Michelle Andree, PMP, SSGBC - Senior Project Manager Resume 120114
Michelle Andree, PMP, SSGBC - Senior Project Manager Resume 120114Michelle Andree, PMP, SSGBC - Senior Project Manager Resume 120114
Michelle Andree, PMP, SSGBC - Senior Project Manager Resume 120114Michelle Andree, PMP
 
PMP Training - 04 project integration management
PMP Training - 04 project integration managementPMP Training - 04 project integration management
PMP Training - 04 project integration managementejlp12
 
Undestand PMBok 5th, Section 3
Undestand PMBok 5th, Section 3Undestand PMBok 5th, Section 3
Undestand PMBok 5th, Section 3Amr Miqdadi
 

Similaire à Program governance Structure (20)

Advanced program management constituency management
Advanced program management   constituency managementAdvanced program management   constituency management
Advanced program management constituency management
 
Model of Programs.pptx
Model of Programs.pptxModel of Programs.pptx
Model of Programs.pptx
 
Program management for goup1
Program management for goup1Program management for goup1
Program management for goup1
 
DAS PM RESPONSIBILITIES
DAS PM RESPONSIBILITIESDAS PM RESPONSIBILITIES
DAS PM RESPONSIBILITIES
 
PMO Proposal For Global Sales Operations
PMO Proposal For Global Sales OperationsPMO Proposal For Global Sales Operations
PMO Proposal For Global Sales Operations
 
Change Management for Technology Projects 4
Change Management for Technology Projects 4Change Management for Technology Projects 4
Change Management for Technology Projects 4
 
MPPC.ppt
MPPC.pptMPPC.ppt
MPPC.ppt
 
It Project Management
It Project ManagementIt Project Management
It Project Management
 
Program management scope management
Program management   scope managementProgram management   scope management
Program management scope management
 
Almm monitoring and evaluation tools draft[1]acm
Almm monitoring and evaluation tools draft[1]acmAlmm monitoring and evaluation tools draft[1]acm
Almm monitoring and evaluation tools draft[1]acm
 
Leon Tisdale Show
Leon Tisdale ShowLeon Tisdale Show
Leon Tisdale Show
 
PMO 3.0 - Next Gen Lean Model - Doug Floyd
PMO 3.0 - Next Gen Lean Model - Doug FloydPMO 3.0 - Next Gen Lean Model - Doug Floyd
PMO 3.0 - Next Gen Lean Model - Doug Floyd
 
Project Management V1
Project Management V1Project Management V1
Project Management V1
 
My Responsibilities as a Manager - M Maqbool Ur Rahman
My Responsibilities as a Manager - M Maqbool Ur RahmanMy Responsibilities as a Manager - M Maqbool Ur Rahman
My Responsibilities as a Manager - M Maqbool Ur Rahman
 
Project monitoring and control & planning for monitoring
Project monitoring and control & planning for monitoringProject monitoring and control & planning for monitoring
Project monitoring and control & planning for monitoring
 
P3O - The Value Adding PMO - from Strategy to Projects
P3O - The Value Adding PMO - from Strategy to ProjectsP3O - The Value Adding PMO - from Strategy to Projects
P3O - The Value Adding PMO - from Strategy to Projects
 
Michelle Andree, PMP, SSGBC - Senior Project Manager Resume 120114
Michelle Andree, PMP, SSGBC - Senior Project Manager Resume 120114Michelle Andree, PMP, SSGBC - Senior Project Manager Resume 120114
Michelle Andree, PMP, SSGBC - Senior Project Manager Resume 120114
 
Project plan overview
Project plan overviewProject plan overview
Project plan overview
 
PMP Training - 04 project integration management
PMP Training - 04 project integration managementPMP Training - 04 project integration management
PMP Training - 04 project integration management
 
Undestand PMBok 5th, Section 3
Undestand PMBok 5th, Section 3Undestand PMBok 5th, Section 3
Undestand PMBok 5th, Section 3
 

Dernier

BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceDelhi Call girls
 
situational leadership theory by Misba Fathima S
situational leadership theory by Misba Fathima Ssituational leadership theory by Misba Fathima S
situational leadership theory by Misba Fathima Smisbafathima9940
 
Does Leadership Possible Without a Vision.pptx
Does Leadership Possible Without a Vision.pptxDoes Leadership Possible Without a Vision.pptx
Does Leadership Possible Without a Vision.pptxSaqib Mansoor Ahmed
 
CEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biographyCEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biographyHafizMuhammadAbdulla5
 
Reviewing and summarization of university ranking system to.pptx
Reviewing and summarization of university ranking system  to.pptxReviewing and summarization of university ranking system  to.pptx
Reviewing and summarization of university ranking system to.pptxAss.Prof. Dr. Mogeeb Mosleh
 
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Hedda Bird
 
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Pooja Nehwal
 
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...Pooja Nehwal
 
Continuous Improvement Infographics for Learning
Continuous Improvement Infographics for LearningContinuous Improvement Infographics for Learning
Continuous Improvement Infographics for LearningCIToolkit
 
Construction Project Management | Coursera 2024
Construction Project Management | Coursera 2024Construction Project Management | Coursera 2024
Construction Project Management | Coursera 2024Alex Marques
 
Day 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampDay 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampPLCLeadershipDevelop
 
internal analysis on strategic management
internal analysis on strategic managementinternal analysis on strategic management
internal analysis on strategic managementharfimakarim
 
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607dollysharma2066
 

Dernier (20)

BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
 
situational leadership theory by Misba Fathima S
situational leadership theory by Misba Fathima Ssituational leadership theory by Misba Fathima S
situational leadership theory by Misba Fathima S
 
Does Leadership Possible Without a Vision.pptx
Does Leadership Possible Without a Vision.pptxDoes Leadership Possible Without a Vision.pptx
Does Leadership Possible Without a Vision.pptx
 
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdfImagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
 
Imagine - Creating Healthy Workplaces - Anthony Montgomery.pdf
Imagine - Creating Healthy Workplaces - Anthony Montgomery.pdfImagine - Creating Healthy Workplaces - Anthony Montgomery.pdf
Imagine - Creating Healthy Workplaces - Anthony Montgomery.pdf
 
CEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biographyCEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biography
 
Peak Performance & Resilience - Dr Dorian Dugmore
Peak Performance & Resilience - Dr Dorian DugmorePeak Performance & Resilience - Dr Dorian Dugmore
Peak Performance & Resilience - Dr Dorian Dugmore
 
Empowering Local Government Frontline Services - Mo Baines.pdf
Empowering Local Government Frontline Services - Mo Baines.pdfEmpowering Local Government Frontline Services - Mo Baines.pdf
Empowering Local Government Frontline Services - Mo Baines.pdf
 
Reviewing and summarization of university ranking system to.pptx
Reviewing and summarization of university ranking system  to.pptxReviewing and summarization of university ranking system  to.pptx
Reviewing and summarization of university ranking system to.pptx
 
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
 
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
 
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...
 
Continuous Improvement Infographics for Learning
Continuous Improvement Infographics for LearningContinuous Improvement Infographics for Learning
Continuous Improvement Infographics for Learning
 
Construction Project Management | Coursera 2024
Construction Project Management | Coursera 2024Construction Project Management | Coursera 2024
Construction Project Management | Coursera 2024
 
Day 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampDay 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC Bootcamp
 
Discover -CQ Master Class - Rikita Wadhwa.pdf
Discover -CQ Master Class - Rikita Wadhwa.pdfDiscover -CQ Master Class - Rikita Wadhwa.pdf
Discover -CQ Master Class - Rikita Wadhwa.pdf
 
Becoming an Inclusive Leader - Bernadette Thompson
Becoming an Inclusive Leader - Bernadette ThompsonBecoming an Inclusive Leader - Bernadette Thompson
Becoming an Inclusive Leader - Bernadette Thompson
 
internal analysis on strategic management
internal analysis on strategic managementinternal analysis on strategic management
internal analysis on strategic management
 
Intro_University_Ranking_Introduction.pptx
Intro_University_Ranking_Introduction.pptxIntro_University_Ranking_Introduction.pptx
Intro_University_Ranking_Introduction.pptx
 
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
 

Program governance Structure

  • 1. PROGRAM GOVERNANCE STRUCTURE SETUP & MANAGEMENT By Saurabh Sardesai www.starvaluemodel.com June 2014
  • 2. Objectives  Establish a Program/Project governance structure within the organization and ensure stakeholder participation  Define the program roles, decision making hierarchy, program execution strategies and best practices  Describe the protocol for proper flow of relevant information to all stakeholders  Establish a project/program review, issue management & change mgmt mechanism  Mechanism to identify program compliance and communications to all stakeholders  Evaluate various models of program governance and investigate their suitability for adaption  Translate business strategy into actual program execution via a proper governance framework
  • 3. Governance defined  Governance, for a program or a project, is a combination of individuals filling executive and management roles, program oversight functions organized into structures, and policies that define management principles and decision making.  This combination is focused upon providing direction and oversight, which guide the achievement of the needed business outcome from the execution of the program effort, and providing data and feedback, which measure the ongoing contribution by the program to needed results within the overall business strategy and direction.
  • 4. Need/Background  The organization was facing a huge problem of managing diverse projects across geographies without having a formal program structure in place  Senior management was finding it increasingly difficult to have an oversight on project execution in absence of proper governance structure and formal feedback channels  There was a clear disconnect between project execution and business mission or strategy  There was no overarching body like a Steering committee to provide oversight to projects  A need was felt to aggregate all multiple projects data in a central place and use the information to better manage the defined outcomes
  • 5. Stakeholders  Board of Directors and C level executives  Project sponsors and funding partners  Internal and external clients of the organization  Business units within the organization  Vendor partners of the organization  Project managers and delivery managers/heads  Development teams, architects and testers  Support staff, line managers and consultants  Product control and management teams  Other relevant project stakeholders
  • 6. Plan of action  Initiate consultations with relevant stakeholders to get their opinion & feedback  Establish a Program Steering Committee as the overarching body for program/project execution  Establish a Program Management Office (PMO)  Establish a Program Organization model and Project Organization model  Define and set up roles for Program Director, Program Managers, PMO managers and PMO support staff  Implement mechanisms to provide guidance and direction regarding policies, governance principles, and decision or authority specifications.  Establish a communications network and protocol for effective program and project communication to internal and external stakeholders of the organization
  • 7. Steering committee models  Consensus Model: Executive-level sponsors who must reach consensus on issues, changes, and adjustments in order to proceed  Consultative Model: Executives and senior managers who are stakeholders for some aspect of the defined outcomes. Their role is to understand issues and needed changes, provide advice and assessment of potential impact, and make needed adjustments within their own responsibility area  Advisory Model: Representatives for the major business segments who are responsible for outcomes, or portions of outcomes, within the business strategy and direction. Their role is to monitor program progress, understand issues raised and adjustments made, assess potential impact within their own business segments, and carry back information about committee decisions to their respective business segments  For our initiative we recommend the Advisory model as the organization is large and has many interdependent businesses that routinely interact with each other
  • 8. Recommended model – Program Management Office (PMO)  The Program Management Office (PMO) provides support along administrative, financial, process, and staff dimensions associated with successful program execution.  The PMO also provides review and tracking of financial expenditures, generation of required reports and financial documents, and ensures compliance with policies and practices.  The PMO provides & administers policies, procedures, & practices that provide an operational framework for program members
  • 11. Sample Project structure within a PMO
  • 12. Benefits of recommended model  Increases the long term potential of the program and individual projects  Continuous linkage to enterprise business strategy and direction  Clear and well-understood decision-making authority  Effective oversight of & insight into program progress and direction  Executive control over program evolution and outcomes  Central storage and management of all project data
  • 13. Measuring Program success  Delivering the program to the client on time and within the dates specified in the agreement, taking into account any amendments or approved change requests  Achieving the financial objectives set forth in the business case, taking into account any amendments or change controls  Meeting all expectations related to quality and fulfilment of program requirements  Adhering to an established program methodology measured by a joint governance board  Achieving overall client satisfaction and repeat business
  • 14. PMO – Tools of engagement  Overview and statement of purpose  Communication plan  Integrated program schedule  Program quality plan  Program risk management plan  Program issue management plan  Program change management  Program monitoring and control management
  • 15. Elements of good program governance  A compelling business case, stating the objects of the project and specifying the in-scope and out-of-scope aspects  A mechanism to assess the compliance of the completed project to its original objectives  Identifying all stakeholders with an interest in the project  A defined method of communication to each stakeholder  A set of business-level requirements as agreed by all stakeholders  An agreed specification for the project deliverables  The appointment of a project manager  Clear assignment of project roles and responsibilities
  • 16. Elements of good program governance….contd.  A current, published project plan that spans all project stages from project initiation through development to the transition to operations.  A system of accurate upward status- and progress-reporting including time records.  A central document repository for the project  A centrally-held glossary of project terms  A process for the management and resolution of issues that arise during the project  A process for the recording and communication of risks identified during the project  A standard for quality review of the key governance documents and of the project deliverables
  • 17. Program Communications Plan  Sets up approved methods of communication  Establishes standard communication procedure  Frequency and type of updates provided to the program/project stakeholders  Provides consistency in information flow  Removes misinterpretations and doubts  What information to be sent to whom & when  Ensures Executive program engagement  Helps keep everyone on the same page
  • 18. Communication Plan elements  Documented communication paths for information sharing, including tools (VOIP, email, video/Web conferencing, etc.) will be used throughout the program & for projects  Program and project contact lists based  Roles and responsibilities matrix for all stakeholders  A program organization chart to identify high-level organization, reporting, escalation and accountability for the program.  Approval and escalation procedures for decision making  Recurring Communication Matrix to ensure timely and effective communication  Program event management plan that ensures the right event occurrence reporting about issues, risks, milestones etc
  • 19. Integrated Program Schedule  Key program tasks  Key program and/or project milestones  Duration of the program and projects in it  Dependencies related to the program  Assigned responsibilities within the program  Key deliverables of the program & schedule  Program tracking and control mechanism  Actual v/s Expected program metrics  Measurement and analysis of any deviations
  • 20. Program Quality Plan  The quality plan defines the expectations of quality that will be delivered by the program.  The plan addresses the overall approach that will be adopted by the program and associated projects to ensure that quality is delivered according to stakeholder expectations.  The quality plan also defines quantitative measures that are used to validate quality prior to moving through a quality gate and eventually prior to implementation.
  • 21. Program Risk Management Plan  The risk management plan is used to define the tolerance for risk throughout the program life cycle as well as the methods for identifying, recording and addressing risk throughout the program.  The early and frequent identification of risk in a program is essential to meeting cost, schedule and quality expectations.  Steering committee and program manager to meet on a monthly basis, or as defined in the communication plan, to review the identified risks, examine each associated action plan and define updates that need to be initiated.  Additionally, the team communicates any newly identified risks that may impact the program as they surface.
  • 22. Sample program risk distribution chart 14% 20% 6% 33% 2% 12% 13% Dependencies Requirements Knowledge Availability Commitment Project size Complexity
  • 23. Program Mgr v/s Project Mgr Program manager Project manager Integrates efforts, continuously assesses and refines approaches and plans, ensures good communication. Plans, organizes, directs, and controls the project effort. Directs managers to achieve defined outcomes aligned with business strategy. Manages for on-time delivery of specific products. Acts as the implementation arm of the program sponsor(s) and / or steering committee. Manages work within the project plan framework. Manages managers. Manages technical staff. As Table above shows, the program manager and project manager roles are quite different from one another. Whereas project managers typically focus on delivering a specific component, program managers typically focus on one or more outcomes that are business strategy components.
  • 24. Links to Business Strategy  Throughout program planning and execution, managers must ensure that the program sustains a connection to the business strategy.  This strategy is dynamic, not static. Both internal and external events affect the enterprise's initiatives,  So programs need mechanisms that will maintain a link between the initiative and the business strategy, and provide for effective data exchange and necessary adjustments.  We can divide such mechanisms into two categories: those active during program mobilization and planning, and those active during execution.
  • 25. Program Mobilization – Strategic Review  IT goals and strategy  Program capital and expenses budget  Program benefits definition  Program outline  Candidate projects identification  Program mobilization plan  Consulting and staffing agreements  A business strategy review  Program planning strategy
  • 26. Program execution reviews  As the program proceeds, the program plan and schedule should provide for periodic strategy reviews by the program sponsor(s) and / or steering committee.  The schedule for these reviews can be aligned with the program's phase structure, which cuts across all of the constituent projects.  As a phase-end approaches, reviewers can compare the program's current state and results against the then-current business strategy, and propose needed adjustments.
  • 27. Decisions and Authority  An important aspect of program governance is assigning specific decision-making authority to each executive and management role.  Program managers can hold special group work sessions for this purpose and then create and distribute a matrix for major decision areas and roles.  Decision hierarchy structure should be clearly communicated to all program stakeholders
  • 29. Program Issue Management Plan  Throughout any program, risks are bound to become issues needing resolution in accordance with the strategy defined in the risk management plan.  In the likely scenario that an issue arises that has not yet been identified as a risk, the issue management plan provides strategies and guiding principles for resolving the issue.  Recognizing that this theoretical situation is not the typical situation in the execution of programs and projects, the same escalation principles identified through the program organization chart apply in the escalation of issues.
  • 30. Program Change Management  Whether due to missed requirements, project issues or increased scope, a program is bound to encounter change during the life cycle.  The program change management plan defines the authority that the program has to approve change from an associated project, how said project requests change the agreed-to plan  How the program should receive approval on change requests that are beyond its authority is also defined in this plan
  • 31. Program monitoring & control  Event log (includes identified risks, issues, changes, decisions and action items)  Project performance information such as key metrics on realized rate, resource utilization, ROI, duration, deliverables etc  Weekly status reports to stakeholders  Recommendations for intervention and corrective actions from senior management  Lessons learnt activities from closed initiatives  Managing change control requests  Effectively manage deviations from baseline
  • 32. Conclusion  Establishing a governance framework is a significant activity requiring participation from all the relevant stakeholders  The key to a program’s success is optimal utilization of the governance framework, policies and best practices  Continuous feedback and communication are the essential ingredients of a Program  Program Management is a ‘people’ thing’ and must be projected that way