NTPC LIMITED
We were appointed to do 24 week training at this esteemed
organization. We were assigned to visit various division of
the plant.
These 24 weeks training was a very educational adventure
for us. It was really amazing to see the plant by our self and
learn how electricity, which is one of our daily requirements
of life, is produced. This report has been made by our
experience at NTPC Badarpur and Faridabad. The material
in this report has been gathered from senior student
reports, trainers manuals and power journals provided by
training department. The specification and principles are as
learned by us from the employees of each division of
respective units.
1)
2)
3)
4)
5)
6)
7)
8)
9)
10)
11)
12)
13)
14)
15)
16)

ABOUT NTPC
STRATEGIES
JOURNEY OF NTPC
ABOUT BTPS
OPERATION OF POWER PLANT
BASIC STEPS OF ELECTRICITY GENERATION
PARTS OF A POWER PLANT
VARIOUS CYCLES AT POWER STATION
MOTORS
COAL HANDLING PLANT (CHP)
ABOUT FARIDABAD THERMAL POWER STATION
POWER GENERATION PROCESS
SWITCHYARD
LT/HT SWITCHGEAR
TRANSFORMER
MAIN PARTS OF TRANSFORMER







India’s largest power company, NTPC was set up in
1975 to accelerate power development in India.
NTPC became a Maharatna company in May, 2010, one
of the only four companies to be awarded this status. 
The total installed capacity of the company is 39,174
MW (including JVs) with 16 coal based and 7 gas based
stations, located across the country.
In addition under JVs, 7 stations are coal based &
another station uses naptha/LNG as fuel. 
The company has set a target to have an installed power
generating capacity of 1,28,000 MW by the year 2032.












BADARPUR THERMAL POWER STATION was established on 1973 and it was the
part of Central Government.
On 01/04/1978 is was given to NTPC.
Since then operating performance of NTPC has been considerably above the
national average.  
Badarpur thermal power station started with a single 95 mw unit.
There were 2 more units (95 MW each) installed in next 2 consecutive years.
Now it has total five units with total capacity of 720 MW. Ownership of BTPS was
transferred to NTPC with effect from 01.06.2006 
The power is supplied to a 220 KV network that is a part of the northern grid.
The ten circuits through which the power is evacuated from the plant are:
1. Mehrauli
2. Okhla
3. Ballabgarh
4. Indraprastha
5. UP (Noida)
6. Jaipur
Basic Principle
As per FARADAY’s Law-“Whenever the amount of magnetic flux linked
with a circuit changes, an EMF is produced in the circuit. Generator works
on the principle of producing electricity. To change the flux in the
generator turbine is moved in a great speed with steam.” 
To produce steam, water is heated in the boilers by burning the coal.
In a Badarpur Thermal Power Station, steam is produced and used
to spin a turbine that operates a generator.
Water is heated, turns into steam and spins a steam turbine which drives
an electrical generator.
After it passes through the turbine, the steam is condensed in
a condenser.
The electricity generated at the plant is sent to consumers through highvoltage power lines
The Badarpur Thermal Power Plant has Steam Turbine-Driven
Generators which has a collective capacity of 705MW. 
The fuel being used is Coal which is supplied from the Jharia Coal Field
in Jharkhand.
Water supply is given from the Agra Canal.


The basic steps in the generation of electricity
from coal involves following steps:
◦ Coal to steam
◦ Steam to mechanical power 
◦ Mechanical power to electrical power
1. Cooling tower
2. Cooling water pump
3. Transmission line (3-phase)
4. Unit transformer (3-phase)
5. Electric generator (3-phase)
6. Low pressure turbine
7. Condensate extraction pump
8. Condenser
9. Intermediate pressure turbine
10. Steam governor valve
11. High pressure turbine
12. Deaerator
13. Feed heater
14. Coal conveyor
15. Coal hopper
16. Pulverised fuel mill
17. Boiler drum
18. Ash hopper
19. Super heater
20. Forced draught fan
21. Reheater
22. Air intake
23. Economiser
24. Air preheater
25. Precipitator
26. Induced draught fan
27. Flue Gas
PRIMARY AIR CYCLE
 SECONDARY AIR CYCLE
 COAL CYLCE
 ELECTRICITY CYCLE
 FLUE GAS CYCLE
 CONDENSATE CYCLE
 FEED WATER CYCLE
 STEAM CYCLE

AC MOTORS
◦ Squirrel cage motor
◦ Wound motor
◦ Slip ring induction motor

 
In modern thermal power plant three phase squirrel cage induction motors
are used but sometime double wound motor is used when we need high
starting torque e.g. in ball mill.

 
BEARINGS AND LUBRICATIONS

A good bearing is needed for trouble free operation of motor. Since it is
very costly part of the motor, due care has to be taken by checking it at
regular intervals. So lubricating plays an important role. Two types
of lubricating are widely used
◦ Oil lubrication
◦ Grease lubrication
◦ Insulation
INSULATION
Winding is an essential part so it should be insulated. Following
types of insulation are widely used
INSTRUMENTS SEEN
MICROMETER 
This instrument is used for measuring inside as well as outside
diameter of bearing.
 MEGGAR 
This instrument is used for measuring insulation resistance.
 VIBRATION TESTER 
It measures the vibration of the motor. It is measured in three
dimensions-axial, vertical and horizontal.
The coal handling plant consists of two plants:
◦ Old Coal Handling Plant (OCHP)
◦ New Coal Handling Plant (NCHP)
The

OCHP supplies coal to Unit- I, II, III &
NCHP supplies coal to Unit- IV and V.
 
COAL SUPPLIED AT BTPS
Coal is supplied to BTPS by Jharia coal mines.
The main constituents of CHP plant are: 
WAGON TIPPLER 
Wagon from coal yard come to the tippler and emptied here. There are 2 wagon tipplers in the OCHP.
CONVEYER 

Conveyer belts are used in the OCHP to transfer coal from one place to other as required in a convenient &
safe way.
ZERO

SPEED SWITCH

It is used as a safety device for the motor i.e. if the belt is not moving & the motor is ON, then it burns to save
the motor. This switch checks the speed of the belt & switches off the motor when speed is zero.
METAL

DETECTOR 

As the conveyer belt take coal from wagon to crusher house, no metal piece should go along with coal. To
achieve this objective, metal detectors & separators are used.
CRUSHER

HOUSE 

Both the plants i.e. OCHP & NCHP use TATA crusher powered by BHEL motor. Crusher is designed to crush
the pieces to 20 mm size i.e. practically considered as the optimum size for transfer via conveyer.
ROTARY

BREAKER 

If any large piece of metal of any hard substances like metal impurities comes in the conveyer belt which
cause load on the metal separator, then the rotary breaker rejects them reducing the load on the metal
detector.
PULL

GUARD SWITCH
These are the switches which are installed at every 10m gap in a conveyer belt to ensure the
safety of motors running the conveyer belts. If at any time some accident happens or coal jumps
from belt and starts collecting at a place, then the switch can be used.
Est. 1997, this state of the art power plant has a
production capacity of up to 430 MW.
 It is the only power plant in this country to supply its
entire power to a state i.e. Haryana rather than to the
national grid.
 It consist of 2 Gas Turbines and 1 Steam Turbine.
 The source of fuel is Natural Gas through HBJ
pipeline.
 The water source canal is Gurgaon Canal.



The Gas/Naphtha from pipeline is taken and
supplied to GT Combustion Chamber where
it is burnt as fuel along with air drawn from
atmosphere. This heat is then converted into
mechanical energy in the Gas Turbine. Gas
turbine through a common shaft rotates a
Generator, which produces electric power.
Flue gas from the turbine exhaust is used to
convert water into steam in the Waste Heat
Recovery Boiler (WHRB). Water required for
steam generation is circulated through the
tubes in the boiler, where heat exchange
takes place and water gets converted into
steam. The steam generated from WHRBs is
used to run a steam turbo generator and
produce electric power. This power is
supplied to customer through 220KV lines.
Line Diagram of Gas Turbine cycle






Switchgear is one that makes or breaks the electrical circuit.
It is a switching device that opens & closes a circuit that defined as apparatus used for
switching, Lon rolling & protecting the electrical circuit & equipments.
The switchgear equipment is essentially concerned with switching & interrupting currents
either under normal or abnormal operating conditions.
The tubular switch with ordinary fuse is simplest form of switchgear & is used to control &
protect& other equipments in homes, offices etc.
However such switchgear cannot be used profitably on high voltage system (3.3 KV) for 2
reasons.
◦
◦








Firstly, when a fuse blows, it takes some time to replace it & consequently there is interruption of service
to customer.
Secondly, the fuse cannot successfully interrupt large currents that result from the High Voltage System.

In order to interrupt heavy fault currents, automatic circuit breakers are used.
There are very few types of circuit breakers in B.P.T.S they are VCB, OCB, and SF6 gas
circuit breaker.
The most expensive circuit breaker is the SF6 type due to gas. 
There are various companies which manufacture these circuit breakers: VOLTAS, JYOTI,
and KIRLOSKAR.
Switchgear includes switches, fuses, circuit breakers, relays & other equipments.
In low tension switch gear thermal over load relays are used whereas in high tension 5
different types of relays are used.
ISOLATOR 
SWITCHING ISOLATOR 
CIRCUIT BREAKER 
LOAD BREAK SWITCHES
EARTH SWITCHES
MAIN SWITCH
Main switch is control equipment which controls or disconnects the main supply. The main switch for 3
phase supply is available for the range 32A, 63A, 100A, 200Q, 300A at 500V grade.
 
FUSES
With Avery high generating capacity of the modern power stations extremely heavy carnets would flow
in the fault and the fuse clearing the fault would be required to withstand extremely heavy stress in
process. It is used for supplying power to auxiliaries with backup fuse protection. With fuses, quick
break, quick make and double break switch fuses for 63A and 100A, switch fuses for 200A,400A, 600A,
800A and 1000A are used.
 
CONTACTORS
AC Contractors are 3 poles suitable for D.O.L Starting of motors and protecting the connected motors.
OVERLOAD RELAY 
For overload protection, thermal overload relay are best suited for this purpose. They operate due to
the action of heat generated by passage of current through relay element. 
AIR CIRCUIT BREAKERS
 It is seen that use of oil in circuit breaker may cause a fire. So in all circuits breakers at large capacity
air at high pressure is used which is maximum at the time of quick tripping of contacts. This reduces the
possibility of sparking. The pressure may vary from 50-60kg/cm^2 for high and medium capacity circuit
breakers.
Contactors used in ntpc

Thermal overload relay
MINIMUM OIL CIRCUIT BREAKER 
These use oil as quenching medium.
AIR CIRCUIT BREAKER 
In this the compressed air pressure around 15 kg per cm^2 is used for extinction
of arc caused by flow of air around the moving circuit . The breaker is closed by
applying pressure at lower opening and opened by applying pressure at upper
opening. When contacts operate, the cold air rushes around the movable contacts
and blown the arc
SF6 CIRCUIT BREAKER 
The principle of current interruption is similar to that of air blast circuit breaker. It
simply employs the arc extinguishing medium namely SF6. When it is broken down
under an electrical stress, it will quickly reconstitute itself.
VACUUM CIRCUIT BREAKER 
It works on the principle that vacuum is used to save the purpose of insulation
and. In regards of insulation and strength, vacuum is superior dielectric medium
and is better that all other medium except air and sulphur which are generally used
at high pressure.
AIR CIRCUIT
BREAKERS

OIL CIRCUIT
BREAKERS

SF6 CIRCUIT
BREAKERS
It is a static machine which increases or
decreases the AC voltage without changing
the frequency of the supply.
It is a device that:

◦ Transfer electric power from one circuit
to another.
◦ It accomplishes this by electromagnetic
induction.
◦ In this the two electric circuits are in mutual
inductive influence of each other.

WORKING

PRINCIPLE:

It works on FARADAY’S LAW
OF ELECTROMAGNETIC INDUCTION (self
or mutual induction depending on the type of
transformer).


CONSERVATOR

It is used generally to conserve the insulating property of the oil from deterioration& protect the
transformer against failure on account of bad quality of oil.


SILICAGEL DEHYDRATING BREATHER

It is used to prevent entry of moisture inside the transformer tank. The breather consists of silica gel.


GAS OPERATED RELAY (BUCHHOLZ RELAY)

It is a gas actuated relay used for protecting oil immersed transformer against all types of faults. It
indicates presence of gases in case of some minor fault & take out the transformer out of circuit in
case of serious fault.


OIL GUAGE

Every transformer with an oil guage to indicate the oil level. The oil guage may be provided with the
alarm contacts which gave an alarm the oil level has dropped beyond permissible height due to oil
leak etc.


BUSHINGS

It is made from highly insulating material to insulate & to bring out the terminals of the
transformer from the container. The bushings are of 3 types:
a.

Porcelain bushings used for low voltage transformer

b.

b. Oil filled bushings used for voltage up to 33KV.

c.

c. Condensed type bushings used for voltage above 33KV.



TAPPINGS

The transformer are usually provided with few tappings on secondary side so that output
voltage can be varied for constant input voltage.


RADIATORS

It increases the surface area of the tank & more heat is thus radiated in less time.


WINDINGS TEMPERATURE INDICATOR (OIL GUAGE)

Device which indicates the temperature of winding of transformer & possible damage to
the transformer due too overload can be prevented.
NTPC faridabad nd badarpur

Contenu connexe

Tendances

Summer Training Report Ntpc barh (ajeet)
Summer Training Report Ntpc barh (ajeet)Summer Training Report Ntpc barh (ajeet)
Summer Training Report Ntpc barh (ajeet)Ajeet Chaurasia
 
NTPC summer training report
NTPC summer training reportNTPC summer training report
NTPC summer training reportsanjeevps12345
 
Ntpc vocational training project report sipat
Ntpc vocational training project report sipatNtpc vocational training project report sipat
Ntpc vocational training project report sipatpratikguptateddy
 
NTPC Badarpur Industrial Training Report
NTPC Badarpur Industrial Training ReportNTPC Badarpur Industrial Training Report
NTPC Badarpur Industrial Training ReportAditya Shekhar
 
Tarun Project Report On NTPC Kanti
Tarun  Project Report On NTPC KantiTarun  Project Report On NTPC Kanti
Tarun Project Report On NTPC KantiTarun Kumar
 
Udbhav's presentation on ntpc
Udbhav's presentation on ntpcUdbhav's presentation on ntpc
Udbhav's presentation on ntpcUdbhav garg
 
NTPC MECANICAL SUMMER REPORT
NTPC MECANICAL  SUMMER REPORTNTPC MECANICAL  SUMMER REPORT
NTPC MECANICAL SUMMER REPORTAnkur Pal
 
Ntpc(btps) report
Ntpc(btps) reportNtpc(btps) report
Ntpc(btps) reportAlok Tiwari
 
training report NTPC Muzaffarpur Bihar
training report  NTPC Muzaffarpur Bihar training report  NTPC Muzaffarpur Bihar
training report NTPC Muzaffarpur Bihar Dilip kumar
 
thermal power plant NTPC singrauli
thermal power plant NTPC singrauli thermal power plant NTPC singrauli
thermal power plant NTPC singrauli Ram Narayan Shah
 
NTPC Barh ppt by Shivank
NTPC Barh ppt by ShivankNTPC Barh ppt by Shivank
NTPC Barh ppt by Shivankshivank Kumar
 
Ntpc KAHALGAON REPORT FILE
Ntpc KAHALGAON REPORT FILENtpc KAHALGAON REPORT FILE
Ntpc KAHALGAON REPORT FILERanjan kumar
 
Steam turbines and its associated systems(ntpc ramagundam)
Steam turbines and its associated systems(ntpc ramagundam)Steam turbines and its associated systems(ntpc ramagundam)
Steam turbines and its associated systems(ntpc ramagundam)abdul mohammad
 
Banti industrial training-report-on-ntpc-dadri GAS POWER PLANT
Banti industrial training-report-on-ntpc-dadri GAS POWER PLANTBanti industrial training-report-on-ntpc-dadri GAS POWER PLANT
Banti industrial training-report-on-ntpc-dadri GAS POWER PLANT94600banti
 
Ntpc kahalgaon training report
Ntpc kahalgaon training reportNtpc kahalgaon training report
Ntpc kahalgaon training reportravi kant
 

Tendances (20)

Summer Training Report Ntpc barh (ajeet)
Summer Training Report Ntpc barh (ajeet)Summer Training Report Ntpc barh (ajeet)
Summer Training Report Ntpc barh (ajeet)
 
Training NTPC
Training NTPCTraining NTPC
Training NTPC
 
Ntpc Report
Ntpc ReportNtpc Report
Ntpc Report
 
NTPC summer training report
NTPC summer training reportNTPC summer training report
NTPC summer training report
 
Ntpc vocational training project report sipat
Ntpc vocational training project report sipatNtpc vocational training project report sipat
Ntpc vocational training project report sipat
 
NTPC Badarpur Industrial Training Report
NTPC Badarpur Industrial Training ReportNTPC Badarpur Industrial Training Report
NTPC Badarpur Industrial Training Report
 
Tarun Project Report On NTPC Kanti
Tarun  Project Report On NTPC KantiTarun  Project Report On NTPC Kanti
Tarun Project Report On NTPC Kanti
 
Udbhav's presentation on ntpc
Udbhav's presentation on ntpcUdbhav's presentation on ntpc
Udbhav's presentation on ntpc
 
Report ON NTPC DADRI .BY ....EMAM
Report ON NTPC DADRI  .BY ....EMAMReport ON NTPC DADRI  .BY ....EMAM
Report ON NTPC DADRI .BY ....EMAM
 
NTPC MECANICAL SUMMER REPORT
NTPC MECANICAL  SUMMER REPORTNTPC MECANICAL  SUMMER REPORT
NTPC MECANICAL SUMMER REPORT
 
Ntpc(btps) report
Ntpc(btps) reportNtpc(btps) report
Ntpc(btps) report
 
training report NTPC Muzaffarpur Bihar
training report  NTPC Muzaffarpur Bihar training report  NTPC Muzaffarpur Bihar
training report NTPC Muzaffarpur Bihar
 
thermal power plant NTPC singrauli
thermal power plant NTPC singrauli thermal power plant NTPC singrauli
thermal power plant NTPC singrauli
 
NTPC Barh ppt by Shivank
NTPC Barh ppt by ShivankNTPC Barh ppt by Shivank
NTPC Barh ppt by Shivank
 
Ntpc KAHALGAON REPORT FILE
Ntpc KAHALGAON REPORT FILENtpc KAHALGAON REPORT FILE
Ntpc KAHALGAON REPORT FILE
 
Steam turbines and its associated systems(ntpc ramagundam)
Steam turbines and its associated systems(ntpc ramagundam)Steam turbines and its associated systems(ntpc ramagundam)
Steam turbines and its associated systems(ntpc ramagundam)
 
Banti industrial training-report-on-ntpc-dadri GAS POWER PLANT
Banti industrial training-report-on-ntpc-dadri GAS POWER PLANTBanti industrial training-report-on-ntpc-dadri GAS POWER PLANT
Banti industrial training-report-on-ntpc-dadri GAS POWER PLANT
 
Ntpc dadri
Ntpc dadriNtpc dadri
Ntpc dadri
 
NTPC Singrauli
NTPC SingrauliNTPC Singrauli
NTPC Singrauli
 
Ntpc kahalgaon training report
Ntpc kahalgaon training reportNtpc kahalgaon training report
Ntpc kahalgaon training report
 

Similaire à NTPC faridabad nd badarpur

ELECTRICAL ENGINEERING THERMAL POWER PLANT Industrial Report
ELECTRICAL ENGINEERING THERMAL POWER PLANT Industrial ReportELECTRICAL ENGINEERING THERMAL POWER PLANT Industrial Report
ELECTRICAL ENGINEERING THERMAL POWER PLANT Industrial ReportUtkarsh Chaubey
 
A summer training presentation on national thermal power
A summer training presentation on national thermal powerA summer training presentation on national thermal power
A summer training presentation on national thermal powerShishupal03012015
 
MAHI REPORT.docx
MAHI REPORT.docxMAHI REPORT.docx
MAHI REPORT.docxAjmal Khan
 
MAHI REPORT.docx
MAHI REPORT.docxMAHI REPORT.docx
MAHI REPORT.docxAjmal Khan
 
MAHI REPORT.docx
MAHI REPORT.docxMAHI REPORT.docx
MAHI REPORT.docxAjmal Khan
 
Internship PPT final.pptx on ukai thermal power station
Internship PPT final.pptx on ukai thermal power stationInternship PPT final.pptx on ukai thermal power station
Internship PPT final.pptx on ukai thermal power stationmalikavita731
 
Internship PPT ukai thermal power station .pptx
Internship PPT ukai thermal power station .pptxInternship PPT ukai thermal power station .pptx
Internship PPT ukai thermal power station .pptxmalikavita731
 
Internship PPT final ukai thermal power station
Internship PPT final ukai thermal power stationInternship PPT final ukai thermal power station
Internship PPT final ukai thermal power stationmalikavita731
 
Ranjan NTPC KAHALGAON ppt
Ranjan  NTPC KAHALGAON pptRanjan  NTPC KAHALGAON ppt
Ranjan NTPC KAHALGAON pptRanjan kumar
 
Parichha thermal power point PPT
Parichha thermal power point PPTParichha thermal power point PPT
Parichha thermal power point PPTankit shrivastava
 
NTPC DADRI THERMAL PLANT PPT
NTPC DADRI THERMAL PLANT PPTNTPC DADRI THERMAL PLANT PPT
NTPC DADRI THERMAL PLANT PPTShivam Sharma
 
Kota thermal power plant ppt
Kota thermal power plant pptKota thermal power plant ppt
Kota thermal power plant pptPrakash Jarotia
 
FEROZE GANDHI UNCHAHAR THERMAL POWER PLANT(NTPC UNCHAHAR) SUMMER TRAINING
FEROZE GANDHI UNCHAHAR THERMAL POWER PLANT(NTPC UNCHAHAR) SUMMER TRAINING FEROZE GANDHI UNCHAHAR THERMAL POWER PLANT(NTPC UNCHAHAR) SUMMER TRAINING
FEROZE GANDHI UNCHAHAR THERMAL POWER PLANT(NTPC UNCHAHAR) SUMMER TRAINING Om Prakash
 
Thermal Power Simulator Training
Thermal Power Simulator TrainingThermal Power Simulator Training
Thermal Power Simulator TrainingVedant Sumaria
 
KSTPS PPT Astha.pptx
KSTPS PPT Astha.pptxKSTPS PPT Astha.pptx
KSTPS PPT Astha.pptxssuser4c2635
 

Similaire à NTPC faridabad nd badarpur (20)

ELECTRICAL ENGINEERING THERMAL POWER PLANT Industrial Report
ELECTRICAL ENGINEERING THERMAL POWER PLANT Industrial ReportELECTRICAL ENGINEERING THERMAL POWER PLANT Industrial Report
ELECTRICAL ENGINEERING THERMAL POWER PLANT Industrial Report
 
adi ntpc.pptx
adi ntpc.pptxadi ntpc.pptx
adi ntpc.pptx
 
A summer training presentation on national thermal power
A summer training presentation on national thermal powerA summer training presentation on national thermal power
A summer training presentation on national thermal power
 
MAHI REPORT.docx
MAHI REPORT.docxMAHI REPORT.docx
MAHI REPORT.docx
 
MAHI REPORT.docx
MAHI REPORT.docxMAHI REPORT.docx
MAHI REPORT.docx
 
MAHI REPORT.docx
MAHI REPORT.docxMAHI REPORT.docx
MAHI REPORT.docx
 
Internship PPT final.pptx on ukai thermal power station
Internship PPT final.pptx on ukai thermal power stationInternship PPT final.pptx on ukai thermal power station
Internship PPT final.pptx on ukai thermal power station
 
Internship PPT ukai thermal power station .pptx
Internship PPT ukai thermal power station .pptxInternship PPT ukai thermal power station .pptx
Internship PPT ukai thermal power station .pptx
 
Internship PPT final ukai thermal power station
Internship PPT final ukai thermal power stationInternship PPT final ukai thermal power station
Internship PPT final ukai thermal power station
 
Ranjan NTPC KAHALGAON ppt
Ranjan  NTPC KAHALGAON pptRanjan  NTPC KAHALGAON ppt
Ranjan NTPC KAHALGAON ppt
 
V.T ppt
V.T pptV.T ppt
V.T ppt
 
Parichha thermal power point PPT
Parichha thermal power point PPTParichha thermal power point PPT
Parichha thermal power point PPT
 
NTPC DADRI THERMAL PLANT PPT
NTPC DADRI THERMAL PLANT PPTNTPC DADRI THERMAL PLANT PPT
NTPC DADRI THERMAL PLANT PPT
 
Kota thermal power plant ppt
Kota thermal power plant pptKota thermal power plant ppt
Kota thermal power plant ppt
 
KTPS
KTPSKTPS
KTPS
 
FEROZE GANDHI UNCHAHAR THERMAL POWER PLANT(NTPC UNCHAHAR) SUMMER TRAINING
FEROZE GANDHI UNCHAHAR THERMAL POWER PLANT(NTPC UNCHAHAR) SUMMER TRAINING FEROZE GANDHI UNCHAHAR THERMAL POWER PLANT(NTPC UNCHAHAR) SUMMER TRAINING
FEROZE GANDHI UNCHAHAR THERMAL POWER PLANT(NTPC UNCHAHAR) SUMMER TRAINING
 
Thermal Power Simulator Training
Thermal Power Simulator TrainingThermal Power Simulator Training
Thermal Power Simulator Training
 
Attachment.doc
Attachment.docAttachment.doc
Attachment.doc
 
KSTPS PPT Astha.pptx
KSTPS PPT Astha.pptxKSTPS PPT Astha.pptx
KSTPS PPT Astha.pptx
 
Complete report
Complete reportComplete report
Complete report
 

Dernier

Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...Shubhangi Sonawane
 
Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxVishalSingh1417
 
An Overview of Mutual Funds Bcom Project.pdf
An Overview of Mutual Funds Bcom Project.pdfAn Overview of Mutual Funds Bcom Project.pdf
An Overview of Mutual Funds Bcom Project.pdfSanaAli374401
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104misteraugie
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17Celine George
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfJayanti Pande
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfAdmir Softic
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.pptRamjanShidvankar
 
psychiatric nursing HISTORY COLLECTION .docx
psychiatric  nursing HISTORY  COLLECTION  .docxpsychiatric  nursing HISTORY  COLLECTION  .docx
psychiatric nursing HISTORY COLLECTION .docxPoojaSen20
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfciinovamais
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactPECB
 
Gardella_PRCampaignConclusion Pitch Letter
Gardella_PRCampaignConclusion Pitch LetterGardella_PRCampaignConclusion Pitch Letter
Gardella_PRCampaignConclusion Pitch LetterMateoGardella
 
Gardella_Mateo_IntellectualProperty.pdf.
Gardella_Mateo_IntellectualProperty.pdf.Gardella_Mateo_IntellectualProperty.pdf.
Gardella_Mateo_IntellectualProperty.pdf.MateoGardella
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdfQucHHunhnh
 
fourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingfourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingTeacherCyreneCayanan
 
Class 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfClass 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfAyushMahapatra5
 
Making and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdfMaking and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdfChris Hunter
 

Dernier (20)

Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
 
Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptx
 
An Overview of Mutual Funds Bcom Project.pdf
An Overview of Mutual Funds Bcom Project.pdfAn Overview of Mutual Funds Bcom Project.pdf
An Overview of Mutual Funds Bcom Project.pdf
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.ppt
 
psychiatric nursing HISTORY COLLECTION .docx
psychiatric  nursing HISTORY  COLLECTION  .docxpsychiatric  nursing HISTORY  COLLECTION  .docx
psychiatric nursing HISTORY COLLECTION .docx
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
 
Gardella_PRCampaignConclusion Pitch Letter
Gardella_PRCampaignConclusion Pitch LetterGardella_PRCampaignConclusion Pitch Letter
Gardella_PRCampaignConclusion Pitch Letter
 
Gardella_Mateo_IntellectualProperty.pdf.
Gardella_Mateo_IntellectualProperty.pdf.Gardella_Mateo_IntellectualProperty.pdf.
Gardella_Mateo_IntellectualProperty.pdf.
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 
fourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingfourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writing
 
Class 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdfClass 11th Physics NEET formula sheet pdf
Class 11th Physics NEET formula sheet pdf
 
Making and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdfMaking and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdf
 

NTPC faridabad nd badarpur

  • 2. We were appointed to do 24 week training at this esteemed organization. We were assigned to visit various division of the plant. These 24 weeks training was a very educational adventure for us. It was really amazing to see the plant by our self and learn how electricity, which is one of our daily requirements of life, is produced. This report has been made by our experience at NTPC Badarpur and Faridabad. The material in this report has been gathered from senior student reports, trainers manuals and power journals provided by training department. The specification and principles are as learned by us from the employees of each division of respective units.
  • 3. 1) 2) 3) 4) 5) 6) 7) 8) 9) 10) 11) 12) 13) 14) 15) 16) ABOUT NTPC STRATEGIES JOURNEY OF NTPC ABOUT BTPS OPERATION OF POWER PLANT BASIC STEPS OF ELECTRICITY GENERATION PARTS OF A POWER PLANT VARIOUS CYCLES AT POWER STATION MOTORS COAL HANDLING PLANT (CHP) ABOUT FARIDABAD THERMAL POWER STATION POWER GENERATION PROCESS SWITCHYARD LT/HT SWITCHGEAR TRANSFORMER MAIN PARTS OF TRANSFORMER
  • 4.      India’s largest power company, NTPC was set up in 1975 to accelerate power development in India. NTPC became a Maharatna company in May, 2010, one of the only four companies to be awarded this status.  The total installed capacity of the company is 39,174 MW (including JVs) with 16 coal based and 7 gas based stations, located across the country. In addition under JVs, 7 stations are coal based & another station uses naptha/LNG as fuel.  The company has set a target to have an installed power generating capacity of 1,28,000 MW by the year 2032.
  • 5.
  • 6.
  • 7.         BADARPUR THERMAL POWER STATION was established on 1973 and it was the part of Central Government. On 01/04/1978 is was given to NTPC. Since then operating performance of NTPC has been considerably above the national average.   Badarpur thermal power station started with a single 95 mw unit. There were 2 more units (95 MW each) installed in next 2 consecutive years. Now it has total five units with total capacity of 720 MW. Ownership of BTPS was transferred to NTPC with effect from 01.06.2006  The power is supplied to a 220 KV network that is a part of the northern grid. The ten circuits through which the power is evacuated from the plant are: 1. Mehrauli 2. Okhla 3. Ballabgarh 4. Indraprastha 5. UP (Noida) 6. Jaipur
  • 8.
  • 9. Basic Principle As per FARADAY’s Law-“Whenever the amount of magnetic flux linked with a circuit changes, an EMF is produced in the circuit. Generator works on the principle of producing electricity. To change the flux in the generator turbine is moved in a great speed with steam.”  To produce steam, water is heated in the boilers by burning the coal. In a Badarpur Thermal Power Station, steam is produced and used to spin a turbine that operates a generator. Water is heated, turns into steam and spins a steam turbine which drives an electrical generator. After it passes through the turbine, the steam is condensed in a condenser. The electricity generated at the plant is sent to consumers through highvoltage power lines The Badarpur Thermal Power Plant has Steam Turbine-Driven Generators which has a collective capacity of 705MW.  The fuel being used is Coal which is supplied from the Jharia Coal Field in Jharkhand. Water supply is given from the Agra Canal.
  • 10.  The basic steps in the generation of electricity from coal involves following steps: ◦ Coal to steam ◦ Steam to mechanical power  ◦ Mechanical power to electrical power
  • 11. 1. Cooling tower 2. Cooling water pump 3. Transmission line (3-phase) 4. Unit transformer (3-phase) 5. Electric generator (3-phase) 6. Low pressure turbine 7. Condensate extraction pump 8. Condenser 9. Intermediate pressure turbine 10. Steam governor valve 11. High pressure turbine 12. Deaerator 13. Feed heater 14. Coal conveyor 15. Coal hopper 16. Pulverised fuel mill 17. Boiler drum 18. Ash hopper 19. Super heater 20. Forced draught fan 21. Reheater 22. Air intake 23. Economiser 24. Air preheater 25. Precipitator 26. Induced draught fan 27. Flue Gas
  • 12. PRIMARY AIR CYCLE  SECONDARY AIR CYCLE  COAL CYLCE  ELECTRICITY CYCLE  FLUE GAS CYCLE  CONDENSATE CYCLE  FEED WATER CYCLE  STEAM CYCLE 
  • 13. AC MOTORS ◦ Squirrel cage motor ◦ Wound motor ◦ Slip ring induction motor   In modern thermal power plant three phase squirrel cage induction motors are used but sometime double wound motor is used when we need high starting torque e.g. in ball mill.   BEARINGS AND LUBRICATIONS A good bearing is needed for trouble free operation of motor. Since it is very costly part of the motor, due care has to be taken by checking it at regular intervals. So lubricating plays an important role. Two types of lubricating are widely used ◦ Oil lubrication ◦ Grease lubrication ◦ Insulation
  • 14. INSULATION Winding is an essential part so it should be insulated. Following types of insulation are widely used INSTRUMENTS SEEN MICROMETER  This instrument is used for measuring inside as well as outside diameter of bearing.  MEGGAR  This instrument is used for measuring insulation resistance.  VIBRATION TESTER  It measures the vibration of the motor. It is measured in three dimensions-axial, vertical and horizontal.
  • 15. The coal handling plant consists of two plants: ◦ Old Coal Handling Plant (OCHP) ◦ New Coal Handling Plant (NCHP) The OCHP supplies coal to Unit- I, II, III & NCHP supplies coal to Unit- IV and V.   COAL SUPPLIED AT BTPS Coal is supplied to BTPS by Jharia coal mines.
  • 16. The main constituents of CHP plant are:  WAGON TIPPLER  Wagon from coal yard come to the tippler and emptied here. There are 2 wagon tipplers in the OCHP. CONVEYER  Conveyer belts are used in the OCHP to transfer coal from one place to other as required in a convenient & safe way. ZERO SPEED SWITCH It is used as a safety device for the motor i.e. if the belt is not moving & the motor is ON, then it burns to save the motor. This switch checks the speed of the belt & switches off the motor when speed is zero. METAL DETECTOR  As the conveyer belt take coal from wagon to crusher house, no metal piece should go along with coal. To achieve this objective, metal detectors & separators are used. CRUSHER HOUSE  Both the plants i.e. OCHP & NCHP use TATA crusher powered by BHEL motor. Crusher is designed to crush the pieces to 20 mm size i.e. practically considered as the optimum size for transfer via conveyer. ROTARY BREAKER  If any large piece of metal of any hard substances like metal impurities comes in the conveyer belt which cause load on the metal separator, then the rotary breaker rejects them reducing the load on the metal detector. PULL GUARD SWITCH These are the switches which are installed at every 10m gap in a conveyer belt to ensure the safety of motors running the conveyer belts. If at any time some accident happens or coal jumps from belt and starts collecting at a place, then the switch can be used.
  • 17. Est. 1997, this state of the art power plant has a production capacity of up to 430 MW.  It is the only power plant in this country to supply its entire power to a state i.e. Haryana rather than to the national grid.  It consist of 2 Gas Turbines and 1 Steam Turbine.  The source of fuel is Natural Gas through HBJ pipeline.  The water source canal is Gurgaon Canal. 
  • 18.  The Gas/Naphtha from pipeline is taken and supplied to GT Combustion Chamber where it is burnt as fuel along with air drawn from atmosphere. This heat is then converted into mechanical energy in the Gas Turbine. Gas turbine through a common shaft rotates a Generator, which produces electric power. Flue gas from the turbine exhaust is used to convert water into steam in the Waste Heat Recovery Boiler (WHRB). Water required for steam generation is circulated through the tubes in the boiler, where heat exchange takes place and water gets converted into steam. The steam generated from WHRBs is used to run a steam turbo generator and produce electric power. This power is supplied to customer through 220KV lines.
  • 19. Line Diagram of Gas Turbine cycle
  • 20.      Switchgear is one that makes or breaks the electrical circuit. It is a switching device that opens & closes a circuit that defined as apparatus used for switching, Lon rolling & protecting the electrical circuit & equipments. The switchgear equipment is essentially concerned with switching & interrupting currents either under normal or abnormal operating conditions. The tubular switch with ordinary fuse is simplest form of switchgear & is used to control & protect& other equipments in homes, offices etc. However such switchgear cannot be used profitably on high voltage system (3.3 KV) for 2 reasons. ◦ ◦       Firstly, when a fuse blows, it takes some time to replace it & consequently there is interruption of service to customer. Secondly, the fuse cannot successfully interrupt large currents that result from the High Voltage System. In order to interrupt heavy fault currents, automatic circuit breakers are used. There are very few types of circuit breakers in B.P.T.S they are VCB, OCB, and SF6 gas circuit breaker. The most expensive circuit breaker is the SF6 type due to gas.  There are various companies which manufacture these circuit breakers: VOLTAS, JYOTI, and KIRLOSKAR. Switchgear includes switches, fuses, circuit breakers, relays & other equipments. In low tension switch gear thermal over load relays are used whereas in high tension 5 different types of relays are used.
  • 22. MAIN SWITCH Main switch is control equipment which controls or disconnects the main supply. The main switch for 3 phase supply is available for the range 32A, 63A, 100A, 200Q, 300A at 500V grade.   FUSES With Avery high generating capacity of the modern power stations extremely heavy carnets would flow in the fault and the fuse clearing the fault would be required to withstand extremely heavy stress in process. It is used for supplying power to auxiliaries with backup fuse protection. With fuses, quick break, quick make and double break switch fuses for 63A and 100A, switch fuses for 200A,400A, 600A, 800A and 1000A are used.   CONTACTORS AC Contractors are 3 poles suitable for D.O.L Starting of motors and protecting the connected motors. OVERLOAD RELAY  For overload protection, thermal overload relay are best suited for this purpose. They operate due to the action of heat generated by passage of current through relay element.  AIR CIRCUIT BREAKERS  It is seen that use of oil in circuit breaker may cause a fire. So in all circuits breakers at large capacity air at high pressure is used which is maximum at the time of quick tripping of contacts. This reduces the possibility of sparking. The pressure may vary from 50-60kg/cm^2 for high and medium capacity circuit breakers.
  • 23. Contactors used in ntpc Thermal overload relay
  • 24. MINIMUM OIL CIRCUIT BREAKER  These use oil as quenching medium. AIR CIRCUIT BREAKER  In this the compressed air pressure around 15 kg per cm^2 is used for extinction of arc caused by flow of air around the moving circuit . The breaker is closed by applying pressure at lower opening and opened by applying pressure at upper opening. When contacts operate, the cold air rushes around the movable contacts and blown the arc SF6 CIRCUIT BREAKER  The principle of current interruption is similar to that of air blast circuit breaker. It simply employs the arc extinguishing medium namely SF6. When it is broken down under an electrical stress, it will quickly reconstitute itself. VACUUM CIRCUIT BREAKER  It works on the principle that vacuum is used to save the purpose of insulation and. In regards of insulation and strength, vacuum is superior dielectric medium and is better that all other medium except air and sulphur which are generally used at high pressure.
  • 26. It is a static machine which increases or decreases the AC voltage without changing the frequency of the supply. It is a device that: ◦ Transfer electric power from one circuit to another. ◦ It accomplishes this by electromagnetic induction. ◦ In this the two electric circuits are in mutual inductive influence of each other. WORKING PRINCIPLE: It works on FARADAY’S LAW OF ELECTROMAGNETIC INDUCTION (self or mutual induction depending on the type of transformer).
  • 27.  CONSERVATOR It is used generally to conserve the insulating property of the oil from deterioration& protect the transformer against failure on account of bad quality of oil.  SILICAGEL DEHYDRATING BREATHER It is used to prevent entry of moisture inside the transformer tank. The breather consists of silica gel.  GAS OPERATED RELAY (BUCHHOLZ RELAY) It is a gas actuated relay used for protecting oil immersed transformer against all types of faults. It indicates presence of gases in case of some minor fault & take out the transformer out of circuit in case of serious fault.  OIL GUAGE Every transformer with an oil guage to indicate the oil level. The oil guage may be provided with the alarm contacts which gave an alarm the oil level has dropped beyond permissible height due to oil leak etc.
  • 28.  BUSHINGS It is made from highly insulating material to insulate & to bring out the terminals of the transformer from the container. The bushings are of 3 types: a. Porcelain bushings used for low voltage transformer b. b. Oil filled bushings used for voltage up to 33KV. c. c. Condensed type bushings used for voltage above 33KV.  TAPPINGS The transformer are usually provided with few tappings on secondary side so that output voltage can be varied for constant input voltage.  RADIATORS It increases the surface area of the tank & more heat is thus radiated in less time.  WINDINGS TEMPERATURE INDICATOR (OIL GUAGE) Device which indicates the temperature of winding of transformer & possible damage to the transformer due too overload can be prevented.